Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
November 2000Revised June, 2001
HVS Test Planfor Goal 7
Dowel Bar RetrofitRehabilitation ofRigid Pavements
Partnered Pavement Research
Prepared for:California Department of Transportation
Prepared by:University of California
Berkeley DynatestWashington State
Department ofTransportation
University of WashingtonSeattle
ii
iii
TABLE OF CONTENTS
Table of Contents ...............................................................................................................iii
1.0 Introduction ............................................................................................................. 1
1.1 Overview of Caltrans Rigid Pavement Network Condition.................................... 1
1.2 Faulting of Rigid Pavements ................................................................................... 3
1.3 Overview of Existing Caltrans Rigid Pavement Structures .................................... 7
1.4 Current Caltrans Practice for Controlling Step-Faulted Pavements........................ 9
1.5 Overview of Dowel Bar Retrofit Technology....................................................... 11
2.0 Goal 7 Test Plan Overview ................................................................................... 12
2.1 Purpose of the Research and Expected Outcome.................................................. 12
2.2 Program Approach ................................................................................................ 14
2.2.1 Accelerated Pavement Testing with the Heavy Vehicle Simulator .............. 15
2.2.2 Live Traffic Testing ...................................................................................... 17
2.2.3 Laboratory Testing and Material Investigation............................................. 18
2.3 Test Site Selection and Test Section Layouts ....................................................... 19
3.0 In-situ Materials Testing ....................................................................................... 20
3.1 Existing Materials Sampling ................................................................................. 20
3.2 Base/Subbase Materials and Subgrade Soils......................................................... 20
3.3 Dynamic Cone Penetrometer (DCP) ..................................................................... 21
3.4 Ground Penetrating Radar (GPR) ......................................................................... 21
3.5 Falling Weight Deflectometer (FWD) .................................................................. 21
3.6 Grout Sampling Plan ............................................................................................. 22
4.0 Field Test Program................................................................................................ 23
4.1 Instrumentation...................................................................................................... 23
iv
4.1.1 Multi-Depth Deflectometer (MDD) .............................................................. 23
4.1.2 Joint Deflection Measuring Device (JDMD) ................................................ 24
4.1.3 Thermocouples .............................................................................................. 28
4.1.4 Weather Station ............................................................................................. 29
4.1.5 Failure Mechanisms ...................................................................................... 30
4.2 HVS Testing Program ........................................................................................... 30
4.2.1 Traffic Loading ............................................................................................. 30
4.2.2 Direction of Loading ..................................................................................... 30
4.2.3 Location of Loading on the Slab ................................................................... 30
4.2.4 Environmental Control.................................................................................. 31
4.3 Falling Weight Deflectometer (FWD) Testing Program....................................... 31
4.4 Live Testing Program............................................................................................ 32
5.0 Laboratory Testing Program ................................................................................. 32
5.1 Static Strength Tests of Existing Concrete............................................................ 33
5.2 Static Strength Tests of DBR Grout...................................................................... 33
5.3 Cement Treated Base, Aggregate Subbase and Subgrade Tests ........................... 34
5.3.1 Cement Treated Base .................................................................................... 34
5.3.2 Aggregate Subbase and Subgrade ................................................................. 34
5.4 Dowel Bar Durability Tests................................................................................... 34
5.4.1 Half-cell Potential of Metallic Dowels.......................................................... 34
5.4.2 Corrosion Resistance of Metallic Dowels in Concrete Pavement................. 36
5.4.3 Visual Inspection of Metallic Dowels........................................................... 39
5.4.4 Weight Loss of Metallic Dowels................................................................... 39
v
5.4.5 Microscopic Examination of Metallic Dowels.............................................. 41
5.4.6 Destructive Mechanical Performance Tests of FRP Dowels ........................ 41
6.0 Design Evaluations................................................................................................ 45
6.1 Mechanistic Analysis ............................................................................................ 45
6.2 Life Cycle Cost Analysis....................................................................................... 46
7.0 Testing Schedule ................................................................................................... 47
7.1 HVS Field Tests .................................................................................................... 47
7.2 Laboratory Testing ................................................................................................ 47
8.0 Benefits.................................................................................................................. 49
9.0 References ............................................................................................................. 49
Appendix A: Ukiah Test Experiment Plan........................................................................ 50
Location............................................................................................................................. 50
Objectives...................................................................................................................... 50
Test Section Layout....................................................................................................... 52
Pavement Structures...................................................................................................... 52
Time Scales ................................................................................................................... 53
HVS Field Tests ......................................................................................................... 53
Laboratory Testing..................................................................................................... 53
Appendix B: Palmdale DBR Test Experiment.................................................................. 60
Location............................................................................................................................. 60
Objectives...................................................................................................................... 60
Test Section Layouts ..................................................................................................... 62
Pavement Structure ....................................................................................................... 62
vi
Time Scales ................................................................................................................... 63
HVS Field Tests ......................................................................................................... 63
Laboratory Testing..................................................................................................... 63
1
1.0 INTRODUCTION
Caltrans operates a state highway network of more than 24,000 centerline
kilometers, with over 78,000 lane-kilometers of pavements. In 1999, about 25,000 lane-
kilometers (ln-km), nearly 32 percent, required corrective maintenance or rehabilitation.
Between 1997 and 1999, Caltrans had a 27.5 percent increase in the number of lane-
kilometers requiring immediate attention to 11,260 ln-km, and a 16.4 percent increase in
the number of lane-kilometers requiring other corrective maintenance or rehabilitation to
13,807 ln-km.
1.1 Overview of Caltrans Rigid Pavement Network Condition
Rigid pavements make up 18 percent of the centerline-kilometers in the state
network, and 32 percent of the total lane-kilometers. The difference indicates the extent
to which rigid pavements have been used for multi-lane facilities.(1)
Rigid pavements (Portland Cement Concrete pavements [PCCP]) make up 25
percent of the rehabilitation project needs, and they accounted for 24 percent of the total
lane-kilometers in California requiring immediate attention, indicating that a large
number of rigid pavements in California are in need of work to restore their
serviceability. Identification of the distress mechanism causing the loss of serviceability
of these pavements rehabilitation is important.
Most of the highway pavements operated by Caltrans, approximately 75 percent,
were constructed in the 15 years between 1959 and 1974, and were designed for 20-year
lives based on traffic volumes and loads estimated at that time. It has been estimated that
approximately 90 percent of the state’s rigid pavement were constructed in those 15
years.(2)
2
Most Caltrans rigid pavements are on heavy truck routes and/or are in urban areas
where heavy traffic volumes exist. Rigid pavements were used extensively for
construction of the state Interstate Highway system—29 percent of the lane-kilometers
requiring immediate attention are located on interstate highways within California.
Faulting is the primary distress mechanism of rigid pavements that affects ride
quality. Ride quality is the primary factor that determines the serviceability of a
pavement for the user. Rough pavements cause discomfort to car and truck drivers and
passengers, increase maintenance and repair costs of vehicles, and in extreme cases, may
increase the potential for accidents.
Caltrans places the highest priority for maintenance and rehabilitation spending
on pavements with poor ride quality and high numbers of vehicles using them. Highest
priority is for pavements with International Roughness Index (IRI) values greater than
316 cm/km (200 inches/mile) and more than 5,000 average vehicles per day (Average
Daily Traffic [ADT]).
Caltrans districts with highest percentages and total lane-kilometers of pavement
with rough ride are:
• District 4 (Bay Area), 25 percent of district ln-km, 1999 total ln-km
• District 6 (San Joaquin Valley), 11 percent of district ln-km, 860 total ln-km
• District 7 (Los Angeles/Ventura counties), 26 percent of district ln-km, 2007
total ln-km
• District 8 (San Bernardino/Riverside counties), 10 percent of district ln-km,
757 total ln-km.
3
1.2 Faulting of Rigid Pavements
Faulting is one of the primary factors affecting the ride quality of rigid pavements.
The term “faulting” in rigid pavements refers to a difference in elevation of adjoining
concrete slabs at the transverse joint. Typically, the leading slab (upstream of the joint) is
higher than the trailing slab (downstream of the joint). Faulting can occur at transverse
cracks as well as transverse joints.
Although no mechanical model of faulting exists, it is understood that the
difference in elevation comes from two actions. The first is caused by migration of
material from under the trailing slab to the underside of the leading slab under traffic, as
shown in Figure 1. The second cause of faulting is the movement of the material out
from under the trailing slab and onto the pavement surface, as shown in Figure 2. This
second mechanism is typically associated with wet conditions in the supporting structure
and pumping action of the slabs caused by traffic, particularly heavy truck traffic.
