31
H1 2019 Results Presentation August 8, 2019

H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

H1 2019 Results Presentation

August 8, 2019

Page 2: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

2

Disclaimer

The information contained in these materials has been provided by ContourGlobal plc (“ContourGlobal” or the “Company”) and has not been independently verified.No representation or warranty, express or implied, is made as to, and no reliance should be placed on, the fairness, accuracy, completeness or correctness of theinformation or opinions contained herein. It is not the Company’s intention to provide, and you may not rely on these materials as providing, a complete orcomprehensive analysis of the Company’s financial position or prospects. The information and opinions contained in these materials are provided as at the date ofthis presentation and are subject to change without notice. Neither the Company nor any of its affiliates, advisors or representatives shall have any liabilitywhatsoever (in negligence or otherwise) for any loss whatsoever arising from any use of this presentation or its contents or otherwise arising in connection with thispresentation.

Certain statements in this presentation are “forward-looking statements.” All statements other than statements of historical facts included in this presentation,including, without limitation, those regarding the Company’s financial position, business strategy, plans and objectives of management for future operations, areforward-looking statements. These statements involve a number of factors that could cause actual results to differ materially, including, but not limited to, changesin economic, business, social, political and market conditions, success of business and operating initiatives, and changes in the legal and regulatory environment andother government actions. Forward-looking statements contained in this presentation regarding past trends or activities should not be taken as a representation thatsuch trends or activities will continue in the future. Any forward-looking statement made during this presentation or in these materials speaks only as of the date onwhich it is made. The Company assumes no obligation to update or revise any forward-looking statements.

Information contained herein relating to markets, market size, market share, market position, growth rates, penetration rates and other industry data pertainingto the Company’s business is based on the Company’s estimates and is provided solely for illustrative purposes. In many cases, there is no readily available externalinformation to validate market-related analyses and estimates, thus requiring the Company to rely on internal surveys and studies. The Company has also compiled,extracted and reproduced market or other industry data from external sources, including third parties or industry or general publications, for the purposes ofits internal surveys and studies. Any such information may be subject to significant uncertainty due to differing definitions of the relevant markets and marketsegments described.

This presentation contains references to certain non-IFRS financial measures and operating measures. These supplemental measures should not be viewed in isolationor as alternatives to measures of the Company’s financial condition, results of operations or cash flows as presented in accordance with IFRS in its consolidatedfinancial statements. The non-IFRS financial and operating measures used by the Company may differ from, and not be comparable to, similarly titled measures usedby other companies. The non-IFRS adjustments for all periods presented are based upon information and assumptions available as of the date of this presentation.

Page 3: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

3

Key Highlights for H1 2019

Operations

Financial Results

Bonaire 28MW Orellana CSP 50MW solar farm (Spain)HAGN 47MW Wind Park (Austria)

Agenda

Growth

Page 4: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

4

262 357

H1 2018 H1 2019

535 617

H1 2018 H1 2019

Revenue ($m)

H1 2019: Strong Growth in All Key Financial Metrics

226 300

H1 2018 H1 2019

111

170

H1 2018 H1 2019

Adjusted EBITDA ($m)

FFO ($m)Proportionate EBITDA ($m)

48% cash Conversion1

Increased cash conversion vs. 42% in H1 18

(1) Cash conversion rate defined as FFO / Adjusted EBITDA

$50m increase from CSP

acquisition, $46m net farm down

gains, -$24m from FX and $10m from positive renewable

resource

Page 5: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

5

✓ Good progress in regards to achieving target of doubling Adjusted EBITDA by 2022

✓ Declaring a second quarterly dividend for 2019 of $24.75 million corresponding to 3.6901 USD cents per share, which

is expected to be paid on September 6, covered by strong cash flow and in line with our policy of growing the dividend

by at least 10% per annum

✓ Mexico CHP¹ acquisition expected to close in the third quarter of 2019 and to generate $110 million of Adjusted

EBITDA on a full year basis

✓ Sale of 49% of our 250 MW Concentrated Solar Power portfolio in Spain in May 2019 with €134m cash proceeds

