Hse 20management 20plan 131015203748 Phpapp01

  • Upload
    -

  • View
    224

  • Download
    0

Embed Size (px)

Citation preview

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    1/48

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    2/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 2 of 48

    Contents

    1. Purpose 6

    2.

    Health, Safety & Environment Projection Policy

    3. Safety Control Organization and Responsibility

    3.1. Safety Control Organization

    3.2. Responsibility

    4. Safety, Health and Environment Implementation 7

    4.1. Safety, Health and Environment Committee

    4.2. Education and Induction

    4.3. Zero Accident Movement (ZAM)

    4.5. Weekly Safety Assembly

    4.6. Notice of Accident

    5. Health/ First Aid 11

    5.1. Medical Center

    5.2. First Aid Boxes5.3. Record Keeping

    5.4. Physical Qualification of Workers

    6. Emergency Plan 12

    6.1. General

    6.2. Fire procedure

    6.3. Site Evacuation

    6.4. Emergency Communications/alarms

    6.5. First Aid Center Function in emergencies

    6.6. Site Emergency Reporting Procedure

    7. Workplace Environment 14

    7.1. General Requirement

    7.2. Sanitation

    7.3. House Keeping

    7.4. Waste Disposal/ Rubbish Collection & Handling

    7.5. Noise

    7.6. Working Times/ Overtime Working

    8. Personal Protective Apparatus & Safety Equipment 188.1. General

    8.2. Safety Helmet

    8.3. Respiratory Protection

    8.4. Hearing Protection

    8.5. Safety nets

    8.6. Safety Shoes

    8.7. Safety Goggles

    8.8. Safety Belts8.9. Safety Gloves

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    3/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 3 of 48

    8.10. Clothing/ Uniform

    9. Equipment Inspections/ Tagging 23

    9.1. General

    9.2. Crane Inspections and Testing

    9.3. Vehicle Inspections General

    9.4. Tools and Equipment Inspection

    9.5. Site Inspections of Tools and Equipment

    10. Electrical Safety Procedures 24

    10.1. Electrical Distribution

    10.2. Temporary Electrical Wiring

    10.3. Electrical Personnel/ Training/ Emergency

    10.4. Electrical Wire and Apparatus

    11. Fire Prevention and Protections 27

    11.1. Fire Prevention

    11.2. Fire Protection

    12. Traffic Rules and Regulations 29

    12.1. General

    12.2. Vehicle Testing and Permits

    12.3. Vehicle Parking

    12.4. Traffic Rules

    13. Safe Work Practices 32

    13.1. Platforms and Scaffolds

    13.2. Hand Tools and Power Tools

    13.3. Ladders13.4. Floor and Wall Openings

    13.5. Manual Lifting and Carrying

    13.6. Mechanized Equipment

    13.7. Compressed Air and Gases

    13.9. Forklifts

    13.9. Cranes

    13.10. Rigging, Hoisting and Jacking

    13.11. Critical and Heavy Lift

    13.12. Signals, Signal Persons, Signs and Tags

    13.13. Material Handling and Storage

    13.14. Welding and Cutting

    13.15. Steel Erection

    13.16. Chemicals/ Hazardous Materials

    13.17. Painting, Coating and Spraying

    13.18. Grinding Wire and Buffing Wheels

    13.19. Shop Work Machinery and Equipment

    13.20. Temporary Electrical Wiring Works

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    4/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 4 of 48

    13.21. Excavation

    13.22. Demolition

    13.23. Blasting and Explosives (to do at a later date)

    13.24. Hot Work Procedures (to do at a later date)

    14. Safety Control System 49

    14.1. Safety Inspections

    14.2. Accident Analysis

    14.3. Reporting

    14.4. Safety Plan Review

    15. Motivation and Incentive Schemes (to be prepared later) 51

    16. General Rules and Regulations for all personnel

    17. Penalties for safety violations/ failure to comply 52

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    5/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 5 of 48

    SITE HEALTH AND SAFETY PLAN

    The following Contractor's Health and Safety Plan is a preliminary document and may be

    amended from time to time as required.

    The Health and Safety Plan contains the minimum requirements the Contractor to observe in this

    respect whilst carrying out the Construction Works.

    Safety is of primary importance and the Contractor are fully responsible for the health and safety

    of his work force at all times.

    1. PURPOSEThis plan is a guide to promote among all staffs and all workers the importance of safety

    accident prevention. The rate of accident needs to be controlled and kept to a minimum to avoid

    the wastage of manpower and resources, and also to prevent physical and mental anguish for the

    construction period of Long Phu 1 Thermal Power Project.

    In case accident occurs, first-aid facilities and first-aid staffs should be available to minimize the

    loss or damage due to personnel injuries. First-aid staffs should be trained persons with effective

    ability to assume such job.

    2. HEALTH, SAFETY & ENVIRONMENT (HSE) PROTECTION POLICY

    We LILAMA Corporation (LILAMA), are committed to achieving Health, Safety and

    Environment (HSE) excellence. This is a responsibility of management and employees in allfunction. We will strive to provide a safe and healthy working environment and to avoid adverse

    impact and injury to the environment and the communities in which we do business.

    The duties and responsibilities of various personnel are laid down to ensure participation by

    everyone with the safety consciousness in prevention of accidents.

    To systematize the safety procedures of the Company, the following is set forth as fundamental

    Safety Policy. During work execution the contents of this Policy will be modified/amended and

    revised according to site situation and for improvement of safety. The requirements of the

    Contract and relevant Vietnamese local rules and regulations shall be met in each case.

    3. SAFETY CONTROL ORGANIZATION AND RESPONSIBILITY

    3.1. Safety control organization

    (Will be submitted later)

    3.2. Responsibility

    A. Site managers responsibility

    The objective of the Site Manager is to constantly work towards:

    1)

    Maintaining a safe and healthy working environment.

    2) To establish and promote practices and procedures to prevent accident and injuries.

    3)

    To observe all safety regulation allotted out by the company.

    4)

    To establish a safety committee.

    5)

    To upgrade standards and control.

    6) To execute Zero Accident Movement (ZAM)

    B.

    Section chiefs responsibility

    1) To maintain safe working conditions and practices for all employees.

    2)

    To maintain good housekeeping in the section.

    3) To ensure adequate personal protective equipment in accordance with safety rules and

    regulations.

    4)

    To ensure all safety rules and regulations complied with and explained to employees in

    his section and subcontractors under his control.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    6/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 6 of 48

    5) To rectify all unsafe conditions and hazards when required by Safety Manager.

    C. Site engineer/FOREMAN/supervisors responsibility

    1) To enforce all safety rules and regulations.

    2)

    To investigate accidents and near misses with Safety Manager.

    3) To ensure that all persons working under him are trained on safe and proper workingprocedures.

    4) To inspect his working areas, tools and equipment frequently

    5)

    To conduct sections regular safety meetings at work sites

    6) To take stop-work action against any person working unsafely

    7)

    To rectify hazards pointed out by Safety Manager or safety personnel

    8) To maintain good housekeeping in his work areas

    D.

    Safety managers responsibility

    1)

    Formulating, administrating and making necessary changes in this HSE plan.

    2) Submitting directly to the Site Manager regular monthly, weekly or daily reports on thestatus of safety.

    3)

    Acting in advisory capacity on all matters pertaining to safety as required for theguidance of management.

    4) Maintaining the accident record system, making necessary reports, personal

    investigations of fatal or serious accidents, securing Site Engineer/Supervisors accident

    reports and checking corrective actions.

    5) Coordinating safety work with first aid.

    6) Making personal inspections for purpose of discovering and correcting unsafe conditions

    or unsafe work practices before they cause accidents.

    7) Maintaining outside professional contracts to exchange information with others and to

    keep this HSE plan up-to-date.

    8)

    Making certain the laws, ordinances or orders bearing on industrial safety.

    9) Securing necessary help or advice from the minister of labor, insurance companies, andother concerned parties relating to safety or health.

    10)Controlling or supervising fire-fighting activities.

    11)

    Checking whether safety equipment used by plant personnel is acceptable.

    12)Executing Zero Accident Movement

    E. Sub-contractors responsibility (if any).

    1) To ensure that all the respective agents and employees conform to the contents of this

    HSE plan.

    2) To supply employees with appropriate safety equipment and appliances when working.

    3) To attend Contractors safety meetings, when called upon, and to conduct safetymeetings for all his employees.

    4) To rectify unsafe conditions and hazards when required by Contractors Safety Manager

    and/or his staff.

    5) To maintain good house keeping

    6) Report all accidents to the Contractors Safety Manager or his staff immediately.

