Subproject: Distribution Efficiency Project
Environmental Management Plan
HA NOI POWER CORPORATION
------------------------------------------------------------
Distribution Efficiency Project (dep)
HA NOI POWER CORPORATION
Component 1: Improve rural nework of old
Ha Noi area - phase 1
Component 1: Improve Ha Dong District
and Son Tay town networks
Environmental Management Plan
(EMP)
Establisher : Pham Thi Hai
Ha noi, 19 April 2012.
dong hai consulting and construction joint stock company
E3035 v8 P
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
ed
Subproject: Distribution Efficiency Project
Environmental Management Plan
Table of contents
(EMP) ......................................................................................................................................... 1
I. GENERAL INTRODUCTION .............................................................................................. 4 II. POLICY, REGULATIONS, AND INSTITUTIONAL FRAMEWORKS ........................... 4
2.1. Vietnamese Legislations ................................................................................................. 4 2.2. World Bank Safeguard Policies ...................................................................................... 5
III. SUBPROJECT DESCRIPTION AND SCOPE OF WORK ............................................... 5
3.1. Objectives of the Subproject ........................................................................................... 5 3.2 Subproject Location ......................................................................................................... 5 3.3 Subproject Management Organization ............................................................................ 7 3.4. Subproject description .................................................................................................... 7
3.4.1 Medium voltage line .................................................................................................. 7 3.4.2 Medium voltage underground cable ...................................................................... 10 3.4.3 Low voltage line ...................................................................................................... 13 3.4.4 Substation ................................................................................................................ 18
3.6. Main Activities Before and During Construction ......................................................... 25 3.6.1. Main Activities Before and During Construction .................................................. 25 3.6.2 Transprortation ....................................................................................................... 25
3.7. Subproject Implementation Schedule and Total Investment ........................................ 26 3.7.1. Subproject Implementation Schedule ..................................................................... 26 3.7.2. Total investment of the project: ............................................................................. 26
IV. ENVIRONMETNAL BACKGROUND ........................................................................... 27 4.1. Summary of natural condition and society of Long Bien district. ............................... 27
4.2. Summary of natural condition and society of Hoang Mai district. .............................. 28 4.4. Summary of natural condition and society of Soc Son district. .................................... 29
4.5. Summary of natural condition and society of Gia Lam district. .................................. 30 4.6. Summary of natural condition and society of Dong Anh district. ................................ 30
4.7. Summary of natural condition and society of Ha Dong district. .................................. 31 4.8. Summary of natural condition and society of Son Tay town........................................ 32
V. SUBPROJECT POTENTIAL IMPACTS ........................................................................... 32 5.1. Environmental screening: ............................................................................................. 32
VI. ENVIRONMENTAL MANAGEMENT PLAN: .............................................................. 38 6.1. Mitigation measures: ..................................................................................................... 38
VII.ENVIRONMENTAL MONITORING PLAN .................................................................. 51 VIII. EMP IMPLEMENTATION ARRANGEMENT AND CAPACITY BUILDING ......... 54
a) During Detailed Design and Preparation of Bidding Contract Documents ................. 54
b) During Construction Phase .......................................................................................... 54 IX. REPORTING PROCEDURE ............................................................................................ 56
X. CAPACITY BUILDING FOR EMP IMPLEMENTATION.............................................. 57 XI.ESTIMATED COST FOR IMPLEMENTING THE EMP ................................................ 58 XII. COMMUNITY CONSULTATION AND DISCLOSURE OF INFORMATION........... 59
12.1 Community consultation: ............................................................................................. 59 12.2 Disclosure of information: ........................................................................................... 64
ANNEX 1................................................................................................................................. 65 TOR for monitoring of emp implementation for construction supervising consultant ........... 65 ANNEX 2................................................................................................................................. 67 Report template for monitoring of EMP implementation ........................................................ 67 ANNEX 3................................................................................................................................. 69
Subproject: Distribution Efficiency Project
Environmental Management Plan
Report template for monitoring of EMP implementation ........................................................ 69
ANNEX 4................................................................................................................................. 71 Subproject area map ................................................................................................................. 71
ANNEX 5................................................................................................................................. 72 Some pictures of project area ................................................................................................... 72 ANNEX 6................................................................................................................................. 73 Consultancy minutes ................................................................................................................ 73 ANNEX 7................................................................................................................................. 74
Environmental protection commitment ................................................................................... 74
Subproject: Distribution Efficiency Project
Environmental Management Plan
I. GENERAL INTRODUCTION
According to electric network investigation figures at 8 districts of Ha Noi city found
that some of Medium voltage lines and low voltage networks not ensure reliability and safety
in supply electricity needed to be upgraded voltage and fall cable for ensure reliability.
Although Some of Low voltage networks are still good but go in the garden of private house,
too close the private house. This will make the operation meet with difficulty in the future.
Therefore, they have to be adjusted to reduce compensation cost. Many actual substations is
over load because the the growing rate is too fast. Thus, the upgrowth of capacity and
supplement of substation to share for actual over load substation is necessary.
Ha Noi Distribution Efficiency subproject comprises two components as follow:
1.Component 1: Improve rural network of old Ha Noi area – phase 1
2.Component 2: Improve Ha Dong District and Son Tay town networks
The Subproject is implemented in 8 districts of Ha Noi city include: Long Bien District,
Hoang Mai district, Tu Liem urban district, Gia Lam urban district, Soc Son urban district,
Dong Anh urban district, Ha Dong district and Son Tay town.
The activities of the project include: i) Construct fifty two of new 35/0.4 kV and
22/0.4kV substations; ii) improve 25 substations; iii) move 9 substations; iv) New
construction and improve 25.427 km 22kV and 35kV underground cable; v) New
construction and improve 926.842 km low voltage line. These activities can cause negative
impacts on environment and public in preconstruction phase, construction phase and
operation phase.
To ensure that the potential negative impacts are identified and mitigated during project
implementation and compliance with policies on environment assessment of World Bank -
(OP/BP 4.01), Environment Management Plan (EMP) of project had been prepared in
accordance with the guidance of the Environment Management Framework (EMF) of DEP.
This EMP includes: project description, policy framework, regulations of environmental
technical, the potential negative impacts, the proposed mitigation methods will be
implemented in the periods of pre-construction, construction and operation, implementation
arrangements. EMP also includes Environmental Codes of Practice (ECOP) will be
incorporated into tender documents and contract, attached with environmental monitoring.
According to regulations of VietNam government, the subproject has to make
environmental protection commitment. The environmental protection commitment of the
subproject is confirmed in the document No 288/TB-UBND dated on 13 December, 2011 by
Gia Lam District people’s Commitee – Ha Noi city, Document No 712/TB-UBND dated on
27th December, 2011 by Hoang Mai District people’s Commitee – Ha Noi city, document No
643/TB-UBND dated on 31st December, 2011 by Tu Liem District people’s Commitee – Ha
Noi city.
II. POLICY, REGULATIONS, AND INSTITUTIONAL FRAMEWORKS
2.1. Vietnamese Legislations
Law on Protection of the Environment No. 52/2005/QH11 passed by the
National Assembly on November, 29th
, 2005 regulates the obligations of individuals,
organizations in protecting environment.
Law on Water Resource No. 08/1998/QH10 dated 20 May, 1998
Decree of Government No. 80/2006/ND-CP dated 9 August, 2006 on guidance
for implementation of Law on Protection of the Environment.
Subproject: Distribution Efficiency Project
Environmental Management Plan
Decree of Government No. 29/2011/ND-CP dated 18 April, 2006 regulating
strategic environmental assessment, environmental impact assessment and
environment protection commitment.
Circular No.26/2011/TT-BTNMT dated 18 July, 2011 on guidance for Decree
No.29/2011/ND-CP dated 18 April, 2011.
Decree of Government No.106/2005/ND-CP dated 17 August, 2005 on
guidance for Law on electricity relating to the protection of high-voltage networks.
Decree of Government No.81/2009/ND-CP dated 12 October, 2009 amending
some Article of Decree No.106/2005/ND-CP dated 17 August, 2005.
Circular No.12/2011/TT-BTNMT dated 14 April, 2011 relating to toxic waste
management.
Vietnam National Standard: QCVN01: 2009/BYT- national technical
regulation on drinking water quality; QCVN02: 2009/BYT- national technical
regulation on domestic water quality; QCVN08: 2008/BTNMT - national technical
regulation on surface water quality; QCVN09: 2008/BTNMT - national technical
regulation on ground water quality; QCVN05: 2009/BTNMT – air quality – Standard
for ambient air quality; QCVN06: 2009/BTNMT – air quality –specified maximum
allowable concentrations of certain hazardous substances in ambient air.
Guidance of EVN No. 2623/CV-EVN - KHCN & MT dated 28 May, 2007 on
management and pollution prevention and exposure to PCBs.
2.2. World Bank Safeguard Policies
An environmental screening was undertaken in line with the guidelines provided in the
Environmental Management Framework (EMF) of the DEP project and it showed that the
World Bank’s policies on Environmental Assessment (OP 4.01) and Involuntary
Resettlement (OP 4.12) will be triggered for the subproject. In addition, the Bank’s
requirements on public consultation and information disclosure will need to be followed. The
implementation of policy on involuntary resettlement (OP 4.12) will be addressed in a
separate report.
III. SUBPROJECT DESCRIPTION AND SCOPE OF WORK
3.1. Objectives of the Subproject
The objectives of the proposed subproject are to:
- Prevent overload of the local power grid for the subproject communes
- Reduce power losses, improve electricity quality, and provide stable power the areas.
- New construction and improve electric network to meet demand for use of electricity
to develop socio-economic at present and in the future of subproject area.
3.2 Subproject Location
The subproject is implemented in 74 communes in 8 districts of Ha Noi city comprise:
Long Bien District, Hoang Mai district, Tu Liem urban district, Gia Lam urban district, Soc
Son urban district, Dong Anh urban district, Ha Dong district and Son Tay town.
List of communes in the project, as follow:
Subproject: Distribution Efficiency Project
Environmental Management Plan
Hoang Mai district (7 wards)
Thinh Liet ward
Đai Kim ward
Hoang Liet ward
Linh Nam ward
Yen So ward
Hoang Van Thu ward
Thanh Tri ward
Tu Liem district (9
communes )
Trung Van commune
Me Tri commune
Tay Tuu commune
Xuan Phuong commune
Minh Khai commune
Tay Mo commune
Dai Mo commune
Thuy Phuong commune
Phu Dien commune
Gia Lam District (10
communes)
Yen Vien commune
Yen Thuong commune
Phu Dong commune
Co Bi commune
Dang Xa commune
Trau Quy Townlet
Da Ton commune
Kim Son commune
Duong Xa commune
Phu Thuy commune
Dong Anh disctrict (5
communes)
Kim No
Co Loa
Dai Mach
Viet Hung
Vong La
Long Bien district (9
wards):
Long Bien ward
Ngoc Thuy ward
Duc Giang ward
Sai Dong ward
Thuong Thanh
Viet Hung ward
Bo De ward
Phuc Loi ward
Gia Thuy ward
Soc Son district (15
communes)
Hong Ky commune
Trung Gia commune
Tan Minh commune
Kim Lu commune
Xuan Thu commune
Tan Dan commune
Minh Tri commune
Mai Dinh commune
Hien Ninh commune
Phu Lo commune
Phu Ninh commune
Quang Tien commune
Duc Hoa commune
Xuan Giang commune
Viet Long commune
Ha Dong (6 wards)
Phu Luong ward
Phu Lam ward
Phu La ward
Dong Mai ward
Bien Giang ward
Yen Nghia ward
Son Tay Town (13 wards,
communes)
Son Dong commune
Kim Son commune
Co Dong commune
Xuan Son commune
Thanh My commune
Duong Lam commune
Xuan Khanh ward
Phu Thinh ward
Trung Son Tram ward
Ngo Quyen commune
Le Loi Ward
Son Loc Ward
Subproject: Distribution Efficiency Project
Environmental Management Plan
Quang Trung Ward
3.3 Subproject Management Organization
- Subproject Owner: Electricity of Ha Noi coporation
- Technical Design Consulting Unit: Dong Hai consulting and construction joint stock
company.
- Subproject Management Unit: Project management Board of EVN Ha Noi - Electricity
of Ha Noi coporation.
3.4. Subproject description
3.4.1 Medium voltage line
Newly construction and improve 35.182 km medium voltage line. Length of section and
subproject areas which line passes descriped as follow:
Table 3.4.1 Table of description of improvement and newly construction medium
voltage line
No
Section Length
(m) Description
I Dong Anh district
1 CoLoa commune
MV transmission line
supply electricity for
Xom Vang 2
substation
500
The line goes along the rice field and the village
road to new Xom Vang 2 Substation
2 Viet Hung commune
MV transmission line
supplies electricity for
Gia Luong 3
substation
450
MV transmission line supplies electricity for Gia
Luong 3 substation is connected to the pole of Gia
Luong 2 substation belong to 473E1 feeder. It
passes through the rice fields and village road to
New Gia Luong 3 substation.
MV transmission line
supplies electricity for
Lo Giao 2 substation
450
MV transmission line supplies electricity for Lo
Giao 2 substation connected to Pole 1 belong to
473E1 feeder. It passes through the road then goes
along the village road to new Lo Giao 2 substation.
MV transmission line
supplies electricity for
Doai 3 substation
270
It starts at pole No 7 belong to feeder476 E1. It
passes through the railway then goes along the
village road of Viet Hung commune then goes
across the rice field to new Doai 3 substation.
3 Vong La commune
MV transmission line
supplies electricity for
Lang Chai 3
substation
330
The line starts from connected point pole then goes
along the village road to new Lang Chai 3
substation.
