HERRENKNECHT State of the Art Tunnel Boring Machines
27th June 2013
W i l m S c h a u b
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 2 17 June 2013
Population growth
Rapidly advancing urbanization
New high-capacity infrastructures to keep people, goods, and resources on the move
Refurbishment and extension of existing underground infrastructure
Congested arrangement of structure in the urban underground
Building of new and extension of existing high-speed train networks
Hydropower Projects
Fresh Water Supply
Irrigation and Sewage
GLOBAL TRENDS
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 3 17 June 2013
Longer Drives
Larger Profiles
Capability to handle high pressure
Capability to excavate in heterogeneous ground conditions
Special reference projects
Answer and Questions
AGENDA : TUNNELLING REQUIREMENTS
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 4 17 June 2013
1985: HERA 5.95m
1996: Sydney 10.70m
1997: Hamburg 14.20m
2011 St. Petersburg
19.25m
2006: Shanghai 15.43m
MIX-Shields
LONGER DRIVES & LARGER PROFILES
DEVELOPMENT OF DIAMETER
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 5 17 June 2013
S-317/318 CHANGJIANG UNDER RIVER TUNNEL | SHANGHAI | CHINA
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 6 17 June 2013
Connection between Pudong and Changxing
Geology consisting of Sand & Clay
2 Double-deck road tunnels:
Upper level: 3 lanes
Lower level: service +safety
Segment OD: 15.00 m
Segment ID: 13.70 m
Tunnel length: 7.170 km each
Yangtze River Crossing: Maximum overburden above tunnel axis: 65m
S-317/318 │THE PROJECT DETAILS
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 7 17 June 2013
MIX-Shield®
Shield = 15.43m
Cutter Head accessible under atmospheric conditions from the arms
Main drive = 7.6m with total power of 15x250kW = 3750kW
Back-Up with installation equipment for road element
Total machine length 130m
S-317/318 │THE MACHINE DETAILS
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 8 17 June 2013
S-317/318 │CUTTER HEAD DESIGN
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 9 17 June 2013
S-317/318 BACK-UP SYSTEM FOR ROAD ELEMENT INSTALLATION
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 10 17 June 2013
CHONGMING UNDER RIVER TUNNEL PROJECT
MIXSHIELD S-317/318
0
20
40
60
80
100
120
140
160
180
37 41 45 49 1 5 9 13 17 21 25 29 33 37 41 45 49 1 5 9 13 17 21 25
me
ter
week 2007
weekly advance
2006
S-317 Shanghai
2008
0
20
40
60
80
100
120
140
160
180
2 7 12 17 22 27 32 37 42 47 52 5 10 15 20 25 30 35 40 45 50
me
ter
week 2007
weekly advance
2008
S-318 Shanghai
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 11 17 June 2013
May 28, 2008 September 5, 2008
BREAKTHROUGH OF THE WORLD‘S LARGEST TUNNEL BORING
MACHINES.
ABOUT 1 YEAR AHEAD OF TIME.
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 12 17 June 2013
Tunnel Length = 3.6 km
Ø = 11.61m MIX Shield
Total Thrust Force: 123000 kN
Max. Op. Pressure: 7.5 bar
Smallest accessible chamber cutter head for tool exchange under atmospheric conditions
Main Drive Power: 2750 kW
S-668 NANJING METRO LINE 10 LOT 3
H E R R E N K N E C H T A G | U T I L I T Y T U N N E L L I N G | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 13 17 June 2013
S-762 ISTANBUL STRAIT CROSSING
Trakya Formation (sandstone/mudstone/dykes)
Transition Zones (rock, soil, gravel, cobbles)
Marine Deposits (sand + clay)
H E R R E N K N E C H T A G | U T I L I T Y T U N N E L L I N G | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 14 17 June 2013
Bore Diameter 13,690 mm
Shield Diameter 13,660 mm
SHIELD CONCEPT.
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 15 17 June 2013
SHIELD DIAMETER CONCEPT.
Main Dimensions
Bore Diameter 13,690 mm
Front Shield Diameter 13,660 mm
Tailskin Diameter 13,620 mm
Outer Lining Diameter 13,200 mm
Ring building clearance
(Deflector strip) = 2 x 45 mm
New features
Camera units 5 No. (transfer chamber & cutter chamber)
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 16 17 June 2013
ISTANBUL STRAIT ROAD CROSSING | MIXSHIELD WITH ACCESSIBLE
CUTTING WHEEL.
5 Main arms (atmospheric accessible)
Center (Main atmospheric access)
5 Side arms (Chamber access)
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 17 17 June 2013
ISTANBUL STRAIT ROAD CROSSING | MIXSHIELD WITH ACCESSIBLE
CUTTING WHEEL.
