172
CPRI-Training Notes 1 Growth Of Powersector And Industry in India By G Venkatraman,Consultant-Cpri 1.0 Evolution Of Indian Power Sector Pre-Independence- Power Was Available In Small Pockets Of India; This Was More Visible In ‗Princely States‘ Owned By Maharajas; British Rulers Provided ‗Power Source‘ In National Capital And Selected Cities With Commercial Interest; Olliery Areas Were Provided With ‗Steam‘ Power Units; Other Sources Were ‗Dg‘ Units With Limited Ditribution Capability; Some Of The Big Industry E.G. Tata Steel Co. Jamshedpur Had Large Captive Plant (60mw); All Generators Were From ‗Great Britain‘ 2.0 Capacity And Energy- Comparison Installed Capacity In 1950- 1362 Mw Gross Energy Generation -4073 Mu Per Capita Consumption- 16.3 Units; Installed Capacity In 31/3/2011 182689mw; Gross Energy Generation 2010-11 789,013mu Per Capita Consumption In 2010-11 813.5mu; 3.0 Existing Power System Indiawas Declared A Sovereign Republic In 1950; There Were Number Of ‗Princely‘ Estates In 1955-60 Period Having Power Generation For Palace. The First Maharaja To ‗Join‘ The Republic Of India Was ‗Maharaja Of Mysore‘. He Donated His Asset Including Power Supply System For Development Purpose. All The Other Maharajas Followed On Same Line. The Existing Power Generation And Supply Network Was Extended To More Areas; Karnataka(Formerly Mysore) Was Getting Power From ‗Hydro‘ Generation Plants -‗Sharavati, ‗Jog‘ And ‗Linganmakki‘ Reservoirs; 4.0 Administrative Arrangement (Central Electricity Authority) The Central Electricity Authority Of India (Cea) Is A Statutory Organisation Constituted Under Section 3(1) Of Electricity Supply Act 1948, Subsequently Superseded By Section 70(1) Of The Electricity Act 2003. Cea Has Provided Advisory And Supervisory Support To Government On Matters Relating To

Growth Of Powersector And Industry in India - …bescom.org/wp-content/uploads/2015/03/CPRI-Training_Module2.pdfGrowth Of Powersector And Industry in India ... Mysore‘. He Donated

Embed Size (px)

Citation preview

CPRI-Training Notes

1

Growth Of Powersector And Industry in India

By G Venkatraman,Consultant-Cpri

1.0 Evolution Of Indian Power Sector

• Pre-Independence- Power Was Available In Small Pockets Of India;

• This Was More Visible In ‗Princely States‘ Owned By Maharajas;

• British Rulers Provided ‗Power Source‘ In National Capital And Selected

Cities With Commercial Interest;

• Olliery Areas Were Provided With ‗Steam‘ Power Units;

• Other Sources Were ‗Dg‘ Units With Limited Ditribution Capability;

• Some Of The Big Industry E.G. Tata Steel Co. Jamshedpur Had Large Captive

Plant (60mw);

• All Generators Were From ‗Great Britain‘

2.0 Capacity And Energy- Comparison

• Installed Capacity In 1950- 1362 Mw

• Gross Energy Generation -4073 Mu

• Per Capita Consumption- 16.3 Units;

• Installed Capacity In 31/3/2011 – 182689mw;

• Gross Energy Generation 2010-11 – 789,013mu

• Per Capita Consumption In 2010-11 813.5mu;

3.0 Existing Power System

• Indiawas Declared A Sovereign Republic In 1950;

• There Were Number Of ‗Princely‘ Estates In 1955-60 Period Having Power

Generation For Palace.

• The First Maharaja To ‗Join‘ The Republic Of India Was ‗Maharaja Of

Mysore‘. He Donated His Asset Including Power Supply System For

Development Purpose.

• All The Other Maharajas Followed On Same Line.

• The Existing Power Generation And Supply Network Was Extended To More

Areas;

• Karnataka(Formerly Mysore) Was Getting Power From ‗Hydro‘ Generation

Plants -‗Sharavati, ‗Jog‘ And ‗Linganmakki‘ Reservoirs;

4.0 Administrative Arrangement (Central Electricity Authority)

• The Central Electricity Authority Of India (Cea) Is A Statutory

Organisation Constituted Under Section 3(1) Of Electricity Supply Act

1948, Subsequently Superseded By Section 70(1) Of The Electricity Act

2003.

• Cea Has Provided Advisory And Supervisory Support To Government

On Matters Relating To

CPRI-Training Notes

2

National Electricity Policy

Formulates Short-Term And Long Term Perspective Plans For

The Development Of Electricity System.

Assessmentof Power Demandfor Concurrentnational 5 Yearplan;

5.0 National „5 Year Perspective Plan‟

Growth Of Power Generation Capacity

Plan Period Installed Capacity(Mw) At End Of Plan

Hydroonly Total % Of Hydro In Total

1st Plan(1950-56) 1061 2886 36.75

2nd

Plan(1956-61) 1917 4653 41.19

3rd

Plan (1961-66) 4124 9027 45.68

4th

Plan (1966-74) 6966 16664 41.8

5th

Plan (1974-79) 10833 26680 40.6

6th

Plan (1979-85) 14460 42565 3.96

7th

Plan (1985-90) 18307 63636 28.77

8th

Plan (1990-97) 21658 85795 25.24

9th

Plan (1997-02) 26269 105046 25.00

Ref Url:

Http://Www.Google.Co.In/Imgres?Imgurl=Http://Eai.In/Ref/Images/3.Jpg&Imgrefurl=

Http://Www.Eai.In/Ref/Ae/Hyd/Hyd.Html&H= 414&W=353&Tbnid=Da9rqq8-

Fkcsfm:&Zoom=1&Docid=Yytl-Gr584vudm&Ei=Vmoiu_Qpnynco4sdgegg&Tbm=Isch

6.0 Hydro‟ Plants–First Power Source

Some Of The Major Hydro Plants Which Were Established During 1955 And

1980 Period Are-

1. Bhakra-Nangal Project (Multi Purpose);

2. Rihand (Pipri) Project;

3. Obra Hydro Project;

4. Damodar Valley Project;

5. Bhadra Reservoir Project;

6. Hirakud And Rengali Dam Project;

7. Upper And Lower Silleru Hydro Project;

8. Koyna Project;

9. Nagarjunasagar Hydro Project;

There Are Many Other Projects In ‗Nort-East‘ And Other States, Not Listed Here.

CPRI-Training Notes

3

7.0 Adoption Of British Practice

• Indian Power System Adopted The Former ‗British‘ Standards I.E.

Power System Voltage Were Graded Into Levels Of 110kv, 66kv, 22kv, 6.6 Kv,

3.3 Kv And 3phase ‗Lt‘ System Was 415 & 230v (1ph).

Power System Frequency - 50hz;

• Machines And Equipment Of Earstwhile ‗British‘ Manufacturing Companies In

India Were Available With Indegenous Cpability.

• Gec, Biecco-Lawrie, Reyrolle-Burn Were Established Electrical Equipment

Manufacturers;

• National Level Industry Such As ‗Ngef‘, Bhel Were Established;

8.0 Formation Of „State Electricity Board

Prior To Formation Of Provinces/State On ‗Linguistic‘ Basis, The Administaration System

Was In The Form Of ‗Electricity/Power Department‘

i) On Formation Of Provinces/State‗State, ‗State Elctricity Board‘ Were

Constituted By Respective State Government;

ii) ‗Electricity‘ Was Deemed As Concuurent Subject Of ‗Centre‘ And ‗State‘.

