52
DETAILED UNIT PRICE ANALYSIS PROJECT NAME: CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF Location: Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboan Item No./Description: 103 Layout and Excavation Works Unit of Measurement: cu.m. Output per day: 18.96 cu.m. /day Quantity: 1.84 cu.m. Designation No. Person No. of Days Daily Rate A. Labor a. Construction Foreman/Eng'g Assist. 1 0.10 524.00 b. Skilled Laborer 4 0.10 366.00 b. Laborer 4 0.10 317.00 Sub-Total for A P Name and Capacity No. of Units No. of Days Daily Rate B. Equipment N/A Sub-Total for B P C. Total (A+B) D. Output per day = 18.96 cu.m. /day Name and Specifications Quantity Unit Unit Cost E. Materials a. 2pcs. - 2" x 4" x 10' Coco Lumber 0.0252 cu.m. 8,899.44 b. 2pcs. - 2" x 3" x 10' Coco Lumber 0.0944 cu.m. 8,899.44 c. 4" C.W. Nail 0.80 kg. 85.00 d. Nylon Chord 1 roll 35.00 Sub-Total for E P F. Direct Cost (C+E) G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 J. Total Cost k. Total Unit Cost

Hand Wash Counter - By Admin

Embed Size (px)

DESCRIPTION

dupa

Citation preview

Page 1: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location: Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

Item No./Description: 103 Layout and Excavation Works

Unit of Measurement: cu.m.

Output per day: 18.96 cu.m. /day

Quantity: 1.84 cu.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.10 524.00 52.40

b. Skilled Laborer 4 0.10 366.00 146.40

b. Laborer 4 0.10 317.00 126.80

Sub-Total for A P 325.60

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 325.60 D. Output per day = 18.96 cu.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

a. 2pcs. - 2" x 4" x 10' Coco Lumber 0.0252 cu.m. 8,899.44 223.98

b. 2pcs. - 2" x 3" x 10' Coco Lumber 0.0944 cu.m. 8,899.44 840.11

c. 4" C.W. Nail 0.80 kg. 85.00 68.00

d. Nylon Chord 1 roll 35.00 35.00

Sub-Total for E P 1,167.09

F. Direct Cost (C+E) 1,492.69

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 74.63

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 1,567.32

k. Total Unit Cost 851.81

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10

UNITS OF FAUCET)

Page 2: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: 104 Embankment

Unit of Measurement: cu.m.

Output per day: 40.00 cu.m. /day

Quantity: 2.00 cu.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.10 524.00 52.40

b. Skilled Laborer 4 0.10 366.00 146.40

b. Laborer 4 0.10 317.00 126.80

Sub-Total for A P 325.60

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Plate Compactor 1 0.10 984.00 98.40

Sub-Total for B P 98.40

C. Total (A+B) 424.00 D. Output per day = 40.00 cu.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E.

a. Filling Materials (loose volume) 2 cu.m. 380.00 760.00

Note: Use Filling Materials for Backfill and Fill

Sub-Total for E P 760.00

F. Direct Cost (C+E) 1,184.00

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 59.20

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 1,243.20

k. Total Unit Cost 621.60

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

Materials (25% Shrinkage Factor)

Page 3: Hand Wash Counter - By Admin

Page 3 of 26

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: 404 Reinforcing Steel

Unit of Measurement: kgs.

Output per day: 609.84 kgs. /day

Quantity: 161.14 kgs.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.30 524.00 157.20

b. Skilled Laborer 10 0.30 366.00 1,098.00

b. Laborer 6 0.30 317.00 570.60

Sub-Total for A P 1,825.80

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Bar Cutter 1 0.30 1,758.00 527.40

