MARCH 31 2019 HAZEL SITE PROGRESS PHOTOS

HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

MARCH 31 2019

HAZEL SITE PROGRESS PHOTOS

Page 2: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

PROJECT MAIN ENTRY – SECURITY ROOM

Page 3: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

CLUB HOUSE- FRONT ELEVATION

Page 4: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

EXTERNAL – CLUB HOUSE

Page 5: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

CLUB HOUSE-GYM,MULTI PURPOSE HALL

Page 6: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

CLUB HOUSE- INDOOR GAMES

Page 7: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

CLUB HOUSE - ACTIVITIES

HOUSEWARMING FUNCTION DANCE CLASS

TABLE TENNISDRAWING CLASS

Page 8: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

CLUB HOUSE - ACTIVITIES

HOUSEWARMING FUNCTION TABLE TENNIS

TABLE TENNISCAROM BOARD

Page 9: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

ROAD FROM MAIN ENTRY TO ‘B’ BLOCK

Page 10: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

BLOCK ‘B’ NORTH SIDE ROAD

Page 11: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

BLOCK ‘B’ SOUTH SIDE ROAD

Page 12: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

TRANSFORMER

Page 13: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

EXTERNAL WORKS – ROAD WORKS/DRAIN WORKS/FIRE HYDRANT

BLOCK E SOUTH SIDE BLOCK F SOUTH SIDE

Page 14: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

EXTERNAL WORKS – ROAD WORKS/DRAIN WORKS/FIRE HYDRANT

IN BETWEEN BLOCK D&F BLOCK F EAST SIDE

Page 15: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

Block C North Side Swimming pool

Page 16: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

WORKS IN PROGRESS:-

compound wall cum storm water drain Completed in Block E ,block F south side and

block A & C north side . Block F north east corner balance 20rmt in progress

Service work Completed in Block E & Block F south& east

side and in-between block D&F. progress in block C north side

Road work Completed in block E& Block F south side ,

85% completed in between block D& F. block F east side 50% ready for rcc road and balance in progress for pcc

Fire fighting work completed block E and block F south side and

progress in block A & C north side .

Swimming pool Structure completed .RR to be submitted the

final service drawing to commence the waterproofing and tiling work.

BLOCK F NORTH EAST CORNER WORKS IN PROGRESS:

Page 17: HAZEL SITE PROGRESS PHOTOShazelproject.in/wp-content/themes/twentyfourteen/... · hazel site progress photos. project main entry –security room. club house- front elevation. external

OSR LANDSCAPE WORKS