MAJOR BUILDING WORKS
SCHEDULES
HOLD POINTS
WITNESS POINTS
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 2 of 24
MAJOR BUILDING WORKS
SCHEDULES
HOLD POINTS
WITNESS POINTS
PROJECT INFORMATION
Project Number: . . . . . . . . . . . . . . . .
RFT Number: . . . . . . . . . . . . . . . . . .
Project title:
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Superintendent:
Name: . . . . . . . . . . . . . . . . . . . . . . . . . .
Phone number: . . . . . . . . . . . . . . . . . . .
Contact person (Project Manager/Officer)
Name: . . . . . . . . . . . . . . . . . . . . . . . .
Phone number: . . . . . . . . . . . . . . . . . . .
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 3 of 24
1. HOLD POINTS AND WITNESS POINTS SCHEDULES
1.1 SCHEDULE 1 – HOLD POINTS
Schedule 1 – Hold Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
General Requirements – Contractor’s submissions – As-constructed drawings
General Requirements – Volatile substances management – Provide details
General Requirements – Camp site/compound/workshop – Provide written approval
General Requirements – Safety – Work health and safety management plan – Provide WHS management plan
General Requirements – Materials and components – Project modifications – Advise Superintendent
Demolition – Materials and components – Hazardous materials – Advise Superintendent
Groundworks – Rock or bad ground – Advise Superintendent
Groundworks – Existing services – Excavation – Approval for excavation within 1m of underground services
Groundworks – Excavation – Explosives – Approval to use explosives
Termite Control – Reticulation system – Acceptance of system design plan
Concrete – Contractor's submissions – Information on saw joints
Concrete – Embedded items – Placing and fixing – Approval to cut
Concrete- Concrete – Ready mixed supply – Submission of slump and mix details
Concrete – Concrete – Hot weather placing – Maximum ambient temperature
Concrete – Joints – Construction Joints – Approval of construction joints not shown on drawings
Structural Steel – Contractor's submissions – Shop drawings
Structural Steel – Construction generally – Availability of lengths/sections – Acceptance of splices and joints information
Structural Steel – Construction generally – Temporary connections (cleats) – Acceptance of information
Structural Steel – Construction generally – Enlargement of bolt holes – Approval
Structural Steel – Welding – Approval of the Weld Procedure Specifications – Provide weld procedure specifications
Structural Steel – Bolting – Anchor bolts – Submit details
Light Steel Framing – Roof trusses – Submission of shop drawings
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 4 of 24
Schedule 1 – Hold Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Masonry – Samples – Masonry unit samples
Masonry – Samples – Face-work sample panels
Masonry – Materials and components – Mortar additives – Acceptance of proposed additives
Masonry – Materials and components – Coloured mortar – Acceptance of proposed coloured mortar
Masonry – Materials and components – Premixed mortar – Acceptance of premixed mortar
Masonry – Materials and components – Mortar damp proof course – Approval for use of premix
Masonry – Construction generally – Cleaning – Acceptance of proposed cleaning system and submission of Safety Data Sheets for proposed chemicals
Masonry – Reinforced masonry – Cleaning core holes – Inspection and approval of cleaning out of cores
Woodwork – Roof trusses – Shop drawings
• Submission
• Certification
Insulation, Sarking & Pliable Membranes – Inspection – Notice
• Inspection after 2 runs of lapped foil installation
• Inspection before covered up
Windows – Contractor's submissions – Shop drawings
Glazing – Contractor’s submissions – Shop drawings
Glazing – Glazing – Installation – Submit proposals for site glazing
Suspended Ceilings – Construction generally – Ceiling grid – Approval of set out
Painting – Materials and components – Paint manufacturer – APAS specification
Painting – Materials and components – Delivery – Submit invoices and delivery dockets
Painting – Painting – Inspection Test Plans (ITP’s) – Submit ITPs
Painting – Painting – Spraying – Approval for spray painting
Stormwater – Tests – Notice – Hydrostatic tests
Stormwater – Tests – Hydrostatic tests – To AS/NZS 3500.3
Stormwater – Contractor’s submissions – Work-as-executed drawings
Stormwater – Subsoil drains – Laying and backfilling – Approval of pipe installation
Sanitary Services – Tests – Notice – Hydrostatic Tests
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 5 of 24
Schedule 1 – Hold Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Sanitary Services – Tests – Hydrostatic tests to AS/NZS 3500.2
Sanitary Services – Contractor’s submissions – Work-as-executed drawings
Sanitary Services – Sanitary plumbing – Building penetrations