b. Bar Bender 1 0.30 2,812.00 843.60

Sub-Total for B P 1,371.00

C. Total (A+B) 3,196.80 D. Output per day = 609.84 kgs. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

1. Column Footing

11.37 kgs. 42.40 482.00

#16 G.I. Tie-wire 0.40 kg. 59.00 23.60

2. Wall Footings

8.53 kgs. 42.40 361.59

5.91 kgs. 32.43 191.73

#16 G.I. Tie-wire 0.40 kg. 59.00 23.60

3. Columns

22.17 kgs. 42.40 939.92

7.38 kgs. 32.43 239.20

#16 G.I. Tie-wire 1.60 kgs. 59.00 94.40

4. Roof Beams

17.05 kgs. 42.40 722.84

11.82 kgs. 32.43 383.45

#16 G.I. Tie-wire 1.20 kgs. 59.00 70.80

5. Brace Beam

14.78 kgs. 32.43 479.45

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

12mm.Ø x 6.00m. Def. Reinforcing Steel

12mm.Ø x 6.00m. Def. Reinforcing Steel

10mm.Ø x 6.00m. Def. Reinforcing Steel

12mm.Ø x 6.00m. Def. Reinforcing Steel

10mm.Ø x 6.00m. Def. Reinforcing Steel

12mm.Ø x 6.00m. Def. Reinforcing Steel

10mm.Ø x 6.00m. Def. Reinforcing Steel

10mm.Ø x 6.00m. Def. Reinforcing Steel

Page 4: Hand Wash Counter - By Admin

Page 4 of 26

#16 G.I. Tie-wire 0.80 kg. 59.00 47.20

6. Lintel Beam

5.92 kgs. 32.43 191.99

#16 G.I. Tie-wire 0.40 kg. 59.00 23.60

7. Concrete Lavatory

26.64 kgs. 32.43 863.94

#16 G.I. Tie-wire 1.20 kg. 59.00 70.80

8. Floor Slab

14.78 kgs. 32.43 479.45

14.78 kgs. 40.54 599.34

#16 G.I. Tie-wire 0.80 kg. 59.00 47.20

Sub-Total for E P 6,336.09

F. Direct Cost (C+E) 9,532.89

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 476.64

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 10,009.53

k. Total Unit Cost 62.12

10mm.Ø x 6.00m. Def. Reinforcing Steel

10mm.Ø x 6.00m. Def. Reinforcing Steel

10mm.Ø x 6.00m. Def. Reinforcing Steel

10mm.Ø x 7.50m. Def. Reinforcing Steel

Page 5: Hand Wash Counter - By Admin

Page 5 of 26

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: 405 Structural Concrete

Unit of Measurement: cu.m.

Output per day: 4.41 cu.m./day

Quantity: 2.93 cu.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.70 524.00 366.80

b. Skilled Laborer 10 0.70 366.00 2,562.00

b. Laborer 6 0.70 317.00 1,331.40

Sub-Total for A P 4,260.20

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Concrete Bagger Mixer 1 0.70 1,376.00 963.20

Sub-Total for B P 963.20

C. Total (A+B) 5,223.40 D. Output per day = 4.41 cu.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

1. Column Footing

Volume: 0.14 cu.m.

Portland Cement 1 bag 260.00 260.00

Washed Sand 0.07 cu.m. 950.00 66.50

Gravel 0.14 cu.m. 950.00 133.00

2. Wall Footings

Volume: 0.16 cu.m.

Portland Cement 2 bags 260.00 520.00

Washed Sand 0.08 cu.m. 950.00 76.00

Gravel 0.16 cu.m. 950.00 152.00

3. Columns

Volume: 0.19 cu.m.

Portland Cement 2 bags 260.00 520.00

Washed Sand 0.10 cu.m. 950.00 95.00

Gravel 0.20 cu.m. 950.00 190.00

4. Roof Beam

Volume: 0.08 cu.m.

Portland Cement 1 bag 260.00 260.00

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

Page 6: Hand Wash Counter - By Admin

Page 6 of 26

Washed Sand 0.04 cu.m. 950.00 38.00

Gravel 0.08 cu.m. 950.00 76.00

5. Brace Beam

Volume: 0.06 cu.m.

Portland Cement 1 bags 260.00 260.00

Washed Sand 0.03 cu.m. 950.00 28.50

Gravel 0.06 cu.m. 950.00 57.00

6. Floor Slab

Volume: 1.82 cu.m.

Portland Cement 18 bags 260.00 4,680.00

Washed Sand 0.90 cu.m. 950.00 855.00

Gravel 1.80 cu.m. 950.00 1,710.00

7. Lintel Beam

Volume: 0.26 cu.m.

Portland Cement 3 bags 260.00 780.00

Washed Sand 0.13 cu.m. 950.00 123.50

Gravel 0.26 cu.m. 950.00 247.00

8. Concrete Lavatory

Volume: 0.22 cu.m.

Portland Cement 2 bags 260.00 520.00

Washed Sand 0.11 cu.m. 950.00 104.50

Gravel 0.22 cu.m. 950.00 209.00

Waterproofing (900 grams/pack) 2 packs 33.00 66.00

7. Forms12mm. Thk. x 1.20m. x 2.40m. Ordinary Plywood 3 shts. 871.00 2,613.00

19pcs. - 2" x 3" x 10' Coco Lumber 76 bd.ft. 20.00 1,520.00

4pcs. - 2" x 3" x 8' Coco Lumber 3 bd.ft. 20.00 60.00

2" C.W. Nail 2 kgs. 84.00 189.00

4" C.W. Nail 1 kg. 77.00 77.00

Sub-Total for E P 16,486.00

F. Direct Cost (C+E) 21,709.40

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 1,085.47

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 22,794.87

k. Total Unit Cost 7,770.11

Page 7: Hand Wash Counter - By Admin

Page 7 of 26

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: SPL - 1 Roofing Works

Unit of Measurement: sq.m.

