Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
STEEL BUILDING BY
AT
FOR
(CONTACT)
Civil & Structural Engineers
50 Punari Street
Currajong, Qld 4812
Fax: 07 4725 5850
Email: [email protected]
ABN 341 008 173 56
Registered Chartered Professional Engineer Regn. No. 2558980
Registered Professional Engineer (Civil & Structural) QLD Regn. No. 9985
Registered Certifying Engineer (Structural) N.T. Regn. No. 116373ES
Registered Engineer - (Civil) VIC Regn. No. EC36692
Registered Engineer - (Civil) TAS Regn. No. CC5648M
Mr Timothy Roy Messer BE MIEAust RPEQ
Registered Professional Engineer 2558980
Signature ............................................................
Date ......................................
Registered on the NPER in the areas of practice
of Civil & Structural National Professional
Engineers Register
FD
S
YR
WG
16
12
8
1/6
/2
02
0
TM
6
2
STEVE HANLEY
MCCARTHY STREET
MULWALA
MCBURNIE GROUP
03 57441111
1/6/2020
20
19
X BRACING IS REQUIRED IN 3 SIDE BAY(S) AND 1 ROOF BAY(S) (BOTH SIDES).
FLY BRACING IS INCLUDED TO BE PLACED ON EVERY SECOND PURLIN AND GIRT ON ENDWALL MULLIONS, INTERNAL COLUMNS AND INTERNAL RAFTERS.
SCALE:
SIDEWALL EXTERIOR ELEVATION1
2
1 = 200
ROOF PURLINS PER
MEMBER SCHEDULE ON
SHEET 5
SCALE:
SIDEWALL EXTERIOR ELEVATION2
2
1 = 200
ROOF PURLINS PER
MEMBER SCHEDULE ON
SHEET 5
SIDEWALL GIRTS PER
MEMBER SCHEDULE ON
SHEET 5
SCALE:
ENDWALL INTERIOR ELEVATION4
2
1 = 200
ROOF PURLINS
PER SCHEDULE
WALL GIRTS PER
MEMBER SCHEDULE ON
SHEET 5
C
5
DK2
3063
437
T.O. CONCRETE
4500
1166
5666
TO PEAK
TO EAVE
C
5
B
5
5
E
SCALE:
ENDWALL INTERIOR ELEVATION3
2
1 = 200
ROOF PURLINS
PER SCHEDULE
WALL GIRTS PER
MEMBER SCHEDULE ON
SHEET 5
C
5
3063
437
4500
1166
5666
TO PEAK
TO EAVE
T.O. CONCRETE
C
5
B
5
5
E
1 2 3 4 56 7
8 9 10 11 12 13 14
STEEL BUILDING BY
AT
FOR
(CONTACT)
Civil & Structural Engineers
50 Punari Street
Currajong, Qld 4812
Fax: 07 4725 5850
Email: [email protected]
ABN 341 008 173 56
Registered Chartered Professional Engineer Regn. No. 2558980
Registered Professional Engineer (Civil & Structural) QLD Regn. No. 9985
Registered Certifying Engineer (Structural) N.T. Regn. No. 116373ES
Registered Engineer - (Civil) VIC Regn. No. EC36692
Registered Engineer - (Civil) TAS Regn. No. CC5648M
Mr Timothy Roy Messer BE MIEAust RPEQ
Registered Professional Engineer 2558980
Signature ............................................................
Date ......................................
Registered on the NPER in the areas of practice
of Civil & Structural National Professional
Engineers Register
FD
S
YR
WG
16
12
8
1/6
/2
02
0
TM
6
3
STEVE HANLEY
MCCARTHY STREET
MULWALA
MCBURNIE GROUP
03 57441111
1/6/2020
20
19
Refer to Sheet #4 for concrete specification.
SCALE:
INTERNAL FRAME SECTION1
3
1 = 100
5
B
A
5
5
F
5
Q5
P
COLUMN AND RAFTER SIZE
PER MEMBER SCHEDULE
ON SHEET 5
STEEL BUILDING BY
AT
FOR
(CONTACT)
Civil & Structural Engineers
50 Punari Street
Currajong, Qld 4812
Fax: 07 4725 5850
Email: [email protected]
ABN 341 008 173 56
Registered Chartered Professional Engineer Regn. No. 2558980
Registered Professional Engineer (Civil & Structural) QLD Regn. No. 9985
Registered Certifying Engineer (Structural) N.T. Regn. No. 116373ES
Registered Engineer - (Civil) VIC Regn. No. EC36692
Registered Engineer - (Civil) TAS Regn. No. CC5648M
Mr Timothy Roy Messer BE MIEAust RPEQ
Registered Professional Engineer 2558980
Signature ............................................................