II Soc Son district
1 Hong Ky commune
Branch to Ca Phe 3
substation 1,080
The branch is connected at the pole before the pole
belong to Tan Yen substation – feeder Trung Gia
Subproject: Distribution Efficiency Project
Environmental Management Plan
972-TG. It goes above the rice field to Ca Phe 3
substation
2 Trung Gia commune
Branch to Xom Do
substation 356
The branch is connected at T6 pole belong to feeder
972 TG. It goes along the village road to Xom Do
substation.
Branch to Xuan Son
substation
256
The branch is connected at feeder972 TG. It goes
along the village road and rice field to Xuan Son 3
Substation
3 Tan Minh commune
Branch to Xuan Dong
substation 30
The branch is connected at no number pole belong
to 674 Da Phuc intermediate feeder. It goes along
the village road to Xuan Dong substation
Branch to Son Doai
substation
520
The branch is connected at no number pole belong
to 974 Da Phuc intermediate feeder. It goes along
the village road to Son Doai 3 substation.
4 Kim Lu commune
Branch to Xuan
Duong 2 substation 500
The branch is connected at pole number 3 belong to
674 feeder. It goes along the village road to Xuan
Duong 2 substation
Branch to Kim Trung
substation 300
The branch is connected at no number pole before
Kim Trung 1 substation. It goes along the village
road to Kim Trung 2 substation.
5 Xuan Thu commune
Branch to Xuan Lai 4
substation 350
The branch is connected at no number pole belong
to 674 Da Phuc intermediate feeder. It goes along
the village road to Xuan Ap substation
6 Tan Dan commune
Branch to Xuan Ap
substation 700
The branch is connected at the pole before electric
industrial school. It goes along the village road to
Xuan Ap substation.
Branch to My Linh 3
substation branch
100
The branch is connected at pole number 5 belong to
478 E1.19 feeder. It goes along the village road to
My Linh 3 substation.
7 Minh Tri commune
Branch to Go Gao
substation
1,252
The branch is connected at the pole before Dong
Bong substation belong to 478 E19 feeder. It goes
along the village road to Go Gao substation
Branch to Lap Tri 4
substation
531
The branch is connected at the pole before Dong
Bong 2 substation belong to 478 E19 feeder. It goes
along the village road to Lap Tri 4 substation.
8 Mai Dinh commune
Branch to Hoang
Duong substation
400
The branch is connected at the added pole between
31 and 32 pole belong to 672 Da Phuc intermediate
feeder. It goes along the village road to Hoang
Duong substation.
Subproject: Distribution Efficiency Project
Environmental Management Plan
Branch to Noi Phat
Substation
900
The branch is connected at no number pole belong
to 673 Phu Lo intermediate feeder. It goes along the
village road to Noi Phat substation.
9 Phu Lo commune
Branch to Phu Lo 9
substation 150
The branch is connected at the pole number 16
belong to 671 Phu Lo intermediate feeder. It goes
along the village road to Phu Lo 9 substation
10 Phu Linh commune
Branch to Ve Linh 3
substation
40
The branch is connected at the pole number 2
belong to 478 E1.19 feeder. It goes along the village
road to Ve Linh 3 substation
Branch to Cong Hoa
2 substation
300
The branch is connected at the pole number 7
belong to 972 Da Phuc intermediate feeder. It goes
along the village road to Cong Hoa 2 substation
11 Duc Hoa commune
Branch to Thanh Hue
2
600
The branch is connected between pole 20 and 21
belong to 674 Da Phuc intermediate feeder. It goes
along the village road to Thanh Hue 2 substation.
Branch to Hau Duc 3
400
The branch is connected at the pole number 6
belong to 674 Da Phuc intermediate feeder. It goes
across the field to Duc Hau 2 substation.
Branch to Duc Hoa 4
substation
400
The branch is connected at the pole number 2
belong to 674 Da Phuc intermediate feeder. It goes
along the village road to Duc Hoa 4 substation
12 Xuan Giang
commune
Branch to Lai Cach 3
substation 490
The branch is connected to 478 E1.19 feeder. It goes
along the village road to Lai Cach 3 substation.
13 Viet Long commune
Branch to Tang Long
2 substation
70
The branch is connected to 973 Trung Gia-Dong
Ngan feeder. It goes along the village road to Tang
Long 2 substation.
Branch to Luong
Phuc 2 substation 300
The branch is connected to 478-E19 feeder. It goes
along the village road to Lai Cach 3 substation.
III Long Bien district
1 Ngoc Thuy ward
Branch to Ngoc Thuy
group 20 substation
320
The branch is connected at the pole number 6
belong to 375 E1 feeder. It goes along the field to
Ngoc Thuy group 20 substation
2 Phuc Loi Ward
Branch to Phuc Loi
14 substation
518
The branch is connected at Hoi Xa 2 substation bus
work belong to 373-E2 feeder. It goes along the
village road to Phuc Loi 14 substation
IV Ha Dong district
Phu Luong
Commune
The line passes 720 The line passes through the railway ( border Ha
Subproject: Distribution Efficiency Project
Environmental Management Plan
through the railway Dong station)
V Son Tay Town
Feeder973 starts at
E1.7 to the pole N0 6
from Tung Thien
intermediate.
6,398
This feeder starts from E1.7. It goes above the rice
field and private house to the pole number 6 from
Tung Thien intermediary. Then it is connected to
Tung Thien intermediate substation.
Feeder979 from E1.7
to the pole N0 17
9,585
This Feeder starts from E1.7. It goes across the
garden, field and private house to near 19/5 business
substation. From that point it turns left. It goes
closely to ancient town to close material depot
substation then turn right. It follows closely road 32
to the pole No 63 belong to Son Tay, Ba Vi district,
Ha Noi city.
Feeder973 from Tung
Thien intermediary to
the pole No 176
4,371
This Feeder starts from Tung Thien intermediary. It
goes along the street and the village road to close
Son Tay-Xuan Mai road. From that point it turns
right then follows closely Son Tay-Xuan Mai road
to circuit breaker 176
Branch to 8 moving
substations
1,245
3.4.2 Medium voltage underground cable
Total length of new construction and improvement medium voltage underground cable
feeder is 25.427km. The length of every section and subproject area that the line goes through
described as follow:
Table 3.4.2: Description of new construction and improve medium voltage
underground cable line
N0
Section Length
(m)
Description
I Tu Liem district
24kV Medium
voltage
underground cable
feeder to Me Tri 8
substation
416
The line goes along pavement of Do Duc Duc street
then turn in lane. It goes along side of the lane near
wasteland. It supplies electricity for new Me Tri 8
substation.
II Gia Lam district
35kV Medium
voltage
underground cable
feeder supply
electricity for Trau
Quy 11 substation
280
The line goes along canal edge of An Dao street . It
supplies electricity for new Trau Quy 11 substation.
III Hoang Mai
district
1 Yen So Ward
Subproject: Distribution Efficiency Project
Environmental Management Plan
Section from pole
14 to Yen Duyen
church substation
135 The line goes on the roadside border on private house.
Section from Yen
Duyen church
substation to Yen
Duyen 2
substation
416 The line goes on the roadside border on private house.
Section from Yen
Duyen 2
substation to Van
Chi substation
461
The line goes on the road right, a part of it boder on
private house, a part of it boder onYen So lake.
Section from pole
number 30.1 to
Yen Duyen B
substation
498
The line goes on the road right to near pole number
38. From that point it turns left to Yen Duyen B
substation.
2 Thinh Liet ward
24kV Medium
voltage
underground cable
line to Thinh Liet
10 substation
271
The line starts from Thinh Liet 2 substation belong to
feeder 484 E3. It goes along 1141 lane, Giai Phong
street to Thinh Liet 10 substation.
24kV Medium
voltage
underground cable
line to Thinh Liet
11 substation
1.066
The line starts from Thinh Liet 7 substation belong to
feeder 483 E3. It goes along 141 lane, Giap Nhi street
to RMU cabinet of Thinh Liet 11 substation.
24kV Medium
voltage
underground cable
line to Thinh Liet
12 substation
116
The line goes along 1295 lane, Giai Phong street. It
supplies electricity for new substation.
24kV Medium
voltage
underground cable
line to Thinh Liet
13 substation
44
The line goes in lane of Nguyen Chinh street.
III Long Bien
district
1 Bo De ward
underground cable
line supplies
electricity for
Ngoc Lam primary
school substation
22
The line connects at the pole number 4. It goes along
pavement to new substation.
2 Sai Dong Ward
Branch to Sai 22 The line is stretched from connected point pole to
Subproject: Distribution Efficiency Project
Environmental Management Plan
Dong 11
substation
extra-high voltage of transformer.
3 Thuong Thanh
ward
Branch to Thuong
Thanh 16
substation
450
The line goes along the lane number 29, Thuong
Thanh street (from Gia Quat Thuong Thanh
substation to new substation).
Branch to Thuong
Thanh 26 Group
substation
430
The line starts from Thanh Am 2 substation. It goes
along Thanh Am street to new substation.
4 Long Bien ward
Underground
cable line connects
feeder 477E15 to
feeder475 E2
3.000
The line starts from 24kV distribution cabinet of
110kV E15 substation to Lam Du substation (feeder
475-E2). The line goes in pavement of internal road
belong to Sai Dong industrial area and pavement of
Tu Dinh road.
IV Ha Dong district
Feeder 485E1.4
4.900
The line starts from 220kV Ha Dong substation. It
goes along 6 highway (on the right of pavement) to
Ba La turning point. From that point the feeder turns
left then goes along 21B highway. Its supplies
electricity for substations belong to Phu Lam ward
and Phu Luong ward.
Feeder 483E1.4
5.900
The line starts from 220kV Ha Dong substation. It
goes along 6 highway (most the line goes along
pavement and right lobby of 6 highway according to
direction from Ha Noi to Hoa Binh) to Dong Dung
gas station turning point. From that point the line turn
on the left then goes along to Mai Linh market - Dong
Mai ward. It supplies electricity for substations belong
to Phu La district area, Nhan Hue hamlet, Mai Linh
market belong to Dong Mai district.
Feeder 481E1.4
6.700
The line starts from 220kV Ha Dong substation ( from
6-22kV distribution room of the substation). It goes
along 6 highway (most the line goes along pavement
and right lobby of 6 highway according to direction
from Ha Noi to Hoa Binh) to Dong dung gas station
turning point. From that point the line turn left then
goes in Co Ban hamlet area. It goes along concrete
lane to Y Son Hamlet-Dong Mai ward supplies
electricity for substations belong to Co Ban hamlet
area, Nhan Dao hamlet and Y Son hamlet.
V Son Tay town
Feeder 979 from
E1.7 to pole 63
150
It is outgoing cable section that adds for outgoing
cable section of feeder 979
Subproject: Distribution Efficiency Project
Environmental Management Plan
Feeder 973 from
E1.7 to pole 6
(from Tung Thien
intermediary)
150
It is outgoing cable section that adds for outgoing
cable section of feeder 973
3.4.3 Low voltage line
Total length of newly construction and improvement low voltage line is 926.842 km.
The length of every section and subproject areas that the line goes through described as
follow:
Table 4.3: Description of new construction and improvement low voltage line
N0
Line Length
(m) Description
I Tu Liem district
1 Dai Mo commune 22,167
The line starts from Quang Tien 5 substation. It
is far from Dai Mo market about 36m. It goes
along village road.
2 Phu Dien commune 10,608
The line starts from Kieu Mai 2 substation .It is
far from Kieu Mai village pagodas about 23m.
The line goes in the village road near private
house.
3 Minh Khai commune 13,413
The line goes in the village road. The line goes
through business production area such as the line
from Cat Soi (Chem) substation. It is far from
area of material exploitation and business of Ha
Noi construction material exploitation and
business company 36m.
4 Me Tri commune 16,992 The line goes in the village road.
5 Tay Mo commune 17,245
The line goes in the village road, alley close to
private house. The line goes through the cultural
and historical such as the line goes through the
Mieu Nha Duoi pagoda. It is far from pagoda
27m.
6 Tay Tuu commune 24,637 The line goes along the village road and goes
through the crop area.
7 Trung Van commune 2,525 The line goes in the village road close to
residential area.
8 Xuan Phuong commune 17,708
The line goes along the village road. Some
sections go along the pagoda, market. The line
goes through the Nhon market distance market
33m. The line goes through the Ngoc Mach
pagoda area distance pagodas 9m. The line goes
through the Thi Cam pagoda distance
pagoda12m.
9 Thuy Phuong commune 9,418 The line goes mainly in the village road
II Gia Lam district
1 Kim Son commune 13,603 The line goes in the village road
2 Duong Xa commune 9,970 The line goes in the village road border on
residential areas.
Subproject: Distribution Efficiency Project
Environmental Management Plan
3 Da Ton commune 9,131
The line goes in the village road border
residential area. Some sections go through
historical monument area such as the line goes
through Dao Xuyen pagoda distance pagoda
27m.
4
Communes:
Dang Xa
Phu Dong
Yen Thuong
Yen Vien
Phu Thi
Co Bi
Trau Quy town
59,082
The line goes in the village road border on
residential area. The line does not go through the
cultural and historical monument area
II Hoang Mai district
1
Wards:
- Dai Kim
- Hoang Liet
- Hoang Van Thu
- Thinh Liet
- Thanh Tri
- Linh Nam
44,123
The line goes in the village road border on
residential area. There is no line that goes
through the cultural and historical monument
area
IV Long Bien district
1
Wards:
Bo De
Ngoc Thuy
Phuc Loi
Sai Dong
Duc Giang
Thuong Thanh
Viet Hung
Gia Thuy
11,387
The line goes mainly in the village road border
on residential area. There is no line that goes
through the cultural and historical monument
area.