Output per day: 5.37 sq.m./day

Quantity: 10.09 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 2 524.00 1,048.00

b. Skilled Laborer 6 2 366.00 4,392.00

b. Laborer 4 2 317.00 2,536.00

Sub-Total for A P 7,976.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Welding Machine 1 2 3,128.00 6,256.00

b. Angular Grinder 1 2 300.00 600.00

Sub-Total for B P 6,856.00

C. Total (A+B) 14,832.00 D. Output per day = 5.37 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

1. Trusses4 pcs. 1,130.00 4,520.00

6011 Welding Rod 0.5 kg. 144.00 72.00

2. Channel Purlins

#14 x 50mm. x 75mm. x 6.00m. G.I. C-Purlins 4 pcs. 532.00 2,128.00

1 pc. 1,130.00 1,130.00

2 pcs. 175.00 350.00

6011 Welding Rod 0.5 kg. 144.00 72.00

3. Fascia Framing and Backing

2mm. Thk. x 20mm. x 20mm. x 6.0m. Angle Bar 5 pcs. 526.00 2,630.00

6011 Welding Rod 0.5 kg. 144.00 72.00

4. Roofing Sheets, Gutters and Ridge Rolls2 pcs. 506.00 1,012.00

2 pcs. 802.00 1,604.00

80 pcs. 4.50 360.00

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

4mm. Thk. x 50mm. x 50mm. x 6.00m. M.S. Angle

Bar

4mm. Thk. x 50mm. x 50mm. x 6.00m. M.S. Angle

Bar (Cleat Angle)

10mm.Ø x 6.00m. Plain Round Bar (Sag Rod)

0.4mm. Thk. x 0.40m. x 2.40m. Galvalume Ridge Roll, Pre-painted0.4mm. Thk. x 0.45m. x 3.65m. Galvalume Spanish Flashing, Pre-painted

3mm.Ø x 10mm. Alum. Blind Rivet

Page 8: Hand Wash Counter - By Admin

Page 8 of 26

7 shts. 1,574.00 11,018.00

182 pcs. 2.00 364.00

100mm.Ø Grinding Wheel 4 pcs. 135.00 540.00

Sub-Total for E P 25,872.00

F. Direct Cost (C+E) 40,704.00

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 2,035.20

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 42,739.20

k. Total Unit Cost 4,234.96

0.4mm. Thk. x 800mm. x 1.83m. Ordinary Corrugated (915) Galvalume Roofing Sheet, Pre-painted4mm x 38mm Tekscrew (for metal) w/ neoprene washer

Page 9: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: SPL - 2a Setting of 100mm. CHB

Unit of Measurement: sq.m.

Output per day: 10.00 sq.m./day

Quantity: 8.49 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 1 524.00 524.00

b. Skilled Laborer 1 1 366.00 366.00

b. Laborer 2 1 317.00 634.00

Sub-Total for A P 1,524.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 1,524.00 D. Output per day = 10.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials

a. 100mm. x 200mm. x 400mm. CHB (NLB) 86 pcs. 14.00 1,204.00

b. Washed Sand 0.32 cu.m. 950.00 304.00

c. Portland Cement 5 bags 260.00 1,300.00

d. 6 pcs. 120.00 720.00

e. #16 G.I. Tie-wire 1 kg. 59.00 59.00

f. Hacksaw Blade 3 pcs. 50.00 150.00

Sub-Total for E P 3,737.00

F. Direct Cost (C+E) 5,261.00

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 263.05

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 5,524.05

k. Total Unit Cost 650.50

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

10mm.Ø x 6.00m. Def. Reinforcing Steel Bar

Page 10: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: SPL - 3a Ceiling Joist and Hangers

Unit of Measurement: sq.m.

Output per day: 16.00 sq.m./day

Quantity: 8.07 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.5 524.00 262.00

b. Skilled Laborer 1 0.5 366.00 183.00

b. Laborer 1 0.5 317.00 158.50

Sub-Total for A P 603.50

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 603.50 D. Output per day = 16.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 25pcs. - 2" x 2" x 8' Mahogany Wood 53 bd.ft. 41.00 2,173.00

b. 4" C.W. Nail 1 kg. 85.00 85.00

Sub-Total for E P 2,258.00

F. Direct Cost (C+E) 2,861.50

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 143.08

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 3,004.58

k. Total Unit Cost 372.15

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

Page 11: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: SPL - 3b Installation of Ceiling Board

Unit of Measurement: sq.m.

Output per day: 30.00 sq.m./day

Quantity: 8.07 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.30 524.00 157.20

b. Skilled Laborer 1 0.30 366.00 109.80

b. Laborer 1 0.30 317.00 95.10

Sub-Total for A P 362.10

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 362.10 D. Output per day = 30.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 6mm. Thk. x 1.20m. x 2.40m. Marine Plywood 3 shts. 509.00 1,527.00

b. 2" Finishing Nails 1 kg. 94.00 94.00

Sub-Total for E P 1,621.00

F. Direct Cost (C+E) 1,983.10

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 99.16

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 2,082.26

k. Total Unit Cost 257.91

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10

UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

Page 12: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

Location:

Item No./Description: SPL - 3c Installation of Fascia Board

Unit of Measurement: sq.m.

