CURRICULUM VITAEPERSONAL INFORMATION
Full Name: Nguyen Huy Hoang
Nationality: Vietnamese Sex: Male
Current Position:Datacenter Manager/Specielist of 21st Century Technologies
Senior System Engineer
Years of Experience in IT field: 15
Years with current Employee: 2
Company Address:No 3, Babatunde Anjous str, Lekki Phase 1, Lagos, Nigeria
Tel: (+234) 8174682234
ACADEMIC EDUCATION
Bachelor of Engineering, Information Technology, Hanoi University of Technology
Bachelor of Engineering, Electric Technology, Hanoi University of Technology
PROFESSIONAL QUALIFICATIONS Year
CCNA – Cisco Certified Network Associate 2004CCNP – Cisco Certified Network Professional 2006MCSA–Microsoft Certified Systems Administrator 2004MCSE –Microsoft Certified Systems Engineer on Microsoft windows Server 2003 2005MCSE Security – Microsoft Certified Systems Engineer Security on Microsoft windows Server 2003 2006
LANGUAGE SKILLS
Fluent Good Fair
Vietnamese
English
EMPLOYMENT HISTORY & WORK EXPERIENCES:
Company/Position/Job Description Year
21st Century Technologies Limited – Nigeria- Datacenter Specialist/Manager
Designing & implementing Private and Public Cloud using Vmware Vcenter 5.5, Vcloud Director , VSM. Networking,Backup & Storage Solutions..
Openstack Cloud environment using Fuel 9.0 Designing & implementing Avaya Telephony Solutions for SMB market
2015- Present
Page 2
FPT Information System(FIS) – Technical Manager of FIS Global
IT consulting for customers from Global market. Designing & implementing systems, application such as: Active Directory, Email
System, Exchange, MS SharePoint, MS CRM, SCCM, Lync, Office 365, SAN, Storage, Backup,Vmware, Private-Public CloundSystem and network monitor-ing tools..
Designing & implementing network infrastructures (LAN, WAN) for Customers, including network devices (routers, switches), firewalls and security solutions. Configuring Cisco routers, switches, Cisco Voice over IP …
Designing & Implementing Data Storage and backup solutions, Experience on site to site backup using Tape libraries, SAN, Raid…
HP and IBM BOM sizing tool for buiding the biding proposal. Systems & Network Monitoring: Systems & network performance, Systems fail-
ures, Internet & LAN’s bandwidth using HP Openview NNM , PRTG, MOM 2005,GFI…
Operating & troubleshooting network and system problems Contribute to written proposals and develop technical documentation. Training Microsoft Windows 2003 Server and Exchange 2007 for FPT Training
Center.
FPT Information System(FIS)
Planning and Scheduling for IT Dept. Designing Network and Security for FPT – IS, such as: Routers, switches, Fire-
walls. Designing System for FPT-IS Implementing Application for FPT- IS: Microsoft
Sharepoint, MS CRM Dynamic 3.0, Antivirus (using Symantec, McAfee..), WSUS, SMS, LCS, Cisco IPphone
System Administration Actively participate in the planning and implementation of systems, infrastruc-
ture and related hardware. Assess and recommend architectural designs/changes to customer systems in
response to business or technical drivers. Design & implement network infrastructures (LAN, WAN) for customers, includ-
ing network devices (routers, switches), firewalls and security solutions. Implement Data Storage (SAN, Tape) and backup solutions using MS DPM
2007, VERITAS. System& Network Monitoring: Systems & network performance, Application
metering using SCOM 2007, Altiris 6.0, HP Openview, PRTG, GFI.Worldview Co., Ltd– Technical manager
Plan, schedule and manage all activities of IT Dept. Build, develop and manage network and system for Worldview Company. Design and implement System and Network for customer using Windows
Server 2000, Cisco switch & router…
FPT Software ( Fsoft) – Developer Code and design database using Visual Basic, Php, C++ and SQL Server,
MySql, MS Access.
2009 –2015
2004-2008
2001 - 2003
2000
Page 3
Design and build website using PHP & MySQL, ASP & SQL Server.
