102
Headgear Erection The Impala 17 Shaft Experience Michael Yates AMRE Safety Seminar 18 September, RPM Club: Lifting Operations

Headgear Erection - amre.org.za

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Headgear Erection - amre.org.za

Headgear ErectionThe Impala 17 Shaft ExperienceMichael Yates AMRE Safety Seminar 18 September, RPM Club: Lifting Operations

Page 2: Headgear Erection - amre.org.za

Introduction

Page 3: Headgear Erection - amre.org.za

Introduction

Impala 17 Shaft Headgear Tower type headgear propped on two sides 81m to the top of the crane rail Centre tower foot print is 14m by 14m square The two braced raking back legs extend to about 42m from the shaft

centre line

Page 4: Headgear Erection - amre.org.za
Page 5: Headgear Erection - amre.org.za

Multi Phase Design

It must accommodate 3 conditions Sinking, development and construction – from 2009 to 2017 Equipping and commissioning – from 2017 to 2018 Permanent condition – for the productive 30+ year life of the mine

Page 6: Headgear Erection - amre.org.za

Design: Working Condition

Raking legs for two ground mounted Koepe winders placed at 90° angles to one another

The deepest Koepe wind to date at 1932m deep Skips running at 18m/s with hoisting capacity of 33 ton Man cage is a double deck cage with counterweight and

accommodates 150 men per deck Service cage is also a double deck cage to take 54 men per

deck and with planned slinging capability of 8 ton

Page 7: Headgear Erection - amre.org.za

Design: Emergency Condition

The headgear is designed for 1.5 times breaking force of 6 50mm ropes

This factor compliments the winder base design Incredible force of 2500kN per rope = 22,500kN. This force is directed from the 60m level through the back

legs into the ground This causes a substantial torque on the head frame

Page 8: Headgear Erection - amre.org.za

Fabrication

Large sections to handle in a workshop i.e. plate girder in the order of 2.5m deep

Heavy cruciform column sections Pin and bracket assembly for the raking legs Large trial assemblies of the floors in the workshop

Page 9: Headgear Erection - amre.org.za

Headgear Erection

Site establishment was in August of 2008 The erection duration was 7 months and ended in February

2009 The final paint coat was applied just prior to assembly and

erection on site Lower four floors were assembled with the columns on

erection bases adjacent to the headgear From the 38.5 m level up the erection was carried out

piecemeal Single beams with a mass of 25 tons were lifted to heights of

up to 70 m

Page 10: Headgear Erection - amre.org.za

Erection Overview

The stair access tower was to be erected in sequence with the floor levels

The headgear tower was erected well within the code requirements (32mm deviation at the top and 140mm is allowed in the code)

The back legs were erected in two preassembled sections, each weighing 80 tons

Page 11: Headgear Erection - amre.org.za

Interesting Facts

Page 12: Headgear Erection - amre.org.za

Interesting Facts

Impala 17#, Rustenburg 2009

81.0m

Page 13: Headgear Erection - amre.org.za

Interesting Facts

69281 Bolts supplied1850 Total tonnage1430 Tons painted420 Tons galvanized1099 m handrails1200 m² flooring406 Stair treads

100000 Manhours on site20000 m welding

8679 Individual pieces of steel2650 Drawings generated

150000 km's for transport and delivery

Page 14: Headgear Erection - amre.org.za

Preparation

Page 15: Headgear Erection - amre.org.za

Detailed risk assessment carried out in June 2008, aspects considered: Assembly and disassembly of the lattice cranes Crane erection Use and movement of the cranes Preassemble and erect the headgear tower Preassemble and erect the raking legs

Risk Assessment

Page 16: Headgear Erection - amre.org.za

Aspects considered: Failure of the equipment; ropes, brakes and components Incorrect operation of the crane; incompetency, lack of skill Injury to persons, damage to equipment; unsafe rigging methods Concurrent activities in the work area; falling objects, poor

communication Inclement weather; wind, rain, lightening, cold, heat Incorrect material handling; unskilled labour, lack of supervision, poor

planning Incorrect rigging; lack of knowledge, lack of training, non adherence to

standards Lifting point failure; poor design, poor installation, shock loading Working at heights; poor housekeeping, slippery surfaces, inclement

weather

Risk Assessment

Page 17: Headgear Erection - amre.org.za

Aspects considered Exposure to hazardous substances; inhalation of fumes, contact of

products Concurrent activities in the work area; falling objects, poor

communication Fire; hot work, electrical failure Non adherence to legal requirements; relevant acts Poor communication; lack of coordination, poor attitude, poor planning Unsafe ground conditions; compaction, rain, sub surface structures Unsafe scaffolding; standards, uncertified erectors, poor ground

conditions, equipment, poor design

Risk Assessment

Page 18: Headgear Erection - amre.org.za

Aspects considered Collapse of trestles; poor design, uneven loading, unstable ground Poor fitting of HD bolts; incorrect survey, negligence, dimensional

errors Limited access for haulage; close proximity of winder buildings Poor ergonomics; nature of the design Suspended platforms; ergonomics, overloading, mechanical failure

Risk Assessment

Page 19: Headgear Erection - amre.org.za

Alternative Crane Arrangements

Page 20: Headgear Erection - amre.org.za

Underground structures required support: Beneath the terrace adjacent to the main shaft are there the access-

ways and a service duct. These were assessed and it was decided to brace and prop these

structures. Areas were demarcated where the assembly cranes were not allowed

to access

Site Preparation

Page 21: Headgear Erection - amre.org.za

Propping Underground Structures

Page 22: Headgear Erection - amre.org.za

Lift Planning

Page 23: Headgear Erection - amre.org.za

Detailed lift planning was carried out considering: Positioning of the main cranes for each lift. Mass and height of each lift. Lifting equipment to be used. Spreader beams required.