Date ......................................
Registered on the NPER in the areas of practice
of Civil & Structural National Professional
Engineers Register
FD
S
YR
WG
16
12
8
1/6
/2
02
0
TM
6
6
STEVE HANLEY
MCCARTHY STREET
MULWALA
MCBURNIE GROUP
03 57441111
1/6/2020
20
19
NOTES:BRACING MATERIALS - THE SHED ERECTOR TO SUPPLY SPECIFIC BRACING.SUITABLE RIGID MEMBERS CAPABLE OF TENSION AND COMPRESSION OR OPPOSINGCHAINS OR OPPOSING LOAD RATED RATCHET STRAPS TO BE USED. (RIGID BRACINGAS SHOWN ON DIAGRAM) ROPE BRACING SUITABLE ONLY FOR SMALLER STRUCTURESIN IDEAL CONDITIONS.
BRACING LOCATION - TEMPORARY BRACING TO BE ERECTED AS CLOSETO 45 DEGREE ANGLE AND FIXED TO THE TOP OF THE COLUMN OR MULLION TOACHIEVE THE OPTIMUM EFFECTIVENESS. IF THERE IS NOT ENOUGH SPACE FOR A45 DEGREE ANGLE, THEN 20 DEGREE ANGLE IS TO BE THE MINIMUM ANGLEALLOWED (REFER TO DIAGRAM). RIGID TEMPORARY BRACING MEMBER TO BE BOLTEDTO HEAVY ANGLE PEGS HAMMERED INTO THE GROUND OR TO A BRACKET, MASONRYANCHORED TO THE SLAB.
BRACING REMOVAL - TEMPORARY BRACING TO REMAIN IN PLACE UNTILCLADDING IS FULLY INSTALLED WHERE POSSIBLE. IN NO CASE SHOULD TEMPORARYBRACING BE REMOVED UNTIL ALL PURLINS, GIRTS (AND PERMANENT CROSS BRACINGWHERE USED) ARE FIXED.
SITE SAFETY - DUE CONSIDERATION TO BE GIVEN TO SITE SAFETY IN REGARDTO LOCATIONS OF BRACING AND PEGS.
GUIDE APPLICATION - TEMPORARY BRACING AS DESCRIBED IS A MINIMUMREQUIREMENT FOR AN AVERAGE, STANDARD SITE CONDITION. PROVIDE ADDITIONALBRACING FOR MORE SEVERE AND/OR HIGH EXPOSURE SITE CONDITIONS.ADDITIONAL BRACING TO BE USED AS AND WHERE NECESSARY TO ENSURE THATENTIRE FRAME IS RIGID THROUGHOUT CONSTRUCTION.RESPONSIBILITY FOR ENSURING STABILITY OF STRUCTURE REMAINS WITH THE BUILDER.
TILT UP METHODFOR STRUCTURES UNDER 9M SPAN, LESS THAN 3M HIGH AND LESS THAN 12M LONG
A. ASSEMBLE THE FIRST SIDEWALL FRAME (COMPLETE WITH WALL SHEETING, BRACING AND GUTTER) ON THE GROUND AND LIFT ASSEMBLED SIDEWALL FRAME INTO POSITION. FIX OFF TEMPORARY SIDE BRACING TO EACH END (REFER TO DIAGRAM). FIX BASE CLEATS.B. ASSEMBLE THE SECOND SIDEWALL FRAME AS PER FIRST SIDEWALL FRAME. LIFT INTO POSITION. FIX OFF TEMPORARY WALL BRACING TO EACH END (REFER TO DIAGRAM) FIX BASE CLEATS.C. FIX GABLE END RAFTERS TO COLUMNS TO TIE WALLS. PROP APEX UNTIL ENDWALL MULLION AND APEX TEMPORARY BRACE ARE FIXED OFF. IF NO MULLION IS REQUIRED THEN PROP AND BRACE APEX UNTIL CLADDING IS COMPLETE.D. INSTALL REMAINING RAFTERS. AS EACH RAFTER PAIR IS INSTALLED, AT LEAST ONE PURLIN PER 3M OF RAFTER LENGTH IS TO BE INSTALLED TO SECURE RAFTERS.E. INSTALL REMAINING PURLINSF. INSTALL KNEE AND APEX BRACES IF AND WHERE APPLICABLE.G. REPEAT FOR LEANTO'S.
