How to Implement OracleProject Management in 60 days

NorCal OAUG Training Day 2009

Timothy Cronin

Cronin Business Solutions

Insert photo here

Page 2: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

2 / January 2009 /

Northern California OAUG Training Day 2009

About Cronin Business Solutions…

Experts in the Oracle Projects suite…

Contact Information:

Timothy Cronin, President

Telephone: 954.243.3101

eMail: [email protected]

Web: www.croninINC.com

Page 3: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

3 / January 2009 /

Northern California OAUG Training Day 2009

Agenda…

• Oracle Project Management Overview

• 60 Day Plan to Implement Project Management

• Configuration Considerations

• Pitfalls, Common Mistakes and Lessons Learned

This presentation will address the following topics…

Page 4: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

4 / January 2009 /

Northern California OAUG Training Day 2009

Overview

Page 5: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

5 / January 2009 /

Northern California OAUG Training Day 2009

Oracle Projects Intelligence

The Projects Suite…

Oracle ProjectFoundation

Oracle ProjectBilling

Oracle ProjectCosting

Oracle ProjectCollaboration

Oracle ProjectResource

Management

Oracle ProjectManagement

Oracle ProjectPortfolioPlanning

Oracle ProjectContracts

Oracle ProjectManufacturing

Oracle Timeand Labor Global Project

Repository

PersonalizedRole-Based Views/ Security

Page 6: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

6 / January 2009 /

Northern California OAUG Training Day 2009

Oracle Project Management…

• Create, manage and version workplans

• Track progress against plan

• Integrate with MS Project

• Create budgets / forecasts to completion

• Provide real time project overview via

a HTML portal

• Manage issues at a project or

task level

• View Gantt charts

• Create work plan dependencies

• Manage change orders

Integrate withMS Project

ManageWorkplans

ManageBudgets

Forecasts

Assign taskweighing

View GanttCharts

HTMLPortal /

Dashboard

Oracle ProjectManagement

Page 7: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

7 / January 2009 /

Northern California OAUG Training Day 2009

Oracle Project Collaboration…

• Provides a secure collaborative workspace

• Visibility to assigned tasks, issues and deliverables

• Single document repository with versioning capabilities

• Related to Oracle Project Management

Oracle ProjectCollaboration

CollaborativeWorkspace

Visibility to tasks,issues anddeliverables

SecureHTML

DocumentVersioning

Page 8: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

8 / January 2009 /

Northern California OAUG Training Day 2009

The 60 Day Plan

Page 9: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

9 / January 2009 /

Northern California OAUG Training Day 2009

The 60 Day Plan: High-level plan…

Team Member Page.

Patching

Exception Reporting

Personalizations

Status Reporting

Upgrade Projects to FPM

Load Project Performance

Day 5 Day 15 Day 25 Day 35 Day 45 Day 55

Roles and Responsibility

MS Integration

Training

Day 10 Day 20 Day 30 Day 40 Day 50 Day 60Day 0

Page 10: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

10 / January 2009 /

Northern California OAUG Training Day 2009

Patches and Packs

Page 11: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

11 / January 2009 /

Northern California OAUG Training Day 2009

Projects Suite Family/Maintenance Packs 11i…

2000 2001 2002 2003 2004 2005

Version11.5.3

Family PackB

Version11.5.4

Family PackD

Version11.5.7

Family PackH

Version11.5.8

Family PackJ

Version11.5.9

Family PackK

Version11.5.10

Family PackL.10

Version11.5.10

Family PackM

Version11i

(11.5)Released

Version11.5.10

Family PackL

2006 2007

M Rollup

2, 3, 4

2008

Page 12: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

12 / January 2009 /

Northern California OAUG Training Day 2009

Patches and Packs…

•Metalink note 302074.1 details the patches necessary toupgrade to Family Pack M

•Patch 5644830: Oracle Projects Rollup Patch 4 for OracleProjects Family Pack M (11i.PJ_PF.M)

