Highway 407 East Phase 1
DESIGN AND CONSTRUCTION REPORT #5
Segment A2 - Grading, Drainage, Paving and Structures
610706-00-6D-RR-CGP-R005_01
September 2013
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 1 of 127 610706-00-6D-RR-CGP-R005 01
Public Record Viewing Locations
(MOE file number EA-02-07)
This document can be electronically accessed at: 38Thttp://www.407eastphase1.ca38T
Copies can also be found at public viewing locations listed below:
City of Pickering: Clerks Department 1 The Esplanade, Pickering Tel: 905-420-2222
Pickering Public Library - Main Branch 1 The Esplanade, Pickering Tel: 905-831-6265
Town of Ajax: Clerk‟s Department 65 Harwood Ave. S., Ajax Tel: 905-683-4550
Ajax Public Library - Main Branch 55 Harwood Ave. S., Ajax Tel: 905-683-4000
Town of Whitby: Clerk‟s Department 575 Rossland Rd. E., Whitby Tel: 905-668-5803
Whitby Public Library - Main Branch 405 Dundas St. W., Whitby Tel: 905-655-6531
City of Oshawa: Clerk‟s Department 50 Centre St. S., Oshawa Tel: 905-436-3311
Oshawa Public Library - Main Branch 65 Bagot St., Oshawa Tel: 905-579-6111
Regional Municipality of Durham: Clerk‟s Department 605 Rossland Rd. E., Whitby Tel: 905-668-7711
407 East Development Group: 407 East Phase 1 Project Office 400 Dundas St. E., Unit 2, Whitby Tel: 1- 855-463-3109
Ministry of Transportation: Major Project Office, Building "D", 7th Floor 1201 Wilson Ave., Downsview Tel: 416-235-3749
Ministry of Environment: Environmental Approvals Branch 2. St. Clair Ave. W., Floor 12A, Toronto Tel: 1-800-461-6290
En français: Ce document hautement spécialisé n'est disponible qu'en anglais en vertu du règlement 411/97, qui en exempte l'application de la Loi sur les services en français. Pour de l'aide en français, veuillez communiquer avec le ministère des Transports, Bureau des services en français au: 905- 704-2045 ou 905-704-2046.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 2 of 127 610706-00-6D-RR-CGP-R005 01
List of Acronyms
407ECGP 407 East Construction General Partnership
407EDG 407 East Development Group
BMP Best Management Practices
CEAA Canadian Environmental Assessment Act
CLOCA Central Lake Ontario Conservation Authority
CP Rail Canadian Pacific Railway
CVP Community Value Plan
DCR Design and Construction Report
DFO Fisheries and Oceans Canada
DSS Designated Substance Surveys
EA Environmental Assessment
EAC 407 East Advisory Committee
Enbridge Enbridge Gas Distribution/Enbridge Pipeline Inc.
ESA Endangered Species Act, 2007
ESCP Erosion and Sediment Control Plan
HADD Harmful Alteration, Disruption or Destruction (of Fish and/or Fish Habitat)
IO Infrastructure Ontario
MNR Ministry of Natural Resources
MOE Ontario Ministry of the Environment
MTAG Municipal Technical Advisory Group
MTCS Ministry of Tourism, Culture and Sport
MTO Ontario Ministry of Transportation
NPC Noise Pollution Control
OEAA Ontario Environmental Assessment Act
PIC Public Information Centre
Project Highway 407 East Phase 1 Project
RAG Regulatory Agencies Group
ROW Right-of-Way
SAR Species at Risk
SWM Stormwater Management
TRCA Toronto and Region Conservation Authority
WDL West Durham Link
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 3 of 127 610706-00-6D-RR-CGP-R005 01
TABLE OF CONTENTS
P.1. PROJECT BACKGROUND AND OVERVIEW ................................................................ 7
P.1.1. 407 East Transportation Corridor ........................................................................ 8
P.1.2. Environmental Assessments ............................................................................... 8
P.1.3. Phased Implementation ....................................................................................... 8
P.1.4. Project Delivery ..................................................................................................11
P.1.5. Current Design Build ..........................................................................................11
P.2. PROJECT ORGANIZATION & IMPLEMENTATION ..................................................... 13
P.2.1. 407 East Development Group ............................................................................13
P.2.2. 407 East Construction General Partnership .......................................................13
P.3. ENVIRONMENTAL ASSESSMENT PROCESS ............................................................ 15
P.3.1. Ontario Environmental Assessment Act .............................................................15
P.3.1.1. Ministry of Transportation Class Environmental Assessment ................ 16
P.3.2. Canadian Environmental Assessment Act ..........................................................17
P.3.3. Other Provincial/Federal Approvals ....................................................................18
P.4 PURPOSE OF DESIGN AND CONSTRUCTION REPORTS (DCR) ............................. 19
P.5 OVERALL CONSULTATION PLAN ............................................................................. 20
P.5.1. Engagement of Stakeholders .............................................................................21
P.6. PLAN FOR HIGHWAY DESIGN, BUILD AND DCR SUBMISSION .............................. 24
1. OVERVIEW OF PROPOSED WORK ACTIVITIES ........................................................ 29
1.1. Structures ...........................................................................................................29
1.2. Drainage, Grading, and Stormwater Management Ponds...................................31
1.2.1. Stormwater Management Ponds........................................................... 31
1.3. Other Related Works ..........................................................................................32
2. CONSULTATION PROCESS ........................................................................................ 41
2.1. Government Agencies and Municipalities ...........................................................42
2.1.1. Municipal Technical Advisory Group ..................................................... 42
2.1.2. 407 East Advisory Committee ............................................................... 44
2.1.3. Regulatory Agency Group..................................................................... 45
2.1.4. Utilities Coordination ............................................................................. 47
2.2. Public and Stakeholder Participation ..................................................................47
2.2.1. Notifications .......................................................................................... 48
2.2.2. Public Information Centre #5 ................................................................ 50
2.3. First Nations Consultation ..................................................................................55
2.4. Public and Stakeholder Input to Detail Design ....................................................56
3. DETAILED DESCRIPTION OF THE RECOMMENDED DESIGN ................................. 57
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 4 of 127 610706-00-6D-RR-CGP-R005 01
3.1. Consideration of Design Alternatives ..................................................................57
3.1.1. Lynde Creek Tributary „A‟, Water Crossing Site 16 (Structure M22) ...... 57
3.1.2. Lynde Creek Tributary „G‟, Water Crossing Site 19 (Structures M35 and M36) ..................................................................................................... 58
3.1.3. Lynde Creek Tributary „D‟, Water Crossing Site 41B (Structure W30) ... 59
3.1.4. Highway 407 East Phase 1 Overpass at WDL E-S Ramp (Structure M31/M31A) ........................................................................................... 59
3.2. Highway 407 East Phase 1 Mainline and West Durham Link .............................60
3.2.1. Highway 407 East Phase 1 Mainline Cross-Section.............................. 60
3.2.2. West Durham Link Cross-Section ......................................................... 62
3.3. Structures ...........................................................................................................63
3.3.1. Lynde Creek Tributary „A‟ Culvert, Structure M22 ................................. 63