Output per day: 30.00 sq.m./day

Quantity: 9.19 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.30 524.00 157.20

b. Skilled Laborer 1 0.30 366.00 109.80

b. Laborer 1 0.30 317.00 95.10

Sub-Total for A P 362.10

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Electric Handrill 1 0.30 300.00 90.00

Minor Tools (10% of Labor Cost) 36.00

Sub-Total for B P 126.00

C. Total (A+B) 488.10 D. Output per day = 30.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa.

5 pcs. 352.00 1,760.00

b. 40 pcs. 2.00 80.00

Sub-Total for E P 1,840.00

F. Direct Cost (C+E) 2,328.10

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 116.41

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 2,444.51

k. Total Unit Cost 265.94

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

12mm. Thk. x 300mm. x 2.40m. Fiber Cement Fascia Board

32mm. Long Galvanized/Zinc-coated Fiber Cement Screw

Page 13: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: SPL - 4 Tile Works

Unit of Measurement: sq.m.

Output per day: 1.52 sq.m./day

Quantity: 5.10 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 3.35 524.00 1,756.78

b. Skilled Laborer 1 3.35 366.00 1,227.06

b. Laborer 1 3.35 317.00 1,062.78

Sub-Total for A P 4,046.63

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Angular Grinder 1 3.35 300.00 1,005.79

Sub-Total for B P 1,005.79

C. Total (A+B) 5,052.42 D. Output per day = 1.52 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 200mm. x 200mm. Glazed Ceramic Wall Tiles 140 pcs. 15.00 2,100.00

b. Portland Cement 1 bag 260.00 260.00

c. Tile Adhesive (25kg./bag) 1 bag 253.00 253.00

d. Tile Grout (2kg./pack) 2 packs 56.00 112.00

e. 6mm. x 2.40m. Tile Trim Plain 5 pcs. 40.00 200.00

f. 1 pc. 94.00 94.00

Sub-Total for E P 3,019.00

F. Direct Cost (C+E) 8,071.42

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 403.57

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 8,474.99

k. Total Unit Cost 1,663.07

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

100mm.Ø Grinding Dics

Page 14: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: SPL - 5 Plastering Works (16mm. Thk.)

Unit of Measurement: sq.m.

Output per day: 12.00 sq.m./day

Quantity: 11.58 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.96 524.00 505.49

b. Skilled Laborer 2 0.96 366.00 706.14

b. Laborer 2 0.96 317.00 611.60

Sub-Total for A P 1,823.22

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 1,823.22 D. Output per day = 12.00 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. Portland Cement 3 bags 260.00 780.00 b. Sand (for plastering) 0.20 cu.m. 1,300.00 260.00

c. 6mm.Ø Washed Pebbles 2 bags 473.00 946.00

Sub-Total for E P 1,986.00

F. Direct Cost (C+E) 3,809.22

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 190.46

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 3,999.68

k. Total Unit Cost 345.51

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10

UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

Note: One out of 3 bags of cement will be used on pavers

Page 15: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: SPL - 6 Painting Works

Unit of Measurement: sq.m.

Output per day: 54.40 sq.m./day

Quantity: 19.74 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.36 524.00 190.14

b. Skilled Laborer 2 0.36 366.00 265.62

b. Laborer 1 0.36 317.00 115.03

Sub-Total for A P 570.79

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 570.79 D. Output per day = 54.40 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. Concrete Neutralizer 1 gal. 297.00 297.00 b. Solvent Based Acrylic Cast 1 gal. 438.00 438.00

c. Solvent Based Acrylic Primer 2 gals. 743.00 1,486.00

d. Solvent Based Acrylic Top Coat White 4 gals. 783.00 3,132.00

Solvent Based Thermoplastic Acrylic Rasin:

e. Raw Sienna (1L/can) 1 can 110.00 110.00

f. Hansa Yellow (1L/can) 1 can 110.00 110.00

g. Black (1L/can) 1 can 110.00 110.00

h. Liquid Tile Venetian Red 1 can 110.00 110.00

i. Liquid Tile Thalo Blue 1 can 110.00 110.00

j. Body Filler w/ Hardener 1 gal. 554.00 554.00

k. Solvent Based Acrylic Reducer 2 gals. 385.00 770.00

l. #120 Sand Paper 8 pcs. 16.00 128.00

m. #150 Sand Paper 8 pcs. 16.00 128.00

n. 7" Roller Brush w/ Handle 1 pcs. 35.00 35.00

o. 4" Paint Brush 2 pcs. 85.00 170.00

p. 2" Paint Brush 2 pcs. 30.00 60.00

Sub-Total for E P 7,748.00

F. Direct Cost (C+E) 8,318.79

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 29 s 2011 415.94

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 -

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 -

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

Page 16: Hand Wash Counter - By Admin

J. Total Cost 8,734.73

k. Total Unit Cost 442.49

Page 17: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: SPL - 7 Wall Siding Installation

Unit of Measurement: sq.m.