Lift Planning

Page 24: Headgear Erection - amre.org.za

Headgear Layout

Raking Legs

Tower Structure

Crane Gantry

Page 25: Headgear Erection - amre.org.za

Establish 400Ton Lattice with 66m Main Boom, 120T Counterweight and 130T Superlift Counterweight

Page 26: Headgear Erection - amre.org.za

Lift 1st Floor (14.5m Lvl) from preassembly pad over Matla HeadgearMass of lift 130 Ton

Page 27: Headgear Erection - amre.org.za

Move crane back and lift 2nd Floor (20.5m Lvl) From 2nd preassembly pad onto headgear. Mass of Lift 55 Ton

Page 28: Headgear Erection - amre.org.za

Lift Stair modules into position up to 26.5m Lvl

Page 29: Headgear Erection - amre.org.za

Lift 3rd Floor (26.5m Lvl) from first preassembly pad on to headgear. Mass of Lift 55 Ton. Lift stair modules up to 32.5m LVL

Page 30: Headgear Erection - amre.org.za

Lift 4th Floor (32.5m Lvl) From 2nd

preassembly pad onto headgear. Mass of lift 55T

Page 31: Headgear Erection - amre.org.za

Lift stair modules up to 38.5m Lvl. Change boom configuration adding 30m Luffing fly and removing Superlift. Establish 225T with 106m boom in Skyhorse configuration.

Page 32: Headgear Erection - amre.org.za

Erect 5th Floor (38.5m Lvl) piecemeal with both cranes, max lift 35 Ton

Page 33: Headgear Erection - amre.org.za

Lift stair modules up to 44.5m Lvl

Page 34: Headgear Erection - amre.org.za

Erect 6th Floor (44.5m Lvl) piecemeal with both cranes, max lift 35 Ton

Page 35: Headgear Erection - amre.org.za

Erect 7th Floor (50m Lvl) piecemeal with both cranes, max lift 35 Ton

Page 36: Headgear Erection - amre.org.za

Lift stair modules up to 60m Lvl

Page 37: Headgear Erection - amre.org.za

Erect 8th Floor (60m Lvl) piecemeal with both cranes, max lift 35 Ton

Page 38: Headgear Erection - amre.org.za

Change boom configuration back to 66m boom and 130T Superliftcounterweight, move to South West of headgear to lift preassembled bottom portion of backleg. Mass of lift 80 T

Page 39: Headgear Erection - amre.org.za

Move crane in position and lift preassembled upper portion of backleg. Mass of lift 80T

Page 40: Headgear Erection - amre.org.za

Move crane in position and lift preassembled bottom portion of backleg. Mass of lift 80T

Page 41: Headgear Erection - amre.org.za

Move crane in position and lift preassembled upper portion of backleg. Mass of lift 80T

Page 42: Headgear Erection - amre.org.za

Move crane back to East of headgear, Change boom configuration to 78m Main boom and 30m luffing fly jib. Bring 225T Crane back in to position. Install stair modules up to 70m Lvl

Page 43: Headgear Erection - amre.org.za

Using both cranes, erect 70m Lvlpiecemeal max lift 35 Ton

Page 44: Headgear Erection - amre.org.za

Install stair modules to top and finish 70m Lvl

Page 45: Headgear Erection - amre.org.za

Lift north elevation of crane gantry into position

Page 46: Headgear Erection - amre.org.za

Lift south elevation of crane gantry into position

Page 47: Headgear Erection - amre.org.za

Lift east walkway of crane gantry into position

Page 48: Headgear Erection - amre.org.za

Lift west elevation of crane gantry into position, place EOT crane and disestablish cranes