• Approval to penetrate structural members and elements or membrane elements
• Approval of locations of sleeves and core holes
Sanitary Services – Access chambers – Construction – Approval for the use of precast chambers
Sanitary Services – Access chambers – Testing of access chambers
• Test with Superintendent present
• Submit test results to Superintendent
Sanitary Services – Access chambers – Testing of access chambers/pipeline connection
• Test with Superintendent present
• Submit test results to Superintendent
Water – Tests – Notice – Hydrostatic tests
Water – Tests – Hydrostatic tests to AS/NZS 3500.1 and AS/NZS 3500.4
Water – Contractor’s submissions – Work-as-executed drawings
Water – Pipework installation – Building penetrations
• Approval to penetrate structural members and elements or membrane elements
• Approval of locations of sleeves and core holes
LP Gas – Tests – Pressure tests – Submission of test results
LP Gas – Contractor’s submissions – NT WorkSafe notification – Submission to NT WorkSafe
LP Gas – Contractor’s submissions – Work-as-executed drawings
LP Gas – Contractor’s submissions – Certificates of compliance – Certificates of compliance provided
LP Gas – Installation – Building penetrations
• Approval to penetrate structural members and elements or membrane elements
• Approval of locations of sleeves and core holes
LP Gas – Compliance plate – Compliance plate installed
General Electrical Requirements – Quality – Written approval for manufacture of switchboards and confirmation of orders for luminaires
General Electrical Requirements – Contractor’s submissions – As-constructed drawings
General Electrical Requirements – Contractor’s submissions – Authority approvals – Shop drawings – Submission to PowerWater
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 6 of 24
Schedule 1 – Hold Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Wiring & Accessories – Movement detector switching – Movement detectors – Movement detector locations approved
Photovoltaic – Contractor’s submissions – Shop drawings
Photovoltaic – Contractor’s submissions – Certification – Section 40 required
Photovoltaic – Completion – Operation and maintenance manuals
Photovoltaic – Completion – Work-as-executed drawings
UPS – Contractor’s submissions – Shop drawings
Generators – Contractor’s submissions – As-constructed drawings
Generators – Completion – On-site commissioning – Notice for commissioning to be witnessed
Switchboards – Contractor’s submissions – Product data for proprietary assemblies
Switchboards – Contractor’s submissions – Shop drawings for custom-built assemblies
Switchboards – Contractor’s submissions – Protection grading study
Switchboards – Contractor’s submissions – Authority approvals – Shop drawings submitted to PowerWater
Switchboards – Custom built switchboards – Approved manufacturers – Switchboard manufacturer details for approval
Luminaires – Contractor’s submissions – Shop drawings
Communications – Inspection – Notice – As-built drawings
Communications – Execution – Firestop – Submit certification
Communications – Completion – As-built drawings
Fire detection – Contractor’s submissions
• Installers statement
• System commissioning statement
• Sound pressure level measurements
• As-installed drawings
Lightning and Surge Protection – Lightning protection – Contractor’s submissions – Shop drawings
Electronic Security and Access Control – Shop drawings
Electronic Security and Access Control – Completion – Commissioning – Commissioning test plan, commissioning history report
General Mechanical Requirements – Preliminary details – Preliminary documents for review
General Mechanical Requirements – Contractor’s submissions –Authority approvals – Submit notes of meetings with authorities
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 7 of 24
Schedule 1 – Hold Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
General Mechanical Requirements – Contractor’s submissions – Building penetrations – Details structural, fire, and other properties
General Mechanical Requirements – Contractor’s submissions – Certification
General Mechanical Requirements – Contractor’s submissions – Design documentation
General Mechanical Requirements – Contractor’s submissions – Contract drawings
General Mechanical Requirements – Contractor’s submissions – Maximum demand calculations – Electrical, natural gas potable water, and waste water
General Mechanical Requirements – Contractor’s submissions – Structural loadings
General Mechanical Requirements – Contractor’s submissions – Execution details – Embedded services, fixing of services and inaccessible services
General Mechanical Requirements – Contractor’s submissions – Marking and labelling – Submit samples and schedules
General Mechanical Requirements – Contractor’s submissions – Operations and maintenance manuals
General Mechanical Requirements – Contractor’s submissions –Maintenance log book
