Upload
others
View
16
Download
0
Embed Size (px)
Citation preview
1
HIGH COURT OF CHHATTISGARH, BILASPUR
SB: HON'BLE PRASHANT KUMAR MISHRA, J
WRIT PETITION (C) No. 6280 of 2010
PETITIONERS Balaji Real Estate & others
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 6282 of 2010
PETITIONERS Chinmay Builders Pvt. Ltd. & others
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 6471 of 2010
PETITIONER Raveendra Banjare
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No.7158 of 2010
PETITIONERS Brijmohan Singh & others
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No.759 of 2011
PETITIONER Rajendra Shankar Shukla & others
Vs.
2
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 2985 of 2011
PETITIONER Vivek Chopda
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 296 of 2012
PETITIONER Smt. Suraj Kali Gupta
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 298 of 2012
PETITIONER Shivji Tiwari
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 437 of 2012
PETITIONER Smt. Shyam Bai Sahu
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 438 of 2012
PETITIONER Jaysingh Devangan
Vs.
RESPONDENTS State of Chhattisgarh and others
3
WRIT PETITION (C) No. 439 of 2012
PETITIONER Devlal Sahu
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 460 of 2012
PETITIONER Ramesh Chandra Maurya
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 461 of 2012
PETITIONER Laxman Prasad Chandrakar
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 462 of 2012
PETITIONER Ramjeewan Vishwakarma
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 799 of 2012
PETITIONER Hemant Kumar Chhatri
Vs.
RESPONDENTS State of Chhattisgarh and others
4
WRIT PETITION (C) No. 800 of 2012
PETITIONER Pawan Chhatri
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 801 of 2012
PETITIONER Bulamal Chhatri
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 802 of 2012
PETITIONER Deepak Kumar Chhatri
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 803 of 2012
PETITIONER Smt. Priya Chhatri
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 804 of 2012
PETITIONERS Smt. Jayvanti Chhatri & others
Vs.
RESPONDENTS State of Chhattisgarh and others
5
WRIT PETITION (C) No. 893 of 2012
PETITIONER Rawal Singh Chawla
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 1217 of 2012
PETITIONERS Anil Kumar Prathwani & others
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITION (C) No. 5847 of 2011
PETITIONERS Vijay Rajani & others
Vs.
RESPONDENTS State of Chhattisgarh and others
WRIT PETITIONS UNDER ARTICLE 226/227 OF THE CONSTITUTION OF INDIA
-----------------------------------------------------------------------------Appearance on behalf of the petitioners:
Shri Ravish Chandra Agrawal, Sr. Advocate with Shri Shankalp Kochar, Smt. Kiran Jain & Shri Saurabh Dangi counsel for the Petitioners in W.P(C). Nos. 6280/2010, 6282/2010 & 1217/2012.
Shri N.K. Vyas counsel for the Petitioners in W.P(C).Nos. 6471/2010, 7158/2010, 296/2012, 298/2012, 437/2012, 438/2012, 439/2012, 460/2012, 461/2012, 462/2012, 799/2012,800/2012,801/2012, 802/ 2012, 803/2012, 804/2012, 893/2012.
Shri P.S. Koshy, Shri Jitendra Pali, Rohit Shukla and Shri Varun Sharma, counsel for the petitioner in W.P(C).No.759/2011.
Shri B.P. Sharma, M.L.Sakat, Sameer Oraon, counsel for the petitioner in W.P.No.2985/2011.
Ku. Sharmila Singhai, counsel for the petitioner in W.P(C). No.5847/2011.
6
On behalf of the respondents:
Shri Prashant G. Desai, Sr. Advocate with Shri Rutul Desai and Shri Kishore Bhaduri, Additional Advocate General for the State.
Miss. Pinky Anand, Sr. Advocate with Shri Sumesh Bajaj and Shri Rajesh Ranjan, counsel for the Respondent RDA.
Shri H.B. Agrawal, Sr. Advocate with Shri Pankaj Agrawal, counsel for the respondent Municipal Corporation, Raipur.
Shri Santosh Kumar Tiwari, Shri Vivek Shrivastava and Shri H.S. Ahluwalia, Standing Counsel for the Union of India.
Shri Manoj Paranjpe and Shri Sudeep Agrawal, counsel for the respective interveners in W.P(C). No.6282/2010, 6280/2010 & 6471/2012.
-----------------------------------------------------------------------------JUDGMENT
(15.04.2013)
1. In this batch of writ petitions filed under Article 226 of the
Constitution of India, the petitioners have sought for quashment of
the Kamal Vihar Town Development Scheme No.4 (hereinafter
referred to as the “Scheme/TDS”) planned, developed and in the
process of execution by the Raipur Development Authority (in short
“RDA”). In some petitions, the petitioners have made alternative
prayer seeking issuance of direction to the respondents to exclude
the lands belonging to the petitioners from the said “Scheme”.
2. ABOUT THE SCHEME : The respondent RDA has
planned the Scheme comprising of 647.84 hectares of land situated
at villages Dunda, Boriya Khurd, Tikrapara, Deopuri and
Dumartarai (hereinafter referred to as the “subject villages”) within
the Raipur Planning Area to construct a modern township for the
purpose of planned development of the growing city of Raipur, the
capital of State of Chhattisgarh. The Scheme has been formulated
under sections 49 & 50 of the C.G. Nagar Thatha Gram Nivesh
7
Adhiniyam, 1973 (henceforth “the Adhiniyam/Act, 1973”) and the
RDA being an authority constituted under the said Act is
implementing the said Scheme.
3. As per the brochure published by RDA (Annexure R/3-A) the
Scheme will be spread over an area admeasuring 647.84 hectares =
1600 acres consisting of 15 sectors with estimated cost of
development of infrastructure assessed at Rs.815.38 crores. Under
the Scheme, the State Government would hand-over Government
land falling within the Scheme area to the RDA and private lands
falling within the Scheme area shall be taken-over by obtaining
consent of the land owners or by acquisition u/s 56 of the Act.
Such land owners shall be returned the developed reconstituted
plots depending upon size of their original plot. However, RDA shall
not charge any contribution cost/incremental cost from the land
holders so that financial burden is not shifted on the land-holders.
The township would have 4 lane main road of 75
meters/45mts/30mts width and two lane roads of 24 mts/18 mts,
width along-with other infrastructure like street lighting, service
duct, underground drainage, green area, foot-path, cycle track,
water supply, sewerage treatment plant, central business district
and 30 meters wide commercial tract abutting ring road with
further facility of small commercial area in every sector. It will also
have recreational facility over 256 Acres; picnic spots and water
sports on 229 acres pond at Boriyakhurd; play ground, city park
over 95 acres and other parks over 62 acres. Separate areas have
been reserved for educational institutions, health services, office
buildings, cultural center, banks, post office etc., Initially RDA
8
shall obtain loan for meeting the expenditure on infrastructure
development which shall be later on recovered by selling 10% plots
to public at large. As per the status report of the project, submitted
along-with written synopsis of RDA, until 31st January 2013, a
sum of Rs.182 crores approx. has already been spent on
infrastructure development.
4. Out of total number of 5095 land owners who are covered
within the Scheme, initially only 685 have not consented for
participation, therefore, the land belonging to these persons have
been subjected to acquisition u/s 56 of the Act. However, out of
these 685 land-owners, 150 more land owners have accorded
consent to the Scheme at subsequent stages and 11 of them have
already received compensation. As against 5095 land owners, only
39 land owners have preferred writ petitions which are disposed of
by this common order. According to the learned counsel for the
RDA, as against the Scheme area of 647.84 hectares, the area
belonging to 39 petitioners covers an area of about 20 hectares only.