This Enabled Respective States To Plan The Development Of All

iii) The Three Desciplines Of Power System I.E. Generation, Transmission And

Distribution Under ‗Singular‘ Administrative Board;

9.0 Demand Forecast Andconsumption

i) Electricty Being A ‗Non‘ Storable Commodity, The Production And

Consumption Is Simultaneous;

ii) Economy Of A Country Is Directly Dependent On Availability Of This

Commodity At Reasonable Cost And Quality; Per Capita Consumption Is

Another Index Of Propseprity Of The Country.

iii) The Two Parameters To Assess The Availability Of This Commodity Are ‗Load

Or Power‘ (In Watts) And ‗Energy‘ (Watt X Hour) ;

Both Are Interlinked But Need Separate Resource Provision;

‗Load Or Power Demand‘ Is Linked To System/Equipment Capacity At An

Instant;

‗Energy‘ Supply Is Linked To Serving All Consumers For The Total

‗Duration‘ (Hour, Month And Year);

10.0 National Power Survey‟ By Cea

The Main Objective Of This Survey And Prepare A Repot Is To:

1. Forecast Year Wise Electricity Demand For Each ‗State‘, Union Teritory,

Region And All India, In Detail Upto End Of The Next 5 Year Plan Period;

2. To Project Perspective ‗Electricity‘ Demand For The Terminal Years Of Two

Subsequent 5 Year Plan Durations;

3. The Demand Analysis And Forecast Would Thus Cover 15year Period.

(Example: 14th

‗Eps‘ Was For Year Wise Forecastin 11th

5 Year Plan Period

(2007-2012) And Total Electricity Demand Projection Upto End Of 2021-22).

CPRI-Training Notes

4

4. Model Used Is Called As ‗Partial End Use Method‘ (Peum);

- For The Assessment Of Load Demand, Capacity Addition Of Generator,

Transformer And Distribution Sub Stations Ineach State, Power Survey

Was Conducted By ‗Cea‘.

- Load Demand Input And Proposal For Establishing Power Stations In

Each State To Meet The Load, Provided By Each State;

Main 5 Heads In The Demand Group:

1. Domestic Consumer;

2. Public Lighting & Public Water Works;

3. Commercial & Misc. Consumers;

4. Irrigation Pumpset;

5. Indutrial (Ht & Lt) Load;

6. Railways Traction And Non-Industrial ;

10.0 Generation And Transmission Planning

Growth Of Installed Capacity Vs Generation

End Of Year Installed. Cap (Mw) End Of Year Installed. Cap (Mw)

1947 1362 1980 30283

1950 1713 1985 42710

1956 2813 1990 64112

1961 5063 1992 69915

1966 9583 1997 86337

1969 13703 2002 105456

1974 18282 2007 132329

1979 28484 2011 182689

Energy Produced Vs Per Capita Consumed

End Of Year (Mu)

Generation Per Capita Consumption

1950 5106 18.2

1956 9662 30.9

1961 16937 45.9

1966 32990 73.9

1969 47434 97.9

1974 66689 126.4

CPRI-Training Notes

5

1979 102523 171.6

1980 104627 172.4

1985 156859 228.7

1990 245438 329.2

1992 287029 347.5

1997 395889 46436

2002 517439 599.2

2007 624495 671.9

2011 789013 813.5

Growth Of 400 Kv „Ehv‟ System From Year 1978 Onwards

End Of Year

Growth Of Transmission System (Length In Kms.)

220 Kv 400 Kv 765kv Hvdc

'Bi Pole’ Total

2006 114629 75722 1704 5872 197927

During 2007-11 19561 26856 1636 1580 49633

Mar‘

2011 140757 114979 4164 9452 269352

11.0 Poor Health Of Power Sector

Some Reasons For Poor Health Of Indian Power System:

1. Exponential Demand Growth-Beyond Forecast

2. High Capital And Running Cost ;

3. Low Recovery Of Investment;

4. Fund Constraint In State And Centre;

5. High ‗T & D‘ Loss;

CPRI-Training Notes

6

6. Theft Of Power In Many States;

Solutions Proposed By Consultants And Committes

Implement ‗Power Reform‘–Administrative & Technical

Modify I.E. Act- ;

Introduce Regulatory Regime In Phases;

Invite Private Power Producer;

Appoint Electricity Regulator As ‗Neutral‘ Empire;

Unbundelling Of ‗Sebs‘ Into Separate Utilities;

Central Support In Rural And Urban Ditribution-Rggvy& Rapdrp Schemes;

12.0 Administrative Reform

Formation Of Central & State Level Regulatory Commissions.

13.0 Technical Reforms

1. Specification Of Equipment ‗Up-Graded‘ And Guideline Documents Prepared

By ‗Cea‘.

2. It Based System In Distribution Area;

3. Use Of ‗Scada‘ In Transmission System;

4. Introduction Of ‗Smart Grid‘ Concept In Entire Poewer Sector;

5. Use Of ‗Smart Meters‘ And Pre-Paid Meter System By Utilities;

6. Installation Of ‗Uhv‘ And ‗Ehv‘ Transmission System And Integration Of 4

Regions In Synchronous Mode;

7. ‗Abt‘ Metering System Usage For Better ‗Grid‘ Discipline;

8. Integration Of Renewable Energy (Wind,Solar Etc.) Into Grid;

CPRI-Training Notes

7

Electricity Distribution in India, private participation in Distribution reforms

P.ChandhraSekhar, CPRI, Distribution Systems Division, Bangalore

1.Introduction- Distribution

The overall quantity of electricity expended per head in the country was 600 kWh. The industrial

sector accounted for about 35.6% of the total expenditure. The domestic segment used up

around 24.8% of the electricity. Consumption by the commercial and the agricultural sector

stood at 8.1% and 22.9% individually. The normal per capita consumption came to about 600

KWH.Along with economic growth and a reduction in the below the poverty level populace, the

per capita electricity spending is sure to rise. Therefore, in order to support a rate of growth

of GDP of around 7 percent per annum, the rate of growth of power supply needs to be over

10 percent annually. The govt. enunciated policy in 1991, allowing private enterprise a larger

role in the power sector.

In the last few years, the focus of the debate and action on power sector reforms

has shifted from generation to distribution side.Several committees, policy documents, and

reform plans have espoused the need for privatization of distribution and have suggested

several actions in terms of legislative and regulatory changes to make privatization of

distribution successful.

The Electricity Act 2003 (EA 2003) is a major step forward to improve and speed up

the power sector reforms in India. Post EA 2003 the power industry has opened up in

generation, transmission, and distribution sector. The opportunities are as follows.

1 .1 Opportunities

The opportunities in the Power Industry in India during Post EA 2003 as follows:

1.1.1 DE licensing of Generation Project

CPRI-Training Notes

8

Generation projects de-licensed subject to meeting the criteria laid out in National

Policy

No TEC clearance required for any thermal generation projects and for hydel upto

500 MWCaptive plant freed from licensing

1.1.2 Open Access

Distribution along with Generation gives lot of opportunities for investors having

CPP to use the open access transmission system

Different entities with varying business models will emerge and will be prospective

participants in the market

Surcharge for meeting the cross subsidy will not be livable in case of open access,

ifProvided to a person who has established CPP for carrying electricity to the

destination of his own use

1.1.3 Multiple Licenses

Multiple licensees allowed distributing electricity within the same distribution circle

Distribution licensee does not require a separate trading license

A consumer could source power from any person other than the Licensee of that

area on payment of additional surcharge

No license is required for generation as well as distribution in forward rural areas

1.1.4 Distributed Generation

The Act gives a freedom to set up own Captive Power Plant and Distribute Electricity

in rural areas as notified by the Govt. without license. This gives huge investment

opportunities to small entrepreneurs for setting up generating plants and distributes

electricity as a lot of risks are mitigated. The excess power can be sold to third party.Rural

Energy Systems will emerge, enabling entities like Users Associations / Co-operatives to also

support trading at local levels.

1.1.5 Antitheft Legislation

CPRI-Training Notes

9

The provision for antitheft legislation will help in reducing the commercial losses of

the utilities and gives a boost to possible investors who were earlier hesitant to invest in this

sector.

1.1.6 Franchisee

A distribution licensee can distribute electricity through another person within its

distribution area. This will make way for micro distribution system concept through

franchisees.