    7) To seek first aid for all injuries, however slight, at the first aid station

    8)

    To be entirely responsible for the implementation of safety measures and full compliancewith regulations of his company in respect of both himself and all his employees

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    7/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 7 of 48

    9) Should accept this HSE plan and perform the work accordingly. In case a subcontractorwants to apply his own safety plan the plan should be reviewed and approved by the

    Contractors Safety Manager.

    F.

    Employees responsibility

    1) To obey all companys safety regulations to prevent himself and h is colleagues from

    injuries.

    2) To report all unsafe acts and conditions to his supervisor or his foreman immediately.

    3)

    To report all accidents to his supervisor or his foreman immediately.4) To seek advice from his supervisor

    a)

    When an unusual situation develops which may appear wrong to him.

    b) When he does not know how to do a job.

    c) When he does not understand the instruction.

    5)

    To wear all personal protective equipment such as safety helmet, safety shoes and other

    equipment required by the work condition.

    6)

    To maintain good housekeeping in the work area.

    7) Not to create unsafe conditions.

    8)

    To rectify any hazard or unsafe condition found at his area of work.

    4. SAFETY, HEALTH AND ENVIRONMENT IMPLEMENTATION

    4.1. Safety, health and environment committee

    Chairman : Site Manager

    Other Members: Safety Manager, Representatives for workers, Representatives for

    Subcontractors (if any), Representative for Owners. It is required that at least companies

    on the project send workers and supervisors to represent the Subcontractors.

    Frequency : Monthly

    Function : - Establishing a monthly execution plan- Conduct monthly safety audits

    - Review the accident statistics for the month

    - Guidance and confirmation of safety rules/regulations

    - Safety control issues and solutions

    - Make amendments and revisions to this HSE Plan

    The minutes of this committee will be submitted to CLIENT (The general agenda format

    is to be developed later).

    4.2. Education and induction

    A.

    New-comer employee education

    1) Object : General Safety Induction for all Lilama Personnel

    2)

    Time : One day before commencing work on the project site

    3) Duration : From 1 to 3 hours

    4)

    Instructor : Safety Manager and/or Safety Induction Officer

    5) Contents :

    Explanation of safety and health rules, regulations.

    Explanation of works, specific site conditions and penalties

    Samples of correct safety equipment to be on display

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    8/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 8 of 48

    Workers to fill out personal information slips and acknowledge undertaking the

    course.

    6) Identification (Photo ID) Badge for site access will be issued by Clients Safety

    Department after completion of the site specific induction.

    B.

    Specific employee education and certification

    1) Object: To give more detailed induction to certain new site employees, whose jobs areconsidered generally more hazardous, i.e. welders/ riggers/ scaffold erectors/

    electricians/working inside tanks, vessels, steam generators, etc.2)

    Time: Once in quarter of the year.

    3) Instructor : Safety Manager/ Safety Induction Officer/ Contractor Specialty Supervisor

    4)

    Contents :

    Dangerous factor of each work process

    Correct use of facilities, equipment & material

    Use of safety equipment and protection materials

    C. Regular education

    1)

    Object : To reinforce safety issues for all site employees

    2) Time: Daily 10 minutes before work starts during Pre start meeting, especially when a

    major phase of construction work starts.

    3) Instructor : Safety Manager/ Safety Induction Officer/ Section chief

    4)

    Contents :

    Dangerous factor of each work process

    Safety/ health performance and accident prevention.

    Example of accidents & prevention of industrial disaster

    Correct use of facilities, equipment & material

    Improvement of work circumstances & prevention of occupational disease

    Use of safety equipment and protection materials

    Zero accident movement

    Other items about site safety control.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    9/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 9 of 48

    D. PRE-START meeting

    1) Object: Explanation of works for the day and familiarization of dangerous area and

    confirmation of safety before work such as the wearing of safety & protection

    equipment.

    2) Duration : Short time (i.e. 10 minutes) before work start

    3)

    Instructor : Site Engineer/ Supervisor or Sub-contractors Engineer/ Safety Officer

    4) Contents :

    Personal protective clothing

    House keeping

    Fire prevention/Fire fighting

    Safe welding and cutting

    Scaffolding

    Power tools

    Safe electrical installation

    Lighting

    Ladders

    Safe material storage

    Manual lifting

    Working with cranes

    Excavations

    Falls

    Chemicals

    Noise

    Intoxicants/ drugs

    First aid

    Sanitation and Hygiene

    Disposal and Handling of waste

    E. Special safety training

    1) Object : Specific Safety training for Workers to be in service for specific tasks that areconsidered as dangerous work

    2) Period & Time : Before work start (Required time will be decided by Safety Manager

    Subject to work condition)3) Instructor : Safety Manager/ Safety Induction Officer/ Contractor Specialty Supervisor

    (e.g. Rigging supervisor/ Heavy Lift supervisor)

    4) Contents: Work procedure, characteristic of work, potential risk of hazard, safety

    requirement and emergency measures.

    4.3. Zero accident movement (ZAM)

    A. Purpose

    As a part of practical safety program to promote autonomous movement for prevention of hazard

    and to encourage a hazard prevention consciousness for all employees and workers, we wish to

    execute this program so called Zero Accident Movement so that the accident ratios might be

    reduced or zero eventually.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    10/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 10 of 48

    B. Enforcement principle

    1) Notice a start of zero accident movement to all employees and head office safety

    management post

    2)

    Before starting ZAM, construct safety management organization and possess a basic

    standard safe device, and educate safety to all employee and worker

    3)

    Establishing target time for zero accident and note the start dates of ZAM to every

    employees and workers.

    4)

    To execute ZAM systemically and efficiently, each section & subcontractor shallestablish their target time for zero accident, check their execution status, records any

    proposal for ZAM on the daily basic. Safety Officer record their zero accident time in

    total.

    5) After achieving the first target time for ZAM, continue the ZAM to double, triple and

    continuously toward to reach the best record.

    6) When a hazard demand recuperation over 4 days, the achieved time of ZAM so far is

    invalid and new time record shall be resumed

    4.4. WEEKLY TOOLBOX MEETING

    The safety assembly will be held on a weekly basic. All staff from the contractor and sub-

    contractors shall attend:

    The purposes are:

    Convey a safety message

    Safety status and activities for the previous month

    Planned safety activities and other related information for this month

    Demonstrate general safety skills such as use of fire extinguisher

    Award for personnel or sub-contractor who achieved the best safety performance

    during previous month

    4.5. Notice of accidentA. All accidents and dangerous occurrences arising out of and in the course of employment

    must be reported by the supervisor to the Safety Manager, Clients Project Safety

    Department , at the time of its occurrence or at latest before the end of the days work

    B. A formal accident notice form must subsequently be submitted to the Safety Manager within

    twenty-four (24) hours following the accident, for him to conduct the necessary

    investigations. Accident Notification and Witness forms are in the appendix.

    C. An accident with any of the consequences listed below shall be immediately reported to the

    Safety Manager or Safety Officer. These accidents will be investigated in depth to identify

    all causes and to recommend hazard control measures. Except for rescue and emergency

    measures, the accident scene shall not be disturbed until it has been released by SafetyManagers instruction. The consequences requiring an in depth investigation are:

    1) Fatal injury

    2)

    Any accident requiring hospitalization of the victim

    3) Any incident involving electricity/ electric shock

    4)

    Five or more persons admitted to a hospital due to same disease

    5. HEALTH/FIRST-AID

    5.1. On Site Medical center

    An onsite Medical Centre (SOS Clinic) is provided by Client and run on site by SOS

    All persons will report here for help

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    11/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 11 of 48

    5.2. First aid boxes

    1) First aid boxes will be provided at the main office of LILAMA, First-aid center, and

    in several locations within the main construction site, carried by all Subcontractors'

    medical staffs.

    2) Client medical center will have on standby a more substantial first aid kit, including

    stretcher for serious medical emergencies when the medical center staffs are called

    out to attend.

    3)

    Safety Manager will periodically inspect all first aid boxes to ensure that they areproperly equipped.

    5.3. Record keeping

    1) Client medical center staff will keep a record of all persons who receive treatment in

    the medical center. This record will include; Name of person, company, ID No.,

    treatment received, cause of accident/ illness, location of accident, medicines issued,

    further treatment required, ambulance use, hospitalization, and any time off work.

    2)

    All records to be passed to Safety Manager weekly.

    3) Subcontractors first aid/ medical staff(s) will be required to submit a weekly report of

    any accident victims that they treat that do not go to main medical center

    5.4. Physical qualifications of employees

    1) All persons shall be physical qualified for performing the duties to which they are

    assigned. Some factors to be considered in making work assignments are strength,

    endurance, agility, coordination, and visual and hearing acuity.

    2) Employees shall not use or be under the influence of alcohol, narcotics, intoxicants

    or similar mind altering substances while on duty. Employees found to be under the

    influence of/consuming these substances will be immediately removed from working

    site.