✓ €100 million 4.125% senior secured notes due 2025 issued subsequent to the end of the half year at 106.0% of par

corresponding to a yield to maturity of 3.024% to fund further growth

✓ Reflecting the timing of the closing of the Mexico CHP acquisition, we expect 2019 Adjusted EBITDA to be in the lower

half of our previously communicated guidance of $720-770 million for the full year at constant foreign exchange rate2

(1) CHP – Combined Heat and Power(2) 0.8851 for EUR/USD, and 3.914 for BRL/USD

Ongoing Strong Growth and Cash Generation

Key Highlights

H1 2019 Consolidated Results

Page 6: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

6

2. OperationsKarl SchnadtExecutive Vice President & Chief Operating Officer

KivuWatt – Methane Gas Extraction Facility & Power Plant (Rwanda) 6

Page 7: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

7

Industry Leading Health & Safety PerformanceTarget Zero achieved in H1 2019

Inka Wind Farm, Peru

Leading the Sector in Health and Safety Performance

‘Target Zero’ Remains ContourGlobal’s Key Priority

Our 2019 TRIR(5) is 0.13 vs. a target of 0.14

(1) Lost time injury rate (LTIR) is an industry standard reporting convention for calculating injuries in the workplace. LTIR measures recordable lost time incident (LTI) rates on the basis of 200,000 working hours (2) Source: peers information as 2018 reported in annual reports/sustainability reports published by companies normalized to basis of 200,000 working hours (3) Selection of comparable peers from study performed by Black & Veatch (4) Based on the 2018 Bureau of Labor Statistics report (5) TRIR: total recordable incident rate is an industry standard reporting convention for calculating recordable injuries in the workplace. TRIR is the total lost time injuries, restricted workday cases and medical treatments on the basis of 200,000 working hours

7

LTIR

2

1 1

0.06

0.03 0.03

0

-0.02

0

0.02

0.04

0.06

0.08

0

0.5

1

1.5

2

2.5

2016 2017 2018 H1 2019# of LTIs LTIR

0.000.03

0.12 0.14 0.17 0.18 0.19 0.200.27 0.27 0.30

0.36 0.38 0.38

0.49 0.500.54

0.68

0.90LTIR

Selected Peers Top Quartile = 0.20

US Utilities Average = 0.6

LTIR(1) - PEERS (2) (2018) VS CG(3)

(4)

Page 8: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

8

92.6% 90.2% 93.3% 93.2%

2017 2018 H1 2018 H1 2019

92.7% 95.8% 95.8% 96.1%

2017 2018 H1 2018 H1 2019

97.8% 98.5% 98.5% 98.2%

2017 2018 H1 2018 H1 2019

99.2% 99.2% 99.7% 98.3%95.3% 96.7% 94.6%

2017 2018 H1 2018 H1 2019

Solar PV Solar CSP

Divisional Operating PerformanceConsistent Performance Across All Technologies

Thermal – Equivalent Availability Factor1 (%)

Hydro – Equivalent Availability Factor1 (%)

Wind – Equivalent Availability Factor1 (%)

Solar – Equivalent Availability Factor1 (%)

(1) Equivalent Availability factor refers to the actual amount of time a plant or group of plants is available to produce electricity

• Technical performance is in line with previous periods and well above minimum PPA required threshold

• Ongoing improvement in Brazil Wind operations driving EAF improvements

8

• Excellent hydro availability; plants primarily rewarded on capacity or regulatory payments as opposed to individual plant generation

• Decrease in H12019 availability due to blade failure in CSP and forced outages and maintenance at Solar Italy

• Strong production performance at CSP despite lower H1 2019 EAF

74% weighted average PPA minimum availability requirement

Page 9: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

9

31%28%

43%

15%

20%

28%

55%

29%31%

43%

15%

24%27%

53%

Brazil Wind Austria Wind Peru Wind Solar PV Spanish CSP Vorotan Brazil Hydro

Renewable Fleet Capacity FactorsMost clusters at or above long-term expected levels

Renewable fleet capacity factors (actual vs. long-term expected for H1)