Output per day: 54.40 sq.m./day

Quantity: 1.42 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.03 524.00 15.72

b. Skilled Laborer 1 0.03 366.00 10.98

b. Laborer 1 0.03 317.00 9.51

Sub-Total for A P 36.21

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 36.21 D. Output per day = 54.40 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 6mm. Thk. x 1.20m. x 2.40m. Marine Plywood 1 sht. 509.00 509.00

b. 6pcs. - 2" x 2" x 8' Mahogany Wood 16 bd.ft. 41.00 656.00

c. 4" C.W. Nail 0.25 kg. 85.00 21.25

Sub-Total for E P 1,186.25

F. Direct Cost (C+E) 1,222.46

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 22 s 2015 61.12

H. Contractor's Profit (CP) 0% per D.O. 22 s 2015 -

I. Value Added Tax (VAT) 0% per D.O. 22 s 2015 -

J. Total Cost 1,283.58

k. Total Unit Cost 903.93

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

Page 18: Hand Wash Counter - By Admin

Page 18 of 26

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: SPL - 8 Plumbing Works

Unit of Measurement: fixtures

Output per day: 1.33 fixture/day

Quantity: 4.00 fixtures

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 3 524.00 1,572.00

b. Skilled Laborer 1 3 366.00 1,098.00

b. Laborer 1 3 317.00 951.00

Sub-Total for A P 3,621.00

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

a. Portable Electric Handrill 1 3 300.00 900.00

b. Portable Pipe Threader 1 3 500.00 1,500.00

Minor Tools (10% of labor cost) 362.10

Sub-Total for B P 2,762.10

C. Total (A+B) 6,383.10 D. Output per day = 1.33 fixtures/day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materials1. Fixtures and Accessories

4 units 269.00 1,076.00

2. Sanitary Pipes

100mm.Ø x 50mm.Ø Sanitary PVC Tee, S-100 2 pcs. 116.00 232.00

100mm.Ø x 3.00m. Sanitary PVC Pipe, S-1000 1 pc. 693.00 693.00

50mm.Ø x 3.00m. Sanitary PVC Pipe, S-1000 2 pcs. 260.00 520.00

100mm.Ø Sanitary PVC Coupling, S-1000 1 pc. 66.00 66.00

50mm.Ø Sanitary PVC P-Trap, S-1000 4 pcs. 102.00 408.00

50mm.Ø x 50mm.Ø Sanitary PVC Tee, S-1000 2 pcs. 46.00 92.00

2 pcs. 33.00 66.00

1 pcs. 76.00 76.00

1 pc. 78.00 78.00

PVC Pipe Cement Solvent (200cc/can) 3 cans 166.00 498.00

3. Cold Pipe2 pcs. 23.00 46.00

8 pcs. 30.00 240.00

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10

UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

100mm. x 100mm. Stainless Floor Drain w/ Double Strainer

50mm.Ø x 90o Sanitary PVC Elbow, S-1000

100mm.Ø x 45o Sanitary PVC Elbow, S-1000100mm.Ø Sanitary PVC Clean Out Adaptor and Plug, S-1000

12mm.Ø x 90o G.I. Elbow, ANSI B16.3 Class 150-

Standard12mm.Ø x 12mm.Ø G.I. Tee, ANSI B16.3 Class 150-Standrad

Page 19: Hand Wash Counter - By Admin

Page 19 of 26

1 pc. 97.00 97.00

12mm.Ø Water Meter Stand Set 1 pc. 1,675.00 1,675.00

2 pcs. 746.00 1,492.00

8 pcs. 18.00 144.00

12mm.Ø G.I. Cap, ANSI B16.3 Class 150-Standard 1 pc. 11.00 11.00

12mm.Ø Faucet - Plain Bibb 6 pcs. 359.00 2,154.00

19mm. Teflon Tape 5 rolls 31.00 155.00

Sub-Total for E P 9,819.00

F. Direct Cost (C+E) 16,202.10

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 29 s 2011 810.11

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 -

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 -

J. Total Cost 17,012.21

k. Total Unit Cost 4,253.05

12mm.Ø G.I. Union Patent, ANSI B16.3 Class 150-Standard

12mm.Ø x 6.00m. G.I. Pipe ASTM A53-90A Heavy Gauge Standard12mm.Ø G.I. Coupling, ANSI B16.3 Class 150-Standard

Page 20: Hand Wash Counter - By Admin

DETAILED UNIT PRICE ANALYSIS

PROJECT NAME:

Location:

Item No./Description: SPL - 9 Scaffolding Works

Unit of Measurement: sq.m.