    3) Operators of any equipment or vehicle must be able to read and understand the sign,signals, and operating instruction in use.

    4) All persons working with explosives shall be in good physical condition and be able

    to understand and give written and oral orders

    5) All staff and workers are required to inform Safety Department of medicalconditions from which they suffer. This information is to be passed to Safety

    Department during induction. This may include, but is not limited to the following:

    diabetes, color blindness, partial deafness, allergies to medicines, etc.

    6. EMERGENCY PLANS

    6.1. GENERAL

    1) The emergency communication system shall be established and poster at the convenient

    access-ways, in all site offices, in all security towers / gates, medical center, in order forspeedy rescue of the accident victims, timely communication with local fire brigade

    office, prompt response from first aid staff, and the soonest possible evacuation of the

    workforce if necessary in a serious emergency.

    2) In an emergency situation such as safety accident, the first observer shall report it toSafety Officer or any persons in reporting line as soon as possible.

    3) The person who receives the report shall first start rescue activity and report to Safety

    Manager or any person in reporting line.

    4) First finders name and ID No. shall be recorded for future use by Safety Department for

    investigation.

    5)

    Site Facilities are available for use in case of Emergency

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    12/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 12 of 48

    6.2. FIRE PROCEDURE

    The best procedure for any fire, is DO NOT LET IT START, failing that, the best means of

    dealing with any fire is to put it out as soon as possible and stop it from speeding. On seeing any

    fire personnel shall.

    Small fire:

    Inform others in the surrounding area- to call safety/ security officers

    Find the nearest fire extinguishers/ water bucket and attempt to put the fire out, if it is

    safe to do so. And they are competent and confident to do soIf unable to contain/ control the fire inform the nearest safety officer/ security office the call

    the fire brigade.

    Make sure all personnel are clear of the fire area and that no one is trapped.

    Major fire:

    Inform others in the area to leave immediately.

    Inform the nearest supervisor/engineer/ safety officer/ security officer to call fire brigade,

    and sound the alarm.

    Make sure all personnel are clear of the fire area and no one is trapped.

    The first finder/ supervisor shall stay in the vicinity if it is the safe to do so, to directemergency service personnel.

    Report to the designated meeting point and wait until the all clear is given.

    6.3. SITE EVACUATION (as per ClientsProcedures)

    6.4. EMERGENCY COMMUNICATIONS/ ALARMS

    The main types of emergency for emergency communication on the project will be:1.Telephone. 2. Two way radio (walkie-talkie) 3. Alarm Siren. 4. Voice.

    1) An emergency telephone numbers list will be developed and posted at all site offices,all gate posts, first aid station and passed to all Project staff with Mobile phone.

    2)

    A list of all frequencies/ channels in use on the project will be developed and issued toall project staff/ security guards/ first aid staff/ safety officers and all Subcontractors.

    There will be a dedicated frequency for safety staff/ emergencies, which any person

    with a radio can use to inform Safety Department of Safety Problem, emergency

    situations, and accidents. First aid station radio will be permanently set to this

    frequency.

    3) An alarm siren shall be established for sounding alarms for site evacuation, fire alarm,

    explosion/ gas leak, start work/ stop work times.

    4)

    The oldest and most reliable form of emergency communication is voice. Someone sees

    a problem/ accident / emergency - they must personally inform the nearest security

    guard, safety officer, supervisor, Contractor staff member. If there is a languageproblem, take the person and show them the problem.

    6.5. FIRST AID CENTRE FUNCTION IN EMERGENCIES

    The function of the first aid centre in any emergencies is to provide first aid services to any

    person injured; this will include coordinating the operation of the Client ambulance, providing

    first aid treatment in the first instance on the site and Client medical center, and communicating

    with the safety department.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    13/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 13 of 48

    6.6. SITE EMERGENCY REPORT SEQUENCE

    7. WORKPLACE ENVIRONMENT

    7.1. GENERAL REQUIREMENTS

    1) Ventilation shall be provided where possible, to remove dusts and poisonous gas in theareas where such pollutants are produced.

    2) The working environment shall be free from the causes of such symptoms as musclespasms, nausea and skin irritation.

    3)

    The working area shall be maintained clean by Contractor and/or Sub-contractors'

    labourers to prevent disease caused by dirty condition.

    4) Maintaining good housekeeping for the clean work environment.

    5)

    Protecting the workers from noise exceeding specified limit.

    6) Ensuring all necessary warning and advisory signs are placed.

    7.2. SANITATION

    A. WATER

    1) Drinking water for site workers will be available on site and will be sign posted

    WATER FOR DRINKING in both Vietnamese and English

    CONTRACTOR

    Site Manager

    CLIENTs

    Project Manager

    Local authoritySafety ManagerChief Medical Officer

    LONG PHU 1

    Contractor and/ Engineer/ Supervisor/

    Safety officer/ Gate security

    First Aid Officer First Finder

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    14/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 14 of 48

    2) The service water will be provided in working area and Subcontractors office area withsignboard CAUTION-WATER UNFIT FOR DRINKING, WASHING OR

    COOKING in both Vietnamese and English

    B.

    TOILETS

    1) Toilet facilities shall be provided in each construction job site.

    Under temporary field conditions, provisions shall be made to assure not less than one

    toilet facility in available.

    2)

    Toilet shall be so constructed that the occupants shall be protected against weather andfalling objects. All cracks shall be sealed and the door shall be tight-fitting, adequate

    ventilation also shall be provided.

    3) Short term temporary toilets may be of simple construction with a toilet pit, providing,

    some lime and a thin layer of soil is added daily, plus good ventilation is provided.

    4) Long term temporary toilets shall be completely portable, fully enclosed, with removal

    waste bowls. Waste shall be transferred by suitable means to a central septic for

    primary treatment before discharge to drainage channel.

    C. TEMPORARY FACILITIES

    1) Temporary facilities such as offices, workshops, warehouses and Subcontractor

    containers shall be built in the word site with good ventilation, well lighted, andmaintained in a clean, orderly manner. All temporary building shall be a safe distance

    away from any hazards, especially fuel storage areas.

    2) Temporary facilities will be equipped with fire extinguishers, that are fully charge,

    serviceable, and located in prominent position

    3) All temporary offices, stores, camps of any kind must have rubbish/ waste bin with

    cover. Such bins will be emptied at least once a week.

    4) All temporary officers/ containers/ stores/ warehouses must have the company name

    clearly displayed in a prominent position.

    D. FIRST AID1) At the start of major work, arrangements shall be made for medical facilities and nurse

    to be available for prompt attention to the injured and consultation on occupational

    health.

    2) The main first aid center shall be located in the project office. There shall be at least

    one nurse on duty whenever works are being carried out on the project.

    3) The safety manager shall check the contents of the first aid kids periodically when or is

    in process to ensure that expended items are replaced.

    7.3. HOUSE KEEPING

    1) All stairways, passageways, gangways, and access ways shall be kept free of materials,

    supplies, and obstructions at all times. This applies especially to access- ways /

    working platforms on scaffolding.

    2) Loose or light material shall not be stored or left on roofs or floors that are not closed

    in, unless it is securely tied down.

    3) Tools, materials, extension cords, hoses or debris shall not cause tripping or other

    hazard.

    4)

    Tools, materials, and equipment subject to displacement or falling shall be adequately

    secured.

    5)

    Empty bags having contained lime, cement, and other dust - producing material shall beremoved daily. This also applies to other dusty waste, such as insulation off-cuts.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    15/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 15 of 48

    6) Protruding nails in scrap boards, planks, and timbers shall be removed, hammered in, orbent over flush with the wood unless placed in containers or trucks for removal. All

    second-hand timber delivered to site must have nails treated as above. Nails that are

    removed must not be left on the ground; they must be placed in suitable container. Such

    work is responsibilities of all workers of Contractor or Sub-contractors.

    7)

    The scrap and debris shall be cleared from work areas, passageways, and stairs in and

    around buildings, storage yards, warehouses and other structures.

    8) All sharp waste i.e. broken glass, sheet metal off-cuts, must be placed in metal drums.

    Accumulation of such debris on the ground is not permitted.

    9) All storage areas and the construction site shall be kept free from the accumulation ofcombustible materials. Grass shall be kept down. Contractor and/or his sub-contractor

    shall establish a regular patrol for cleanup of the area.

    10) Rubbish, brush, long grass, or other combustible material shall be kept out from areas

    where flammable and combustible liquids are stored, handled, or processed.

    11) Accumulation of flammable and combustible liquids on floors, etc., is prohibited. All

    spills of flammable and combustible liquids shall be cleaned up immediately.