1.1.7 Market Challenges Competition& Risks

The market challenges in terms of competition and risks involved in the Power

Industry for BESCOM in the Post EA 2003 scenario are explained below in table 1.1 and table

1.2.

1.1.7.1 Competition

Table 1.1:Product Differentiation-Competition

Major Competitor Product/

services

PRODUCT DIFFERENTTIATION

BESCOM Competitors

Captive Generation by High value consumers

Electricity Grid support and multiple power sourcing avenues.

Lesser reliability and concerns of stranded /suboptimal investment. Promotes the concept in

industrial circles of “Leaving the non-core

activities”

No / Low entry

barriers (Sec 9 of

EA 2003). Low cost without cross subsidy component in tariff(no surcharge of wheeling)

No universal service

obligation

Retail competition -

Switchover of our

Consumers By way

of open access

Electricity Efficient consumer

service, Higher network

reliability & regulated tariff

to protect revenue

leakage through levy of

wheeling charges,

surcharge etc

Low cost and

possibility of offering

bundled services,

better branding

CPRI-Training Notes

10

Retail competition -

Switchover of our

Consumers - By

Parallel Network

Electricity Lower cost due to

depreciated asset & high

switchover cost to

consumer in terms of

additional surcharge

Higher reliability and

efficient system

parameters like

voltage etc

1.1.7.2 Risks

Major risks with their impact and action plan for mitigation of those risks are shown in

tabular form below:

Table 1.2:Product Differentiation-Risks

Major Risks Impact ( Nature and Time of Incidence )

Operational

Performance Risk

T& D loss estimation Methodology

Non achievement of targeted AT & C loss reduction levels

Delay in completion of identified projects & augmentation works

Regulatory Risk in

terms of Tariff setting

Lower Rate of Return (lower or non-admissibility of a particular costcomponent in the Annual Revenue Requirement (ARR) – an exercise undertaken annual)

Availability of cash for Appropriation of Dividend after providing for deferred tax & Depreciation

Financial Risks Funding for Capex scheme

Loan Repayments after 5 years

Transitional Support - inadequacy of Govt. Subsidy – may put pressureon assured 16% RoEExtent of Revenue gap

Govt. Support RoW permissionLandLaw & Order situation

Transmission &

Supply Risks

Shortfall in Quantity of electricity required for the licensed areaHigher price for incremental power

Others – UI, Reactive charges etc

CPRI-Training Notes

11

Market Risks Decrease in overall revenue due to competition in retail supply and/or increased Captive Generation by high value consumers

Inadequate cost recovery including reasonable return due to decreased sales volume because of adverse consumer mix and/or some

Buyers shifting to other Retailer/ Licensee as and when open access is introduced in distribution segment

Quality of Manpower Sub- optimal cost centers

Senior Management Capability

Risks arising out of

mis-interpretation/gaps in

Transfer scheme

Unfunded liability arising out of VRS in Pension Trust

Exhaustion of Transitional Support - inadequacy of Govt. Subsidy Land & RoW requirement

2. Distribution Performance Parameters

The functional areas for performance parameters are proposed as follows:

2.1Operational Performance:The availability, reliability, and quality of power

Delivered to consumers, provision of maintenance and repair services, and level of

Technical and commercial losses.

2.2Customer Service: Provision of key customer services such as connection

Services, handling of complaints, consumer education activities, testing services,

DSM programs.

2.3.Metering, Billing and Collection: Extent and accuracy of metering, billing

Practices, collection efficiency, arrears on receivables.

2.4.Financial Performance and Competitiveness: Cost recovery, profitability, level

of capital investment (and reinvestment), and comparative tariff levels.

2.5.Operational Cost Control:Total cost of distribution services, staffing levels and

labor costs, other operating and capital costs, inventory management.

CPRI-Training Notes

12

The following parameters will be evaluated in the Distribution Business as shown in Table 1.3 .

Table 1.3: Performance of parameters

Area Performance Measure Effect Measured Data Source

Op

erat

ion

al P

erfo

rman

ce

SAIFI Frequency of outages Sub Station Logs

SAIDI Duration of outages Sub Station Logs

CAIDI Duration-Frequency Sub Station Logs

Aggregate technical &

commercial losses

Effectiveness in

minimizing

unrecoverable energy

cost

Reports to regulators

or internal

Technical losses Efficiency of

distribution

infrastructure

Substation energy

audits/load flow

studies

Unplanned outages/total

outages

Relative impact of

outages

on customers and

system

Substation reports

Service restoration time

distribution

Responsiveness of

maintenance

Substation, district

serv.

logs

Annual replacement rate of

distribution transformers

(%)

Role of transformer

failures

in maintenance effort

Maintenance and

equipment records

Area Performance Measure Effect Measured Data Source

Cust

om

er

Ser

vic

e

Lead time for new

connections

Responsiveness and

service

orientation of

connection

services

Customer account

records

Lead time to test/replace

meters in case of complaint

Commitment to

metering

accuracy

Customer account and

meter service records

Response time from fault

complaint to service visit

Effectiveness of

complaint

response

Customer account and

service records

CPRI-Training Notes

13

Customer care personnel

per customer

Adequacy of customer

service resources

Employment records

Employees providing

special services per 1000

customers

Provision of value-

added

services to customers

Employment and

special program

records

Area Performance Measure Effect Measured Data Source

Met

erin

g,

Bil

lin

g a

nd

Co

llec

tio

n

Metered customers/total

customers

Ability to bill

consumers for

energy consumption

Aggregated reports or

customer account

records

Meters/meter reader Adequacy of resources Employee records

Frequency of meter/seal

inspection

Control of tampering

and

maintenance of

accuracy

Service and customer

account records

Meters replaced/meters in

service

Adequacy of meter

technology

Service records

% of bills that are

estimated

Billing accuracy Meter reading/billing

policy

Time lag between meter

reading and bill dispatch

Billing efficiency Billing reports and

records

Ave level of customer

arrears

Collection efficiency Accounting records

Area Performance Measure Effect Measured Data Source

Co

st a

nd

Man

agem

ent Distribution cost/unit Operating efficiency

and cost

reasonableness

Financial reports

Functional shares of non-

energy

distribution costs:

admin, maintenance,

equipment, etc.

Norms of cost

allocation

Cost accounting

reports

Total labor cost/customer Labor cost efficiency Financial reports

Employees/customer Employment level

norm

Employment records

Training participant

days/employee-year

Adequacy of training Human

resource/training

records

Sick and injury

days/employee

Safety practices Human resource

records

Area Performance Measure Effect Measured Data Source

Fin

anci

al

Per

form

anc

e

Average tariff levels by class Competitiveness Tariff sheets, internal

reports

Cost recovery (op

revenue/cost)

Sustainability of cost

levels/ tariffs

Financial reports

Ave capital exp/net asset

value

Capital sustainability Financial reports

Customer

receivables/monthly

revenue collections

Cash flow

management

Internal accounting

reports

CPRI-Training Notes

14

Commercial losses (% of

sales)

Control of theft and

unaccounted losses

Reports on AT&C

losses and estimates

of

technical losses

CPRI-Training Notes

15

3. Distribution Business Models:

The Distribution franchise model is a public private Partnership Initiative (PPP) that has emerged as a solution to the problems affecting the Power Distribution business –high technical and commercial losses, Poor Infrastructure, weak financial position and lack of customer orientation. The model as evolved as a means to break the vicious cycle of low realisation, low investments, low consumer satisfaction and in turn low realisation. The first input and investment based distribution franchise model has been implemented in the bhiwandi circle in Maharastra with exemplary success.

3.1 Challenges:

Despite Bhiwandi’s exemplary success ,the progress in distribution franchising is very slow.The following are the two major factors that are hampering the progress and the solutions that can be implemented to overcome the challenges.

3.1.1 Inadequate Power Supply:

Although the distribution franchise model aims to cut distribution losses and improve customer service, the franchisee dependent on the utility of electricity supply.The licensee usually guarantees usually to provide the same volume of energy that was supplied in the previous year, thud lending an element of certainty to the franchisee’s business model.