•Rollup 5 does not exist yet, however, there are a series ofadditional patches that may be needed to support targetedfunctionality

Apply the Family Pack M Patch – Rollup 4 to your instance

Page 13: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

13 / January 2009 /

Northern California OAUG Training Day 2009

Responsibilities andRole Based Security

Page 14: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

14 / January 2009 /

Northern California OAUG Training Day 2009

Responsibility Based Security…

• HTML Based

– Project Super User

– Project Manager

– Project Administrator

– Resource Manager

– Staffing Manager

– Operations Manager

– Team Member

• Forms Based

– Project Costing Super User

– Project Billing Super User

– Projects Implementation SuperUser

– Project Manager (Non-HTML)

The Oracle Projects Suite contains the following predefinedresponsibilities:

Page 15: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

15 / January 2009 /

Northern California OAUG Training Day 2009

Role Based Security…

• Role based security controls access based on the role theuser plays on a project

• Access for a user can be different on each project

• Role based security overrides responsibility based securityfor individual users

• Provides additional features for specific modules such asResource MGT and Contracts

Role Based Security is a key component of Oracle ProjectManagement’s security functionality

Page 16: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

16 / January 2009 /

Northern California OAUG Training Day 2009

Upgrading Projects

Page 17: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

17 / January 2009 /

Northern California OAUG Training Day 2009

Upgrading Projects…

Configuration Steps

• Set Licensing Profile Options

• Upgrade Resource Lists to Planning Resource Lists

–UPG: Upgrade Resource List To Planning Resource List

• Enable Financial Plan, Workplan and Deliverable Structuresfor specific projects

• Assign yourself as a key member with an appropriate Role

• Upgrade Budgets

–UPG: Upgrade Budget Types and Budget Versions

• Configure Workplan settings

• Configure Financial Plan settings

The following steps are necessary to upgrade projects forProject Management

Page 18: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

18 / January 2009 /

Northern California OAUG Training Day 2009

Upgrading Projects…

Configuration Steps:

• This configuration allows existing resource lists to be used as PlanningResource Lists and Resource Breakdown Structures

Upgrade Resource Lists to Planning Resource Lists

Page 19: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

19 / January 2009 /

Northern California OAUG Training Day 2009

Upgrading Projects…

Configuration Steps:

• Setup with Workplan

• Navigate: Forms – Setup- Projects- Project Templates- Query Project -Structures

Enable Structures

Page 20: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

20 / January 2009 /

Northern California OAUG Training Day 2009

Upgrading Projects…

Configuration Steps:

• Family Pack M grants access based on roles assigned in the Key Membersform or the equitant HTML functionality

• Navigate: Forms – Setup- Projects- Project Templates- Query Project – KeyMembers

Assign Key Members to Projects

Page 21: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

21 / January 2009 /

Northern California OAUG Training Day 2009

Upgrading Projects…

Configuration Steps:

• This concurrent process will migrate your budgets from forms to HTML

Upgrade Budgets

Page 22: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

22 / January 2009 /

Northern California OAUG Training Day 2009

Upgrading Projects…

Configuration Steps:

• This concurrent process will migrate your budgets from forms to HTML

Upgrade Budgets

Page 23: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

23 / January 2009 /

Northern California OAUG Training Day 2009

Upgrading Projects…

Configuration Steps:

• Navigate to your workplan in Family Pack M (HTML) – Setup:

– Configure Settings

– Configure Progress

– Configure Workplan Structure Information

Configure Workplan Settings

Page 24: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

24 / January 2009 /

Northern California OAUG Training Day 2009

Upgrading Projects…

Configuration Steps:

• Setup the Financial Plan

• Navigate: Forms – Setup- Projects- Project Templates- Query Project –Financial Plan - Settings

Enable Financial Plan Settings

Page 25: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

25 / January 2009 /

Northern California OAUG Training Day 2009

MS Excel Integration

Page 26: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

26 / January 2009 /

Northern California OAUG Training Day 2009

MS Excel Integration…

Users can build budgets in Oracle Project Managementusing MS Excel

–The integration is supported by standard functionality

–Ability to integrate:

•Actuals

•Quantity

•Raw Cost

•Burdened Cost

–The following patch is needed to support MS Excel Integration:

•Patch 5367017

Oracle Project Management Provides standard MSExcel Integration via ADI

Page 27: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

27 / January 2009 /

Northern California OAUG Training Day 2009

MS Excel Integration…

Configuration Steps:

• Financial Plan – Budget Version – Export to Excel

Oracle Project Management standard MS Excel Integration

Page 28: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

28 / January 2009 /

Northern California OAUG Training Day 2009

MS Excel Integration…

Microsoft Excel Interface:

– Note the “Oracle” menu plug-in that is added to Excel

Oracle Project Management standard MS Excel Integration

Page 29: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

29 / January 2009 /

Northern California OAUG Training Day 2009

Project PerformanceReporting

Page 30: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

30 / January 2009 /

Northern California OAUG Training Day 2009

Project Performance Reporting…

Project Performance Reporting is the next generationof PSI

Page 31: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

31 / January 2009 /

Northern California OAUG Training Day 2009

Project Performance Reporting…

Configuration Steps to Load Project PerformanceReporting…

–PRC: Load Project and Resource Base Summaries

–PRC: Load Project Performance Data

–PRC: Update Project and Resource Base Summaries

–PRC: Update Project Performance Data

• Refer to Metalink Note 364621.1 for a detailed Overview and FAQfor Project Performance Reporting

• Ensure that you have adequate table space to perform the load

–Refer to Metalink Note 311745.1 for table space suggestions

Project Performance Reporting is the next generationof PSI

Page 32: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

32 / January 2009 /

Northern California OAUG Training Day 2009

Revenue and BillingSummary

Page 33: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

33 / January 2009 /

Northern California OAUG Training Day 2009

Revenue and Billing Summary…

Revenue and Billing Summary

– Navigate: Financial Tab – Billing

Project Performance Reporting will also load aRevenue and Billing summary

Page 34: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

34 / January 2009 /

Northern California OAUG Training Day 2009

Personalizations

Page 35: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

35 / January 2009 /

Northern California OAUG Training Day 2009

Personalizations…

Most Project Management pages can be personalizedusing standard functionality

–Pages that can be personalized include:

• Workplan – Published

• Workplan – Working

• Deliverables

• Issues

• Change Requests

• Change Orders

• Financial Plan – Versions

• Percent Complete

• Tasks

• Task Summary

• Resource Summary

You can personalize views in Oracle ProjectManagement using standard functionality

Page 36: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

36 / January 2009 /

Northern California OAUG Training Day 2009

Personalizations…

Oracle Project Management provides extensivepersonalization functionality

Page 37: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

37 / January 2009 /

Northern California OAUG Training Day 2009

Exception Reporting

Page 38: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

38 / January 2009 /

Northern California OAUG Training Day 2009

Exception Reporting…

Oracle Project Management provides extensive ExceptionReporting features

Page 39: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

39 / January 2009 /

Northern California OAUG Training Day 2009

Exception Reporting…

Exception Reporting Considerations:

• Define and assign Key Performance Areas and Scoring Rules

• Optional: Create Custom Performance Rules

• Assign Performance Rules to your project or Template

–Navigate to the Project Template or Project in HTML – ReportingTab – Setup – Performance Rules

• Run PRC: PRC: Generate Performance Scores and Notifications

Oracle Project Management provides extensive ExceptionReporting features

Page 40: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

40 / January 2009 /

Northern California OAUG Training Day 2009

Exception Reporting…

Exception Reporting Considerations:

• Define and assign Key Performance Areas and Scoring Rules

• Optional: Create Custom Performance Rules

• Assign Performance Rules to your project or Template

–Navigate to the Project Template or Project in HTML – ReportingTab – Setup – Performance Rules