    12) Safety Manager will inspect the work area daily for adequate housekeeping and record

    unsatisfactory finding on the "Site Safety Inspection Record".13) All litter, food scraps, paper, cigarette packets, food packaging, cardboard etc. must be

    placed in rubbish bins. These bins must be provided at every office and container and

    store, and be provided with lid to prevent windblown debris.

    14)

    Vermin (rats, mice, insects) will be controlled primarily by the strict control of eating

    anywhere within the construction site, the use of bins with lids, the frequent removal of

    rubbish to control / eradicate any infestations that occur, using approved sprays /

    poisons etc.

    15) Control of dust from construction activity and traffic will be controlled by the regular

    use of water trucks to spray sufficient water to keep the ground damp if any.

    7.4. WASTE MATERIAL DISPOSAL/RUBBISH COLLECTION& HANDLING

    1) All waste material and rubbish shall be disposed to the designated place (will be

    determined later) by the Main Contractor & / or his Subcontractor.

    2) Waste material will be treated according to CLIENTs requirements.

    3) All vehicles carting waste material from the site to designated place must have coversover the load, and the Subcontractor concerned must immediately clean up any spillage

    of waste material on both site roads and public roads.

    4) For both security and safety purpose, rubbish removal will not be permitted at night.This will discourage the practice of placing valuable goods on the bottom and covering

    with rubbish, to easily pass through security gates.

    5) All scrap lumber, waste material, and rubbish shall be collected and stored in piles or

    containers for removal.

    6) Garbage shall be collected in dustbins placed in several points at site and disposal daily.

    7) All rubbish bins will have lids to prevent litter being blown about by the wind, and tostop vermin getting into the bins.

    8) All rubbish/waste / excess material must be removed from the site by Subcontractor /

    Contractor waste removal Subcontractor by vehicle. There will be no scavenging of

    waste by workers or locals at any place on the project site. Workers are not allowed to

    leave the site carrying any kind of rubbish / waste.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    16/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 16 of 48

    9) Oils, chemicals and other industrial wastes shall be collected at differently appointedplaces and disposed to the designed place in accordance with approved regulations and

    Client Site Environment Policy

    10)

    The dumping of waste oils / toxic chemical in site drainage system is strictly prohibited.

    Any Subcontractor found disposing of waste materials in this way will be required to

    clean the entire area.

    7.5. NOISE

    1)

    In all cases where the noise levels exceed specified limits, a continuing and effectiveprotection program shall be administered.

    2) When the sound pressure level in a working area is too much high, personal earprotection equipment such as earplugs or earmuffs shall be worn.

    3) Noise hazardous areas will be marked with caution signs indicating both the presence of

    hazardous noise levels and the necessity of ear protection device.

    7.6. WORKING TIMES / OVERTIME WORKING

    The following will be the normal working times for the project: comply with the provisions of

    CLIENT.

    In conjunction with these times the following operating procedure will apply:

    1.

    During the times when the workers entry gate is opened, all workers will have to use this

    gate, they will not gain entry through any other gate workers will be required to pass

    through in single file, presenting their ID cards, and being checked for items such as safety

    helmet, safety shoes, company uniform, no food, no alcohol, and carrying no goods or

    equipment.

    2. Any ways are carried out after 5 PM will need to be requested in advance, by submitting an

    Overtime Work request (OTW Request) sheet. This sheet must be submitted before 3 PM on

    the way in which the over time will be worked, and will include the following details:

    Company name, locations and nature of works, number of workers, name of person in charge

    / supervisor, planned duration of work and any requirements for inspections / tests by

    Contractor Staff, Overtime Work Request sheets.

    3. OTW request sheets must be passed to CLIENT to which the work is applicable, who in turn

    will pass a copy of the sheet to safety department.

    4. Copies of approved Overtime Request Sheets will be passed to gate security, and only those

    companies that have requested to work and been approved will be permitted entry.

    5. Note that works at each dark place, at night need sufficient lighting. This includes

    deliveries, concrete works, bar bending, any work activity. Works will not proceed unless

    there is ample light for working safety. For dangerous and critical works at night, an

    inspection must be carried out by Safety department during the day, for assessing the nature

    of hazard, to determine whether overtime request will be granted.

    6.

    Overtime works include any work activity, plus material deliveries to the main site.

    Preparation and workshop activities in the contractor lay down area do not require a request

    for overtime, however all works must be carried out safety , day or night and unsafe work

    practice or conditions will not be tolerated by Safety Department at any time of day, on any

    part of the project.

    8. PERSONAL PROTECTIVE APPARATUS & SAFETY EQUIPMENT

    8.1. GENERAL

    1) Personal protective devices shall be used as a minimum by everyone whenever on site.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    17/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 17 of 48

    2) Personal working on electrical distribution systems shall be provided with lineman'sbelts, insulating gloves, insulating hoods, insulating blankets, insulating line hose, and

    hot line tools as necessary, which shall be tested and maintained in safe condition.

    3)

    Electric welding, gas welding, cutting blazing pressure and fusion welding, and

    operations shall require goggles, face masks, shields, or helmet, suitable to the type of

    work.

    4) Persons handling rough, sharp-edged, abrasive materials or where the work subjects the

    hands to lacerations, punctures, burns, or bruises shall use gloves.

    8.2. SAFETY HELMET

    1) Each person on site shall wear approved safety helmets when on the project site.Exclusions to this are within offices and fully enclosed vehicles/ equipment.

    2) Hard hat usage will include the entire construction site, basically anywhere that work is

    being carried out, supervised, or inspected- helmets must be worn. There are no

    exceptions made for visitors/ operators outside their cabins, office staff, and senior

    management.

    3) Holes must not be made in safety hats as these lessen the ability to withstand impact.

    4) Safety hats should not be painted as solvents in some paints could cause them to

    become brittle.5) All helmets must have the company name and/ or logo that the wearer works for to be

    marked clearly visible on the helmet. Loose fittings / broken / substandard helmets will

    be confiscated and the worker will not be permitted on the site.

    8.3. RESPIRATORY PROTECTION

    Before any work commences that requires respiratory protection, a confined space inspection

    must be requested and carried out by CONTRACTOR Safety Department in conjunction with

    Client Safety Department. Simply wearing respiratory equipment is not sufficient to protect

    against many on the dangers associated with working with gases and vapors.

    1) When respiratory protective equipment is required, only the specified equipment shall

    be use, wore correctly, maintained properly and stored in the correct manner.

    2) Only approved respiratory protective devices shall be provided and used to protect

    against exposure to hazardous atmospheres containing dusts, fibers, fumes, mists, gases,

    vapors, other contaminants, atmospheres deficient in oxygen, or otherwise considered

    immediately dangerous to life or health.

    3) Respiratory devices using compressed oxygen, liquid air, liquid oxygen, or mixed gases

    are prohibited unless approved prior to use.

    4) When sufficient ventilation cannot be obtained without blocking access, such as listedbelow, shall be performed with general mechanical ventilation, air-line respiratory or

    local exhaust ventilation sufficient to reduce welding fumes and smoke to safe limits.

    Local exhaust ventilation will consist of movable hoods placed near the work to remove

    smoke and fumes at the source.

    a)

    Zinc-bearing of filler metals coated with zinc-bearing materials (galvanized)

    b) Cadmium bearing metals of metals coated with cadmium-bearing materials.

    c)

    Chromium bearing metals or metals coated with Chromium-bearing materials.

    d) Metals coated with mercury-bearing materials. etc

    8.4. HEARING PROTECTION

    Workers in area's with generally high noise levels, working with power tools that produce

    excessive noise, working with loud equipment should wear hearing protection. Hearing

    protection can be in the form of earmuffs (cover the ear), or ear plugs (inserted into the ear

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    18/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 18 of 48

    cavity). Some examples of operations that require hearing protection are: Pile driving operations,

    use of jack hammers, continual use of power saws, angle grinders and concrete hammer drills.

    8.5. SAFETY NETS

    1)

    Workers in unguarded work places over water, machinery, dangerous operation or

    where 7m above the surface shall be protected by safety nets. Nets shall be installed as

    close under the work surfaces as practical but in no case more than 1.8m below such

    work surface. Nets shall be hung with sufficient clearance to prevent contact with the

    surfaces or structures below.

    2)

    It must be emphasized that safety nets are to be used in conjunction with

    handrails/barricades. They are not the primary means of preventing workers and or

    objects from falling. Kick-boards on scaffolding, safety harnesses, guard-rails etc., are

    primary means of preventing falling items.

    3) Nets shall be inspected daily for cuts and damage from abrasions, chemicals, or heat.

    Repairs shall be made before work above work the nets is resumed.

    4) Debris shall be removed from safety nets at least daily and combustible materials shall

    be removed above the net.