Faulting appears earlier under the following conditions (refer to Figures 1 and 2):
• when the base material beneath the slabs is erodible, meaning that it is not
well bound and will move under the pumping action of traffic and/or water;
• when there is poor load transfer across the joint or crack, which results in
more independent action of the slabs across the joint or crack, and greater
pumping action.
Load transfer in rigid pavements can come from three sources (refer to Figure 3):
• Aggregate interlock between the slabs across the joint or crack. In the
creation of concrete transverse joints, the concrete is cut only about half way
through the slab from the surface. This cut initiates a controlled crack that
4
propagates downward through the concrete. The irregularity of the crack
promotes aggregate interlock and load transfer at the joint.
• Through the base material. This is the weakest means of obtaining load
transfer.
• Load transfer devices. The typical load transfer device used for transverse
joints (or transverse cracks when retrofitted) is a dowel.
Load transfer efficiency (LTE) is a measure of load transfer across a joint or
crack, and can be applied to longitudinal as well as transverse joints and cracks. Loss of
LTE and faulting across longitudinal joints and cracks are safety and maintenance issues,
but do not have an effect on roughness as it is currently measured. Load transfer
efficiency is defined in terms of relative deflections across a joint or crack under loading,
as illustrated in Figure 3.
Extensive evaluation of field pavements across the country indicates that load
transfer efficiency is one of the primary variables controlling the rate of fault
development.(3) Mechanistic-empirical models have been developed to predict fault
development based on LTE, traffic, climate, and base type. These models will be used in
this study to help predict the development of faulting in dowel bar retrofitted pavements.
These models also include a term for “bearing stress” between the dowel and the
concrete that surrounds it in the slab. High bearing stresses in the concrete around the
dowel lead to loosening of the dowel, which reduces its effectiveness in providing load
transfer. High bearing stresses are reduced primarily by increasing the diameter of the
dowel or secondarily by increasing the number of dowels, which distributes the load on
the dowel across a larger area of concrete or across more dowels, respectively.
5
Figure 1. Mechanism of base material movement and faulting and in rigidpavements.
6
Figure 2. Mechanism of pumping with water and faulting in rigid pavements.
7
Figure 3. Load transfer efficiency definition.
In addition to faulting, good load transfer across the transverse joints reduces the
potential for corner cracking. Good load transfer across transverse joints can be provided
by tie bars in the longitudinal joints between lanes and between a lane and a concrete
shoulder.
1.3 Overview of Existing Caltrans Rigid Pavement Structures
Caltrans rigid pavements have no load transfer devices (dowels) at the transverse
joints, except for a few pavement sections built since 1999. The main reason that
Caltrans did not use dowels in the 1950s and 1960s when most of its rigid pavements
were built was because of construction difficulties with dowel placement, which can lead
to early failure of the pavement. Typical dowel practice at that time also included the use
of small diameter dowels (on the order of 19 to 25 mm [3/4 to 1 inch]), with high bearing
8
stresses. The result was that dowels were not particularly effective in reducing faulting
even when placed correctly.
Caltrans rigid pavements are also all plain jointed concrete (again, except for a
few experimental sections), meaning they contain no continuous steel reinforcement to
hold transverse cracks in slabs together, with the result that transverse cracks behave as
transverse joints with irregular geometry. Caltrans does not use reinforced concrete
pavement because it is typically more expensive to build and maintain than plain jointed
concrete pavement.
Historically, Caltrans has relied on improving the non-erodability of base
materials and increasing aggregate interlock to mitigate fault development.
Nearly all of the rigid pavements needing rehabilitation were built with cement
treated bases (CTB). In rigid pavements built before August 1964, the CTB layer was
100 mm thick and had a compressive strength requirement of 2067 kPa (300 psi) at 7
days when the PCC slab was 200 mm thick; the CTB was 100 mm thick and had a
compressive strength requirement of 4479 kPa (650 psi) when the PCC slab was 225 mm
thick.
After 1964, the CTB thickness requirements were changed to 105 mm with a
compressive strength of 2756 kPa (400 psi) for 200-mm thick PCC slabs. A 150-mm
thick CTB with a compressive strength of 5168 kPa (750 psi) was required for 225-mm
thick PCC slabs.
Caltrans experience with CTB bases is that in many cases they have deteriorated
through cracking and erosion. Caltrans has also found that their CTB bases have not
prevented fairly rapid development of faulting. As study performed by Mcleod and
9
Monismith in 1979 indicated that faulting generally occurred within 1 million to 4
million equivalent single axle loads (ESALs). At today’s traffic rates, this represents less
than five years of traffic for many Caltrans concrete freeways. The rate is somewhat
dependent on the CTB specification used during original construction, with
improvements in CTB compressive strength resulting in a slightly reduced rate of
faulting, as reported in Table 1.
Table 1 Faulting Development in Caltrans Rigid Pavements in the 1970s (4)Millions of ESALs
Faulting Severity CTB before 1967 CTB after 1967Moderate Faulting Begins 1.0 1.0
Severe Faulting Begins 1.5 2.0Severe Faulting is Typical 2.5 4.0
The performance of CTB in Caltrans rigid pavements may be partially related to
construction practice in the 1950s and the early 1960s. During that period, the CTB was
prepared either as road mix (earlier), or placed with a paver (later). In both cases, the
CTB was then planed to a level surface with a motor grader and the resulting loose
material was rolled into the surface of the CTB prior to placement of the concrete. It is
thought that the material rolled into the surface may be highly erodible and may be a
major contributor to the rapid fault development found in Caltrans pavements built during
that period.
1.4 Current Caltrans Practice for Controlling Step-Faulted Pavements
The current Caltrans rigid design guide has a maximum slab thickness of 260 mm
with various types of non-erodible base for which thickness depends on the design traffic
level. Current emphasis is on the use of lean concrete base (LCB), asphalt treated
10
permeable base (ATPB), cement treated permeable base (CTPB), and asphalt concrete
base (ACB). CTB can only be used with special permission because of the relatively
poor performance of many CTB sections. Non-erodible bases reduce the faulting
development rate, however, eventually the aggregate interlock degrades in the joints and
faulting will develop. Newer pavements without dowels may eventually become
candidates for dowel bar retrofit.
The most common rehabilitation strategy for failed rigid pavements is the
cracking and seating of the existing PCC slabs followed by an asphalt concrete overlay.
Some of these rigid pavements are failed primarily in terms of roughness from faulting.
In particular, if the truck lanes (outer one or two lanes typically) require an AC overlay
because they are cracked as well as faulted, the inner passenger lanes which are
uncracked but faulted must also be overlaid to maintain a uniform elevation across the
lanes. The AC overlay thickness is typically 120 to 180 mm. AC overlays of rigid
pavement cost about $107,000 per lane-kilometer in 1998-99.
If faulting is the only form of failure on a pavement, it is typically temporarily
eliminated with a diamond grinding process or cracking and seating followed by an
asphalt concrete overlay. Grinding of rigid pavements costs about $35,500 per lane-
kilometer in 1998-99.
In 1998-99 Caltrans contracted out about $29,6500,000 on AC overlays of rigid
pavements, and $5,700,000 on grinding. Maintenance and rehabilitation work performed
by Caltrans forces is not included in these costs.(1)
If load transfer is poor across slabs, pavements that have been diamond ground to
remove faulting may develop faulting again fairly quickly, on the time scale described in
11
Table 1. AC overlays do not result in later development of faulting on Caltrans
pavements because Caltrans cracks and seats the slabs prior to overlay. On the other
hand, AC overlays cost about three times more than diamond grinding. The diamond
grinding and AC overlay strategies are the primary options that should be compared to
dowel bar retrofit in terms of Life Cycle Cost to help select the optimal strategy.
1.5 Overview of Dowel Bar Retrofit Technology
Improved techniques for retrofitting existing concrete pavements with dowel bars
have been developed over the past seven years by the Washington State DOT, among
others. Dowel bar retrofitting (DBR) consists of sawing slots for the dowels across
transverse joints, inserting the dowels, and grouting them in place. This is followed by
grinding to remove faulting and smooth the grout surface where the dowels were
installed. The joint load transfer provided by the dowels significantly slows the
development of new faulting under truck traffic.
Dowel bar retrofit is not appropriate if the concrete slabs have multiple cracks or
if there are other significant durability problems with the pavement such as alkali-silica
reaction (ASR), sulfate attack, D-cracking, or other concrete problems. D-cracking is a
concrete materials problem that typically occurs in areas with prolonged freezing
temperatures. It is seldom observed in California.
WSDOT has estimated that based on Washington state traffic volumes, dowel bar
retrofit must last about 13 years in order to be economically viable compared to other
strategies. The cost break point of dowel bar retrofit versus diamond grinding alone and
AC overlay has not yet been established using Caltrans Life Cycle Cost Analysis
12
procedures. In addition, both WSDOT and Caltrans are interested in determining the
estimated performance life of DBR projects for inclusion in Life Cycle Cost Analysis.
