HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER

ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT

OF THE ROAD, PROJECT CONSTRUCTED IN 1 DAY, MARCH 10, 2009

BY PIKE COUNTY PUBLIC WORKS DEPT, LaDON ATKINSON, ROAD

SUPERVISOR

Page 2: HAW  CREEK GENERAL  INFORMATION

HAW CREEKGENERAL INFORMATION

Bank erosion is threatening county road, threatening public safety

Stream wildly meandering in response to historic straightening

Decent riparian areas in places Bed material: gravel-sand. Channel is incised Pool-riffle-pool regime, slope less than 1% Average width 30-40 ft, 15 ft tall banks Funding, equipment, and manpower provided by

Pike County, MO

Page 3: HAW  CREEK GENERAL  INFORMATION

DIRECTIONS TO HAW CREEK, From Hwy 61 (Pike County, 15 miles south of Hannibal, MO), turn east on Rt. B, then left on Rt. 107. 3-4 miles

project is on the south side after a long straight section, then “S” bend.

Contact: Jaynie Doerr, regulatory, St. Louis Dist.

[email protected]

Page 4: HAW  CREEK GENERAL  INFORMATION

PRE-PROJECT PHOTOSby

JAYNIE DOERR, REGULATORY,

ST. LOUIS DISTRICT FEBRUARY 25, 2009

Page 5: HAW  CREEK GENERAL  INFORMATION

Looking US at the bend US of the project bend.

PRE PROJECT-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 6: HAW  CREEK GENERAL  INFORMATION

Looking DS @ the upper end of the project bend.

PRE-PROJECT - HAW CREEK-PIKE COUNTY MO. PIX BY JAYNIE DOERR 2-25-09

Page 7: HAW  CREEK GENERAL  INFORMATION

LOCKED LOGS

We utilized the two existing logs (next picture) that had fallen in by

placing them angled downstream and building the LPSTP on top to “lock”

the logs in place.

Page 8: HAW  CREEK GENERAL  INFORMATION

Looking DS @ the center of the bend & the threatened County Road 107, Pike County, MO. We used the two trees as Locked Logs.

PRE-PROJECT - HAW CREEK-PIKE COUNTY MO. PIX BY JAYNIE DOERR 2-25-09

Page 9: HAW  CREEK GENERAL  INFORMATION

Looking DS @ the lower end of the project bend

PRE-PROJECT - HAW CREEK-PIKE COUNTY MO. PIX BY JAYNIE DOERR 2-25-09

Page 10: HAW  CREEK GENERAL  INFORMATION

Looking DS @ exit conditions to the project bend

PRE-PROJECT - HAW CREEK-PIKE COUNTY MO. PIX BY JAYNIE DOERR 2-25-09

Page 11: HAW  CREEK GENERAL  INFORMATION

Looking US @ the project bend. Road is 4 ft from 14 ft tall eroding bank.

PRE-PROJECT - HAW CREEK-PIKE COUNTY MO. PIX BY JAYNIE DOERR 2-25-09

Page 12: HAW  CREEK GENERAL  INFORMATION

Down at the farm & feed store, education !!!!

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 13: HAW  CREEK GENERAL  INFORMATION

CONSTRUCTION PHOTOS

by Dave Derrick, COE; Jaynie Doerr, COE; & Matt Methaney, MDC

MARCH 10, 2009

Page 14: HAW  CREEK GENERAL  INFORMATION

We have 500 willows, stone, diesel, equipment, and time on our hands! A dangerous combination!!

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 15: HAW  CREEK GENERAL  INFORMATION

Forest

Pike County Highway 107

The vertical eroding bank is 14 ft tall & 4 ft from the

shoulder of the road.

WE NEED SPACE!!!!