    5) To prevent small objects from passing though the safety nets, if they are used as

    overhead protection, fine woven mesh may be added on top of the rope or steel net.6) For overhead protection where objects can fall from more than 5m, or any hot-works

    are carried out above, safety net must consist of steel mesh with plywood and metal

    sheeting. The thickness of both will depend on the height from which objects can fall,

    the type of objects expected, and the type of area/access covered.

    8.6. SAFETY SHOES

    1) To prevent injuries to the feet caused by protruding or falling objects, all employees

    working on Long Phu 1 project sites shall wear fully enclosed steel capped safety

    footwear. All such footwear must be of a suitable sturdy material to offer protection to

    the feet and to be worn correctly so that whole foot is encased and protected. ( The foot

    must fit snuggly into the appropriate footwear so that whole foot area iscovered/protected)

    2) All sub-contract employees shall wear safety shoes with steel-cap or other acceptablesafety footwear (steel capped Gum Boots/wellingtons etc) as approved by the Client

    safety Department.

    3) *The wearing of slippers is generally prohibited anywhere on the project site.

    Under no circumstances is any or work or activity to be performed in bare feet.

    4) *Personnel involved with rigging, handling heavy materials, operating jack-hammers(heavy air/hydraulic tools), the erection of steel structures etc, must wear properly fitted

    and appropriate steel capped safety footwear.

    5)

    There are generally no exceptions for everyone on site to be wearing nonapproved/appropriate safety footy wear. Vehicle operators / security guards / office

    cleaners etc, must all wear project approved footwear /shoes. *Slippers/sandals etc of

    any nature will as a rule be forbidden to be worn on the site.

    6)

    There may be controlled exceptions e.g. When working in vessels / places that require

    strict cleanliness/minimizing contaminates, in which case it would necessary to remove

    dirty safety footwear and substitute with clean slippers or similar, another identified

    area is within the confines of the site administration /management complex.

    *Unless a risk assessment indicates otherwise or exemption is granted from Long

    Phu 1 projects management.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    19/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 19 of 48

    8.7. SAFETY GOGGLES/GLASSES

    1) To prevent eye injuries whilst working on Long Phu 1 sites, all employees engaged in

    cutting, grinding, using of power tools, chipping, doing oxyacetylene cutting, etc. shall

    wear safety glasses along with a correctly fitted full face shield in effect givingDouble

    Eye Protection as per ClientsPolicies and procedures.

    2)

    Contractor shall provide safety goggles/glasses to all employees who are employed on

    the Long Phu 1 project site as per Clients PPE standard eye protection, under the

    following conditions:a) All issued safety goggles/glasses must be maintained in good condition.

    b) Lenses which have become pitted or scratched are blurred or damaged as a

    result or normal use shall be replaced.

    8.8. SAFETY HARNESS (Full body type)

    1) Safety harness fitted with double lanyards (100% constant hook up) must be worn and

    used in the manner that at all times (1)one lanyard is constantly attached to an

    independently anchored line or other secure anchor point/rail when;

    - Working from scaffolds, platforms or other surfaces/structures which do not provide

    sufficient protection against a fall from height of 1.8m or greater.

    -

    Working on any roof with a slope greater than one in four, or on any sloping roof

    that is wet.

    - Working within 2m of any unprotected edge where a fall to another level that is

    greater than 1.8mtr exists. e.g., roofs, excavations, platforms/walkways, tops on

    vessels /tanks, structures etc)

    - Being lifted or working from a basket suspended from a crane. Lanyard to be

    attached to an independent connection of crane wire rope

    - When working in any elevated work platform basket.

    2)

    Safety harness should be visually inspected for defects prior to each use and return to

    work supervisor if found defective3) Hardware for linemans body belts, safety traps, and lanyards shall be drop forged or

    pressed steel and have a corrosive resistive finish and surface shall be smooth and free

    of sharp edges.

    4) All safety harness/ ropes/shackles etc. must be checked and approved by Safety

    Department as passed fit for purpose before going into service and then all ongoing

    checks before each use are too made by the suitably competent user or supervisor.

    8.9. SAFETY GLOVES

    1)

    Gloves can prevent many injuries when handling rough materials or substances which

    can cause skin irritation. A general guideline for the type of glove to use when handling

    various materials are:

    - Cloth gloves are suitable for protection against dirt, silvers, chafing and abrasion

    these are satisfactory for light handling job and should not be used for handling

    rough, sharp or heavy materials.

    - Rubber, neoprene and vinyl gloves protects against acid, oils, solvents and causticmaterials. These should be washed, inside and outside after use and inspected for

    leaks regularly.

    -

    Leather gloves are generally used for heavy-duty works, as they are able to resist

    sparks, moderated heat, chips and rough objects. Welder use chrome-tanned leather

    or horsehide gloves.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    20/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 20 of 48

    - Heat resistant and thermal gloves should be used when there is the possibility ofreceiving burns from hot and very cold sources.

    2) Gloves contaminated with oil, grease or chemical should not be used.

    3)

    Gauntlet type must not be used when working with moving or rotating machinery and

    equipment which could cause the gloves to become caught and result in hand injuries.

    8.10. CLOTHING-UNIFORM (High- Visibility)

    Clothing is an important part of personal safety equipment for several reasons. All workers on

    the project must be supplied with and wear their company uniform with high visibility for entryto the site.

    - Workers should have the most suitable clothing for the weather conditions and the

    works to be carried out. This includes wet weather clothing and clothing with allows

    the workers to conduct their particular work effectively.

    - Workers who have suitable/comfortable clothing are less likely to have accidents and

    will be able to work more productively.

    -

    It enables contractor to control access to their work areas to their workers only. This

    is a benefit for safety control and for security purposes.

    9. EQUIPMENT INSPECTIONS/ TAGGING

    9.1. GENERAL

    To the ensure no accidents are caused by poor quality/ faulty equipment, all: vehicles, majorequipment, electrical tools, gas tools, air tools, electrical distribution equipment, hydraulic tools,

    hoists, explosive tools and scaffolding/ ladders will be inspected prior to going into service on

    the project site. Hand tools will not be inspected prior to use, however, the same conditions

    apply, that is, the tool must be in good condition, and appropriate for the work to be carried out.

    Hand tools in poor condition, are to be Tagged out of service and removed from the job site by

    safety department during site inspections or as identified by the supervisor or workers.

    9.2. CRANE INSPECTIONS AND TESTING

    All cranes operating on the Long Phu 1 project site must be in good condition. To ensure that allcranes operating on the project are satisfactory and meet the Long Phu 1 projects site standards

    the safety department will carry out these inspections on all cranes along with Client Safety

    Department prior to being approved for use

    The following items will be inspected and must be immediately repaired or replaced if found to

    be defective or sub-standard if the crane is to remain on site. Unless cranes are inspected and

    passed, they will not be permitted to work on the project. Crane Inspection sheetshould contain

    the followings:

    1) Engine condition.

    2) Hoist condition

    3)

    Boom condition- any defective part to be repaired an re-inspected. This includes bent,broken, missing, and previously poorly repaired members.

    4) Hook condition - swivel hook, wire sleeve, bearings.

    a. main hook and safety latch

    b. aux. hook and safety latch

    5) Out rigger condition - hydraulic ram condition, footing pad condition.

    6) Safety switch:

    a. Over hoist limit switch at boom top should activate when the hook

    touches the anti tool block

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    21/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 21 of 48

    b. Reverse alarm switch - audible noise when crane reversing

    c. Horn and flashing light, during operation

    7) Lifting capacity table should be installed in operators cabin

    8)

    Load indicator in operator box.

    9) Boom angle indicator to be installed on side of boom base

    Following items will be inspected for condition of rigging tackle.

    10) For handling of steel structure, sling belts are required to prevent slippage of structure

    pieces.

    11) For lifting of long, heavy or items with specific lifting points - 2 or more wire or sling

    belts shall be used.

    12)

    For sling belt, specific type of shackle for use with sling must be used.

    13) All chain, wire rope, nylon slings to be used must be in good condition, and beaccompanied by recent test certificate.

    14) All rigging will be inspected every month and register documents will be kept by safety

    department.

    9.3. VEHICLE INSPECTION GENERAL

    Refer to section on Vehicle testing in section 12.2 and must be approved by Client Safety

    Department.

    9.4. TOOLS AND EQUIPMENT INSPECTIONS

    All tools (electric, explosive, hydraulic, pneumatic, gas) and equipment, especially for electrical

    distribution, welding, oxyacetylene cutting, jacking, hoisting, will be inspected by safety

    department before being allowed to be used on site.

    9.5. SITE INSPECTION OF TOOLS AND EQUIPMENT

    During the daily and weekly safety inspections on site by the safety Department, specialattention will be given to: the checking of equipment status, the observation of correct use,

    (including use of safety gear), the condition of hand tools, and to the condition and use of non-

    mechanical equipment such as ladders and scaffolding. Any equipment in poor condition will be

    removed by safety Department or the supervisor. Larger equipment that cannot be easily

    removed will be shut down if is found to be in poor condition, for example material and

    personnel hoists, cutting machines.