Cutters 35 No. x 19”
Twin disc Monobloc.
Pressure compensated
Spacing 100 mm
(120 mm center)
Scrapers 32 No. x 250 mm
Atmospheric accessible
Scrapers 90 No. x 220 mm
Buckets 2 x 10 No.
Flushing
outlets 7 No.
Sizers 800 mm
(max. 1,200 mm)
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 18 17 June 2013
1991: Taipei 6.26m
2000: Madrid 9.33m
2003: Barcelona 12.06m
2010: Sparvo 15.50m
2006: Madrid 15.20m
EPB-Shields
DEVELOPMENT OF DIAMETER
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 19 17 June 2013
DEVELOPMENT OF TORQUE IN MIXSHIELD AND EPB TUNNELLING
Diameter [m]
Torq
ue [
kN
m]
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 20 17 June 2013
S-574 GALLERIA SPARVO = 15.615M – HERRENKNECHT EPB SHIELD.
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 21 17 June 2013
Torque: 94.800kNm
Breakout Torque : 125.000kNm
MAIN DRIVE
Power: 12.000kW
Speed: 2,16 rpm
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 22 17 June 2013
12 electric motors with 1.000 kW each
50 hydraulic motors with a torque of 2.387 Nm each
50 planetary gearboxes with transmission ratio of 51,42
Creating a max. total cutterhead torque of: 125.268 kNm
CUTTERHEAD DRIVE.
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 23 17 June 2013
315.000kN @ 400bar
THRUST FORCE
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 24 17 June 2013
CAPABILITY TO HANDLE HIGH PRESSURE
DEVELOPMENT OF OPERATION PRESSURE
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 25 17 June 2013
S-502 Lake Mead, Intake No. 3 | Las Vegas | USA
Dual-Mode TBM - Hard
Rock /Mixshield
Diameter: 7,180mm
Tunnel length: 4,800m
Cutterhead power: 2,800kW
Geology: Basalt, sandstone,
amphibolite, conglomerate
S-502 │LAKE MEAD, USA
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 26 17 June 2013
Sedimentary and volcanic geology
Depth of the tunnel
Potential for high groundwater inflows and high hydrostatic pressures
CHALLENGES IN MECHANIZED TUNNELLING.
GROUNDWATER PRESSURE.
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 27 17 June 2013
CAPABILITY TO EXCAVATE IN HETEROGENEOUS GROUND CONDITIONS
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 28 17 June 2013
SINGAPORE – CUSTOMIZED SOLUTIONS FOR CHALLENGING PROJECTS
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 29 17 June 2013
• The Mixshield is an improvement of the original slurry techniques
• Invented by HERRENKNECHT and WAYSS & FREYTAG in the 1980’s
• Designed for a more accurate face pressure control and thus to minimise the risk of settlements
MIXSHIELD TECHNOLOGY
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 30 17 June 2013
SLURRY SHIELD - MIXSHIELD
Hydraulic
transport cycle
Bulk head
Air bubble
Bentonite
suspension
Bulk head
Hydraulic
transport cycle
Slurry Shield Mixshield
without air bubble with air bubble
Bentonite
suspension
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 31 17 June 2013
MIXSHIELD - ACCURATE FACE PRESSURE CONTROL
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 32 17 June 2013
1. Cutting Wheel
2. Bulkhead
3. Air – Cushion
4. Submerged Wall
5. Slurry Line
6. Stone-crusher
7. Feed Line
8. Erector
MIX – SHIELD
1
2
3
4
5 6
7
8
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 33 17 June 2013
PRESSURE REGULATION ACCURACY
0
1
2
3
0 10 20 30 40 50
time [sec]
Support Pressure MIX Shield - Double Chamber
Reference Pressure Support Pressure Slurry Shield - Single Chamber
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 34 17 June 2013
TBM DESIGN
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 35 17 June 2013
Optimized design in terms of machine length
Customized design for various operation pressures
Thrust Cylinder arrangement solutions for 5+1 and 7+1 segment lining
SHIELD
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 36 17 June 2013
Dual man lock design 2 x (3+2)
Operating pressure: 7 bar
Complies to CENEN12110 regulations
Fully equipped for compressed air works
Manufactured and tested in Germany
Oxygen Decompression System
SHIELD – MAN LOCK
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 37 17 June 2013
Independent Lock for transfer of cutting tools from and to the excavation chamber
No obstruction in air lock
Safe for workers
SHIELD – MATERIAL LOCK
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 38 17 June 2013
SHIELD – SLURRY CIRCUIT
Injection Lines for bentonite on various positions of pressure wall and submerged wall
Discharge line in shield invert
Heavy duty hydraulic driven ball valves for operation from the control cabin
Chamber flushing
Clogging prevention
Crusher flushing
Pipe bends made of extra wear resistant material
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 39 17 June 2013
If the geology bears an increased risk of clogging, the submerged wall gate opening could cake up gradually and eventually be completely closed. This could lead to a pressure rise in the excavation chamber.