IT SKILLS
Skills Year of Experience
Operating Systems and Applications
Windows Server NT/2000/2003/2008/2012
Microsoft Exchange 2003/2007/2010/2013
Microsoft Office 365
Microsoft SharePoint 2007/2010/2013
Microsoft CRM
Microsoft Lync 2010
Microsoft SCOM 2007/ SCCM 2007-2010
Microsoft ISA 2006
Crystal Report Server Administration
SQL Server 2005/2008/2012
Symantec Netbackup, Backup Exec VERITAS Backup,
Lotus Domino Server
Microsoft SCOM, SCCM 2007
Vmware ESXi 5.5, VSPhere 5.5
Vmware VCenter, Vcloud Director
Symantec Netbackup , Backup Exec
13
3
6
12
7
5
4
5
8
3
9
7
5
5
5
5
Network & System implementation
WAN
LAN
Cisco devices
Security devices
8
8
8
8
PROJECTS INVOLVED
No Projects Description
1 Project Name Process Automation Management for SingtelCustomer Suntek, SingaporeDuration Jan 2014 to Dec 2014Project Position Architecture and Teachnical LeadProject Description Implement the IT automation processesTasks Desgin, implement infrastructure
o Vmware Esxi 5.5 to create 20 VM serverso Install and configure SAN V3700 to connect to
physical Server
Page 4
PROJECTS INVOLVED
No Projects Descriptiono Install and configure Cluster SQL Databaseo Install and configure 10 Application servers
Implement Symantec Netbackup
Project size
No. of locations Head Office
No. of seats 500
Project size 12 man months
Technical EnvironmentHardware equipment/standard software
IBM Server, Vmware Esxi , Vsphere 5.5, SAN IBM V3700, IBM X3650M4 server
OS Platforms Windows Server 2012 Ent, Windows Server 2008System Software SQL 2012, VMWareApplication model Client/serverDatabase SQL Server
Group Size 15 people2 Project Name Migration of SharePoint 2007 to SharePoint 2013
Customer Bedok, SingaporeDuration Nov 2013 to Jan 2014Project Position Team LeaderProject Description SharePoint 2007 to SharPoint 2013Tasks Installing Exchange 2007, 2013 servers (on Lab and Production)
o AD preparationo Install and configure 02 SP2013 Front Ent servers
with NLBo Install and configure 02 SP2013 Search serverso Install and configure 02 SP2013 Application servers
Migrate current SP2007 to SP2013
Project size
No. of locations Head Office (Bedok Singapore )
No. of seats 4000+ Seats
Project size 4 man months
Technical EnvironmentHardware equipment/standard software
HP Server, VMware
OS Platforms Windows Server 2012 Ent, Windows Server 2008System Software SharePoint 2007, SharePoint 2013, SQL 2008, VMWareApplication model Client/server
Page 5
PROJECTS INVOLVED
No Projects DescriptionDatabase SQL Server
Group Size 6 people
3 Project Name Implement website and application for Ministry Of Commerce Cambodia
Project PositionSenior SharePoint consultant, SP Administrative and workflow development
Tasks
- SharePoint Infrastructure Design, Implement and Administrative- Consultancy the functionalities of SharePoint 2010 and custom-
ize SP2010 for the website- Implementing SP workflow for application- Developing Infopath form for report
Project DescriptionsCustomer for Ministry Of Commerce CambodiaProject Target - Implementing the website and application for MOCYear 2013Project SizeProject size 12 man monthsNo.of locations Pnom Penh, CambodiaNo. of engineers 20 engineersNo. ofend users 10000Technical EnvironmentHardware equipment IBM, DS8700, TS3310.OS Platforms Microsoft Windows 2008
System Software
- VMware ESX 4.1- SharePoint 2010- Microsoft Windows Server 2008 Enterprise R2
Database SQL Server 2008,4 Project Name DR for Ministry Of Finance
Project Position Architecture
Tasks
- Design, implement backup solution for DRC using TSM (Tivoli Storage Manager)
- Design infrastructure for DRC- Virtualization of Storage, Servers, Network for DRC
Project DescriptionsCustomer Ministry Of Finance VietnamProject Target - Performing backup solution of DRC using IBM TSM
Year 2013-2014Project SizeProject size 12 man monthsNo.of locations Hanoi, Ho Chi Minh and 61 provincesNo. of engineers 15 engineersNo. ofend users 15000Technical EnvironmentHardware equipment IBM, DS8700, TS3310.OS Platforms Microsoft Windows 2008
Page 6
PROJECTS INVOLVED
No Projects Description
System Software
- VMware ESX 4.1- Microsoft Windows Server 2008 Enterprise R2- IBM TSM 6.4
Database SQL Server 2008, Oracle 10G5 Project Name IT & Infrastructure Upgrading for Bank Of Industry Nigeria (BOI)
Project Position Project Manager & Architecture
Tasks
- Virtualization of 24 servers running on Windows Server 2008 R2 using VMware ESX 4.1
- Design, implement and Migrate from Active Directory 2003 to 2008 R2
- Design, implement and Migrate from Exchange 2003 to Ex-change 2010 DAG
- Design, implement and customize SharePoint 2010 for BOI’s in-ternal use
- Design, implement and customize Microsoft Dynamic CRM 2011 for BOI
- Training on Job for BOI’s IT teamProject DescriptionsCustomer Bank Of Industry Nigeria (BOI)
Project Target
- Performing all IT upgrading: AD, Exchange, SharePoint, Virtual-ization, and CRM for BOI.