V Dong Anh district
1 Viet Hung commune 34,875
The line goes mainly in the village road border
on residential area. The line goes through the Gia
Loc pagoda area distance pagodas 15m. The line
goes through Lo Giao pagoda distance pagoda
12m.
2 Kim No commune 19,149
The line goes mainly in the village road border
on residential area. The line goes through the
cemetery area distance 12m. The line goes
through the Bac Pagoda area distance pagoda
20m. The line goes through the Kim No market
area distance market 17m.
3 Dai Mach commune 22,915
The line goes mainly in the village boarder on
residential area. The line border on Linh Quang
Tu Pagoda distance pagoda 15m. The line goes
through Mai Chau church area distance church
12m.
4 Vong La commune 16,246
The line goes mainly in the village road belong
to residential area. The line border on Sap Mai
pagoda distance pagoda 13m. Some sections go
Subproject: Distribution Efficiency Project
Environmental Management Plan
through the waste area and rice field.
5 Co Loa commune 31,464
The line goes mainly in the village road belong
to residential area. The line border on Co Loa
citadel distance citadel 10 m.
VI Soc Son district
1 Hong Ky commune 54,923 The line goes mainly in the village road belong
to residential area.
2 Trung Gia commune 35,840
The line goes mainly in the village road belong
to residential area. The line goes through Trung
Gia Soc Son revolution monument area
distance it 7m.
3
Communes:
Tan Minh
Kim Lu
Xuan Thu
Tan Dan
Minh Tri
Mai Dinh
Hien Ninh
Phu Lo
Phu Ninh
Quang Tien
Duc Hoa
Xuan Giang
Viet Long
338,693
The line goes in the village road border on
residential area. There is no line goes through the
cultural and historical monument area.
VII Ha Dong district
1 Phu Luong ward
Wards:
Phu Luong
Phu Lam
Phu La
3,223
The line goes in the village road border on
residential area. There is no line goes through the
cultural and historical monument area.
2 Yen Nghia ward
Do Lo 1 substation 988
The line goes mainly in the village road border
on residential area. There is no line goes through
the cultural and historical monument area.
Do Lo 2 substation 1,490
The line goes along Highway 6. There is no line
goes through the cultural and historical
monument area.
Hoa Binh 1 substation 1,070
The line goes mainly in the village border on
residential area. No the line go through the
historical and cultural.
Hoa Binh 2 substation 1,164
The line goes mainly in the village road border
on residential area. Some sections close to pond.
There is section that goes through the village
pagoda distance pagoda 10m.
Substations:
Nghia Lo 1 substation
Nghia Lo 2 substation
Yen Lo 1 substation
3,240 The line goes mainly in the village road. Some
sections border on the pond.
Yen Lo 2 substation 1,162 The line goes mainly in the village road border
Subproject: Distribution Efficiency Project
Environmental Management Plan
on residential area. There is no line goes through
the cultural and historical monument area.
5 Bien Giang ward
Substations:
Bien Giang 1 substation
Bien Giang 2 substation
Bien Giang 3 substation
2,484
The line goes along the highway 6. There is no
line goes through the cultural and historical
monument area.
VIII Son Tay town
1 Son Dong commune
Thong Nhat substation 3,868
The main line goes in the village road. Some
sections border on the rice fields. The line goes
through Khai Nguyen pagoda area distance
pagoda 15m.
Son Dong center substation 3,443
The line goes mainly in the village road. Some
sections border on the rice fields. The line goes
through Ngach pagoda area distance pagodas
17m.
Van An substation 1,109
The main line goes in the village road, lane,
hamlet border residential area. There is no line
goes through the cultural and historical
monument area.
2 Kim Son commune
Kim Chung substation
3,901
The line goes mainly in the village road border
on residential area. There is no line goes through
the cultural and historical monument area.
Kim Tan substation 3,564
The line goes mainly in the village border on the
residential area. Some sections go through crop
area. There is no line goes through the cultural
and historical monument area.
Ngai Son substation 3,165
The line goes mainly in the village road border
on the residential area. Some sections go through
crop area. There is no line goes through the
cultural and historical monument area.
3 Co Dong commune
La Thanh substation 4,090
The line goes mainly in the village road border
on the residential area. Some sections go through
crop area. There is no line goes through the
cultural and historical monument area.
Bac Kien substation 2,245
The line goes mainly in the village road border
on the residential area. Some sections go through
crop area, canal. There is no line goes through
the cultural and historical monument area.
4 Xuan Son commune
Substations:
Xuan Son 1 substation
Xuan Son 2 substation
Xuan Son 3 substation
Nhan Ly 1 substation
9,901
The line goes mainly in the village road border
on the residential area. Some sections go through
the people’s land.
5 Thanh My commune
Subproject: Distribution Efficiency Project
Environmental Management Plan
Substations:
Doi Mang substation
Go Lang center substation
10,172
The line goes mainly in the village road. There is
no line goes through the cultural and historical
monument area.
6 Duong Lam commune
Ha Tan substation 3,721
Some sections go in the village road border on
the residential area. Some sections go in land
area border on Highway 32. Some sections go
through the rice field area.
Duong Lam 1 substation 3,383
The line goes mainly in the village road border
on the residential area. Some sections go through
the people’s cultivate land.
Mong Phu substation 3,923 The line goes mainly in the village road border
on the residential area.
7 Xuan Khanh ward
Substations:
Electric instrument
substation
Xuan Khanh 1 substation
Xuan Khanh 3 substation
Xuan Khanh 4 substation
Xuan Khanh 5 substation
Xuan Khanh 7 substation
Xuan Khanh 8 substation
3,152
The line goes mainly in the village road border
on the residential area. There is no line goes
through the cultural and historical monument
area.
8 Phu Thinh ward
Phu Thinh substation 940 The line goes along Phu Thinh street.
9 Trung Son Tram ward
Go Ma substation 1,079
The line goes mainly in the village road border
on the residential area. Some sections go through
the cultivate land of the people.
Trung Hau substation 561
The line goes mainly in the village road border
on the residential area. Some sections border on
the Trung Son Tram market area distance market
18m. Some sections border on the highway 21.
10 Ngo Quyen ward
Substations:
Chua Moi substation
Hang Dan substation
Ngo Quyen 1 substation
Ngo Quyen 2 substation
Pho Duc Chinh substation
Tran Hung Dao 2substation
3,977 The line goes mainly in village road.
Tran Hung Dao 1 substation 1,013
The line goes mainly in village road. The line
goes through Tam market area distance market
15m. The line goes along Phan Chu Trinh street
The line border on citadel distance citadel 20m.
11 Le Loi ward
Substations: 3,574
Subproject: Distribution Efficiency Project
Environmental Management Plan
Hau Ninh substation
Le Loi 1 substation
Le Loi 3 substation
Le Loi 4 substation
Le Loi 5 substation
Doc Ngu substation
Trang Trinh substation
Hong Ha substation
Phu Xa substation
Trung Vuong 2 substation
The line goes mainly in village road.
12 Son Loc ward
Substations:
Ai Mo 1 substation
Ai Mo 4 substation
Chua Thong substation
1,936
The line goes mainly in the village road.
13 Quang Trung ward
Substations:
Quang Trung 2 substation
Phung Khac Khoan 2
substation
Cau Chi substation
Bui Thi Xuan substation
Pham Hong Thai 1
substation
Pham Hong Thai 2
substation
2,215
The main line goes in the village road.
3.4.4 Substation
New Construct 52 substations with total capacity of 18,960 kVA. Number of improvement
substations (no move substation) is 25 substations. Number of improvement substations
(move substation) is 9 substations. The detail of improvement and new construction
substations as follow:
Table 3.4.4: Description of substation
N0
Substation Subproject
commune/ward Description of substation
I New contruction substation
1 Me Tri 8 substation
(630kVA – 22/0,4kV)
Me Tri commune,
Tu Liem district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 10B. The distance
between two poles is 2.6 m.
Location: The substation is located at
lane 12, Do Duc Duc street.
2 Trau Quy 11 substation
(400kVA – 35( 22)/0,4kV)
Trau Quy
commune, Gia Lam
district
Location: The substation is located
close to the canal edge of An Dao street.
Substation type: Suspended substation.
Subproject: Distribution Efficiency Project
Environmental Management Plan
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 10B. The distance
between two poles is 2.8 m.
3 Xom Vang 2 substation
(400kVA -22/0,4kV )
Co Loa commune,
Dong Anh district
Location: The substation is located on
the prospective Land area which is far
from 22kV line 500m in Co Loa
commune, Dong Anh district, Ha Noi.
Substation type: Suspended substation
4 Gia Luong 3 substation
(400kVA -22/0,kV)
Viet Hung
commune, Dong
Anh district
Location: On vacant land in residential
area of Gia Luong hamlet, Viet Hung
commune, Dong Anh district, Ha Noi
city.
Substation type: Suspended substation
5 Lo Giao 2 substation
(400kVA -22/0,kV)
Viet Hung
commune, Dong
Anh district
Location: On vacant land border on the
road edge in Lo Giao village, Viet Hung
commune, Dong Anh district, Ha Noi city.
Substation type: Suspended substation
6 Doai 3 substation (400kVA
-22/0,kV)
Xã Việt Hùng,
huyện Đông Anh
Location: On vacant land near nursery
school in Viet Hung commune, Dong
Anh district, Ha Noi city.
Substation type: Suspended substation
7 Tho Da 3 substation
(400kVA -22/0,4kV )
Kim No commune,
Dong Anh district
Location: Located under the 22 kV line
471E21 feeder belong to Kim No
commune, Dong Anh District, Ha Noi
city.
Substation type: Suspended substation
8 Lang Chai 3 substation
(400kVA -22/0,kV)
Vong La commune,
Dong Anh district
Location: Located at turning point near
Thang Long bridge. All substation
equipments are installed on the rack
placed on centrifugal concrete pole 10B.
The distance between two pole is 2.6m
9 Thinh Liet 10 substation
(630kVA – 22/0,4kV)
Thinh Liet ward,
Hoang Mai district
Location: The substation located at the
alley 88/61, Giap Nhi road near heroes
cemetery.
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 10B. The distance
between two pole is 2.6m
10
Thinh Liet 11
substation(630kVA –
22/0,4kV
Thinh Liet ward,
Hoang Mai district
Location: The substation located on the
lane 141, Giap Nhi road near nursery
school.
Substation type: suspended station
column. Transformer is located on the
transformer pillar that is far from the
ground 2.5m
11 Thinh Liet 12 substation
(630kVA – 22/0,4kV)
Thinh Liet ward,
Hoang Mai district
Location: On the public land in the lane
1295, Giai Phong road.
Substation type: Suspended substation.
All substation equipments are installed
Subproject: Distribution Efficiency Project
Environmental Management Plan
on the rack placed on centrifugal
concrete pole 10B. The distance
between two pole is 2.6m
12 Thinh Liet 13 substation
(630kVA – 22/0,4kV)
Thinh Liet ward,
Hoang Mai district
Location: On the public land in lane
143/34/18, Nguyen Chinh road near Set
river.
Substation type: suspended station 1
pole . The transformer is located on the
transformer pillars that is far from the
ground 2.5m
13 Ngoc Lam substation
(630kVA – 10(22)/0,4kV)
Bo De ward, Long
Bien district
Location: The substation is placed on
the pavement of the lane 310/15 Bo De,
Bo De ward, Long Bien district
14
Ngoc Lam school substation
(400KVA-22/0,4)
Ngoc Lam ward,
Long Bien district
Location: on the sidewalk of the lane
310/15 Bo De, Bo De ward, Long Bien
district.
15 Ngoc Thuy substation
(630KVA-35/0,4)
Ngoc Thuy ward,
Long Bien district
Location: on the sidewalk lane 532
Ngoc Thuy, Ngoc Thuy ward, Long
Bien district.
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B. The center distance
of two pole is 2.8m
16 53 Duc Giang substation
(400KVA-35/0,4)
Duc Giang ward,
Long Bien district
Location: On the vacant land in the 359
Ngoc Thuy lane
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
17
26 Duc Giang substation
(400KVA-35/0,4)
Duc Giang ward,
Long Bien district
Location: on the sidewalk of Duc
Giang street, opposite the lane 97/17 be
long to 26 group of Duc Giang ward.
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B. The center distance
of two pole is 2.8m
18 Sai Dong 11 substation
(400KVA-22/0,4)
Sai Dong ward,
Long Bien district
Location: on the sidewalk of the lane
64, Sai Dong street, Sai Dong ward.
Substation type: substation 1 pole
19 Phuc Loi 14 substation
(400KVA-35/0,4)
Phuc Loi ward,
Long Bien district
Location: The substation was builded
on field land belong to group 2, Phuc
Loi ward.
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B. The center distance
of two pole is 2.8m
20 Thuong Thanh substation 16
(400KVA-35/0,4)
Thuong Thanh
ward, Long Bien
Location: On vacant land, opposite the
lane 29/25 Thuong Thanh.
Subproject: Distribution Efficiency Project
Environmental Management Plan
district Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B. The center distance
of two pole is 2.8m
21 26 Thuong Thanh substation
(400KVA-35/0,4)
Thuong Thanh
ward, Long Bien
district
Location: On the vacant land, at the end
of Thanh Am street. The substation is
far from Duong dike 30 m.
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B. The center distance
of two pole is 2.6m
22 1 Gia Thuy substation
(400kVA-35/0,4 kV)
Gia Thuy ward,
Long Bien district
Location: Sub station located at
stadium, lane 640/21, Nguyen Van Cu
street.
Substation type: Suspended substation.
