HIDD HEIGHTS PROGRESS REPORT About the Project:
Project Developer Bin Faqeeh Real Estate Investment Company S.P.C.
Title of Project Hidd Heights
Project Reference BFHH/22/0102-2802/2019
Design & Supervision Consultant
Salah Alkooheji
Interior Design Consultant
Dar Al Décor
Main Contractor Al Jameel Construction SPC
About Progress Report:
Title of Document Progress Report of Hidd Heights
Reporting Period February 1, 2019 to February 28, 2019
Authors & project role United Arab Construction Co. (UACC)
Date March 14, 2019
DESCRIPTION PERCENTAGE
(%) OF COMPLETION
REMARKS
SUB STRUCTURE
1. Excavation 100% Completed
2. Dewatering 100% Completed
3. Pile Cutting 100% Completed
4. Back Filling and Compaction for Pile Cap 100% Completed
5. Pile Cap 100% Completed
6. Tie Beam 100% Completed
7. Water Tank 100% Completed
8. Grade Slab 100% Completed
9. Septic Tank 100% Completed
10. Substation 99% In Progress
SUPER STRUCTURE
Ground Floor
1. Lift Core Wall 100% Completed
2. Column and Shear Wall 100% Completed
3. Ramp and Staircase 100% Completed
4. 1st Floor Slab 100% Completed
1st Floor
1. Lift Core Wall 100% Completed
2. Column and Shear Wall 100% Completed
3. Ramp and Staircase 100% Completed
4. 2nd Floor Slab 100% Completed
2nd Floor
1. Lift Core Wall 100% Completed
2. Column and Shear Wall 100% Completed
3. Ramp and Staircase 100% Completed
4. 3rd Floor Slab 100% Completed
3rd Floor
1. Lift Core Wall 100% Completed
2. Column and Shear Wall 100% Completed
3. Shear Wall 100% Completed
4. 4th Floor Slab 100% Completed
4th Floor to 11th Floor
- Column and Shear Wall 100% Completed
- Lift Core Wall 100% Completed
- 5th to 12th Floor Slab 100% Completed
12th Floor
- Column 100% Completed
- Shear Wall 100% Completed
- Lift Core Wall 100% Completed
- Roof 100% Completed
SUPERSTRUCTURE
Block Work
- Ground Floor 100% Completed
- 1st Floor to 2nd Floor 100% Completed
- Podium Floor 100% Completed
- 1st to 9th Typical Floor 100% Completed
- Roof 100% Completed
Plastering Work
- Ground Floor 100% Completed
- 1st Floor to 2nd Floor 100% Completed
- 1st to 9th Typical Floor 100% Completed
- Podium Floor 100% Completed
Painting Work – Wall and Ceiling (1st Primer & 1st Coat Filler / 2nd Coat Filler & 1st Coat Paint)
- 1st Floor to 2nd Floor 100% Completed
- 1st Typical Floor to 3rd Typical Floor 100% Completed
- 4th Typical Floor to 9th Typical floor 100% Completed
Painting Work – Wall and Ceiling (2nd Coat Filler / 2nd Coat Paint)
- GF 80% In Progress
- 1st Floor 10% In Progress
- 2nd Floor, Stair 2 & Podium Floor 100% Completed
- 1st Typical to 8th Typical (Flats) 100% Completed
Gypsum Work
- 1st Typical Floor to 9th Typical Floor (Living, Kitchen, Bedrooms & Toilets)
100% Completed
- Podium Floor 100% Completed
Wall Cladding
- 1st Typical Floor to 9th Typical Floor 100% Completed
- Ground to Podium Floor 100% Completed
Lift Lobby Wall Cladding
- 1st to 9th Typical Floor 100% Completed
- Ground to Podium 100% Completed
Floor Tile
- 1st Typical Floor to 9th Typical Floor 100% Completed
- Podium 100% Completed
Wall Tile
- 1st to 9th Typical Floor 100% Completed
- Podium 100% Completed
Marble Work
- GF to 9th Typical Floor - Corridor 100% Completed
WATERPROOFING
Toilets
- 1st Typical Floor to 9th Typical Floor 100% Completed
Balcony
- 1st Typical Floor to 9th Typical Floor - Corridor
100% Completed
ROOF WATERPROOFING
Roof – PU Foam 100% Completed
Geotextile covering 100% Completed
Light Weight Screed 100% Completed
Membrane 100% Completed
Ground Floor Paving and Curbe Work
- Parking in Ground Floor 100% Completed
- Parking in Entrance Area 100% Completed
Epoxy Floor in Super Structure
- 1st Parking 100% Completed
- 2nd Parking 100% Completed
Parking Wheel Stopper
- 1st and 2nd Parking 100% Completed
Corner Guard
- GF, 1st and 2nd Parking 100% Completed
On-site photos:
(Structural Elevation)
(Structural Elevation)
(Final coat paints for Electricl Room at GF) (Final coat painting at Poduim Floor)
(Fixing of wheel stopper and number at 1st & 2nd parking floor)