(1) Long term expected capacity factors before repowering program completion(2) Hydro plants are less affected by generation; primarily rewarded on capacity or regulatory payments as opposed to individual plant generation

1

Wind Solar Hydro

9

2 2

(1%)

(2%)

4%

3%(2%)

Expected H1 2019 Expected H1 2019 Expected H1 2019 Expected H1 2019 Expected H1 2019 Expected H1 2019 Expected H1 2019

Expected and actual capacity factors are for H1 only. Seasonality of resource means majority of renewable generation occurs in H2

0%

0%

Page 10: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

10

3. Financial ResultsStefan SchellingerExecutive Vice President & Chief Financial Officer

Asa Branca Wind Farm (Brazil) 10

Page 11: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

11

434

536 610

226 300

576

2017A 2018A LTM H12019

H12018

H12019

513

610

706

262

357

650

2017A 2018A LTM H12019

H12018

H12019

Robust Financial PerformanceSignificant growth in all key financial metrics

(1) Adjusted EBITDA and FFO are non-IFRS measures as defined in IPO Prospectus(2) Pro forma numbers: Adjusted to reflect full year contribution of Spanish CSP(3) Growth based on 2017 to LTM H1 2019 (CAGR)(4) EBITDA includes net gains from farm down transactions of $46m

Adjusted EBITDA1

($m)

+24%3 +26%3

FFO1

($m)

2

Proportionate Adjusted EBITDA($m)

2

+25%3

11

+36% +33% +53%

4 4

2

256 302

361

111

170

330

2017A 2018A LTM H12019

H12018

H12019

Page 12: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

12

120 119 119 129 131 184

214 214

10 3 52

46

(1)

(16)

Adj. EBITDA H12018

Availability Resource Other Organic Acquisitions Farm downs FX Impact andOther

Adj. EBITDA H12019

163 163 161 161

9

(11)

Adj. EBITDA H1 2018 Availability and dispatch FX Impact and Other Adj. EBITDA H1 2019

Successful Integration of New Business Driving Growth

ADJUSTED EBITDA – THERMAL DIVISION ($m)

ADJUSTED EBITDA – RENEWABLE DIVISION ($m)

1

(1) Spanish CSP Acquisition closed on May 10th, 2018

78% increase

1%decrease

Austria Wind: +$4m / Solar assets: +$3m / Hydros: +$1m / Others: +$2m

+$50m CSP Spain

Increased availability and higher dispatch

12

1

11

BRL and EUR depreciation

Page 13: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

13

Significant Cash Conversion Achieved in H1 2019

(1) Funds From Operations is defined as Cash Flow from Operating Activities excluding changes in working capital, less interest paid, less maintenance capital expenditure, less distribution to minorities. Funds from Operations is a non-IFRS measure.

(2) Includes net cash gain on sale of minority interests in CSP and Solar Italy and Slovakia(3) Cash conversion rate defined as FFO / Adjusted EBITDA

H1 2019 ADJUSTED EBITDA TO FFO1

(2)

13

48% cash conversion³(42% in H1 2018)

357.2

169.8

1.5

(100.8) (8.1)

(19.7)(14.3)

(46.0)

Adjusted EBITDA Interest paid Income tax paid Maintenancecapex

Cash distributionminorities

JV and Associates Net gain on farmdowns

Funds fromOperations

Page 14: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

14

4.1x 4.4x

4.0x

2017A 2018A LTM H1 2019

Jun-19 liquidity – ($m)

Ample Cash Resources to Support Future Growth and DividendImprovement in Net debt / EBITDA metric – at the lower range of 4.0x-4.5x guidance

• $2.9bn Net Debt as of June 30, 2019

• Committed to high value growth while maintaining strong BB credit metrics

• Improvement in Net Debt / EBITDA metric to 4.0x

• $497m liquidity at parent level, including $445m of cash and $52m undrawn capacity under corporate level revolver

14

299

796 445

52

Asset LevelCash

HoldCoLevel Cash

RevolvingCreditFacility

TotalLiquidityJun-19

Net Debt/EBITDA (x)Jun-19 net debt – ($m)