All substation equipments are installed
on new 12B centrifugal concrete pole
and utilization 14 centrifugal concrete
pole. The center distance of two pole is
2.8m
23 Ca Phe substation (3250
kVA–10(22)/0,4kV)
Hong Ky commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
24 Do substation
(250 kVA–10(22)/0,4kV)
Trung Gia
commune, Soc Son
district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
25 Xuan Son 3 substation (250
kVA–10(22)/0,4kV)
Trung Gia
commune, Soc Son
district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
26 Xuan Dong substation
(250 kVA–6(22)/0,4kV)
Tan Minh
commune, Soc Son
district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
27 Son Doai substation
(250 kVA–6(22)/0,4kV)
Tan Minh
commune, Soc Son
district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
28 Xuan Duong 2 substation
(250 kVA–6(22)/0,4kV)
Kim Lu commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
29 Kim Trung 2 substation
(250 kVA–6(22)/0,4kV)
Kim Lu commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
30 Xuan Lai 4 substation Xuan Thu Substation type: Suspended substation.
Subproject: Distribution Efficiency Project
Environmental Management Plan
(250 kVA–6(22)/0,4kV) commune, Soc Son
district
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
31 Xuan Ap substation
(250 kVA–6(22)/0,4kV)
Tan Dan commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
32 My Linh 3 substation
(250 kVA–22/0,4kV)
Tan Dan commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
33 Go Gao substation
(250 kVA–22/0,4kV)
Minh Tri commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
34 Lap Tri 4 substation
(250 kVA–22/0,4kV)
Minh Tri commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
35 Hoang Duong substation
(250 kVA–22/0,4kV)
Mai Dinh
commune, Soc Son
district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
36 Noi Phat substation
(250 kVA–6(22)/0,4kV)
Mai Dinh
commune, Soc Son
district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
37 Phu Lo substation
(250 kVA–6(22)/0,4kV)
Phu Lo commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
38 Ve Linh 3 substation
(250 kVA–22/0,4kV)
Phu Linh commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
39 Cong Hoa 2 substation
(250 kVA–10(22)/0,4kV)
Phu Linh commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
40 Thanh Hue 2 substation
(250 kVA–6(22)/0,4kV)
Duc Hoa commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
41 Duc Hau 3 substation
(250 kVA–6(22)/0,4kV)
Duc Hoa commune,
Soc Son district
Substation was built for the suspended
station on 02 concrete centrifugal
columns high 12 m.
42 Duc Hoa 4 substation
(250 kVA–6(22)/0,4kV)
Duc Hoa commune,
Soc Son district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12B
Subproject: Distribution Efficiency Project
Environmental Management Plan
43 Lai Cach 3 substation
(250 kVA–22/0,4kV)
Xuan Giang
commune, Soc Son
district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12m
44 Tang Long 2 substation
(250 kVA–10(22)/0,4kV)
Viet Long
commune, Soc Son
district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12m
45 Luong Phuc 2 substation
(250 kVA–22/0,4kV)
Viet Long
commune, Soc Son
district
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12m
46 Dong Mai 2 substation
(400kVA-22/0,4 kV)
Dong Mai ward, Ha
Dong district
Location: On the vacant land in Mai
Linh market, border on highway 6,
Dong Mai ward, ha Dong district.
Substation type: Suspended substation
47 Dong Mai 3 substation
(400kVA-22/0,4 kV)
Dong Mai ward, Ha
Dong district
Location: On the vacant land border on
dike and Nhan Dao pagodas be long to
Dong mai ward, Ha Dong district.
Substation type: Suspended substation
48 Dong Mai 4 substation
(400kVA-22/0,4 kV)
Dong Mai ward, Ha
Dong district
Location: opposite Cultural house of Y
Son Hamlet, Dong Mai ward, Ha Dong
district.
Substation type: Suspended substation
49 Phu Lam 3 substation
(400kVA-22/0,4 kV)
Phu Lam ward, Ha
Dong district
Location: border on highway 21B be
long to Thanh Lam hamlet, Phu Lam
ward, Ha Dong district.
Substation type: Suspended substation
50 Phu Lam 4 substation
(400kVA-22/0,4 kV)
Phu Lam ward, Ha
Dong district
Location: Border on the village road
near C area, group 3, Thanh Lam
hamlet, Phu Lam ward, Ha Dong
disttrict.
Substation type: Suspended substation
51 Phu Luong 7 substation
(400kVA-22/0,4 kV)
Phu Luong ward,
Ha Dong district
Location: On the vacant land, before
Trinh Luong Pagoda belong to Thuong
Mao hamlet, Phu Luong ward, Ha Dong
district.
Substation type: Suspended substation
52 Ba La 7 substation
(400kVA-22/0,4 kV)
Phu La ward, Ha
Dong district
Location: Located next to the concrete
road in front of 220 kV Ha Dong
substation.
Substation type: Suspended substation
II Movement substation
1 Yen Thuong substation
Yen Thuong
commune, Gia Lam
district
Movement substation is built at the
position of connected point pole belong
to the Branch to old Yen Thuong
substation.
Substation type: Suspended substation.
All substation equipments are installed
on the rack placed on centrifugal
concrete pole 12m.
Subproject: Distribution Efficiency Project
Environmental Management Plan
2 Dam Quang substation
(320kVA – 10(22)/0,4kV)
Trung Son Tram
ward, Son Tay town
Location: On the land area of Dam
Quang hamlet, Trung Son Tram ward.
Substation type: Suspended substation
3 Go Dinh substation
(180kVA – 10(22)/0,4kV)
Co Dong commune,
Son Tay town
Location: On the land area of Go Dinh
hamlet, Co Dong commune.
Substation type: Suspended substation
4 Song Hang substation (
320kVA – 10(22)/0,4kV)
Xuan Khanh
commune, Son Tay
town
Location: On the land area of Xuan
Khanh commune.
Substation type: Suspended substation.
5 Vi Thuy substation
(180kVA – 10(22)/0,4kV)
Thanh My commune,
Son Tay town
Location: On the land area near canal
of Thanh My commune.
Substation type: Suspended substation
6 Doi Mang substation
(320kVA – 10(22)/0,4kV)
Son Dong commune,
Son Tay town
Location: On the land area of Doi
Mang hamlet, Son Dong commune.
Substation type: Suspended substation
7 Son Dong town substation
( 320kVA – 10(22)/0,4kV)
Son Dong commune,
Son Tay town
Location: on the land area of Dong Son
commune.
Substation type: Suspended substation
8 Duong Lam 2 substation
( 320kVA – 10(22)/0,4kV)
Duong Lam
commune, Son Tay
town
Location: on the field land area belong
to Duong Lam village, Duong Lam
commune.
Substation type: Suspended substation
9 Ha Tan substation (320kVA
– 10(22)/0,4kV)
Duong Lam
commune, Son Tay
town
Location: on the Land area belong to
Phu Thinh village, Duong Lam
commune.
Substation type: Suspended substation
III Renovation substation
The improvement substation remain the old location, only increase capacity or replace
equipment and other acessories in the substation
3.5 Subproject Main Work Volume
Table 3.5. Work volume to be implemented in Ha Noi City
No. Construction and installation Unit Quantit
y
Executing
methods
I Line and underground cable
1 Pole foundation digging cubic
meter 20,973 Manual
2 Pole foundation filling cubic
meter 14,691 Manual
3 Concrete cubic
meter 6,998 Manual
6 Foundation steel, earthing, bolts ton 6,932 Manual
7 Erect Concrete pole pole 8,860 Manual
8 Stretching the 22kV conductors km 53.458 Manual
9 Stretching the 35kV conductors km 0.838 Manual
10 Stretching the 22kV underground
cable
km 24,697
Manual
Subproject: Distribution Efficiency Project
Environmental Management Plan
No. Construction and installation Unit Quantit
y
Executing
methods
11 Stretching the 35kV underground
cable
km 0.73
Manual
12 Stretching the low voltage
underground cable
km 0.368
Manual
13 Stretching the aerial bundled
cable
km 835.746
Manual
II Substations
1 Pole foundation digging cubic
meter 1,885
Manual
2 Pole foundation filling cubic
meter 1,565
Manual
3 Concrete cubic
meter 320
Manual
4 Foundation steel Ton 1,503 Manual
5 Erect Concrete pole pole 112 Manual
6 Stretching the conductors km 5.208 Manual
7 Erect transformer unit 76 Manual
8 Erect low voltage cubic unit 67 Manual
9 Erect disconnection switch unit 5 Manual
3.6. Main Activities Before and During Construction
3.6.1. Main Activities Before and During Construction
a. Activities Before Construction
- To implement the clearance compensation;
- To receive the site, build temporary camps;
- To mobilize manpower, machinery, material and equiptment to the constrution site;
- To dig the pole foundation, erect poles, stretch line.
b. Activities During Construction
- Digging foundatio, erect pole, streching conductors
- Transport material to site
- Erect line accessories
- Types of main equipment and material used comprise: cement, sand, rock, iron, pole, bar,
insulator, concrete mixer.capstan.
3.6.2 Transprortation
a. Material and equiptment supplying source:
- The electrical material are bought in Hanoi and transported to the construction site.
- Steel structures: is bought in domestic.
- Construction material: is bought in the local area.
Subproject: Distribution Efficiency Project
Environmental Management Plan
b. Method of transprorting equipment, material, machine to work site
- Equipment and material are transported from the receving place in Ha Noi to the store in the
subproject Districts by specific vehicles by land. The specific vehicles are selected in
accordance with goods packing methods that specified in the contracts.
- Cross-arm, bracket structure, accessories are transported by five-ton strucks and loaded
manually.
- Goods that must be stored at site such as: conductors, insulators, accessories, ... are
transported intermediately from the store to the manual transporting position by mechanical
and manual combination.
- The whole material are transported manually to the site. The average transportation distance
is 100m.
3.7. Subproject Implementation Schedule and Total Investment
3.7.1. Subproject Implementation Schedule
The estimated schedule as follow:
- Establishing investment project: from November 2011 to December 2011.
- Establishing executing drawing design: from april 2012 to october 2012.
- Establishing equipment and construction bidding document: from january to March
2013.
- Deploying time of the subproject: from june 2013 to December 2013.
- End of project: December 2013
3.7.2. Total investment of the project:
i) Component 1: Improve rural network of old Ha Noi area – phase 1
No. Capital structure Amount (VND)
1 Construction cost 310,508,026,794
2 Compensation cost 33,627,830,881
3 Project management cost 1,045,894,857
4 Construction investment consultancy
cost 4,972,684,401
5 Other cost 29,412,381,782
6 Provision cost 26,046,049,343
Total: 63,948,481,183
ii) Component 2: Improve Ha Dong District and Son Tay town networks
Subproject: Distribution Efficiency Project
Environmental Management Plan
No. Capital structure Amount (VND)
1 Construction cost 147,185,496,608
2 Compensation cost 8,529,418,823
3 Project management cost 2,520,108,813
4 Construction investment consultancy
cost 2,227,237,200
5 Other cost 11,289,106,169
6 Provision cost 14,616,074,890
Total: 30,479,487,501
IV. ENVIRONMETNAL BACKGROUND
4.1. Summary of natural condition and society of Long Bien district.
4.1.1 Geography
Long Bien district is located along the north shore of the Red River, the east border on
the Duong River, the west border on the Red River, the south border on the Gia Lam district,
the north border on the Duong River.
The district has 14 wards with 301 population groups.
Total area of district: 60.38 km2.
4.1.2 Topography
Long Bien District with flat plain terrain.
4.1.3 Climate, hydrology:
Long Bien of the tropical monsoon climate has two distinct seasons (dry season, cold
from November to March next year, hot and rainy season from May to September, Together
with two transitional period in April and October, Long Bien has all four seasons: spring,
summer, autumn and winter. Average temperature 210C; lowest temperature: 5°C; average
humidity: 80%. Average annual rainfall: 2000mm.
Overall the weather was relatively mild, no storm and fewer flood, is rare these
abnormal changes in the weather.
Hydrology: All the east, the north border the Duong river, the west border Red River.
The province also has river systems, canals internal carry water for production agriculture.
4.1.4 Population:
The total Long Bien district population is 237,000 people (The statistical yearbook
2010).
4.1.5 Transportation infrastructure:
Road traffic: Long Bien District with major transport project go through the highway5
Waterway: Long Bien has Red River is limited to the Hoan Kiem district, Thanh Tri,
Tay Ho, Hai Ba Trung; Duong River is limited to Gia Lam and Dong Anh district.
Air traffic: Gia Lam Airport.
Subproject: Distribution Efficiency Project
Environmental Management Plan
4.2. Summary of natural condition and society of Hoang Mai
district.
4.2.1 Geography:
Hoang Mai district is located in the southeast of Hanoi city, the east border Gia Lam
district, the west and south border Thanh Tri district, the north border and Thanh Xuan
district and Hai Ba Trung district with 14 administrative units directly under ward 14 is
formed on the basis of full 9 communes and part in Tu Hiep Commune of Thanh Tri district,
and 5 ward of Hai Ba Trung district.
Hoang Mai District has a total natural land area is 4104.1 ha.
4.2.2 Topography
Hoang Mai district is located in the south of Hanoi with relatively low-lying terrain, the
average height of 4.5 m. Downhill terrain changes from north to south and from east to west.
The District's wards are mainly located in the Red River dike, in addition to a beach area
outside the dike with an area approximate 920 ha of the wards: Thanh Tri, Tran Phu, Yen So,
Linh Nam.
4.2.3 Climate, hydrology:
Hoang Mai under the tropical monsoon climate has two distinct seasons (dry season,
cold from November to April next year, hot and rainy season from may to october). The
average temperature is 21°C; lowest temperature: 5°C; average humidity: 80%; Average
annual rainfall: 2000mm.