3.3.2. Kinsale Road Underpass, Structure M23 .............................................. 63
3.3.3. Lake Ridge Road Underpass, Structure M24 ........................................ 63
3.3.4. Lake Ridge Road Loop Ramp N-E Overpass at WDL Ramp W-S, Structure M29 ....................................................................................... 64
3.3.5. WDL S-W Ramp Underpass, Structure M30 ......................................... 64
3.3.6. Highway 407 East Phase 1 Overpass at WDL E-S Ramp, Structure M31 ............................................................................................................. 64
3.3.7. Lake Ridge Ramp E-N/S Overpass at WDL Ramp E-S, Structure M31A ............................................................................................................. 65
3.3.8. Coronation Road Underpass, Structure M32 ........................................ 65
3.3.9. Coronation Road Underpass at WDL Ramp E-S, Structure M33 .......... 65
3.3.10. Coronation Road Underpass at WDL Ramp S-E, Structure M34 .......... 65
3.3.11. Lynde Creek Tributary „G‟ Bridge, Structure M35 .................................. 66
3.3.12. WDL Ramp E-S Bridge over Lynde Creek Tributary „G‟, Structure M36 66
3.3.13. Lynde Creek Tributary „H‟ Bridge, Structure M37 .................................. 66
3.3.14. WDL Ramp E-S Overpass at Highway 7, Structure W26 ...................... 67
3.3.15. WDL Ramp S-W Overpass at Highway 7, Structure W27 ..................... 67
3.3.16. WDL Ramps S-W and S-E Bridge over Lynde Creek Tributary „D‟, Structure W30 ....................................................................................... 67
3.4. Drainage Systems and Stormwater Management ..............................................67
3.4.1. Highway 407 East Phase 1 Mainline - West of the Halls Road ............. 68
3.4.2. Highway 407 East Phase 1 Mainline - WDL Interchange and Eastward 69
3.4.3. West Durham Link ................................................................................ 69
3.4.4. Stream Realignments ........................................................................... 70
3.5. Utility Relocations ...............................................................................................70
3.6. Construction Staging, Traffic Management, Road Closures and Detours ...........72
3.6.1. Lake Ridge Road. ................................................................................. 72
3.6.2. Kinsale Road ........................................................................................ 72
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 5 of 127 610706-00-6D-RR-CGP-R005 01
3.6.3. Coronation Road .................................................................................. 73
3.6.4. Highway 7/Winchester Road ................................................................. 73
3.6.5. Halls Road and Country Lane - Permanent Road Closures .................. 73
4. ENVIRONMENTAL IMPACTS, PROPOSED MITIGATION AND COMMITMENTS ...... 74
4.1. Natural Environment ...........................................................................................74
4.1.1. Fish and Fish Habitat ............................................................................ 74
4.1.2. Groundwater ......................................................................................... 82
4.1.3. Vegetation ............................................................................................ 84
4.1.4. Wildlife and Wildlife Habitat .................................................................. 87
4.1.5. Surface Water Protection/Erosion and Sediment Control ...................... 93
4.1.6. Designated Environmentally Significant Features ................................. 96
4.1.7. Species at Risk ..................................................................................... 97
4.2. Socio-Economic Environment .......................................................................... 101
4.2.1. Provincial and Municipal Policies and Plans ....................................... 101
4.2.2. Community Value Plan ....................................................................... 102
4.2.3. Land Use ............................................................................................ 103
4.2.4. Traffic Staging and Management ........................................................ 107
4.2.5. Noise and Vibration ............................................................................ 108
4.2.6. Air Quality ........................................................................................... 110
4.2.7. Property Contamination and Waste Materials Management ............... 113
4.2.8. Landscaping ....................................................................................... 117
4.3. Cultural Environment ........................................................................................ 118
4.3.1. Archaeological Resources .................................................................. 118
4.3.2. Built Heritage Resources and Cultural Landscapes ............................ 121
4.4. Summary of Environmental Effects, Proposed Mitigation and Commitments to Further Work ............................................................................................................... 123
5. PROJECT MONITORING ........................................................................................... 125
5.1. 407EDG Obligations ......................................................................................... 125
5.2. Ontario Ministry of Transportation Obligations .................................................. 126
5.3. Environmental Assessment Compliance Monitoring ......................................... 126
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 6 of 127 610706-00-6D-RR-CGP-R005 01
LIST OF TABLES Table P.1: Other Permits and Approvals Required Prior to Construction .............................19 Table P.2: Overall Plan for Design and Construction Reports and PICs ..............................26 Table 2.1: Summary of Public and Stakeholder Comments from PIC #5 .............................53
LIST OF FIGURES Figure P-1: Highway 407 East Phase 1 and 2 .......................................................................10 Figure P-2: 407 East Development Group ............................................................................14 Figure P-3: Overview of Highway 407 EA Process ...............................................................16 Figure P-4: Highway 407 East Phase 1 Key Plan .................................................................25 Figures 1-1: Highway 407 East Phase 1 - Segment A2 (A2-1 to A2-6) ...................................34 Figure 3-1: Typical Cross Section – Highway 407 East Phase 1 Mainline ............................61
APPENDICES 38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38T38TAppendix A Design Drawings
Appendix A-1 Civil Design Drawings Appendix A-2 Structural Design Drawings
Appendix B Consultation Materials
Appendix B-1 Notice of Public Information Centre Appendix B-2 Public Information Centre Display Boards Appendix B-3 Submitted Comment Forms Appendix B-4 Notice of Submission
Appendix C Summary of Environmental Effects, Proposed Mitigation and
Commitments to Further Work Appendix C-1 Summary of EA Commitments and Compliance Monitoring Appendix C-2 EA Commitments and Assurances Appendix C-3 Environmental Effects Monitoring Commitments Appendix C-4 MOE Notice of Approval Conditions
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 7 of 127 610706-00-6D-RR-CGP-R005 01
PREFACE
P.1. PROJECT BACKGROUND AND OVERVIEW
In 2007 the Ontario Ministry of Transportation (MTO) in consultation with the Region of Durham,
and surrounding municipalities initiated the 407 East Individual Environmental Assessment and
Preliminary Design Study (August, 2009) (“407 East Transportation Corridor EA”) under the
Ontario Environmental Assessment Act. This study was intended to support the transportation
objectives of the provincial Growth Plan for the Greater Golden Horseshoe by providing for the
efficient movement of people and goods within the study area.