- Performing actual mail migration from Exchange 2003 to Ex-change 2010 DAG
- Providing the knowledge transfer and training on job for BOI’s IT staff.
Year 2011-2012Project SizeProject size 12 man monthsNo.of locations Head office and 06 branches in NigeriaNo. of engineers 08 engineersNo. ofend users 500Technical EnvironmentHardware equipment HP, Quanta server, CiscoOS Platforms Microsoft Windows 2008
System Software
- VMware ESX 4.1- Microsoft Windows Server 2008 Enterprise R2- Exchange Server 2010 Sp1- SharePoint 2010- MS Dynamics CRM 4.0
Database SQL Server 2008
6 Project Name Implementation the Server’s operation and performance monitoring solution
Project Position System EngineerTasks - Install SQL database and SCOM 2007
- Configure the monitoring exchange with SCOMProject DescriptionCustomer Vietnam Mobile Service
Project Target Design and deploy System Center Operation Manager to monitor the servers’ operations and performance.
Page 7
PROJECTS INVOLVED
No Projects DescriptionYear 2011
Project SizeNo. of Engineers 3No. of locations 5 centers
Technical EnvironmentOS Platforms Windows Server 2003 and Windows Server 2008
Database SQL Server 2008
System Software System Center Operation Manager 2007
7 Project Name Implementation Monitoring system for Main ServersProject Position Technical operational specialistTasks - Install SQL database and SCOM 2007
- Add Management pack and configure roles in SCOMProject DescriptionCustomer Vietnam’s General Department of TaxationProject Target Implement the monitoring system for servers’ operations & performanceYear 2010Project SizeNo. of Location 10 branchesNo. of Engineers 5Project SizeOS platform Windows Server 2003 and Windows Server 2008Database SQL server 2005Software System Center Operation Manager
8 Project Name Mail migration from Domino Server to Exchange 2007Project Position Team leader
Tasks
- Design and deploy Exchange 2007 Server CCR- Migration and coexistence tools deployment (Quest Migrator,
Microsoft Transporter Suite, CMTC)- Migration service and coexistence service for all the end-users
Group size 03Project DescriptionsCustomer Vietnamese - Russian joint venture bank - VRBProject Target Migrate Lotus Domino to Microsoft Exchange 2007 for 1500 usersYear 2010Project SizeProject size 12 man monthsNo. of locations 01 Hanoi Head OfficeNo. of engineers 03No. of end users 1500Technical EnvironmentHardware equipment IBMOS Platforms Microsoft WindowsSystem Software - Microsoft Windows Server 2008 Enterprise Edition
- Exchange Server 2007- Microsoft transporter suite- CMT Co-existence 1.8.1 & 2.0.5- Quest Notes Migrator version 4.1
Page 8
PROJECTS INVOLVED
No Projects Description- SQL 2005 STD- Lotus Domino Server- Lotus note client
9 Project Name Wong Partnership Exchange 2007 migration - SingaporeProject Position Technical Leader
Tasks
Installing Exchange 2007 servers (on Lab and Production)o AD preparationo Install and configure 02 Hub&Cas servers with NLBo Install and configure 02 mailbox CCR serverso Install and configure 02 Edge Transport serverso Install and publish OWA in 02 ISA 2006 server
(NLB)o Install Forefront securityo Install and configure Data Protection Manager
(DPM) 2007 for mailbox backup Configure the mail flow, High Availability, Public folder, Routing
group connector with co-existing Exchange 2003 system. Write the script move mailbox. Migrate mailbox from Exchange 2003 to Exchange 2007 system Install and configure SCCM 2007 Server Install outlook 2007 for 500 clients using SCCM Decommission Exchange 2003 Knowledge transfer to IT Team
Project DescriptionCustomer Wong Partnership, SingaporeProject Target Exchange 2007 migrationYear 2009Project sizeProject size 4 man monthsNo. of locations 02 in SingaporeNo. of engineers 04No. of end users 600Technical EnvironmentHardware equipment HP Server DL360, DAS, Firewall, Tumbleweed, Bluecoat.OS Platforms Microsoft Windows
System SoftwareExchange 2007 SP1, DPM 2007, ISA 2007, ISA2006, SCCM 2007, Outlook 2007 client, Forefront Security, Symantec Endpoint...