Haw Creek, MO Pre-project

Forest

Page 16: HAW  CREEK GENERAL  INFORMATION

Pike County Highway 107

110 ft of Longitudinal

Peaked Stone Toe Protection with

Single Stone Bendway Weirs

Haw Creek, MO. Highway protection plan

30 ft long vegetated key with soil cover

Straight vegged key

15 ft wide engineered floodplain bench with Living Dikes, poles, & Live Siltation

Page 17: HAW  CREEK GENERAL  INFORMATION

Pike County Highway 107

Haw Creek, MO. Highway protection plan

Page 18: HAW  CREEK GENERAL  INFORMATION

Self-Adjusting, Self-Filtering Stone Depending on size, angularity, and gradation, stone can be

neither, either, or both!! Self-Adjusting Stone:

Stone must be well-graded (from coarse to fine) so that it has the ability to "launch", or self-adjust into, and armor, scour holes formed on the streamward side, and/or stream end, of a river training structure.-Charlie Elliott says a good rule of thumb in Mississippi sand-bed streams {CAUTION: this might not apply equally well to every stream in the world} is that one ton of rock per linear ft will armor three ft of scour

Self-Filtering StoneA soil analysis should always be performed to

determine stability and erodability of bank materials and whether a filter material, (either granular or synthetic) is required.

A self-filtering stone that has worked well on the Mississippi River, and numerous other rivers and smaller streams (acting as a granular filter to prevent loss of underlying bank material) has 10% to 15% of the gradation either less that 4 inches in diameter, or less than one pound in weight, depending on how the stone is specified.

Page 19: HAW  CREEK GENERAL  INFORMATION

QUESTIONABLE STONE

Stone used for keys & LPSTP was a sub-standard shot rock of questionable hardness. The amount of fine material was close to 20-30%. This was a self-

filtering stone, but not well-graded, & not self-

adjusting.

Page 20: HAW  CREEK GENERAL  INFORMATION

Stone is not well-graded & too many fines. The stone is self-filtering, but not self-adjusting, but only $4.70/ton delivered.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 21: HAW  CREEK GENERAL  INFORMATION

STONE COSTS However, the stone was extremely inexpensive. The 432 tons of rock

used in the project, at $4.70 per ton (delivered) total cost of stone =

$2032. That was very cost effective for what we accomplished.

Page 22: HAW  CREEK GENERAL  INFORMATION

THE PLAN

Page 23: HAW  CREEK GENERAL  INFORMATION

HAW CREEKMETHODS EMPLOYED

110 ft of Longitudinal Peaked Stone Toe Protection (LPSTP), crest built to 4 ft above the base flow water surface elevation

Locked Logs A vegetated floodplain bench Single-Stone & Short Bendway Weirs Live Willow Pole Plantings Vegetated & curved upstream key, straight DS key Living Dikes Slit Brush Layering (Joint Planting) in riprap bank Live Siltation

Page 24: HAW  CREEK GENERAL  INFORMATION

We will construct from

upstream (US) to

downstream (DS)

Page 25: HAW  CREEK GENERAL  INFORMATION

THE UPSTREAM

KEY

Page 26: HAW  CREEK GENERAL  INFORMATION

A KEY HAS ONE MAIN JOB, TO CONNECT THE

RIVER TRAINING STRUCTURE TO THE REST

OF THE WORLD (DON’T LET THE STREAM GET BEHIND {FLANK} RIVER TRAINING STRUCTURES)

Page 27: HAW  CREEK GENERAL  INFORMATION

THE STEP-BY-STEPS FOR HAW CREEK,

TRIB. TO SALT RIVER, PIKE

COUNTY, FRANKFORT, IOWA

All drawings by Dave Derrick

Page 28: HAW  CREEK GENERAL  INFORMATION

Detail for key

Cross-section for keywayFlow

Page 29: HAW  CREEK GENERAL  INFORMATION

Looking DS at hoe digging the upstream key.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 30: HAW  CREEK GENERAL  INFORMATION

Looking DS. Setting topsoil aside for use as backfill topping

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 31: HAW  CREEK GENERAL  INFORMATION

Place Willow Poles against the DS side of the trench

Detail for key

Flow

Page 32: HAW  CREEK GENERAL  INFORMATION

Looking DS. Placing willow poles against the DS side of key trench.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 33: HAW  CREEK GENERAL  INFORMATION

Place stone in trench

Detail for key

Flow

Page 34: HAW  CREEK GENERAL  INFORMATION

Choke stone with gravel (white areas) & water in.