GROUNDS OF CHALLENGE
5. The petitioners have assailed the validity of the scheme on the
grounds that the provisions contained in Section 23-A of the Act
has been violated inasmuch as a Town Development Scheme is
formulated to implement the master plan whereas in the present
case the master plan has been modified after preparation of the
Scheme. Another facet of this argument has been raised on
submission that modification of lay out plan/development plan
after finalization of the Scheme has vitiated the entire
proceedings and that after modification of the development plan,
9
the earlier scheme stood amended necessitating de novo steps
commencing from Section 50(1) to Section 50(7) and in absence of
such proceedings having been drawn and completed, the entire
Scheme deserves to be quashed. It has also been argued that the
Scheme itself is in contravention of master plan (revised/
Punarvilokit) 2021 and further that in absence of zonal plan, a
Town Development Scheme cannot be formulated.
6. It appears, the RDA resolved to formulate the Scheme on
21.03.2006 and requested the State Government for change in land
use of such lands which are presently shown to be falling under
‘agricultural use’. The RDA thereafter wrote a letter to the Joint
Director, Town and Country Planning (T&CP) for providing the land
use of certain Khasra Numbers. A meeting of the Sarpanchs of the
affected villages was convened on 01.06.2006 wherein all the
Sarpanchs consented to the Scheme. The RDA thereafter requested
the State Government for communicating the land use so that steps
u/s 50 can be taken. In this communication as well as in the
subsequent communication dated 20th September 2006 the words
‘integrated township’ is mentioned. The State Government by its
letter dated 20.09.2006 sought information from RDA on several
aspects of the Scheme like the area, population and the affected
agricultural lands under the Scheme. This was answered by RDA on
14.11.2006. The RDA again requested the State Government for
change in land use by its letter dated 03.05.2007 and thereafter on
04.05.2007, a request was made to Hon’ble Minister seeking
permission for publication of notices u/s 50 and change of land use
u/s 23-A of the Adhiniyam. RDA by its letter dated 15.06.2007
10
again requested for permission with an alternative proposal of 4
different schemes of about 100 acres each. On 25.01.2008, State
Government granted permission for publication of the Scheme u/s
50 and to complete the Scheme within 5 years. The RDA in turn
informed the State Government that the Scheme has been prepared
in accordance with the land use notified under Raipur Development
Plan 2021 (in short “RDP 2021”). The Board of Directors of RDA
passed a resolution; made a declaration u/s 50(1) and the
notification dated 26.05.2009 u/s 50(2) was published in official
gazette on 05.06.2009.
7. When the notification u/s 50(2) was thus published, RDA
convened a meeting of its Board of Directors on 14.07.2009 for
increasing the area under the Scheme upto additional extended
area of 1900 acres and to seek permission from the State
Government u/s 50(1) followed by letter addressed to the State
Government on 20.07.2009 interalia mentioning that after spot
inspection, it was felt that the Scheme deserves to be extended for a
larger area so as to give full effect to the RDP 2021 for curtailing
scattered and haphazard development of the area. The RDA’s
intention to implement the Scheme by reconstruction of plots and
handing-over proportionate developed plots to the land holders was
also mentioned in the letter. The state Government granted
permission u/s 50(1) to the extended Scheme with certain
conditions by its letter dated 10.08.2009 and accordingly a
declaration u/s 50(1) was made by RDA by circulation amongst
members and the amended notification dated 25th August, 2009
was published in the official gazette dated 04.09.2009.
11
8. The RDA thereafter decided to publish the draft scheme in its
meeting dated 05.11.2009 and thereafter notification dated
09.11.2009 was published in the official gazette dated 20.11.2009
under Section 50(3) inviting objections/suggestions from the
affected persons to be submitted within 30 days. In accordance with
Section 50(5) of the Act, RDA constituted a 3 member Committee for
considering the objections/suggestions on 30.11.2009 and the
Committee decided to afford personal hearing to the objectors for
which notices were issued by Certificate of Posting, Courier Service,
Mobile SMS etc. Hundreds of objections were received and the
documents filed by the RDA demonstrate that notices were issued
to different set of objectors for appearance on different dates and
thereafter they have been dealt-with and disposed of. The
Committee in its meeting dated 09.04.2010 decided to consider
even those objections which were received after the stipulated time
of 30 days.
9. The RDA, thereafter, requested the State Government by its
letter dated 15.04.2010 for change of land use in the RDP 2021.
The State Government by its letter dated 20.05.2010 in turn
directed the RDA, to submit proposal for modification of RDP 2021
as required u/s 23-A of the Act. By yet another letter dated
28.05.2010 the State Government informed the RDA that its
proposal for modification of RDP 2021 shall be considered after the
Committee constituted u/s 50 of the Act approves the Scheme. In
its meeting dated 08.06.2010, the Committee submitted its proposal
u/s 50(6) for consideration by the Board of Directors of RDA, which
was later on approved.
12
10. In its meeting dated 21.06.2010 and 22.06.2010, the Board of
Directors of RDA approved the proposal recommended by the
Committee and decided to publish the final draft of the Scheme as
required u/s 50(7) of the Adhiniyam. In this meeting the RDA
inter-alia approved the change of the name of the Scheme from
“Kamal Vihar Integrated Township Scheme, Dunda” to “Town
Development Scheme No.4 Kamal Vihar”; reconstitution of plots
reserving 15% reconstituted plots for Economically Weaker Sections
(EWS); to make proposal for modifying the land use of such Khasra
numbers of which major part of area falls under residential use and
the remaining for the agriculture use so that the entire Khasra will
have residential land use.
11. It was also decided by the Committee that such land holders
whose lands are situated on new Dhamtari Road or old Dhamtari
Road will be allotted reconstituted plots on the main road and
similarly other land holders will be allotted reconstituted plots at or
near the same place or near to the place where their original lands
were located and if this is not possible then reconstituted plots will
be allotted in the same village. The final draft of the Scheme was
thereafter sent to the State Government for approval.
12. The RDA by its letter dated 14.07.2010 suggested some
minor modifications in the land use and submitted a proposal for
modification in RDP 2021 under Section 23-A of the Act. The
changes in the land use were with respect to (i) Change of place of
regional park without changing total area under the said land use;
(ii) some land of few Khasra numbers of villages Deopuri,
13
Dumartarai and Dunda have been shown to be under residential
use in RDP 2021, however, the remaining part of the same Khasra
number have been marked for agricultural use, therefore, to make it
workable the entire area of few such Khasra numbers be made for
residential use; (iii) some area marked for educational use in RDP
2021 has been reserved for residential purpose, therefore, to make
it workable same extent of area reserved for educational purpose
under the scheme be modified which does not affect the total area
under the educational land use in RDP 2021 as only the location is
changed.
13. By notification dated 05th July 2010 published in
Chhattisgarh gazette dated 16th July, 2010, the final Scheme was
published as required u/s 50(7) of the Act.
14. The Joint Director, Town and Country Planning (T&CP),
Raipur, submitted its report with respect to the proposal for
modification submitted by RDA to opine that one particular Khasra
Number is already entered in the revenue records as Boriyakhurd
Tank, therefore, the said area can be treated as land for recreation
and as such, there would be no requirement of changing the land
use of some residential land to recreation land. The other proposal
for changes submitted by RDA was approved in terms of the
Schedule. The said area for which changes were required was for
approximately 10 hectares of land which is less than 2% of the total
Scheme area of 647.84 hectares. In fact, as against the proposal for
modification covering 33.38 hectares of land, the modification was
approved only for about 10 hectares of land.