General Mechanical Requirements – Contractor’s submissions – Prototypes
General Mechanical Requirements – Contractor’s submissions – Records – As-built, photographs, system diagrams, schedules, and log books
General Mechanical Requirements – Contractor’s submissions – Samples
General Mechanical Requirements – Contractor’s submissions – Tests – inspection and testing plan, certificates, fire hazard properties, and test reports
General Mechanical Requirements – Shop drawings – Approval
General Mechanical Requirements – Shop drawings – Variations to shop drawings – Submission and approval to use
General Mechanical Requirements – Shop drawings – Functional descriptions approval
General Mechanical Requirements – Shop drawings – Preliminary submission
General Mechanical Requirements – Shop drawings – Detailed submission
General Mechanical Requirements – Shop drawings – As-installed documentation
General Mechanical Requirements – Products – Substitutions – Alternative product documentation
General Mechanical Requirements – Warranties
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 8 of 24
Schedule 1 – Hold Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Mechanical Systems – Contractor’s submissions – Electrical loading information for mechanical services – Electrical loading information before completion
Mechanical Systems – Contractor’s submissions – Mechanical services contract drawings
Ductwork – Contractor’s submissions – Certification
Ductwork – Contractor’s submissions – Samples
Ductwork – Leakage tests – Reports
Ductwork Insulation – Contractor’s submissions – Samples
Air Grilles – Installation of air grilles – Alternative plenum and cushion head boxes
• Provide shop drawings for approval
• Provide warranties
Mechanical Pipework – Design – Documentation
Mechanical Pipework Insulation – Contractor’s submissions – Samples
Water Treatment – Completion – Tests before building occupation
BMS – Contractor’s submissions – Listings – Submit hardware and populates graphics
BMS – Contractor’s submissions – Samples
BMS – Contractor’s submissions – Drawings
BMS – Contractor’s submissions – Inspection Test Plans (ITPs)
BMS – Contractor’s submissions –Manuals
BMS – Contractor’s submissions – Prototypes
BMS – Execution – Pre-completion tests
BMS – Execution – Completion – Provide training
Mechanical Commissioning – Fire and life safety training
Mechanical Commissioning – meeting – Document and submit handover meetings
Mechanical Commissioning – Handover training
Mechanical Commissioning – Final completion documentation – Provide final approved hard copy originals
Mechanical Maintenance – Products – Product selection – Submit products to be substituted
Mechanical Maintenance Handover training
Mechanical Maintenance – Handover meeting – Document and submit handover minutes
Mechanical Maintenance – Final completion documentation – Provide final approved hard copy originals
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 9 of 24
Schedule 1 – Hold Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Civil Works – General – Inspection Test Plan (ITP) – Submit ITPs
Civil Works – Earthworks – Excess material – Inform Superintendent
Civil Works – Earthworks – Rock in subgrade – Inform Superintendent
Civil Works – Earthworks – Unsuitable material below subgrade surface other than rock – Inform Superintendent
Civil Works – Earthworks – Unsuitable material beneath fill – Superintendent directions before works commence
Civil Works – Earthworks – Proof rolling – Submit a proof rolling procedure
Civil Works – Earthworks – Conformance testing – Ordering procedures
Civil Works – Pavements and shoulders – Process control testing – Submit program and procedure
Civil Works – Pavements and shoulders – Proof rolling – Notice
Civil Works – Pavements and shoulders – Conformance testing of pavements and shoulders – Superintendent’s approval for pavement conformance prior to any surfacing work
Civil Works – Spray Sealing – Spray rates – Spray rates required
Civil Works – Spray Sealing – Application of aggregate – Approval of aggregate loader
Civil Works – Dense graded asphalt – Design mix requirements
• Approval of registered mix design
• New mix design procedure
Civil Works – Conformance testing – Inspection Test Plans (ITPs) – Submission required for procedures and test plans
Civil Works – Pavement marking – Workmanship – Remove defective markings
Civil Works – Road furniture and traffic control devices – Certification of guide posts
Civil Works – Road furniture and traffic control devices – Guide post characteristics – Sample required from each batch
Civil Works – Road furniture and traffic control devices – Road signs – Approval of anti-graffiti film or coating
Fabric shade structures – Contractor’s submissions – Design drawings
Fabric shade structures – Building certification – Section 40