The need for an east-west freeway, north of Toronto and connecting to Highway 35/115 in
Clarington was initially considered in the 1950s and 1960s, and the 407 transportation corridor
was included in the Parkway Belt West Plan in 1978. The existing Highway 407 corridor
originates at the Queen Elizabeth Way in the City of Burlington and terminates at Brock Road in
the City of Pickering. To date, planning decisions related to land use and transportation have
included the easterly extension of the Highway 407 corridor. Various planning studies were
previously undertaken to determine the location of particular segments of the 407 corridor as it
exists today. A recommendation for the inclusion of a dedicated right-of-way (ROW) for transit
as part of the 407 East Transportation Corridor through Durham Region was also made
previously through a variety of studies.
Key areas addressed in the 407 East Transportation Corridor EA included:
To provide a new transportation corridor to address transportation capacity deficiencies;
To provide a comprehensive freeway network through Durham Region to improve
mobility, network flexibility and provide an alternative emergency/detour freeway route in
Durham Region;
To offer relief to traffic congestion on local roads, as the freeway will provide an alternate
route for through traffic;
To meet infrastructure needs to address continued population and employment growth in
Durham Region and eastern Greater Toronto Area; and
To allow for better and more efficient transportation and flow of goods between Toronto
and eastern Ontario.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 8 of 127 610706-00-6D-RR-CGP-R005 01
P.1.1. 407 East Transportation Corridor
The 407 East Transportation Corridor will extend Highway 407 by 50.0 kilometres (km) from
Brock Road to Highway 35/115. This includes 2 north-south links of 10.0 km connecting the
Highway 401 to the proposed 407 Transportation Corridor, with 1 link in West Durham (Whitby)
and the other link in East Durham (Clarington).
The ultimate design plan of includes:
Ten lanes from Brock Road to Harmony Road and 8 lanes from Harmony Road to the
East Durham Link;
Six lanes from the East Durham Link to Highway 35/115, 6 lanes on the West Durham
Link (WDL) and 6 lanes on the East Durham Link;
110.0 metre (m) highway ROW and 60.0 m transitway ROW. The highway component
includes provisions for High Occupancy Vehicle lanes for passenger vehicles;
Twenty interchanges, 14 road closures, 42 road crossings, 65 stormwater management
(SWM) ponds; and
Two highway maintenance facilities, 2 transitway maintenance facilities, 2 commercial
vehicle inspection facilities, 3 truck lay-bys along the links and 17 transitway stations.
P.1.2. Environmental Assessments
The 407 East Transportation Corridor EA was captured by both federal and provincial
environmental assessment (EA) legislation.
In June 2010, the Ontario Minister of the Environment (MOE), under the Ontario Environmental
Assessment Act (OEAA), granted approval (subject to conditions) of the 407 East
Transportation Corridor EA.
Shortly afterwards, in July 2011, the Federal Minister of the Environment, under the Canadian
Environmental Assessment Act (CEAA), approved the Comprehensive Study Report and made
a decision that the 407 Transportation Corridor is not likely to cause significant adverse
environmental effects with the implementation of appropriate mitigation measures.
P.1.3. Phased Implementation
The Highway 407 East Transportation Corridor will be implemented in phases by Infrastructure
Ontario (IO), in partnership with MTO (“the Province of Ontario”). Please refer to Figure P-1.
Phase 1 (“Highway 407 East Phase 1”, “the Project”) is scheduled to start early in 2013 and will
be completed by late 2015 and includes 32.0 km of highway from east of the Brock Road
interchange in Pickering to east of Harmony Road in Oshawa and the WDL.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 9 of 127 610706-00-6D-RR-CGP-R005 01
Phase 2 of the 407 East Transportation Corridor will be divided in 2 parts. Phase 2A from
Harmony Road to Taunton Road/East Durham Link is scheduled to be completed by 2017.
Phase 2B includes the section from Taunton/East Durham Link to Highway 35/115, and a 10.0
km north-south highway (East Durham Link) connecting Highway 407 East and Highway 401
and is anticipated to be completed in 2020.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 10 of 127 610706-00-6D-RR-CGP-R005 01
Figure P-1: Highway 407 East Phase 1 and 2
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 11 of 127 610706-00-6D-RR-CGP-R005 01
P.1.4. Project Delivery
The implementation of Highway 407 East Phase 1 will occur using an Alternative Finance and
Procurement delivery model. The Province of Ontario has awarded the rights to design, build,
finance and maintain the Project for a 30-year concession period to the 407 East Development
Group (407EDG). The Province of Ontario will retain control and ownership of the facility and
be responsible for the tolling rates and revenue.
Design, build, finance and maintain differs from traditional highway design-bid-build projects
because both the finalization of the design details and the construction of a project are carried
out simultaneously. The Highway 407 East Phase 1 is divided into strategic components and
work packages in a manner that allows early parts of the Project to go ahead with construction,
while latter parts of the Project are finalizing their design details. This method is advantageous
for larger construction projects with a short schedule and makes efficient use of resources to
support completion. The Highway 407 East Phase 1 will be a new multi-lane toll highway with
staged widening toward the ultimate development of a comprehensive freeway network through
Durham Region.