14
15. The State Government published notice for modification u/s
23-A(i) inviting objections. The notices were published in two
newspapers on consecutive days of its publication and when no
objections were received, the modifications were approved u/s 23-
A(2) of the Adhiniyam, accordingly modifying the RDP (Revised)
2021 making the modified plan as part of the RDP 2021.
16. Learned counsel for the petitioners would urge that in view of
the judgment of the Supreme Court in Indore Vikas Pradhikaran
Vs. Pure Industrial Coke and Chemicals Limited (2007) 8 SCC
705, the modification in the master plan i.e., RDP 2021 after
finalization of the Scheme is wholly illegal inasmuch as the Scheme
is prepared in terms of the master plan and not vice versa.
In the matter of Indore Vikas Pradhikaran (supra), the
State Government issued a notification under sub-section (i) of
Section 13 of the Adhiniyam constituting Indore Planning Area
including 37 villages therein, however, two villages namely Bicholi
and Karadiya were not included in the planning area itself. Despite
the said fact that the said villages are not included in the planning
area, the Development Authority declared its intention to frame
Town Development Scheme for those two villages along-with other
areas and the building plan submitted for sanction by the
petitioners were rejected on the ground that a Town Development
Scheme is to be prepared for the area. The High Court struck down
the declaration under sub-section (2) of Section 50 of the Act with
respect to the said two villages on the ground that unless the
development plan for the area is published, the draft development
scheme cannot be finalized by the Town and Country Development
15
Authority u/s 50(2) of the Act. This judgment of the High Court
was upheld by the Supreme Court. Thus in the said case, firstly,
the entire Scheme was not quashed but it was quashed for only
those two villages which were not included in the planning area
itself and secondly that before initiation of preparation of a Scheme
for any area, there has to be a development plan for the area.
In the present case, the subject villages were already included
in the RDP 2021 and it is not a case where the areas were not at all
included in the planning area of RDP 2021. The modification made
u/s 23-A became part of the originally formulated RDP 2021 so that
the land included in few Khasras covering about 10 hectares of
land, of which, major part is residential in the RDP 2021 be
modified and the land covered in the entire Khasra Number be
covered under residential land use. The said area of 10 hectares is
less than 2% of the Scheme area. It will not be out of place to
mention that none of the petitioners own any land of which the land
use has been modified from agriculture to residential. It is possible
that the land owners have not approached this Court because the
change in land use for remaining part of their Khasra number from
agriculture to residential benefits them and in the event the said
modification u/s 23-A(2) of the Act is nullified, the sufferer would be
the land owner and not the petitioners.
Be that as it may, it is not a case where there was no
development plan at all for the subject khasra numbers as in the
case of Indore Vikas Pradhikaran (supra), therefore, the case is
clearly distinguishable on facts.
16
17. The petitioners have further argued that once the master
plan is modified, the entire steps under Section 50(1)(2) and
section 50(7) have to be taken de novo as all the previous actions
became nullified when the RDP itself has suffered modification.
18. The details of the procedure discussed above have made it
clear that the modification of the master plan is with respect to few
Khasra numbers only. It is not a case of a new master plan
altogether. The modification in the master plan affects less than 2%
of the area. None of the land-holders whose lands have suffered
change in ‘land use’, after modification of the master plan, has
approached this Court. With these facts in mind, it is to be seen
that u/s 23-A, the modification made in the development plan shall
be an integrated part of the revised development plan meaning
thereby that the modification would relate back to the date of first
publication of RDP (Revised) 2021 when it was first notified on
07.04.2008. Section 23-A(1) makes the modification an integral
part of the revised development plan so as to avoid taking steps de
novo and it is precisely for this reason sub-section (3) of Section 23-
A provides that Section 18 regarding publication of approved
development plan and Section 19 regarding sanction of development
plan will not be applicable for modification made by the State
Government. More importantly, it cannot be lost sight of the fact
that the modification in the master plan has not been challenged in
the writ petition nor any of the petitioners have preferred any
revision before the revisional authority u/s 51 of the Act to
challenge the modification of the development plan.
17
19. The petitioners have further assailed the Scheme on the
ground that modification of master plan is not in conformity
with the provisions contained in Section 23-A(1) as no ‘urgent
public purpose’ is involved and the procedure prescribed u/s
23-A(2) has not been followed. To buttress their submission, it
has been urged that housing and planned development of a city is
not an ‘urgent public purpose’ and in any case the preparation of
the scheme having commenced in 2006, there was no ‘urgent public
purpose’. Learned counsel for the petitioners have compared
provisions contained in Section 17 of the land Acquisition Act and
Section 23-A of the Adhiniyam and have thereafter referred to
Supreme Court decisions in the matters of Devender Kumar Tyagi
and others Vs. State of Uttar Pradesh and others (2011) 9 SCC
164; Devendra Singh and others Vs. State of Uttar Pradesh
and others (2011) 9 SCC 551; Radhy Shyam (Dead) through
LRS and others Vs. State of Uttar Pradesh and others (2011) 5
SCC 553.
20. Responding to the argument Shri Desai, learned Senior
Advocate appearing for the State and Ms. Pinki Anand, Sr. Advocate
for the RDA would refer to a Division Bench Judgment of M.P. High
Court in the matter of Jaganath Dhaniram Jindal and another
Vs. State of M.P., and others, 2003 (1) MPLJ 152 to put forth
their case that there can be no comparison between Sections 4 and
17 of the Land Acquisition Act with Section 23-A of the Adhiniyam
as they operate in two different spheres and it does not warrant any
kind of fusion.
18
21. The phraseology ‘urgent public purpose’ has not been defined
in the Act and although the words ‘public purpose’ has been defined
under the Land Acquisition Act 1894 (for short Act, 1894) and
urgency clause is invoked u/s 17 of the Act, 1894, the two
enactments operate in different fields. Section 23-A is about
modification of development plan and not per-se for acquisition of
the land. U/s 54 of the Adhiniyam, the Scheme should commence
implementation within two years or should complete its
implementation within 5 years from the date of notification, failing
which, the scheme would lapse. Making a provision for time bound
implementation and completion of Scheme makes it imperative that
when development plan is modified on the request of development
authority, it is for the urgent public purpose. Under the explanation
to Section 23-A, creation, development and maintenance of human
settlement or any part thereof has been included within the
meaning of ‘public purpose’ meaning thereby that anything
concerning human settlement is a ‘public purpose’.
22. In course of argument, learned State Counsel has referred to
the Hindi text of the Adhiniyam wherein the word “Atyavashyak”
has been used in place of ‘urgent’. According to them, the word
‘Atyavashyak’ would mean “most important public purpose” and not
“urgent public purpose”. In this context, a Full Bench Judgment of
M.P. High Court in the matter of Gulabchand v. State of M.P.
1982 JLJ 170 and other decisions in M/s. Govindram Ram
Prasad Vs. Assessing Authority (Sales Tax) AIR 1958 MP 16 and
Satya Bhan Singh Jadon Vs. State of M.P., and another 1997
(2) MPLJ can be profitably referred wherein it has been stated that
19
the official language of the State being Hindi, Hindi version of the
State Act would prevail for understanding the meaning of any
provision of the Act. For all these reasons, this Court is of the
considered view that the argument regarding lack of ‘urgent public
purpose’ must fail.
23. The petitioners have harped upon the ground that the
procedure prescribed u/s 23-A(2) of the Act has not been
followed inasmuch as notices were not published continuously
for two days in the local newspapers and that modified plan was
not published along-with the newspapers publication at any
conspicuous place which is mandatory. The draft modification was
published in two daily newspapers on 05.11.2010 and 07.11.2010.