Most states in India face electricity shortages .Despite the guaranteed quantum of electricity supply, there are shortfalls and the distribution franchisees have to resort to loading .Thus the objective of improvement in customer service is only partially achieved.

Going forward, a key driver will be the ability of the distribution franchisee to bring in additional power supply. A model under which the franchisee required to achieve 100 percent supply levels ( By sourcing additional power ) in the medium term (Two to three years) will find favour with the franchising utility as well as the consumers. Thus it can be a preferred model and provide impetus to distribution franchising .

This revised model would open up new opportunities for players that are backward integrated into generation and /or have the ability to source additional power.The power generated /sourced by them will find a captive market and thus de risk the business models in the long run.

3.1.2 Rehabilitation of the existing employees of the Utility

Another major impediment is rehabilitation of the licensees existing employees in the area to be franchised. While the franchise model in the current form addresses the concerns of the consumers, the licenses and the franchisee .the concerns of the existing employees are not addressed effectively. Since it is not obligatory for the franchisee to take on the existing employees of the utility. Most of the staff has to be transferred to the other distribution areas under the utility.

The utility and the franchisee need to work together to ensure that the majority of the existing employees can be absorbed in the same area through training and reskilling. Further the utility

CPRI-Training Notes

16

should work out a compassionate transfer process for the employees who are to be transferred to other areas. This will ensure acceptance amongst the utilitys employees and smooth transition.

4. Concept of AT&C loss& its impact on Business :

The following are the different losses evaluated in the distribution system

4.1 Technical losses: Every element in a power system- a line- a transformer etc. consumes some energy because of its inherent property while performing their expected duty. Cumulative energy by all these elements constitutes technical losses i.e I2R losses. These losses cannot be avoided completely from the system but may be reduced as far as possible by improving the ST&D system. Some of the major reasons for the technical losses to occur in the system are mentioned below

• Lengthy Distribution (11 KV & LT) lines

11 KV & LT lines are extended for unduly long distances in Rural Areas (low load density)

• Inadequate Conductor sizes

Initially lower size conductors not replaced with load growth. • Haphazard and adhoc planning ignoring scientific methods • Wrong location of DTRs with incorrect ratings • Low power factors – no control over reactive power • Low voltage pockets • Bad workmanship

4.2 Commercial losses: These losses occur on account of following

Non performing meters

Under performing meters

Meters not read

Application of lower multiplication factors

Pilferage by manipulation

Theft by direct tapping etc.

Here it is to mention that many distribution companies across the country are adopting the approach of “100% consumer metering and Total Energy Audit” to curb thecommercial loss. While load flow analysis is universally used for technical loss estimation, the commercial loss is obtained by subtracting technical loss from the total loss .

AT&C losses:

=(1- billing Efficiency x collection efficiency ) * 100

= Billing Efficiency:Energy Billed

Input Energy ∗ 100

CPRI-Training Notes

17

= Collection Efficiency: Revenue Collected

Amount Billed ∗ 100

High technical losses in the system are primarily due to inadequate investments over the years for system improvement works, which has resulted in unplanned extensions of the distribution lines, overloading of the system elements like transformers and conductors, and lack of adequate reactive power support.

The commercial losses are mainly due to low metering efficiency, theft & pilferages. This may be eliminated by improving metering efficiency, proper energy accounting & auditing and improved billing & collection efficiency. Fixing of accountability of the personnel / feeder managers may help considerably in reduction of AT&C loss.

It reduces the customer satisfaction level and poor investment in the distribution business .The utility will not be financially viable and Average Revenue Realisation will come down. The Average cost of supply will be increased. The overall brand image of the company will decrease.

5. References

1. Performance benchmarks for electricity distribution business in south asia(2004), Nexant

2. Technology: Enabling the transformation of Power Distribution, Infosys Report (2008)

3. Distribution Franchise, Evolution, Experience and outlook, Power line (2009)

4. www.Powermin.nic.in

Maintenance and diagnostic testing of Distribution Transformers By K.Mallikarjunappa, Joint Director,Central Power Research Institute, Bangalore

Introduction

Distribution Transformers form the largest population of transformers in the Electrical Power Supply network. The distribution Transformer is the last in the chain of electrical energy supply to the households and industrial enterprises. These transformers are installed in both rural & urban areas to supply electrical power. The distribution transformers serve the crucial function of transforming of high voltage (11kV) to lower values (433V) to meet the requirements of household appliances and industries.

Operational reliability of distribution transformers is most important for uninterrupted supply of electrical power. Improper use, maintenance and neglect can cause not only premature failure but also heavy financial losses to the distribution companies and inconvenience to the consumers.

The distribution transformers represent substantial capital investment for distribution companies and hence reliability is at most important to avoid loss of revenue resulting from premature failure. In this era of reformation and liberalization of electricity markets, the distribution companies are faced with new challenges of providing uninterrupted quality power supply with minimum cost. In this, endeavor, the distribution companies are looking for appropriate O & M procedures and diagnostic test methods to determine state & condition of the distribution transformers.

CPRI-Training Notes

18

Types of distribution transformers

The Distribution transformers are classified as follows:

1. Naturally cooled out door distribution transformers 2. Naturally cooled sealed distribution transformers 3. Completely self-protected distribution transformers

1. These distribution transformers are oil immersed, naturally cooled 3phase outdoor type transformers of capacities 16,25,63 &100KVA for use on systems with normal voltage of 11KV.

2. These distribution transformers are also oil immersed, naturally cooled 3phase outdoor type sealed transformers of capacities 16,25,63 &100KVA.

3. These distribution transformers are oil immersed, naturally cooled 3phase outdoor type completely self protected transformers of capacities 16,25,63 &100KVA. These transformers are equipped with circuit breakers on LV side, 11KV fuses and 11KV Lightning arresters on 11KV side as integral parts of the equipment.

Distribution transformer failures

The failure of distribution transformers in our country is high. The average failure rate in our country is about 9.2% and in some of the states it is as high as 32%. The revenue losses as a result of distribution transformer failure is unacceptably high

Some of the possible reasons for Distribution transformer failures:

1. Continuous over loading of transformer beyond rated capacity. 2. Improper tap position can cause excessive core loss and consequently excessive heating. 3. Outgoing cable faults if not cleared in specific time. 4. Improper contact of fuses/ over capacity fuses. 5. Loose cable connection to LT busing terminals. 6. Improper/loose earthing connection. 7. Unbalance load conditions. 8. Improper maintenance/checking of oil level in conservator/transformer and not topping up oil

to required level. 9. Non checking of the condition of silica gel/ not changing/reactivating the silica gel if silica gel

has turned pink in colour. 10. Non checking oil level in bottom of breather/forming oil seal and not making up the oil level

when required. 11. Not periodically checking the condition of gasket joints and tightening/replacing gaskets if

needed.

Factors affecting life of a transformer

A) Effect of moisture- Transformer oil readily absorbs moisture from the air. The effect of water in solution in the oil is to decrease the dielectric strength of the oil as well as the insulating paper which absorbs and stores the moisture due to its higher affinity of water over oil. All possible preventive steps should, therefore, be taken to guard against moisture penetration to the inside of the transformers.

CPRI-Training Notes

19

B) Effect of Oxygen- Oxygen may be present inside the transformer due to air remaining in oil, air pockets trapped in the winding, etc. The oxygen reacts with cellulose of the insulation and the decomposition products of the cellulose lead to the formation of organic acid soluble in oil and sludge which block the free circulation of the oil. Care should be taken to eliminate air from transformer by filing the transformer under vacuum.

C) Effect of solid impurities- The dielectric strength of oil diminishes appreciably if minute quantities of solid impurities are present in the oil. New transformer may contain particles of insulating material and other solid impurities. It is therefore, a good practice to filter the oil after it has been in service for a short time.