Detail for key

Flow

Page 35: HAW  CREEK GENERAL  INFORMATION

Looking DS. Placing stone and creek gravel choke in US key trench.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 36: HAW  CREEK GENERAL  INFORMATION

Backfill and overfill with native soils, then compact

(some settling will still occur)

Detail for key

Flow

Page 37: HAW  CREEK GENERAL  INFORMATION

Looking DS. Backfilling key with quality top soil.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 38: HAW  CREEK GENERAL  INFORMATION

Hydro seed

DONE

Detail for key

Flow

Page 39: HAW  CREEK GENERAL  INFORMATION

LONGITUDINAL PEAKED

STONE TOE PROTECTION

(LPSTP)

Page 40: HAW  CREEK GENERAL  INFORMATION

ENHANCED LONGITUDINAL PEAKED STONE TOE

PROTECTION (LPSTP) WITH SINGLE-STONE BENDWAY WEIRS, LOCKED LOGS, SOIL CHOKING,

LIVE SILTATION, POLE PLANTINGS, LIVING DIKES,

ROOTED – STOCK PLANTS, & A FLOODPLAIN BENCH

Page 41: HAW  CREEK GENERAL  INFORMATION

Stream channel

Top bank

Eroding bank

ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)

Road

Page 42: HAW  CREEK GENERAL  INFORMATION

“Locked Logs” placed on bed of river for improved aquatic habitat & energy dissipation. Locked Logs should be angled downstream 25 to 35 degrees so as to shed debris.

ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)

Road

Page 43: HAW  CREEK GENERAL  INFORMATION

LONGITUDINAL PEAKED STONE

TOE PROTECTION {LPSTP} Description: A continuous stone dike placed

longitudinally at, or slightly streamward of, the toe of the eroding bank. Cross-section is triangular. The LPSTP does not necessarily follow the toe exactly, but can be placed to form a "smoothed" alignment through the bend. Smoothed alignment might not be desirable from the environmental or energy dissipation points of view . Amount of stone used (2 tons/linear ft, 1 ton/ft, or less) depends on depth of scour at the toe, estimated stream forces (impinging flow) on the bank, and flood durations and stages.

Tie-backs are short dikes connecting the LPSTP to the bank at regular intervals. Tie-backs are usually the same height as the LPSTP or elevated slightly toward the bank end, and are keyed into the bank. If tie-backs are long they should be angled upstream to act as bendway weirs.

Page 44: HAW  CREEK GENERAL  INFORMATION

Longitudinal Peaked Stone Toe Protection (LPSTP)

As-built

After a couple of high flow events stream has scoured at the

toe & stone has self-adjusted

Sediment has deposited landward of the LPSTP

Page 45: HAW  CREEK GENERAL  INFORMATION

Locked Logs are then “locked” under the Longitudinal Peaked Stone Toe Protection (LPSTP).

ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)

Page 46: HAW  CREEK GENERAL  INFORMATION

Looking US @ completed US key. Forming stone into Longitudinal Peaked Stone Toe Protection (LPSTP)

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 47: HAW  CREEK GENERAL  INFORMATION

Looking US. LPSTP crest is 4 ft above base flow stage

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 48: HAW  CREEK GENERAL  INFORMATION

ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)

Tree or shrub poles (called Live Siltation)

installed on top of LPSTP

Willow, dogwood, river birch poles can then be laid on the stone and up against the bank. Basal ends should be in vadose

zone (capillary zone). Willow used on this project.

Page 49: HAW  CREEK GENERAL  INFORMATION

ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)

Live Willow poles were then laid up against the eroded bank

Page 50: HAW  CREEK GENERAL  INFORMATION

Looking DS. Class laying willow on LPSTP & against bank.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DOERR 3-10-09

Page 51: HAW  CREEK GENERAL  INFORMATION

Looking US. Class laying willow poles against eroding bank.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 52: HAW  CREEK GENERAL  INFORMATION

Looking US. LPSTP with willow on both sides of floodplain bench.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 53: HAW  CREEK GENERAL  INFORMATION

Looking DS. Derrick teaching during construction

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DOERR 3-10-09

Page 54: HAW  CREEK GENERAL  INFORMATION

ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)

Backfill material from point bar to form a floodplain bench at the Q-2 flood elevation

Page 55: HAW  CREEK GENERAL  INFORMATION

Looking DS. Backfilling between LPSTP & bank to form floodplain bench @ the Q-2 elevation.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 56: HAW  CREEK GENERAL  INFORMATION

LIVING DIKES are dense rows of deep-planted adventitious

rooting poles oriented perpendicular to the direction of high flow

Page 57: HAW  CREEK GENERAL  INFORMATION

ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)

At intervals, install willow Living Dikes (densely deep-planted adventitious poles perpendicular to direction of high flow)

Page 58: HAW  CREEK GENERAL  INFORMATION

Floodplain bench

planted on a grid

patternF

low

AERIAL VIEW OF ENHANCED LPSTP WITH A FLOODPLAIN BENCH WITH VEGETATION PLANTED ON

A GRID PATTERN.