DBR in Washington and other states has typically used epoxy coated dowel bars.
The epoxy coating is intended to slow dowel bar corrosion. The use of fiber reinforced
polymer (FRP) dowels has been suggested as a means of eliminating the potential for
corrosion failure. The effects of the lower stiffness of FRP dowels on faulting
development, and their fatigue characteristics under repeated loading in rigid pavements
is not known at this time.
WSDOT began using four dowels per wheelpath (8 dowels per joint) as standard
design. Caltrans used uniform spacing of dowels across the entire transverse joint (9
dowels per joint) on the DBR experiment project on I-10 in Los Angeles County in 1999.
WSDOT has recently moved to the use of three dowels per wheelpath (6 dowels per
joint), but has not been able to assess the impact of the new design on performance.
WSDOT has generally found no problem with DBR on slabs with longitudinal
cracks, and on transverse cracks, but has not yet determined from field projects whether
the long-term performance of those slabs are the same as for uncracked slabs.
2.0 GOAL 7 TEST PLAN OVERVIEW
2.1 Purpose of the Research and Expected Outcome
The goal of this research is to establish whether the dowel bar retrofit (DBR)
rehabilitation technique provides adequate performance relative to its cost for the
rehabilitation of rigid pavements. If the additional pavement life obtained with DBR and
construction cost result in a Life Cycle Cost that is comparable to or less than traditional
13
rehabilitation or reconstruction strategies, then DBR will likely be considered by Caltrans
as an option for pavement rehabilitation. Life cycle cost advantages alone do not
determine which option will be selected, but it is used in combination with other factors
such as traffic delay constraints, available funds, and long-term plans for a facility.
This test plan is designed to provide Caltrans and the other research partners with
important information regarding the DBR rehabilitation treatment. The research program
is expected to provide the following:
• Data on the feasibility of the dowel bar retrofit rehabilitation treatment based
on the existing condition of the concrete slabs. The existing condition would
be evaluated in terms of level of faulting, fatigue cracking, corner cracking,
and age of the slabs.
• Magnitude of load transfer restoration provided by DBR.
• Determination of the expected life of a DBR pavement based on the condition
of the slabs at the time of rehabilitation and the measured load transfer
efficiency.
• Mechanism of failure of the dowel bars at the end of their useful life.
• Best practice of dowel bar retrofit treatment in terms of design, materials, and
construction.
• An indication of the best rehabilitation treatment based on life-cycle-cost-
analyses.
14
2.2 Program Approach
In order to obtain the expected outcome of the research, the program will address
the following four areas of research:
1. Field Accelerated Pavement Testing with the Heavy Vehicle Simulator
HVS): to collect full-scale data quickly, although with heavier loads than
normally occur under real traffic. This testing also includes measurement of
load transfer efficiency (LTE) and other pavement properties with the Falling
Weight Deflectometer (FWD). Several generic types of dowels will be
included in the field test sections. Note that an HWD (Heavy Weight
Deflectometer) will be used for FWD measurements—the only distinction is
that the HWD is capable of applying greater loads than an FWD.
2. Field Live Traffic Testing: to collect field data on a long-term basis
(approximately two years) under real loads. This testing permits calibration of
HVS and analysis results.
3. Laboratory testing of materials: permits evaluation of additional variables
that cannot be included in the HVS testing, such as corrosion of the dowels
and dowel types not included in the field test sections. Laboratory testing is
also used to characterize materials used in the HVS test sections.
4. Modeling:
· Finite element analysis of doweled concrete pavement joint: allows for
performance prediction of other options without testing; permits
extrapolation of HVS results.
15
· Compilation of performance data from existing DBR projects
throughout the USA: allows for calibration of HVS and analysis results
to field project results.
· Life-Cycle-Cost-Analyses.
The objectives for each research area follow.
2.2.1 Accelerated Pavement Testing with the Heavy Vehicle Simulator
The general objective of the accelerated pavement testing with the HVS is to
evaluate the performance of full-scale pavement with and without dowel bar retrofit
under wheel loading with respect to faulting and joint distress. The results will be used to
determine whether the DBR treatment will provide the performance desired by Caltrans
and other research partners. The HVS trafficking is intended to accelerate pavement
damage while closely approximating the distress mechanisms that would occur under
normal traffic loading.
Accelerated pavement testing will be conducted at several locations to test various
slab conditions under various environmental conditions, particularly differences in
support from the underlying layers and differences in curling due to different climates.
The variables considered in the test program will be:
• pavement age, represented in the number of years since the pavement was
constructed;
• existing condition, represented as the amount of physical distress determined
from visual inspections, deflection testing, laboratory testing, and traffic; and
16
• climate condition, represented by precipitation regime at the project location
(wet or dry). Climate condition will be controlled if necessary at a given site
to maintain relatively constant temperature and subsurface water conditions
by means of the temperature cabinet and introduction of water into the
pavement.
The matrix of accelerated pavement testing proposed for this research goal is
summarized in Table 2.
Table 2 Matrix of Variables for Accelerated Pavement Testing
Pavement Conditions Climate Condition
Age ExistingCondition Wet Dry
Old Bad
Old Good
New Bad
More detailed descriptions of each experiment are presented in Appendix A.
At each location, accelerated pavement will be conducted on three or four slabs,
including the joints at each end of the slab. The slabs to be tested will include all or some
of the following conditions:
• Two undoweled joints, which will serve as the control section,
• Doweled joints,
• Doweled transverse cracks,
• Slabs with and without a longitudinal crack.
The control and dowel bar retrofitted sections will be tested using bi-directional
loading of 40, 80, and 100 kN on dual wheels with highway tires, and possibly the 150
17
kN aircraft single-tire wheel to accelerate damage. The legal limit for a highway wheel
load is 44.4 kN. The performance of the various test sections will be evaluated by
measuring the load transfer efficiency across the joints and/or transverse cracks. The
HVS loading will be applied at a speed of seven kilometers per hour along the slab in
both directions. Trafficking loads will be channelized over the dowels in the wheelpath
in order to accelerate damage.
The estimated time for completing each HVS location is four to six months,
depending on the number sections to be tested and the individual performance of the
pavements.
2.2.2 Live Traffic Testing
Live traffic testing will be performed at locations where safety, maintenance, and
other considerations allow the district to permit it. At the current time it is assumed that
this will only be implemented at Ukiah.
The objective of these tests is to evaluate the longer-term performance of the
dowel bar retrofit treatment under normal loading conditions. This is a long-term test
program that will permit the calibration of HVS results to normal traffic loads and speeds
and seasonal variation over several years.
Live traffic testing will be conducted on test sections that will replicate the HVS
test sections described in Section 2.3. A weather station will be used to record weather
conditions at the test site. Load transfer efficiency and slab corner movement will be
recorded using deflection gauges placed beneath the shoulder surface at the edge of the
slabs and an automatic data acquisition system placed off the roadway. The estimated
time for completing the live traffic testing is about two years from the time that they are
18
instrumented. Because the sections will be subjected to live traffic, all of the sections
will be trafficked at the same time. Testing may continue somewhat longer, depending
upon district considerations and the durability of the instrumentation.
2.2.3 Laboratory Testing and Material Investigation
Laboratory testing will provide information regarding the structural integrity and
condition of the existing slabs, properties and durability of the various construction
materials, and the effects of construction and design variables on the performance of the
DBR rehabilitation treatment. The laboratory testing will be divided into two primary
areas of interest: laboratory testing of existing in-situ materials and durability testing of
materials used in the DBR treatment.
2.2.3.1 Laboratory Testing of In-situ Materials
Laboratory testing of in-situ materials is necessary to establish the condition of
the existing concrete slabs. Cores will be obtained in order to determine the compressive
strength characteristics of the slabs and cement treated bases (if applicable and possible).
In-situ dynamic cone penetrometer (DCP) testing will be conducted to estimate the
strength of bases, subbases, and the subgrade. Raw materials used for the DBR grout will
be sampled and beams and cylinders will be prepared from the grout to measure its
strength gain.
2.2.3.2 Laboratory Durability Testing of Dowels
For DBR to be effective in reducing the potential for faulting, the properties of the
dowels must remain relatively constant throughout the design life, and preferably long
19
afterward. Metallic bars have the risk of corrosion while fiber reinforced polymer (FRP)
dowels have the risk of damage due to fatigue loading. The potential for damage to FRP
dowels of environmental degradation is minimal unless they exposed to sunlight prior to
their installation in the slab.