Fabric shade structures – As-constructed drawings
Landscape – Contractor’s submissions – Samples
Landscape – Topsoil – imported topsoil – Approval of supplier
Landscape – Excavation and planting – Setting out of holes – Approval of set out
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 10 of 24
Schedule 1 – Hold Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Landscape – Mulching – Mulch – Approval of supplier
Irrigation – Contractor’s submissions – Design drawings
Irrigation – Tests – Hydrostatic tests
Irrigation – Excavation and installation – Backfilling trenches – Inspection
Irrigation – Completion – Work as-executed drawings
Irrigation – Shop drawings
Irrigation – Control cabling – Inspection before backfilling trenches
Irrigation – Tests – Hydrostatic tests – Approval of results
Irrigation – Contractor's submissions – Design plans – Submission for approval
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 11 of 24
1.2 SCHEDULE 2 – WITNESS POINTS
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
General Requirements – Contractor’s submissions – As-constructed drawings – PDF and CAD drawings
General Requirements – Contractor’s submissions – Amended drawings – Procedure for recording and submitting amended drawings
General Requirements – Contractor’s submissions – Warranties
General Requirements – Contractor’s submissions – Authority approvals – Submit documents
General Requirements – Contractor’s submissions – Inspection Test Plans (ITPs)
General Requirements – Contractor’s submissions – Testing and commissioning reports – Submit reports
General Requirements – Safety – Safety officer – Appointment and details
Demolition – Inspections – Notice required
• Commencement
• Adjoining structures
• Underground structures
• Trees to be retained
• Excavations remaining after removal of underground work
• Structures after removal of roof sheeting or wall cladding
• Services after diversion or re-connection
• Site after removal of demolished materials
• Completion of demolition
Groundworks – Inspections – Notice required
• Enclosures to trees to be retained
• Excavation completed to contract levels or founding material
• Services laid in trenches and ready for backfilling
Groundworks – Excavation – Explosives – Licences and certificates
Groundworks – Proof rolling – Notice required
Ground works – density tests – Compaction test results – Test certificates
Termite control – Inspections – Notice required
• Chemical spraying of under slab areas
• Stainless steel mesh barriers installed, before concrete is poured
• Chemical reticulation system installed ready for testing
Termite control – completion – Durable notice required
Concrete – Inspections – Notice required
• Base or subgrade before covering
• Membrane or film underlay installed on the base or subgrade
• Termite barrier and film underlay installed on the base
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 12 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
• Completed formwork, and reinforcement, cores and embedments fixed in place
• Commencement of concrete placing
• Before core filling masonry
• Evaluation of the off-form finishes
• Evaluation of surface finish
Structural steel – Inspections- Notice required
• Commencement of shop fabrication
• Completion of fabrication before surface preparation
• Surface preparation prior to painting
• Completion of protective coating before delivery to site
• Reinforcement and formwork in place before any encasement
• Steelwork and column bases erected on site, before grouting, encasing, site painting or cladding
• Completed grouting, encasement, fire protection, or site painting
Structural steel – Contractor’s submissions – Compliance – Evidence of steel
Structural steel – Welding – Certification of welders and welding supervisors
Structural steel – Welding – Preparation – Weld procedure
Light Steel Framing – Framing inspection – Notice required
Masonry – Inspection – Notice required
• Damp-proof courses
• Flashings, downpipes and other work to be concealed
• Bottoms of cavities after cleaning out
• Lintels in position
• Structural elements being built in
• Bottoms of core holes before grouting
• Core filling
• Control joints ready for insertion of joint filler
Masonry – Reinforced masonry – Clean out blocks – Notification required
Woodwork – Inspection – Notice – Inspection of structural woodwork before covering up
Woodwork – Contractor’s submissions – Roof truss certification
Woodwork – Contractor’s submissions – Roof truss moisture content
Roofing – Inspection – Notice
• Substrate
• Roof supports
• Sarking, vapour barriers, pliable membranes
• Insulation
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 13 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
• Roof plumbing – gutters, rainwater heads, sumps, overflow relief systems, downpipes, inspection/maintenance openings etc.
