Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Headgear ErectionThe Impala 17 Shaft ExperienceMichael Yates AMRE Safety Seminar 18 September, RPM Club: Lifting Operations
Introduction
Introduction
Impala 17 Shaft Headgear Tower type headgear propped on two sides 81m to the top of the crane rail Centre tower foot print is 14m by 14m square The two braced raking back legs extend to about 42m from the shaft
centre line
Multi Phase Design
It must accommodate 3 conditions Sinking, development and construction – from 2009 to 2017 Equipping and commissioning – from 2017 to 2018 Permanent condition – for the productive 30+ year life of the mine
Design: Working Condition
Raking legs for two ground mounted Koepe winders placed at 90° angles to one another
The deepest Koepe wind to date at 1932m deep Skips running at 18m/s with hoisting capacity of 33 ton Man cage is a double deck cage with counterweight and
accommodates 150 men per deck Service cage is also a double deck cage to take 54 men per
deck and with planned slinging capability of 8 ton
Design: Emergency Condition
The headgear is designed for 1.5 times breaking force of 6 50mm ropes
This factor compliments the winder base design Incredible force of 2500kN per rope = 22,500kN. This force is directed from the 60m level through the back
legs into the ground This causes a substantial torque on the head frame
Fabrication
Large sections to handle in a workshop i.e. plate girder in the order of 2.5m deep
Heavy cruciform column sections Pin and bracket assembly for the raking legs Large trial assemblies of the floors in the workshop
Headgear Erection
Site establishment was in August of 2008 The erection duration was 7 months and ended in February
2009 The final paint coat was applied just prior to assembly and
erection on site Lower four floors were assembled with the columns on
erection bases adjacent to the headgear From the 38.5 m level up the erection was carried out
piecemeal Single beams with a mass of 25 tons were lifted to heights of
up to 70 m
Erection Overview
The stair access tower was to be erected in sequence with the floor levels
The headgear tower was erected well within the code requirements (32mm deviation at the top and 140mm is allowed in the code)
The back legs were erected in two preassembled sections, each weighing 80 tons
Interesting Facts
Interesting Facts
Impala 17#, Rustenburg 2009
81.0m
Interesting Facts
69281 Bolts supplied1850 Total tonnage1430 Tons painted420 Tons galvanized1099 m handrails1200 m² flooring406 Stair treads
100000 Manhours on site20000 m welding
8679 Individual pieces of steel2650 Drawings generated
150000 km's for transport and delivery
Preparation
Detailed risk assessment carried out in June 2008, aspects considered: Assembly and disassembly of the lattice cranes Crane erection Use and movement of the cranes Preassemble and erect the headgear tower Preassemble and erect the raking legs
Risk Assessment
Aspects considered: Failure of the equipment; ropes, brakes and components Incorrect operation of the crane; incompetency, lack of skill Injury to persons, damage to equipment; unsafe rigging methods Concurrent activities in the work area; falling objects, poor
communication Inclement weather; wind, rain, lightening, cold, heat Incorrect material handling; unskilled labour, lack of supervision, poor
planning Incorrect rigging; lack of knowledge, lack of training, non adherence to
standards Lifting point failure; poor design, poor installation, shock loading Working at heights; poor housekeeping, slippery surfaces, inclement
weather
Risk Assessment
Aspects considered Exposure to hazardous substances; inhalation of fumes, contact of
products Concurrent activities in the work area; falling objects, poor
communication Fire; hot work, electrical failure Non adherence to legal requirements; relevant acts Poor communication; lack of coordination, poor attitude, poor planning Unsafe ground conditions; compaction, rain, sub surface structures Unsafe scaffolding; standards, uncertified erectors, poor ground
conditions, equipment, poor design
Risk Assessment
Aspects considered Collapse of trestles; poor design, uneven loading, unstable ground Poor fitting of HD bolts; incorrect survey, negligence, dimensional
errors Limited access for haulage; close proximity of winder buildings Poor ergonomics; nature of the design Suspended platforms; ergonomics, overloading, mechanical failure
Risk Assessment
Alternative Crane Arrangements
Underground structures required support: Beneath the terrace adjacent to the main shaft are there the access-
ways and a service duct. These were assessed and it was decided to brace and prop these
structures. Areas were demarcated where the assembly cranes were not allowed
to access
Site Preparation
Propping Underground Structures
Lift Planning
Detailed lift planning was carried out considering: Positioning of the main cranes for each lift. Mass and height of each lift. Lifting equipment to be used. Spreader beams required.
