Upload
mr-trupen
View
227
Download
1
Embed Size (px)
Citation preview
8/10/2019 High Voltage Distribution System
1/72
1
Single Phase Transformers
in
H. V. Distribution Systems
8/10/2019 High Voltage Distribution System
2/72
2
Nature of Rural Loads
Loads in rural India are predominantlypumpsets used for lift irrigation
These loads have low p.f., low load
factor
Load density is low due to dispersal of
loads
Existing system is to lay 11 KV lines,employ 3 phase DTRs 11kv / 433 volts
and lay long LT lines
8/10/2019 High Voltage Distribution System
3/72
3
Nature of Rural Loads (Contd.)
To fetch a load of one pump set of 5 HP
(4 kw) ; two or three L.T. spans are to
be laid
On each DTR 63 or 100 KVA 20 to 30such pump sets are connected. If used
for domestic services about 100
consumers can be connected
They run for about 1500 Hrs in an year
of 8760 hours.
8/10/2019 High Voltage Distribution System
4/72
4
Disadvantages experienced with LVDS
Poor tail end voltages
High quantum of losses
Frequent jumper cuts and fuse blow outs
Motor burn outs almost twice in each cropping
period of 100 days
DTR failures due to frequent faults
Loss of standing crops due to inordinatedelays in replacement of failed DTRs
8/10/2019 High Voltage Distribution System
5/72
5
Solution ? H V D S ?
To improve quality of supply and reduce
losses HVDS is recommended
11 KV lines are extended to as nearer to
the loads as possible and erect small size
single phase transformers 5, 10 or 15 KVAand release supply with NO or least LT line
Aim at LTlesssystem starting from Less
LT
Unavoidable short LT lengths to be covered
by insulated wires like ABC (Aerial Bunched
Cables)
8/10/2019 High Voltage Distribution System
6/72
6
Technical Superiority of HVDS
For the distribution of same power, the
comparison of voltage drop, losses etc., with100 as base is illustrated below
Parameter Single Phase 6.3
kv / 433 V HVDS
Conventional 3
phase LVDSCurrent (A) 11 100
Losses (kw) 8.5 100
Voltage drop 12.7 100
8/10/2019 High Voltage Distribution System
7/727
Technical Superiority of HVDS
Smaller size conductors can be employed
Excellent voltage profile
Reduced losses
No frequent fuse blow outs
Negligible transformer failures
Two or three consumers get effected against
30 if DTR fails (even 100 domestic)
Very easy and quick replacement
8/10/2019 High Voltage Distribution System
8/72
8
HVDS Single phase - Irrigation
Good quality single phase motors areavailable
High yield of water as pump set
efficiency is high
Single phase motors are capacitor
startand capacitorrun
Starters not required Built in capacitor
8/10/2019 High Voltage Distribution System
9/72
9
Additional advantages of HVDS
Unauthorised hooking of loads is not possible as
LT lines are short and insulated
System power factor improves (0.95) causing
easy reactive power control
As only two or maximum (3) pump sets are
connected on each DTR ; the consumers assumeownership and responsibility
High quality of power supply earns total
consumer satisfaction
8/10/2019 High Voltage Distribution System
10/72
10
Questions & Critical issues
frequently faced on HVDS
A. Whether HVDS is for future areas to be
electrified or to convert existing LVDS?
B. Can HVDS & LVDS coexist in the same area?
C. What is the linkage between load density andtype of Distribution System
D. Economics & payback period
E. Policy on procurement of single phase
transformers
8/10/2019 High Voltage Distribution System
11/72
11
A&B
H.V.D.S. to be implemented straight away
where new villages are being electrified inview of its technical superiority
Where 3 phase pump sets are in use HVDS can
be implemented by converting existing LT
lines for 11 KV
Even three Nos. smaller size single phase
transformers can be used for providing three
phase LT supply capacity (3Xindividual
capacity)
8/10/2019 High Voltage Distribution System
12/72
12
A&B (Contd.)