(1) Restricted cash at the operating assets’ level(2) Unrestricted cash at the HoldCo level(3) Includes full year earnings of Spanish CSP, which was acquired in May 2018 (+$40m of Adjusted EBITDA based on FY Earnings)

(3)

2,744 2,857

857

(744)

ProjectDebt

CorporateDebt

Cash Net DebtJun-19(IFRS)

(1) (2)

Page 15: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

15

90 99

2018A 2019E

• 2018 dividend of $0.1342 per share or $90m

• 2019 guidance of $0.1476 per share or $99m

• ContourGlobal declare a second quarterly dividend for 2019 of $24.75m corresponding to 3.6901 USD cents per share to be

paid on September 6, 2019

ContourGlobal’s strong and predictable cash flow supports our commitment to dividend growth of 10% p.a.

15

Dividend – ($m)

$0.1476 per share

Dividend policy of 10% annual Growth

$0.1342 per share

Page 16: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

1616Sao Domingos II Hydro Power Plant (Brazil)

4. GrowthJoseph C. BrandtPresident & Chief Executive Officer

Page 17: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

17

Mexican Cogeneration Business Acquisition Signed in Jan 2019; closing expected in Q3 2019

• Acquisition of natural-gas fired combined heat & power assets

with 518MW of operational capacity at completion, potential

for a further 414MW in development

• More than 90% contracted revenues including heat and steam

with seller

• Integration of Mexico CHP¹ is progressing as planned with all

key integration workstreams on track

• Commissioning of 414 MW CGA 1 plant progressing with COD²

and closing expected in Q3 2019

• $590m project financing underwritten by Scotiabank to be

syndicated in Q3 2019 with syndication progressing well

• Estimated Adj. EBITDA of $110m in first full year of operations

Transaction Highlights and Update Geographic Footprint

Altamira, TamaulipasCGA

Cosoleacaque, VeracruzCELCSA

(1) CHP – Combined Heat and Power(2) Commercial Operations Date

Page 18: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

18

Latest development

• Resignation of Prime Minister and potential change of government creates timing uncertainty

State-of-the-art coal plant

• State-of-the-art coal plant with Best Available technology

• The new plant will replace Kosovo’s current plant, the most polluting plant in Europe emitting 9 times more damaging particulate matter than the average of coal plants in the Balkans.

• It’s expected to significantly decrease all emissions, including CO2 , resulting in significantly improved environmental and health outcomes

EPC Contract

• General Electric selected as EPC preferred bidder in May 2019

• Awarded after a highly competitive procurement process for turn key contract

Key Areas of Progress in 2018-19

Major Milestones So Far

Project Agreements Effective Date May-2018

Receipt of EPC Technical Proposals Dec-2018

EPC Selection Announcement May-2019

Signing of EPC contract Q3 2019

KosovoGeneral Electric Selected as EPC Preferred Bidder; Resignation of Prime Minister Creates Potential Delay

Financing

• Financing consists of a mix of Development Finance Institutions (“DFI”) and Export Credit Agencies (“ECA”)

• ECA is driven by EPC bidder selection. ContourGlobal engaged with multiple parties

Page 19: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

19

Renewable UpdatesFurther Growth with both Strategic Projects and M&A. Successful Refinancing at Solar Assets

Installed Capacity(1) : 1,820 MW Adjusted EBITDA H1 2019: $214m

(1) As of June 2019, including Solar Italy Interporto acquisition(2) Feed in tariff (3) Assuming consistent amount of debt

Austria Wind Repowering

• Phase 1 (30 MW): Repowering of Velm (13 MW) reached COD on 31st Jan 2019 on time and below budgeted cost, with FiT secured for 13 years;

• Scharndorf (17 MW) to complete in H2 2019 / H1 2020 , with FiT secured for 13 years

Solar Europe Growth

• Acquisition of a 12.4MW add-on Solar Italy asset completed in June 20 – rooftop PV solar portfolio with average remaining FiT² period of 13 years, located close to existing Northern Italy hub