Samples from representative manufacturers of several types of dowels will be
collected. Metallic dowel types (plain steel, epoxy coated, stainless clad, hollow
stainless) will be subjected to accelerated corrosion testing in the laboratory. Relative
corrosion rates will be measured. The translation of the accelerated laboratory results to
field conditions in different climate regions in California will require careful
consideration. As a minimum, the different dowel types will be ranked from the
accelerated laboratory testing, after consideration of any potentially biases of the test
conditions for the different dowel types.
Samples from FRP dowels will be subjected to shear fatigue testing. A new
device will need to be developed to run this test.
2.3 Test Site Selection and Test Section Layouts
The test site locations will be selected and evaluated based on the matrix of
variables presented in Table 2. Selection will depend in large part on which locations
districts can make available for lane closure and HVS testing. A description of each of
the test sites is presented in Appendix A.
Three to four sections will be tested under the HVS and three to four under
normal traffic, if possible, for each DBR experiment location. The sections will be
numbered chronologically as testing proceeds. Live traffic sections will be numbered
based on the HVS sections the live traffic sections replicate plus the two letters LT. For
20
example, the live traffic section that replicates HVS Section 553 will be designated
Section 553LT.
Typical Caltrans plain jointed rigid pavements were described in the introduction
of this test plan. Sections representative of those eligible for DBR will be selected for the
HVS test sections.
3.0 IN-SITU MATERIALS TESTING
Existing materials including the PCC slabs, base materials, and subgrade soil will
be tested to determine their thickness and strength. In addition, the grout used for the
DBR installation will be sampled and tested.
3.1 Existing Materials Sampling
Three cores per test slab (102-mm diameter) will be taken from the existing
concrete slabs and transported to the UCB laboratory. Tests will be performed on these
cores to determine the in-situ compressive strength of the concrete and to verify the
concrete slab thickness.
3.2 Base/Subbase Materials and Subgrade Soils
Where possible, materials samples of the base, subbase and subgrade materials
will be obtained and taken to the UCB laboratory for testing. Estimated quantity of the
materials is shown in Table 3.
Table 3 Field Material Sampling PlanMaterial Quantity Responsible for Sampling
CTB appropriate amount UCBAB 25 kg UCB
Subgrade Soil 25kg UCB
21
3.3 Dynamic Cone Penetrometer (DCP)
Dynamic Cone Penetrometer tests will be conducted through the aggregate base,
subbase, and subgrade soil in locations where slab cores have been obtained. The DCP
provides information regarding the in-situ shear strength of the unbound pavement layers.
The DCP results for a material can be correlated to the CBR and elastic modulus. Work
is underway at UCB to relate DCP measurements to R-value.
3.4 Ground Penetrating Radar (GPR)
GPR testing will be conducted on the test sections to evaluate its effectiveness in
measuring:
• Dowel bar vertical location in the slabs;
• Horizontal and vertical alignment of the dowels bars in the slabs; and
• Presence of any voids between the grout and the dowel bars.
At this time, coring is the only option to determine dowel location, dowel
alignment (or even the presence of dowels) once the construction process has been
completed. Dowel misalignment and lockup can cause failure of the dowel bar retrofit.
3.5 Falling Weight Deflectometer (FWD)
The FWD will be used to measure deflections on the existing pavement at the slab
center, edges, corners, and across joints. This data will be used for backcalculation of
pavement layer moduli and load transfer efficiency across the transverse joints and
transverse cracks. Load transfer efficiency (LTE) will be measured with the FWD:
• Before the dowel bar retrofit;
22
• After the dowel bar retrofit; and
• After HVS testing.
LTE in each of the cases listed above will be measured twice in a 24-hour period,
once in the early hours of the morning when the slab temperature is lowest and there is
maximum upward curl of the slabs at the joints, and once in the late afternoon when the
slab temperature is highest and there is maximum downward curl of the slabs at the joint.
The critical case for LTE is the night-time condition, when the joints are at maximum
opening due to thermal contraction, and the upward curl at the joints can create a
cantilever condition.
3.6 Grout Sampling Plan
Cylindrical samples of size 100 × 200 mm and prismatic beam samples of size
152 × 152 × 533 mm will be made from the concrete material (grout) placed in the field.
Eight cylinders and eight beams per test section will be collected and transported to the
Pavement Research Center laboratory at UCB to perform strength tests. Table 4 shows
the sampling schedule for grout. The grout sampling and respective tests are intended to
provide information about the strength gain and ultimate strength of the DBR grout.
Table 4 Field Grout cylinder sampling, 100 mm x 200 mmGrout SampleCuring Time
Number ofSamples perTest Section
Number of TestSections
Total Number ofCylinders
100 × 200 mm
Total Number ofBeams
152 × 152 × 533 mm3 Hours 2 3 or 4 6 or 8 6 or 824 Hours 2 3 or 4 6 or 8 6 or 87 Days 2 3 or 4 6 or 8 6 or 828 Days 2 3 or 4 6 or 8 6 or 8
Total Cylinders: 24 or 32 24 or 32
23
4.0 FIELD TEST PROGRAM
The purpose of the field test program is to develop joint distress relations for full-
scale slabs under realistic loading conditions and to evaluate the performance of the
dowel bar retrofit rehabilitation technique. The HVS field test program is conducted to
quickly develop the joint distress relations and evaluate the performance of the DBR
treatment. The purpose of the live traffic field test program is to calibrate the results of
the HVS field test program under normal loading and seasonal climate conditions.
4.1 Instrumentation
Instrumentation will be placed in/on test sections to measure curling, joint
deflections, and load transfer efficiency (LTE). Joint deflection measuring devices
(JDMD) and, if possible and practical, Multi-Depth Deflectometers (MDD) will be
placed in three test sections to capture displacements caused by HVS trafficking.
Thermocouples will be placed in the slabs to relate curling and joint opening to
temperature change.
The following sections describe the instruments that will be used.
4.1.1 Multi-Depth Deflectometer (MDD)
If possible and practical, Multi-Depth Deflectometers (MDD) will be placed in
three test sections to capture displacements caused by HVS trafficking. MDDs use
Linear Variable Differential Transformers (LVDTs) to measure vertical deflections under
dynamic loading at several depths in the pavement structure. Figure 5 shows a typical
MDD installation on a rigid pavement.
24
PCC
Aggregate Base
Subgrade
Joint
Chucks attached to rod anchored 3.3 m down
MDDs
Figure 5. MDD setup for measurement of pavement structure deflection at joint orcrack.
4.1.2 Joint Deflection Measuring Device (JDMD)
JDMDs will be used to measure vertical and horizontal displacement caused by
HVS loading and environmental changes. JDMD are dc-operated Linear Variable
Differential Transformers (LVDTs) that are mounted on plates attached to a rod driven 1
m into the shoulder for absolute vertical displacement measurement. For relative
displacement, the LVDTs are mounted on blocks glued to one side of a selected
transverse joint to measure horizontal displacement across a joint. The particular LVDT
model used, an HSD 750-500 manufactured by Macro Sensors, was chosen because it is
25
hermetically sealed and has the ability to withstand moisture. The HSD 750-500 has a
total range of 25.4 mm.
An HVS test section on PCC includes trafficking across two joints such that one
full slab and two partial slabs are trafficked. Five JDMDs measuring absolute joint
displacement will be placed near the shoulder edge: one at the corner of each slab at each
joint (4 total) and one at the center of the full slab, as shown in Figure 6. A sixth JDMD
will measure the relative displacement of the joint nearest the tow end of the HVS to
obtain measurement of horizontal joint movement.
TT
TT
JDMD TMDD TCFigure 6. Location of instrumentation on typical test section.
JDMDs will also be placed at slabs that won’t be tested by the HVS in order to
capture displacements due to environmental changes. These JDMDs will be installed
below the road surface safe from traffic so that measurements can continue when the test
section is opened to traffic. A smaller model HSD 750-250 (12.7 mm range) or smaller
will be used for this purpose. Typical JDMD setups are presented in Figures 7–10.
26
PCCAC Shoulder
Base
Anchor to base
LVDT
To data
Figure 7. JDMD setup for absolute vertical deflection measurement of PCC.
Base
To data acquisition
Anchor to base
PCC
LVDT
Figure 8. JDMD setup for absolute vertical deflection measurement, front view.
27
Base
Anchor to base
To data acquisition
PCC
LVDT
Figure 9. JDMD setup for absolute vertical deflection measurement at middle slab.
To data acquisition
LVDT for Vertical Displacement Measurement Relative to Slab B
LVDT for Horizontal DisplacementMeasurement Relative to Slab B
A B
Target and LVDT Blocks Epoxied to PCC Surface
PCC
AggregateBase
Joint
Figure 10. JDMD setup for relative horizontal and vertical displacementmeasurements over a crack or joint.
28
4.1.3 Thermocouples
Type K thermocouples will be installed in the PCC in various locations to
measure temperature at the surface, 50, 100, 150, and 200 mm below the surface.