Living Dikes-plants

perpendicular to flow

Live Siltation

Live Poles

Page 59: HAW  CREEK GENERAL  INFORMATION

Looking US. Willow poles on bank (part of the floodplain bench) near the road we are protecting

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 60: HAW  CREEK GENERAL  INFORMATION

Looking US. Installing Living Dikes perpendicular to high flow, Live Siltation & Live Poles are parallel with the stream.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 61: HAW  CREEK GENERAL  INFORMATION

A Living Dike (perpendicular to high flow) on the floodplain bench.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 62: HAW  CREEK GENERAL  INFORMATION

Looking US @ the completed Floodplain bench.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 63: HAW  CREEK GENERAL  INFORMATION

Looking DS. Nice S-shaped creek alignment.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 64: HAW  CREEK GENERAL  INFORMATION

ENHANCED LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)

Install appropriate rooted-stock plants on the floodplain bench & seed and

mulch, or hydro-seed.

Floodplain bench will be seeded and mulched, & rooted-stock plants added shortly.

Page 65: HAW  CREEK GENERAL  INFORMATION

Looking US. Raining & but we still building & teaching

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 66: HAW  CREEK GENERAL  INFORMATION

Flo

w

AERIAL VIEW OF ENHANCED

LPSTP WITH SINGLE- STONE

BENDWAY WEIRS, & A

FLOODPLAIN BENCH. NOTE ROAD IS ONLY

4 FT FROM BANK

Single-Stone Bendway Weir

Single-Stone Bendway Weir

Page 67: HAW  CREEK GENERAL  INFORMATION

Looking from top bank. Placing a Single-Stone Bendway Weir (SSBW) against the LPSTP. SSBW were spaced 20-25 ft apart.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 68: HAW  CREEK GENERAL  INFORMATION

Looking from top bank. Single-Stone Bendway Weirs

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 69: HAW  CREEK GENERAL  INFORMATION

Looking US. Single Stone Bendway Weirs will move thalweg from toe of LPSTP out to the ends of the SSBW’s

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 70: HAW  CREEK GENERAL  INFORMATION

Looking US @ Single Stone Bendway Weirs, LPSTP, & Live Siltation, the US key, & floodplain bench.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 71: HAW  CREEK GENERAL  INFORMATION

JOINT PLANTING IN EXISTING RIPRAP The county got a little ahead of us by placing

riprap against the bank @ the DS end, so we left it, but I wanted to show how

hard it was to vegetate that new existing riprap.

Page 72: HAW  CREEK GENERAL  INFORMATION

Looking DS. LaDon grabbing poles, some poles in.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 73: HAW  CREEK GENERAL  INFORMATION

Looking DS. Track hoe had a very hard time digging & raising stone a few inches to insert the willow stakes.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX-METHANEY 3-10-09

Page 74: HAW  CREEK GENERAL  INFORMATION

Looking DS. Hoe had a very hard time digging in & raising stone so stakes can be inserted into the riprap

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX-METHANEY 3-10-09

Page 75: HAW  CREEK GENERAL  INFORMATION

Looking DS. Row of willow stakes have been inserted into the riprap bank. It was hard to do.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX BY DERRICK 3-10-09

Page 76: HAW  CREEK GENERAL  INFORMATION

THE DOWNSTREAM

KEYIn this case the key is

vegetated & parallel to the bank so that flow will not

cross and erode the opposite bank.