Single phase transformers 6.3 kv / 233
Volts can be manufactured with single
or two bushings
Three single phase transformers can be
connected with HVs in star or delta
8/10/2019 High Voltage Distribution System
13/72
13
nN
Aa
Bb
Cc a
nA B
C
cb
Star Star Vs. Delta - Star
8/10/2019 High Voltage Distribution System
14/72
14
Comparison
Star Star Delta Star
Vector group connections
outside
Vector group connections
outside
Single HV bushing Two 11 kv bushings
Graded insulation on HV Entire HV winding to beinsulated for 11 kv
Current rating is high and
hence more copper
Current in HV is less in
delta and hence less
copper
8/10/2019 High Voltage Distribution System
15/72
15
(C) Linkage with current density
In Metro areas with high load densities ashigh as 20 MW per sq km due to rise
multistoried complexes enough load can
be met with practically no LT
In smaller urban areas, single phase
transformers can be employed selectively
for single phase as well as three phase
8/10/2019 High Voltage Distribution System
16/72
16
(C) Linkage with current density (Contd.)
Even if one limb fails, single phaseloads on that phase can be distributed
on the other two and the failed unit can
be replaced very quickly as it is easy to
transport and erect
In the case of 3 phase large capacity
transformers, entire unit is to be
replaced and down time is high
8/10/2019 High Voltage Distribution System
17/72
17
(C) Linkage with current density (Contd.)
In rural areas of low load densitiesHVDS using one or three Nos. single
phase transformers can be employed
without any hesitation
Rural loads even village habitat portion
are too low and mostly single phase
In villages getting electrified afresh;
the load densities are bound to be too
low
8/10/2019 High Voltage Distribution System
18/72
18
(D) Economics
Cost of three Nos. single phasetransformers of capacity K is equal to a
three phase transformer of capacity (3K)
Cost of employing three single phase
transformers is 1.3 times the cost of a 3phase transformer
There is no difference in no load losses
and full load losses between one 3 phasetransformer of 3 K and three Nos. single
phase transformer of K
8/10/2019 High Voltage Distribution System
19/72
19
(D) Economics (Contd.)
However current for same capacity istoo low at 11 KV compared to LT
For 100 KVA current is 5 Amps at 11 KV
and 140 Amps at LT Line losses get reduced in the ratio
52:1402(25:19600)
Hence highly economical
(E) Usage of three Nos single phase against one
8/10/2019 High Voltage Distribution System
20/72
20
(E) Usage of three Nos. single phase against one
three phase transformer in urban localities
The schemes being implemented inmany rural areas are mostly such as
Kutir Jyothi and A Lamp for each
house do not need high capacity
transformers.
There are single 5, 10, 15 / 16 capacity
transformers also which can be used
advantageously in these light loadareas
(E) U f th N i l h i t
8/10/2019 High Voltage Distribution System
21/72
21
(E) Usage of three Nos. single phase against one
three phase transformer in urban localities
This has many advantages as follows
Capacities of single phase units can be so
selected to avoid laying LT lines as these
units are available in ratings from 5 KVA to
15 KVA
Single phase loads can be connected on
individual single phase transformers duly
dividing them.
(E) U f th N i l h i t
8/10/2019 High Voltage Distribution System
22/72
22
(E) Usage of three Nos. single phase against one
three phase transformer in urban localities
In respect of extremely few three phaseloads with connected loads of 4 kw or
above (very rare in rural areas) three
single phase transformers of smaller
capacities can be employed.
The loads are too small that they cannot
contribute to high unbalances.
(E) Usage of three Nos single phase against one
8/10/2019 High Voltage Distribution System
23/72
23
(E) Usage of three Nos. single phase against one
three phase transformer in urban localities
In the event of one phase unit givingtrouble, the loads can be distributed on
the other two phase units and the
defective unit can be taken out easily
Transport, replacement is very easy and
can be done much faster.
In fact a rolling stock of 4% can be
maintained at each distribution sectionoffice for faster replacement
PROS & CONS i R t t i i ti
8/10/2019 High Voltage Distribution System
24/72
24
PROS & CONS in Restructuring existing
LVDS to HVDS
99.99% customers avail supply at 415 / 240Volts thus operational performance of LV
network is key to customer services
Losses in Indian Power System are around
20%. LV system is responsible for high lossscenario as LV line losses are 6 times of
target limit and 3 times maximum
tolerable limit. Switchover to HVDS alone
can bring losses to international norms.