It is for this reason, the petitioners have contended that the
publication was not continuous as there was gap of one day
between 5th November and 7th November. The respondents have
stated on affidavit that 5th November 2010 was the day of Diwali
festival, therefore, there was no publication of the newspaper on
06.11.2010. According to the State and RDA, since there was no
publication at all of the newspapers on 6th November on account of
Diwali Festival, the publication of notice on 5th November and 7th
November would amount to continuous publication.
While construing the meaning of the term “continuous
service” for not less than one year as defined under Section 2(eee) of
Industrial Disputes Act, 1947, the Supreme Court in the matter of
S.E. and Stamping Works Limited Vs. The Workmen, AIR 1963
S.C. 1914, held that “continuous service” is defined in Section
2(eee) as meaning uninterpreted service, and includes service which
20
may be interpreted merely on account of sickness or authorized
leave or an accident or a strike which is not illegal or a lock-out or a
cessation of work which is not due to any fault on the part of
workman.
Though in the said case, the employee had not worked for one
year i.e., for 12 months, therefore, his continuous service of 240
days was not found sufficient for the purpose of section 25-B and
Section 25-F of the I.D. Act, however, seeking guidance from the
definition of word “continuous service”, this Court would hold that
when publication of newspaper on 6th November, 2010 on account
of Diwali holiday was not in the hands of RDA and the non-
publication of newspaper was not due to fault of RDA, the
publication on 5th & 7th of November would amount to continuous
publication.
Therefore, this Court has no hesitation in accepting the
submission made by the State and RDA. Had it been a case that
the newspaper was published on 6th November and yet the notice
was not published on the said issue of the newspaper, the argument
raised by the petitioners would carry substance, however, when
there was no publication at all because of Diwali festival, it must be
treated that the notification was published on two continuous days
when the newspaper was published.
On perusal of the advertisement, it would clearly appear that
Khasra numbers, names of the villages and the proposed
modification are mentioned therein with further statement that the
map of modified plan is available for inspection and any aggrieved
21
person can inspect the same. Thus the publication was in
accordance with law.
24. This Court shall now deal with petitioners challenge to the
Scheme on the alleged non-compliance of Section 50(1) to
Section 50(7) of the Act.
25. It has been urged by the petitioners that ‘declaration of
intention’ has not been made as required u/s 50(1) of the Act,
therefore, the Scheme is bad in law and there is no ‘declaration of
intention’ for the notification u/s 50(2) published on 04.09.2009
and further that Rule 18 of the C.G. Nagar Tatha Gram Nivesh
Niyam, 1975 (for short “Rules, 1975) has not been followed while
publishing notification u/s 50(2), 50(3) & 50(4) of the Act, 1973 and
the notices published are not in prescribed form as provided under
the Schedules. It has also been urged that notification u/s 50(8)
specifies the Khasra numbers only, therefore, it is not in conformity
with the provisions of law. The petitioners have also argued that
the RDA has not sought permission of the State Government
regarding inclusion of villages Boriya Khurd, Deopuri and
Dumartarai before issuing notification dated 25.08.2009 u/s 50(2)
and as such the Scheme is bad in law on this score also.
26. From the documents available on record, it would appear that
in its meeting dated 14.07.2009, the Board of Directors of RDA
decided to extend the area of the Scheme and pursuant thereto the
RDA informed the State Government that under the
amended/revised proposal, the Scheme shall include lands in
villages Dunda, Boriyakhurd, Tikrapara, Deopuri and Dumartarai
spreading over almost 2300 acres (400 acres originally planned plus
22
1900 acres extended area). Responding to this proposal, the State
Government granted permission on 10.08.2009, therefore, the
argument that no permission has been granted for including
villages Boriyakhurd, Deopuri and Dumartarai is contrary to record
and thus sans substance.
27. Similarly, pursuant to the State Government’s permission
dated 10.08.2009, RDA declared its intention to formulate the
Scheme and publish the draft as required u/s 50(2) of the Act.
The Board of Directors declared this intention of RDA on
20.08.2009 by circulation and thereafter the modified/amended
notification dated 25.08.2009 was published in the Chhattisgarh
Gazette dated 04.09.2009. Thus it cannot be said that there was no
‘declaration of intention’ before issuing the amended notification.
So far as it relates to argument regarding absence of publication of
‘declaration of intention’, it is to be seen that sub-section (1) of
Section 50 provides that the Development Authority may, at any
time, declare its intention to prepare a Town Development Scheme,
however, it does not provide for publication of declaration and no
form is prescribed under the Rules, 1975 for issuance of notice to
declare its intention.
28. On a conjoint reading of sub-sections (1) & (2) of Section 50 of
the Act, 1973 along-with Rule 18 of the Rules 1975, it emerges that
in fact, the declaration of intention as mentioned in sub-section (1)
is to be published in the official gazette under sub-section (2) and it
is precisely for this, Rule 18 makes it obligatory for the Development
Authority to publish a notice under sub-section (2) of Section 50 in
Form XIII declaring the intention of making the Scheme. In other
23
words, what is to be published is the declaration as required under
sub-section (2) of Section 50 and not under sub-section (1) of
Section 50. The argument raised by the petitioners on this account
is not supported by the provisions of law, therefore, it fails.
29. The first notification under sub-section (2) of Section 50 was
published on 05.06.2009 and prior to that it was also published in
the newspaper on 27.05.2009, however, when the boundaries were
amended/modified, a fresh notification was published in the official
gazette on 04.09.2009 and prior to that it was published in two
newspapers on 27.08.2009. The petitioners have objected to the
notice on submission that details of the area of each land-holder
have not been mentioned. In this regard, it is pertinent to mention
that the form of notice in Form-XIII prescribed under Rule 18 of
Rules, 1975 does not prescribe any such format wherein the area
of each landholder is to be mentioned. On perusal of Form-XIII, it
would appear that the Development Authority is only required to
mention the area i.e., the locality and not the area of each Khasra
Number because there is no mention under the provisions of the Act
or under the Rules or in the Form prescribed that area belonging to
each landholder shall be included in the notification. In the gazette
notification, RDA has mentioned the boundaries i.e., the outer limit
of the Scheme and in the opinion of this Court, such description of
the area for which the Scheme is to be prepared cannot be faulted
with. More over the publication of notification is with a view to
inform the residents of the locality. Most of the petitioners have
raised objection to the draft Scheme, therefore, it is not a case
where the petitioners were not aware of the preparation of Scheme
24
and because of that they failed to submit their objections. More-
over, in the notification issued under sub-section (3) of Section 50,
which was published in the official gazette on 20.11.2009 in the
manner prescribed under Form No.XIV, it was clearly mentioned
that the draft scheme is available for inspection in the office of RDA
as well as in the office of Joint Director, Town and Country
Planning, Raipur. Therefore, it cannot be said that members of the
area were not at all informed about the Scheme.
30. Another argument has been raised regarding notification
issued under sub-section (8) of Section 50 to submit that their
land has been taken-over without payment of compensation.