    10. ELECTRICAL SAFETY PROCEDURES

    10.1. ELECTRICAL DISTRIBUTION

    1. System generally.

    The system of electrical distribution and control on the project will have the following main

    component:

    Transformers.

    Main Distribution Boards:

    All electrical supply from the transformers will be through CLIENT.

    Other Temporary Distribution:

    Contractors electric box, switchboards, tools, welding machines, cables and other

    temporary distribution connected through an ELCB: All to be inspected by safety

    department prior to use on site, with periodic re-inspection.

    2. Access Controls

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    22/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 22 of 48

    A) TransformersOnly authorized Contractor electrical section personnel to access transformers. This

    applies equally to the generators and transfer switches.

    B) CONTRACTOR distribution Boards:

    All CONTRACTOR DBs to be lockable steel cabinet. Keys to be held only by electrical

    section and safety department. Works to be carried out on the DB, only CONTRACTOR

    authorized electrical staff.

    All field Distribution Boards supplying socket outlets shall be fitted with appropriatelysize 30A RCD/ELCBprotection devices

    All Field Distribution Boards shall be weatherproof.

    All Field Distribution Board shall be mounted on a stand

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    23/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 23 of 48

    3. Connection Control

    A) Connection of CONTRACTOR DBs to LDPConnection prepared by CONTRACTOR electrical section, this include the cable, DBs,

    cable termination etc. Before connection, it is requires that inspection by authorized

    person from electrical section, sign off sheet, and power on.

    B) Connection of equipment /Tools/ Temporary distribution to DBs.

    All connection, temporary, testing and checking to be done by approved contractor

    electrician. All temporary wiring system must be approved prior to power on.

    4. Record/logs.

    CONTRACTOR electrical section to maintain and update daily, the list of all

    connections.

    All CONTRACTOR DB's to have numbering system for ease of record keeping and

    repair/ maintenance.

    All incoming cables to CONTRACTOR DB's must be identified as to which companys

    DB/ equipment is connected.

    Log to be maintained for all connections, disconnections and requests to power on. If

    there are frequent requests to re-close the circuit to a particular DB, or a fault is detected

    on contractor DB, that DB will be disconnected, and will require connection procedure

    again after repair.

    Detailed survey and plans must be made and kept of all buried cable.

    5. Electrical wire and apparatus

    A. General

    1) Live parts of wiring or equipment shall be guarded to protect all persons or objects from

    harm

    2) Transformer banks or high voltage equipment shall be protected from unauthorizedaccess. Entrances not under constant observation shall be kept locked. Sign warning of

    high voltage and prohibiting unauthorized entrance shall be posted at entrances.Metallic enclosures shall be grounded.

    3) Gates or doors to enclosures for electrical equipment shall swing outward or provideclearance from installed equipment

    4) Electric wire or flexible cord passing through work areas shall be protected from

    damage by foot traffic, vehicles, sharp corners, projections, pinching and any contact

    with acids, corrosives or other liquids.

    5) Insulation mats or platforms of substantial construction shall be so placed on floors andon the frames of equipment having exposed live parts so that an operator or persons in

    the vicinity cannot touch such any such part.

    6)

    All circuits shall be protected against overload.

    7) When fuses are installed or removed with one or both terminals energized, special tools

    insulated for the voltage shall be used.

    8) Patched, oil soaked, worn or frayed electric cords cables shall not be used.

    9)

    Disconnecting boxes shall be securely fastened to the surface and fitted with covers.

    10) Plugs and receptacles shall be kept out of water unless of an approved submersible

    type.

    B. Disconnect and over current protection.

    1)

    Switches shall be of the enclosed safety type, within enclosures grounded, and installed

    so as to minimize the danger of accidental operation.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    24/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 24 of 48

    2) Fuses and circuit breakers shall be of the proper rating for the circuit protected.

    3) Switches, circuit breakers, fuse panels, and motor controllers in wet locations or outside

    shall be in a weatherproof enclosure or cabinet.

    4)

    Over current protection devices must be readily accessible, clearly labeled, not exposed

    to physical damage and not placed in the vicinity of easily ignitable materials.

    C. Temporary wir ing

    1) Temporary wiring shall be guarded, buried, or isolated by elevation to prevent

    accidental contact by workers or equipment2) Wires with non-rated weatherproof insulation shall not be enclosed in metal raceways

    nor used for wiring in tanks, penstocks and tunnels.

    3) Wires shall be insulated from their supports.

    4) Exposed empty light sockets and broken bulbs shall not be permitted.

    5)

    Nonmetallic sheathed cable may not be used where precluded by the NEC (National

    Electric Code)

    a. As portable extension cords.

    b. Laying on the ground subject to any type of traffic or potential damages

    c. Where subject to frequent flexing.

    d. As service entrance cable

    D. Overhead l ine

    1) Overhead transmission and distribution lines shall be carried on towers and poles that

    provide at clearances over roadways and structures.

    2) Clearances shall be adequate for the movement of vehicles and for the operation of

    construction equipment

    3) Floating plant and associated equipment shall not be sited or placed within 6m of

    construction equipment

    4)

    Operations adjacent to overhead lines shall not be initiated until coordinated with theutility officials.

    5) SIGNS/ MARKERS.

    All warning signs, danger signs, advisory signs, instruction signs, and the like to beprominently displayed, of reasonable size to allow readability from 5m, have the primary

    signage in Vietnamese, and secondary in English. All signs must be have Vietnamese.

    Transformer enclosure to have No Unauthorized Access signs, Danger- HIGH

    VOLTAGE signs. Transformer to have clearly displayed Danger- HIGH VOLTAGE

    signs and Danger - Electricity

    All DBs (CONTRACTOR and Sub-contractor) to have Danger - Electricity signs andDanger- 400 Volts (or similar) on the doors.

    All electrical section mains cable/ DB connection cable in building must be enclosed in

    conduit, duct and any other approved means.

    All buried cable must be identified and below surface with tape on the surface with

    marker posts at a maximum Spacing of 30m and at all junctions and transition points. A

    monthly inspection to be carried out by electrical section to ensure that any missing pegs

    are replaced.

    6. Electrical equipment inspection.

    Prior to any electrical section equipment being used on the site, it will be inspected by

    safety department, and Client safety department. Equipment will be checked for: general

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    25/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 25 of 48

    condition, cable and wiring, connections, casing, switches, grounding resistance,

    suitability for work intended, markings and/or warnings, guards and covers, plugs, etc. If

    equipment is satisfactory, it will be allowed into the construction site for use. Equipment

    which fails in the inspection must be repaired or replaced before re-inspection.

    10.2. TEMPORARY ELECTRICAL WIRING

    Generator notes

    Live parts of wiring or equipment must be guarded to protect all persons or objects fromaccidental contact.

    Electric wire and cable passing through work areas shall be protected from damage by foot

    traffic, vehicles, sharp corners, projections, pinching and crossing/ acids

    All electric cord must be doubly insulated. No single of an approved submersible type.

    Switches, circuit breakers, fuse panels, motor controllers, and the like, in wet conditions or

    outside shall be in weatherproof cabinets/boxes.

    Temporary lighting shall be equipped with guards to prevent accidental contact with the

    bulb, except when the bulb is deeply recessed within a reflector.

    All connections /splicing/ cable junctions must be made via mechanical means. Twisting wires together and tapping up it strictly prohibited.

    All neutral bars must be inside electric box.

    All electric box to have lockable cover, with approved electrical staff in control of the keys.

    All generators will be connected from the generator earth to the structure being worked on or

    to the main plant earth grid

    Where small generators are being used with extensions leads being plugged in directly to the

    generator these must be fitted with an appropriately sized 30mA RCD/ELCB protection

    device.

    All generators shall be fitted with an effective silencer.

    All generators shall be free of fluid and oil leaks

    CABLE AND WIRE DETAIL.

    1.

    Mains:

    All damage of cable must be cleared before buried.

    Cable markers at max, spacing of 30m, plus junctions and transition points.

    2. Temporary Cables/ Wire:

    Must be well insulated from scaffolding / handrails/ structural steel Must not be lying in water, unless approved marine cable and all connections/ sockets etc.,

    approved submersible type.

    No electric cable/ wire to be run across vehicle access way. This includes, motorbikes,forklifts, cars, material trolleys, any kind of wheeled vehicles cannot drive over electric cable

    or wire.

    3.

    Road Crossings.

    Buried minimum 0.5m for mains.

    Buried 100-200mm for temporary lines in (steel or PVC pipe)

    4.

