Jonas Kimontas
HEKLA : LNG Reloading Station project
Photo A. Kubaitis
8th of March, 2016 Sopot
2
Expected project timeline
Preparatory works
(partially financed by EU)
Construction works
Commercial part
Financing
2014 2015 2016 2017
EIA screening
Technological
concept FEED
EPC tender EPC contract
Bid for EU
subsidy
Financing from institutional banks (EIB, NIB)
Market consultation
Preliminary capacity
reservation agreements
Off-take contracts
Detailed scheduling
Commissioning and
start-up
3
Key Results
8 December 2014
Design company assigned
March 2015
Technological concept
27 March 2015
Business plan presentation to the Board
10 July 2015
Approved support from EC
26 August 2015
FID
24 November 2015
EPA conclusion on EIA
1 July 2015
Tender launched
12 February 2016
Winner awarded
2014 2015 2016
July 2015
Engineering and geotechnical surveys of the soil
August 2015
Other infrastructure preparation works were commenced
4
LNG reloading station concept
KN oil terminal
LNG supply route FSRU
LNG Supply Route
LNG unloading
FSRU Independence
LNG LNG
LNG LNG
LNG reloading service
(regulated service by the Operator)
LNG transportation
LNG reloading into LNG trailers
Integrated service LNG Reloading station
Flexible hose LNG dispenser
LNG trailer C-type containers
5
Synergies with oil terminal
LNG loading and
bunkering location
Boil off would feed existing boilers
Existing jetty sufficient to hold required equipment
Existing firefighting systems
Instrument air and electrical systems
Qualified staff
Existing sufficient security measures
Truck loading performed already (light oil products)
Safe distance from neighbors
6
Technological concept
BOG management unit
LNG pumps
LNG storage
5x1.000m3
LNG loading from small-
scale carrier (1.000m3/h)
LNG reloading
(bunkering) to ships
LNG reloading to trucks
(2-3 loading bays)
LNG
LNG
LNG
Gas fired heating
boilers
LNG
LNG
LNG
LNG
LNG
LNG