D) Effect of varnishes- Some varnishes particularly of the oxidizing type, enter readily in reaction with transformer oil and precipitate sludge on the winding. Synthetic varnishes having acid inhibiting properties generally delay the natural formation of acid and sludge in the oil.

E) Effect of slackness of windings- Because of repeated movements of the transformer, coils may be displaced from their original position which can cause electric and magnetic unbalance. It is therefore required that the tie rods or pressure screws should be tightened.

Maintenance:

If a transformer is to give long and trouble free service it should receive a reasonable amount of attention and maintenance. The causes of breakdown of transformers may be classified as follows:-

a) Faulty design or construction b) Incorrect installation, operation and maintenance c) Overload d) Neglect e) Wear and tear and other deterioration f) Accidents g) Failure of auxiliary equipment.

A rigorous system of inspection and preventive maintenance will ensure long life, trouble-free service and low maintenance cost. Maintenance consists of regular inspection, testing and reconditioning where necessaryRecords should be maintained of the transformer, giving details of all inspection and tests made, and of unusual occurrences if any.

The principal objective of maintenance is to maintain the insulation in good condition. Moisture dirt and excessive heat are the main causes of insulation deterioration and avoidance of these will in general keep the insulation in good condition. The limiting factor is the ageing of the insulation and decline in the quality of the insulation during the ageing process due to chemical and physical effects.

CPRI-Training Notes

20

Maintenance procedure

Safety precautions

Before starting any maintenance work the transformer should be isolated from the supply

and the terminals earthed. The level of oil in the transformer should be borne in mind when

undoing nuts and bolts and before unsealing the tank. No fire should be kept near the

transformer while maintenance work is in progress.

Oil

The oil level varies with the oil temperature. The indicator generally show the ‘cold’ level when the oil is at a temperature of about 25 Deg.C The transformer should be topped up as necessary with clean transformer oil. If the oil level drops appreciable over a short period, the tank should be checked for leaks. In case there is a leak on a welded joint, it should be rewelded. A leaking gasket may be attended to by tightening the bolts. If this is not sufficient, the gasket should be replaced.

Conservator

Conservators are so arranged that the lower part acts as a sump in which any impurities entering the conservator can collect. A valve/plug is fitted at the lowest point of the conservator for draining oil. The inside of the conservator should be cleaned every two or three years.

The oil level indicator should be kept clean and examined at regular intervals, and oil should be added.

Transformer body: The transformer tank and other parts should be inspected for any rust or leak. Rusted portions should be cleaned thoroughly and repainted with proper paints. Leaking joints can be rectified by tightening the bolts to the correct pressure or replacing the gaskets.

Bushings: The bushings should be inspected for any cracks or chippings of the porcelain at regular intervals and keep free from dust and dirt. The bushings should be cleaned at regular intervals.

External connections: All external connections should be tight. If they appear to be blackened or corroded, the same can be cleaned or should be replaced. The HT & LT jumpers shall have appropriate size lugs properly crimped for making connections to the transformer terminals

Dehydrating Breather: Breather should be examined to ascertain if the silica gel requires changing. More frequent inspections are needed when the climate is humid and when the transformer is subjected to fluxuating loads. So long as the silica gel is in active stage its colour is blue but as it become saturated with moisture its colour gradually changes to pale pink. The gel should then be replaced or reactivated.

The level in the oil seal must be maintained at the marked level.

Gaskets: Gaskets sometimes shrink during service. It is therefore necessary to check the tightness of all the bolts fastening gasketed joints. Leaking gaskets should be replaced.

CPRI-Training Notes

21

Inspection and maintenance schedule: The frequency of inspection should be determined by the size of the apparatus. Local climatic and atmospheric conditions will also influence inspection schedule.

Following table may be used as a guide for determining the inspection schedule ( CBI&P Manual on Transformers)

Recommended inspection schedules for transformers rating less than 1000KVA are given in table.1

S Inspection frequency

Item to be Inspected

Inspection notes Action required if inspection shows unsatisfactory conditions.

1. Hourly i)Load (amperes)

ii) Temperature

iii) voltage

i) Check against rated figures

ii) Oil temperature and ambient temperature

iii) Check against rated figures

-----

-----

-----

2. Daily Dehydrating breather

i) Check that air-passage are clear.

ii) Check colour of active agent

If silica gel is pink, change by spare charge. The old charge may be reactivated for use again.

3. Monthly i) Oil level in transformer

ii) Connections

i) Check transformer oil level

ii) Check tightness

i) If low, top up with dry oil, Examine transformer for leaks.

ii) if loose, tighten.

4. Quarterly Bushings Examine for cracks and dirt deposits

Clean and replace.

5. Half yearly i) Non-conservator transformer.

ii) cable boxes, gasketed joints, gauges and general paint work

Check for moisture under cover inspect

Improve ventilation, check oil.

6. Yearly

i) Oil in transformer

i) Check for dielectric strength and water content. Check for acidity and sludge

i) Take suitable action to restore quality of oil.

ii) Take suitable actions

CPRI-Training Notes

22

ii) Earth resistance

iii) Relays, alarms the circuits,etc

ii) ----

iii) Examine relay and alarm contacts, their operation, fuses, etc. Check relay accuracy, etc

if earth resistance is high.

iii) Clean the components and replace contacts and fuses if necessary,

iv) Change the setting, if necessary.

7. 2Yearly Non-conservator transformers

Internal inspection above core

Filter oil regardless condition.

8. 5 Yearly -------- Overall inspection including lifting of core and coils

Wash by hosing down with clean dry oil.

Location of distribution transformers

The installation site should be such that there is easy accessibility for inspection. The transformer installation position should be such that the breather, oil level indicator, rating and diaphram plate, dial thermometers etc., can be safely examined with the transformer energized. It should also be possible to have access to the operating mechanisms of the on load tap changer/ off circuit tap switch, marshalling box etc. The sampling valve, drain valve etc. should be of convenient locations.

When transformers are installed indoors, proper ventilation should be provided and adequate

space should be provided to enable it to dissipate the losses properly. If adequate spacing is

not provided, the temperature of the transformer will increase, and this will adversely affect

the insulation of the winding and the condition of the oil.

Foundation

Special foundation is not required for the installation of a distribution transformer, except a level floor strong enough to support the weight and to prevent accumulation of water. The transformer foundation should be provided with adequate oil soak pits and drains.

For outdoor installations, a level concrete plinth of correct size to accommodate the transformer in such a way that no person may step on the plinth, should be provided for transformers.

Condition monitoring and O & M measures:

The distribution transformers, being so large in nos. and scattered all over the places, it is

impossible to exercise the same amount of monitoring/ care like that for power transformers.

However load monitoring of each distribution transformer is carried out once a year and load

CPRI-Training Notes

23

balancing/ relieving of overloaded transformers, to the extent possible, is carried out as a

follow up action, Pre-festival check for any oil leakage/ low oil level/over-heated joints for

distribution transformers, at strategic locations are also carried out for taking necessary

corrective actions.

Exhaustive database on make, year of purchase, technical details, peak load reading, accessories, date of commissioning, location, history of maintenance/repairs etc. and performance shall be maintained. All failed transformers are inspected thoroughly prior to repair/disposal with a view to finding out the probable cause of failure, since such inspection provides vital feedback on design/manufacturing deficiency or any abuse that it might have been subjected to. Depending on the outcome of such inspections, review and amendments of specification are initiated.

Following are the diagnostic tests recommended for condition assessment of the Distribution Transformers.

a) On-line Diagnostic tests

Sl. no Tests Detection capability

1. Infrared thermo imaging Detects hot spots.

2. Transformer oil analysis Healthiness of oil

Internal condition

b) Off- line Diagnostic tests.

Sl.no

Tests

Detection capability

1.

Insulation Resistance

Winding Resistance

Transformer Turns Ratio

Tan delta

Index of dryness

Loose/damage of conductor.

Shorted turns &open winding

Dielectric Losses

Care to be exercised to avoid failures:

Sl.no In Manufacturing Stage In Transport In Working Conditions

1.