    Minimum Cable and Wire requirements:

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    26/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 26 of 48

    Minimum requirement for wire is that it be double insulated wire. No single insulated wire,

    or single wire strands taped together are permitted on the project.

    All cable for connection of welding machines direct to CONTRACTOR DB's must be

    proposed prior to connection.

    All extension leads will be of a heavy duty double insulated flexible cable with a minimum

    size of 1.5mm2

    All extensions leads will be fitted with heavy duty weatherproof plugs with I.P.56 rating.

    No extension leads will be longer than 30 m in length.

    All extension leads and plugs will include an earth core.

    All extension leads shall be kept clear of the ground and run in such a way as to not impede

    workers access.

    Layout of CONTRACTOR Distribution Board:

    To be done later

    10.3. ELECTRICAL PERSONNEL

    All electrical personnel working on the project site must submit for record: their

    qualification/certificate/training courses undertaken etc, to the safety department. Only

    approved electricians from CONTRACTOR will be permitted to undertaken any form of

    electrical wiring, connection, testing. Electrical staff will be identified on their ID cards and

    on safety helmets, by means of approval stickers.

    10.4. ELECTRIC EQUIPMENT.

    1)

    Switching equipment for shutting down the welding machine shall be provided on or

    near the welding machine.

    2) The non- current carrying metal parts of electrically powered welding machines shall be

    grounded. Grounding circuits, other than by means of the structure, shall be checked to

    ensure that the circuit between the ground and the equipment to ground has resistance

    low enough to permit sufficient current to flow to cause the over-current device to

    interrupt the circuit. The rounding to rotating equipment such as pumps, turbines shallbe prohibited.

    3) Neither terminal of the welding generator shall be bonded to the frame of the welder

    when the leads unattended.

    4) Cable with splices or repaired insulation within 3m of the holder.

    5)

    Welding supply cables shall not be place near power supply cables or other high-

    tension.

    6) Welding leads shall not be permitted to contact metal parts supporting suspended

    scaffolds.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    27/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 27 of 48

    11. FIRE PREVENTION AND PROTECTION

    11.1. FIRE PREVENTION

    A. General restrictions

    1) A survey of the suitable and effectiveness of fire prevention and protectionmeasures and facilities existing at each project or installation shall be made by

    the Safety manager at least monthly. Records of the survey findings and

    recommendations shall be retained on file at the project.

    2)

    No Fires are permitted anywhere on the project site. This includes the burning of

    rubbish, fires for warmth, fires for heating PVC pipes for joining, fires for

    heating bitumen and other similar products, etc.

    3) Smoking is completely prohibited within the project offices and buildings

    including warehouses. Smoking is permitted within designated areas of

    contractor offices.

    4)

    Smoking shall be prohibited in all area where flammable, combustible, or

    similar hazardous materials are stored.

    5) All sources of ignition shall be prohibited within 15m of operations whichconstitute a fire hazard. The area shall be conspicuously posted: NO SMOKING

    or OPEN FLAME.

    B. Spacing emergency access

    1) Emergency lanes to provide access to all areas shall be established and maintained free

    of obstruction.

    2) At least 3m clearance from buildings or structures shall be maintained for piles of

    lumber and other combustible materials to be used in the construction.

    3) Material shall be piled to minimize the spread of fire internally and to permit access for

    firefighting or other emergency vehicles

    4) Clearance shall be maintained around lights and heating units to prevent ignition of

    combustible materials.

    C. Flammable and combustible liquids

    1) All sources of ignition shall be prohibited in areas where flammable liquids are stored,handled, and processed. Suitable NO SMOKING OR OPEN FLAME signs shall be

    posted in all such areas.

    2) Flammable or combustible liquids shall not be stored in areas used for exits, stairways,

    or areas designated as a safe passageway of people.

    3)

    All buildings, rooms, and compartments where flammable liquids are stored, processed

    or used shall be well ventilated by a gravity or mechanical exhausting system.

    4)

    Drums, barrels, and other flammable liquid containers shall be tightly capped. Safetycans or other portable service containers of flammable liquids shall be painted with

    name of the contents.

    5) Smoking or open flames within 15m where flammable materials are being used or

    transferred or where equipment is being fueled is prohibited.

    6) Workers shall be required to guard carefully against any part of their clothing becoming

    contaminated with flammable or combustible fluids. Gloves and clothing contaminated

    with fuels/ combustible fluids shall not be worn and must be taken off the construction

    site.

    11.2. FIRE PROTECTION

    A. Fire protection

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    28/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 28 of 48

    1) Fire extinguishers shall be suitably placed, distinctly marked, readily accessible, andmaintained in a fully charged and operable condition

    2) Fire barrels and buckets shall be painted red, marked For Fire Only". Barrels shall bekept filled at all times.

    3) Fire extinguisher equipment shall be provided in each storage area according to the fire

    hazard present.

    4) Every office, warehouse area, storage container must have a minimum of one

    operational fire extinguisher.B. Fire fighting organizations, training and drilling.

    1) Fire fighting organizations shall be provided to assure adequate protection to life and

    property.

    2) Demonstrations and training in fire fighting shall be conducted at intervals to ensure

    that project personnel are familiar with and are capable of operation of firefighting

    equipment.

    3)

    Emergency telephone numbers and reporting instructions shall be conspicuously

    posted, at every gate post and guard station, at the site offices, and at major building

    entry points.

    12. TRAFFICE RULES AND REGULATIONS12.1. GeneralThe aim of this section is to provide a framework for traffic operations on and around the project

    to ensure there are no accidents involving vehicles &/or personnel. All traffic accidents are

    preventable, so particular attention will be paid to condition of vehicles and enforcement of rules

    and regulations.

    12.2. Vehicle testing and permits

    All vehicles on the project site must be approved by Long Phu 1 Project and be road -worthy.

    All vehicles will be tested before being allowed to work on site. Test will include brakes,

    exhaust system, indicator lamps, lights, horns and reversing signals. Vehicles that do not comply

    will not be granted access to the site. It is to be noted that farming vehicles from the surroundingarea are not suitable for working on the project or making deliveries to the site.

    All vehicles in use shall be checked at the beginning of each shift to assure that all parts,

    equipment, and accessories that affect safe operation are in proper operation condition and free

    from defects. All defects shall be corrected before the vehicle is placed in service.

    12.3. Vehicle parkingAll workers bikes and motorbikes are to be parked in the designated area (see site layout plan)

    All project vehicles that are permitted to enter the construction site will be required to make use

    of designated parking area as they are established, and to ensure no access is blocked.

    12.4. Traffic rules

    1) Speed limit for all vehicles on the project will as sign posted across the project

    2) All construction traffic must give way when entering the public roads.

    3) All heavy vehicles are required to have flashing yellow light when operating/moving.

    4) All trucks carrying earth/debris/ rubbish on the public roads must have a cover over theload when traveling

    5) Spillage of material of the public roads must be immediately cleaned up.

    6)

    Companies involved in cartage of excavated material to and from dump locations must

    provide water trucks for dust control, and wash down of public roads

    7)

    All drivers/operators must comply with all traffic signs and directions as they moveabout the site.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    29/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 29 of 48

    8) At night all excavations must have flashing yellow lights around the perimeter, at amaximum spacing of 10m.

    9) Vehicles with cabin for one operator are to only have one person in the cabin.

    10)

    Riding on vehicles is prohibited unless the vehicle designed for transporting people,

    i.e. no riding in the back of tracks, standing on the foot plate of forklift, etc.) No seat no

    ride, seat belts where fitted must be worn

    11) Pedestrian traffic has right of way over all vehicular traffic.

    12)

    Vehicles without lights will not be permitted to operate at night. No exceptions13) Farm vehicles are not allowed on site

    14)

    All vehicle operators are required to wear shoes and to have a safety helmet with them.

    Operators outside their vehicles must wear safety helmets.

    15) All vehicles should be switched off whilst being refueled and strictly no smoking isallowed within 15m of that vehicle.

    16) Traffic signs apply to all vehicles: including cranes, concrete trucks, motorbikes,

    company cars, forklifts, bikes, delivery trucks, and excavators.

    17) All heavy equipment, large cranes, piling, heavy earthmoving equipment etc, must only

    travel around the site when accompanied by a signal man on foot to keep the area

    around the equipment clear and prevent collisions or escorted by an approved vehicle

    escort.

    13. SAFE WORK PRACTICES

    13.1 Platforms and Scaffolds

    A. General;

    SCAFF TAG SYSTEM WILL BE USED.

    1) Scaffold platforms shall be kept free of grease, mud or any other material or

    material/equipment which will render them unsafe or hazardous to persons using them.

    2) Where walkways and work surfaces are slippery, abrasive material shall be used to

    assure safe footing.

