This monthly progress report (MPR) summarizes environmental restoration activities conducted by the Navy at Hunters Point Shipyard (HPS) during June 2005. This MPR is prepared in accordance with the HPS Federal Facility Agreement, Section 6.6. The MPR is presented in three sections: Section 1.0, Parcel Updates, summarizes key activities at each parcel completed during the past month and planned for the upcoming 2 months; Section 2.0, Schedule, identifies submittals, meetings, and field activities completed during the past month and planned for the upcoming 2 months; Section 3.0, Other, is intended for special announcements, changes in personnel, basewide issues, or other topics that are not included in Sections 1.0 or 2.0; Section 3 appears in this MPR only when needed. 1.0 PARCEL UPDATES This section summarizes key activities at each parcel completed during the past month and planned for the upcoming 2 months. 1.1 PARCEL B The activities completed during June 2005 and planned for the upcoming 2 months at Parcel B are summarized below. June 2005 Activities Continue to prepare the draft work plan for the investigation of groundwater and soil gas at Parcels B and C. Continue to prepare the draft technical memoran- dum in support of a Record of Decision amend- ment. Finalize the final quarterly groundwater report with responses to comments (RTCs) for July to Sep- tember 2004. Prepare the draft quarterly ground- water monitoring report for January to March 2005. Continue preparing the draft annual groundwater monitoring report. Complete field work for the April to June 2005 quarterly groundwater monitoring report. Continue to implement the work plan for the follow- on (Phase III) soil vapor extraction (SVE) treatability study. July to August 2005 Activities at Parcel B Submit the draft work plan for the investigation of groundwater and soil gas at Parcels B and C. Continue to prepare the draft annual groundwater monitoring report. Submit the draft summary report for the treatability study using sequential anaerobic and aerobic bioremediation at Building 134. HUNTERS POINT SHIPY HUNTERS POINT SHIPY HUNTERS POINT SHIPY HUNTERS POINT SHIPY HUNTERS POINT SHIPYARD ARD ARD ARD ARD MONTHL MONTHL MONTHL MONTHL MONTHLY PROGRESS REPOR PROGRESS REPOR PROGRESS REPOR PROGRESS REPOR PROGRESS REPORT JULY 28, 2005 USS John C. Stennis www.navybracpmo.org/bracbases/california/hps/default.aspx Hunters Point Shipyard South Basin India Basin San Francisco Bay Parcel F Boundary E D C B E-2 Non-Navy Property Non-Navy Property Parce l F Bou nd ary

HUNTERS POINT SHIPYARD - bracpmo.navy.mil · ity study using sequential anaerobic and aerobic bioremediation at Building 134. ♦ Continue to prepare the draft feasibility study (FS)

  • Upload
    hadieu

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

This monthly progress report (MPR)summarizes environmental restorationactivities conducted by the Navy at HuntersPoint Shipyard (HPS) during June 2005. ThisMPR is prepared in accordance with the HPSFederal Facility Agreement, Section 6.6. TheMPR is presented in three sections: Section1.0, Parcel Updates, summarizes keyactivities at each parcel completed during thepast month and planned for the upcoming 2months; Section 2.0, Schedule, identifiessubmittals, meetings, and field activitiescompleted during the past month and plannedfor the upcoming 2 months; Section 3.0, Other,is intended for special announcements,changes in personnel, basewide issues, orother topics that are not included in Sections1.0 or 2.0; Section 3 appears in this MPR onlywhen needed.

1.0 PARCEL UPDATESThis section summarizes key activities at each parcelcompleted during the past month and planned for theupcoming 2 months.

1.1 PARCEL BThe activities completed during June 2005 and plannedfor the upcoming 2 months at Parcel B are summarizedbelow.

June 2005 Activities

♦ Continue to prepare the draft work plan for theinvestigation of groundwater and soil gas at ParcelsB and C.

♦ Continue to prepare the draft technical memoran-dum in support of a Record of Decision amend-ment.

♦ Finalize the final quarterly groundwater report withresponses to comments (RTCs) for July to Sep-tember 2004. Prepare the draft quarterly ground-water monitoring report for January to March 2005.Continue preparing the draft annual groundwatermonitoring report. Complete field work for the Aprilto June 2005 quarterly groundwater monitoringreport.

♦ Continue to implement the work plan for the follow-on (Phase III) soil vapor extraction (SVE) treatabilitystudy.

July to August 2005 Activities at Parcel B

♦ Submit the draft work plan for the investigation ofgroundwater and soil gas at Parcels B and C.

♦ Continue to prepare the draft annual groundwatermonitoring report.

♦ Submit the draft summary report for the treatabilitystudy using sequential anaerobic and aerobicbioremediation at Building 134.