Cladding – Inspection – Notice of framing with sarking and flashings before fixing cladding
Cladding – Aluminium composite panels
• Fire engineer report
• Test certificates and group number
• Supply certificates
Windows – Inspection – Notice
• Fabricated window assemblies at the factory ready for delivery to the site
• Openings prepared to receive windows
• Fabricated window assemblies delivered to the site, before installation
• Commencement of window installation
Windows – Contractor’s submissions – Subcontractors – Names and contract details
Windows – Contractor’s submissions – operation and maintenance manual
Windows – Contractor’s submissions – Warranties
Windows – Materials and components – Ceramic-coated spandrel glass – Fall out resistance test to ASTM C1048
Windows – Materials and components – Opacified glass – Report required
Windows – Construction generally – Certification – Compliance with AS 2047
Glazing – Materials and components – Noise reducing glazed assemblies – Identification and Rw rating
Glazing – Glazing – Installation – Temporary marking
Doors – Inspection – Notice – Door frames in place before building in
Doors – Contractor’s submissions – Tests – Type test results and certificates
Hardware – Contractor’s submissions – Manufacturer’s data
Suspended ceilings – Inspection – Notice
• Suspension system, before ceiling installed
• Completion
Suspended ceilings – Contractor’s submissions – Fire hazard properties – Group number
Suspended ceilings – Contractor’s submissions – Warranties
Partitions – Inspection – Notice
• Set out
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 14 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
• Completion
Partitions – Contractor’s submissions – Samples
• Panel and door finish
• Hardware
Partitions – Contractor’s submissions – Warranties
Lining – Inspection – Notice
• Substrate or framing, before installation
• Finished installation
Lining – Contractor’s submissions – Fire hazard properties – Group number
Lining – Contractor’s submissions – Warranties
Lining – Materials and components – Tongue and groove boards – Certified timbers
Rendering and Plastering – Inspections – Notice
• Prior to commencement of plastering
• On completion
Rendering and Plastering – Contractor’s submissions – Samples
• Plaster systems
• Beads and embedded items
Metal Work – Inspection – Notice
• Shop fabricated or assembled items, before delivery to site
• Commencement of shop or site welding
• Site erected assemblies on completion of erection, before covering up by cladding and/or encasing
• Steel surfaces prepared for, and immediately before, site applied finishes
Metal Work – Contractor’s submissions – Operation and maintenance manuals
Metal Work – Contractor’s submissions – Manufacturer’s data
Metal Work – Contractor’s submissions –Shop drawings
Metal Work – Contractor’s submissions – Subcontractors – Names and contact details
Metal Work – Contractor’s submissions – Execution details – Proposed welding procedures
Fixed furniture – Inspection – Notice
• Items fabricated off site, before delivery
• Openings prepared to receive assemblies
• Site erected assemblies on completion of erection, before covering up by cladding and/or encasing
• Surfaces prepared for, and immediately before, site applied finishes
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 15 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
• Completion of installation
Fixed furniture – Contractor’s submissions – Warranties
Fixed furniture – Contractor’s submissions – Operations and maintenance manuals
Fixed furniture – Contractor’s submissions – Shop drawings
Fixed furniture – Contractor’s submissions – Subcontractors – Names and contact details
Tiling – Inspection – Notice
• Completion of waterproof membrane
• Substrate before tiling
• Initial or trial set out
• Control joints before sealing and grouting
• Grout and sealant colours before application
Tiling – Contractor’s submissions – Waterproofing membranes – Submit a report on the application
Tiling – Contractor’s submissions – Samples
• Tiles
• Fittings
• Accessories
• Trims
• Grout
• Sealants
Tiling – Substrate – Moisture content – Test to AS?NZS 2455.1 Appendix B
Resilient finishes – Inspection – Notice
• Substrate before fixing resilient finishes or underlay
• Completed underlay
• Finished surface before applying sealers or polishes
• Completed installation
Resilient finishes – Contractor’s submissions – Fire hazard properties – Critical radiant flux
Resilient finishes – Contractor’s submissions – Manufacturer’s data
Resilient finishes – Contractor’s submissions – Warranties
Resilient finishes – Substrate – Moisture content – Test substrate to AS 1884
Carpets – Inspection – Notice
• Substrate before fixing resilient finishes or underlay
• Fixings, edge strips, underlay, before laying carpet
• Completed carpet after cleaning and before covering for protection
Carpets – Contractor’s submissions – Fire hazard properties
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 16 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Carpets – Contractor’s submissions – Samples
Carpets – Contractor’s submissions – Manufacturer’s data
Carpets – Contractor’s submissions – Warranties
Carpets – Contractor’s submissions – Shop drawings
Carpets – Substrate – Moisture content – Test substrate to AS/NZS 2455.1
Painting – Inspection – Notice
• Substrate immediately prior to commencement of painting