Temperatures will be recorded during data collection of JDMDs and MDDs and
automatically at sections not subjected to HVS testing. For automatic data collection,
Campbell Scientific CR10X data acquisition systems will be used.
Given that the HVS will be testing on existing PCC, holes will need to be drilled
into the PCC to provide an installation point for thermocouples. Sets of thermocouples
will be placed in the middle of a slab, center edge, corner, and at the transverse center
near a joint.
A typical thermocouple setup is presented in Figure 11.
Thermocouple Wiresto Data Acquisition Wooden Dowel
Hole Drilled forInsertion of Thermocouples
Tape to Hold Thermocouple Wires in Desired Levels
Thermocouple Ends at 0, 50, 100, 150, and 200 mm Below Surface
Figure 11. Typical thermocouple installation with wires on wooden dowels fortemperature readings at various depths.
29
4.1.4 Weather Station
Weather data, including air temperature, relative humidity, wind speed, and
rainfall, will be collected using a Davis Weather Station. A picture of the Davis Weather
Station is shown in Figure 12.
Figure 12. Davis Weather Station used to obtain weather data at test sites.
30
4.1.5 Failure Mechanisms
The failure mechanism for the test sections is the reduction in load transfer
efficiency (LTE) across joints and cracks. If any faulting occurs, it will be measured.
However, faulting is not expected because of the bi-directional trafficking to be applied
by the HVS.
Other causes of failure may include:
• Distresses caused by the retrofit process itself (dowel misalignment and
lockup),
• Deterioration of the dowel due to corrosion, cracking, or loosening.
4.2 HVS Testing Program
4.2.1 Traffic Loading
The HVS trafficking will be initiated using a 40-kN load on dual tires and
gradually increased to 80 kN and then to 100 kN. The traffic load will finally be
increased to 150 kN using a single aircraft tire to accelerate the process, if required.
4.2.2 Direction of Loading
Bi-directional loading will be used on all sections.
4.2.3 Location of Loading on the Slab
Loading with the dual wheel tires will be centered on the natural wheelpath of the
pavement and over the centerline of the retrofitted dowel sets in each wheelpath for all
tests. No transverse wander will be used for HVS loading.
31
4.2.4 Environmental Control
No environmental control will be provided, but environmental conditions during
testing will be monitored. The testing will be sequenced at each location to reduce or
balance the impact of weather on comparisons between different experiment variables.
4.3 Falling Weight Deflectometer (FWD) Testing Program
FWD Deflection data will be obtained along three rows: 1) the centerline of the
lane on which the HVS test sections are located, 2) along the edge adjoining the AC
shoulder, and 3) along the edge adjoining the adjacent lane. Note that in some cases, it
may not be possible to conduct tests on all three rows. In particular, tests along the edge
adjoining the adjacent lane are sometimes not possible due to the location of a k-rail
barrier.
Data will be taken within the limits of the project. The FWD will be properly
setup to achieve plate loads of 10 and 20 kips (44.5 and 89 kN). The spacing of the
geophones starting from the loading plate will be as follows: 0, 200, 300, 800, 1200,
1600, and 2000 mm. To measure deflections across a joint, the FWD will be positioned
such that the joint/crack of interest is between geophone 2 (200-mm setting) and
geophone 3 (300-mm setting).
The first test (centerline or edge) will always start at the center of a slab, which is
required for structural and load transfer efficiency analyses using the pavement analysis
program ELMOD. The coordinates of each test with respect to the coordinates of the
first test are critical as it tells the program where the tests were conducted. Each test will
have an ID number X.Y, with X denoting the distance from the first test and Y denoting
the position on the slab as follows: center slab (.1), centerline joint (.2), slab center at the
32
shoulder edge (.21), slab corner at the shoulder edge (.3), slab center at the adjacent lane
edge (.23), and slab corner at the adjacent lane edge (.33), as shown in Figure 13.
Station 0 Station 5 Station 10
Centerline
Shoulder Edge
5.1 10.2
5.21 10.3
10.335.23Adjacent Lane Edge
Direction of Traffic
Figure 13. FWD load plate locations and their respective Y-coordinates.
4.4 Live Testing Program
The live test sections will be instrumented exactly the same as the HVS test
sections. Data will be collected using an automatic data acquisition with a data logger
collecting temperature, rainfall, wind speed and other climate data, and deflections from
the JDMDs, on a regular basis. The data will be downloaded from the data acquisition
system via cell phone.
5.0 LABORATORY TESTING PROGRAM
The laboratory testing program included in this test plan includes the following
objectives:
1. Measure strength of existing concrete in the retrofitted slabs.
2. Measure strength and strength gain of grout used for dowel bar retrofit.
33
3. Characterize underlying pavement materials, including the cement treated
base, aggregate subbase, and subgrade.
4. Measure dowel bar durability: relative corrosion resistance of different
metallic dowel types using representative products of each type. Also,
develop and perform an appropriate durability test for fiber reinforced
polymer dowels.
5.1 Static Strength Tests of Existing Concrete
Static compressive strength tests will be performed on 100-mm diameter cores
following ASTM C39.
5.2 Static Strength Tests of DBR Grout
Static compressive strength tests will be performed on 100 mm diameter × 200
mm tall cylinders following ASTM C39. Static flexural strength tests will be performed
on 152 × 152 × 533 mm beams following ASTM C78.
These specimens will be made in the field using grout materials sampled as it is
being placed in the dowel bar slots. The specimens will be cured in the field for the first
24 hours and tested following the schedule shown in Table 4. The field curing conditions
will include spraying a curing compound over the surface and leaving the specimens in
the shade at ambient temperatures. Specimens will be transported to the UCB laboratory
in Richmond within approximately 24 hours, and further curing will occur under
conditions of 23°C temperature and 95 percent relative humidity.
34
5.3 Cement Treated Base, Aggregate Subbase and Subgrade Tests
5.3.1 Cement Treated Base
If the CTB has sufficient strength to permit sampling, cores will be taken for
observation of their condition. Permeability tests may also be performed on the CTB
cores.
5.3.2 Aggregate Subbase and Subgrade
If they can be collected, the aggregate subbase and subgrade will be tested for
gradation and Atterberg limits.
5.4 Dowel Bar Durability Tests
Testing of dowel bars will include both destructive and non-destructive tests.
Non-destructive tests will be performed at regular intervals. Destructive tests will be
performed on one of the replicates every four months, which will destroy that specimen
for further monitoring. The measurement methods and the time basis on which they will
be performed is shown in Table 5. Further description of each of the tests is presented in
the following sections.
5.4.1 Half-cell Potential of Metallic Dowels
The half-cell potential measurement has been widely used in the field due to its
simplicity and general agreement among researchers that this technique provides a good
indication of the existence of active corrosion along the steel reinforcement in concrete.
35
Table 5 Metallic (plain steel, epoxy coated, stainless clad, hollow stainless)Dowel Bar Test and Measurement Methods
DowelType Test Frequency Purpose
metallic1 Half-cell potential Weekly To monitor corrosion state insitu
metallic Corrosion resistivity Weekly To measure the potential forcorrosion
metallic Visual inspection WeeklyTo inspect physical change:stains, cracks, and change ofspecimen dimension.
metallic Weight loss Every othermonth
To inspect mass loss and cross-section loss.
metallic Microscopic inspection Afterweight loss
To study the corrosion damageon micro-structure of the steel.
fiberreinforcedpolymer(FRP)
Destructive mechanicalperformance tests: flexuralmodulus (stiffness), shearstrength, tensile strength
To bedetermined
To study shear and fatigueproperties of FRP dowels
1 metallic dowel types include plain steel, epoxy coated, stainless clad, and hollowstainless
All metals display a different interface potential with respect to a reference
electrode. During corrosion, the metal is polarized and the interface potential changes.
The half-cell potential method (ASTM C876-91) is based on the principle that the
potential decreases as the corrosion process progresses.
Half-cell measurements may be made relatively easily using only a potential
meter and a standard reference electrode, such as a copper-copper sulfate electrode
(CCS). As shown in Figure 14, the voltmeter connects the steel with the CCS such that
the steel is at the positive terminal of the voltmeter. The potential recorded in the half-
cell measurement can be used to indicate the probability of corrosion of the steel
reinforcement, as shown in Table 7. A potential map that plots the potentials obtained on
the locations of the reference electrode is usually used to indicate the possible sites of
active corrosion.
36
Figure 14. Copper-copper sulfate half cell circuitry.
