44
HB650 Cryomodule Vincent Roger International workshop on cryomodule design and standardization 6 th September 2018

HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

HB650 Cryomodule

Vincent Roger

International workshop on cryomodule design and standardization

6th September 2018

Page 2: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

1. Description of the HB650 cryomodule

2. Assembly process

3. Instrumentation

Layout

2 4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 3: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

3

1. Description of the cryomodule

• Vacuum vessel : 9.7 m long and around 1.5 m high compared to the beam axis• Thermal shield at 35-50 K• 5 K line used as thermal intercept & to cool down the cold-mass• 5 Bayonets, 2 cryogenic valves & an heat exchanger• 6 Cavities, tuners & couplers• A cold magnetic shield around each cavity, and warm magnetic shield on the inner

surface of the vacuum vessel (still under discussion)

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 4: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

4

1. Description of the cryomodule

• Max Cryomodule height: 2.8 m

• Beamline height from floor: 1.3 m

• Max allowed heat load to 35-50 K: 160 W

• Max allowed heat load to 5 K: 61 W

• Max allowed heat load to 2 K: 50 W

• Transverse cavity alignment error < 0.5 mm

• Angular cavity alignment error < 1 mrad

• Max variation of pressure in the 2-phase helium pipe: 0.1 mbar

1.1 Cryomodule requirements

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 5: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

5

1. Description of the cryomodule

• Some analytical calculations have been done to size this vessel.• Relief analysis has been done.• FEA need to be done in order to be sure about the locations of the supports post and

the lifting lugs.• The vacuum vessel is composed of 11 tuner ports which are used also for the

instrumentation.

1.2 Vacuum vessel

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 6: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

6

1. Description of the cryomodule

1.3 Layout of the cryomodule

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 7: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

7

1. Description of the cryomodule

1.4 Cryogenic lines

Pipe G - 2phase He pipe & Relief lineMAWP: 2.05 bar warm, 4.1 bar cold

Pipe A - 2 K supplyMAWP: 20 bar

Pipe C & D - 5 K lineMAWP: 20 bar

Pipe E & F - 35-50 K lineMAWP: 20 bar

Pipe B - Pumping lineMAWP: 2.05 bar warm, 4.1 bar cold

Pipe H - Cool down /warm up line

MAWP: 20 bar

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 8: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

8

Calculations have been done in order to demonstrate that all the pipes of HB650cryomodule have been designed per venting requirements.

Needed diameter for the chimney of the dressed cavity

Needed diameter for the 2-phase helium

pipe

Needed diameter for the relief line

Loss of insulating vacuum

28.8 mm 74.7 mm 75.2 mm

Cavity vacuum loss 40 mm 97.8 mm 97.8 mm

Considereddiameter

93.5 mm 146.8 mm 122.8 mm

The two-phase helium pipe has been oversized in order to increase the gas volumeand therefore the pressure stability.

1.5 Pipe sizing

1. Description of the cryomodule

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 9: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

9

2. Assembly process

• Workstation 1: Assembly of the cavity string in the clean room• Workstation 2: Lifting of the string assembly

Welding of the cool-down / warm up lineMoving down the string assembly on the strong-back assembly

• Workstation 3: Assembly of the cold-mass• Workstation 4: Insertion of the cold-mass in the vacuum vessel

Completion of the cryomodule

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 10: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

10

2. Assembly process

All the cryogenic lines have been pre-designed based on anassembly process, but the design stage is not over yet. Simulations,and several parts need to be designed including the beam line.

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 11: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

11

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 12: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

12

2. Assembly process

35-50 K line will be leak tested and pressure tested by the manufacturer.

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 13: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

13

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 14: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

14

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 15: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

15

2. Assembly process

Under the lifting tooling:• The tuner will be set up on each cavity.• The cool down line will be welded to the cavities• MLI will be set on each cavity and on the cryogenic lines.• A magnetic shield around each cavity will be set up.

Design pressure of the cool down line : 20 barg.Design pressure of the weld making the connection with the dressed cavities: 2.05 barg at warm, 4.1 barg at cold .

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 16: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

16

2. Assembly process

Same fixtures as LCLS II to align the cavities.

Rough alignment of the cavities

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 17: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

17

2. Assembly process

Weldment of the 5 K line and leak tests

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 18: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

18

2. Assembly process

Set up of the pumping line, and the 2 K lines connected to the heat exchanger

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 19: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

19

2. Assembly process

Inlet of the helium in the 2 phase helium pipe

Weldment of the two phase helium pipe and leak tests

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 20: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

20

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 21: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

21

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 22: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

22

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 23: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

23

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 24: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

24

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 25: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

25

2. Assembly process

Final pressure test of the 35-50 K line.

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 26: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

26

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 27: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

27

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 28: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

28

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 29: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

29

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 30: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

30

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 31: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

31

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 32: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

32

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 33: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

33

2. Assembly process

Radiographic tests of the weld between the CD line & the CD valve.Final pressure test of the 5 K line.Leak test 2 K line and pumping line.

The CD and JT valves have a similar design as LCLS II project to avoid

thermal acoustic oscillations

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 34: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

34

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 35: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

35

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 36: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

36

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 37: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

37

2. Assembly process

Final pressure test of the 2 K line, the pumping line and the dressed cavities.

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 38: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

38

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 39: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

39

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 40: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

40

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 41: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

41

2. Assembly process

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 42: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

42

2. Assembly process

Leak test of the vacuum vessel.

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 43: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

43

3. Instrumentation

In the interface document all the external interfaces of SSR1 Cryomodule havebeen mapped out, how it interfaces with the connected systems of PIP-II and thePIP-II Injector Test (formerly known as PXIE).

4-7 September 2018 Vincent Roger | HB650 Cryomodule

Page 44: HB650 Cryomodule...• A magnetic shield around each cavity will be set up. Design pressure of the cool down line : 20 barg. Design pressure of the weld making the connection with

44

3. Instrumentation

• The instrumentation will be very similar to what has been done on SSR1 cryomodule.• Having two ports for each tuner it is possible to split the instrumentation in order to

have more room to do these connections.• On the top of the cryomodule, two pressure transducers will read the pressure inside

the two-phase helium pipe.

4-7 September 2018 Vincent Roger | HB650 Cryomodule