Overall the weather was relatively mild, no storms and fewer flood.
4.2.4 Population:
The total Hoang Mai district population is 346,900 people (The Statistical yearbook
2010).
Ethnic minority:
The district has no ethnic minority.
4.2.5 Transportation infrastructure:
Railway transport: Transport of Hoang Mai includes north-south railway , development
will connect with the railway on the Yen Vien-Ngoc Hoi and the belt railway, has Giap Bat
station, Yen So station.
Road Traffic: District has National Highway 1A, the belt 3.
Waterway: The Hoang Mai district has waterway traffic on the Red River.
4.3. Summary of natural condition and society of Tu Liem district.
4.3.1Geography: Tu Liem is a district of Hanoi. Tu Liem district border two districts: Dan Phuong and
Hoai Duc district to the west, border Cau Giay district, border Tay Ho and Thanh Xuan to the
east, Ha Dong district to the south, and Dong Anh District to the north.
Tu Liem district has 16 administrative units at commune / ward, has a town (Cau Dien)
and 15 communes.
The total natural area of the district is 75.32 km2.
4.3.2 Topography
The terrain in Tu Liem district is relatively low, the average height approximate 4.5 m.
The terrain changes to steep incline from West to North and from East to West. The
communes of the district are mostly in the Red River dike, in addition to a pool with beach
Subproject: Distribution Efficiency Project
Environmental Management Plan
outside the dike area of about 320 ha in the commune as Thuong Cat and Lien Mac.
4.3.3 Climate:
Tu Liem district of the tropical monsoon climate has two distinct seasons (dry season,
cold from November to April next year, hot and rainy season from may to October
accompanied by heavy rain).
The highest temperature: 400C.
The lowest temperature: 50C.
Average temperatures: 210C.
The average annual humidity:81%.
Average annual rainfall: 1470mm.
Overall the weather was relatively mild, no storm and fewer flood, is rare these
abnormal changes in the weather.
4.3.4 Population:
The total Tu Liem district population is 429,400 people (according to Statistical
yearbook 2010).
Ethnic minority:
The district does not have ethnic minority.
4.3.5 Transportation infrastructure:
Tu Liem district has Lang - Hoa Lac highway.
The system of internal road are open investment as extended Le Van Luong, 32 road-
widening the Cau Dien-Nhon.
4.4. Summary of natural condition and society of Soc Son district.
4.4.1 Geography:
Soc Son district is located in the north of Ha Noi. Soc Son border Pho Yen district of
Thai Nguyen province to the north, Yen Phong district of Bac Ninh province and Hoa Hiep
of Bac Giang province to the northeast, northwest border Phuc Yen town of Vinh Phuc and
south border Me Linh district and Dong Anh district of Hanoi .
The total area of the district is 306.5 km2. The district consists of 1 town and 25
communes.
4.4.2 Topography
Soc Son District uneven terrain, with many mountains and hills, low terrain from
northwest to southeast.
4.4.3 Climate:
Soc Son district of the tropical monsoon climate has two distinct seasons (dry season,
cold from November to April next year, hot and rainy season from may to October
accompanied by heavy rain).
Average annual temperature: 260C
Average annual rainfall: 1400-1800 mm.
Annual average humidity: 85%
The rainy season starts from may to October, mainly in June to august accounts for 60%
of annual rainfall, water drainage occurs faster at the long-term flooding.
4.4.4 Population:
District population is 293,200 people (according to Statistical yearbook 2010).
Ethnic minority:
Subproject: Distribution Efficiency Project
Environmental Management Plan
The district does not have ethnic minority.
4.4.5 Transportation infrastructure:
Road Traffic: Soc Son district has highway 2, 3, Provincial Road 402, 131 ; Ha Noi -
Thai Nguyen Railway.
Air traffic: Soc Son district has Noi Bai International Airport.
4.5. Summary of natural condition and society of Gia Lam district.
4.5.1 Geography:
Gia Lam is a suburban district east of Ha Noi, the northern border Dong Anh and Long
Bien district Hanoi city, the east border Bac Ninh province, the south border Hung Yen
province, the west border Red River.
Total area of Gia Lam district is 108.4466 km2. The district consists of 20 administrative
divisions including 20 communes and 2 towns.
4.5.2 Topography
Located in the east of Hanoi city with relatively low-lying terrain.
4.5.3 Climate:
Gia Lam has a tropical monsoon climate, less cold winter, low rainfall, hot summer and
rainy. The climate of the year is divided into two distinct seasons:
Hot and rainy season from April to November every year.
Cold and rain from December to march next year.
Average annual rainfall 1.600-2000 mm is concentrated in the month 8-10.
Annual average humidity: 84%
Average annual temperature: 270C
The rainy season starts from May to October, mainly in June to August accounts for 60%
of annual rainfall, water drainage occurs faster at the long-term flooding.
4.5.4 Population:
The total Gia Lam district population is 239,300 people (The Statistical yearbook 2010).
Ethnic minority:
The district does not have ethnic minority.
4.5.5 Transportation infrastructure:
Railway traffic: The district has a number of national railway as the railway goes
through Hanoi's belt running from the Thanh Tri bridge to Co Bi, crossed the Duong river,
north of Yen Vien to go Yen Vien. Lang Son railway from the station of Yen Vien, Gia Lam
station, the railway from Hai Phong at the north highway 5 connection with the railway belt.
Waterway: The district has waterway transport systems, including Hong River, Duong
river, Cau Bay river, Bac Hung Hai river. Thien Duc River flows through.
Road Traffic: Gia Lam is important roads go through include: highway 5, highway 1A.
4.6. Summary of natural condition and society of Dong Anh district.
4.6.1 Geography Dong Anh is a suburban district of the north Hanoi city, the east, the northeast border
Bac Ninh province, the south border Red River, the southeast border Gia Lam district, the
west border Me Linh district, the north border Soc Son district.
Dong Anh district include 23 communes and 1 town.
Area: 18,230 ha (182.3 km2).
4.6.2 Topography
Subproject: Distribution Efficiency Project
Environmental Management Plan
Topography of Dong Anh is relatively flat, sloping direction from the Northwest to
Southeast.
4.6.3 Climate: Dong Anh has the same climate regime of Hanoi, which is tropical, humid monsoon.
From may to October is summer, humid climate, abundant rainfall. From November to April
next year is winter, early dry - cold, but last season the rain, wet. Between the two seasons
that make the transition Dong Anh as well as Ha Noi rich seasons: spring, summer, autumn
and winter.
Annual average temperature is 250C, the two hottest months are June and July, monthly
mean temperature most often occurs in July was 37,50 C. The two coldest months are January
and February, the average temperature in January is 130C.
The average humidity is 84%, humidity is also very little change over the months of the
year, usually ranging from 80-87%.
Overall the weather was relatively mild, no storm and fewer flood, is rare these abnormal
changes in the weather.
4.6.4 Population: The total in Dong Anh district population is 350,500 people (The Statistical yearbook
2010).
Ethnic minority:
The district does not have ethnic minority.
4.6.5 Transportation infrastructure: Railway traffic: The district has two railway running through: Hanoi - Thai Nguyen and
Ha Noi - Yen Bai
Air traffic: Noi Bai International airport is connected to Ha Noi by highway 3 and Thang
Long - Noi Bai highway, Dong Anh district particularly through 7.5 km long.
Waterway: The district has Red River system, Duong River and Ca Lo River .
Road Traffic: Dong Anh district has roads relatively convenient, Thang Long highway,
highway 3.
4.7. Summary of natural condition and society of Ha Dong district.
4.7.1 Geography
Ha Dong is a district of the Ha Noi capital, from central Ha Noi 10 km . Ha Dong
district is located along Highway 6 from Hanoi to Hoa Binh and the confluence Nhue river,
La Khe river, northern border Tu Liem district, Hoai Duc district, east border Thanh Tri
district, northeast border Thanh Xuan district, west border Quoc Oai, Hoai Duc district,
southwest border Chuong My district, southwest border Thanh Oai district.
The total area of Ha Dong district is 47,91 km2. District includes 17 wards.
4.7.2 Topography
Ha Dong district is plain flat terrain.
Climate:
Ha Dong district of the tropical monsoon climate has two distinct seasons (dry season,
cold from November to April next year, hot and rainy season from may to October). The
average temperature 25°C; lowest temperature: 5,7°C; average humidity: 81,7%, average
annual rainfall: 1480mm.
Overall the weather was relatively mild, no storm and fewer flood, is rare these
abnormal changes in the weather.
4.7.3 Population:
The total in Ha Dong district population is 241,900 people (The Statistical yearbook
Subproject: Distribution Efficiency Project
Environmental Management Plan
2010).
Ethnic minority:
Ward does not have ethnic minority.
4.7.4 Transport infrastructure:
Ha Dong district has road go through the highway 6 from Hanoi to Hoa Binh.
4.8. Summary of natural condition and society of Son Tay town.
4.8.1 Geography
Son Tay town is the gateway to the west of Hanoi with geographical coordinates 210 to
the north and 1050 to the east, the center of Hanoi 42 km west north, east border Phuc Tho
district, west border Ba Vi district; south border Thach That district of Ha Noi, north border
Vinh Tuong district of Vinh Phuc.
Son Tay town has a total natural area is 113.46 km2, divided into 15 administrative units
including 9 wards and 6 communes.
4.8.2 Topography
Son Tay town with hilly terrain.
4.8.3 Climate:
Son Tay town of the tropical monsoon climate: In summer hot, humid, rainy; winter cold
and little rain falls. The dry season, cold from November to April next year the average
temperature of 18,6°C, hot and rainy season from May to October rains accompanied by
temperatures averaging 280C). Average annual rainfall: 1495mm.
Overall the weather was relatively mild, no storm and fewer flood, is rare these
abnormal changes in the weather.
4.8.4 Population:
Total population of the Son Tay town is 129,000 people (according to Statistical
yearbook 2010).
Ethnic minority:
4.8.5 Transportation infrastructure:
Road Traffic: Son Tay town with the major transport projects run by the highway 21A,
highway 32, highway 2C to Vinh Phuc.
Waterway has Red River.
V. SUBPROJECT POTENTIAL IMPACTS
5.1. Environmental screening:
Table 5.1. Environmental impact assessments
Screening Question Yes No Remarks
1. Is project located near or in
sensitive area with regards to?
Cultural heritage X Most of The line which goes through
the Cultural and historical monument is
the low voltage line. The line is far
from the Cultural and historical
monument from 7 to 27 metre.
Subproject: Distribution Efficiency Project
Environmental Management Plan
Screening Question Yes No Remarks
According to electrical equipment
standard 2006 of ministry of industry,
safety distance of low voltage line is
1.5m. Thus, the impact of the
subproject on this area is small. But it
is necessary to implement measures to
minimize impact. The measures
described in section VI
Reservation zone X
Wetlands X
Forests X
Estuary X
Reservation buffer zone X
Rivers and reservoirs
X There are some rivers and lakes in the
subproject area as Set river be long to
Hoang Mai district, Yen So lake belong
to Yen So ward, Hoang Mai district,
some of lakes belong to Yen Nghia
ward, Ha Dong district and Kim Son
commune Song Tay town. The Line
goes along the river an lake. The pole
is constructed not close to the river and
lake. The impact of the subproject on
this area is small
Canaland irrigation
network
X Some of lines goes through rice field,
canal land in Co Loa commune, Dong
Anh district, Trau Quy town – Gia Lam
District, Hong Ky commune – Soc Son
district, Son Dong commune – Son Tay
town. The pole is constructed not close
to the canal. The impact of the
subproject on this area is small. The
measures described in section VI will
be implemented to minimise the impacts
2. Potential environmental impact,
by project?
Intrusion to cultural and historical sites X New construction low voltage line is far
from the Cultural and historical
monument from 7 to 27 meter.
According to electrical equipment
standard 2006 of ministry of industry,
Subproject: Distribution Efficiency Project
Environmental Management Plan
Screening Question Yes No Remarks
safety distance of low voltage line is
1.5m. Thus, The construction of line not
affect the Cultural and historical
monument
Intrusion to ecosystem (ex: nature
reserve, national park)
X
Affecting landscape and resulting in
waste
X Because of ROW clearance, there
would be small changes of the
landscape and increase in wastes but
these changes are considered as small
and the appropriate mitigation
measures would be taken.
Undermining vegetation cover or
cutting down trees for site during site
clearance for substations and along the
transmission line?
X Only cutting down high tree, vegetation
cover and low tree remain (vegetation
cover is only impacted at foundation
during executing time but area of
foundation is small.
Change surface water quality or river
course
X
Increase water turbidity
due to change in surface water
quality or erosion
X -The excavated soil (6.603 m3) is
collected and transported by car to
waste plain of the city.
-The subproject would be
implemented in relatively flat areas.
Therefore, the danger of erosion is
small.
- The impact on surface water is
assessed as small and could be
mitigated.
Domestic waste water
by workers is discharged
directly into outside water
bodies?
X The constructing units rent private
houses, so the wastewater is collected
into the general sewage system.
In the case constructing units uses
temporary tents, wastewater and
garbage have to collected according to
regulation.
Construction waste
water is discharged directly into
outside water bodies?
X
Result in more dust? X The excavated soil (6.603 m3) is
Subproject: Distribution Efficiency Project
Environmental Management Plan
Screening Question Yes No Remarks
collected and transported by car to
waste plain of the city. The
transportation result in dust.
The transportation of material (sand,
rock) causes dust.
- The measures described in section VI
will be implemented to minimise the
impacts of dusts.
Increase noise and/or vibration? X -The old pole and old conductors
which not used would be taken down
and transported to depot of
management Board. Transportation
will result in noise.