Table 7 ASTM Criterion for Corrosion of Steel in Concrete (ASTM C876-91)Measured Potential (mV vs. CSE) Corrosion probability>-200 Low, 10% risk of corrosion-200 ~ -350 Intermediate<-350 High, 90% risk of corrosion
It is more accurate to correlate the measured potential and the corrosion condition
of embedded steel. By correlating measured potential with the concrete resistivity, the
corrosion sites along the dowels can be located more accurately.
5.4.2 Corrosion Resistance of Metallic Dowels in Concrete Pavement
In the field, dowel bars are exposed to moisture and de-icing salts in the vicinity
of the joints, and it is recognized that it is not possible to construct and maintain a
watertight joint. Consequently, metallic dowels bars are subject to corrosion. The loss of
cross-sectional area of the dowels bars can result in the loss of load transfer efficiency
across the joint.
37
The American Concrete Paving Association estimates that steel dowel bars can
fail in as little as seven to fifteen years while the concrete highway slab itself can perform
for 35-40 years. Both stainless steel and epoxy-coated steel are often used for structural
applications because of their high corrosion resistance.(5, 6) Due to the special situation
of pavement joints, the corrosion resistance of these materials when used as dowel bars in
pavements is not clear and no comprehensive, well balanced study has been performed
yet.
This project includes an evaluation of the corrosion resistance of various
commercially available steel dowel bars, including plain steel, stainless steel, and epoxy-
coated steel. The goal of this research is to develop a database of accelerated laboratory
results for the selection of a steel dowel type. The corrosion state of dowels cast in
concrete and conditioned in the laboratory will be monitored by non-destructive tests in-
situ, close physical inspection, and eventually destructive weight-loss measurement.
Mechanical performance and microscopic study of the dowel bars will help further the
study.
5.4.2.1 Specimen Preparation and Conditioning
Beam specimens, 152 × 152 × 533 mm will be cast with the dowels inside in the
longitudinal direction, at mid-slab height and width. A joint will be formed in the middle
of the beams using backer board or plastic. The joint will be cast through the entire
beam.
The concrete grout material for the beams will be prepared using a typical dowel
bar grout mix design, a typical Fast Setting Hydraulic Cement (FSHC) meeting Caltrans
current DBR specifications, and locally available aggregate used by a DBR contractor.
38
To the extent possible, the grout material will match that typically used in practice in
California under current specifications.
Four dowel types will be included in the experiment:
• plain steel dowels
• epoxy coated dowels,
• stainless-clad dowels, and
• concrete filled, hollow stainless dowels.
All dowels will be 38 mm in diameter unless that size is not available. A set of
each of the four types of dowel will be obtained from representative manufacturers.
Prior to casting, all dowels will be weighed. Coated thin metal wires will be
attached to the dowels prior to casting to permit half-cell potential and resistivity
measurements.
Once cast, three replicates of each of the four doweled beams will be conditioned
for up to one year under the following conditions:
• 38°C, 100 percent relative humidity
• 4°C, 100 percent relative humidity
• 38°C, 50 percent relative humidity
• 4°C, 50 percent relative humidity
The specimen conditioning and dowel types are summarized in Table 6.
39
Table 6 Dowel Bar Specimens and Test ConditionsTest Conditions
Dowel Bar Type 38°C, 100%Relative
Humidity
4°C, 100%Relative
Humidity
38°C, 50%Relative
Humidity
4°C, 50%Relative
Humidity
Plain steel 3 replicates 3 replicates, 3 replicates 3 replicates
Epoxy-coated steel 3 replicates 3 replicates 3 replicates 3 replicates
Stainless-clad 3 replicates 3 replicates 3 replicates 3 replicates
Concrete filled,hollow stainless steel 3 replicates 3 replicates 3 replicates 3 replicates
5.4.3 Visual Inspection of Metallic Dowels
As the laboratory testing continues, the dowels will be visually inpsected for
corrosion on the portion of the dowel bar visible in the joint. The concrete may also
eventually crack if there is significant corrosion on the parts of dowel embedded in the
concrete, and the corrosion product is expansive.
5.4.4 Weight Loss of Metallic Dowels
Weight loss analysis is the simplest, and longest-established, method of
estimating corrosion losses of metals and alloys. A weighed sample of the metal or alloy
under consideration is introduced into the process, and later removed after a reasonable
time interval. The sample is then cleaned of all corrosion products and is re-weighed.
The proportionality between the weight loss m and the current rate Icorr, or
corrosion reaction rate is given by Faraday's Law:
m = IcorrtanF
where:
40
F = Faraday’s constant (96,500 coulombs/equivalent)
n = number of equivalents exchanged in the corrosion reaction
a = atomic weight
t = time
A corrosion rate (CR) in terms of mass loss per unit time per unit area is given by
the following equation:
CR = mAt
where A is the corrosion area.
From the first equation, the mass loss per unit time per unit area can be converted
to a total thickness loss, or average corrosion penetration rate (CR) (mm y-1) by the
following equation:
CR = mAtD
where D is the density of the metal.
Weight loss analysis has a number of attractive features that account for its
sustained popularity. First, it is simple—no sophisticated instrumentation is required to
obtain a result. Second, it is direct—direct measurement is obtained without theoretical
assumptions or approximations. Finally, it is versatile—it is applicable to all corrosive
environments and provides data on all forms of corrosion.
Initial preparation of the sample surface, and for cleaning the sample after use, is
critical in obtaining useful data. ASTM G1 gives useful guidelines for preparation,
cleaning, weighing of corrosion samples.
41
In the third equation above, it can be seen that the metal averages the amount of
weight loss over the period of exposure. It also assumes that the corrosion of the metal is
uniform. So it is important to evaluate the corrosion area visually. ASTM G46 gives
procedures for analysis of localized corrosion.
5.4.5 Microscopic Examination of Metallic Dowels
Scanning Electron Microscopy (SEM) may be used to study the microstructure of
the dowel bars in the corrosion area. The microscopic examination of the damage
mechanism will facilitate the understanding of the corrosion mechanism and the
prediction of corrosion resistance in the various dowel bars used.
5.4.6 Destructive Mechanical Performance Tests of FRP Dowels
The primary chemical durability issue for fiber reinforced polymer (FRP) dowels
is exposure to ultraviolet light, which breaks the bonds in the polymer. Given that FRP
dowels will be embedded in slabs in the field, with minimal exposure to direct sunlight
during their life, this is not expected to be a major issue. However, tt is important that the
FRP dowels be kept away from direct sunlight during storage prior to construction.
The primary durability issue for FRP dowels is fatigue damage from repeated
bending and repeated shear loading. Damage to the dowels during construction, such as
notching and nicks due to rough handling which can lead to the nick or notch propagating
through the dowel, will also be an issue. Notching or nicks can also occur under loading
due to penetration of sharp aggregates in the concrete into the dowel.
42
5.4.6.1 Shear Fatigue Test of FRP Dowels
To address the potential for fatigue damage of FRP dowels, a test will be
developed to subject the dowels to direct repeated shear. The test will consist of casting
short dowels in a concrete prism with a cast joint in the middle, as illustrated in Figure
15. The prism will be tested in the SHRP Shear Tester (SST). An opening in the range
of 2 to 5 mm will be set between the two concrete prisms, and the dowel will be
subjected to direct shear over that opening. The specimen will be subjected to a repeated
sinusoidal shear stress wave, the magnitude of which will be selected based on finite
element analysis of doweled joints in full-scale pavements under highway loads.
Movement between the two prism halves will be measured with an LVDT.
43
Figure 15. Diagram of FRP dowel shear fatigue test setup using the SST.
The shear displacement should increase with repeated loads due to loosening of
the dowel in the concrete and/or stiffness reduction in the dowel. The frequency of the
shear wave will be selected based on slow moving highway traffic loading speeds.
This test will be performed at two temperatures, two stress levels, two
temperatures, and two replicates. It will be performed on two types of FRP dowels, and
will be replicated (except for temperature) on two steel dowels, for reference. The
factorial is summarized in Table 8. A total of 20 tests will be performed. If the test is
44
successful, it will be repeated with notched dowels in the joint opening. The actual notch
dimensions and geometry will need to be determined.
Table 8 Experiment Design for FRP Dowel Shear Fatigue Tests.*
Dowel Type 50°Chigh stress
5°Chigh stress
50°Clow stress
5°Clow stress
Steel dowel 2 replicates 2 replicatesFRP dowel type 1 2 replicates 2 replicates 2 replicates 2 replicatesFRP dowel type 2 2 replicates 2 replicates 2 replicates 2 replicates*Entire matrix will be repeated with notched FRP dowels if successful.
5.4.6.2 Flexural Frequency Sweep Test of FRP dowels
Flexural frequency sweep tests will be performed on the FRP dowels to evaluate
their bending stiffness as a function of time of loading and temperature. This test will
measure the bending stiffness in the axial direction. The shear fatigue test, described in
Section 5.4.2.1, will provide an indication of the stiffness in the cross-direction.