• Strong Solar Europe pipeline identified for future growth

Vorotan Refurbishment

• Electro-mechanical refurbishment and modernization program started in 2017 to improve operational performance, safety, reliability and efficiency of Vorotan. Initial phase has been completed and the project is on track with completion expected in 2020, ahead of original schedule and on budget

• Total $71.5m investments: electrical part funded by a €51m loan with a Development Finance Institution and additional civil works at $13.5m are funded by company’s operating cash flow

• Civil works to be entitled to a reimbursement and a regulated unlevered return through an adjustment to the tariff

• Expected Results: Vorotan EBITDA increases by approx. $7m from 2019 to 2021

Solar Italy and Solar Slovakia Refinancing

• Refinancing of Italian and Slovakian solar businesses in two separate financings• €196m refinancing in Solar Italy – increased tenor by 2.7 years from 8.9 years to 11.6

years and reduced interest costs by 1.49% p.a. (incl. breakage costs) from 4.14% to 2.65%

• €51m refinancing in Slovakia – increased tenor by 1.4 years from 5.4 years to 6.8 years and reduced interest costs by 1.95% p.a. (incl. breakage costs) from 4.48% to 2.53%

• €4m interest savings on an annualized basis³

Page 20: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

20

Thermal UpdatesContinuation of established projects across geographies: Battery Upgrade Project implemented in Bonaire, serving as Pilot Project for future growth

Installed Capacity(1) : 3,027 MW Adjusted EBITDA H1 2019: $161m

(1) As of June 2019, including Mexico CHP and Cogeneration Assets(2) Reliability charge is a regulated fixed monthly fee to incentivize base load plants to be available

• With the acquisition of Bonaire in 2013, the company moved into a newhybrid technology and gained further expertise in battery storage withoutassuming construction risk

• In 2018 we commenced an innovative battery replacement and hybridexpansion project, which will enable us to integrate more wind energy intothe system and further reduce costs to the island customers

• Project status:

• Phase 01: Successfully implemented 6 MW/MWh Battery upgradeproject in Q1 2019. 7.7 GWh production increase

• Phase 02: Replace rented engines and ensure security of supply andgrid stability COD in Nov 2019

• Phase 03: 10 MW PV plant, 7-10 MW wind park expansion andadditional battery capacity

• Expected Results: Upon completion, the project will increase the energyproduction in line with growing energy demand on the island, achieve furtherenergy tariff reductions and increase the renewable mix on the island.Moreover, ContourGlobal will become the sole power producer on theisland.

Bonaire Hybrid Concept, a 24

MW integrated Wind, Diesel and Battery Power Plant

TermoemCali Reliability

charge assignment

extension and refinancing

• $80m refinancing: $45m long term and $35m working capital facility completed following Reliability Charge2 (the primary source of EBITDA for this peaker CCGT plant) assignment extension until November 2023.

• Optimizes capital structure and demonstrates long-term positive outlook for the asset post current regulatory period

Page 21: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

21

Appendix

21Sao Domingos II Hydro Power Plant (Brazil)

Page 22: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

22

17%

15%

6%

17%

14%

23%

8%

Coal Natural Gas

Fuel oil High Efficiency Cogen

Wind Solar

Hydro

Maintaining a Diversified Footprint Across Geographies and Technologies

LTM H1 2019 PF EBITDA by Technology1

LTM H1 2019 PF EBITDA by Currency1

LTM H1 2019 PF EBITDA by Geography1

(1) PF for full year EBITDA of Mexican CHP acquisition signed in January 2019 ($110m) and Solar InterPorto acquisition completed in June 2019 ($6m). Split excludes Thermal and Renewable HoldCo expenses and gain on CSP and Solar Italy and Slovakia farm downs

53%

11%

36%

Europe Africa Latin America

54%31%

13%

2%

EUR USD BRL Other

Renewable45%

HE Cogen17%

Thermal38%

Page 23: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

23

+$95m: Growth driven mainly by the CSP acquisition (full 6 months), CSP farm down and higher resource partially offset by negative FX impact due to weaker EUR and earn-out payments to make to Credit Suisse related to Italy farm down (non cash in H1 2019)