Output per day: 5.20 sq.m. /day

Quantity: 4.46 sq.m.

Designation No. Person No. of Days Daily Rate Amount

A. Labor

a. Construction Foreman/Eng'g Assist. 1 0.86 524.00 450.64

b. Skilled Laborer 1 0.86 366.00 314.76

b. Laborer 1 0.86 317.00 272.62

Sub-Total for A P 1,038.02

Name and Capacity No. of Units No. of Days Daily Rate Amount

B. Equipment

N/A

Sub-Total for B P -

C. Total (A+B) 1,038.02 D. Output per day = 5.20 sq.m. /day

Name and Specifications Quantity Unit Unit Cost Amount

E. Materialsa. 10pcs. - 2" x 4" x 10' Coco Lumber 0.15812 cu.m. 8,899.44 1,407.18

b. 7pcs. - 2" x 3" x 10' Coco Lumber 0.08260 cu.m. 8,899.44 735.09

c. 4" C.W. Nail 2 kgs. 85.00 170.00

Sub-Total for E P 2,312.27

F. Direct Cost (C+E) 3,350.29

G. Overhead, Contingencies & Miscellaneous 5% per D.O. 29 s 2011 167.51

H. Contractor's Profit (CP) 0% per D.O. 29 s 2011 -

I. Value Added Tax (VAT) 0% per D.O. 29 s 2011 -

J. Total Cost 3,517.81

k. Total Unit Cost 788.75

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10

UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

Page 21: Hand Wash Counter - By Admin

Republic of the PhilippinesZAMBOANGA CITY WATER DISTRICT

Pilar St., Zamboanga City

GANTT CHARTPROJECT : CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Location : Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga CityProject Cost : Php 143,805.89 Project Duration : Thirty (30) Calendar DaysManpower Requirements : 11 Manpower (1-Construction Foreman/Eng'g Assist., 4-Laborer and 6-Skilled Laborer)

Work Item Amounts % PerfectedC A L E N D A R D A Y S

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

Mobilization/Demobilization PhP 1,356.66 0.94%103 Layout and Excavation Works PhP 1,567.32 1.09%

104 Embankment PhP 1,243.20 0.86%

404 Reinforcing Steel Bar PhP 10,009.53 6.96%

405 Structural Concrete PhP 22,794.87 15.85%

SPL-1 Roofing Works PhP 47,359.20 32.93%

SPL-2a Setting of 100mm. Thk. CHB PhP 5,524.05 3.84%

SPL-3a Ceiling Joist and Hangers PhP 3,734.01 2.60%SPL-3b Installation of Ceiling Board PhP 2,616.71 1.82%SPL-3c Installation of Fascia Board PhP 3,001.74 2.09%SPL-4 Tile Works PhP 10,050.60 6.99%SPL-5 Plastering Works (16mm. Thk.) PhP 3,999.68 2.78%SPL-6 Painting Works PhP 8,734.73 6.07%SPL-7 Wall Siding Installation PhP 1,283.58 0.89%SPL-8 Plumbing Works PhP 17,012.21 11.83%SPL-9 Scaffolding Works PhP 3,517.80 2.45%

TOTAL PROJECT COST Php 143,805.89 100%

CASH OUTLAY REQUIREMENT Php143,805.89

TARGETED COMPLETION THIS PERIOD 100.00%

COMMULATIVE COMPLETION TO DATE 100.00%

Recommending

Prepared by: Checked & Submitted by: Approved by: Project Implementation: Approved for Project Implementation:

FELIXBERTO R. CAARE, JR. RMP EDITO M. BAUTISTA MARLI ACOSTA-DE FIESTA ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZResearcher/Analyst A (J.O.) Officer-In-Charge Officer-In-Charge Assistant General Manager General ManagerPlanning Division Design Division Engineering and Construction DepartmentTechnical Services Group

Page 22: Hand Wash Counter - By Admin

Republic of the PhilippinesZAMBOANGA CITY WATER DISTRICT

Pilar Street, Zamboanga CityStandard Form Number: SF-INFR-01 Contract Reference Number

Revised on: July 28, 2004 Name of the Contract

Location of the Contract

APPROVED BUDGET FOR THE ADMIN.