The flexural frequency sweeps will be performed in the asphalt concrete flexural
beam machine using special clamps for the round dowels, as shown in Figure 16. The
test will be performed at two strain levels and two temperatures. Frequencies will be 20,
10, 5, 2, 1, 0.5, 0.2, 0.1, 0.05 and 0.01 Hz. The factorial is shown in Table 9.
Table 9 Experiment Design for FRP Dowel Flexural Frequency Sweep TestsDowel Type 50°C
high strain5°C
high strain50°C
low strain5°C
low strainFRP dowel type 1 2 replicates 2 replicates 2 replicates 2 replicatesFRP dowel type 2 2 replicates 2 replicates 2 replicates 2 replicates
45
Figure 16. Diagram of flexural frequency sweep test setup using the asphaltconcrete flexural beam machine.
5.4.6.3 Tensile Strength of FRP dowels
At present, a specific tensile strength test has not been developed. Such a test
may be developed and performed if deemed appropriate.
6.0 DESIGN EVALUATIONS
6.1 Mechanistic Analysis
Finite element analyses, material characterization, and results from the HVS
testing will be used to model the failure mechanisms in dowel bar retrofitted concrete
pavement so that predictions can be made for real traffic and pavement conditions in
California. This modeling will permit extrapolation of the limited HVS test section
results to develop predictions for other pavement and traffic scenarios.
The main output variables for the finite element analyses will be the bearing stress
on the concrete due to the dowel and the predicted load transfer efficiency. If possible,
these will be related to faulting.
46
The finite element analysis will consider the following variables:
• Dowel spacing
• Dowel size
• Number of dowels in the wheel path
• Dowel looseness
• Base/subgrade type and condition
• Slab dimensions
• Temperature regime in the slabs
The EverFE 3-dimensional finite element analysis program will be the primary
tool used for this analysis. EverFE is expected to be upgraded in the next year to meet
the requirements of this goal. The upgrade is being performed by the University of
Maine and the University of Washington and is being made possible by funding from
Caltrans.
The first step in the analysis will be the verification of the model used to predict
performance on the HVS test sections. After verification and any necessary
modifications, the model will be used to predict performance in different conditions.
6.2 Life Cycle Cost Analysis
After the best estimates of dowel bar retrofit performance life have been
established for different climate regions in the state, traffic levels, and pavement designs,
a life cycle cost analysis will be performed to estimate the required design life for DBR to
be economically justified. These results will provide an indication of the economics of
47
DBR, but must be used by Caltrans in conjunction with other criteria, per the Caltrans
Highway Design Manual, to determine when and where to use or not use DBR.
7.0 TESTING SCHEDULE
The following sections present the estimated time schedule for HVS field tests
and laboratory testing involved in this test plan. A Gantt chart containing the schedule
for the major tasks in the project based on current assumptions is shown in Figure 17.
7.1 HVS Field Tests
HVS testing takes one to two months per test section. The HVS is expected to
operate 24 hours per day, 7 days per week at each location. The two sites that have been
identified for HVS testing are on US101 in Mendocino county (District 1), and on SR14
in Los Angeles County (District 7). The US101 site will likely be tested in the spring of
2001. The SR14 site will be tested between the fall of 2001 and the summer of 2002.
7.2 Laboratory Testing
The testing of in-situ materials and concrete grout should be completed within
two months after construction of the DBR test sections.
The corrosion and FRP dowel testing will take one year to complete, beginning in
June 2001. Analysis of the data is expected to take approximately 4 months.
Finite element modeling and analysis will likely take 18 months. Life cycle cost
analysis should be completed at approximately the same time.
ID Task Name Duration Start Finish1 Goal 7 Dowel Bar Retrofit 545d Fri 01-12-00 Thu 02-01-03
2 Ukiah HVS tests 545d Fri 01-12-00 Thu 02-01-03
3 construct Ukiah sections 43d Fri 01-12-00 Tue 30-01-01
4 HVS tests Ukiah sections 66d Fri 02-02-01 Fri 04-05-01
5 set up Ukiah instrumentation 40d Mon 07-05-01 Fri 29-06-01
6 monitor Ukiah instrumentation 394d Mon 02-07-01 Thu 02-01-03
7 write Ukiah report 44d Fri 01-06-01 Wed 01-08-01
8 lab test Ukiah grout 23d Tue 30-01-01 Thu 01-03-01
9 Palmdale HVS tests 242d Thu 28-06-01 Fri 31-05-02
10 construct Palmdale sections 2d Thu 28-06-01 Sun 01-07-01
11 HVS tests Palmdale sections 137d Thu 20-09-01 Fri 29-03-02
12 lab test Palmdale grout 22d Thu 28-06-01 Fri 27-07-01
13 write Palmdale report 45d Mon 01-04-02 Fri 31-05-02
14 corrosion testing 305d Fri 01-06-01 Thu 01-08-02
15 cast corrosion specimens 17d Fri 01-06-01 Mon 25-06-01
16 monitor corrosion 261d Fri 15-06-01 Fri 14-06-02
17 write corrosion report 110d Fri 01-03-02 Thu 01-08-02
18 FRP lab testing 152d Mon 03-09-01 Tue 02-04-02
19 set up FRP tests 21d Mon 03-09-01 Mon 01-10-01
20 perform FRP tests 90d Mon 01-10-01 Fri 01-02-02
21 write FRP lab report 42d Mon 04-02-02 Tue 02-04-02
22 finite element analyses 217d Thu 01-11-01 Fri 30-08-02
23 life cycle cost analyses 45d Mon 01-07-02 Fri 30-08-02
24 write final report 45d Mon 02-09-02 Fri 01-11-02
25 finish goal 0d Fri 01-11-02 Fri 01-11-02
Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qt2000 2001 2002
Figure 17. Gantt chart (schedule and tasks) for Goal 7.
48
49
8.0 BENEFITS
The primary benefits of this project to Caltrans and the other research partners is
to provide information and tools to design and construct dowel bar retrofit projects for
maximum performance and to determine whether and under what conditions dowel bar
retrofit is the most cost-effective strategy for rigid pavement rehabilitation. Caltrans is
currently considering widespread use of dowel bar retrofit.
In addition, this project will provide information regarding the most effective
dowel materials, and the number of dowels to place in each wheelpath.
9.0 REFERENCES
1. Maintenance Program, California Department of Transportation. California, State ofthe Pavement Report, 1999. Sacramento, March, 2001.(http://www.dot.ca.gov/hq/maint/99sop.pdf)
2. Presentations by James Roberts, Robert Marsh and Kevin Herritt, ConcretePavement Rehabilitation Workshop/Seminar, Ontario, California, 16-18 July, 1997.
3. Darter, M., and E. Barenberg. Design of Zero Maintenance Plain Jointed ConcretePavements, Vol. 1, Development of Design Procedures." Federal HighwayAdministration Report No. FHWA-RD-77-111, 1977.
4. Macleod, D. R., and Monismith, C. L. Performance of Portland Cement ConcretePavement. Department of Civil Engineering, Institute of Transportation Studies,University of California, Berkeley. February 1979.
5. Sagues A., H. Perez-Duran, and R. Powers, “Corrosion Performance Of Epoxy-Coated Reinforcing Steel In Marine Substructure Service,” Corrosion, 1991 Nov,Vol 47 Number 11:884-893.
6. Gu, P., S. Elliott, J. Beaudoin, and B. Arsenault, “Corrosion Resistance Of StainlessSteel In Chloride Contamination Concrete,” Cement And Concrete Research, Vol.26, Number 8, pp.1151-1156, 1996.
50
APPENDIX A: UKIAH TEST EXPERIMENT PLAN
LOCATION
Three sections will be tested on State Highway 101 near Ukiah in Mendocino
County, California (see Figure A1). The site is located in the coastal mountain range.
The selected test site is located in a road cut section. The existing pavement is
approximately 30 years old with concrete slabs 200 mm thick resting on a cement treated
base. The pavement has skewed transverse joint spaced 3.6 m up to 12 m apart. The 5-
to 6-m long slabs all have a transverse crack located mid-slab. The 12-m long slab has
two transverse cracks located at approximately one-third slab length from the joints. Few
of the slabs exhibit longitudinal cracking. Figure A2 shows the layout of the project site.
Objectives
The objective of the accelerated pavement testing to be performed with Caltrans
HVS No. 2 (HVS2) on the Ukiah test sections sections is to evaluate the performance of
full-scale pavement with different type of dowel bar retrofit under wheel loading. The
testing will examine faulting and joint distress to determine whether dowel bar retrofit
will provide the performance desired by Caltrans and the other research partners. The
HVS trafficking is intended to accelerate pavement damage without significantly
changing the distress mechanisms that occur in the field.