The Chhattisgarh Nagar Thatha Gram Nivesh Adhiniyam,
1973 was amended with effect from 16.06.2010 i.e., the date of
publication of the amendment in the official gazette, inter-alia
inserting sub-section (8) of Section 50 in the Adhiniyam. The newly
inserted sub-section provides that where a Town Development
Scheme has come into operation, all land required by the Town and
Country Planning Authority for the purposes specified in the
following clauses :
(a) Lay out of new streets or roads construction, diversion, extension, alteration, improvement and closing up of streets and roads and discontinuance of communications etc.,
(b) Drainage, inclusive sewerage, surface or sub-soil drainage and sewage disposal ;
(c) Lighting;
(d) Water supply
Shall vest absolutely in the Town and Country Department Authority free from all encumbrances and further that nothing in sub-section (1) shall affect any right of the
25
owner on the land vesting in the appropriate authority under that sub-sections.
Thus the newly inserted sub-section specifically provided for
vesting of the land so that after coming into operation of the
Scheme, the Development Authority does not face any hindrance in
commencing infrastructure development activity.
On a reading of the above quoted provision contained in sub-
section (8) of section 50, it would appear that when a Town
Development Scheme has come into operation, all land required by
the Authority for the purpose specified under Clauses (a) to (d) of
Clause-1 of the said sub-section shall vest absolutely in the Town
and Country Development Authority free from all encumbrances,
however, the said vesting shall not affect any right of the owner of
land vesting in the appropriate authority under that sub-section.
The provision would mean that after the notification comes into
operation the Development Authority can commence its activity for
infrastructure development. However, any right of the land-owner
shall not be affected because of such vesting and thus the owner
would be entitled to compensation or reconstituted plot in the
manner decided by the authority. Even otherwise, this notification
has not been called in question and no prayer has been made in
any of the writ petition for quashing this notification.
For the foregoing discussion, the petitioners’ argument on
this count also deserves to be rejected.
31. The petitioners have complained that the Committee
constituted under sub-section (5) of Section 50 has not applied
its mind and while submitting the report under sub-section (6),
26
it has acted in an arbitrary manner. According to the petitioners,
their land consists of superstructure built on it and this aspect has
not been properly appreciated and the Committee has adopted pick
and choose policy while deciding the objections. In W.P(C). No.437/
2012 learned counsel for the petitioner Shri N.K. Vyas has
specifically urged that the land belonging to similarly placed person
Ms. Kanta Agrawal was excluded from the Scheme and the
petitioners’ land was not excluded even though a superstructure is
standing on the land belonging to the petitioners also.
32. The Committee appears to have undertaken mammoth
exercise and has dealt with about 2500 objections and such
objectors who appeared before the Committee were also afforded
personal hearing.
The Committee obtained report from the revenue authority
regarding density of population/construction and on the basis of
such report, the thickly populated/densely constructed areas were
excluded, however, the scattered superstructure within the Scheme
area were identified and depending upon the percentage of
construction over the plot, it was decided that if the construction is
on less than 35% of the area of the plot proposed to be allotted, the
construction would be allowed to remain intact and similarly even if
the construction is little more than 35% but the person is earning
his livelihood, the same would be allowed and in appropriate cases,
cost of the marginal extra land required to retain the construction
would be obtained from the landholder. In other cases, when the
construction is not exceeding marginally, but is much more than
35%, the same would be demolished and compensation shall be
27
granted and reconstituted plot shall also be allotted to such person.
It was also decided that till the time the land owner is able to raise
new construction on his allotted plot, he would be given alternative
accommodation.
33. With respect to the allegation that construction belonging to
one Kanta Agrawal has been excluded from the Scheme but similar
treatment has not been meted out with the petitioner of W.P(C). No.
437/2012, it has been stated that in the case of Kanta Agrawal, her
land/construction was within the densely constructed area,
therefore, it was excluded from the Scheme whereas on the land
belonging to the petitioner of W.P(C). No.437/2012, the
construction/land was not falling in a densely constructed area,
therefore, the objection was over-ruled. In the opinion of this Court,
the explanation offered appears to have substance as it is based on
report of revenue authority, therefore, it is not a case of pick and
choose but the authority has taken an objective decision depending
upon density of construction in the concerned area and the
petitioner of W.P(C). No.437/2012 has not been singled out for
discrimination. Such decision has been taken on the basis of report
submitted by the Patwari, therefore, it cannot be said that there was
non-application of mind while choosing Kanta Agrawal’s land for
exclusion or for not accepting the objection of the petitioner of
W.P(C).No.437/ 2012. Similar is the explanation offered in the
cases of petitioners Jai Singh Dewangan (W.P(C).No.438/2012);
Deolal Sahu (W.P(C).No.439/2012); Ramesh Chandra Mourya
(W.P(C) No.461/2012) and Ramjivit Vishwakarma (W.P.No.462/
2012). These petitioners have their construction in isolated and
28
scattered areas and not within the thickly populated/densely
constructed area, therefore, their objections were over ruled by the
Committee.
34. Other arguments regarding levying of contribution cost;
reserving land for Economically Weaker Sections (EWS);
allotting plot upto only 35% of the original area; not following
all the recommendations of the Committee; upgradation of plot
at higher price etc., have also been raised by the petitioners.
35. The subject enactment falls under Entry No.18 of List II and
Entry No.20 of List III of the 7th Schedule of the Constitution of
India. In Maneklal Chhotalal Vs. M.G. Makwana AIR 1967 S.C.
1373, the principle of town and country planning has been lucidly
dealt with by quoting the principles from a renowned author Lewis
Keepl and thereafter meaning of the words 'planning' in Corpus
juris Secondum” has been referred, to mean in connection with the
Municipalities, the term connotes a systematic development
contrived to promote the common interest in matters embraced
within the policy power, with particular reference to the location,
character, and extent of streets, squares, parks and to kindred
mapping and chatting. In Encyclopedia Britannica Vol.5, “City
Planning” is stated to mean : the guidance of the growth and
change of urban areas. As such, it is aimed at fulfilling social and
economic objectives which go beyond the physical form and
arrangement of buildings, streets, parks, utilities and other parts of
the urban environment. City planning takes effect largely through
the operations of the government and requires the application of
specialized techniques of survey, analysis, forecasting and design.
29
Thus, city planning may be described as a social movement, as a
Governmental function, or as a technical profession. Each aspect
has its own concepts, history and theories. Together they fuse into
the effort of modern society to shape and improve the environment
within which increasing proportions of humanity spent their lives :
the city”.
The Adhiniyam has thus been enacted to achieve the object of
city planning and is not only for acquiring the land which is
otherwise also an incidental matter but mainly for making
infrastructure facility for better living to facilitate social intercourse
at the societal level by adopting methods of colonization by
reconstruction and allotment of plots. The city planning has an
inbuilt intention of working in public interest for the benefit of
Society.
36. In the matter of MIG Cricket Club Vs. Abhinav Sahakar
Education Society and others (2011) 9 SCC 97, the Supreme
Court has held that town planning is an expert job. Para 28 of the
said judgment can be profitably referred as below :
“28. It is well settled that the user of the land is to be decided by the authority empowered to take such a
decision and this Court in exercise of its power of judicial review would not interfere with the same unless the change in the user is found to be arbitrary. The process involves consideration of competing claims and requirements of the inhabitants in present and future so as to make their lives happy, healthy and comfortable. We are of the opinion that town planning requires high degree of expertise and that is best left to the decision of the State Government to which the advice of the expert body is available. In the facts of the present case, we find that the power has been exercised
in accordance with law and there is no arbitrariness in the same.”
(Emphasis supplied)
30
In Greater Kailash Part II Welfare Assn. and others Vs.
DLF Universal Ltd and others (2007) 6 SCC 448 the Supreme
Court has held that the writ court is not entitled to sit on appeal
over the decision of the Executive Authority based on opinion of
experts.