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

Stations : Length : Contract Duration: Thirty (30) Calendar Days

DESCRIPTION QUANTITY UNIT

MARK-UPSTOTAL MARK-UP

VAT TOTAL COSTITEM ESTIMATED IN PERCENT TOTAL UNITNO. DIRECT COST

OCM PROFIT % VALUEINDIRECT COST COST

(1) (2) (3) (4) (5) (6) (7) (8)(9) (10) (11) (12) (13)

(5)X(8) 5%((5)+(9)) (9)+(10) (5)+(11) (13)/(3)Mobilization/Demobilization 1 lot 1,356.66 0% 0% 0% 0.00 0.00 0.00 1,356.66 1,356.66

103 Layout and Excavation Works 1.84 cu.m. 1,492.69 5% 0% 5% 74.63 0.00 74.63 1,567.32 851.80104 Embankment 2.00 cu.m. 1,184.00 5% 0% 5% 59.20 0.00 59.20 1,243.20 621.60404 Reinforcing Steel Bar 161.14 kgs. 9,532.89 5% 0% 5% 476.64 0.00 476.64 10,009.53 62.12405 Structural Concrete 2.93 cu.m. 21,709.40 5% 0% 5% 1,085.47 0.00 1,085.47 22,794.87 7,770.11

SPL-1 Roofing Works 10.09 sq.m. 45,104.00 5% 0% 5% 2,255.20 0.00 2,255.20 47,359.20 4,693.68SPL-2a Setting of 100mm. Thk. CHB 8.49 sq.m. 5,261.00 5% 0% 5% 263.05 0.00 263.05 5,524.05 650.50SPL-3a Ceiling Joist and Hangers 10.09 sq.m. 3,556.20 5% 0% 5% 177.81 0.00 177.81 3,734.01 370.07SPL-3b Installation of Ceiling Board 10.09 sq.m. 2,492.10 5% 0% 5% 124.61 0.00 124.61 2,616.71 259.34SPL-3c Installation of Fascia Board 11.49 sq.m. 2,858.80 5% 0% 5% 142.94 0.00 142.94 3,001.74 261.25SPL-4 Tile Works 6.37 sq.m. 9,572.00 5% 0% 5% 478.60 0.00 478.60 10,050.60 1,577.80SPL-5 Plastering Works (16mm. Thk.) 11.58 sq.m. 3,809.22 5% 0% 5% 190.46 0.00 190.46 3,999.68 345.51SPL-6 Painting Works 19.74 sq.m. 8,318.79 5% 0% 5% 415.94 0.00 415.94 8,734.73 442.49SPL-7 Wall Siding Installation 1.42 sq.m. 1,222.46 5% 0% 5% 61.12 0.00 61.12 1,283.58 903.93SPL-8 Plumbing Works 4.00 fixtures 16,202.10 5% 0% 5% 810.11 0.00 810.11 17,012.21 4,253.05SPL-9 Scaffolding Works 4.46 sq.m. 3,350.29 5% 0% 5% 167.51 0.00 167.51 3,517.80 788.75

TOTAL 137,022.60 6,783.29 143,805.90

Prepared by: Checked & Reviewed by: Approved by: Recommending Project Implementation:

FELIXBERTO R. CAARE, JR., RMP EDITO M. BAUTISTA, JR. MARLI ACOSTA - DE FIESTA ARNULFO A. ALFONSO

Researcher/ Analyst A (J.O.) Officer-In-Charge Officer-In-Charge Assistant General ManagerPlanning Division Design Division Engineering & Construction DepartmentTechnical Services Group

Approved for Project Implementation:

LEONARDO REY D. VASQUEZGeneral Manager

Page 23: Hand Wash Counter - By Admin

PROJECT/LOCATION OF PROJECT: CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)

Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

BREAKDOWN OF EXPENDITURES % OF TOTAL AMOUNTI - ESTIMATED COST

A. DIRECT COST:1. Mobilization/Demobilization . . . . . . . . . . . . . . . . . . . . . 0.99 1,356.66 2. Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 63.03 86,147.70

2.1 Supply Delivery . . . . . . . . . . . . . . . . . . . . . . . . .2.2 Testing Materials . . . . . . . . . . . . . . . . . . . . . . . .

3. Labor (including fringe benefits) . . . . . . . . . . . . . . . . . . 21.00 28,700.77 4. Equipment Expenses . . . . . . . . . . . . . . . . . . . . . . . . . 9.65 13,182.49

B.1. INDIRECT COST:1. Overhead contingency Miscellaneous . . . . . . . . . . . . . . 4.68 6,401.55 2. Profit . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

B.2. VAT & INCIDENTAL EXPENSES:1. Comprehensive All Risk Insurance . . . . . . . . . . . . . . . .2. Value Added Tax (5% of EDC, OCM and Profit) . . . . . . 3. Materials Testing 7% of 1% of OCM . . . . . . . . . . . . . .

S U B - T O T A L (CONTRACT COST) 135,789.20

II - ESTIMATED GOVERNMENT EXPENDITURES1. Engineering & Administrative Overhead 0.65 882.63 2. POW/Site Acquisition/Pre-Engineering3. Materials to be furnished by the government4. Materials Quality Control & Hydrology (MQCH)5. Retention for RO & C.O.

S U B - T O T A L

III - CONTINGENCIES/RESERVED:

1. Physical (up to 5% of the Estimated Contract Cost) . . . . . . .

2. Price Escalation (up to 12% of the Estimated Contract Cost) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3. Preliminary Engineering . . . . . . . . . . . . . . . . . . . . . . . . . .