- The transportation of material
supplied by domestic supplier and
transport to work site result in noise
- The construction of substation
results in noise and vibration. The
substations are located far from
residential areas not affect local
communities.
- Relevant measures listed in section
VI will be implemented to minimise
these impacts.
Permanent land acquisition X All lines and substations are
constructed along existing
communication route. Thus, it doesn’t
affect private house and architecture.
The position of new foundation
construction need to acquire permanent
land but Permanent land acquisition be
long to public land managed by Ward
people’s committee
Temporary land acquisition X Temporary occupied land area is
21,889 square meter. Land for ROW is
mainly agricultural land. The project
will apply mitigation measures in order
to mitigate minimum.. These measures
are presented in part VI.
Subproject: Distribution Efficiency Project
Environmental Management Plan
Screening Question Yes No Remarks
Resetlement of households? If yes, how
many households?
X There is not household to move, so
there is not resettlement
Would the resettlement site is
environmentally and/or culturally
sensitive
X
Is there any risk of disease
dissemination from construction
workers to the local peoples (and vice
versa)?
X - Construction force divides into nine
construction team in seventy three
communes, each team will have about
40 workers. The total number of
workers on the site at the peak time is
about 360 peoples but they are in many
places of the route, not gathering in
one place. Therefore, the spread of
disease will also be limited.
Is there any potential for conflict
between construction workers and local
peoples (and vice versa)?
X Workers and local people are different
in income, lifestyle, custom thus it will
generate small conflict but it will be
limited.
Are explosive and hazardous chemicals
used within the Project?
X
In the past, there was any accident
incurred due to landmines or explosive
materials remaining from the war?
X This area is defined that has landmines
or explosive remaining from the war
but the investor will hire army agency
to disarm safely before constructing.
Will Project's construction cause
disturbance to the transportation in the
Project's site?
X The traffic density in project area is not
heavy, time of loading and unloading
material, equipment is short (about one
hour), besides constructing material
(sand, soil, macadam, …) is
transported by trucks, so the level of
disturbance to the transportation in the
Project's site is not high.
Project's construction will cause any
damage to the existing local roads,
bidges or other rural infrastructures?
X All of material and equipments are
divided into smaller part to transport in
accordance with loading capacity of
road, so the impact is negligible.
Will soil excavation during Project's X The constructing time for each pole
Subproject: Distribution Efficiency Project
Environmental Management Plan
Screening Question Yes No Remarks
construction cause soil erosion? foundation is not long (maximum about
one week) and avoiding to construct in
raining seasons and constructing
definitively each item, so the erosion is
negligible.
Will Project need to open new access
roads?
X Using the current road system to
construct because the route and
substation areas are along traffic road
Will Project cause fragmentation of
habitat of flora and fauna?
X
Will Project cause impact on air
quality?
X The impact level to the environment by
exhaust fumes of traffic means during
transportation will be limited by
covering, avoid scattering.
Will Project cause accident risks for
workers and community during
construction phase?
X Accident risks include:
- Transporting bulky materials and
equipment (pole, transformer), it is
easy to cause accident for community
- The workers construct in sloping area
are able to be in risk as falling if they
are not equipped safety knowledge and
labor protection
The mitigation measures for these risks
of workers and community when
constructing are presented in part 6
Will Project generate hazardous wastes
including PCBs from the replacement
of transformers?
X In this project, there is replacement of
old suspending transformers. These
transformers are verified not to include
PCBs, so it will not affect environment.
Will Project cause risk to safety and
human health (electric and magnetic
fields, electric shock etc.)?
X - The transmission lines shall be
designed and constructed in
accordance with applicable standards
of power industry (in accordance with
Vietnam applicable technical
regulations, electromagnetic field
(EMF) < 5 kV/m), wherein impacts
from EMF and safety standards and
operation safety have to be taken into
due account.
Subproject: Distribution Efficiency Project
Environmental Management Plan
Screening Question Yes No Remarks
- Prior to operation, all safety
indicators shall be tested and accepted
by the project owner, contractor and
operation entity therefore workers
shall not be suffering from such EMF
impacts.
- In the phase of commissioning, the
safety in power use of households of
ethinic minorities who use electricity
for the first time also needs to be paid
attention to minimize the risk of
electric shock. However, this impact is
very little and avoidable if the people
are trained well in safe power use.
- The mitigation measures in Section VI
will also be implemented to minimise
safety risks
VI. ENVIRONMENTAL MANAGEMENT PLAN:
6.1. Mitigation measures:
Table 6.1. Mitigation measures description as ECOP
Period Potential impact Mitigation measures Responsibility
Preparation
Permanent and
temporary land
acquisition will
impact affected
households and
agriculture
production
To plan for construction activities after
harvesting season and try to shorten the
progress.
Inform the affected HHs about
permanent and temporary land
acquisition.
Properly compensate for land
acquisition and tree compensation in
accordance with the Resettlement
Policy Framework of the DEP project
and Resettlement Action Plan of the
Subproject.
PMU
Contractor
Impacts on
vegetation cover as a
result of site
clearance (ROW)
Minimize land clearing by planning
for installation of
transmission/distribution lines above
existing vegetation.
Utilize hand clearing of vegetation if
possible. Save as much vegetation as
possible. Careful manage cutting trees.
Cut only tree above 4m within the
PMU
Contractor
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
ROW.
Do not burn cleared trees and branches;
Carry out the safety procedures to
prevent hazard of downing trees.
Dispose at established dump site.
During clearing, contact with the
affected HHs in order to mitigate
impacts and carry out compensation.
Temporary duty
roads
Use roads/trails that are available. Any
new road cause minimum damage to
the local land usage.
Contracter
Construction
Surface water,
sediment and
landslides
(Levelling)
The contractor will comply with the
water drainage system design to prevent
rain drop from causing local inundation,
soil erosion in high risk areas.
To ensure proper operation of the
drainage system.
To sustain those areas not impacted by
construction activities.
The excavation work needs to be done
in compliance with applicable technical
construction regulations.
To prevent the spreading of mud into
surrounding environment, take proper
measures to control sedimentation in
high risk areas.
When there is a need to dry
construction site (foundation concrete
pouring), the pumped water containing
sand will be controlled with regards to
sedimentation before discharging it into
outside water bodies.
Use diversion techniques at
construction to prevent deposit from
being stirred up in water bodies.
Contractor
CSC
Dust generation
The contractor is responsible for
implementing the state applicable
regulations related to air quality.
The contractor will ensure minima dust
generation and no impact on local
residents and take proper measures to
control dust generation (for example,
Contractor
CSC
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
praying water, covering the trucks when
carrying material).
Material will be covered up during.
transportation to prevent scattering of
material along the way.
Material dump site and storage yards
will be covered up and isolated from
winds and located away from schools
and residential areas.
Workers will be provided with masks
when working in high risk areas.
Air pollution
All transportation vehicles must comply
with applicable regulations of Vietnam
with regards to exhaust gases.
Transportation vehicles in must be
tested frequently on the waste gases and
have to show certificate of quality,
technical safety and environmental
friendliness according to Decision
No.35/2005/QD-BGTVT.
Do not burn waste or construction
materials at the site.
Contractor
CSC
Noise and vibration
level
The contracter will be responsible for
complying with applicable regulations
related to permitted noise and vibration
levels.
All transportation vehicles need to
show certificate of quality, technical
safety and environmental friendliness
according to the Decision
No.35/2005/QD-BGTVT; to prevent
excessive noise level from machinery
that is not properly maintained, proper
noise reduction measures are taken,
including noise reducers or arrangement
of noisy machinery in a specific noise
proof area.
To prevent or reduce traffic in
residential area as well as processing of
material in residential areas (concrete
mixing)
Contractor
CSC
Waste water
pollution
The contractor will be responsible for
complying with applicable regulations Contractor
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
related to waste water treatment and
discharge.
To provide mobile toilets or construct
proper toilets for workers at the site.
Toilet waste water and restaurants will
be treated before discharging into the
outside environment.
When construction is completed, toilets
have to be properly destroyed and/or
removed.
CSC
Material warehouse
and material quarry
management
Material storage yards will be
predetermined in the approved
engineering design.
Material supplied by local suppliers
need to have operation licenses for
particular material type.
To rehabilitate material storage yard
after construction is completed.
Contractor
CSC
Waste and hazardous
waste
Prior to construction, the contractor
needs to prepare a procedure for
controlling waste (storage, use of
recycle bins, site decommissioning,
etc.) and strictly complying during
construction phase.
Prior to construction, all necessary
licenses have to be obtained related to
waste management.
Proper measures are taken to ensure
good practices in waste management
and treatment. The contractor will
provide recycle bins, containers and
other means to collect waste from
necessary areas.
Waste can be stored temporarily at the
site when it is approved by the
Construction Monitoring Consultant,
local authorities before collection and
treatment. If in the absence of such
authorities, normal domestic waste can
be land filled.
Recycle bins or containers storing waste
have to be covered up from weather
impacts and intrusion by scavengers.
Contractor
CSC
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
Do not burn waste.
Recyclable waste such as wood form,
waste steel and packing material will be
collected and separated at the site from
other waste sources for reuse, refilling
or sale to an external company.
If it is impossible to carry away from
the site, solid waste can be land filled at
a certain place approved by the
construction supervising consultant
provide in the waste management plan.
Under any circumstance, the contractor
has to treat all construction waste
within the site.
Waste lubricants will be taken out from
the site by an authorized recycling
company.
Waste lubricants and cleaning solutions
will be collected into covered
containers and carried away by a
contracted external company that is
permitted to treat hazardous waste
Site clearance
The contractor will prepare a plan on
site clearance and vegetation recovery
according to applicable regulations for
the construction supervising consultant
to approve. The contractor will strictly
comply with this plan.
Do not use chemicals in clearing
vegetation.
Do not cut down any trees when it is
not provided in the vegetation clearance
plan.
If necessary, set up temporary fence to
protect valuable trees prior to starting
any construction activities.
Contractor
CSC
Impact on cultural
property
During construction phase if the
contractor finds any cultural and
historical sites, including commentary
or tombs, the contractor will:
- Stop construction activities in the
particular area;
- Protect the area from any damage or
Contractor
CSC
PMU
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
loss to the sites. In case the historical
objects can be removed or sensitive
objects assign a person to protect it until
local authorities come to confirm and
take over the issue;
- Notify the construction supervising
consultant, who will be responsible for
informing local authorities or the state
agencies of such cultural or historical
sites (within 24 hours or less);
- Local authorities or state agencies will
be responsible for protecting and
isolating such area before any further
processing.
Decide how to process such issues is
the responsibility of the local
authorities, including change, (in case a
cultural or historical site is found and
cannot be removed), reservation,
isolation, rehabilitation and rescue;
If the cultural or historical site are of
high value and the reservation is
recommended by relevant agencies the
project owner will have to change
project design accordingly for the
component in that particular area;
Decisions related to the management of
found sites will be notified in writing to
relevant authorities;
Construction work will continue only
after relevant authorities come and take
responsibility of potential sites.
Traffic management
Prior to construction, conduct
consultation with local authorities and
traffic police.
Impacts on traffic flow needs to be
considered in the construction plan
before approval. Traffic routes,
particularly those with heavy duty
vehicles need to consider high risk area
such as schools, hospitals or markets.
It is necessary to provide sufficient
lighting system for night time to ensure
proper traffic conditions.
Contractor
CSC
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
Arrange indication signs at the
construction site to inform public
people, provide instructions to different
components and instructions and safety
directions.
Take proper traffic safety measures
including sign posts and flags to
indicate danger
Do not transport material during peak
house.
Space spared for walkers and vehicles
at the site need to be separate from the
site and can be easily accessible.
Provide proper sing posts where
necessary.
Cultural property
Apply settlement procedures if
accidentally discover during
in digging activities.
Contractor,
PCs
Interruption of utility
and business
services
Planned or unplanned interruptions to
services such as water, gas power
supply and internet access: The
contractor will be prepared for
emergency scenarios and any potential
failures.
Cooperate with services suppliers
(water, telecommunications, etc.) to
work out a proper construction
schedule.
During the laying out of cables crossing
over telecommunications cable,
mitigation measures have to be taken
(What are the measures?)
Notify affected households of
construction schedule as well as
expected interruptions (at least 5 days
in advance)
Interruptions to water supply for
agriculture production need to be
avoided.
The contractor will ensure alternative
water supply for affected residents in
case it is more than one day.
Any damage to the existing service
Contractor
CSC
PMU
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
cables will be notified to the local
authorities for timely repair.
Rehabilitation of
affected areas
Clearance areas such as soil or rock
quarries, waste treatment areas, worker
houses, warehouse and wood forms and
any other temporary areas during
construction phase will be rehabilitated
with regards to the landscape and
vegetation cover.
Compensate the vegetation cover at the
soonest. Use proper vegetation for such
rehabilitation.
Do not use exotic or banned vegetation
for such rehabilitation
Excavated hillsides and waste yard need
to be planted with grass to prevent soil
erosion and landslide;
All the affected areas will be
compensated with proper landscape and
there should be no delay in doing so,
including any necessary repair or
construction of green space and other
affected areas.
Soil contaminated with chemicals or
hazardous waste will be carried away
and land filled in a proper hazardous
dump site
Rehabilitate all affected roads and
bridges due to the project construction
Contractor
CSC
Labor and public
safety
The contractor will comply with all
applicable regulations related to labor
safety.
Prepare and implement action plan in
response to risk and emergency cases.
Prepare emergency services right at the
site.
Provide training for workers on labor
safety requirements.