P.1.5. Current Design Build
The Highway 407 East Phase 1 design-build development stage encompasses transportation
layout, community features and environmental impact mitigation measures. Supporting
elements, such as drainage, stormwater management (SWM), lighting system and signage are
also considered.
Transportation Layout
The main line of the Highway 407 East Phase 1 is approximately 22 km long, with 7.4 km of 6-
lane east-west freeway from east of Brock Road to the WDL and 12.9 km of 4-lane east-west
freeway from WDL to east Harmony Road. Interchanges are found at Lake Ridge Road,
Baldwin Street (Highway 7/12), Thickson Road, Simcoe Street and Harmony Road.
The WDL is a 4-lane north-south freeway connecting Highway 407 and Highway 401 with
interchanges at Highway 407, Highway 7, Taunton Road, Dundas Street, Lake Ridge Road and
Highway 401.
The Highway 401 and WDL Interchange includes a 5.0 km realignment of Highway 401 (6-lane
freeway) from east of Salem Road to west of Henry Street, with an interchange at the realigned
Lake Ridge Road.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 12 of 127 610706-00-6D-RR-CGP-R005 01
Community Features
Considerations for community-focused features are identified in the Community Value Plan
(CVP) and include but are not limited to:
Enhanced corridor landscaping and aesthetic screening;
Noise mitigation measures;
Gateway features, signage;
Architectural enhancement of bridges;
Local heritage strategies (such as commemorative plantings, signage; adaptive resource
use);
Designated wildlife crossings and associated wildlife fencing;
Wetland restoration;
Trails and pathways; and
First Nations/community commemorative landscape and bridge architectural elements.
Environmental Impact Mitigation Measures
The EAs conducted for the Project concluded that environmental effects of the undertaking can
be appropriately prevented, mitigated or remedied. Mitigation will include noise mitigation,
SWM and snowdrift control among other identified measures.
Vegetation Restoration will be undertaken to replace the loss of forests and wetlands within the
Project lands at 1:1 compensation ratio. The objective of the vegetation compensation will be to
restore and/or enhance wildlife and ecological linkages among vegetation communities and
promote the re-establishment of self-sustaining terrestrial and aquatic environments, including
restoration of Species at Risk (SAR) habitat. In addition, environmental conservation,
enhancement and compensation measures will include:
SAR permit requirements, including implementation and monitoring of Overall Benefit
Plans for recovery of endangered species (Butternut, Redside Dace, Bobolink, Eastern
Meadowlark and Barn Swallow);
Mitigation and documentation of historical First Nations and early settlement sites;
Remediation of contaminated soil;
Implementation of terrestrial mitigation measures (Edge Management Plans, Invasive
Species Management Plan, etc.); and
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 13 of 127 610706-00-6D-RR-CGP-R005 01
Design and implementation of fish habitat compensation plans using natural channel
principles for stream realignment designs to ensure no net loss of fish habitat, and where
feasible, overall enhancement.
Public Participation
The public has an important role to play during the design and construction phases of the
Project. Community input to detail designs required for construction will be solicited at Public
Information Centres (PIC) in 2012 and 2013. Questions, feedback and comments are always
welcome.
P.2. PROJECT ORGANIZATION & IMPLEMENTATION
On March 21, 2012, a fixed-price contract between the Province and the 407EDG to design,
build, finance and maintain the Highway 407 East Phase 1 was signed. This partnership is
committed to ensuring that mitigation measures and compliance monitoring are implemented
relative to the commitments made during the EA process and in subsequent detail design
phases.
P.2.1. 407 East Development Group
The 407EDG team includes designers, builders, financiers and operators who will complete the
Project. 407EDG has assumed the responsibility for delivering and complying with all
obligations, commitments, and responsibilities stated in the approved provincial and federal
EAs, applicable permits, authorizations and approvals that are required to execute the Project.
407EDG consists of 2 companies, Cintra Infraestructuras S.A., a division of Ferrovial S.A, and
SNC-Lavalin Inc. (through its division, SNC-Lavalin Capital).
P.2.2. 407 East Construction General Partnership
To design and build the Highway 407 East Phase 1, 407EDG has formed and established a
“Design-Build Contractor” in the form of a “Joint Venture” company referred to as the 407 East
Construction General Partnership (407ECGP). 407ECGP will act as the designers and builders
of the Project and are directly responsible for executing construction and will manage the
design. 407ECGP consists of a fully integrated team of 2 equity members SNC-Lavalin Inc.
through its SNC-Lavalin Construction Division and Ferrovial Agroman S.A. This relationship
ensures the highest levels of quality, innovation, and safety for the design and construction of
the Project.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 14 of 127 610706-00-6D-RR-CGP-R005 01
407ECGP has retained a design team consisting of 3 companies, Jansen & Spaans
Engineering Inc.; AIA Engineers Limited; and SNC-Lavalin Environment (a Division of SNC-
Lavalin Inc.). These 3 companies are responsible for the overall highway design, including road
and pavement design, structures, utilities, illumination, traffic management, environmental
protection and compensation, and components of the CVP.
Figure P-2 outlines the team structure.
Figure P-2: 407 East Development Group
Cintra is one of the world’s largest private developers of highway infrastructure with more than 40 years experience in development and managing highways.
SNC-Lavalin Inc. is one of the leading engineering and construction groups in the world, and major player in the ownership of infrastructure and in the provision of operation and maintenance services.
Ferrovial Agroman is the company heading up the construction division of Ferrovial S.A. and is involved in all areas of construction. Within the context of civil works, the company designs and builds all types of infrastructures such as roads, railways, hydroelectric works and industrial projects.
SNC-Lavalin Construction is a world leader in engineering and construction projects, driven by its overall objective of creating value, in the constant respect of quality, environment and health & safety.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 15 of 127 610706-00-6D-RR-CGP-R005 01
P.3. ENVIRONMENTAL ASSESSMENT PROCESS
The 407 East Transportation Corridor Study was undertaken in accordance with the
requirements for an Individual EA under the OEAA and the requirements of the CEAA, which
are described in the subsequent subsections. Both EA processes were coordinated in
accordance with the Canada-Ontario Agreement on Environmental Assessment Cooperation.