With a communicating pipe, the bentonite which is pumped into the excavation chamber can flow via the communicating tube and thus prevent a sudden pressure rise in the excavation chamber.
SHIELD – SLURRY CIRCUIT – COMMUNICATING PIPE
[1] Excavation chamber [2] Working chamber [3] Communicating tube [4] Feed line [5] Slurry line [6] Clogged submerged wall door
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 40 17 June 2013
= 700mm crushing size
Wiping mode for clogging prevention in softground
Optimized hydraulic connection lines
Independent hydraulic power pack
Grid in front of discharge line to prevent large obstacles from entering the slurry circuit.
STONE CRUSHER
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 41 17 June 2013
2 x high performance rock drills mounted on 360° drill rig
Inclined probe holes through TBM shield
Horizontal probe holes through TBM shield and cutting wheel
1 x adjustable center probe drill hole
PROBE DRILLING
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 42 17 June 2013
PROBE DRILLING – DRILLING PATTERN
Inclined probe drill lines
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 43 17 June 2013
Horizontal probe drill lines
PROBE DRILLING – DRILLING PATTERN
Center inclined probe drill lines
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 44 17 June 2013
Combined drilling pattern
PROBE DRILLING – DRILLING PATTERN
H E R R E N K N E C H T A G | U T I L I T Y T U N N E L L I N G | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 45 17 June 2013
Blow out preventer Equipped with rotating seal, pressure relieve valve, mechanical clamping and manual ball valve
PROBE DRILLING – BLOW OUT PREVENTER
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 46 17 June 2013
Heavy Duty Robust Structure
Adaptation of proven solutions
Implementation of experience gained from former Herrenknecht projects with MIX-Shields in Rock and Mixed Face conditions.
FE Analysis to meet the requirements of the project
CUTTING WHEEL - STRUCTURE
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 47 17 June 2013
19” center disc cutter
19” face and gauge disc cutter
Scrapers
Bucket lips
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 48 17 June 2013
CUTTING WHEEL – SHIFTING OF GAUGE DISCS
Shifting of Gauge
Discs by C-Piece with
full load capacity for
overcut in curve
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 49 17 June 2013
Durable heavy duty mounting system for rock application
Load transfer through the housing into the steel structure of the cutting wheel
Wedge to fix the cutter axis
CUTTING WHEEL – WEDGE LOCK MOUNTING
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 50 17 June 2013
CUTTING WHEEL – PRESSURE COMPENSATING DISCS- FOR HIGH
OPERATION PRESSURE
For a standard disc cutter, there is no pressure compensation. Under high pressure (>3.5bar), the external pressure is higher than the internal pressure.
For non P.C unit, high pressure (>3.5bar) can result in slurry and muck pressing against seal sets and contaminating inside of disc cutters
Damage of the seal sets reduces the lifetime of the cutter and higher cost of refurbishment of cutters
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 51 17 June 2013
Herrenknecht pressure compensating discs use a bladder design that is installed into the shaft. The balance of the pressure is through the compensating bore in the shaft
P.C unit is balancing the pressure difference at the seal sets
The bladder is easy to change and maintain
P.C cutters ensure a higher lifetime, reduce risk of bearing failure and reduce refurbishment cost of cutters
Project references:
S502 Lake Mead
S536 Hong Kong Lai Chi Kok
S548/549 Singapore DTL2
S602/603/604/605/617 Singapore DTL2
CUTTING WHEEL – PRESSURE COMPENSATING DISCS- FOR HIGH
OPERATION PRESSURE
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 52 17 June 2013
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 53 17 June 2013
Hydraulic Wear detectors for Disc Cutter
Hydraulic Wear detector for Steel Structure
Circumferential GRILL BARS Hardox 400 – HRC 40
Circumferential welded Hardfacing on shield edge. HRC 56
VAUTID Plates on front surface HRC 60
CUTTING WHEEL – WEAR DETECTION&PROTECTION
GRILL BARS Hardox 400 HRC 40
HARDFACING On shield edge HRC 56
VAUTID PLATES 100 x 100 mm HRC 60
Wear detector For cutting wheel structure
Wear detector For disc cutter
H E R R E N K N E C H T A G | U T I L I T Y T U N N E L L I N G | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 54 17 June 2013
Down to the present day, this is the only TBM‘s of this kind. Especially it is developed to handle the karstic geology of Kuala Lumpur.
