Innovation Driven, Service Led, Solutions Based.
High Speed FTTx Deployment
Minimising Cost & Disruption
Maximising Effectiveness
Mike Harper
Innovation Driven, Service Led, Solutions Based.
Micro-‐trenching for FTTx
Who are S7rling Lloyd? • UK & US Based Materials Manufacturer
• Infrastructure Specialists (40 years)
• 7 years in micro-‐trenching for fibre
deployment
We’re “in Highways”. In the UK we work with
• Local AuthoriMes (ADEPT)
• Highways England
• HAUC
Innovation Driven, Service Led, Solutions Based.
Cracked / Fre?ed Joint
Micro-trenching for FTTx
2013
2015
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
Great Progress ……. right? • IniMal target 90% properMes at
100 Mbps by end 2015
• Current target 95% of properMes at
24 Mbps (or beXer) by end 2017
• Current posiMon at August 2015
= 83% of properMes done to date
(source: DCMS & Telecoms.com)
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
So now what? How do we complete the last 12%
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
So now what? How do we complete the last 12% • There are 23 million premises
approx. in the UK
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
So now what? How do we complete the last 12% • There are 23 million premises
approx. in the UK
• To reach the 95% target we have
2.85 million properMes remaining
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
So now what? How do we complete the last 12% • There are 23 million premises
approx. in the UK
• To reach 95% we have 2.85 million
remaining
• The UK average is 9 to 11 linear
metres per property
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
So now what? How do we complete the last 12% That means we have 17,700 miles of
fibre to install in the next 24 months…..
…. and we’ve done all the easy stuff!
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
That’s the same as …… John O Groats to Lands End ……
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
That’s the same as …… John O Groats to Lands End ……
20 7mes!!!
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
That’s the same as …… John O Groats to Lands End ……
20 7mes!!! We can do that, right….?
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
Oh, and that could cost £1 billion! And take many years if we do it like this (i.e. by “tradi7onal dig”)
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
What’s the alterna7ve?
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
Introducing … Micro-‐trenching
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
Process train
What is Micro-‐trenching? • Cucng just enough – and no
more
• Systemising the process
• UMlising new techniques and materials
• Installing at a shallower depth
• Doing less damage to highway assets
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
What can micro-‐trenching offer? Superfast deployment
• Greater Output (typically 6x faster than tradiMonal dig)
• Up to 600m (2000 j.) per day
• Less disrupMon to the public
• Less traffic congesMon
Shetland, UK (2010)
Innovation Driven, Service Led, Solutions Based.
Why micro-‐trench? Lower Environmental Impact
• Significantly less waste created to be disposed of
• Less new materials imported
• Fewer truck movements
• Less traffic congesMon
All this means lower CO2
Micro-trenching for FTTx
Las Vegas, Nevada, US (2015)
Innovation Driven, Service Led, Solutions Based.
Why micro-‐trench? Lower cost
• Lower first cost – typically 1/3 of tradiMonal dig
• Lower long term maintenance costs -‐ no secondary compacMon / sunken trenches
• Less damage to the highway / footway asset
• Less mess outside your potenMal customers house!
Micro-trenching for FTTx
Galway, Ireland (2012)
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
Process train
Reinstatement • Process train approach moves
conMnuously along the road
• All the processes are in this image
• Rapid cure of the reinstatement means minimal traffic management behind the works
• 600 lm (2000 j.) per day complete installaMon
Innovation Driven, Service Led, Solutions Based.
Overcoming Objec7ons….
York Phase 1, UK (2014)
Micro-trenching for FTTx
Innovation Driven, Service Led, Solutions Based.
New UK Guidance • Published in 2014
• Detailed coverage on what is required for successful micro trenching
• Published as a supplement to the
SpecificaMon for the Reinstatement of Openings in Highways
York Phase 1, UK (2014)
Micro-trenching for FTTx
Innovation Driven, Service Led, Solutions Based.
York Phase 1, UK (2014)
Micro-trenching for FTTx
Innovation Driven, Service Led, Solutions Based.
Cores taken in Oklahoma, US (2014)
Micro-trenching for FTTx
Core samples… • Samples taken
approximately 60 minutes ajer install
• Full bonded
• No cracking
Innovation Driven, Service Led, Solutions Based.
Minnesota, US (2015)
Micro-trenching for FTTx
Safetrack micro-‐trench installa7ons… Shetland Islands, UK (2010)
York – Phase 1, UK (2014)
York -‐ Phase 2 (2015)
Galway, Ireland (2012)
Le Zion, Israel (2014)
Toronto, Canada (2014)
South Africa (2014)
Sea?le, US (2015)
Minnesota, US (2015)
Las Vegas -‐ US (2015)
York,UK (2014) Seattle, US (2015)
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
Tradi7onal dig
The alterna7ve… • TradiMonal trench dig would be up to 6 x slower
• Would create much more disrupMon for residents and road users
• Uses far more material and creates much more waste
• Far higher carbon footprint
• Much greater damage to the road or pavement asset and likely requirements for more long term maintenance liability (secondary compacMon etc.)
• Costs 3x as much!
Innovation Driven, Service Led, Solutions Based.
Micro-trenching for FTTx
Final thoughts… • Just because we have always done it that way….. • The scale of the task – we need innovaMve techniques • New techniques require suitable materials
Thank you e -‐ [email protected] t -‐ +44 (0) 7976 517200