37. While dealing with the similar provision under the Bombay
Town Planning Act, a Constitution Bench of Supreme Court in the
matter of State of Gujrat Vs. Shantilal Mangaldas and others,
AIR 1969 S.C. 634 observed that “in making a town planning
scheme” the lands of all persons covered by the scheme are treated
as if they are put in a pool and the Town Planning Officer then
proceeds to reconstitute the plots for residential buildings and to
reserve lands for public purpose. The reconstituted plots are
allotted to the land-holders and the reconstituted plots having
regard to the exigencies of the Scheme need not be of the same
dimensions as the original land. Their shape and size may be
altered and even the site of the reconstituted plot allotted to an
owner may be shifted. The Town Planning Officer may lay out new
roads, divert or close existing roads, reserve lands for recreation
grounds, schools, markets, green belts and similar public purposes
and provide for drainage, lighting, water supply, filling up or
reclamation of low lying, swamp or unhealthy areas or levelling up
of lands so that the total area included in the scheme may conduce
to the health and well being of the residents. It is further observed
that the object of the scheme being to provide amenities for the
benefit of the residents generally, the area in the occupation of the
31
individual holders of land is generally reduced, for they have to
contribute out of their plot areas which are required for maintaining
the services beneficial to the community. In such matter, it is
further stated that the cost of the scheme is to be met wholly or in
part by contributions to be levied by the local authority on each plot
included in the final scheme calculated in proportion to the
increment which is estimated to accrue in respect of each plot.
In the said matter Hon’ble the Supreme Court has further
considered the meaning of expression “reconstituted plot and its
rearrangement” and the underlying principles in the following
manner in Paragraphs 15, 16 & 17
“15. The relation between Sections 53 and 67 which have been declared ultravires by the High Court and the other related provisions may now be determined. Section 53 of the Act provides :
“On the day on which the final scheme comes into force.—
(a) All lands required by the local authority shall, unless it is otherwise determined in such scheme, vest absolutely in the local authority free from all encumbrances;
(b) All rights in the original plots which have been re-constituted shall determine and the re-constituted plots become subject to the rights settled by the Town Planning Officer.”
The expression “reconstituted plot” is defined in Section 2(9) as meaning a plot which is in any way altered by the making of a Town Planning Scheme, and by the Explanation the word “altered” includes alteration of ownership. By Cl.(b) of Section 53 ownership in a plot belonging to a person is substituted by the ownership in the reconstituted plot: his ownership in the original plot is extinguished and simultaneously therewith he becomes the owner of a reconstituted plot subject to the rights settled by the Town Planning Officer. On the coming into force of the scheme all lands which are required by the local authority, unless otherwise determined in the scheme, by the operation of Section 53(a), vest absolutely therein free from all
32
encumbrances. The result is that there is a complete shuffling up of plots of land, roads, means of communication, and rearrangement thereof. The original plots are reconstituted, their shapes are altered, portions out of plots are separated, lands belonging to two or more owners are combined into a single plot, new roads are laid out, old roads are diverted or closed up and lands originally belonging to private owners are used for public purposes i.e., for providing open spaces, green belts, dairies etc. In this process the whole or part of a land of one person, may go to make a reconstituted plot, and the plot so reconstituted may be allotted to another person and the lands needed for public purposes may be earmarked for those purposes.
16. The re-arrangement of titles in the various plots and reservation of lands for public purposes require financial adjustments to be made. The owner who is deprived of his land has to be compensated, and the owner who obtains a reconstituted plot in surroundings which are conducive to better sanitary living conditions has to contribute towards the expenses of the scheme. This is because on the making of a Town Planning Scheme, the value of the plot raises and a part of the benefit which arises out of the unearned rise in prices is directed to be contributed towards financing of the scheme which enables the residents in that area to more amenities, better facilities and healthier living conditions. For that purpose provision is made in Sec.65 that the increment shall be deemed to be the amount by which at the date of the declaration of intention to make a scheme, the market value of plot included in the final scheme, estimated on the assumption that the scheme has been completed, would exceed at that date, the market value of the same plot estimated without reference to improvements contemplated by the scheme. By Section 66 the cost of the scheme is required to be met wholly or in part by contributions to be levied by the local authority on each plot included in the final scheme calculated in proportion to the increment which is estimated to accrue in respect of such plot by the Town Planning Officer. Section 67 provides:
“The amount by which the total value of the plots included in the final scheme with all the buildings and works thereon allotted to a person falls short of or exceeds the total value of the original plots with all the buildings and works thereon of such person shall be deducted from or added to, as the case may be, the contributions leviable from such persons, each of such plots being estimated at its market value at the date of the declaration of intention to make a scheme or the date of a notification under sub-section (1) of Section 24 and
33
without reference to improvements due to the alteration of its boundaries.”
Section 67, it will clearly appear, is intended to make adjustments between the right to compensation for loss of land suffered by the owner, and the liability to make contribution to the finances of the scheme; and Section 71 is a corollary to Section 67. Section 71 provides :
“If the owner of a original plot is not provided with a plot in the final scheme or if the contribution to be levied from him under Section 66 is less than the total amount to be deducted therefrom under any of the provisions of this Act, the net amount of his loss shall be payable to him by the local authority in cash or in such other way as may be agreed upon by the parties.”
17. The provisions relating to payment of compensation and recovery of contributions are vital to the successful implementation of the Scheme. The owner of the reconstituted plot who gets the benefit of the scheme must make contribution towards the expenses of the scheme: the owner who loses his property must similarly be compensated. For the purpose of determining the compensation, the Legislature has adopted the basis of market value of land expropriated, but the land is valued not on the date of extinction of the owner’s interest, but on the date of the declaration of intention to make the scheme.”
38. In the matter of Kiritbhai Nandvadan Bhatt and others Vs.
Ahmadabad Municipal Corporation 1996 (1) GLH 905, it has
been held that making provision for allotment of land to EWS
persons is not prohibited in any law as it is a public purpose. The
town planners are within their authority to provide plots to be used
for a public purpose, therefore, when plots are reserved for the
members of EWS, the same is neither illegal nor arbitrary. In the
said case, the concerned Corporation allowed slum dwellers to
remain in occupation of Plot No.463 instead of dislocating them
and asking them to shift to Plot No.187, which was reserved for
EWS. Although by permitting this deviation, the land use was
34
violated to some extent but the Supreme Court permitted the same
with an observation that even if there is a lapse on the part of the
authorities in not meticulously following the procedural
requirements, but when substantial justice has been done it would
not be proper to interfere in the matter.
39. The report of the Committee constituted u/s 50(5) has been
filed as Annexure R-3/2, on a reading of which, it would clearly
appear that the committee report running into about more than 100
pages have considered all the aspects mentioned in sub-section (6)
of Section 50 by defining and demarking the areas allotted to or
reserved for public purpose; demarking the reconstituted plots;
determining as to whether the areas reserved for public purpose are
wholly or partially beneficial to the respondents within the area of
Scheme; evaluate the value of the original and reconstituted plots;
and other matters as contained in Clauses (v), (vi) and (vii) which
have been dealt with by mentioning that that they are not
applicable because the State Government has decided not to seek
payment of incremental cost/contribution cost from the land-holder
on account of development of area while prescribing the size of the
reconstituted plots for which respective landholders would be
entitled. It was decided by the Committee, after considering the
provisions of National Building Code of India, 2005 and C.G. Land
Development Rules 1984, that the minimum size of the
reconstituted plots should be 50 square meters and the persons
who are holding smaller plots upto 1500 sq.ft. shall be allotted
reconstituted plots of 40-43% area; those who possess plots of size
1500 sq.ft. to 2900 sq.ft., shall be provided plots having 35-36% of
35
the original area and those persons who are holding the land more
than 2900 square feet shall be allotted/reconstituted plot of an area
equal to 35% of their original area.