The dowel bar retrofit experiment will consider the following variables:
• Two undoweled joints. This will be the control section.
• Two doweled joints and inclusion of a longitudinal crack.
51
• One doweled joint and one doweled crack
If the damage is not excessive following HVS loading, some of the retrofitted
joints/cracks will be left in place and opened to regular traffic. Data will continue to be
collected from the test sections as they are subjected to live traffic and environmental
conditions.
The dowel bar retrofitted and control sections will be evaluated using bi-
directional loading using 40-, 80-, and 100-kN dual and possibly an aircraft wheel under
a 150-kN load to accelerate damage. The performance of the various test sections will be
evaluated by measuring the load transfer efficiency across joints/cracks. The applied
loads will be moving at a speed of seven kilometers per hour along the slab in both
directions. The loading will be channelized (no traffic wander) in line with the dowels.
The data collected through accelerated pavement testing and measurement of
environmental conditions will be used in the evaluation of the adequacy of the dowel bar
retrofit rehabilitation treatment.
The results of the dowel bar retrofit of rigid pavements will provide Caltrans and
the other research partners involved in this study with the information needed to design
and construct dowel bar retrofit projects to obtain maximum performance. The results
will also help to determine where dowel bar retrofit is the most cost-effective strategy for
rigid pavement rehabilitation.
52
Test Section Layout
Three sections have been selected for HVS testing:
• Section 553: 11.4-m long slab located between Stations 86 and 124. This slab
has two transverse cracks located at Stations 96 and 107, respectively (see
Figure A3).
• Section 554: 3.3-m long slab located between Stations 186 and 197. This slab
has a longitudinal crack starting at Station 189 and ending to the joint at
Station 197. This longitudinal crack is located at about two-thirds the width
of the slab measured from the shoulder (see Figure A4).
• Section 555: 3.5-m slab located between Stations 383 and 396. This slab has
a longitudinal crack that crosses the length of the slab and is located at about
two-thirds the width of the slab measured from the shoulder (see Figure A5).
These three sections will also be opened to live traffic upon completion of HVS
trafficking. The test section numbers will be amended with a “-LT” as follows to identify
them as live traffic sections, (i.e., Sections 533-LT, 544-LT, and 555-LT).
Pavement Structures
The slabs are 200 mm thick and 3.7 m wide. The slabs are on a cement treated
base about 100 mm thick resting on the natural subgrade. All of the slabs have asphalt
concrete shoulders and have skewed, plain transverse joints with spacing varying from
3.3 m. to 12 m.
Figures A3 to A5 show the instrumentation layout for Sections 553, 554, and 555
and Sections 553-LT, 554-LT, and 555-LT.
53
Time Scales
HVS Field Tests
Caltrans has indicated that the test sections will be available for HVS testing for a
period of 4 months. The detour construction, pavement testing, and detour removal is
expected to begin in December 2000 and be completed by May 2001. The schedule for
HVS testing is summarized in Figure 17 in the main body of this document.
Laboratory Testing
The schedule for laboratory testing is shown in Figure 17 in the main body of this
document.
Figure A1. Ukiah project lo
s
Project Limitcation
PM 29.62
54
.
Figure A2. Slab layout and test sections.
55
TT
TT
8.0 m
5.131 m 3.302 m 2.946 m
AC Shoulder
PCC
2.43
8 m
3.65
8 m
JDMDMDDTCT
Joint 10 Joint 7Joint 8Joint 9
Figure A3. Section 553 (HVS).
56
TT
TT
AC Shoulder
PCC
2.43
8 m
3.65
8 m
JDMDMDDTCT
3.926 m 4.953 m3.353 m
8.0 m
Joint 17 Joint 16 Joint 15 Joint 14
Figure A4. Section 554 (HVS).
57
TT
TT
AC Shoulder
PCC
2.43
8 m
3.65
8 m
JDMDMDDTCT
8.0 m
4.953 m 3.505 m 5.029 m
Joint 32 Joint 31 Joint 30 Joint 29
Figure A5. Section 555 (HVS).
58
59
60
APPENDIX B: PALMDALE DBR TEST EXPERIMENT
LOCATION
Four sections will be tested on State Route 14 approximately 6 kilometers south
of Palmdale in Los Angeles County (see Figure B1). The test site is located in a road cut
with steep side slopes. The existing pavement is approximately 3 years old with 200-mm
thick concrete slabs resting on 100 mm of cement treated base and 150 mm of aggregate
sub base. The pavement has transverse joints spaced 3.7, 4.0, 5.5, and 5.8 m apart.
Figure B2 shows the layout of the project site.
Objectives
The objective of the accelerated pavement testing to be performed with Caltrans
HVS No. 2 (HVS2) at the Palmdale test sections is to evaluate the performance of full-
scale pavement with different type of dowel bar retrofit under wheel loading. The testing
will examine faulting and joint distress to determine whether dowel bar retrofit will
provide the performance desired by Caltrans and the other research partners. The HVS
trafficking is intended to accelerate pavement damage without significantly changing the
distress mechanisms that occur in the field.
The dowel bar retrofit experiment will consider the following variables:
• First test section has four epoxy coated steel dowels per wheel path.
• Second test section has three epoxy coated steel dowels per wheel path.
61
• Third test section has four dowels per joint, with one epoxy coated doweled
joint and one stainless steel hollow doweled joint plus one combination of
epoxy and hollow doweled crack.
• Fourth test section has four dowels per joint, with one joint and one crack for
Fiber Reinforced Polymer dowels and one joint for epoxy coated dowels.
The dowel bar retrofitted sections will be evaluated using bi-directional loading
with a dual-tire wheel under 40 kN, 80 kN and 100 kN loads, and possibly an aircraft
wheel under a 150-kN load to accelerate damage. The loading will be along the inside
wheelpath closest to the adjoining traffic lane. This load location was selected because of
extensive cracking along the asphalt concrete shoulder sides of the slabs from previous
testing. The longitudinal joint between the slab to be tested and the adjoining traffic lane
slab is an untied cold joint with minimal load transfer efficiency.
The performance of the various test sections will be evaluated by measuring the
load transfer efficiency across joints/cracks. The applied loads will be moving at a speed
of seven kilometers per hour along the slab in both directions. The loading will be
channelized over the centerline of the wheelpath and dowels. The estimated time for
completing the HVS testing is four to six months from September of 2001. The data
collected through accelerated pavement testing and measurement of environmental
conditions will be used in the evaluation of the adequacy of the dowel bar retrofit
rehabilitation treatment.
The results of the tests on dowel bar retrofit of rigid pavements will provide
Caltrans and other research partners with the information needed to design and construct
62
dowel bar retrofit projects to obtain maximum performance and to determine where
dowel bar retrofit is the most cost-effective strategy for rigid pavement rehabilitation.
Test Section Layouts
Four sections have been selected for HVS testing:
• Section 556 (Slab 39): 4.0-m long slab located between stations 893+20 and
893+30. The approach slab (Slab 38) has a transverse crack and the following
slab (Slab 40) has a longitudinal crack. Figure B3 shows this test section.
• Section 557 (Slab 36): 3.8-m long slab located between stations 893+00 and
893+10. This slab has a transverse crack. Figure B4 shows this test section.
• Section 558 (Slab 42): 5.8-m slab located between stations 893+30 and
893+40. Figure B5 shows this test section.
• Section 559(Slab 33): 5.3-m long slab located between stations 892+90 and
893+00. This slab has a transverse cracks located in the middle of the slab.
Figure B6 shows this test section.
Pavement Structure
All of the slabs are 200 mm thick by 3.7 m wide. The lengths vary to match the
joint spacing of the adjacent lane. The slabs are on a cement treated base constructed in
1998 following 1964 Caltrans specifications: approximately 100 mm of CTB resting on a
150-mm aggregate subbase on natural subgrade. All the slabs have asphalt concrete
shoulders. The slabs are made with a blend of 80 percent Fast Setting Hydraulic Cement
and 20 percent portland cement.
63
Figures B3 to B6 show the instrumentation layout on Sections 556, 557,558 and
559.
Time Scales
HVS Field Tests
Caltrans District 7 has indicated that the test sections will be available for HVS
testing for a period of 12 months. The schedule for HVS testing is summarized in Figure
17 in the main body of this document.
Laboratory Testing
The schedule for laboratory testing is shown in Figure 17 in the main body of this
document.
64
Project Location
Figure B1. Palmdale Project Location
Figure B2. Slab Layout and Test Sections
65
K-rail
Section 556
Figure B3. Section 556 (HVS)
66
Figure B4. Section 557 (HVS).
67
Figure B5. Section 558 (HVS).
68
Figure B6. Section 559 (HVS).
69