+$7m: In H1/2018, related essentially to all CSP acquisition costs (M&A closed). In H1/2019, related essentially to Mexico CHP (M&A not yet closed)

+$46m: CSP farm down net profit ($52m) partially offset by net amount of earn-outs on farm down of Italy and Slovakia ($6m)

+$25m: Largely driven by CSP acquisition (full 6 months)

+$21m: Increase in finance costs largely driven by (i) the Slovakian and Italian refinancings which required early settlement of the existing swaps ($11m) and immediate recycling to P&L of deferred financing costs ($4.2m, non-cash), and (ii) full six month impact of Spain CSP interests, partially offset by lower interests on the corporate bond following July 2018 refinancing.

Adj. EBITDA to Adj. Net Income1 Bridge

23

11

2

2

3

35

5

4

4

(1) Net income adjusted for one-off items

5

Adj. EBITDA to IFRS net income bridge (US$m) H1 2019 H1 2018

Adjusted EBITDA 357.2 261.8

Share of adjusted EBITDA in associates (10.1) (12.0)

Share of profit in associates 8.3 2.8

Acquisition related items (5.3) (12.3)

Costs related to CG Plc IPO - (0.8)

Cash gain on sale of minority interest (46.1) -

Restructuring costs (0.1) -

Private incentive plan (4.7) -

Other (1) (16.7) (19.2)

EBITDA 282.5 220.3

Depreciation & Amortization (131.5) (106.4)

Finance costs net (127.7) (107.0)

Income tax (17.2) (4.2)

Net Income 6.0 2.7

Bond refinancing one-off cost - -

CG Plc IPO costs - 0.8

Acquisition related items 5.3 12.3

Italian / Slovakian refinancing 15.4 -

Restructuring costs 0.1 -

Private incentive plan (non cash, non PLC cost) 4.7 -

Adj. Net Income 31.5 15.8

Minorities (8.1) (1.0)

Net Income attributable to Group 14.1 3.7

Page 24: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

24

Financial HighlightsKey financial metrics

24

Six months ended June 30 Var Var %

In US$ millions 2018 2019

Revenue 535 617 82 15.3%

Gross profit 144 171 27 19.1%

SG&A (22) (20) 2 (10.5%)

Adjusted EBITDA 262 357 95 36.4%

Proportionate EBITDA 226 300 74 32.6%

Operating profit 112 143 31 27.4%

Net finance cost (107) (128) (21) 19.4%

Income tax expense (4) (17) (13) 309.5%

Net profit / (loss) after income tax 3 6 3 122.2%

Basic earnings per share (pence) 0.01 0.02 0.01 110.4%

FFO 111 170 59 53.2%

Page 25: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

25

Contributors to Adj. EBITDA

(1) EBITDA is calculated by asset excluding corporate costs and thermal and renewable holdcos(2) Includes Solutions Europe and Africa and Solutions Brazil(3) Includes Solar Italy, Solar Slovakia, Solar Romania and Biogas Italy

25

Top Contributors to Adj. EBITDA1 2016 2017 2018 H1 2019

Top contributors from Thermal fleet

Maritsa East III 117 125 120 62

Arrubal 62 61 63 31

KivuWatt 22 24 26 12

Cap des Biches 12 26 27 14

Togo 21 25 25 13

CG Solutions2 12 27 27 10

Caribbean 21 27 24 12

Colombia 21 22 21 10

Others (0) 2 1 (0)

Top contributors from Renewable fleet

Spanish CSP - - 89 67

Brazil Wind 79 82 59 21

Solar Europe, excl. CSP3 31 31 41 23

Brazil Hydro 9 28 41 22

Peru Wind 31 25 29 15

Austria Wind 23 25 20 14

Vorotan 22 23 23 12

Others - - - (0)

Total 485 553 638 339

Page 26: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

26

Contributors to CFADS1

(1) CFADS (Cash Flows Available for (Corporate) Debt Service) as defined in Bond Indenture(2) Includes Solar Italy, Solar Slovakia and Solar Romania(3) Includes Solutions Europe and Africa and Solutions Brazil(4) 2018 and LTM H12019 not including thermal and renewable holding costs