Page 77: HAW  CREEK GENERAL  INFORMATION

Look sideways @ the downstream key with live poles.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX-METHANEY 3-10-09

Page 78: HAW  CREEK GENERAL  INFORMATION

Looking US @ the downstream key.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX-METHANEY 3-10-09

Page 79: HAW  CREEK GENERAL  INFORMATION

PROJECT CONSTRUCTED

IN 1 DAY, MARCH 10, 2009

Page 80: HAW  CREEK GENERAL  INFORMATION

PROJECT COMPLETE

LOOKING FROM UPSTREAM TO DOWNSTREAM

Page 81: HAW  CREEK GENERAL  INFORMATION

Looking DS @ entrance conditions to the project bend.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX-METHANEY 3-10-09

Page 82: HAW  CREEK GENERAL  INFORMATION

Looking DS. SSBW, LPSTP, 500 willows, floodplain bench

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX-METHANEY 3-10-09

Page 83: HAW  CREEK GENERAL  INFORMATION

Looking DS @ floodplain bench, willows, LPSTP, SSBW.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX-METHANEY 3-10-09

Page 84: HAW  CREEK GENERAL  INFORMATION

Looking DS. Note straight exit flow does not adversely affect DS opposite bank.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX-METHANEY 3-10-09

Page 85: HAW  CREEK GENERAL  INFORMATION

PROJECT COMPLETE

LOOKING FROM DOWNSTREAM TO UPSTREAM

Page 86: HAW  CREEK GENERAL  INFORMATION

Looking US@ floodplain bench, willows, LPSTP, US key, & US bend.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX-METHANEY 3-10-09

Page 87: HAW  CREEK GENERAL  INFORMATION

Looking US @ flow attack angle into project bend.

CONSTRUCTION-HAW CREEK-PIKE COUNTY, MO. PIX-METHANEY 3-10-09

Page 88: HAW  CREEK GENERAL  INFORMATION

Bank Protection redundancy:

Fully functioning both hydraulically & environmentally. Multiple protection redundancy. LPSTP provides a robust, adjustable, direct armor bank toe protection. Single-Stone Bendway Weirs move scour & thalweg away from attacked bank, with velocities reduced within weir field. Locked Logs & vegetation roughness reduces near-bank velocities. Roots strengthen bank & bind soil. Floodplain bench plantings reduce flow velocities, provide stability & a continuous riparian corridor.

Page 89: HAW  CREEK GENERAL  INFORMATION

Stream Project Functions: LPSTP provides scour protection at toe Integrated Live Siltation provides vegetative roughness, increases

height of protection “soft protection”, shades stone & water, & has many wildlife functions {everything from carbon input to structure cover to insect production, beneficial to pollinators, etc.}

Vegetation on bank planted to slow floodwaters, capture alluvium, colluvium, woody debris, carbon, and native seed.

Bendway Weirs increase stream roughness, provide mini pool-riffle-pool sequences, reduce toe scour, & provide diversity & complexity of depth, velocity (horizontal & vertical) & substrate, & move the thalweg away from the toe of the eroding bank

Integrated Locked Logs dissipate energy, reduce near-field scour, provide toe protection & aquatic habitat complexity

Container plants on bank & overbank (to be added soon) will provide a diversity of plant species for fully functioning riparian corridor.

Page 90: HAW  CREEK GENERAL  INFORMATION

LESS THAN 2 MONTHS AFTER

PROJECT COMPLETION Looking US to DS

Photos by LaDon Atkinson MAY 4, 2009

Page 91: HAW  CREEK GENERAL  INFORMATION

LaDon Atkinson, Pike County Road Supervisor says “The veg is looking

great! This little creek has been hammered with water. We have had

several rains and the last one was 3.5" in a couple of hours. The water

has been on the floodplain bench 3 or 4 times now, notice all the sediment

that has dropped out.”

Page 92: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Looking DS @ LPSTP, Bendway Weirs, poles & floodplain bench.

Page 93: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Looking DS @ willow poles in US key

Page 94: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Close-up looking DS @ willows in US key

Page 95: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Looking DS @ the floodplain bench (overtopped 3 times in 2 months)

Page 96: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Deposition on floodplain bench from being overtopped 3 times in 2 months

Page 97: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Looking DS @ section of project parallel with road.

Page 98: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

From road looking DS @ project.

Page 99: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Looking downhill @ Slit Brush Layering in riprap bank

Page 100: HAW  CREEK GENERAL  INFORMATION

LESS THAN 2 MONTHS AFTER

PROJECT COMPLETION

Looking DS to US. Photos by LaDon Atkinson

MAY 4, 2009

Page 101: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Looking US @ entire almost the entire project.