Page 49: Headgear Erection - amre.org.za

Putting the Plan in Action

Page 50: Headgear Erection - amre.org.za

Establishing Site

Page 51: Headgear Erection - amre.org.za

14.5m Lift

Page 52: Headgear Erection - amre.org.za

14.5m Lift

Page 53: Headgear Erection - amre.org.za

20.5m Lift

Page 54: Headgear Erection - amre.org.za

20.5m Erected

Page 55: Headgear Erection - amre.org.za

26.5m Lift

Page 56: Headgear Erection - amre.org.za

32.5m Lift

Page 57: Headgear Erection - amre.org.za

32.5m Erected

Page 58: Headgear Erection - amre.org.za

38.5m Frames

Page 59: Headgear Erection - amre.org.za

38.5m Frames

Page 60: Headgear Erection - amre.org.za

38.5m Piecemeal

Page 61: Headgear Erection - amre.org.za

38.5m Piecemeal

Page 62: Headgear Erection - amre.org.za

DSE Workshop Inspection

Page 63: Headgear Erection - amre.org.za

44.5m Piecemeal

Page 64: Headgear Erection - amre.org.za

44.5m Frame

Page 65: Headgear Erection - amre.org.za

One Dark Stormy Night05 November 2008 at 23h30

Page 66: Headgear Erection - amre.org.za

Some Incidents to Recall

Page 67: Headgear Erection - amre.org.za

Houston Texas: 16 July 2008

Page 68: Headgear Erection - amre.org.za

Houston Texas: 16 July 2008

Page 69: Headgear Erection - amre.org.za

‘Big Blue’ Milwaukee - Wisconsin: 14 November 1999

Page 70: Headgear Erection - amre.org.za

‘Big Blue’ Milwaukee - Wisconsin: 14 November 1999

Page 71: Headgear Erection - amre.org.za

Bellevue WA: Tower Crane21 Nov 2006

Page 72: Headgear Erection - amre.org.za

Crane Collapse

Page 73: Headgear Erection - amre.org.za

Crane Collapse

Page 74: Headgear Erection - amre.org.za

Crane Collapse

Page 75: Headgear Erection - amre.org.za

Key points from the investigation: 225T American 9310 crane was rigged in ‘Sky Horse’ configuration

with 106m boom, boom angle 73°. High wind speeds recorded (50km/h). Effect of the wind was multiplied by the proximity of the sheeted winder

buildings. Fortunately there were no injuries and no damage to other structures.

The program was maintained by revising the erection sequence and mobilising an additional crane

Crane Collapse

Page 76: Headgear Erection - amre.org.za

50m Erected

Page 77: Headgear Erection - amre.org.za

Raking Leg Preassembly

Page 78: Headgear Erection - amre.org.za

60m Erected

Page 79: Headgear Erection - amre.org.za

60m Erected

Page 80: Headgear Erection - amre.org.za

Laydown Areas and Painting Area

Page 81: Headgear Erection - amre.org.za

Columns to the 70m Level

Page 82: Headgear Erection - amre.org.za

Raking Leg Preassembly

Page 83: Headgear Erection - amre.org.za

Raking Leg Preassembly

Page 84: Headgear Erection - amre.org.za

Kibble Shaves on the 60m Level

Page 85: Headgear Erection - amre.org.za

Stage Winder Rope-up

Page 86: Headgear Erection - amre.org.za

70m Erected

Page 87: Headgear Erection - amre.org.za

Crane Installation on 81m Level

Page 88: Headgear Erection - amre.org.za

Stair Tower Preassembly

Page 89: Headgear Erection - amre.org.za

Tower Compete

Page 90: Headgear Erection - amre.org.za

Man Winder Raking Leg Erection

Page 91: Headgear Erection - amre.org.za

Preparing to Lift Rock Winder Raking Leg

Page 92: Headgear Erection - amre.org.za

Rock Winder Raking Leg Erection

Page 93: Headgear Erection - amre.org.za

Rock Winder Raking Leg Erection

Page 94: Headgear Erection - amre.org.za

Rock Winder Raking Leg Erection

Page 95: Headgear Erection - amre.org.za

Erection Complete

Page 96: Headgear Erection - amre.org.za

Site Disestablishment

Page 97: Headgear Erection - amre.org.za

Final Survey

Page 98: Headgear Erection - amre.org.za

Following the Big Blue Incident: Implement specifically engineered lift plans designed by professional

engineers based on rated capacity, measured weight of the load, thorough study of the wind speed and its effect on the load, and consideration of ground conditions and dynamic forces on the crane's stability.

Cranes and work areas should be equipped with wind instrumentation at or near the elevation of hoisted loads.

Suspended personnel platforms should not be used in adverse weather conditions which may endanger workers.

Provide alternate observations methods for locations not easily visible from the ground.

Only use personnel necessary to safely complete the lift in hoisted platforms.

Lessons Learnt

Page 99: Headgear Erection - amre.org.za

Following the Impala 17 Shaft Incident: Consider the effect of prevailing wind conditions exaggerated by

surface features and buildings. Wind monitoring equipment to be installed and monitored even after

hours, alarm systems to be considered. Crane to be parked with the slew brake off. Boom to be lowered to 45° at end of daily site activities. Risk assessment reviewed.

Lessons Learnt

Page 100: Headgear Erection - amre.org.za

Headgear Erection: Erected successfully without any lost time injuries. Exceeded the required degree of accuracy.

Lessons Learnt

Page 101: Headgear Erection - amre.org.za

Owner/ Client: Impala Platinum

Main Contractor/ Engineer/ Project Manager: TWP (WorleyParsons)

Steelwork Contractor: Grinaker-LTA

Steelwork Fabricator: DSE Structural Engineers

Credits

Page 102: Headgear Erection - amre.org.za

Presentation Close