Guardrail Basics for Design and Construction Scott Keller MDT Conference January 2007 “You Could Learn a Lot About Guardrail From a Dummy….. (and his crash

Embed Size (px)

Citation preview

  • Slide 1

Guardrail Basics for Design and Construction Scott Keller MDT Conference January 2007 You Could Learn a Lot About Guardrail From a Dummy.. (and his crash tests) Slide 2 Why Guardrail? The main purpose of guardrail is to reduce the potential for, and severity of accidents involving vehicles that leave the road Slide 3 Slide 4 Guardrail Saves Lives Just ask this guy! Slide 5 Statistics u Approximately 42,000 fatalities on U.S. highways annually u Nearly 12,000 of these occur as a result of run-off-the-road (R.O.R.) accidents u Approximately 1,200 of the R.O.R. fatalities are caused by guardrail as the first harmful event Slide 6 Is Guardrail A Hazard? A guardrail installation is a hazard when... Slide 7 Blunt End - Flared Terminal Slide 8 Disastrous Results with BCT Slide 9 Modified Eccentric Loader Terminal (M.E.L.T) Slide 10 Turndown Approach Terminal Slide 11 Blunt End - Bridge Transition Slide 12 Guardrail Is Often A Hazard Since Guardrail itself is a hazard, it should be used only as a last option. Before using guardrail: u Remove the hazard completely (Trees, Large Rocks, etc.) u Eliminate the hazard (fill depressions, holes, etc.) Then, and only then: u Protect the hazard with barrier u Use the minimum amount of barrier required to protect hazard u Protect the barrier end with an approved end terminal Slide 13 AASHTO Roadside Design Guide Slide 14 Example of simple barrier installation guideline Slide 15 Federal Highway Administration (FHWA) Policy requires the following roadside safety features used on the National Highway System to meet the performance criteria of NCHRP Report 350 u Traffic Barriers u Barrier Terminals u Crash Cushions u Bridge Railings u Light Pole Supports u Sign Post Supports u Work Zone Hardware Slide 16 What is the NCHRP Report 350? Slide 17 NCHRP Report 350 is the research report adopted by FHWA as the standard for determining safe and acceptable performance of roadside features for use on the National Highway System. Slide 18 What types of longitudinal guardrail, guardrail end terminal and crash cushion installations are NCHRP 350 approved? http://safety.fhwa.dot.gov/programs/roadside_hardware.htm Slide 19 Longitudinal Barriers Slide 20 NCHRP Report 350 Test Levels For Longitudinal Barriers Slide 21 NCHRP 350 Approved and Non-Approved Guardrail (Concrete Barrier Rail not shown) Slide 22 Guardrail on Steel Post with Steel Block Slide 23 Guardrail on Wood Post and Wood Block Slide 24 Guardrail on Steel Post with Wood Block Slide 25 Guardrail on Steel Post with Plastic Block Slide 26 W-Beam Grading Requirements: Provide 10:1 or flatter slopes in front of rail and terminal sections. Provide two feet (600 mm) of soil behind the posts to develop adequate soil resistance. Use new 7 foot (2.1 M) posts with half-post spacing design in areas that you cannot provide two feet (600 mm) of widening. (See Dtl. Drwg. No. 606-11A and 606-11B) Slide 27 Plant Mix Overlays and W-Beam Guardrail Three inch (75 mm) tolerance on height of rail Replace rail when the overlay exceeds 0.25 feet or 75 mm in thickness Slide 28 Guardrail End Terminals Slide 29 1994 FHWA Memorandum Dean Carlson, Executive Director some obsolete roadside hardware or poor practices thought to have been upgraded or eliminated still remain on the Nations main roadway systems ...FHWA has a responsibility to identify hardware designs and practices that are no longer acceptable for specific conditions the following nationwide traffic barrier upgrading issues, most of which involve terminals, are identified as needing attention: u Replacement of Blunt End Terminal u Use of Turn-Down Terminals u Breakaway Cable Terminal (BCT) u Terminal Replacement Slide 30 1994 FHWA Memorandum Dean Carlson, Executive Director Breakaway Cable Terminal (BCT) u The BCT does not pass 100 km/hour testing with the 820 kg car. u Use of BCT no longer accepted for installation after 1 year of referenced memorandum on the approach end of high speed, high volume roads on the NHS. u Existing BCT units should be replaced with crashworthy terminals when units are damaged, or when significant roadway work is done in the same area. Slide 31 NCHRP 350 Guardrail Terminal Test Matrix Slide 32 ET-Plus With Wood Posts Slide 33 Slide 34 Slide 35 ET-2000 with HBA Posts Slide 36 ET-PLUS and SKT 350 Advantages: u Softer Ridedown for smaller vehicles u Address Future Side-Impact Testing Criteria u Successfully Tested to NCHRP Report 350 Test Level 3 Criteria u Easier to install (New Heads are Lighter) Slide 37 ET-Plus with HBA Posts Slide 38 ET-Plus and SKT 350 Advantages: u NCHRP Report 350 Test Level 3 Approved u Wood Post or Steel Post Options u Tangent terminal reduces installation costs u Majority of parts are reusable after end on impact Slide 39 Impact Attenuators Slide 40 Crash Cushion Attenuator Test Matrix Slide 41 Slide 42 TRACC Advantages: u NCHRP Report 350 Approved: 6.4 Meter Length Test Level 3 (100 km/hour) u Majority of parts are reusable after end-on impact u All-steel construction extends product life and minimizes maintenance u Installed on Concrete or Asphalt Slide 43 Newest Tracc Family Member - Widetracc TL-3 Slide 44 Quadguard Advantages: u NCHRP Report 350 Approved: 6 Bay Design Meets Test Level 3 (100 km/hour) u Majority of parts are reusable after end-on impact u Collapsible cartridges extend product life and minimizes maintenance u Installed on Concrete or Asphalt Slide 45 QUEST is the newest MDT approved Impact Attenuator Very similar to TRACC in design and appearance Majority of parts are reusable after end-on impact All-steel construction extends product life and minimizes maintenance Slide 46 Transitions/ Bridge Approach Sections Slide 47 Concrete Bridge Transition Test Slide 48 MDT Detailed Drawings Guardrail W-Beam, Box Beam, Cable, and Concrete Barrier Rail Terminal Sections Bridge Approach Sections Impact Attenuators Guardrail Hardware Slide 49 Additional Information Scott Keller, P.E. MDT/MSU Design PO Box 174252 Bozeman, MT 59717-4252 (406) 994-1843