34
Tatiana Antysheva, Head of Strategic Growth Group Stepan Borovitskiy, Chief specialist, Reactor Unit Design Group 8 July 2011

Head of Strategic Growth Group Chief specialist, Reactor ... · PDF fileTatiana Antysheva, Head of Strategic Growth Group Stepan Borovitskiy, Chief specialist, Reactor Unit Design

Embed Size (px)

Citation preview

Tatiana Antysheva,

Head of Strategic Growth Group

Stepan Borovitskiy,

Chief specialist, Reactor Unit Design Group

8 July 2011

Reactor design introduction

Nuclear steam supply system

Safety concept

Design/Safety Implications from the

Fukushima Event

Design certification and deployment schedule

SVBR-100 Reactor Modules

2

Reactor Design Introduction

3

• Sustainability: Minimal environmental impact (reduced spent fuel amount due to long fuel campaign)

Possibility to work in closed fuel cycle systems

• Safety and reliability: Any radiological emergency possible for SVBR reactor could not lead to high pressure radioactive emissions

into the atmosphere:

Passive safety systems

Correspondence with current regulatory system

• Economical efficiency:

Transportation and construction simplicity

Flexibility for local energy needs due to scalable modular design (100-200-300+… MWe)

Long fuel campaign and fuel universality

Possibility of deployment near residential area (less than 1 km)

Broad range of products: electricity, heat, desalinated water, steam for some industrial needs

Relative ease of system integration (fewer requirements to local infrastructure)

• Public acceptance due to high safety characteristics

SVBR-100 Reactor Modules – New Generation Nuclear

Systems

4

• Operational experience:

80 reactor years of experience on Russian submarines (Alpha class)

• Prototype research facilities:

Test prototype 27/VT: more than 50 years of experience

Test prototype KM-1

• R&D program to support reactor design includes about 20 test facilities

(both existing, modernized and new ones) (6 russian research institutes

involved)

Historical Technical Basis

5

6

SVBR-100 Power Plant Key Performance Indicators

Coolant material Lead-bismuth

Reactor thermal output 280 MW(th)

Power plant output with one reactor module:

Electricity 101 MW(e)

Heat* max. 70 Gkal/hour

Desalinated water* max. 200 000 tons/day

Power plant efficiency 36%

Availability factor 90%

Fuel campaign duration 7-8 years (UO2 fuel with average 16.3% of U235)

Steam parameters Saturated steam, p=6.7MPa, T~282.9°C

Load following capability 0.5-2%Nnom per minute in 70-100% power range

Seismic stability

For structures and pipelines: safe shutdown earthquake – horizontal

PGA=0,12 g (7-point on the MSK-64 scale),

For reactor module equipment: safe shutdown earthquake – horizontal

PGA=0,25 g (8-point on the MSK-64 scale)

Reactor module weight ~235 ton

Reactor module dimensions 4.5 / 7.86 meters (diameter/height)

Design lifetime for reactor vessel and structures 60 years

*- if appropriate equipment is installed

** - incl. O&M, fuel, decommissioning fund

Nuclear Steam Supply System

7

SVBR-100 Reactor Layout

8

Main circulation

pump (MCP) x 2

Steam generator (SG)

modules x 12

Core

Monoblock

vessel

Control

adsorbing

rods

Basic Technical Characteristics of Core Performance

(for UO2 fuel, saturated steam)

Lead-bismuth coolant (LBC) temperature,

input / output, С 350 / 500

Average power density of the core, kW/dm3 160

Average linear load on the fuel element, W/cm 300

Fuel: type

U loading, kg U-235 average enrichment, %

UО2

9100

16.3

Core lifetime, thousand full power hours Not less than 50

Average burn-up, % h.a. 6.9

Max burn-up,% h.a. 11.4

Max Damaging doze, dpa 85

9

Gas System Condenser

Bursting

Membrane

Reactor

Monoblock

(RMB)

Passive

Cooldown Vessel

Feedwater

Saturated

Steam Cooldown

Condenser

Bubbling

Chamber

| 9 |

SVBR-100 NSSS Design

10

Reactor operates without partial

refueling.

Spent nuclear fuel is unloaded cassette-

by-cassette.

Fresh fuel is loaded as a single cartridge.