• Prior to application of final coat
Painting – Contractor’s submissions – Specialist applicators – Names and contact details
Painting – Contractor’s submissions – Warranties
Painting – Materials and components – Low VOC paints – Provide manufacturer’s specifications
Stormwater – Inspection – Notice
• Excavated surfaces
• Concealed or underground services before concealing or backfilling
• Placing of in situ concrete
• Upon completion
Stormwater – Subsoil drains – End walls – Clean out complete
Sanitary services – Inspection – Notice
• Excavated surfaces
• Concealed or underground services before concealing or backfilling
• Testing of access chambers
• Testing of access chambers/pipeline connection
Water – Inspection – Notice
• Excavated surfaces
• Concealed or underground services before concealing or backfilling
LP Gas – Inspection – Notice
• Before testing
• Before pipes are buried, concealed or built in
LP Gas – Contractor’s submissions – Operating instructions for each appliance
General Electrical Requirements – Inspections – Notice
• Conduits prior to backfilling
• Conduits and wiring prior to covering
• Required site tests
General Electrical Requirements – Contractor’s submissions – Shop drawings
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 17 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
General Electrical Requirements – Contractor’s submissions – Product data
General Electrical Requirements – Contractor’s submissions – Samples
General Electrical Requirements – Contractor’s submissions – Quality assurance documentation
General Electrical Requirements – Contractor’s submissions – Plant and equipment – List of installers
General Electrical Requirements – Operation and maintenance manuals
Wiring and Accessories – Contractor’s submissions – Shop drawings
Wiring and Accessories – Contractor’s submissions – Cable sizing calculations
Wiring and Accessories – Contractor’s submissions – Protection grading study
Wiring and Accessories – Power cables – Support of fire resisting cables – Provide test certificates
Wiring and Accessories – Cable pits – Proprietary cable pits – Structural certification
Wiring and Accessories – Movement detector switching – Movement detectors – Final sensitivity tests
Photovoltaic – Contractor’s submissions – Rebate application – Submit documentation
Photovoltaic – Contractor’s submissions – Technical data
Photovoltaic – Contractor’s submissions – Tests
Photovoltaic – Completion – Warranties
UPS – Contractor’s submissions – Design documentation – Calculations
UPS – Contractor’s submissions – Operation and maintenance manuals
UPS – Contractor’s submissions – Tests
UPS – Maintenance – Maintenance period – Routine testing and routine maintenance and servicing training
Generators – Contractor’s submissions – Operations and maintenance manuals
Generators – Contractor’s submissions – Products and materials – Technical data
Generators – Contractor’s submissions – Products and materials – Technical data
Generators – Contractor’s submissions – Shop drawings
Generators – Inspection – Notice – Inspection and load testing before delivery
Generators – Completion – Pre commissioning tests – Notice for commissioning to be witnessed
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 18 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Generators – Completion – Temporary test loads
Generators – Completion – Reports
Generators – Maintenance – Maintenance period – Provide testing, maintenance and servicing training
Liquid fuels – Fuel transfer and fuel polishing equipment – Operation and maintenance manuals
Liquid fuels – Fuel transfer and fuel polishing equipment – Manufacturer’s test certificates
Liquid fuels – Fuel transfer and fuel polishing equipment – Warranties
Switchboards – Inspection – Notice
• Assembly installed and connected, prior to site tests
• Commissioned and complete
Switchboards – Contractor’s submissions – Manufacturers data
Switchboards – Contractor’s submissions – Calculations – Certified calculations verifying design characteristics
Switchboards – Contractor’s submissions – Type test data
Luminaires – Contractor’s submissions – Operation and maintenance manuals
Luminaires – Contractor’s submissions – Products and materials – Technical data and photometric test results
Luminaires – Contractor’s submissions – Samples
Luminaires – Reuse of luminaires – Modifications and refurbishing – Provide test results
Communications – Inspections – Notice
• First fix
• Testing stage
• Before practical completion
Communications – Contractor’s submissions – Certification
Communications – Contractor’s submissions – Technical data
Communications – Contractor’s submissions – Samples
Communications – Contractor’s submissions – Shop drawings
Communications – Distributors – Cross connect patch panels – Vendor certification and warranty period
Communications – Distributors – Optical fibre termination panels – Vendor certification and warranty period
Communications – Completion – Operation and maintenance manuals
Communications – Warranty
Master Antenna TV – Inspection – Notice – Installation and testing stage
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 19 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Master Antenna TV – Contractor’s submissions – Certification
Master Antenna TV – Contractor’s submissions – Documentation to AS/NZS 1367
Master Antenna TV – Contractor’s submissions – Technical data
Master Antenna TV – Contractor’s submissions – Product data