MTO and 407EDG are committed to ensuring that compliance monitoring of commitments made
during both the EAs and subsequent phases, including those related to conditions of permits
and approvals, are adhered to. 407EDG in partnership with MTO is maintaining consultation
efforts to keep interested parties and First Nations informed of activities, future design stages,
and Project implementation.
P.3.1. Ontario Environmental Assessment Act
OEAA Purpose
The purpose of the OEAA is to protect and conserve Ontario‟s environment by ensuring that
projects subject to the Act follow a planning process leading to environmentally sound decision-
making. The intent is to predict the environmental effects of proposed initiatives or projects
before they are carried out. A key component of the OEAA and good planning is to ensure that
reasonable and meaningful consultation opportunities for members of the public, agencies, First
Nations and other key stakeholders are provided throughout the process.
EA Project Phases
The 407 East Transportation Corridor EA followed the requirements of the OEAA under the EA
process (Section 6.1 (2) of the OEAA), with the framework for this study set out in the 407 East
EA terms of reference approved by the MOE in January, 2005.
Six main Project phases were examined, as follows:
Project Initiation;
Transportation Problems and Opportunities;
Transportation Alternatives (Alternatives to the Undertaking);
Route Alternatives (Alternative Methods);
Preliminary Design; and
EA Report.
An overview of the EA study process is shown in Figure P-3.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 16 of 127 610706-00-6D-RR-CGP-R005 01
Figure P-3: Overview of Highway 407 EA Process
Individual Environmental Assessment Report
The 407 East Transportation Corridor EA, was completed in August 2009 and submitted to the
MOE for review and approval. Approval under the OEAA was granted by the Minister of the
Environment in June 2010. The 407 East Individual Environmental Assessment and Preliminary
Design Study (August, 2009) (“EA report”), can be accessed at www.highway407east.com.
P.3.1.1. Ministry of Transportation Class Environmental Assessment
The MTO Class Environmental Assessment for Provincial Transportation Facilities 2000 (MTO
Class EA) is an approved planning document under the OEAA that defines groups of projects
and activities and the EA process which MTO commits to follow for each undertaking, under the
provision of the OEAA.
Under the MTO Class EA, the 407 East Transportation Corridor is considered a „Group A‟ level
Project, due to it being a new provincial transportation facility. Therefore, in accordance with the
MTO Class EA, the 407 East Transportation Corridor EA was conducted following the Individual
EA planning process requirements under the OEAA.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 17 of 127 610706-00-6D-RR-CGP-R005 01
The Highway 407 East Phase 1 is utilizing the MTO Class EA (Design and Construction Report
preparation) in order to document how "Commitments to Future Work and Public Participation"
as described in the EA report are being addressed prior to the commencement of construction
activities.
P.3.2. Canadian Environmental Assessment Act
Overview
The CEAA sets out the responsibilities and procedures for carrying out the EA of projects that
involve federal government decision-making. Under legislation prior to 2012, the federal EA
process applied whenever a federal authority (such as a federal department or federal agency)
had a specified decision-making responsibility in relation to a project. This was known as
triggering for an EA. There were 2 triggers for the Project, federal lands were required to enable
the undertaking to be carried out and the federal government needed to exercise regulatory
duties in relation to the undertaking issue a permit or license that is included in the Law List
Regulations pursuant to CEAA (i.e., Authorization under the Fisheries Act).
Project Scope
The scope of the Project for the federal EA included the entire 407 East Transportation Corridor
development and began as a screening level assessment in May 2008. In March 2010, as a
result of the January 21, 2010 Supreme Court of Canada ruling in MiningWatch Canada versus
Canada (Minister of Fisheries and Oceans et al.), it was determined that the Project was
required to continue to a higher elevated level of assessment, as a Comprehensive Study.
Comprehensive Study Report
As part of federal EA process, the public and Aboriginal groups were invited to provide
comments on the conclusions and recommendations contained in the Comprehensive Study
Report prepared for the Project. The Comprehensive Study Report presents the public,
Aboriginal groups and the Canadian Minister of the Environment with the Canadian
Environmental Assessment Agency‟s analysis, conclusions and recommendations on the
fundamental consideration set out in the Act, which is whether or not the Project is likely to
cause significant adverse environmental effects.
In July 2011, the federal Minister took into account the implementation of appropriate mitigation
measures, and rendered a decision based on the Comprehensive Study Report, that the Project
is not likely to cause significant adverse environmental effects. A follow-up compliance
monitoring program to verify the accuracy of the federal EA and/or determine the effectiveness
of measures taken to mitigate the adverse environmental effects is required, and will by
documented in separate document by 407EDG.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 18 of 127 610706-00-6D-RR-CGP-R005 01
P.3.3. Other Provincial/Federal Approvals
Ontario Endangered Species Act, 2007
Purpose and Project Scope
The Ontario Endangered Species Act, 2007 (ESA) came into force on June, 2008. The Act
provides species protection (s.9) and habitat protection (s.10) to those species listed as
extirpated, endangered and threatened on the SAR in Ontario List, Ontario Regulation 230/08,
issued under the ESA. Note that as of June 30th, 2013, general habitat protection is in place for
transition species. Therefore, all species listed as threatened or endangered under Ontario
Regulation 230/08 are afforded as minimum general habitat protection, unless a habitat
regulation for the species has been issued. At this time, specific habitat protection guidelines
are being rolled out by the Ministry of Natural Resources (MNR) for individual species.
Identified Species at Risk
Through several years of natural heritage inventories, it was determined that the construction of
the Highway 407 East Phase 1 will interact with 5 species and/or their habitat protected under
the ESA, including:
Butternut (Juglans cinerea);
Bobolink (Dolichonyx oryzivorus);
Eastern Meadowlark (Sturnella magna);
Barn Swallow (Hirundo rustica); and
Redside Dace (Clinostomus elongatus).
Permits under Section 17(2)(c) of the ESA have been secured by the MTO for the above SAR.