40. This Court has gone through the report on item No.4 i.e.,
reconstituted plots recommended by the Committee only to find that
the matter has been considered by the Committee in an elaborate
manner after considering the relevant parameters, therefore, the
recommendation on this aspect is neither arbitrary nor illegal nor
can be said to be without application of mind or irrational.
Therefore, the objection raised by the petitioners on this aspect also
deserves to be rejected.
41. It has also been argued that the area of reconstituted plot
is much less than the area of original plot, therefore, it
amounts to deprivation of land and hence the Scheme of
reconstitution of plots is arbitrary and confiscatory being
violative of Article 31 of the Constitution of India.
The above argument appears to be attractive, however, while
dealing with similar argument, the Supreme Court in the matter of
Maneklal Chhotalal (Supra) has held that the petitioners may
have originally owned larger extents of land, in different areas,
which may or may not be fit for building purposes, there can be no
controversy that the reconstituted plots, though of a lesser area,
have a higher value, as building sites, in view of various
improvements and amenities provided under the Town Planning
Scheme. What parties, like the petitioners, may have lost in actual
area of land, can certainly be considered to have been more than
sufficiently compensated by the increased value of the reconstituted
36
plots. There is no question of any deprivation of property, therefore,
so as to attract Article 31 of the Constitution.
The Scheme in question is formulated in exactly the same
manner in which the Scheme before the Supreme Court in the
above referred matter of Maneklal Chhotalal (supra) was
formulated, in so far as it concerns reconstitution of plots and
allotment of reconstituted plots to the landholders. Since the law
has been settled by the Supreme Court, this Court does not find
any arbitrariness much less deprivation of property when the area
of reconstituted plots allotted to the landholders are less than their
original area.
42. Regarding reservation of land for EWS dealt with as Item
No.6, the Committee proceeded to examine the provisions of RDP
2021, C.G. Municipalities (Registration of Colonizer Terms and
Conditions) Rules 1998, C.G. Gram Panchayat (Registration of
Colonizer Terms and Conditions) Rules 1999; National Urban
Housing and Environment Policy 2007 and the Provisions of
Adhiniyam 1973. Referring to the National Housing Policy 2007,
the Committee elaborately discussed that the said Policy lays
special emphasis for making provision of housing for weaker section
and lower income groups. It is to be seen that u/s 49 of the
Adhiniyam, a Town Development Scheme has to make provision for
acquisition and development of land for public purpose such as
housing development and it is the duty of the Committee to address
itself to define and demark the areas allotted to or reserved for
public purpose while making proposal under sub-section (6) of
Section 50. In other words, the housing development is one of the
37
public purpose and when it is meant for EWS class of persons, it
cannot be said that such provision cannot be made. In any case,
there is no restriction or prohibition for reserving the land for
persons belonging to EWS. Annexure R-3/10 is the Housing Policy
of Chhattisgarh which also makes provision for reserving the land
for EWS category and the National Building Code of India
(Annexure R-3/11) has also high-lighted housing requirement of
EWS category and has thereafter recommended that special action
plan should be prepared for urban slum dwellers. Thus,
considering from all angles, reservation of land for EWS is in public
interest and the same being in conformity with the States Housing
Policy as well as National Housing Policy is in consonance with the
public policy, therefore, it is not unlawful. Anything which is for
welfare of weaker sections of Society will not be branded as illegal
when the subject enactment does not prohibit making such
reservation. When there is no specific provision for a particular
action but the authority while making such provision/action is
guided by State Policy and National Policy, the action can never be
branded as arbitrary.
43. It is also put-forth by the petitioners that as per the
environment clearance certificate, RDA has to maintain 185
hectares of green area, however, from the final scheme; it would
appear that green area is much less than that, therefore, there
being clear violation, the environment certificate and the scheme
cannot be acted upon. In the area analysis of town development
scheme No.4 Kamal Vihar, which is part of Annexure R-3/2, an
area of 25.43 hectares has been reserved for city park and 103.98
38
hectares for regional park. There is another area of 0.83 hectares
for water bodies. The total of these areas is a little more than 130
hectares. It has been stated by RDA that there would be extensive
road side plantation along all the major roads as well as sector
roads and the green area would cover more than 185 hectares.
Apart from that, community open space, graveyard/ cremation
grounds and play grounds would cover more than 40 hectares of
land. From the area analysis of the scheme and the statement
made by learned counsel for the RDA, this Court is satisfied that
the green area in the scheme, as per the terms of the environment
clearance is not violated. Even otherwise, it is to be seen that the
project is not an industrial project and there would be no such
pollution such as it happens in a chemical factory or thermal power
plant.
44. The petitioners have further assailed the Scheme on the
ground that environmental clearance has not been obtained
from appropriate authority i.e., the Central Government,
therefore, the Scheme is vitiated and deserves to be quashed on this
ground also. Indisputably, the environment clearance has been
obtained from State Level Environment Impact Assessment
Authority vide its order dated 25.01.2011. According to the
notification issued by the Ministry of Environment and Forest
(MOEF) dated 14.09.2006, there are two categories of projects,
namely Category ‘A’ and Category ‘B’, which require environment
clearance by the respective authorities. While category ‘A’ projects
have to seek clearance from Central Government, the projects
falling under Category ’B’ are required to seek clearance from State
39
Level Environment Impact Authority. The present project is covered
under Clause VIII (b) of the notification as it covers an area of more
than 50 hectares for township and area development projects and is
appraised as Category ‘B-1’ project.
45. In the return filed by the Central Government in W.P(C).
No.6040/2011 (the writ petition was later on withdrawn), the
Central Government has categorically stated that the subject project
has been duly cleared by appropriate authority i.e., the State Level
Environment Impact Assessment Authority. Thus, in view of the
categorical assertion by the central government, this Court has no
hesitation in holding that the respondents have obtained
environment clearance in terms of notification dated 14.09.2006.
46. Another argument has been raised that the notification
dated 04.03.2011 is not authenticated in terms of Article 166
of the Constitution of India, therefore, it is not a notification in
the eye of law and for this, the Scheme deserves to be quashed. The
respondent State has explained that when several notifications of
the concerned department are published together, it is the
established practice that the authentication as required under
Article 166 of the Constitution of India is mentioned in the last
notification of the series. Such practice has been approved to be a
valid exercise of power by a Division Bench of M.P. High Court in
the matter of Iftikhar Ahmed S/o Dost Mohammad vs. State of
Madhya Pradesh, AIR 1961 MP 140. In the present case also,
there are more than one notification including the notification dated
04.03.2011 which were published on the same day and the last
notification bears the authentication of the Governor, therefore, in
40
view of the law laid down by the M.P. High Court in the matter of
Iftikhar (supra), there is no substance in the argument raised by
learned counsel for the petitioners that the notification is not
properly authenticated.
47. Yet another ground has been raised by the petitioners that
the Scheme being essentially u/s 49(viii) of the Adhiniyam,
1973, no land can be acquired for the Scheme as the said
clause provides for reconstruction of plots for the purpose of
buildings, roads, drains, sewage lines and other similar
amenities but does not provide for acquisition of land for such
matters.
