Cairo University Faculty of Engineering Public Works Department Highway and Traffic Engineering PBW 401 2013 - 2014 4. Horizontal Alignment : Dr. Dalia Said, Assistant Professor, Highway and Traffic Engineering Civil Engineering Department, Cairo University, [email protected] 4. Horizontal Alignment : Superelevation

Highway and Traffic Engineering PBW 401

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Highway and Traffic Engineering PBW 401

Cairo University

Faculty of Engineering

Public Works Department

Highway and Traffic Engineering

PBW 401

2013 -2014

4. Horizontal Alignment :

Dr. Dalia Said,

Assistant Professor, Highway and Traffic Engineering

Civil Engineering Department,

Cairo University,

[email protected]

4. Horizontal Alignment :

Superelevation

Page 2: Highway and Traffic Engineering PBW 401

Horizontal Alignment

–Minimum radius of a circular horizontal curve is governed by:

1.

2

PIARC 2003

Page 3: Highway and Traffic Engineering PBW 401

Max Superelevation (e)

•Controlled by 4 factors:

1.Weather conditions in area (amount of ice and snow)

2.Type of terrain (flat, rolling, mountainous)

3.Highway Location (rural or urban)

4.Frequency of slow moving vehicles (may be affected by

higher superelevation rates

33

higher superelevation rates

–Highest in common use = 10%, 12% with no ice and snow

–8% is logical maximum to minimize slipping by stopped

vehicles, considering snow and ice

–For consistency a single rate within a project or on a

highway is used

Page 4: Highway and Traffic Engineering PBW 401

Horizontal Alignment

–Minimum radius of a circular horizontal curve is governed by:

Sight Distance (S)

m

4

R

Centerline of

Inside Lane

Obstruction

Line of Sight

R

Page 5: Highway and Traffic Engineering PBW 401

–Note: Object can have a constant height (m= constant) or a variable

height

mm

5

m

CL of inside lane

CL of inside lane

mhav

Page 6: Highway and Traffic Engineering PBW 401

–Spiral (transition) curves are curves with changing radii, and are

placed between tangents and circular curves or between two

successive circular curves

R = Rc

R = ∞ ∞∞∞

TS

C

Spiral (transition) curves

6

TS

SC

CS

ST

PI

L

Lc

L

Page 7: Highway and Traffic Engineering PBW 401

Advantages

1.Provides a vehicle path that gradually increases or decreases

the radial force as the vehicle enters or leaves a curve. (lateral

force increases and decreases gradually)

2.Provides location for superelevation runoff (not part on

tangent/curve)

3.Aesthetic

Spiral Curve

7

7

3.Aesthetic

Page 8: Highway and Traffic Engineering PBW 401

–Common form for spiral curves:

, or

R ls= A2 (A= spiral parameter)

lsR

1∝

Spiral (transition) curves

8

Page 9: Highway and Traffic Engineering PBW 401

9

TAC (1999)

Page 10: Highway and Traffic Engineering PBW 401

1.Limit rate of change of centripetal acceleration (maximum = 1 to 3 ft/sec2/sec)

–(V= km/h, R= m, C= 0.6)

2.Provide enough length of superelevationrunoff

3.Add to the highway aesthetics

minimum spiral parameter demand governed by

Spiral Length

10

minimum spiral parameter demand governed by

comfort, superelevation and aesthetic criteria in

relation to curve radii for a given design speed

radius (m)

spiral parameter

parameter based on comfort

Page 11: Highway and Traffic Engineering PBW 401

–For all these criteria: get Afrom the design tables

–Then: ls= A2/R

11

Page 12: Highway and Traffic Engineering PBW 401

12

Page 13: Highway and Traffic Engineering PBW 401

–Highway cross section on straight segments is “normal crown”

–On curved segments, it is “superelevated”

–To change a normal crown section into a superelevatedsection, a

superelevationrunoff length is required

–Superelevationrunoff length equals the length of the spiral curve

–If no spiral curve is used, superelevationrunoff length is

Development of Superelevation

13

–If no spiral curve is used, superelevationrunoff length is

distributed as 67% on tangent and 33% on curve

–Superelevationcan be attained by revolving section about:

• • •

Page 14: Highway and Traffic Engineering PBW 401

Superelevation

Page 15: Highway and Traffic Engineering PBW 401

Road Plan View

Superelevation

Road Section View

CL

2%

2%

Page 16: Highway and Traffic Engineering PBW 401

Road Plan View

Superelevation

Road Section View

CL

2%

-0.0%

Page 17: Highway and Traffic Engineering PBW 401

Road Plan View

Superelevation

Road Section View

2%

-2%

CL

Page 18: Highway and Traffic Engineering PBW 401

Road Plan View

Super elevation

Road Section View 4%

-4 %

CL

%

Page 19: Highway and Traffic Engineering PBW 401

Road Plan View

Superelevation

Road Section View 2%

-2%

C L

Page 20: Highway and Traffic Engineering PBW 401

Road Plan View

Superelevation

Road Section View 2%

C L-0.0%

Page 21: Highway and Traffic Engineering PBW 401

Superelevation

Road Section View

2%

C L2%

Road Plan View

Page 22: Highway and Traffic Engineering PBW 401

CL

O.E

SC

Rotation about centerline

22

CL

I.E

I.EO.E

Page 23: Highway and Traffic Engineering PBW 401

CL

O.E

Rotation about centerline

23

CL

I.E

Superelevation runoff

Tangent runout

I.EO.E

Page 24: Highway and Traffic Engineering PBW 401

Maximum Values of ∆ ∆∆∆s of relative pavement profile

24

Page 25: Highway and Traffic Engineering PBW 401

Tangent Runout: Length of roadway needed to accomplish a

change in outside-lane cross slope from normal cross slope rate to

zero

Superelevation runoff: Length of roadway needed to accomplish a

change in outside-lane cross slope from 0 to full superelevation or

25

vice versa

Page 26: Highway and Traffic Engineering PBW 401

Rotation about inside edge

Cl

O.E

26

Cl

O.EI.E

I.E

Superelevation runoff

Tangent runout

Page 27: Highway and Traffic Engineering PBW 401

Axis of Rotation for Roads with Median

Case I: whole travelled way is

superelevated

Case II: two travelled ways are

rotated separately around median

27

rotated separately around median

edge

Case III: Two travelled ways are

treated separately