Page 102: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Looking US @the floodplain bench. Note deposition on bench.

Page 103: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Looking US @ the upper end of the project.

Page 104: HAW  CREEK GENERAL  INFORMATION

2 MONTHS LATER-HAW CR.-PIKE COUNTY, MO PIX-ATKINSON 5-4-2009

Looking US @ flow into project & floodplain bench

Page 105: HAW  CREEK GENERAL  INFORMATION

4 MONTHS AFTER PROJECT

COMPLETION Looking US to DS Photos by LaDon

Atkinson JULY 11, 2009

Page 106: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking DS @ the project bend.

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 107: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking DS @ the US key. Great willow growth

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 108: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking DS @ key, floodplain bench, & LPSTP

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 109: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking DS @ the thalweg trace, LPSTP, Single Stone Bendway Weirs & the floodplain bench.

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 110: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking DS @ LPSTP & Slit Brush Layering in riprap

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 111: HAW  CREEK GENERAL  INFORMATION

After 4 months, great growth from the 500 willows we planted!

LaDon says the floodplain bench has

about 6 inches of sediment deposition on it.

Page 112: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking DS @ floodplain bench

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 113: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking DS @ Slit Brush Layering in riprap

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 114: HAW  CREEK GENERAL  INFORMATION

4 MONTHS AFTER PROJECT

COMPLETION Looking DS to US Photos by LaDon

Atkinson JULY 11, 2009

Page 115: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking US @ thalweg, SSBW & LPSTP.

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 116: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking US @ SSBW, LPSTP & Live Siltation

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 117: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-From top bank looking US @ project bend

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 118: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking US @ project & road

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 119: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking US-close-up of floodplain bench. Fantastic growth & great hydraulic roughness.

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 120: HAW  CREEK GENERAL  INFORMATION

4 MONTHS LATER-Looking US @ a Living Dike on the floodplain bench

4 MONTHS LATER - HAW CREEK–From LaDon Atkinson-7-11-09

Page 121: HAW  CREEK GENERAL  INFORMATION

Haw Creek Project

April 20, 2010 PhotosOne Year After Completion

By Jaynie Doerr, Regulatory,St. Louis District, U.S. Army Corps of Engineers

Page 122: HAW  CREEK GENERAL  INFORMATION

Looking DS

Page 123: HAW  CREEK GENERAL  INFORMATION

Look at that Veg!

Page 124: HAW  CREEK GENERAL  INFORMATION

Busy Beavers

Page 125: HAW  CREEK GENERAL  INFORMATION

Looking US

Page 126: HAW  CREEK GENERAL  INFORMATION

Drainage Just DS of Project

Page 127: HAW  CREEK GENERAL  INFORMATION

Haw Creek Project (5 inch rain 48 hours prior to photos)

September 20, 2010Two Growing Seasons After Completion

Photos By Rob Gramke, Regulatory,St. Louis District, U.S. Army Corps of Engineers

Page 128: HAW  CREEK GENERAL  INFORMATION

Looking upstream from road

Sep 2010-notice how wide the shoulder appears now

March 2009-bank 4 feet from road

Page 129: HAW  CREEK GENERAL  INFORMATION

Looking upstream

May 2009

April 2010

Page 130: HAW  CREEK GENERAL  INFORMATION

Looking upstream – September 2010

Page 131: HAW  CREEK GENERAL  INFORMATION

Looking downstream

March 2009

September 2010

Page 132: HAW  CREEK GENERAL  INFORMATION

Looking downstream from left descending bank. The vegetation has almost completely grown over the rock – Sept 2010

Page 133: HAW  CREEK GENERAL  INFORMATION

From the road-notice height of willows (Sept 2010) These are happy willows!

Page 134: HAW  CREEK GENERAL  INFORMATION

Rock toe & short Bendway Weirs

Page 135: HAW  CREEK GENERAL  INFORMATION

Locked log still in place

Page 136: HAW  CREEK GENERAL  INFORMATION

This PowerPoint presentation was developed & built by Dave Derrick.

Any questions or comments, call my personal cell @ 601-218-7717, or email @ [email protected]

Enjoy the information!!