Federal Fisheries Act Authorizations
Affected Watercourses
There are a total of 33 watercourses within the Project footprint that will require modification or
alteration of fish habitat to facilitate construction of the 407 East Phase 1. These watercourses
are located in the watersheds of Duffins Creek, Carruthers Creek, Lynde Creek and Oshawa
Creek. The works at 19 of the 33 watercourse sites have been determined to result in the
harmful alteration, disruption or destruction (HADD) of fish and/or fish habitat and, therefore, will
require authorization under the Fisheries Act for channel realignments and/or enclosures along
the Highway 407 East Phase 1 corridor.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 19 of 127 610706-00-6D-RR-CGP-R005 01
The 407EDG, on behalf of MTO, will obtain authorizations under subsection 35(2) of the
Fisheries Act from Fisheries and Oceans Canada (DFO) for the HADD of fish habitat prior to
relevant construction works or activities.
Other Permits and Approvals
The construction of the Highway 407 East Phase 1 will require other permits and approvals from
municipal, provincial, and federal departments and agencies. Not all permits are required for
each work package. The types of permits, approvals and activities that they apply to are
summarized in Table P-1.
Table P.1: Other Permits and Approvals Required Prior to Construction
Permit or Approval Related Requirement
Federal
National Energy Board Trans-Northern Oil Pipeline (WDL area) and Trans-Canada Gas Pipeline to construct crossings of their oil/gas pipelines.
Canadian Transportation Act Agreement with Canadian Pacific Rail between Rossland Road and Taunton Road on WDL to construct a crossing of its corridor.
Provincial
Highway Traffic Act (Designation of Construction Zone)
Construction activities associated with provincial highways.
Ontario Water Resources Act (Permit to Take Water)
For dewatering activities exceeding 50,000 liters/day (e.g., to keep excavation areas dry for construction).
Ontario Heritage Act (Clearance)
Areas with known archaeological resources, or with archaeological potential, prior to ground disturbance and excavation.
Municipal
Noise By-law Exemption – City of Pickering, Town of Whitby, Town of Ajax, City of Oshawa
For construction activities outside permitted hours stipulated in local municipal noise control by-laws.
Road Occupancy Permit For construction on existing local and regional municipal road ROW.
Road Entrance Permit Required for closing and establishing new entrances on existing municipal roads.
P.4 PURPOSE OF DESIGN AND CONSTRUCTION REPORTS (DCR)
In accordance with MTO‟s Class EA, commitments to future Project work include the
preparation of documentation necessary for the Detail Design phase. This is required in the
form of a Design and Construction Report (DCR) which documents the development of the
Preliminary Design scheme to a design implementation level (referred to as Detail Design). A
DCR addresses and documents significant design alternatives generated during the course of
Detail Design and the Recommended Plan. It includes a summary of the consultation process
during Detail Design, a description of the proposed design features, a summary of
environmental investigations conducted during Detail Design, specific environmental issues,
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 20 of 127 610706-00-6D-RR-CGP-R005 01
mitigation measures and commitments, and commits to monitoring procedures associated with
the implementation of a project.
This DCR demonstrates how EA commitments and associated MOE Conditions of Approval
have been addressed as applicable to the Highway 407 East Phase 1 work activities described
in this report. It is not intended as a mechanism to reopen planning decisions documented in
the approved EA report.
DCR Contents
In general, DCRs will include the following information:
Introduction and overview of the Project;
Summary of the proposed design and work activity addressed in the DCR;
Description and results of the consultation program;
The transportation, engineering and environmental issues and how they are being
incorporated;
Description of the Recommended Plan, including design alternatives, if applicable;
Description of existing environmental conditions, effects and mitigation measures;
Identification of all project approvals, clearances, licenses and permits that have been or
must be obtained prior to construction;
Commitments to future work and monitoring aspects of the Project; and
Supporting technical documentation and selected construction contract package
elements.
P.5 OVERALL CONSULTATION PLAN
The 407EDG has prepared a Community and Stakeholder Consultation Plan (Consultation
Plan) which provides a comprehensive approach to consultation that will be flexible, inclusive,
and integrated to proactively solicit feedback and input from all stakeholder groups on design
and construction. It is a living document and will be reviewed for the relevance in its strategy
and application every 6 months.
The Consultation Plan conforms to the requirements set out in the both federal and provincial
EA approvals and ensures that the full ranges of topics related to the Project are examined by
the public.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 21 of 127 610706-00-6D-RR-CGP-R005 01
The Consultation Plan is guided by the following principles:
External stakeholders, including external agencies and the public will be notified of the
407EDG‟s intention to carry out a study at the beginning of the study, before the
407EDG becomes committed to a particular solution.
Will place emphasis on consultation with the stakeholders most directly affected.
Will provide timely, user-friendly opportunities for input by the public and the agencies
whose mandates are most directly affected.
Consultation will be used to assist in the identification of data requirements.
The 407EDG will constructively address input received during the consultation process.
During later planning and design phases, the 407EDG will show how the input received
in earlier stages affected the Project.
The amount, extent and timing of consultation will vary according to the complexity of a
specific issue(s), the nature of the specific environmental issue(s), and the concerns
expressed by the public and external agencies.
For each consultation event, appropriate methods of notification will be selected based
on the nature of the study area, the external parties to be contacted, the stage of the
study, and the issues to be addressed.
The 407EDG will make reasonable efforts to resolve concerns. Mediation will be
considered for major issues, at key decision points.
P.5.1. Engagement of Stakeholders
Consultation with stakeholders will include, but not be limited to, the following groups:
The general public;
Elected officials and staff of the Regional Municipality of Durham, the Town of Ajax, the
City of Oshawa, the Town of Whitby, and the City of Pickering;
Emergency service providers;
Transit providers;
Interested community groups;
Neighbourhood/resident associations and community groups;
Federal and provincial agencies including conservation authorities;
Local business owners;
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 22 of 127 610706-00-6D-RR-CGP-R005 01
Individual property owners;
Utility companies;
First Nations. (Note: Province retains responsibility for Aboriginal consultation and
communications); and
All applicable parties listed in Chapter 4 of the 407 East Transportation Corridor EA
including: the Municipal Technical Advisory Group (MTAG); the Regulatory Agency
Group (RAG), and ad hoc Neighbourhood Issues Advisory Groups.