2.

3..

Proper insulation arrangement

Mechanical rigidity to withstand heavy forces

Adequate cooling arrangement

Safe handling during transport and erection

Adoption of standards for Erection of transformer

Standard construction

Maintenance of oil level

Maintenance of Breather with silica gel & oil seal

Periodical testing of IR values

CPRI-Training Notes

24

4.

5.

6.

7.

Adequate quantity of oil for insulation & cooling

Maintaining atmospheric pressure inside with pure air

Rigid fixing of core-coil

Adequate earthing of core & other metallic parts

Periodical tests on transformer

Earth resistance values and earth maintenance

Keeping standard voltage & frequency at load terminals.

Maintaining lightining arresters to prevent damage due to surges

Maintaining LT system

Keeping the loading within the limits

Examination of failed distribution transformers:

Sl.no

External Check up

Internal Physical

Verification

1.

2.

3.

4.

5.

Oil level and quantity available

Places of oil leakage

Condition of Breather &Silica gel

Condition of Bushing & Bushing rods

Condition of vent Diaphragm

Condition of Valves

Conditions of HT coils in all the three phases

Check lead connection from coil (Delta &Star points)

Condition of core

Condition of Tap switch and connections

Condition of core earthing

CPRI-Training Notes

25

6.

7.

8.

IR value & continuity

BDV Test on oil

Presence of sludge & moisture in oil & physical condition of oil

Protection of distribution transformers:

Pole mounted distribution transformers of capacities ranging from 16kVA to 200kVA

with voltage ratio of 11000/433-250 volts shall have protection as given in Table below.

Voltage ratio Capacity (KVA) Protection

Primary side Secondary side

11000/433-250

Volts

16,25, 63,100

&200

Drop out/ Horn gap fuse Moulded case

circuit breaker

(MCCB)

Ground mounted distribution transformers of capacities ranging from 200KVA to 3150KVA with voltage ratio of 11000/433, 33000/433 and 33000/11000 volts shall have the protection as given in Table below.

Voltage ratio Capacity KVA Protection

Primary side Secondary side

11000/433-250 315,630,1000,and 1600 HRC/Expulsion fuse MCCB

33000/433 630,1000,1600 HRC/Expulsion fuse MCCB

33000/433 1600 HRC/Expulsion fuse CB

Concept of AT&C losses and Measures for reduction of AT&C losses

Viji Bharathi, Engineering Officer, Distribution Systems Division, CPRI

Introduction

Electricity Distribution plays a vital role in the social and economic development of our

society. It has a great impact on the quality of life of a common man. There is a vast gap

CPRI-Training Notes

26

existing between the demand and supply of electricity. Various schemes like APDRP, R-

APDRP, RGGVY etc., are put forth by the Govt. of India to address the existing demand-

supply gap. The Government of India also came up with an ambitious target of―Power for all

by 2012‖ under the National electricity Policy.

Transmission & Distribution (T&D) Loss

The difference between the Energy Input and the Energy Sales which is the Energy loss is

termed as the Transmission and Distribution (T&D) loss. The State Electricity Boards are

characterized by the T&D loss.

Energy loss = Energy Input-Energy Sold =

T&D loss

Due to lack of adequate investment in the T&D works, the T&D losses have been on the

higher side and reached to the level of 32.86% in the year 2000-2001. The reduction of these

losses was essential to bring economic viability to State utilities.

Overview

ARR is termed as the Average Rate of Realization of Revenue from the sale of Energy.

ACS is termed as the Average Cost of Supply at which the Energy is purchased from

transmission for distribution to end user.

The gap between the Average Rate of Realization (ARR) and the Average cost of supply

(ACS) has been constantly increasing till 2000-01. This gap was causing the state electricity

boards (SEB) run under huge revenue losses.

In view of the losses faced by the SEB's, the Government of India/MoP has undertaken

reforms in power sector with a step by the Electricity Act 2003 and then through the

Accelerated Power Development Programme (APDP) that was renamed as the Accelerated

Power Development and Reforms Programme (APDRP) in 2001-02. The main aim of

APDRP was restoring the commercial viability in the distribution sector.

Concept of AT&C loss

As the T&D loss was not able to capture all the losses in the network, concept of Aggregate

Technical and Commercial (AT&C) loss was introduced. AT&C loss captures technical as

well as commercial losses in the network and is a true indicator of total losses in the system.

High technical losses in the system are primarily due to inadequate investments over the

years for system improvement works, which has resulted in unplanned extensions of the

distribution lines, overloading of the system elements like transformers and conductors, and

lack of adequate reactive power support.

CPRI-Training Notes

27

The commercial losses are mainly due to low metering efficiency, theft & pilferages. This

may be eliminated by improving metering efficiency, proper energy accounting & auditing

and improved billing & collection efficiency. Fixing of accountability of the personnel may

help considerably in reduction of AT&C loss.

AT&C loss = 1-(Billing Efficiency*Collection Efficiency) =

(Energy Input – Energy realized) * 100

(Energy Input)

where, (i) Energy Realized (MU) = Collection Efficiency * Energy Billed

(ii) Collection Efficiency= Revenue Collected (Crores) *100

Revenue Billed (Crores)

(iii) Billing Efficiency (%)= Energy Billed (MU)* 100

Energy Input (MU)

The two main components of AT&C loss are (i) Technical loss and (ii) Commercial loss.

Technical Loss

Every element in a power System (a line or a transformer etc) offers resistance to power flow

and thus consumes some energy while performing the duty expected of it. The cumulative

energy consumed by all these elements is classified as ―Technical Loss.‖

Commercial Loss

Losses occur on account of non-performing and underperforming meters, wrong applications

of multiplying factors, defects in CT & PT circuitry, meters not read, pilferage by

manipulating or by passing of meters, theft by direct tapping etc. These are all due to non-

metering of actual consumption and are called commercial losses. The total of ―Technical‖

and ―Commercial‖ losses is termed are T&D loss. It is unfortunate that in addition to the

above, there is also a loss in revenue due to non-realisation of billed demand. This is in

addition to commercial losses and the aggregate of T&D loss and revenue loss due to non-

realisation is termed as ―AT&C loss‖ (Aggregate technical and Commercial loss).

Therefore AT&C loss to the utility is the sum total of technical loss, commercial losses and

shortage due to non-realisation of total billed demand.

Typical Example

Let the Energy Input be 100MU and the Energy Billed be 70MU.

CPRI-Training Notes

28

Then, T&D loss = 100-70 = 30MU and % T&D loss = 30%.

Let‘s say, the Revenue is billed (Revenue demand) for 70MU, while the Revenue collected is

only for 90% of the billed energy, i.e. 0.9*70 = 63MU.

Then, AT&C loss = 100-63 = 37MU and% AT&C loss = [1-(Billingefficiency*Collection

efficiency)] *100 = [1-(0.7*0.9)] *100 = 37%.

Factors contributing to High Technical Losses

The main factors that contribute for high technical losses are:

(i) Lengthy Distribution Lines: The primary and secondary distribution lines in rural areas

usually extend over long distances and are mostly radially laid. This results in high line

resistance and therefore high I2 R losses in the line.

(ii) Inadequate Size of Conductors:Rural loads are usually scattered and generally fed by

radial feeders. The conductor size of these feeders should be properly selected.

The size of the conductor should be selected on the basis of kVA x KM capacity of standard

conductor for required voltage regulation.

Tables 1 & 2 below indicate the length of lines for 11kV and 415 volts corresponding to

different loads for the voltage regulation prescribed by IE Rules; for different sizes of

conductors respectively.