PROS & CONS in Restr ct ring e isting
8/10/2019 High Voltage Distribution System
25/72
25
PROS & CONS in Restructuring existing
LVDS to HVDS
Power loss for transmission of equal loadin LVDS (415V) and HVDS (11000V) lines
are in ratio 13:1
Maximum permissible voltdrop between
DSS and customer premises is 10%. Hencecompliance with IE rule. 56 on voltage
drop is difficult and very expensive in
LVDS whereas it is simple in HVDS
PROS & CONS in Restructuring existing
8/10/2019 High Voltage Distribution System
26/72
26
PROS & CONS in Restructuring existing
LVDS to HVDS
The investigation of typical LV feeders in
LVDS indicate that 75% of LV feeders havevoltdrop above 5% and is the cause of high
losses whereas in HVDS losses on LV line
are insignificant.
The current for distribution of same power
in L.V.D.S. is high and existing conductors
get loaded beyond economic loading
limits. It can be avoided by switch over to
HVDS
PROS & CONS in Restructuring existing
8/10/2019 High Voltage Distribution System
27/72
27
PROS & CONS in Restructuring existing
LVDS to HVDS
The monitoring of feeders in LVDS is
difficult compared to HVDS as number of
feeders to be monitored is in ratio of 60:1
Unauthorised tapping of LV lines is simpleand rampant in LVDS whereas it is very
difficult in HVDS
ABC cables with tough insulation areindigenously available
PROS & CONS i R t t i i ti
8/10/2019 High Voltage Distribution System
28/72
28
PROS & CONS in Restructuring existing
LVDS to HVDS
3 Phase HVDS
The work involved in restructuring
distribution work are
Conversion of existing low voltage lines to
single phase 2 wire HV lines
Replacement of existing three phase
distribution transformers with smallcapacity single phase transformers
Utilisation of existing three phase motors.
8/10/2019 High Voltage Distribution System
29/72
29
HIGH VOLTAGE DISTRIBUTION SYSTEM
IN
APSPDCL
8/10/2019 High Voltage Distribution System
30/72
30
8/10/2019 High Voltage Distribution System
31/72
31
Existing LT Distribution of KOTTUR - SS-I
39 Agl Services3.6 km LT Line
8/10/2019 High Voltage Distribution System
32/72
32
Existing LT Distribution of Murakambattu - SS-II
24 Agl Services
3.0 km LT Line
8/10/2019 High Voltage Distribution System
33/72
33
Existing LT Distribution of PatnamSS II
9 Agl Services
1 no Poultry Service
1.59 km LT Line
8/10/2019 High Voltage Distribution System
34/72
34
Existing LT Distribution of Bangaru PalemSS IV
38 Agl Services
3.3 km LT Line
8/10/2019 High Voltage Distribution System
35/72
35
Present LT Distribution system consists of 3 phase distributiontransformer with a capacity of 100 KVA in rural areas which
feeds supply to all the consumers through 3 phase 4 wire LT
network.
DISADVANTAGES OF EXISTING SYSTEM
Lengthy LT Lines.
Voltage drop at the consumer end.
High I2R losses .
Frequent motor burn-outs due to low voltage and consequent
expenditure on repairs.Transformer failures-expenditure towards repairs and
inconvenience to the consumers.
Existing LT Distribution Network
Continue
8/10/2019 High Voltage Distribution System
36/72
36
Damage to standing crops, due to delay in
replacement of failed distributiontransformers.
Fluctuations in voltages due to more
number of consumers connected under thistransformer (say 25 to 30 consumers).
Nobody owns the transformer since
everybody thinks that others will take care ofthe transformer.
8/10/2019 High Voltage Distribution System
37/72
37
CALCULATION OF LT LINE LOSSES
Continue
Electronic meters fixed on the LV Side of the
distribution transformers
All Agricultural Services provided with
electronic energy meters.
