Upload
cameron-dwyer
View
217
Download
2
Tags:
Embed Size (px)
Citation preview
Hardin Hilltop Wind Farm……An Example of Community Wind in Iowa
Kansas Community Wind WorkshopCloud County Community CollegeConcordia, Kansas
October 31, 2006
Thomas A. Wind
Wind Utility Consulting
Jefferson, Iowa
2
Topics I Will Cover
• Initial formation of project
• Electrical Interconnection
• Need for Incentives• Key Issues• Economic
Feasibility• Benefits of the
Project
3
Initial Formation of Project
• All wind projects start with one person…. the one who has the “crazy idea”
• It was a crazy idea for many reasons
• He pesters the others who then reluctantly buy into the “crazy idea”
• He becomes the “champion” for the project.
Local Land Owners and Farmers who Own the Wind Turbine Project
4Greene County
Hardin Township
5
7.35
7.20
7.05
6.90
6.75
6.60
6.45
6.30
6.15
6
Meteorological Test Tower Installed November 2003 Cost $11,000
7
Farmer-Owned Wind Farm Proposed in
Greene County, Iowa
Greene County
Hardin Township
HHW
Interconnection
Photo by GE Wind -
9
High Voltage Transmission System for the Upper Midwest
10
High Voltage Transmission System for Iowa
Little generation in this area…This helps with getting transmission access!
11
New 34.5 kV Underground Line
Existing 34.5 kV OHTransmission System
Interconnecting the Project to the Grid
The main interconnection issues for this project are the power factor and operating voltage levels at the Point of InterconnectionThere will be a 4- month period of reduced output due to substation equipment delays.The wind farm will also be subject to occasional curtailments over its lifetime
Point of Interconnection
12
About half of the wind turbines were turned off due to insufficient transmission capacity
Buffalo Ridge Minnesota this Morning from 10,000 feet
13
Key Issues
Photo by GE Wind -
14
The Major Challenge for This Project:--- Wind turbine procurement ---
• It is a Seller’s Market!• Most major manufacturers have no wind turbines available
for 2006 or 2007– Large wind farm developers have purchased most wind
turbines– Earliest delivery for major new projects may be in 2008– A few turbines become available as construction
schedules slip– Three years ago, delivery time was 20-25 weeks
• Manufacturers favor larger orders rather than smaller orders since they make more money– In many cases, no manufacturers may even bid on
supplying a single wind turbine• To get a turbine in the near future you may have to work
through a larger developer• Avoid single turbine projects unless you have a lot of
money!
15
Power Purchase Agreement
• Local utility (Alliant Energy) was required by PURPA to purchase power
• All power will be sold to the local investor-owned utility serving in the area– Fifteen year term contract– Power sold at utility’s long term avoided cost
(about 3 ¢ per kWh) as required by PURPA– Green tags are separately valued and sold
• Wind power will be integrated in with the utility’s other power supply resources– Alliant likes wind power, one of the largest
purchasers of wind power
16
Financial Structure is LLC Flip Model
• Ownership structure based on Minnesota LLC Flip model– Outside Investor for utilizing income tax benefits (“Tax
Investor”) becomes a partner in your LLC and provides the majority of the capital
– Ownership flips sometime after 10 years from Tax Investor to local owner when the tax benefits lapse and when the Tax Investor achieves his target rate of return
• Seven USDA grants were obtained averaging $247,000 each– Reduces Production Tax Credit and depreciation basis
for Tax Investor• Iowa Energy Center $250,000 nine-year zero interest loan• Local owners will have modest down payment• Long-term debt partially from local bank and partially from
outside debt sources
Need forIncentives to beEconomically
FeasibilityPhoto by GE Wind -
18
Cost ofMoney
WindSpeed
Priceof Electricity
Higher ValuesDISCOURAGE
WindGeneration
Higher ValuesFAVOR
WindGeneration
Cost ofTurbine
Cost toInterconnect
Financial Incentives
The Overall Economics of Wind Generation is Determined by a Balance of Factors
19
12
3 4 5 67
M
Wind Turbine #1
Met TowerM1
0.02 Mps per
ColorChange
Mean Annual Wind Speed
In Meters per Second at 50 Meters
Selecting Specific Sites
20
Wind Turbine
Underground 34.5 kV
Legend
Alliant OH 34.5 kV
Jefferson Water Works Sub
Point of Interconnection(West Side of WW Sub)
Alliant Substation
To Grand Jct. 161/115/34.5 Sub
To Jefferson &Scranton
161/34.5 Sub
1.0 Mile
3.6 Mile 34.5 kV Lineto Center of Wind Farm
Jefferson, IA
N
Hardin HilltopWind Farm
Turbine 1 Zontos Wind, LLCTurbine 2 Sutton Wind Energy, LLCTurbine 3 Hardin Wind Energy, LLCTurbine 4 Wind Family Turbine, LLCTurbine 5 Poverty Ridge
Turbine 6 Cy-Hawk Wind Energy, LLC
Turbine 7 Greene Wind Energy, LLC
12 3
4 5 67
34.5 kV
21
Economic Feasibility• A small project usually
cannot be cost competitive on a per kWh basis with a 100 MW wind project
• Small projects need something extra to make them feasible:– Higher selling price
for the power AND / OR– Financial
incentives.
Foundation under construction for 2.1 MW wind turbine near Jefferson, Iowa
22
Need for Financial Incentives• Iowa provides a 1.5 ¢
per kWh tradable state tax credit for 10 years
• Each local owner applied for a USDA Section 9006 grant, which averaged $247,000 each
• Each local owner received a $250,000 nine year zero interest loan
• All of these were necessary to be competitive in this lower wind speed area.
Completed foundation for large 2.1 MW wind turbine near Jefferson,
Iowa
23
Benefits fromthe Project
Photo by GE Wind -
24
Plowing in underground high voltage cables for wind turbines
Locally Generated Power
• Reduces high voltage transmission grid losses since power is generated where it is used
• Tends to reduce congestion on the high voltage grid if the wind generation is in an area with little generation.
25
The view from top of one farmer-owned wind turbine in Iowa
(235 feet high)
Local Property Taxes
• Iowa allows the county board of supervisors to phase in and abate property taxes for privately-owned wind generation projects
• The Hardin Hilltop project will pay about $25,000 per turbine per year after the 7 year phase-in period.
26
Electrical Infrastructure
• The construction of the turbines, electric lines and substations adds to the electrical infrastructure
• The established wind site and equipment will have value after the normal wind turbine lifetime of 20-25 years
• This value is often ignored, but it may be very significant in the long term.
Proposed Locally-Owned
15 MWWind Farm
JeffersonScranton
Churdan
Grand Jct.
Rippey
Paton
• The proposed wind farm would generate about 47,000 megawatt-hours per year
• Jefferson uses about that same amount of energy per year
• The Proposed Wind Farm Will Be a Significant Supplier of Electricity to the County
• The whole county uses about 100,000 MWH per year
• Along with a second hypothetical wind farm about the same size, the two wind farms would generate enough energy on average to provide all of the county’s electricity needs.
JeffersonScranton
Churdan
Grand Jct.
Rippey
Paton
HypotheticalSecond
Wind Farm
29
Proposed Locally-Owned
15 MWWind Farm
JeffersonScranton
Churdan
Grand Jct.
Rippey
Paton• The 15 MW Locally-Owned Wind Farm Will Save the Equivalent of Enough Coal To Fill a Train 3 Miles Long Every Year