Ensure to provide protective devices for
workers, including noise protection at
high risk places
In destroying existing structures,
Contractor
CSC
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
workers and community need to be
protected from falling objects by taking
proper protection measures
Provide protective fences and warnings
of danger at the construction site to
indicate danger to local resident.
The contractor will provide safety
measures such as installation of fences,
provision of warning signs at high risk
areas, including pole foundation under
construction to prevent traffic accidents
as well as other risk to local residents.
Only allow trained workers to install,
maintain or repair electrical equipment.
Cut off and do correct earthling for the
existing power line prior to construction
work.
Comply with labor safety procedures
when working at height and with
electrical equipment
Communications to
local community
Sustain communications to local
authorities and community; the
contractor will work with local
authorities to agree on construction
schedule for sites near sensitive areas or
at sensitive time (regional festivals).
Enhance relationship with local
community in order to obtain necessary
information about the project activities
in the region, progress and
performance;
Keep track of the community concerns
and information required such as
project progress;
Respond to community concerns via
telephones and documents in a timely
manner;
Notify local residents of construction
schedule, work schedule, potential
interruptions to services and detour
roads and temporary buses, any
destruction or mine explosion schedule;
Provide technical data and drawings for
community, particularly a scheme on
Contractor
CSC
PMU
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
construction sites and EMP;
Provide notice boards at all sites to
provide information about the site
manager, environmental officer,
medical and safety officer, with
concrete contact details and other
information so that affected people will
be able to raise their voice and
concerns.
Operations
Health and safety for
workers and local
residents
Disseminate the information on
electricity safety regulations to the
users.
Comply Decree No. 106/2005/ND-CP
dated 17 August 2005 of Goverment on
protecting grid; Decree No.
81/2009/ND-CP dated 12 October 2009
of Goverment on protecting hight
voltage grid
Regular training for local technicians
and people on safety issues.
Use warning signs, barriers (locks,
gates, iron barriers...) around substation
or tower to prevent people reach danger
equipment;
Putting warning signs, barriers on the
ground close to electricity wire to
prevent electric shock
NPC
Fire and explosion
Periodically inspect fire prevention and
fighting facilities.
Organize training on fire prevention and
fighting for operation workers.
NPC
Transmisison line -
Mitigation measures
related to
transmission lines
Only allow workers who have been
trained and obtained certificates on
installation, maintenance and repair of
electrical equipment
Cut off power and provide safe
earthling before construction on the
power line or where it is near power
line
Ensure operations related to power line
will be undertaken by trained workers
with strict compliance with safety
regulations. Qualified or trained
NPC
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
workers to operate power lines need to
able to:
Distinguish between online and
offline power lines from other parts
of the distribution system
Determine voltage of online power
lines
Understand safety distance for each
cable types
Ensure correct and sufficient use of
safety devices and other safety
procedures or other online parts of
the distribution system
- Even when being trained, workers
will not contact any online parts
unless:
Workers have been safely isolated
from online parts via gloves or other
insulation devices
Online parts have been safely
isolated from workers and other
parts or
Workers have been isolated and
safely insulated from online objects
When operations and maintenance
request minimum distance, provide
trainings on safety measures and safety
devices for individuals and other
preventive measures identified in the
health and safety compliance plan.
(Below is the recommended safety
distance for workers:
2-15 kV: 0.6 m
15.1-35kV: 0.71 m
72.6-121 kV: 1.01 m
Safety measures
when working at
height
Preventive and control measures
include:
- Check the firmness of structures
before starting work
- Take anti-fall measures including
climbing skills, use of supporting
NPC
Subproject: Distribution Efficiency Project
Environmental Management Plan
Period Potential impact Mitigation measures Responsibility
devices and first aid toolkit
- Install supporting and anti-fall
devices
- Safety bands will not be smaller
than 16 mm, two layers, and durable
strength. Safety bands will be
replaced before any defect or crack
is detected or if is too old
- When working with tools at height,
workers will need an additional
safely band (backup).
- Sign posts and other obstacles need
to be removed before starting work
- Use standard tool bag to carry tools
and materials to the height when
working on pillars
EMF impacts
- Prevent or minimize exposure to
EMF in the working environment
by developing and implementing a
EMF safety program with the
following components:
- Determination of potential exposure
level
- Trainings for workers on how to
identify their exposure to EMF and
its impacts
- Determination of safe areas in order
to differentiate those areas with
higher EMF impacts than the others
where EMF impacts are small
enough not to be provided with
mitigations and minimize exposure
to high EMF impact areas
- The exposure detector for
individuals will be installed to give
warning when exposure is below the
safety limit (for example, 50%).
Action plans for mitigating impacts
includes taking turn to work in high
risk areas, and if necessary being
provided with protective devices.
NPC
Table 6.2. Site specific mitigation measures
Subproject: Distribution Efficiency Project
Environmental Management Plan
Preriod Protential impact Mitigation measures Responsibility
Construction
Influence on trees
and canal while
extending line,
building the
foundation and
erecting pole
Construction is made after the harvests and
construction progress should be reduced.
When extend line through rice field or crop
area use bamboo peg to stark line to not affect
crop and rice.
If construction make canal broken down, must
refund
Garbage arise in construction affect to canal,
have to drag canal and widen flow.
Appropriate compensation is made for losses
as specified in the Resettlement Policy
Framework of the project and the
Resettlement Action Plan of the subproject.
Contractor
CSC
PMU
Cutting off
electricity on the
crossing over line
will influence
production and
living activities in
the electricity
cutting- off area
Select suitable time to cutting off electricity,
avoid electricity cutting off at peak time. If the
construction is implemented in harvest time
the power management unit will cut local
electricity during the day(when people go to
work on the fields).
The contractor should work directly with the
electricity control team of the commune and
the hamlet for permission to report about
electricity cutting off time and deploy
subproject. the electricity control team of the
commune and the hamlet will inform in
advance the electricity cutting-off time to the
local people to arrange their production plan
and living.
cut off electricity during the setting up of
scaffoldings and avoid electricity cutting-off
during peak time. The electricity control team
of the commune and the hamlet will inform in
advance the electricity cutting-off time to the
local people to arrange their production plan
and living.
However, in order to avoid electricity cutting-
off for a long time when the line crossing over
the information line; line 35; 22; 0,4 kV;
scaffoldings must be used. After the setting-up
of scaffoldings, electricity should be supplied
again to the line. Only after that, line
extending could be conducted.
Contractor
CSC
PMU
Subproject: Distribution Efficiency Project
Environmental Management Plan
Preriod Protential impact Mitigation measures Responsibility
Construction near
sensitive area as
cultural and
historical
monument area,
school, hospital
There are many cultural and historical
monument area in the subproject area.
Thus, before deploying the subproject The
contractor should work directly with local
government to report about the subproject
implementing plan and must be approved by
local government.
When construction in festival time must let
warning signs, propaganda to arise labor
discipline awareness for workers.
Encourage drivers to transport supplies and
equipment through the sensitive areas such as
temples, schools, hospitals not to abused horn
to avoid to cause noise.
Contractor
CSC
PMU
VII.ENVIRONMENTAL MONITORING PLAN
Table 7.1: Environmental monitoring plan is shown in the below table
Impact Monitored
parameter
Monitored
point
Monitoring
equipment
/method
Timing/
frequency of
monitoring
Responsibility
Construction phase
I.
Vegetation
cover
clearance or
cutting
down trees
-Clearance
technique
- Disposal of
cut-down trees.
- Along the
transmission
line
- In a
centralized
place for
processing.
Observation -From
beginning to
the last
moment.
-Contractor
-Construction
supervising
consultant
I I. Rural
roads in the
project
region
- All heavy
tonnage
vehicles on the
local roads
- Along the
roads
Observation
and
consultation
with local
residents.
-Weekly basis
when material
is transported
to the region.
- Four months.
- Contractor,
-Construction
supervising
consultant
III. Surface
water
quality,
sedimentati
on and
- Not excavate
while it is
raining
- Not clear
plants
- Surface
water near
the site.
Observation -During and
after heavy
rain
-Contractor,
-Construction
supervising
consultant
Subproject: Distribution Efficiency Project
Environmental Management Plan
Impact Monitored
parameter
Monitored
point
Monitoring
equipment
/method
Timing/
frequency of
monitoring
Responsibility
erosion completely
IV. Dust
and air
pollution
- Dust
concentration
in material
storage area
- Cover for
material during
transportation
process
- Areas with
excavation
foils and
material
storage
Observation -In presence of
strong winds
-Contractor,
-Construction
supervising
consultant
V. Noise
level
- Noise by
machinery
- Local
resident
response to
noise from the
construction
process
- The line
section
running over
residental
area
Consultatio
n with local
residents
-During
activities that
may result in
high noise
level;
Complaints by
local residents
-Contractor,
-Construction
supervising
consultant
VI. The
culture and
history
monuments
- The effects of
noise
-At the
construction
places close
to culture and
history
monuments
Observing
the local
residents
-During
construction,
the activities
emanate noise
-Contractors
-Construction
monitoring
consultant
VII.
Sanitation
situation at
the
construction
site,
including
the hygiene
of workers’
camps
-Garbage,
waste water at
the
construction
site and
workers’ tents
- If he tents
have been
supplied clean
water and had
sanitary
latrines
-At the tents Observing -Every week,
when official
acceptance of
work
-Contractors
-Construction
monitoring
consultant
VII. Safety
of workers
and local
presidents
- Accidents
happen
- At the sites,
local areas
- Consult,
Record the
constructio
n log of the
contractor
-Contractors
-Construction
monitoring
consultant
Subproject: Distribution Efficiency Project
Environmental Management Plan
Impact Monitored
parameter
Monitored
point
Monitoring
equipment
/method
Timing/
frequency of
monitoring
Responsibility
Operation phase
I. Maintain
and protect
the ROW
The height of
plants along
the ROW
Along the
ROW, houses
and trees
Prune trees
and ensure a
safe
distance for
the ROW
One month/
time
North High
Voltage grid
Company
II. Danger
due to
danger
-The intact
situation of
poles,
insulators,
protecting
devices of the
station
- At the pole
of the line
route, the
position of
the station
- Observing
and
assessing
3months/
time
-North high
voltage grid
Company
Subproject: Distribution Efficiency Project
Environmental Management Plan
VIII. EMP IMPLEMENTATION ARRANGEMENT AND CAPACITY BUILDING
a) During Detailed Design and Preparation of Bidding Contract Documents
During the detailed design and bidding invitation preparation, the project management
unit will be responsible for incorporate the EMP (mitigation measures, responsibilities of the
contractor) into the attached annexes in the bidding invitation and contract signed with the
contractor. Engineers taking charge of the detailed design will also refer to findings in the
EIA and EMP to ensure environmental issues will be looked at in the final design.
During the bidding invitation preparation and the contract, it is necessary to ensure the
contractor is fully informed of its responsibilities in implementing environmental mitigation
measures and its commitment to compliance.
b) During Construction Phase
PPMU will assign the Construction Supervising Consultant (CSC) and/or field engineer
to be responsible for supervision of safeguard performance of contractor on a daily basis. A
generic Terms of Reference (TOR) is provided in Annex 1. CSC and/or field engineers will
carry out, but not limited to, the following tasks:
- Before the commencement of the construction, confirm that all compensation for land
and facilities are provided and relocation and/or land acquisition/donation has been
completed.
- Closely supervise the implementation of safeguard measures throughout the
construction period.
- Confirm the compliance with the EMP and inspect for any damages caused by the
contractor. If necessary, prepare a minutes to ask the contractor to compensate or
rehabilitate as provisions of the contract. Contractor safeguard performance will be
included in the subproject progress report.
Role and responsibilities of parties in implementing EMP are summarized in the below table:
Table 8.1. Responsibility for EMP Implementation
Role Responsibility Organization
- Project
owner
- Take final responsibility with regards to the
management and implementation of project including
environmental compliance environmental
performance.
-North
Electricity
Corporation
- Environme
ntal officer
- Indicate specific responsibility and provide contact
details.
Environmental
officer of
project
Subproject: Distribution Efficiency Project
Environmental Management Plan
Role Responsibility Organization
- Project
manageme
nt and
implement
ation entity
Responsible for cooperating and managing the
implementation of project including providing guidance
and implementing the EMP:
- Develop plan and implement EMP activities during
construction.
- Cooperate with relevant stakeholders with regards to
environmental performance.
- Conduct internal supervision and independent audit.
- Supervise and provide budget for monitoring
activities.
- Report environmental information to relevant
stakeholders.
PMU
- Project
operation
entity
- Operating the project including environmental
management and supervision during operation phase.
North High
Voltage Grid
Company
- Contractor
supervisor
- Support the PMU in supervising project operations
with regards to environmental impacts mitigation
according to measures described in the EMP and keep
in touch with local residents.
Construction
supervising
consultant
hired by the
PMU
- Contractor Constructing and complying with technical requirements of
the EMP, including:
- Taking mitigation measures to minimize negative
impacts as described in the EMP.
- Communicating with local residents and taking action
to prevent environmental and social interruptions in
the project region during construction.
- Ensuring at least one officer supervises compliance to
EMP during construction.
- Ensuring all construction activities are given
necessary approvals from relevant authorities.
- Ensuring workers and officers understand their
responsibilities and procedures in environmental
management.
- Reporting to the construction supervising consultant
on difficulties and solutions.
- Reporting to local authorities and PMU and
cooperating with relevant agencies to address any
issues.
Construction
supervising
consultant
hired by the
PMU
Subproject: Distribution Efficiency Project
Environmental Management Plan
IX. REPORTING PROCEDURE
Responsibility and frequency of reporting on EMP implementation are shown
in the below table.
N
o.
Report by Submitted to Frequency of reporting
1 By contractor to project owner PMU Once prior to starting
construction afterwards
every one month.