    3) The width of all scaffolds, runway, and platforms shall be determined by the purpose,

    but in no case they shall be less than 45cm

    4) Employees on the ramps, scaffolds, roofs, floors, or other working surfaces from which

    they may fall 1.8m or more or working over water, machinery or dangerous operations

    shall be protected by guardrails with intermediate rail or catch platforms or temporary

    floors or safety nets or safety belts.

    5) All planking or platforms shall butt together (not overlap on top of each other creating atrip hazard) and be supported below each side of abutment with scaffold tube be

    overlapped (minimum 20cm)and secured from movement.

    6)

    Scaffolding will be inspected weekly by competent person and signed off on reverse of

    Scafftag as fit for purpose; safety department will also constantly monitor these

    structures.

    B. Standard guardrail

    1)

    A standard railing shall consist of top rail, intermediate rail, and posts, and shall have a

    vertical height of approximately above 0.9m from upper surface of top rail to floor,

    platform, runway, or ramp level. The top rail shall be smooth-surfaced throughout the

    length of the railing.

    2) Posts and top and intermediate railings for pipe railings shall be at least 1 & 1/2 inches

    nominal diameter with posts spaced not more than 2.4m on center.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    30/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 30 of 48

    3) Other types, and arrangements of railing construction are acceptable provided they meetthe following conditions:

    4) A smooth- surfaced top rail at the height above floor, platform, runway, or ramp levelof approximately 0.9m

    5) Strength to withstand at least 200 pounds top rail pressure with a minimum deflection.

    6)

    Protection between top rail and floor, platform, runway, ramp, or stair treads, equivalent

    at least to that of that afforded by standard intermediate rail.

    7)

    Elimination of overhang or rail ends unless such overhang does not constitute a hazard.C. Material scaffolds and tower.

    1) All such equipment shall be erected in accordance with manufacturers specifications

    and the load limits as recommended by the manufacture shall not be exceeded.

    2) Extreme caution shall be taken where metal scaffolds are used in the vicinity ofenergized electrical circuits.

    3) All metal scaffolds shall be plumb and level.

    4)

    The sections of metal shall be securely connected.

    5) All braces shall be securely fastened.

    6)

    Planking shall be created at both ends to prevent movement.7) Work platforms shall be securely fastened to the scaffolds.

    8) All wheels and casters on rollers shall have a positive locking device, securely fastened

    to prevent accidental movement

    9) The force necessary to move mobile scaffolds shall be applied as close to the base aspractical and provision shall be made to stabilize the tower during movement from

    location to another.

    10)

    Freestanding mobile scaffolds working platform heights shall not exceed three times

    the smallest base dimension.

    11)

    No person shall be allowed to ride on manually propelled scaffolds.

    12) Where ramps are used a minimum width of 1.2m for personnel and 3.6m for equipment

    shall be provided. Guardrails shall be provided on all personnel ramps.

    13.2 Hand tools and power tools

    A. General.

    1) Tools having defects that will impair their strength or render them unsafe shall be

    removed from service

    2) When work is being performed overhead, tools not in use shall be secured or placed in

    holders.

    3) Throwing tools or materials from one location to another, form one person to another,

    or dropping them to lower levels, shall not be permitted.

    4) Only non-sparking tools shall be used in locations where sources of ignition may a fire

    or explosion.

    5) Power tools shall be inspected, tested and determined to be in safe operation condition

    prior to use.

    6) Loose and frayed clothing, loose long hair, dangling jewelry, shall not be worn while

    working with any power tool or machine.

    B. Power saw.

    1)

    Circular saws shall be equipped with guards that automatically and completely enclose

    the cutting edges, splitters, and anti-kickback devices.2)

    Cracked, bent, or damaged blades shall be destroyed.

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    31/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 31 of 48

    3) Power saws shall not be left running unattended.

    4) Each hand-fed crosscut table saw shall have a spreader to prevent the material from

    squeezing the saw or being thrown back on the operator.

    C. Wood working machinery

    1) A brush shall be provided for the removal for sawdust, chips, and shavings on all wood

    working machinery

    2) Blades of planers and jointers shall be fully guarded and cylindrical heads with throats

    in the cylinder.3) A push-stick, block or other safe means shall be used on all operations close to high-

    speed cutting edges.

    4) The use of cracked, bent, or otherwise defective parts such as saw blades, cutters, and

    knives is prohibited.

    13.3 Ladders

    1) All ladders must be visually inspected prior to use.

    2) Portable metal ladders shall not be used for electrical work or where they may contact

    electrical conductors.

    3)

    No one shall use a straight or extension ladder unless the ladder is provided with safetyfeet and is held, tied or otherwise made secure to prevent slipping or falling

    4)

    Ladders shall not be used over machines with exposed moving parts, unless it is held by s

    second person, or the top securely lashed.

    5)

    To prevent slipping and breaking, straight and extension ladders shall be placed with the

    feet approximately one fourth of the ladders extended length from the wall or object

    against which the top is resting; when this position is not possible, the ladder shall be

    another unless the top is securely lashed.

    6) The person shall face ladder and use both hands for support when ascending or

    descending. A persons feet shall never be placed higher than the third rung from the top

    of the ladder, unless the ladder is placed against a structure which affords a support thatcan be used for holding onto with the hands, such as a substation structure, pole, or other

    similar structure.

    7)

    When working on a ladder where the top cannot be lashed or otherwise secured the

    reaching distance shall not exceed one arms length to ei ther side.

    8)

    A stepladder shall be used in the open position. It shall be opened fully and locked.

    Personnel shall not stand on the top board of any stepladder.

    9) Wires, cables or ropes being installed or removed shall not be attached to ladders or

    personnel working on them.

    10) The use of ladders with broken or missing rungs or steps, broken or split side rails, or

    other faulty construction is prohibited

    11) Job-made Laddersa) All wood used to construct job-made ladders shall be thoroughly seasoned,

    straight grained, and free from knots, decay, and other defects.

    b) Job-made ladders shall be constructed for the intended used. If the ladder is to

    provide the only mean of access or exit from a working area for 25 or more

    personnel, or simultaneous two-way traffic is expected, a double cleat ladder shall

    be installed.

    c) Double cleat ladders shall not exceed 7 meter in length.

    d) Single cleat ladders shall not exceed 9 meter in length.13.4 Floor and wall openings

  • 7/24/2019 Hse 20management 20plan 131015203748 Phpapp01

    32/48

    PROPOSED HSE PLAN FOR BIDDING Doc. No: LLM/2013/P-LP1/HSE-00Rev. No: A

    Page 32 of 48

    1) Floor openings shall be securely protected by use of secured guardrail or cover. If acover is used, it shall be secured and identified. Also, it shall be of sufficient strength to

    support personnel or material that may pass over it.

    2)

    When covers are removed (appropriate warning signs erected) to run piping, conduit,

    duct work, etc., through floor opening, the cover shall be replaced when the work is

    completed and/or when the workers leave the area.

    3) If it is necessary to remove a cover for work reasons that take several days or more, a

    barricade must be erected around the penetration and appropriate warning signs erected.

    13.5 Manual lifting and carrying

    Many accidents on construction sites are caused by the incorrect method used to lift objectsmanually, and trying to move objects are too heavy for the person(s) trying to do. There are

    correct method for lifting things as a team or individually. The most important part of any lift is

    to stop for a few minutes and think. Can I lift this safety. If not, get more help or call for a

    forklift/crane.

    Follow the following points:

    If the load is too heavy-ask for help

    Remember it is very easy to get hurt carrying heavy loads

    Take special care when carrying long material around corners-there might be someone

    coming

    Every person can safety carry a different load-not all personnel can carry the same

    weight

    The knees must be used to lift object not the lower back

    Loads must never be carried up ladders. A material hoist or block and tackle must be

    used instead

    13.6 Mechanized equipment

    1) Operators shall always check to make certain that other workers are in the clear before

    starting equipment.

    2) No one shall jump or off machines.

    3) Before repairs are made on earth-moving equipment, the operator should make certain

    that the motor is not running. Motors of all equipment shall be stopped before refueling

    is done.

    4) Where any portion of the equipment or vehicle projects into the road, it shall be

    adequately marked with warning devices i.e. flashers; red flags shall be used in

    daytime. Local regulations governing work site traffic control standards shall be

    observed.

    5)

    The operator shall never leave his/her machine on an incline or on loose material withthe motor idling.

    6) Heavy earth-moving equipment shall be equipped with a reverse signal alarm, which

    will operate automatically with backward movement. The alarm shall give an audible

    signal suitable for the conditions.

    7) Positive stops shall be utilized during all repair and maintenance operations.

    8)

    Signal-men shall wear a red or orange warning garment or an armband while flagging.

    Warning garments or armband worn at night shall be reflective.

    13.7 Compressed air and gases

    1) Cylinders shall be secured in an upright position. Valve protection caps