Energy sent out from the transformer measured.
During the same period energy consumed by the
Agricultural consumers measured .Losses worked out.
8/10/2019 High Voltage Distribution System
38/72
38
Sl.No Particulars Kottur-ss I Murakkombattu
ss II
1 Crop pattern Sugarcane,
paddy
Coconut , mango garden, paddy and part
of the land cultivated by sugarcane.
2 Length of LT
lines
3.6Km 3.0 Km
3 No. of Pump sets 39 24
4 Connected Loads 179.5 HP 130 HP
5 No. of days 13 days 14 days
6 Input 4290 units 3059 units
7 Output 3490.4 units 2638 units
8 Loss of units 799.6 units 421 units
9 % of line loss 18.63% 13.76%
ORIGINAL 100 KVA DTR VOLTAGE &LINE LOSS COMPARISON
8/10/2019 High Voltage Distribution System
39/72
39
Sl.No Particulars Patnam-ss Bangarupalem ss
1 Crop pattern Sugarcane-
90% paddy
&G.nut
Sugar cane,Paddy,Coconut,Mango
Garden
2 Length of LT
lines
1.59Km 3.3 Km
3 No. of Pump sets 9 38
4 Connected Loads 72.5 HP+2.25
KW
130 HP
5 No. of days 40 days 19 days
6 Input 17672 units 6152 units
7 Output 14700 units 5149 units8 Loss of units 2972 units 1003 units
9 % of line loss 16.82% 16.30%
ORIGINAL 100 KVA DTR VOLTAGE &LINE LOSS COMPARISON
8/10/2019 High Voltage Distribution System
40/72
40
As seen from the previous table results the LT line
losses are more in LT distribution network.
To overcome this,HVD 3Ph system is introduced by
A.P.S.P.D.C.L to maintain better voltages andreliability of supply.
8/10/2019 High Voltage Distribution System
41/72
41
Existing LT 3Phase 4 wire line
on support
Same support with HVD System
Conversion of existing LT 3ph 4w Line into HT Line
8/10/2019 High Voltage Distribution System
42/72
42
HVD SYSTEM
Original 3ph 100KVA Dist.Transformer replaced
with 11KV.CTPT set
3ph 15KVA Dist.Transformer erected
under HVDS to cater 2 to 3 services
8/10/2019 High Voltage Distribution System
43/72
43
H.T. and L.T Layout of HVD System.KOTURU-SS-I
39 Agl Services
3.6 km LT Line
2.6 km converted to HT
1.0 km LT Line
11 Nos 15 kVA DTRs
8/10/2019 High Voltage Distribution System
44/72
44
H.T and L.T layout of HVD System Murakambattu SS I1
24 Agl Services3.0 km LT Line2.04 km converted to HT0.96 km LT Line10 Nos 15 kVA DTRs
8/10/2019 High Voltage Distribution System
45/72
45
H.T. and L.T Layout of HVD System.Patnam SS-II
9 Agl Services
1.59 km LT Line
1.59 km converted to HT
8 Nos 15 kVA DTRs
8/10/2019 High Voltage Distribution System
46/72
46
H.T and L.T layout of HVD System Bangaru Palem SS IV
38 Agl Services
3.3 km LT Line
2.5 km converted to HT
0.8 km LT Line
9 Nos 15 kVA DTRs
8/10/2019 High Voltage Distribution System
47/72
47
HVD SYSTEM
Existing LT Lines converted into HV Lines by replacing
L T 3-Phase crossarm by 11KV . V crossarm
Replacement of 3 number L T pininsulators with 3 number 11KV pin
insulators.
Replacement of 3 number LT shackles with 3 number 11KV strain
insulators .
Erection of additional supports where ever clearances are inadequate.
Erection of smaller capacity 3 phase distribution transformer of 15 KVA
capacity for every 2 to 3 pumpsets.
Connection of existing pumpsets from the newly erected 15KVA
distribution transformers with airbunched cable .
8/10/2019 High Voltage Distribution System
48/72
48
Calculation Of HT Line Losses in HVD System
11 KV CT PT set erected in place of existing 100
KVA Distribution Transformer
Readings taken simultaneously at CT PT set and at
all pump sets.