Convertible between 4 different advance mode
LATEST DEVELOPMENT: VARIABLE DENSITY TBM
H E R R E N K N E C H T A G | U T I L I T Y T U N N E L L I N G | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 55 17 June 2013
EPB – Mode
Support medium pasty earth cake
EPB – Mode with bentonite support
Support medium pasty – liquid earthcake
2
Mixshield – Mode
Thin suspension (bentonite suspension)
1 4
HDSM – Mode
Thick suspension (bentonite suspension with
filter)
3
WORKING MODES WITH THE DIFFERENT SUPPORT MEDIA.
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 56 17 June 2013
VARIABLE DENSITY SYSTEM.
Excavation & Working chamber
Air bubble
Screw conveyor
Flushing box
with the crusher
High density
slurry
Slurry pump
Feed line
Slurry circuit
Slurry line
H E R R E N K N E C H T A G | U T I L I T Y T U N N E L L I N G | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 57 17 June 2013
Apart from tunnel face support, material transport can also be changed in line with the respective geology. The system can switch from hydraulic transportation via pipeline to solid transportation via belt conveyor or muck car haulage.
MUCK TRANSPORTATION
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 58 17 June 2013
SPECIAL REFERENCE PROJECTS
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 59 17 June 2013
Convertible EPB / Single Shield
Shield = 10.02 m
Operating Pressure 3.0bar
Tunnel Length 2 x 3860m
Convertible Cutter Head
Simultaneous installation of screw conveyor and conveyor belt in shield for quick conversion
S-670 │CONVERTIBLE EPB / SINGLE SHIELD
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 60 17 June 2013
S-670 │CONVERTIBLE EPB / SINGLE SHIELD
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 61 17 June 2013
S-575 | Linth Limmern | Switzerland
Gripper-TBM
Diameter: 5,200mm
Tunnel length: 2 x 1,000m
Cutterhead power: 2,205kW
Geology: limestone
Incline: 85% 40°
Customer: Marti Tunnelbau
40° INCLINE TUNNEL FOR HYDROELECTRIC POWER.
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 62 17 June 2013
PUMPED STORAGE HEPP LIMMERN / SWITZERLAND.
TRANSPORT TO THE JOBSITE BY CABLE-CAR.
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 63 17 June 2013
H E R R E N K N E C H T A S I A H E A D Q U A R T E R S | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 64 17 June 2013
Machine type: Gripper TBM
Diameter: 5,200mm
Tunnelling length: 1,045m
Gradient: 40.3°
Commissioning: 24.06.2010
Breakthrough: 14.10.2011
Best daily performance: 28.8m
Best weekly performance: 132.6m
PUMPED STORAGE HEPP LIMMERN / SWITZERLAND.
BREAKTHROUGH FIRST TUNNEL ON OCTOBER 14, 2011.
H E R R E N K N E C H T A G | U T I L I T Y T U N N E L L I N G | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 65 17 June 2013
Mechanized enlargement of existing railway tunnels
Maintains route availability with relatively little reconstruction work
RAILWAY TUNNEL ENLARGEMENT – RESEARCH AND DEVELOPMENT
H E R R E N K N E C H T A G | U T I L I T Y T U N N E L L I N G | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 66 17 June 2013 Page 66
Tunnelling projects all over the world are demanding TBM technology with permanently higher requirements on the TBM design especially in regards of:
settlement control
operation effeciency
labour safety
operating loads (water pressure, overburden)
adaptability to multiple kinds of geology (Multi Purpose TBM)
cost efficiency
SUMMARY- PERSPECTIVES
H E R R E N K N E C H T A G | U T I L I T Y T U N N E L L I N G | T R A F F I C T U N N E L L I N G
Wilm Schaub Slide 67 17 June 2013 Page 67
As a supplier of Tunnel Boring Machines, Herrenknecht is continuously striving to optimize and extend the TBM product portfolio .
A few exemplary development steps are:
Cutting Wheel geometry closely adapted to project geology (Custom made)
More wear resistant cutting tools and wear parts
Spherical- and displacable main drives
Accessable Cutting Wheels (smallest Diameter= 11,62m, S-668 Nanjing), extended application range
Improved tailskin sealing systems
Double Screw Conveyor (mainly Chinese market)
More accurate Muck control systems
Geology exploration systems
Data monitoring/ recording systems
SUMMARY- PERSPECTIVES
THINK POSITIV.
TOGETHER WE BUILD THE FUTURE.
Thanks for your attention. THANKS FOR YOUR ATTENTION!