• Run PRC: PRC: Generate Performance Scores and Notifications

Oracle Project Management provides extensive ExceptionReporting features

Page 41: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

41 / January 2009 /

Northern California OAUG Training Day 2009

Status Reporting

Page 42: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

42 / January 2009 /

Northern California OAUG Training Day 2009

Status Reporting…

Oracle Project Management provides robust statusreporting functionality

Page 43: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

43 / January 2009 /

Northern California OAUG Training Day 2009

Status Reporting…

Status Reporting Configurations:

• Optional: Define Status Report Sections

• Create and Assign a Status Report to your Project Template orProject

–Navigate: Query Project or Template in HTML – Reporting Tab –Setup – Status Reports – Add Status Report – Define:

•Effective Dates

•Layout

•Reporting Cycle

•Approval Options

•Reminder Rules

• Navigate: Reporting Tab – Status Reports – Create Status Report

Oracle Project Management provides robust statusreporting functionality

Page 44: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

44 / January 2009 /

Northern California OAUG Training Day 2009

Team MemberHome Page

Page 45: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

45 / January 2009 /

Northern California OAUG Training Day 2009

Team Member Home Page…

Manage your project withthe Team Member HomePage

• View Owned Work

• Manage Issues

• Review Assigned Actions

• Update Progress

• Manage Deliverables

• Manage Change Documents

The Team Member Home Page Provides a collaborativespace for your project

Page 46: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

46 / January 2009 /

Northern California OAUG Training Day 2009

Team Member Home Page…

If you have configured any of the following features, they willbe available on the Team Member Home Page:

Deliverables

Issues

Progress

Change Documents

Owned Work

Etc…

The Team Member Home Page requires limitedconfiguration

Page 47: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

47 / January 2009 /

Northern California OAUG Training Day 2009

MS ProjectIntegration

Page 48: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

48 / January 2009 /

Northern California OAUG Training Day 2009

MSP Integration…

Microsoft Project Integrationallows for extensive integrationwith Oracle ProjectManagement

• Create Workplan Tasks

• Create Financial Plan Tasks

• Delete Tasks

• Manage Resources

• Manage Progress

• Interface actual Cost to Microsoft

• Integrate detailed schedule data

• Manage resource loaded plans

• Store plan versions

• Role Based Security

Oracle Project Management provides extensiveMicrosoft Project Integration

Please apply Patch 5367017 to support this feature

Page 49: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

49 / January 2009 /

Northern California OAUG Training Day 2009

MSP Integration…

Configuration Considerations:

•Structures

–MSP Integration works differently depending on the Structureassigned to the project

•Install MSP Integration

–Navigate: Project Super User – Setup – Microsoft ProjectIntegration Installation

•Complex Project Plans are exception prone

–Detailed resource loaded schedule integration needs expertisewith MSP and Oracle Project Management

•Recommended Integration Settings

–Use MSP to define large numbers of tasks and interface to eitherthe Workplan or the Financial Plan

Oracle Project Management provides extensive MicrosoftProject Integration

Page 50: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

50 / January 2009 /

Northern California OAUG Training Day 2009

Lessons Learned

Page 51: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

51 / January 2009 /

Northern California OAUG Training Day 2009

Lessons Learned, Pitfalls and Common Mistakes…

•Rollout Project Management slowly

–This reduces risk and allows for a longer training period

•Ensure that there is adequate training

–We recommend UPK (User Productivity Kit)

•Obtain Executive Buy in for the effort

•Advertise the benefits of Oracle Project Management

–Collaborative Environment

–Project Performance Reporting

–Exception Reporting

–MSP Integration

•Develop Super Users

–A strong Super User community can reduce risk and improveimplementation success

Our experience tells us:

Page 52: How to Implement Oracle Project Management in 60 · PDF fileHow to Implement Oracle Project Management in 60 days NorCal OAUG Training Day 2009 Timothy Cronin Cronin Business Solutions

52 / January 2009 /

Northern California OAUG Training Day 2009