Master Antenna TV – Contractor’s submissions – Record drawings
Master Antenna TV – Contractor’s submissions – Correspondence with network operators – Correspondence and service agreements
Master Antenna TV – Contractor’s submissions – Samples
Master Antenna TV – Contractor’s submissions – Shop drawings
Master Antenna TV – Commissioning – Testing – System testing results
Fire Detection – Commissioning – Commissioning program prior to testing
Fire Detection – Commissioning – Acceptance testing – Written acceptance test procedure
Lightning and Surge Protection – Lightning protection contractor submissions – Operation and maintenance manuals
Lightning and Surge Protection – Lightning protection contractor submissions – Records – To AS/NZS 1768
Lightning and Surge Protection – Lightning protection contractor submissions – Subcontractors – Names and details
Electronic Security and Access Control – Contractor’s submissions – Cabler(s) registration details
General Mechanical Requirements – Inspections – Notice – Written notice of tests
General Mechanical Requirements – Contractor’s submissions – Sequences of operation – Submit changes to the operating procedure
General Mechanical Requirements – Contractor’s submissions – Products
General Mechanical Requirements – Installation – Shop drawings
General Mechanical Requirements – Testing – Test reports
General Mechanical Requirements – Testing – Notice for inspection of commissioning
General Mechanical Requirements – Testing – Certification
General Mechanical Requirements – Testing – Manufacturer’s certificates for each factory test
General Mechanical Requirements – Testing – Calibration certificates – To AS/NZS ISO 10012 by NATA testing facility
General Mechanical Requirements – Commissioning – Air balancing tests – Notice to attend
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 20 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
General Mechanical Requirements – Commissioning – Water balancing tests – Notice to attend
General Mechanical Requirements – Commissioning – Noise testing tests – Notice to attend
General Mechanical Requirements – Commissioning – Vibration testing tests – Notice to attend
General Mechanical Requirements – Commissioning – Acceptance tests – Notice to attend
General Mechanical Requirements – Commissioning – Final tests – Notice to attend
Mechanical Systems – Contractor’s submissions –Calculations
Mechanical Systems – Contractor’s submissions – Electrical loading information for mechanical services
• Loading and connection
• Starting characteristics
• Switchboard information
Mechanical Systems – Contractor’s submissions – Technical data
Mechanical Systems – Contractor’s submissions – Control function descriptions – Submit descriptions of control sequences
Mechanical Systems – Inspections – Notice
• Off-site duct construction methodology
• First install trade component fixing concealed services
• First install trade based components fixing exposed services
• Piping pressure tests
• Switchboard thermal imaging
• Fire and life safety operating sequence
Chillers Combined – Contractor’s submissions – Certification – Manufacturer’s certification to AS/NZS 4776.1.2
Chillers Combined – Contractor’s submissions – Tests
Chillers Combined – Product data
Chillers Combined – Commissioning – Commission under the supervision of the equipment manufacturer’s representative
Cooling Towers – Contractor’s submissions –Technical data
Cooling Towers – Completion tests – Type tests/production tests
Ductwork – Inspections – Notice – Leakage testing
Ductwork – Contractor’s submissions – Calculations
Ductwork – Contractor’s submissions – Construction standards – Duct construction methodologies`
Ductwork – Contractor’s submissions – Execution details
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 21 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
• Access panel details
• Mechanical fire dampers proposed installation details
• Proposed sealing methods and materials
Ductwork – Contractor’s submissions – Fire hazard properties – Evidence of conformance
Ductwork – Contractor’s submissions – Tests
• Assembly to AS 4254.2
• Sealants to AS/NZS 1530.3
• Tapes to ASTM E2342/E2342M
Ductwork Insulation – Contractor’s submissions – Calculations – Insulation values and vapour barrier statements
Ductwork Insulation – Contractor’s submissions – Exposed cold surfaces – Condensation tray statements
Ductwork Insulation – Contractor’s submissions – Acoustic performance – In duct and break out radiated noise performance
Ductwork Insulation – Contractor’s submissions – Fire hazard properties – Evidence of conformance
Ductwork Insulation – Contractor’s submissions – Products and materials – Conformance to AS/NZS 4859.1
Air Grilles – Contractor’s submissions – Products and materials – Acoustic performance test results
Air Grilles – Contractor’s submissions – samples
Mechanical Pipework – Contractor’s submissions – Products and materials
• Valves and pipeline components – Specifications
• Calibrated balancing valves – Calibration charts and test reports
• Automatic/dynamic system balancing valves – Manufacturer’s reports
Mechanical Pipework – Installation – General – Submit structural point loads
Mechanical Pipework – Testing – Hydrostatic testing
• Notice for testing to be witnessed
• Submit test results
Mechanical Pipework Insulation – Contractor’s submissions – Calculations – Insulation values and vapour barrier statements
