Upload
brittany-barnett
View
212
Download
0
Embed Size (px)
Citation preview
Johan Bremer
Helium Spill Test in LHC tunnelto define length of restricted working areas
Actual situation Evolution How to continue Set-up of the spilling test
How Where When Risks
On-going work Conclusions
01/11/2013
Johan Bremer
Helium Spill Test in LHC tunnelActual situation
01/11/2013
LHC Project Report 684*: header Caverage flow 1 kg/slength helium jam 6 m
After discussion (HSE and DSO): make restricted work area of 3 m, centred around release point.
*SUMMARY OF THE EXPERIMENTAL STUDIES OF COLD HELIUM PROPAGATION ALONG A SCALE MODEL OF THE LHC TUNNEL (2003)
Johan Bremer
Helium Spill Test in LHC tunnelEvolution
01/11/2013
New proposal based on scale model
New proposal based on simulations
~100 m
Restrictedworking-area
50 + 30 m(45 % of tunnel)
Vacuum barrier Pressure reliefdevice (w/o spring)
VentilationJumper
Restrictedworking-area
6 + 6 m(9 % of tunnel)
Johan Bremer
Helium Spill Test in LHC tunnelHow to continue
01/11/2013
Large difference between proposal based on scale model and proposal based on simulation work
Make a representative spilling test in the tunnel to check the validity of the different models and calculations and base new access rules on these validated
calculations:
Liquid helium spill of 1 kg/sTotal spill per test 125 kg (= 1000 liquid liters)
Ventilation flow in access mode: 18000 m3/h, about 0.7 m/s in tunnel
Johan Bremer
Helium Spill Test in LHC tunnelSet-up of the spilling test: how
01/11/2013
Pressurize dewars with warm helium gas taken from cylinder. The liquid mass flow will be measured by balances on which the dewars will be placed
1450 mm
DN 200
Dewar: Design pressure 2 barSafety valve 0.5 barPressure drop system 0.1 bar
Johan Bremer
Helium Spill Test in LHC tunnelSet-up of the spilling test: how
01/11/2013
Equip the tunnel with measurement system 25 Temperature sensors (Pt100) 25 ODH (special development of fast reacting measurement head) 6 cameras 4 air velocity sensors 2 mass balances (used for calculation of mass flow)
Equipment will be placed on 15 stands, 8 downstream (over 200 meter) and 7 upstream (over 100 meter) of ventilation direction, at places referenced to the simulation model
Most sensors will be placed at 1.75 m height, in passage area
Total of two to three tests will be made
Johan Bremer
Helium Spill Test in LHC tunnelSet-up of the spilling test: where / when
01/11/2013
Test should be made at a point where the ventilation flow is out-going (un-even point)
Test should be made at the end of continuous cryostat section, to minimize effect on the chosen sector
Test should be made where there is least interference with on-going work
The ODH sensors have to be developed (fast reacting sensors not available on the market)
Discussion with SMACC, VSC and coordination:
Test foreseen for end of January 2014 in sector 4-5, left of 5,300 meter into arc
Johan Bremer
Helium Spill Test in LHC tunnelSet-up of the spilling test: risk
01/11/2013
Risk assessment based on LHC sector 3-4 experience and modelisation:
Sector 3-4 Estimate of situation during helium release*:
first 40 sec helium flow: 15 to 26 kg/s (spill: 1 kg/s)
helium mass released first 120 sec : 2000 kg (spill: 125 kg)
No explicit damage to tunnel structure, cable trays, electrical cabinets, cryogenic piping / valves etc, directly related to helium flow
Modelisation helium spill in XFEL tunnel**: Modeled helium flow in the range of spill test; Maximum temperature drop of mechanical equipment in the tunnel is
not going over 40 degrees (if jet not directed onto equipment)
Conclusion: very confident that collateral damage is excluded, but…..* CERN-ATS-2009-002: Task Force Report: Safety of Personnel in LHC underground areas following the accident of 19 th September 2008**Simulation study of helium release in the XFEL tunnel, WUT-ref:#630333/I22-01
Johan Bremer
Helium Spill Test in LHC tunnelSet-up of the spilling test: risk
01/11/2013
Helium spill tests will only be performed outside of normal working hours (no access in sector 4-5)
Interconnects will be closed in area in which the spill test will find place
All equipment owners in the area where the spill test will find place, are asked to protect their sensitive material (electronic cards, connectors etc.) against condensation of water during and directly after the spilling test
* Simulation study of helium release in the XFEL tunnel, WUT-ref:#630333/I22-01
Johan Bremer
Helium Spill Test in LHC tunnelon-going work
01/11/2013
Prototype of ODH system under test
Instrumentation for test has been ordered, DAQ-chain being programmed
Full instrumentation test by end of November
Testing of emptying by pressurization at this moment with LN2
Discussion with LHC coordination
First discussion on how to implement future test results on “restricted working areas” will start shortly
Johan Bremer
Helium Spill Test in LHC tunnelConclusions
01/11/2013
No consistent data to support length of “restricted working areas” in LHC tunnel
Existing models have to be verified with “real life” spilling test
Necessary equipment and instrumentation has been identified
Possibility of collateral damage has been classified as minimal
Equipment owners have to be aware of eventual water condensation on their equipment
Cost of test: about 110 kCHF, without helium (6000 CHF / test)
Tests will take place during last week of January in sector 4-5 left of 5, first 300 meter into the continuous cryostat