Consultation with Regulatory Agencies and Municipalities
Consultation with regulatory agencies and municipalities will be undertaken as part of the
consultation process for the Highway 407 East Phase 1. This involved the establishment of the
RAG and MTAG.
The RAG is comprised of representatives from regulatory agencies with mandates for
environmental protection and related approvals. Prospective RAG members include MTO,
MNR, MOE, Ministry of Tourism Culture and Sport, Conservation Authorities, DFO, Canadian
Environmental Assessment Agency, Environment Canada, Transport Canada, and Natural
Resources Canada. The representatives are expected to have the authority to make decisions
on behalf of their organizations at the roundtable sessions. Technical meetings with individual
agencies may be held outside the RAG forum to address site-specific issues.
The RAG will meet at regular intervals (monthly or as otherwise deemed appropriate) to:
Provide strategic participation by regulatory agency representatives to achieve Project
implementation objectives (e.g., involvement in development of environmental
protection, mitigation and compensatory strategies, plans and designs as prescribed in
the EA commitments/conditions of approval);
Facilitate approvals; and
Provide updates on legislative and regulatory requirements.
At the outset, MTAG will receive information on the overall approach to implementation of the
Project; including provisions pertaining to the design, construction, and handover of new
municipal infrastructure.
The MTAG addresses matters of interest to municipal engineering, planning, operations and
emergency services staff/providers. Information is provided to the group at milestone junctures
(outset; proposed design schemes; major construction staging and scheduling). Meetings are
generally held to coincide with PIC, but may also be convened as required.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 23 of 127 610706-00-6D-RR-CGP-R005 01
It is expected that MTAG members will keep their respective Councils apprised on the Project.
The 407EDG with its design and construction, and operations, maintenance and rehabilitation
groups, will provide municipal Councils with special purpose presentations in these regards at
the request of MTAG members.
Section 2.0 of this DCR documents the consultation process undertaken for the DCR.
Commitment to Consultation
407EDG and MTO are committed to ongoing engagement with stakeholders and members of
the community throughout the design and construction phases of the Highway 407 East Phase
1. The following key messages are specific to the consultation process and are the underlying
pillars that will ensure successful engagement of the public and all other stakeholders:
The 407EDG is committed to an open, transparent consultation process;
Everyone‟s views will receive consideration; and
A reply will be provided in a timely manner, if a response is requested.
Consultation efforts will ensure that stakeholders and interested community members are aware
of the Project throughout design and construction, while mitigating potential negative impacts to
the greatest extent possible. The consultation approach and activities planned include:
Consultation related to Design Construction Reports;
Consultation through formal groups, including the MTAG, RAG and 407EAC, and with
utilities and railway companies;
Consultation through Neighbourhood Issues Advisory Groups to deal with specific issues
relating to the Project, such as local traffic disruption, noise or dust; and
Consultation through additional outreach activities to promote interaction with the
general public.
The 407EDG is committed to consultation while maintaining an open and on-going dialogue with
the public and all other stakeholders throughout the duration of the Highway 407 East Phase 1.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 24 of 127 610706-00-6D-RR-CGP-R005 01
P.6. PLAN FOR HIGHWAY DESIGN, BUILD AND DCR SUBMISSION
To meet the completion schedule, construction of the Highway 407 East Phase 1 will be initiated
using a staged approach and will include a number of discrete but linked work packages, based
for the most part on designated “Segments”, with corresponding DCRs. This approach will
allow for effective timing of approvals and review of the DCR specific components by
stakeholders through the consultation process. The breakdown of the Project by work package
Segments for the Highway 407 East Phase 1 Mainline (A1, A2, A3, A4 and A5) and WDL (B1,
B2 and B3) are shown in Figure P-4. Six DCRs are to be prepared to cover the complete 407
East Phase 1 Detail Design and Construction phases. This DCR is the fifth in the series of 6
separate DCRs that will focus on various aspects of the design and construction of the Highway
407 East Phase 1. As part of the DCR process, all parties are encouraged to take time to
review all of the DCRs as they become available and provide feedback. Table P.2 (after Figure
P-4) shows the PICs that are being held to obtain input on proposed design and construction
activities in each of the 6 DCRs, and the approximate timing for the release of the DCRs for
review.