Losses worked out.
Continue
8/10/2019 High Voltage Distribution System
49/72
49
Sl.No Particulars Kotturu SS-I Murakkambattu ss-II
1) No 15KVA distribution
transformer erected
11 nos 10 nos
2) No of days 15 days 13 days
3) INPUT 5310 units 3926 units
4) OUTPUT 5019.2 units 3712.2 units
5) Losses 290.8 units 213.8 units
Continue
8/10/2019 High Voltage Distribution System
50/72
50
Sl.No Particulars Kotturu ss-I Murakambatt
u ss-II
6) % of line losses
on HVDS
5.47% 5.44%
7) % of line losson earlier LT
Distribution
System
18.63% 13.76%
8) % Net
reduction in
line losses
13.16% 8.32%
8/10/2019 High Voltage Distribution System
51/72
51
Sl.No Particulars Patnam SS-II Bangarupalem ss-II
1) No 15KVA distribution
transformer erected
8 nos 9 nos
2) INPUT 1299 units 334 units
3) OUTPUT 1229 units 321.4 units
4) Loss of units 69.7 units 12.6 units
Continue
8/10/2019 High Voltage Distribution System
52/72
52
Sl.No Particulars Patnam ss-II Bangarupalem
ss-II
5) % of line losses on
HVDS
5.30% 3.77%
6) % of line loss on
earlier LT
Distribution
System
16.82% 16.30%
7) % Net reduction
in line losses
11.52% 12.53%
8/10/2019 High Voltage Distribution System
53/72
53
Comparison between LT System with HVD System
Particulars LT HVDS
Length of HT
lines- 2.6Km
Length of LTlines
3.6 Km 1 Km
No of Distribution
transformers100 KVA1 no/.. 15KVA- 11 no/..
Voltage at tail end 350 volts 420 volts
% line losses 18.63% 5.47%
KOTTURU SS-I
8/10/2019 High Voltage Distribution System
54/72
54
Voltage at tail end
350
420
300
320
340
360
380
400
420
440
Voltageat
tailend
Series1
Series2
Tail end Voltage in LT System
Tail end Voltage in HVD System
8/10/2019 High Voltage Distribution System
55/72
55
% Line losses
18.63%
5.47
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
18.00%
20.00%
% line losses
%L
inelo
sses
% Line losses before HVD System
% Line losses after HVD System
8/10/2019 High Voltage Distribution System
56/72
56
Particulars LT HVDS
Length of HT
lines- 2.04Km
Length of LT
lines3.6 Km 0.96 Km
No of Distribution
transformers100 KVA1 no/.. 15KVA- 10 no/..
Voltage at tail end 385 volts 430 volts
% line losses 13.76% 5.44%
MURAKAMBATTU SS-II 100 KVA
8/10/2019 High Voltage Distribution System
57/72
57
Murakambattu SS II 100 KVA
430
375
340
350
360370
380
390
400
410
420
430
440
Voltage at tail end
Voltageattailend
Series1
Series2
Tail end Voltage in LT System
Tail end Voltage in HVD System
8/10/2019 High Voltage Distribution System
58/72
58
Murakambattu SS II 100 KVA
13.76%
5.44%
0.00%
2.00%4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
% line losses
%
Linelosses
8/10/2019 High Voltage Distribution System
59/72
59
Particulars LT HVDS
Length of HT
lines- 1.59 Km
Length of LT
lines 1.59 Km -
No of Distribution
transformers63 KVA1 no/.. 15KVA- 8 no/..
Voltage at tail end 340 volts 420 volts
% line losses 16.82 % 5.30%
PATNAM SS-II 63 KVA
8/10/2019 High Voltage Distribution System
60/72
60
Patnam SS II 63 KVA
340
420
340
350
360370
380
390
400
410
420
430
440
Voltage at tail end
Voltageattailend
Series1
Series2
Tail end Voltage in LT System
8/10/2019 High Voltage Distribution System
61/72
61
Patnam SS II 63 KVA
16.82%
5.3%
0.00%
2.00%
4.00%
6.00%
8.00%
10.00%
12.00%
14.00%
16.00%
% line losses
%L
in
elosse
8/10/2019 High Voltage Distribution System
62/72
62
The New version of HVDS system is an extension of
HVDS work executed at previous locations.The H.T
line losses in previous systems is 5.3%. An effort
has been done to further reduce the H.T line losses
by adopting following methods.