4

26

Contributors to CFADS(Before Corporate and Other Costs)1 2016 2017 20184 LTM H1 20194

Spanish CSP - - 35 75

Solar Europe excl. CSP2 22 55 38 61

Maritsa 118 30 65 34

Arrubal 19 28 18 29

Brazil Hydros (1) 55 14 23

CG Solutions3 28 41 15 15

Cap des Biches - 7 17 12

Peru Wind 23 5 15 12

Colombia 4 8 4 12

KivuWatt - - 4 8

Vorotan 111 13 9 5

Austria Wind 7 8 4 5

Togo 6 6 7 5

Caribbean 10 9 5 4

Brazil Wind 2 5 (0) (2)

Total 349 270 249 298

Page 27: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

27

1,196 1,132

1,587 1,712

2,399 2,222

2,029

345 341 456 476

614 580 567

3.5x 3.3x

3.5x 3.6x 3.9x 3.8x

3.6x

(0.5x)

0.5x

1.5x

2.5x

3.5x

4.5x

5.5x

-

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

Jun-16 Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19

NGPTI Prop. Adj. EBITDA (LTM)

Leverage Ratio Incurrence Level (5x max)

Leverage Ratio1 DSCR1

In $m or multiple In $m or multiple

Continued Strong Bond Credit Metrics7.4x DSCR & 3.6x Non-Guarantor Combined Leverage Ratio as of June 2019

27

(1) DSCR and Leverage Ratio (Non-guarantor combined leverage ratio) as defined in Bond Indenture. Please see slide 31 for calculation of Bond Indenture Leverage Ratio, including Proportionate Adjusted EBITDA and NGPTI (Non-Guarantor Proportionate Total Indebtedness) .

5x

202

301

237 232

291

203

251

32 33 41 41 43 34 34

6.3x

9.2x

5.7x 5.6x

6.8x

6.1x

7.4x

(0.5x)

0.5x

1.5x

2.5x

3.5x

4.5x

5.5x

6.5x

7.5x

8.5x

9.5x

-

50

100

150

200

250

300

350

400

450

500

Jun-16 Dec-16 Jun-17 Dec-17 Jun-18 Dec-18 Jun-19

CFADS (LTM) Annualized Debt Service

DSCR Incurrence Level (2x min)

2x

Page 28: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

28

Reconciliation of Bond Metrics to IFRS Financials

Bond metrics definitions use Proportionate Adjusted EBITDA (“PAE”) and Non-Guarantor Proportionate Total Indebtedness(“NGPTI”) to calculate leverage ratios. These definitions exclude Corporate Level Financings and Project Finance Subsidiaries(“PFS”) (projects not yet reached, or recently passed, COD). As of December 31, 2018, no project is treated as a PFS.

PAE (Proportionate Adjusted EBITDA)

• Includes our share in JVs (Sochagota & TermoemCali)

• Pro forma for acquisitions mainly relates to our acquisition of theSpanish CSP portfolio

NGPTI (Non-Guarantor Proportionate Total Indebtedness)

• Excludes debt at parent company level (corporate bond)

• Increase in gross debt and NGPTI relating to our acquisition ofthe Spanish CSP portfolio

28

Calculation of PAE ($m) Dec-18 LTM Jun -19

Income From Operations 262 293

Depreciation & Amortization 239 264

Share in JVs 21 19

Other 88 129

Adjusted EBITDA 610 706

Pro Forma Acquisitions 46 13

Project Finance Subsidiaries (PFS) - -

HoldCos & Other 20 21

Pro Rata Adjustment (97) (173)

PAE 580 567

Calculation of NGPTI ($m) Dec-18 Jun-19

Non-current Borrowings 3,287 3,342

Current Borrowings 273 260

Consolidated Gross Debt 3,560 3,601

Accrued Int & IFRS Adj. 53 41

Share in JVs 6 13

Project Finance Subsidiaries (PFS) - -

Peru Wind Letter of Credit 9 9

DSRA (185) (117)

Corporate Bond (860) (853)

Pro Rata Calculation (361) (665)

NGPTI 2,222 2,029

Page 29: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

29

Segment Facility / Project Name LocationGross Cap.