Fuel element is of a container type.

Wrappless fuel sub-assemblies(FSA)

(total number is 61)

Boron carbide is an absorbing material in

CPS rods (enrichment in 10В - 50%)

Reactor Core Layout

FSA without rods (7)

Control and

compensating rods

(12)

Compensating

rods (22)

Automatic

control rod (2)

Additional emergency

protection rods,12

EP rods (6)

11

SVBR-100 Fuel Assemblies

Upper reflector

Low reflector

Fuel

Cladding

Gas volume

Upper grid

Lower grid

Collet

Middle grid

Fuel assembly cross-section

Lattice type Triangular

Core height 900 mm

Modified UO2 fuel with improved heat conduction cause

lower fuel temperatures => lower ratio of gas fragments=>

lower pressure under the fuel element cladding

Ferrite-martensite steel used for fuel cladding with low

swelling cause lower damage dozes

12

Displacers

SVBR-100 SG Module

Heat removal rate 23 MWt

Active region height 4465 mm

SG module diameter 570 mm

System pressure 6.7 MPa

Number of tubes 192

Water/Steam temperature 240/282.9 oC

Coolant

entrance

Feedwater

entrance

Steam

SG cross-section

Coolant

flow-out

Coolant

flow-out

13

• An abcence of partial refueling ensures the possibility to change significantly each fuel

load

• At the first stage: UO2 fuel, CBR = 0,84

• MOX fuel, CBR 1:

Due to high content of plutonium, first spent UO2 fuel load can be used as a main

component for a third fresh fuel load and etc. Estimated fuel campaign duration for

uranium nitride or uranium-plutonium fuel is up to 15 years

Fuel Cycle

The consumption of natural

uranium during 60 years could

be by 30 % less than that for

WWER reactors (for 1 GWe)

* G.I.Toshinskiy and Co, “Fuel cycle of reactor SVBR-100”,Global’09

Safety Concept

14

SVBR-100 Safety Principles

Chemically inert

lead-bismuth coolant

Fast reactor

Integral design of the reactor

components:

core, pumps, SG, etc.

Inherent (by-nature)

safety – for free

By-design

safety

First circuit

low pressure

15

Stability & simplicity

under normal operation

Tolerance to the design

and

beyond-design basis

accidents

+

SVBR-100 Safety

16

Accident SVBR-100 Design

Loss of Flow Accident Natural LBC circulation mode

Loss of Coolant Accident Double vessel structure

Transient Over Power Passive safety systems

Local Blockage Wrappless fuel sub-assemblies

Loss of Heat Sink To be simulated

17

SVBR-100: Design Safety Features

Integral layout

of the core, MCP

and SG in

a common vessel

(monoblock)

In case of failure of all cooling systems

and black-out:

no core melting occurs

integrity of the monoblock is provided passively

as a result of heat accumulation by in-vessel

structures and coolant

heat removal is provided with water tank (96 hours)

Absence of the pipelines and primary circuit valves

outside the reactor monoblock:

simplifies the design

prevents from losses of coolant

prevents blockage of circulation of the coolant

through the core

SVBR-100: Fast Reactor

Operating reactivity

margin

is less than

the delay-neutron fraction

no prompt neutrons

runaway (under no condition chain

reaction can go out of control)

No Xe poisoning effects

Small negative

temperature reactivity

coefficient

Special algorithm of controlling

the compensation

absorbing rods

Fast reactor

18

SVBR-100: Lead-Bismuth Coolant

High boiling

Temperature (1670 ºС)

Chemical inertness

of coolant to

water and air

Low primary

circuit pressure

simplification of the reactor design

enhancement of reliability

no possibility of primary circuit’s

over-pressurization and thermal

explosion of the reactor

Accident with

loss-of-sealing in the primary circuit and

with inter-circuit leaks in the SG occur without

hydrogen release and exothermic reactions

No chemical explosions and

internally-caused fires

Coolant – lead-bismuth eutectic alloy

19

20

Impact of Potential Energy of the Coolant

Coolant type Water Sodium Lead,

Lead-bismuth

Parameters P = 16 MPa

Т = 300 ºС

Т = 500 ºС

Т = 500 ºС

Maximal potential energy, GJ/m3, incl.:

~ 21,9 ~ 10 ~ 1,09

Thermal energy

incl. compression

potential energy

~ 0,90

~ 0,15

(PWR)

~ 0,6

None

~ 1,09

None

Potential Chemical energy of interaction

With zirconium

~ 11,4

With water 5,1

With air 9,3 None

Potential chemical energy of interaction of released hydrogen with air

~ 9,6 ~ 4,3 None

Potential hazard from the NPP is determined by two factors:

1. accumulated radiation (radiotoxicity contained in the reactor) facility

2. probability of radioactivity release into the environment

Total radioactivity is proportional to the thermal power of the reactor (size) and duration of its operation, i.e., by

energy production – doesn’t depend on the reactor type

Probability depends on the reactor type and is determined by reactivity margin, feedbacks, design features,

and potential energy, accumulated in the coolant

Coolant potential energy strongly influences the number and complexity of the safety systems and can display

its impact in case of accidents (especially severe)

Source: G.I. Toshinsky et. al “EFFECT OF POTENTIAL ENERGY STORED IN REACTOR FACILITY

COOLANT ON NPP SAFETY AND ECONOMIC PARAMETERS”

21

Separator

Steam generator

(SG)

Main circulation

pump (MCP)

Autonomous

cooldown

condenser

Valve-controller

Reactor core

Lead-bismuth

coolant (LBC)

Autonomous Cooldown Principal Scheme

Fusible locks of the additional safety rods to provide passive shutdown of the core

in the event of coolant’s overheating over 700 C caused by CRDM fault

Passive Operation of Safety Systems:

Extraction of the RRs at nominal power without actuation of

the EP rods

22

0 1 0 0

0 . 0

0 . 2

0 . 4

0 . 6

0 . 8

1 . 0

1 . 2

1 . 4

1 . 6

1 . 8

2 . 0

1 0 0

2 0 0

3 0 0

4 0 0

5 0 0

6 0 0 N , r e l T , о С

Time, s

N

Outlet T

Inlet T

р < 1 МПа

Small leak

р = 1 МПа

Large leak

Gas system

condenser

Breaking

membrane

Bursting disk (membrane) prevents the reactor vessel from over-pressurization over 1.0 MPa in case of postulated large leak (several tubes) in the SG

Passive Operation of Safety Systems:

SG internal leak localization

23

The mode with blocking the central FSA at the inlet (Тclad – ~ 520 оC).

The mode with blocking the half of the core flow area at the inlet (Тclad – ~ 592 оC).

The mode with blocking the central FSA at the level of the active part of fuel

elements (Тclad – ~ 596 оC).

24

Passive Operation of Safety Systems:

Partial blockage of the flow area

High thermal-technical reliability of the core is the result of non-casing FSA design, high transverse heat-mass-exchange and «shift» of

the active part of a fuel element to the upper part of the core.

Distribution of LBC heating Distribution of LBC velocities

Steam generator

(dried)

Lead-bismuth

coolant (LBC)

Reactor core

MCP

(de-energized)

Removal of steam

from

the PHRS tank

PHRS tank filled

with water

Heat sink

(out of)

25

Passive Operation of Safety Systems:

Heat removal in case of all RMB systems failure

26

Time, h

Тclad

H water

Passive removal of residual heat in the event of NPP black out is assured by transferring the heat via the reactor and guard vessels walls to the water tank: evaporation of water

allows 4 days of the let-alone period (grace period).

Passive Operation of Safety Systems:

Heat removal in case of all RMB systems failure

Design/Safety Implications from

the Fukushima Event

27

Reactor

shutdown

SVBR-100 Response to a Fukushima-like Initiating Event

Hard to compare 40-50-ty year old NPP design (though modernized) with “after” Chernobyl &

TMI & Fukushima NPPs designed up to “the lessons learned”

However:

Full blackout

Inability to remove Fuel afterheat

Fuel rods zirconium casing interaction

with water

Growth of temperature in the reactor core

Impossibility to organize

repair works +

Lead-Bismuth Coolant evaporation Not possible. tb = 1670ºC

No zirconium (steel casing)

design features: 96 hours of

non-interference (100 tn water

tank) + no loss of coolant

Hydrogen extraction & explosion Not possible in significant

quantities

No consequences 28

Design Certification and

Deployment Schedule

29

SVBR-100 Project

30

JSC AKME-engineering

- a 50/50 joint venture of Russian State Atomic Corporation Rosatom and EuroSibEnergo (En+ Group),

aimed to commercialize SVBR lead-bismuth nuclear reactor technology.