Table 1

Length of 11kV line

Size of

Conductor

(with Code No.)

kVA-KM for 8%

voltage drop at 0.8

pF

Maxi-mum

length of line

(kM)

Load that can be

connected (kW)

50 MM2 ACSR

Rabbit 10,640 30 355

30 MM2 ACSR

Weasel 7,200 20 360

20 MM2 ACSR

Squirrel 5,120 15 341

Table 2

Length of 415V line

Size of conductor

(with Code No.)

kVA-km for 8%

voltage drop at 0.8

pF

Maxi-mum length

of line (kM)

Load that can be

connected (kW)

30 MM2 ACSR

Rabbit 11.76 1.6 7.35

CPRI-Training Notes

29

The figures of Table 1 &2 are for a conductor temperature of 60° C. For a conductor

temperature of 50° C, the above figures shall be about 3% higher and for a temperature of 70°

C about 3% lower.

(iii) Distribution Transformers (DTs) not located at Load Centre: Rural loads are usually

scattered and generally fed by DTs not Located at Load centre on the Secondary

Distribution System.Consequently, the farthest consumers obtain an extremely low

voltage even though a reasonably good voltage level is maintained at the transformers‘

secondary. This again leads to higher line losses. (Decreased voltage at the consumer

terminals lead to increased losses).

Therefore in order to reduce the voltage drop in the line to the farthest consumers, the

distribution transformer should be located at the load centre to keep voltage drop within

permissible limits and thus minimize the losses.

(iv) Over-rated Distribution Transformers leading to under-utilization: Studies on 11 kV

feeders have revealed that often the rating of DTs is much higher than the maximum

kVA demand on the feeder. Over rated transformers draw unnecessarily high iron losses.

In addition to these iron losses in over rated transformers the capital costs locked up is

also high.

From the above it is clear that the rating of DT should be judiciously selected to keep the

losses within permissible limits. For an existing distribution system the appropriate capacity

of a DT may be taken as very nearly equal to the maximum kVA demand at good PF (say

0.85). Such an exercise has been carried out for a number of distribution systems and

transformers with capacity of 25, 63,100,160, 315 kVA are standardized for different systems

varying with power factors and diversity factors.

(v) Low Voltage (less than declared voltage) at Transformer and Consumer Terminals:

Whenever the voltage applied to induction motor is varied from the rated voltage, its

performance is affected. Within permissible voltage variation of +/- 6% in practice, the

supply voltage varies by more than 10% in many distribution systems. A reduced voltage

in case of induction motor results in higher currents drawn for the same output.

For a voltage drop of 10%, the full load current drawn by the induction motors increase

by about 10% to 15%, the starting torque decreases by nearly 19% and the line losses in

the distributor increases by about 20%.

As the bulk load of rural areas and small scale industrial areas consists of induction

motors, the line losses in the concerned distribution systems may even touch 20%.

The above situation is corrected by operating an "on-load-tap changer" in the power

transformer situated at 66/11 kV high voltage sub-stations and 33/11 kV sub-

stationsandby providing a combination of switched capacitors and automatic voltage

regulatorson the 11 kV feeders

20 MM2 ACSR

Weasel 7.86 1.0 4.86

13 MM2 ACSR 5.58 1.0 5.58

30 MM2 AAC ANT 12.06 1.6 7.54

16 MM2 AAC Gnat 6.96 1.0 6.96

CPRI-Training Notes

30

Further, the "off load tap changer" in DTs is adjusted prior to the commencement of

agricultural load season which is readjusted before the on-set of monsoons when the

rural load is small if the off-load tap changing gear is available.

(vi) Low Power Factor:In most of the LT distribution circuits, it is found that the PF ranges

from 0.65 to 0.75. A low PF contributes towards high distribution losses. For a given

load, if the PF is low, the current drawn is high. Consequently, the losses that are

proportional to the square of the current will be more.

Thus, line losses owing to poor PF can be reduced by improving the PF. This can be done by

installing shunt capacitors.

Shunt capacitors can be connected in the following ways:

Shunt capacitors are connected on the secondary side (11 kV side) of the 33/11 kV power

transformers.

Line losses in LT distribution lines may also be considerably reduced by installing shunt

capacitors of optimum rating at vantage points as decided during load stations.

The optimum rating of capacitor banks for a distribution system is 2/3rd

of the average

kVAR requirement of that distribution system. The vantage point is at 2/3rd

the length of the

main distributor from the transformer.

A more appropriate manner of improving the PF of the distribution system thereby reducing

the line losses is to connect capacitors across the terminals of the motors (inductive load).

Many electricity supply authorities are making it compulsory for the consumers to provide

capacitors of adequate rating for all types of installations with connected loads of 5 HP and

above.

(vii) Bad Workmanship Resulting in Poor Contacts at Joints and Connections: Bad

Workmanship contributes significantly towards increase in distribution losses. The

significance leads to:

Joints are a source of power loss. Therefore the number of joints should be kept to

minimum. Proper jointing techniques should-be used to ensure firm connections.

Connections to the transformer bushing-stem, drop-out fuse, isolator, LT switch etc,

should be periodically inspected and proper joint ensured to avoid sparking and heating of

contacts.

Replacement of deteriorated wires and services should also be made timely to avoid any

cause of leakage and loss of power.

Haphazard and adhoc planning which ignore scientific methods also lead to high technical

losses.

Measures to reduce technical loss:

Short term measures:

(i) Network Re-configuration:

The term network reconfiguration includes any one or all the works such as:

Formation of new links to minimize within a feeder to form a tree structure.

CPRI-Training Notes

31

Erection of interlinking lines to change the area of feed from one substation to another

and balance the load among the substation.

Bifurcation of existing feeder to form parallel paths of power flow.

Network reconfiguration among feeders is effective only when the voltage drop between the

nodes to be linked is rich and the distance between the nodes is short. The nodes to be linked

have to be selected taking the quotient of voltage difference and the distance between the

nodes as criteria. Network reconfiguration within a feeder is effective only when zig-zag

factor is high. Zig-zag factor is defined as the ratio of total length of feeder to the bee line

distance between the Distribution substation and minimum voltage point. The links have to

be chosen so as to create a tree structure.

The distribution network in developing countries was expanded in adhoc manner to minimize

the initial investment cost; and longrange planning studies are not generally undertaken. This

situation has given a vast scope for reconfiguring the network to minimize losses.

(ii) Reactive power control: (a) Shunt Compensation: The load incident on the distribution system is mostly inductive,

requiring large reactive power. The best method is to compensate the reactive power at

the load end itself but it is difficult to implement in practice. Hence, providing

compensation on the distribution system is essential. The shunt capacitor supplies

constant reactive power at its location, independent of the load. So, optimal compensation

provided for peak load condition may result in over compensation during light load

conditions, necessitating automatic switching schemes. The problem of determining the

number, size and location of shunt capacitors required to be provided is formulated as an

optimization problem. Objective function is the cost of energy saved due to reduction of

power losses by the installation of capacitor banks less the annual cost of capacitors

installed. The voltage constraints need not be considered, as the capacitors are switched

on and off along with load to avoid over voltage during low load operation; and capacitor

alone cannot economically improve the voltage during peak load period to satisfy the

statutory lower limit.

(b) Series Compensation:The maintenance of voltage at customer premises within statutory

limits at all loads is the responsibility of utility. Series capacitor introduces negative

reactance in the line and improves the voltage which in turn also reduces the power

losses. The main advantage of series capacitor is the quantum of compensation is highly

responsive of series capacitor is that the quantum of compensation is highly responsive to

load current and series capacitor can be kept in the circuit during the complete load

cycle, without causing any adverse effect of over voltages, during low load conditions.

The problem of determination of optimal location and capacity of series capacitor is

formulated as an optimization problem. The objective function is similar to that of shunt

compensation. The voltage constraint is that the voltage at the location of capacitor shall

not exceed permissible upper is less than the difference between the permissible upper

limit of voltage and voltage at the location of capacitor without series capacitor. Solution

to the problem of determination of optimal capacity and location of series capacitor is

obtained through an interactive approach.