(MW)Number of

Assets Fuel Type1ContourGlobal

Ownership COD Power Purchaser PPA Expiration

Maritsa Bulgaria 908 1 Coal 73% 1978 NEK 2024

Arrubal Spain 800 1 Natural Gas 100% 2005 Gas Natural Fenosa 2021

TermoemCali Colombia 240 1 Natural Gas / Diesel 37% 1999 Various N/A

Sochagota Colombia 165 1 Coal 49% 1999 Gensa 20192

Togo Togo 100 1 Natural Gas / HFO / Diesel 80% 2010 CEET 2035

Cap des Biches Senegal 86 1 Oil /Natural Gas 100% Q2 2016 / Q4 2016

Senelec 2036

Energies Antilles / Energies St Martin

French Caribbean 35 2 HFO / LFO 100% 2000; 2003 EDF 2020; 2023

Bonaire Dutch Antilles 28 1 HFO / Wind 100% 2010 WEB 2025

KivuWatt Rwanda 26 1 Natural Gas 100% Q4 2015 EWSA (ex-Electrogaz & REC) 2040 (expected)

Total Thermal 2,388 10

Mexican CHP assets(5) Mexico 518 2 Natural Gas cogeneration 100% 2014/19 Mexican industrial/commercial N/A

ContourGlobal Solutions Europe – Nigeria –Brazil

132 11 Natural Gas / Diesel / LFO 100%;100%; 80% 1995-2015 Investment grade global industrial companies

2018-2032

Total Cogen 650 13

Chapada Complex Brazil 438 3 Wind 51%, 51%, 100% 2015; Q1 2016 CCEE; distribution companies 2035

Vorotan Armenia 404 1 Hydro 100% 1970 AEN 2040

CSP Portfolio Spain 250 5 CSP 100% 2010 CNMC 2034-2037

Hydro Brazil Brazil 167 9 Hydro 79%3 1963; 1992; 2009-2012

Distribution companies 2027-2042

Asa Branca Brazil 160 1 Wind 100% 2013 Distribution companies 2033

Austria Wind Austria 155 10 Wind 94% 2003-2014 OeMAG 2016-2027

Inka Peru 114 2 Wind 100% 2014 Distribution companies 2034

Solar Italy4 Italy 77 48 Solar 51% 2007-2013 Gestore Servizi Energetici S.p.A 2027-2033

Solar Slovakia Slovakia 35 3 Solar 51% 2010-2011 Distribution companies 2025-2026

Solar Romania Romania 7 1 Solar 100% 2013 Distribution companies 2028

Biogas Italy Italy 2 2 Biogas 100% 2013 Gestore Servizi Energetici S.p.A 2028

Total Renewable 1,809 85

Total portfolio 4,847 108

ContourGlobal Portfolio

Thermal Renewables

(1) HFO refers to heavy fuel oil, and LFO to light fuel oil. (2) CES has already signed 4 contracts to replace existing PPA, extending expiration to 2024, with an additional 5 year extension expected(3) Capacity weighted(4) Italian solar assets in 20 clusters. Includes InterPorto acquisition, which was completed in June 2019(5) Signed but not closed

29

Page 30: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

30

IR InformationNext Event & Contact Point

Date Event Location

8th August H1 2019 Results CallDial-in details available on

website

3 – 4th SeptGoldman Sachs EMEA

Leveraged Finance London

5 – 6th SeptJP Morgan European

High Yield and Lev Finance

London

12 – 13th SeptMorgan Stanley Power

and Utility Summit London

Alice HeathcoteSVP, CFO RenewablesEmail: [email protected]

or

[email protected]

Corporate Websitewww.contourglobal.com

Investor Relations www.contourglobal.com/investors

IR ContactNext IR Events

30

Web Resources

Page 31: H1 2019 Preliminary Results Presentation - ContourGlobal · 2019-08-08 · H1 2019 Results Presentation August 8, 2019. 2 Disclaimer The information contained in these materials has

For further information please visit www.contourglobal.com