1. Reinforcement of existing LT net work of 7/2.59
ACSR conductor with 55 sqmm conductor.
2.Providing of required rated capacitors at eachagricultural services.
NEW VERSION OF HVDS SYSTEM
Bangaru Palem SS-IV 100 KVA
8/10/2019 High Voltage Distribution System
63/72
63
Particulars LT HVDS
Length of HT
lines- 2.5 Km
Length of LT
lines
3.3 Km 0.8 Km
No of Distribution
transformers100 KVA1 no/.. 15KVA- 9 no/..
Voltage at tail end 320 volts 430 volts
% line losses 16.30 % 3.77%
Bangaru Palem SS-IV 100 KVA with reinforcement of
conductor and installing rated capacitors.
8/10/2019 High Voltage Distribution System
64/72
64
Particulars
HVDS with
existing
conductor
HVDS with
Reinforcement ofconductor and rated
capacitors
Voltage at tail
end420 volts 430 volts
% line losses 5.31 % 3.77%
Bangaru Palem SS-IV 100 KVA.
Comparison between HVDS with existing conductorand HVDS with reinforcement of conductor and
installing rated capacitors
8/10/2019 High Voltage Distribution System
65/72
65
Bangaru Palem SS IV 100 KVA
320
430
340
350
360
370
380
390
400
410
420430
440
Voltage at tail end
Volt
ageattailend
Series1
Series2
Tail end Voltage in LT SystemTail end Voltage in HVD System
8/10/2019 High Voltage Distribution System
66/72
66
Bangaru Palem SS IV 100 KVA
16.30%
3.77%
0.00%
2.00%
4.00%
6.00%8.00%
10.00%
12.00%
14.00%
16.00%
% line losses
%
Line
losses
8/10/2019 High Voltage Distribution System
67/72
67
ADVANTAGES OF HVD SYSTEM
The registered customers will feel ownership and take responsibility and
not allow others to meddle with the L.T. Network.
Prevention of unauthorized loads by the consumers themselves since the
distribution transformer may fail if loaded beyond its capacity.
Failure will be minimal because of no over loading and no meddling of L.T
Lines.
In the event of equipment failure only 2 or 3 customers will get affected
instead of 25 to 30 customers in original system.
High quality of supply since there is practically no voltage drop.
Less burnouts of motors because of good voltage and less fluctuations.
Continue
8/10/2019 High Voltage Distribution System
68/72
68
Considerable reduction in line losses and consequent
savings in power purchase cost
Since Losses are reduced considerably ,Power can be
supplied to additional loads without any further
investment on infrastructure.
No additional generation capacity needed for giving
new loads due to reduction in power drawals.
Accidents due to touching of snapped conductors
reduced due to the fact that the breaker trips atsubstation since the line is at 11 KV potential.
8/10/2019 High Voltage Distribution System
69/72
69
Interaction with the consumers by CMD/APSPDCL& JMD
(vigilance)A.P. Transco on 01.10.2002 at Doddipalle
8/10/2019 High Voltage Distribution System
70/72
70
8/10/2019 High Voltage Distribution System
71/72
71
Interaction with the consumers by CMD/APSPDCL& JMD
(vigilance)A.P.Transco on 01.10.2002 at Murakambattu SSII
Consumers opined that
The motors are drawing less current and hence life span of
motor has increased.The rate of motor burnouts are also reduced.
The motors running smoothly without hissing noise.
The transformer failures are almost avoided.
Theft of energy eliminated since the consumers will not allow
others to pilfer from their Distribution Transformer.
Interruptions have been minimized and quality of supply
assured.
Due to reliability of supply ,2 crops can be raised and can
increase the productivity.
8/10/2019 High Voltage Distribution System
72/72