HUNTERS POINT SHIPY HUNTERS POINT SHIPY HUNTERS POINT SHIPY HUNTERS POINT SHIPY HUNTERS POINT SHIPYARDARDARDARDARDMONTHLMONTHLMONTHLMONTHLMONTHLYYYYY PROGRESS REPOR PROGRESS REPOR PROGRESS REPOR PROGRESS REPOR PROGRESS REPORTTTTT

JULY 28, 2005

USS John C. Stenniswww.navybracpmo.org/bracbases/california/hps/default.aspx

Hunters Point Shipyard

South Basin

India Basin

San FranciscoBay

Parcel F Boundary

E

D

C

B

E-2

Non-N

avy

Proper

ty

Non-N

avy

Proper

ty

Parce l F Boundary

Monthly Progress Report - Hunters Point Shipyard June 2005

www.navybracpmo.org/bracbases/california/hps/default.aspx

♦ Submit the draft technical memorandum for theinvestigation of soil gas at Installation Restoration(IR)-07/ IR-18 sites

♦ Continue to prepare the draft technical memoran-dum in support of a Record of Decision amend-ment.

♦ Submit the draft and prepare the final and RTCs forthe quarterly groundwater monitoring report forJanuary to March 2005. Prepare and submit thefinal annual groundwater report with RTCs.

♦ Finish implementing the work plan for the follow-on(Phase III) SVE treatability study, begin preparationof the draft summary report if activities.

1.2 PARCEL CThe activities completed and planned for the upcoming2 months at Parcel C are summarized below.

June 2005 Activities at Parcel C

♦ Prepare RTCs for summary report of water sam-pling at Dry Dock 4.

♦ Continue to prepare the draft report for the treatabil-ity study using sequential anaerobic and aerobicbioremediation at Building 134.

♦ Continue to prepare the draft feasibility study (FS)report for Parcel C.

July to August 2005 Activities at Parcel C

♦ Continue to prepare and submit RTCs for summaryreport of water sampling at Dry Dock 4.

♦ Submit the draft report for the treatability studyusing sequential anaerobic and aerobicbioremediation at Building 134.

♦ Continue to prepare the draft FS report for Parcel C.

1.3 PARCEL DThe activities completed and planned for the upcoming2 months at Parcel D are summarized below.

June 2005 Activities at Parcel D

♦ Continue to prepare the draft final FS report forParcel D.

♦ Continue to prepare the draft report for the Phase Vradiological investigation.

July to August 2005 Activities at Parcel D

♦ Continue to prepare the draft final FS report forParcel D.

♦ Continue to prepare the draft report for the Phase Vradiological investigation

1.4 PARCEL EThe activities completed and planned for the upcoming2 months at Parcel E are summarized below.

June 2005 Activities at Parcel E

♦ Continued to prepare the draft technical memoran-dum for shoreline characterization.

♦ Prepared the final IR-02 NWC removal action workplan with RTCs

♦ Prepared the final metal reef and slag removalaction implementation work plan and RTCs

♦ Continued pre-mobilization at the shoreline removalaction areas

Silt Curtain Installation Complete

Monthly Progress Report - Hunters Point Shipyard June 2005

www.navybracpmo.org/bracbases/california/hps/default.aspx

♦ Began to implement the final work plan for the metalreef and slag removal action

♦ Continued to prepare the draft RI report for ParcelE.

July to August 2005 Activities at Parcel E

♦ Submit the Final IR-02 NWC Removal Action WorkPlan with RTCs

♦ Submit the draft technical memorandum for shore-line characterization.

♦ Submit the final metal reef and slag removal actionimplementation work plan and RTCs

♦ Continue shoreline removal actions.♦ Continue to prepare the draft RI report for Parcel E.

1.5 PARCEL E-2The activities completed and planned for the upcoming2 months at Parcel E-2 are summarized below.

June 2005 Activities at Parcel E-2

♦ Submitted the 2004 to 2005 annual report for thelandfill storm water discharge management plan

♦ Continued monthly gas monitoring at the landfill.♦ Prepared the final work plan and RTCs for the

polychlorinated biphenyl (PCB) removal action,continued to implement the work plan.

♦ Continued to prepare the draft RI/FS report forParcel E-2.

♦ Began the shoreline removal action areas andbegan removal actions at the PCB area.

♦ Continued to prepare the final dust control plan forthe shoreline removal action areas.

♦ Submit the 2004 to 2005 annual report for thelandfill storm water discharge management plan

July to August 2005 Activities at Parcel E-2

♦ Submit the final work plan and RTCs for the PCBremoval action.

♦ Continue monthly gas monitoring at the landfill.♦ Navy/Regulatory Agency Feasibility Study kick off

meeting♦ Continue preparation for the Stanford University

PCB treatability study♦ Continue to prepare the draft RI/FS report for Parcel

E-2.

Silt Curtain Installation at Metal Debris Reef

♦ Record monthly visual observations of storm waterat the landfill during rain (if any).

♦ Continue field activities for the shoreline removalaction areas.

♦ Submitted the final dust control plan for the shore-line removal action areas.

1.6 PARCEL FThe activities completed and planned for the upcoming2 months at Parcel F are summarized below.June 2005 Activities at Parcel F

♦ Continue to prepare the draft FS for Parcel F.

July to August 2005 Activities at Parcel F

♦ Continue to prepare the draft FS for Parcel F.♦ Prepare the work plan for the Stanford University

PCB treatability study

Monthly Progress Report - Hunters Point Shipyard June 2005

www.navybracpmo.org/bracbases/california/hps/default.aspx

2.0 SCHEDULEThis section presents meetings conducted and planned and deliverables submitted and planned during this reportingperiod.