Section 49 of the Adhiniyam provides that the town
development scheme may make provision for any of the matters as
provided under Clauses (i) to (ix). Clause (iii) speaks about the
acquisition and development of land for public purposes such as
housing development, development of shopping centers, cultural
centers and administrative centers. Similarly, other clauses provide
for acquisition, development and sale or leasing of land for the
purpose of town expansion and for commercial and industrial
purposes; for the purpose of laying out or remodeling of road and
street patterns; for play grounds, parks, recreation centers and
stadia. Section 50 of the Adhiniyam prescribes the procedure as to
how a town development scheme is to be prepared and sub-section
(5) thereof provides for constitution of a Committee where the town
development Scheme relates to reconstitution of plots and the
Committee has been enjoined with the duty to consider several
aspects as mentioned in Clauses (i) to (vii) of sub-section (6) which
41
include evaluation of the value of original and reconstituted plots,
payments of compensation or obtaining contribution from the
beneficiaries of the Scheme on account of reconstitution of the plots
etc., etc. A conjoint reading of Sections 49 & 50 makes it absolutely
clear that the present Scheme is not only under Section 49(viii) but
it is a Scheme as a whole u/ss 49 & 50. The Entire procedure
prescribed u/s 50 has been followed by the RDA, therefore, the
arguments raised by the petitioners to the contrary by treating the
same as if it is a scheme only u/s 49(viii) is absolutely
misconceived.
48. The petitioner in W.P(C). No.759/2011 has argued that the
petitioner’s land is situated at a distance of more than one
kilometer from the terminal end of the scheme and is thus
segregated from the main area, yet his land has been included
in a malafide manner. He would submit that the land adjacent to
the petitioner’s land has been excluded from the Scheme and there
is no contiguity of the other scheme area with the area belonging to
the petitioner. According to the RDA, when the draft scheme was
notified inviting objections, the land of the petitioner was
contiguous, however, when a patch of thickly populated/densely
constructed area falling between the petitioner’s land and the main
scheme land was excluded upon considering the report of the
revenue authorities, petitioner’s land was segregated and it is not a
case that from the very beginning his land was included even
though it was segregated from the main area. The respondents
have further submitted that the petitioner’s land is connected with
the Scheme area through the Highway.
42
On perusal of the relevant map, it would appear that there are
other lands situated along-with the land of petitioner in W.P(C).
No.759/2011. There is village settlement of Dumartarai, which is
coming within the boundary of town development scheme.
However, the said area was left out to avoid large scale demolition
because it is thickly populated. Further the petitioner has not
raised any such objection regarding non-contiguity of the land when
the matter was considered by the Committee constituted u/s 50(5)
of the Adhiniyam. In Babulal Badriprasad Verma Vs. Surat
Municipal Corporation (2008) 12 SCC 401, it has been held that
if no objection is raised before the Committee in respect of the draft
scheme the petitioners are estopped from raising such contentions
before the writ court. Thus the petitioner is also estopped from
questioning the Scheme on this ground which was not raised before
the Committee.
There is yet another reason why this argument raised in
W.P(C). 759/2011 sans substance because the land in question is
covered under sector 14-B and 15-C of the sanctioned lay out plan
of the Scheme. These sectors cover an area of 22 acres belonging to
19 land owners. Thus, it is not a case where the petitioner has
been singled out for inclusion in the scheme and more over,
according to RDA all other land owners have either consented or
have not objected to the scheme as they have not preferred any writ
petition. Thus, the action of RDA in including the land belonging to
the petitioners of W.P(C). No. 759/2011 is not arbitrary or malafide.
49. The petitioners have also objected to the use of the term
“integrated township” in all the correspondences prior to
43
finalization of the Scheme to submit that the RDA, in fact, wanted
to frame a scheme for “integrated township” and not a town
development scheme and since “integrated township” is a concept
under “Bhumi Vikas Rules 1984”, the Scheme in question
prepared under the Adhiniyam 1973 is not in accordance with
law.
This Court has gone through the documents concerning the
procedure followed by the RDA for preparing/finalizing the Scheme
only to find that the RDA has never referred to Bhumi Vikas Rules
1984 (for short “Rules, 1984”) even though initially the term
“integrated township” was used. If the Scheme has been prepared
under the provisions of the Adhiniyam, 1973, mere use of the words
“integrated township” which is otherwise defined and used in the
Bhumi Vikas Rules, 1984, would not vitiate the exercise under the
Adhiniyam, 1973. Had it been a case that initially an “integrated
township” under the Rules, 1984 was conceived and processed but
it was left midway and thereafter the development authority took
shelter of the provisions of the Adhiniyam 1973, there might have
been some substance in the argument regarding nomenclature,
however, since Rules 1984 were never invoked, there is absolutely
no substance in the argument raised by the petitioners and this
ground of challenge must also fail.
50. It is settled law that when the decision making authority has
been vested with power to do a particular thing, mere quoting of
wrong provision does not invalidate the action. See MIG Cricket
Club Vs. Abhinav Sahakar Education Society (Supra). Drawing
the analogy from the said legal principle, this Court has no
44
hesitation in concluding that mere quoting of different name which
is otherwise referred in the Bhoomi Vikas Rules 1984, is not fatal
for the subject Scheme which is otherwise formulated under the
Adhiniyam 1973.
51. Having dealt with the grounds of challenge raised by the
petitioner, this Court deems it appropriate to refer to some other
aspects of the matter as they have material bearing on the outcome
of the writ petition and the respondents have also raised these
objections.
The petitioners have challenged the Scheme prepared by the
RDA on the ground that master plan has been notified after
preparation of the Scheme. However, they have chosen not to assail
the validity of the modified master plan. In absence of such
challenge, the revised plan has merged into and has become a part
of the original plan, therefore, once it is held that the modified
master plan cannot be quashed, the petitioners may not challenge
the Scheme on the ground that it is not in conformity with the
master plan. In fact, the Scheme itself could have been challenged
by the petitioners by filing a revision petition u/s 51 of the
Adhiniyam, however, none of the petitioners have preferred any
revision u/s 51 of the Adhiniyam and have chosen to approach this
Court directly. Many grounds have been raised before this Court
and they have been dealt with, however, most of the arguments
were not raised before the Authority or the Committee constituted
u/s 50(4) of the Adhiniyam. In Babulal Badriprasad Varma Vs.
Surat Municipal Corporation, (2008) 12 SCC 401 the Supreme
Court has held that once the petitioners filed objections but did not
45
pursue it, they cannot raise grounds at subsequent stage.
Similarly, in Sanjay Gandhi Grah Nirman Sahkari Sanstha
Maryadit Vs. State of Madhya Pradesh, AIR 1991 MP 72, it has
been held by the M.P. High Court that the petitioners could have
placed all the facts in detail before the revisional authority and had
an opportunity to say that the action of the Development Authority
is discriminatory, but it appears that the petitioners claiming
discrimination had not resorted to this remedy available to them.
Therefore, such plea cannot be considered. Similar is the law laid
down by the Supreme Court in the matter of Raipur Development
Authority Vs (RDA) Vs. Anupam Sahkari Griha Nirman Samiti
(2000) 4 SCC 367. The petitioners have raised grounds regarding
non-issuance of notice in prescribed form or other kinds of
procedural violation. In this context, this Court would refer to
judgment of Supreme Court in the matter of Shambhu Prasad
Sharma Vs. Charandas Mahant and others (2012) 11 SCC 390
wherein it has been held that when a substantial compliance with
the requirement as to form is made, every departure from the
prescribed format cannot be made a ground for rejection of
nomination paper. Thus if the substantial compliance has been
made which this Court has already found to have been complied
with, the impugned Scheme cannot be quashed.
52. For the foregoing reasons, this Court does not find any
substance in any of the writ petitions. Consequently, all the writ
petitions fail and are hereby dismissed.
JUDGERao