Salem
Roa
d
Lake
Ridg
e Roa
d
Salem
Roa
d
Highway 7
Thick
son R
oad N
orth
Thorn
ton R
oad N
orth
Coron
ation
Roa
d
Concession Road 7
Halls
Road
Nort
h
Westn
ey R
oad
Harm
ony R
oad N
orth
Concession Road 5
Taunton Road West
Simco
e Stre
et No
rth
Churc
h Stre
et No
rth
King Street East
Winchester Road East
Rossland Road
Dundas Street EastDundas Street West
Conlin Road
King Street WestKingston Road EastFinch Avenue
Kinsa
le Ro
ad
Harw
ood A
venu
e Nort
h
Whitevale Road
Kingston Road
Rossland Road East
Padd
ock R
oad
Sideli
ne 1
6 Roa
d
Columbus Road East
Concession Road 6
Concession Road 3
Concession Road 4
Scott
Stree
t
Garde
n Stre
et
Harw
ood A
venu
e Sou
th
Kingston Road West Ash S
treet
Broc
k Stre
et
Broc
k Roa
d
-
-
Coun
try La
ne
Winchester Road West
-
-- -
- Highway 401
-
Columbus Road West
Corbett Creek
West Oshawa Creek
Spring Creek
Urfe Creek East D
uffins
Cree
k
Lynde Creek
Brougham Creek
Goodman Creek
Osha
wa Cr
eek
Pring
le Cree
k
Ganatsekiagon Creek
Lynde
Creek
West Oshawa Creek
Lynde Creek
West Oshawa Creek
0 1 20.5 km
Highway 407 East Phase 1Key Plan
Date: 2013/02/04 File Number: 0000 Sub Code: 0000Figure: Rev.:
Ü
P-4
REGION OF DURHAM
SEGMENT A1 SEGMENT A2 SEGMENT A3 SEGMENT A4 SEGMENT A5
SEGM
ENT B
2SE
GMEN
T B1
SEGM
ENT B
3
WHITBY OSHAWA
AJAX
WEST
DUR
HAM
LINK
WESTNEY / SALEM 407 / WEST DURHAM LINK BALDWIN STREET SIMCOE STREET - N HARMONY ROAD
STATION 17+600
STATION 13+250
STATION 11+100
STAT
ION
9+13
2
STAT
ION
14+1
29
TAUN
TON
ROAD
ROSS
LAND
ROA
DHW
Y 401
/ WE
ST D
URHA
M LIN
K
STAT
ION
18+8
00
STAT
ION
24+1
00
STAT
ION
12+7
00
STAT
ION
17+5
00
STAT
ION
12+8
00
STAT
ION
15+5
50
HIGHWAY 407 EAST PHASE 1
PICKERING
GO Transit / CN Rail
CP Rail Line
LegendPhase 1 InterchangePhase 1 Deferred InterchangePhase 1 Deferred Ramp6 Lane Section4 Lane Section
RailwayRoadsWatercoursesWaterbody
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 26 of 127 610706-00-6D-RR-CGP-R005 01
Table P.2: Overall Plan for Design and Construction Reports and PICs
DCR #
DCR Title
and
Project Area
Work Addressed Public
Information Centre
Issue Date for 30-Day
Public Review
1 Segments B2 and B3 – Grading, Drainage, Paving and Structures Segments A1, A2, A3, A4, A5, B1, B2 and B3 - Vegetation Clearing
Vegetation Clearing
Structures
Earthworks, Drainage and Grading
Stream Realignments
Canadian Pacific Railway (CP Rail) Detour
Construction Staging and Traffic Management
December 12 and 13, 2012
January 31, 2013
2 Segments A1, A3, A4, A5 and B1 - Structures and Stream Realignments
Structures
Stream Realignments
Construction Staging and Traffic Management
January 29, 2013
March 18 2013
3 Segments B1, A3 and A4 - Grading, Drainage, Paving, Structures and Stream Realignments Segment A1 – Remaining Structures and Stream Realignments
Structures
Earthworks, Drainage and Grading
Stream Realignments
Construction Staging and Traffic Management
Noise Barriers – Preliminary
April 3, 2013
May 14, 2013
4 Segment A1 - Grading, Drainage and Paving Segment A2 - Selected Structures and Stream Realignments Segment A5 - Grading, Drainage, Paving, Remaining Structures and Stream Realignments
Structures
Earthworks, Drainage and Grading
Stream Realignments
Construction Staging and Traffic Management
April 23, 2013
June 12, 2013
5 Segment A2 - Grading, Drainage, Paving and Selected Structures
Structures
Earthworks, Drainage and Grading
Construction Staging and Traffic Management
July 17, 2013
September 16, 2013
6 All Segments - Landscaping Plan and Illumination
CVP (e.g., trails, gateway features, heritage commemorative sites, etc.)
Landscaping Plan
Vegetation Restoration Plans
Final Noise Barrier Wall Design
Stormwater Management Ponds
Maintenance Facility
Fall 2013 December 2013
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 27 of 127 610706-00-6D-RR-CGP-R005 01
Consultation
The 407EDG recognizes that a staged approach to highway construction may be unfamiliar to
the public and stakeholders, and therefore is committed to continuously engaging with the
public, agencies and all other interested and affected stakeholders throughout the DCR
process. For each work package and associated DCR, regulatory agencies, municipalities, First
Nations and other potentially affected and interested parties will be provided with an opportunity
to review and provide feedback.
Viewing Locations
This DCR is being made available to the public, regulatory agencies, municipalities, First
Nations and other potentially affected and interested parties for a 30-day review period.
Following the 30-day review period, construction may commence in accordance with the
description provided in this document, contingent upon completion of appropriate consultation
and the receipt of any other required approvals, permits and authorizations.
The following recipients will receive a copy of this DCR for the public record and viewing as
stipulated in Condition 3 (Public Record) of the Ontario MOE Notice of Approval for the Project:
MTO, Major Project Office, Central Region;
Regional Municipality of Durham, Clerk‟s Office;
Town of Whitby, Clerk‟s Office;
Town of Ajax, Clerk‟s Office;
City of Oshawa, Clerk‟s Office;
City of Pickering, Clerk‟s Office; and
MOE, Environmental Approvals Branch.
In addition to those listed above, this DCR will also be available for public review at the following
locations:
City of Pickering Public Library, Main Branch;
Town of Ajax Public Library Main Branch;
Town of Whitby Public Library, Main Branch;
City of Oshawa Public Library, Main Branch; and
407EDG Project Office.
Project Name Highway 407 East Phase 1
Client Name: Her Majesty the Queen
Title Page Document Number Rev.
Design and Construction Report #5 28 of 127 610706-00-6D-RR-CGP-R005 01
A copy of this DCR will also be provided to:
MOE, Central Region Office;
MOE York-Durham District Office;
MNR, Aurora District Office;
Toronto and Region Conservation Authority; and
Central Lake Ontario Conservation Authority.
The DCR, including supporting documentation, can be accessed electronically from the Project
website http://www.407eastphase1.ca.
Design and Construction Report Amending Procedure
During the course of the Detail Design phase, unexpected changes in conditions, development
of new technologies or mitigation measures, or the identification of previously unknown
concerns may occur, all of which may lead to modifications to the proposed design and related
commitments made in the DCR. In this regard, an amendment to the DCR may be required
where there are significant changes to commitments made in the DCR. Where significant
changes to commitments made in the DCR are proposed, 407EDG will discuss proposed
changes with the affected party(ies). If all affected parties can be clearly identified and those
parties agree that an Addendum to the DCR is not required, then none will be prepared. If an
Addendum is required, the environmental effects associated with the change, and the proposed
mitigation will be documented in a subsequent future DCR or an Addendum, which will be filed
in the Public Record for 30 calendar days. Since there is no opportunity to request a Part II
Order for this DCR, no such opportunity would be available for the DCR Addendum.