Lift Planning
Headgear Layout
Raking Legs
Tower Structure
Crane Gantry
Establish 400Ton Lattice with 66m Main Boom, 120T Counterweight and 130T Superlift Counterweight
Lift 1st Floor (14.5m Lvl) from preassembly pad over Matla HeadgearMass of lift 130 Ton
Move crane back and lift 2nd Floor (20.5m Lvl) From 2nd preassembly pad onto headgear. Mass of Lift 55 Ton
Lift Stair modules into position up to 26.5m Lvl
Lift 3rd Floor (26.5m Lvl) from first preassembly pad on to headgear. Mass of Lift 55 Ton. Lift stair modules up to 32.5m LVL
Lift 4th Floor (32.5m Lvl) From 2nd
preassembly pad onto headgear. Mass of lift 55T
Lift stair modules up to 38.5m Lvl. Change boom configuration adding 30m Luffing fly and removing Superlift. Establish 225T with 106m boom in Skyhorse configuration.
Erect 5th Floor (38.5m Lvl) piecemeal with both cranes, max lift 35 Ton
Lift stair modules up to 44.5m Lvl
Erect 6th Floor (44.5m Lvl) piecemeal with both cranes, max lift 35 Ton
Erect 7th Floor (50m Lvl) piecemeal with both cranes, max lift 35 Ton
Lift stair modules up to 60m Lvl
Erect 8th Floor (60m Lvl) piecemeal with both cranes, max lift 35 Ton
Change boom configuration back to 66m boom and 130T Superliftcounterweight, move to South West of headgear to lift preassembled bottom portion of backleg. Mass of lift 80 T
Move crane in position and lift preassembled upper portion of backleg. Mass of lift 80T
Move crane in position and lift preassembled bottom portion of backleg. Mass of lift 80T
Move crane in position and lift preassembled upper portion of backleg. Mass of lift 80T
Move crane back to East of headgear, Change boom configuration to 78m Main boom and 30m luffing fly jib. Bring 225T Crane back in to position. Install stair modules up to 70m Lvl
Using both cranes, erect 70m Lvlpiecemeal max lift 35 Ton
Install stair modules to top and finish 70m Lvl
Lift north elevation of crane gantry into position
Lift south elevation of crane gantry into position
Lift east walkway of crane gantry into position
Lift west elevation of crane gantry into position, place EOT crane and disestablish cranes
Putting the Plan in Action
Establishing Site
14.5m Lift
14.5m Lift
20.5m Lift
20.5m Erected
26.5m Lift
32.5m Lift
32.5m Erected
38.5m Frames
38.5m Frames
38.5m Piecemeal
38.5m Piecemeal
DSE Workshop Inspection
44.5m Piecemeal
44.5m Frame
One Dark Stormy Night05 November 2008 at 23h30
Some Incidents to Recall
Houston Texas: 16 July 2008
Houston Texas: 16 July 2008
‘Big Blue’ Milwaukee - Wisconsin: 14 November 1999
‘Big Blue’ Milwaukee - Wisconsin: 14 November 1999
Bellevue WA: Tower Crane21 Nov 2006
Crane Collapse
Crane Collapse
Crane Collapse
Key points from the investigation: 225T American 9310 crane was rigged in ‘Sky Horse’ configuration
with 106m boom, boom angle 73°. High wind speeds recorded (50km/h). Effect of the wind was multiplied by the proximity of the sheeted winder
buildings. Fortunately there were no injuries and no damage to other structures.
The program was maintained by revising the erection sequence and mobilising an additional crane
Crane Collapse
50m Erected
Raking Leg Preassembly
60m Erected
60m Erected
Laydown Areas and Painting Area
Columns to the 70m Level
Raking Leg Preassembly
Raking Leg Preassembly
Kibble Shaves on the 60m Level
Stage Winder Rope-up
70m Erected
Crane Installation on 81m Level
Stair Tower Preassembly
Tower Compete
Man Winder Raking Leg Erection
Preparing to Lift Rock Winder Raking Leg
Rock Winder Raking Leg Erection
Rock Winder Raking Leg Erection
Rock Winder Raking Leg Erection
Erection Complete
Site Disestablishment
Final Survey
Following the Big Blue Incident: Implement specifically engineered lift plans designed by professional
engineers based on rated capacity, measured weight of the load, thorough study of the wind speed and its effect on the load, and consideration of ground conditions and dynamic forces on the crane's stability.
Cranes and work areas should be equipped with wind instrumentation at or near the elevation of hoisted loads.
Suspended personnel platforms should not be used in adverse weather conditions which may endanger workers.
Provide alternate observations methods for locations not easily visible from the ground.
Only use personnel necessary to safely complete the lift in hoisted platforms.
Lessons Learnt
Following the Impala 17 Shaft Incident: Consider the effect of prevailing wind conditions exaggerated by
surface features and buildings. Wind monitoring equipment to be installed and monitored even after
hours, alarm systems to be considered. Crane to be parked with the slew brake off. Boom to be lowered to 45° at end of daily site activities. Risk assessment reviewed.
Lessons Learnt
Headgear Erection: Erected successfully without any lost time injuries. Exceeded the required degree of accuracy.
Lessons Learnt
Owner/ Client: Impala Platinum
Main Contractor/ Engineer/ Project Manager: TWP (WorleyParsons)
Steelwork Contractor: Grinaker-LTA
Steelwork Fabricator: DSE Structural Engineers
Credits
Presentation Close