The company was established in December 2009

The JV’s targets:

• Completion of the R&D for reactor unit/fuel, safety analysis report

• Detailed design of the reactor unit and principal equipment

• Reactor and power plant licensing

• Commissioning of the SVBR pilot plant by the end of 2017

• Development of manufacturing, servicing and marketing infrastructure for commercial serial production and

sales

Growing worldwide interest in SMR

technologies

Strong trend towards inherently safe

and intrinsically secured nuclear power

technologies

Advanced lead-bismuth fast reactor

technology with 80 reactor-years

operational experience on Russian

submarines

Background

31

2011 2014 2018 + 2010 2012 2013 2015 2016 2009 Preliminary design of reactor unit, core and key

equipment, Site selection, Feasibility study

Development of manufacturing and servicing

Infrastructure, Marketing

Construction, Commissioning,

Operation licensing

Pilot operation

Serial

manufacturing of

commercial units 2017 Target:

•Operation license obtained

•Pilot plant commissioned

Status June 2011:

•Site selected

•AKME appointed as operator for pilot

plant

•Siting license works underway

•Specifications on pilot plant approved

•Key R&D on reactor and reactor core are

underway

2013 Targets:

•Preliminary Safety report &

Construction license

obtained

•Reactor & power plant

design completed

Manufacturing and delivery of reactor unit

and power plant components

SVBR-100 Pilot Plant: project schedule and milestones

R&D Preliminary

design Design Construction Operation

Commer-

cialization

Power Plant Design engineering,

Reactor safety report, Construction licensing

2017

32

Licensing Issues for SVBR-100

Key issues to be proved: Solutions in Russian regulatory framework:

? Operation staff requirements Requirements are flexible and depend on safety level of NPP

(proved by a SAR) ? Emergency zone planning

? Distance from residential area

Requirement of the RF Ministry of Emergency is 25 km

distance between NPP and residential area. But there is

practice of reduction this distance up to 1-3 km by additional

justifications

? Safeguard requirements Requirements are fixed and depend on NPP technology and

design (vulnerability analysis)

? Liability insurance

Maximum liability for NPP operator is about $195mln and

causes annual insurance payments which could not be a

financial burden for a SMR operator, but can be additionally

reduced for SMRs

RF regulations are sufficient to carry out activities regarding SVBR during it’s

lifetime and support innovative features of new SMRs

SVBR-100 Pilot Plant: design & engineering organizational

diagram (as of June 2011)

AKME-engineering

Owner, project manager

OKB Gidropress Reactor unit& core chief

designer, design integrator

Atomenergoproekt

NPP design & engineering

TBD Owner’s engineer

CDBMB Main circulation

pump (MCP) designer

IPPE Reactor core fuel

elements designer, coolant technology

Prometey, NIIAR Construction materials’

experimental examination

NIIIS/NITI/Siemens ? Automatic control system

designer

Lonas, Zarubezhenergoproekt

Turbine isle design and engineering

LMZ, Alstom,? Turbine developer and manufacturer

VEI MCP power

drive designer

33

Nuclear isle BOP

Legend:

OKB Gidropress – Experimental and Design Organization “Gidropress”

CDBMB – Central Design Bureau of Machine Building

IPPE – Institute for Physics and Power Engineering

VEI – All-Russian electro-technical institute

Prometey - Central Research Institute of Structural Materials “Prometey”

NIIAR – State Scientific Center Research Institute of Atomic Reactors

NIIIS – Research Institute of Measuring Systems

Atomenergoproekt – engineering company, general designer of nuclear power plants with WWER

Lonas, Zarubezhenergoproekt – Russian design & engineering companies

LMZ - Leningradsky Metallichesky Zavod (Russian power machine building enterprise)

34

Thank you!

JSC “AKME-engineering”

Tel. +7 495 7307960

Fax +7 495 7306292

24 B.Ordynka str., Moscow 119017, Russia

[email protected]

www.akmeengineering.com