FRAME FIRST METHODFOR STRUCTURES OVER 9M SPAN, GREATER THAN 3M HIGH AND GREATER THAN 12M LONG
A. ASSEMBLE PORTAL FRAMES ON THE GROUND (WITH KNEE AND APEX BRACES IF AND WHERE APPLICABLE). LIFT THE FIRST PORTAL FRAME ASSEMBLY INTO POSITION. FIX OFF TEMPORARY END BRACING (REFER TO DIAGRAM). FIX BASE CLEATS.B. PROP APEX UNTIL ENDWALL MULLION AND APEX TEMPORARY BRACE ARE FIXED OFF. IF NO MULLION IS REQUIRED THEN PROP AND BRACE APEX UNTIL CLADDING IS COMPLETE.C. THE SECOND PORTAL FRAME ASSEMBLY TO BE LIFTED INTO POSITION. FIX EAVE PURLINS AND AT LEAST ONE PURLIN PER 3M OF RAFTER TO SECURE FRAME ASSEMBLY. FIX BASE CLEATS. FIX TEMPORARY SIDEWALL BRACING.D. STAND REMAINING PORTAL FRAME ASSEMBLY AS PER STEP C, FIXING TEMPORARY SIDE WALL BRACING TO EVERY SECOND BAY. BRACE OTHER END PORTAL FRAME AS PER FIRST PORTAL FRAME.E. INSTALL REMAINING PURLINS AND GIRTS.F. REPEAT FOR LEANTO'S.
TILT UP METHOD DIAGRAM
1
1
FRAME FIRST METHOD DIAGRAM
1
2
GUIDE TO THE INSTALLATION OF TEMPORARY BRACING(REFER TO INSTALLATION GUIDE MANUAL FOR THE TWO METHODS OF CONSTRUCTION)
FIRST SIDEWALL FRAME
1
1A
SECOND SIDEWALL FRAME
1
1B
FIRST & SECOND PORTAL FRAME ASSEMBLY
1
2A
COMPLETE PORTAL FRAME ASSEMBLY
1
2B
TILT UP METHOD DIAGRAM
1
1C
TEMPORARY BRACING LOCATION
FRAME FIRST METHOD DIAGRAM
1
2C
TEMPORARY BRACING LOCATION
STEEL BUILDING BY
AT
FOR
NOT PART OF COUNCIL APPLICATION DOCUMENTATION
IF YOU HAVE A ROLLER DOOR IN THE GABLE END OF YOUR SHED, CONTACT YOUR
DISTRIBUTOR TO SEE IF MULLION NEEDS TO BE ROTATED FOR USE AS A DOOR JAMB.
FD
S
YR
WG
16
12
8
1/6
/2
02
0
TM
STEVE HANLEY
MCCARTHY STREET
MULWALA
MCBURNIE GROUP
03 57441111
BOLT LAYOUT PLAN
SCALE:
BOLT LAYOUT PLAN1
1
1 = 200
27500
12000
12000
BD
4000 3900 3900 3900 3900 3900 4000
C
3152
3152
2848
2848
2848
2848
3152
3152
5000
5000
H
K
2500
2500
2500
2500
SLAB EDGE
COLUMN
BASE PLATE
DETAIL B
104
102
163
243
SLAB EDGE
COLUMN
BASE PLATE
DETAIL C
102
163
243
66
C FRAME
L
BASE PLATE
COLUMN
SLAB EDGE
DETAIL D
102
1632
43
59
SLAB EDGE
COLUMN
BASE PLATE
DETAIL H
104
102
163
243
C FRAME
L
BASE PLATE
COLUMN
SLAB EDGE
DETAIL K
102
163
243
59
Proposed Plans - 67 McCarthy Street MULWALAApplication Form - 67 McCarthy Street MULWALAStatement of Environmental Effects- Shed 467 sqm- Industrial - 67 McCarthy Street MULWALA 2647 - S & J Hanley Investment Pty Ltd