2 Construction supervisor (cum
environmental monitor)
PMU Monthly
3 Community supervisor (if any) MPU If any complaint
4 PMU EVN Quarterly
5 EVN WB Biannually
Subproject: Distribution Efficiency Project
Environmental Management Plan
X. CAPACITY BUILDING FOR EMP IMPLEMENTATION
Table 10.1. Estimates of capacity building for implementing EMP
Training
content Trained staff
Trainee
quantity
Training
time
Training
organizing
agency
Cost
1 2 3 4 5 6
Training about
environmental
management
Staff responsible
for environmental
management of
EVN Ha Noi
Six mans
January,
2012
EVN
* Cost:
2,000,000VND per man x 5 mans = 10,000,000VND
Training about
mitigation,
environmental
monitor
Staff of district
power company
Twenty mans December,
2012
EVN Ha
Noi
* Document cost: 300,000VND per man x16
mans=4,800,000 VND
* Subsistence cost:
300,000VND per day x 3 days x16 mans =
14,400,000VND
* Travelling cost for trainees:
50,000VND per man x 16 mans = 8000,000VND
* Supporting cost for training lecturer: 2,000,000VND x
3 mans = 6,000,000VND
Total cost 43,200,000VND
Subproject: Distribution Efficiency Project
Environmental Management Plan
XI.ESTIMATED COST FOR IMPLEMENTING THE EMP
Table 11.1. Table of estimate cost
No. Activity Construction
Phase Operation Phase
Total
(VND)
1 Implement
Mitigation Measures
The costs are
covered in
Contract with
Construction
Contractors
The cost is covered in
production cost of EVN
Ha Noi
480,000,000
2
Environmental
monitoring during
construction phase
by Construction
Supervisor
The costs are
covered in the
contract of hiring
monitoring
consultant
120,000,000
3 Capacity Building 43,200,000
Total cost 643,200,000
Subproject: Distribution Efficiency Project
Environmental Management Plan
XII. COMMUNITY CONSULTATION AND DISCLOSURE OF INFORMATION
12.1 Community consultation:
Through public consultation, advice obtained result summarized as follows:
Table 12.1. Summary of public consultation
N0
Subproject Location Time and date Number of
Participant
Representative of
local authorities
and households
to participate
Issues or
concerns to be
discussed /
raised
I
Improve
rural
network of
old Ha Noi
area
- Period 1
Meetting-hall
communes
people’s
committee have
project
Chairman, vice
chairman of
commune
people’s
committee
Fatherland Front
Committee
League
Executive Board
Women's
Executive Board
Farmer
association
Veterans’
organization
Elderly people
Households
(see attachment)
Description
project: line
project,
project
location,
construction
size, the need
of
construction
project.
Description
impacts of the
project with
environmental
(air, water,
traffic...)
The measures
of minimize
passive
impacts.
The measure
of
compensation
for damage to
property
caused by the
project
Project
planning
1 Hoang Mai
district
Hoanng Liet
ward people’s
committee
8 h to 11h30
date13/12/2011
11
(5 woman)
Hoang Van Thu
ward people’s
committee
8 h to 11h30
date 9/12/2011
11
(4 woman)
2 Tu Liem
district
Trung Van
commune
people’s
committee
1h to 4h
date14/12/2011
6
(3 woman)
Me Tri
commune
people’s
committee
7h30 to 11h30
date
10/12/2011
10
(4 woman)
Dai Mo
commune
people’s
committee
7h30 to 11h30
date 8/12/2011
11
(4 woman)
3 Gia Lam
district
Da Ton
commune
people’s
committee
1h30 to 5h
date12/12/2011
11
(3 woman)
Phu Thi
commune
people’s
committee
7h30 to 11h30
date13/12/2011
11
(4 woman)
Subproject: Distribution Efficiency Project
60
The result obtained through the community consultation are summarized as follows:
N0
District
(ward/commune) Place Time
Number of
Participants Delegate
Summary comment
of delegates
I Hoang Mai district
1 Hoang Liet ward
Hoang Liet ward
people’s
committee hall
8 h to 11h30
date 13/12/2011 11
1. Nguyen Van Sang : Vice chairman
of ward people’s committee.
2. Tran Thi Minh: Chairman of the
Executive Board of the farmer.
3. Ta Thi Tha: Representative of
women's Executive Board.
4. Nguyen Dinh Tuat: Chairman of
Fatherland Front Committee.
5. Tran Ba Giap: Representation of
veterans’s organization Executive
Board.
6. Tran Toan Thuong: Representative
of league Executive Board.
7. The representative household assets
affected: 5/8 households.
- Guiding People in
the project area
electrical safety
measures.
- Minimize the
impact on daily
life of the people.
Subproject: Distribution Efficiency Project
61
2 Hoang Van Thu
ward
Hoang Van Thu
ward people’s
committee hall
8 h to 11h30
date 9/12/2011 11
1. Nguyen Tiet Cuong: Vice chairman
of ward people’s committee.
2. Tran Thi Thuy Hang: Secretary of
league Executive Board.
3. Dinh Thi Ngat: Chairman of
women's Executive Board.
4. Tran Xuan Ngoc: Vice chairman of
Fatherland Front committee.
5. The representative household assets
affected: 7/7 households.
- Implement
measures to
minimize
environmental
impact.
- Implementation of
the appropriate
time to reduce the
loss of property to
people.
II Tu Liem district
1 Trung Van
commune
Trung Van
commune
people’s
committe hall
1h to 4h date
14/12/2011 6
1. Nguyen Trong Cong: Chairman of
commune people’s committee.
2. Ngo Quang Chien: Representative
Veterans’ organization.
3. Bui Dinh Loc: Chairman of
commune Fatherland Front
committee.
4. The representative household assets
- Construction
implementation
when the crop
harvested.
- Implement
measures to
minimize
environmental
impact.
Subproject: Distribution Efficiency Project
62
affected: 3/3 households.
2 Me Tri commune
Me Tri commune
people’s
committee hall
7h30 to 11h30
date 10/12/2011 10
1. Nguyen Thi Huong: Vice chairman
of commune people’s committee.
2. Thu Hoa: Representative of women's
Executive Board.
3. Ngo Van Tich: Representative of the
Executive Board of the farmer.
4. The representative household assets
affected: 7/7 households.
- Construction
implementation
when the crop
harvested.
- Guiding People in
the project area
electrical safety
measures.
3 Dai Mo commune
Dai Mo
commune
people’s
committee hall
7h30 to 11h30
date 8/12/2011 11
1. Nguyen Minh Giang: Chairman of
commune people’s committee.
2. Nguyen Thi Thoa: Representative of
women's Executive Board.
3. Do Dac Tieu: Representative of
veterans’ organization Executive
Board.
4. The representative household assets
affected: 7/8 households.
- Construction
implementation
when the crop
harvested.
- Implement
measures to
minimize
environmental
impact.
- Guiding People in
the project area
Subproject: Distribution Efficiency Project
63
electrical safety
measures.
III Gia Lam district
1 Da Ton commune
Da Ton
commune
people’s
committee hall
From 1h30 to 5h
date 12/12/2011 11
1. Tran Duc Dien: Chairman of
commune people’s committee.
2. Bui Van Ma: Representation of
commune Fatherland Front
committee.
3. Nguyen Thi Nga: Representative of
women's Executive Board.
4. Le Anh Dung: Representative of
league Executive Board.
5. The representative household assets
affected: 6/6 households.
- Construction
implementation
when the crop
harvested.
- Implement
measures to
minimize
environmental
impact.
2 Phu Thi commune
Phu Thi
commune
people’s
committee hall
7h30 to 11h30
date 13/12/2011 11
1. Le Van Huy: Chairman of commune
people’s committee.
2. Nguyen Van Thanh: Chairman of
commune Fatherland Front
committee.
3. Dang Van Dac: Representative of
- Construction
implementation
when the crop
harvested.
- Implement
measures to
Subproject: Distribution Efficiency Project
64
elderly people commune Executive
Committee .
4. Nguyen Duong Thanh:
Representative of the Executive
Board of the farmer.
5. The representative household assets
affected: 7/8 households.
minimize
environmental
impact.
- Guiding People in
the project area
electrical safety
measures.
12.2 Disclosure of information:
- The EMP report in Vietnamese will be announced at ward/commune People's Committee in the subproject area for the public,
organizations are able to access. The abbreviated EMP will be sent to the ward People's Committee that the line come across to announce for
crowded public to stydy. Estimated disclosure time is in April 2012.
- The EMP report in English and Vietnamese will be sent to The Center for Information and Development of Vietnam at 63 Ly Thai To -
Hanoi for the evaluation of government office and community;
- The EMP report in English will be sent to the Infoshop of World Bank in Washington to announce.
Subproject: Distribution Efficiency Project
65
ANNEX 1
TOR for monitoring of emp implementation for construction supervising consultant
Background
The construction supervising consultant will deliver technical services (“Services”) to ensure
efficient implementation of the EMP for the project.
Scope of services:
Services provided by the supervising consultant will include reviewing and monitoring of
construction activities to ensure mitigation measures described in the EMP for the project are
correctly complied with and negative environmental impacts are minimized.
On behalf of the PMU, supervising consultant undertakes the following duties:
- Conduct frequent field inspection;
- Review the implementation of environmental protection measures described in the EMP
and contract documentation;
- Review the effectiveness of the mitigation measures and environmental performance of
the project;
- If necessary, validate the acceptability of construction methods with regards to
environmental compliance (for temporary and permanent items), relevant design plans
and other submitted documents. If necessary, the supervising consultant will seek for and
recommend methods with less environmental impacts with consultation with the design
consultant and the PMU;
- Validate inspection results with regards to any non-conformance to environmental
performance and effectiveness of any countermeasures;
- Provide audit results for the leading engineer of the contractor in accordance with non-
conformance handling procedure described in the EMP;
- Direct the contractor to take corrective actions within a specific time period and exercise
additional monitoring if necessary, as per the requirements of the contract in case of non-
conformance and complaints;
- Direct the contractor to take actions to mitigate impacts and comply with the EMP in case
non-conformance is found;
- Direct the contractor to stop any activity resulting negative impacts and/or in case the
contractor does not fulfill requirements of the EMP, to take corrective actions.
- For contracts that need Site Environmental Management Plan (SEMP), the
supervising consultant will conduct a final review and approve all environmental plans at
the site that may affect environment. This work includes but not limited to: dredging
areas, material quarries and dumping areas and worker houses. The supervising
consultant will review and approve such SEMP submitted by the contractor. If such plans
are found non-compliant to the EMP, EPC or RAP, the supervising consultant will work
with the PMU and contractor for a proper solution.
- Complaint handling: Complaints from local residents will be collected by site officer of
the contractor, which may include violations to noise level, dust concentration and traffic
safety requirements. The lead consultant of the contractor and the supervising consultant
will address and work out a final solution organizes all such complaints. The supervising
Subproject: Distribution Efficiency Project
66
consultant will provide a list of these complaints and confirm they have been properly
handled by the contractor in the same way with issued identified during site inspection.
- Confirmation of monthly payment: The supervising consultant will confirm monthly
payment for environment related activities undertaken by the contractor.
- Report: The supervising consultant will make the following reports in English:
o Report twice a week on non-conformances
o Monthly summary report will include issues and findings from the reviewing
and monitoring of construction activities
o At the end of project, the supervising consultant will make a final summary
report on findings from their work, number of violations, and solutions, etc. as
well as provide consultancy and guidance on how to implement such duties in
future.
Subproject: Distribution Efficiency Project
67
ANNEX 2
Report template for monitoring of EMP implementation
(Used for report by supervising consultant to PMU)
Project name:
Project location: Province: District:
Commune/Town:
Supervising consultant:......Full name Date of report:……………………
No. Parameter
Assessment of
comments by
supervising
consultant and
community
Comment/
Recommenda
tion
Construction phase
1 Water turbidity and soil erosion
2 Noise level at the site and nearby
residential area
3 Dust concentration
4 Solid waste and site cleaning after
construction
5 Conflict between workers and local
residents
6 Disease spreading
7 Hygiene condition and safety for workers
8 Local traffic interruption
9 Road damage
10 Safety measure application
11 Material management
12 Remained soil and rock management
13 Evidences about loss to biodiversity (if
any)
14 Evidences about loss to cultural and
Subproject: Distribution Efficiency Project
68
No. Parameter
Assessment of
comments by
supervising
consultant and
community
Comment/
Recommenda
tion
historical sites
15 Other environmental issues (if any)
….
Operation phase
16 Transmission line lobby maintenance
17 1. Health and safety for operation
workers and local residents
Subproject: Distribution Efficiency Project
69
ANNEX 3
Report template for monitoring of EMP implementation
(Used for reports by contractor)
Project name:
Project location:
Contractor name:
Initial or monthly report:
Date of report:
No. Impact Mitigation
measure taken Comment
Construction phase
1 Surface water pollution
2 Noise and vibration level
3 Soil erosion
4 Air pollution
5 Impacts on agriculture land due to
temporary land acquisition
6 Local traffic interruptions
7 Existing road damage
8 Solid waste from excavation
9 Remained soil management
10 Environmental impacts by workers
11 Conflict between workers and local
residents
12 Disease spreading between workers
and local residents
13 Health and safety
14 …..
Reported by :
Title :
Subproject: Distribution Efficiency Project
72
ANNEX 5
Some pictures of project area
TBA Liên Hợp - xã Tây Mỗ
TBA Tây Tựu 6 - xã Tây Tựu
Cột hạ thế tận dụng
Cột hạ thế tận dụng
Cột hạ thế tháo dỡ
Cột hạ thế tháo dỡ