Database SQL ServerProgramming/development tools
VB scripts to run migration mailboxes
10 Project Name Design & Installation Email system for Luvina Software CompanyProject Position Team LeaderProject DescriptionsCustomer Luvina Software CompanyProject Target Install Exchange 2003 FE &BE and migrate dataYear 2008-2009Project SizeProject size 1 man-monthNo. of locations 01 Head OfficeNo. of engineers 02
Page 9
PROJECTS INVOLVED
No Projects DescriptionNo. of end users 150Technical Environment
Hardware equipmentIBM x346, HP DL380G5 Server, Cisco Router 2811, Cisco 2960Switch, Pix501 Firewall
OS Platforms Microsoft WindowsSystem Software Exchange 2003, ISA 2006, Bright mailDatabase SQL Server
11 Project Name Upgrade Email System for Vietnam Petrolimex CorporationProject Position Team member
Task
- Install Windows Server 2003- Install & configure Exchange 2007, ISA 2006, and Symantec
Anti-Virus.- Migrate data from Exchange 2003 to Exchange 2007
Project DescriptionsCustomer Vietnam Petrolimex CorporationProject Target Upgrade from Exchange 2003 to Exchange 2007 CCR and migrate dataYear 2007Project SizeProject size 20 man monthsNo. of locations 01 Head OfficeNo. of engineers 05No. of end users 3000Technical EnvironmentHardware equipment IBM Server, Cisco Router, Switch, FirewallOS Platforms Microsoft WindowsSystem Software Exchange 2007, ISA 2006Database SQL Server
12 Project Name Design, implement network and system for FPT-ISProject Position Team Leader
Task
Analyzing, designing and implementing all IT systems, including network, system security, IP phone, network and system monitoring.Network: Design and Configure LAN, WAN, Configure Cisco Routers, Switches, Firewall, Wi-Fi... Implement Cisco IP phones for 800 clients
System: Install and configure Windows 2003 Server, AD , WINS, DHCP,
DNS services Design and configure Domain Policy Install and configure SMS 2003 Install and configure Norton Anti-Virus Corporate Edition
System.Application: Migrate from SharePoint 2003 to SharePoint 2007 Install Microsoft CRM 3.0 Install SQL 2000 Server
Install and configure IIS, Web applicationProject DescriptionsCustomer FPT Information System Corp.Project Target Design and Deployment System Infrastructure for FPT-ISYear 2006-2007
Page 10
PROJECTS INVOLVED
No Projects DescriptionProject SizeProject size 6 man monthsNo. of locations 01 Head Office + 03 BranchNo. of engineers 04No. of end users 1200Technical EnvironmentHardware equipment IBM, HP Server, Cisco Router 2821, Switch Cisco 3560, FirewallOS Platforms Microsoft WindowsSystem Software Exchange 2003, ISA 2004, SharePoint 2003, SQL Server 2000Database SQL Server
13 Project Name Information Security: ISMS Project (Information Security Management System – ISO 27001)
Project Position Team member
Task- Designing & implementing all IT requirements for the project.- Responsible for writing Network and System Security policy doc-
uments following the project requirements.Group size 20 peopleProject DescriptionsCustomer FPT Information SystemProject Target Design and Deployment ISMS infrastructure for FPT-ISYear 2006Project SizeProject Size 40 man monthsNo. of locations 01 Head OfficeNo. of engineers 15No. of end users 1200Technical Environment
Hardware equipmentIBM x365,X225, HP DL380 Server, Cisco Router 2821, Cisco 2960 Switch, Netscreen 25 Firewall
OS Platforms Microsoft Windows
System SoftwareExchange 2003, ISA 2006, SMS 2003, MOM, SharePoint 2003, SQL Server 2000
Database SQL Server
REFEREES
Mr. Wale Wajisebutu – Vice Executive Chairman of 21st Century Technologies
Page 11
Certificates:
Cisco CCNP:
Page 12