Mechanical Pipework Insulation – Contractor’s submissions – Exposed cold surfaces – Condensation tray statements –
Mechanical Pipework Insulation – Contractor’s submissions – Acoustic performance – In duct and break out radiated noise performance
Mechanical Pipework Insulation – Contractor’s submissions – Fire hazard properties – Evidence of conformance
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 22 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Mechanical Pipework Insulation – Contractor’s submissions – Products and materials – Conformance to AS/NZS 4859.1
Water Treatment – Inspection – Contents of strainer baskets after initial chemical cleaning and flushing
Water Treatment – Contractor’s submissions – Execution details –
• Cathodic protection systems
• Microbial testing authority
• Water treatment systems
BMS – Contractor’s submissions – Documentation
BMS – Contractor’s submissions – Products and materials – Product data
BMS – Contractor’s submissions – Subcontractors qualifications – Installers qualifications
BMS – Contractor’s submissions – Technical data
BMS – Contractor’s submissions – System hardware – Manufacturer’s literature and samples of hardware devices
BMS – Contractor’s submissions – System software – Programming, software, operating protocols and passwords
Mechanical Commissioning – Inspections – Notice for first official start-up and commissioning of the installation
Mechanical Commissioning – Contractor’s submissions – Certification
• Instrumentation calibration certificates
• Conformance to contract documents
• Statutory requirements
• Compliance certification reports
Mechanical Commissioning – Contractor’s submissions – Completion program
• Completion, commissioning, testing, and instruction
• Program revisions
Mechanical Commissioning – Contractor’s submissions – Records – Report demonstrating that equipment has been properly installed and is functioning correctly
Mechanical Commissioning – Commissioning – Reports – Observations and results of tests and compliance or non-compliance with requirements
Mechanical Maintenance – Inspection – Notice
Mechanical Maintenance – Contractor’s submissions – Records – Periodic maintenance and performance report
Mechanical Maintenance – Contractor’s submissions – Statutory certification – inspect and submit inspection reports
Mechanical Maintenance – Contractor’s submissions – Statutory reporting – Submit statutory reports to AS 1851
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 23 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
Mechanical Maintenance – Periodic maintenance – Replacement materials and consumables – Substitution details
Paving – Inspection – Notice
• Completed base preparation ready for paving
• Completion of trial set-out for unit paving
• Completed unit paving
• Commencement of surface preparation ready for asphalt
• Commencement of asphalt surfacing
• Completion of asphalt surfacing
Paving – Spray sealed surfacing works – Notice required 48 hrs bitumen
Paving – Dense graded asphalt – Spreading – Notice required 24 hrs
Civil Works – Earthworks – Proof rolling – Notice required 24 hrs
Civil Works – Spray sealing – Spraying – Notice required 48 hrs
Civil Works – Dense graded asphalt – Surface preparation – Notice required 24 hrs
Civil Works – Dense graded asphalt – Spreading
• Notice required 24 hrs
• Construction program
Civil Works – Dense graded asphalt – Compaction – Temperature limits
Civil Works – Conformance testing – Notice of testing – Provide written order of testing
Civil Works – Pavement marking – Road marking paint – Submit a Certificate of Compliance
Civil Works – Pavement marking – Application
• Equipment approval required
• Evidence of equipment calibration to NTTM 405.1
Fabric Shade Structures – Contractor’s submissions – Samples – Samples of fabric and technical data
Fabric Shade Structures – Inspections – Notice
• Steel work cleaned ready for application of coating
• Footing holes before steel structure is placed in the holes
• Before concrete footings are poured
Fabric Shade Structures – Maintenance manual – Hard copy and electric
Fencing – inspections – Notice
• Boundary survey location
• Set out before construction
• Foundation conditions before placing of concrete
Landscape – Inspections – Notice
Doc ID Version Issued Printed Page
3.11 Hold & Witness–NATSPEC Basic Major Bldg Works 2019.03 July 2019 1/08/2019 24 of 24
Schedule 2 – Witness Points
CLAUSE TITLE
SE
CT
ION
PA
GE
No
INIT
IAL
S
DA
TE
• Subgrades cultivated or prepared for placing topsoil
• Grassing bed prepared prior to turfing, seeding, or temporary grassing
• Set out of planting holes prior to excavation
• Plant holes excavated and prepared for planting
• Grassing or turfing completed
• Planting, staking, and tying completed
• Completion of planting establishment work
Landscape – Contractor’s submissions – Suppliers data
• Certificates identifying seed species and germination viability
• Material source of supply
• Recommendations for planting and maintenance of plants
Landscape – Contractor’s submissions – warranties
Landscape – Topsoil – Imported topsoil – 5 kg sample required
Landscape – Mulching – Mulch – 5 kg sample required
Irrigation – Inspection – Notice
• Excavated surfaces ready for installation
• Installation ready for testing
• Concealed or underground services ready for backfill
Irrigation – Contractor’s submissions – Manufacturer’s data