TOTAL ESTIMATED PROJECT COST 100.00 136,671.83

PREPARED BY: CHECKED & SUBMITTED BY:

FELIXBERTO R. CAARE, JR., RMP EDITO M. BAUTISTA, JR.Researcher/Analyst A (J.O.) Officer - In - Charge

Planning Division Design Division

APPROVED BY: RECOMMENDING PROJECT IMPLEMENTATION:

MARLI ACOSTA - DE FIESTA ARNULFO A. ALFONSOOfficer - In - Charge Assistant General Manager

Eng'g and Construction Department Technical Services Group

APPROVED FOR PROJECT IMPLEMENTATION:

LEONARDO REY D. VASQUEZ

Page 24: Hand Wash Counter - By Admin

General Manager

Page 25: Hand Wash Counter - By Admin

Republic of the Philippines ZAMBOANGA CITY WATER DISTRICT

Pilar Street, Zamboanga City

INDIVIDUAL PROGRAM OF WORK

31-Mar-15

PROJECT/LOCATION OF PROJECT: APPROPRIATE: Php136,671.83SOURCE OF FUNDS:ISSUED OBLIGATED:AUTHORITY RELEASED:CALENDAR DAYS Thirty (30) Calendar Days

PROJECT CATEGORY: TO COMPLETE:DESIRABLE STARTING DATE: upon Approval

School FacilityCONTRACT / / ADMINISTRATION / X /

PROJECT DESCRIPTION:Construction of 10 Units Faucet Hand Washing Counter

MININUM EQUIPMENT REQUIRED TECHNICAL PERSONNEL REQUIREDDescription No. Description No. Description No. Description

1 Construction Foreman/Eng'g Assist.1 Carpenter 1 Plumber1 Steelman1 Welder1 Painter1 Masons4 Laborers

ESTIMATED COST OF PROPOSED PROJECTS

ITEM NO. DESCRIPTION UNIT QTY.DIRECT COST

TOTAL UNIT COSTMobilization/Demobilization 0.99% lot 1.00 1,356.66 1,356.66 1,356.66

103 Layout and Excavation Works 1.09% cu.m. 1.84 1,492.69 811.24 851.81 104 Embankment 0.86% cu.m. 2.00 1,184.00 592.00 621.60 404 Reinforcing Steel Bar 6.96% kgs. 161.14 9,532.89 59.16 62.12 405 Structural Concrete 15.84% cu.m. 2.93 21,709.40 7,400.11 7,770.11

SPL-1 Roofing Works 32.92% sq.m. 10.09 45,104.00 4,470.17 4,234.96 SPL-2a Setting of 100mm. Thk. CHB 3.84% sq.m. 8.49 5,261.00 619.52 650.50 SPL-3a Ceiling Joist and Hangers 2.60% sq.m. 10.09 3,556.20 352.45 372.15

SPL-3b Installation of Ceiling Board 1.82% sq.m. 10.09 2,492.10 246.99 257.91

SPL-3c Installation of Fascia Board 2.09% sq.m. 11.49 2,858.80 248.81 265.94

SPL-4 Tile Works 6.99% sq.m. 6.37 9,572.00 1,502.67 1,663.07

SPL-5 Plastering Works (16mm. Thk.) 2.78% sq.m. 11.58 3,809.22 329.06 345.51

SPL-6 Painting Works 6.07% sq.m. 19.74 8,318.79 421.42 442.49

SPL-7 Wall Siding Installation 0.89% sq.m. 1.42 1,222.46 860.89 903.93

SPL-8 Plumbing Works 11.82%fixtures 4.00 16,202.10 4,050.53 4,253.05

SPL-9 Scaffolding Works 2.45% sq.m. 4.46 3,350.29 751.19 788.75

TOTAL 100% 137,022.60

PREPARED BY: CHECKED & SUBMITTED BY:

FELIXBERTO R. CAARE, JR., RMP EDITO M. BAUTISTA, JR.Researcher/Analyst A (J.O.) Officer - In - Charge

Planning Division Design Division

APPROVED BY: RECOMMENDING PROJECT IMPLEMENTATION:

MARLI ACOSTA - DE FIESTA ARNULFO A. ALFONSO

Officer - In - Charge Assistant General Manager

Eng'g and Construction Department Technical Services Group

APPROVED FOR PROJECT IMPLEMENTATION:

CONSTRUCTION OF 1 - UNIT HAND WASHING COUNTER DETACHED (10 UNITS OF FAUCET)

Guiwan Elementary School, Bougainvillea Road, Brgy. Guiwan, Zamboanga City

% OF TOTAL

ADJUSTED UNIT COST

Page 26: Hand Wash Counter - By Admin

LEONARDO REY D. VASQUEZ

General Manager