(iii)Network Re-conductoring:

CPRI-Training Notes

32

Network Re-conductoring is replacement of the existing conductor on the feeder with optimal

conductor size for optimal length of the feeder. This scheme arises where existing conductor

is no more optimal due to rapid load growth. This is particularly relevant to developing

countries, where annual growth rates are high and the conductor sizes are chosen to minimize

the initial capital investment. Studies of several distribution feeders indicate that the losses in

the first few main sections (4 to 5 say) from source constitute a major part of the losses in the

feeder and by reinforcing these sections with conductor of optimal size, the losses can

minimize the total cost, that is, cost of investment and cost of energy losses over a period of 5

to 10 years.

(iv) Automatic Voltage Booster:

The functioning of Automatic booster (AVB) is similar to that of series capacitor. AVB is an

on load tap changer. It boosts the voltage at its point of location in discrete steps and this in-

turn improves the voltage profile and reduces the losses in the section beyond its point of

location towards receiving end. An AVB generally has a total voltage boost of 10% in four

equal steps. The loss reduction is directly proportional to voltage boost and maximum

permissible voltage boost is limited by the difference between the permissible maximum

voltage and voltage at the point of location of AVB. The problem of determination of optimal

location and percentage of boost of boost of AVB is formulated as an optimization problem.

The objective function is the cost of energy saved due to desirable constraints is that the

voltages at all sections should not exceed the statutory upper and lower limits. An interactive

type of algorithm is adopted in the proposed solution approach.

(v) Maintenance Schedule:

Strict terms to adhere to implement the scheduled maintenance practices for various

distribution network components like Power transformers, distribution transformers should be

framed. The distribution utilities generally have a schedulefor maintenance. The only

constraint would be that these maintenance schedules are not put in practice regularly.

(vi) Software tools:

Software tools may be used to identify the network reconfiguration which results in

maximum LRVI (loss reduction and voltage improvement) with least investment. Based on

cost benefit ratio, the best option for investment can be chosen. A combination of GIS and

network analysis tools like Power Net may be adopted.

As a last resort, to go in for another sub-station followed up by reconfiguration.

In addition to the above which is a general up-gradation of the distribution network,

thefollowing measures may be adopted to reduce the technical loss.

(vii) High Voltage Distribution System (HVDS): Whenever there are widely distributed and sparse consumers on an LT feeder involving long

lines to the load, the line losses (I2R losses) become very high. It is more practical to use

high voltage (11kV) distribution of power to such remote loads thereby reducing the line

losses as the equivalent HV current is of a much lower magnitude. The first attempt at

HVDS was for a single phase 11kV and a neutral wire feeding small capacity like

5/10/15kVA transformers with a primary of 6350V and secondary of 230V powering

individual single phase pump sets. This was area specific and therefore resulted in unbalance

CPRI-Training Notes

33

in the power transformer feeding the HVDS. Secondly, there was slight voltage drop at the

end of the line on load resulting in lower secondary voltage. One method used by APSEB

was to repair single phase copper wound transformers with aluminium HV windings thereby

boosting the secondary voltage. With judicious loading of the power transformer, HVDS is

an attractive distribution method where the loads are distributed widely and removed from

power transformer.

(viii) Amorphous Core Transformers:

Amorphous Core Transformersmay be used where the core magnetizing or no-load loss gets

substantially reduced. They are not economical at present. Efforts are being made to make

amorphous core material indigenously and the cost is expected to go down considerably.

Factors contributing to Commercial Losses:

The main causes for commercial loss can be grouped into two. (i) Due to the deliberate action

of the regularized/ unauthorized consumers and (ii) Due to internal shortcomings of the utility

system/policy

Deliberate action of consumers

Unscrupulous consumers extract energy illegally which is the act of Pilferage of energy.

Energy pilferage is done by direct tapping by the non-customers and by the existing

customers.

In certain areas, direct tapping of power by non-customers is widely prevalent. This is mainly

in domestic and agricultural categories. Geographical remoteness, mass basis for theft, poor

law enforcement capability and inaction on the part of utility are helping this phenomenon.

Theft by existing consumers is by various means such as totally bypassing the meter,

tampering the meter in different ways, etc. New methods are being constantly evolved.

Internal shortcomings of the utility

This prevails mainly due to Metering, Billing and Collection inefficiencies.

Metering: There are many services unmetered. The meters get sluggish over a period of

time. Many stuck up meters are allowed for years. There is considerable voltage drop in

metering cables. The meter capacity and the load have no relation.Manual errors in meter

reading such as no readings furnished by the meter reader for a good number of services,

constant ‗nil‘ consumption cases reported without any comment, progressive readings in

disconnected services, etc.Wrong multiplication factors (MF) are adopted. After the MF is

changed, it is not intimated to the billing agency.

Billing: There are reasons such as non-receipt / late receipt of bills, wrong bills, wrong

calculations, and manual errors in billing etc.contributing to commercial losses.

CPRI-Training Notes

34

Collection: Bad payment history, regular defaulters, over dues, long dues by the Government

departments and Subsidies by Governments to distribution utilities and wrong tariff category

with respect to the connected load/ sanctioned load are some of the reasons for commercial

losses.

Measures to reduce the Commercial loss

A good distribution network shall be in place for providing reliable power supply at assured

voltage levels to consumers and the same shall be with least technical losses. The commercial

losses can be reduced by accurate metering, efficient billing and prompt collections

implementing.

Accurate Metering (A metering plan for installing meters with sustained accuracy).

Appropriate range of meter with reference to connected load.

Electronic meters with (Time of day, tamper proof data and remote reading facility) for

HT & HV services.

Intensive inspections by pooling up staff.

Reduce meter exceptional.

Use of Energy Audit as a tool to pinpoint areas of high losses.

Eradication of theft.

Automated Meter Reading (AMR) systems.

Measures to reduce Power pilferage

Electricity theft can never be totally eradicated in any power system. Setting-up of the

strengthened Vigilance and Raids with police enforcement help curtail power theft.Electricity

theft and corruption appear to be closely linked. To curb theft, a combination of strong

technical improvements with intelligent and active anti-theft remedial measures is to be

introduced. Imprisonment, heavy fines are to be levied for compounding. Some change in

the value systems of the society is also needed. The opinion makers and social leaders are to

be involved to effectively tackle this massive social evil.

Analysis on very high consumption when compared to the similar connected loads and

continuous monitoring on abnormal variation in consumption help detect unauthorized

additional loads through special tools.

Electricity Act 2003 has brought radical changes in all the facets of the electricity sector.

Though originally the vigilance wing was meant only for detection of pilferage, of late its

functions also cover many other facets like:

Malpractice

Back billing

Excess connected loads

Poor power factors in all categories

Running of captive generator sets without adequate safety arrangements etc.

Non sealing of AB switches, meter boxes, and terminal covers.

Line losses in selected towns, industrial feeders etc.

Functioning of border meters, capacitor banks etc.

Bus, P.T. and C.T. facilities for efficient metering.

Inspection of high value UDC services.

Study of MRBs.

CPRI-Training Notes

35

Applying CAT for HT & LT services and inspecting class F services, etc.

Maintenance of assets by local officers.

Billing irregularities in transformer repairs, maintenance and construction works.

Nonstandard releasing of services.

Releasing of services in UDC premises.

Releasing of services in wrong categories.

Coordinating massive inspections with all engineers and APTS personnel wherever required.

Involvement of employees in various irregularities.

Payment and billing pattern of services of VIPs.

Effective implementation of law with the aid of Electricity Act 2003 can eradicate / mitigate

theft which forms substantial portion of the commercial losses.

Administration should be reformed to bring out improved transparency, greater

accountability and streamlining the structure eliminating all forms of corruption for corporate

governance.

To overcome the shortcomings of the utility

Adoption of Common billing software and application of the Consumer Analysis Tool (CAT)

to have a meaningful control, review, storage and retrieval of the consumer data base.

Increased customer convenience such as drop box facility, Any Time Payment (ATP) options

etc. shall be the guiding factor for smooth collections to increase the revenue.

Effective disconnection of defaulters, target on high arrears services, immediate action of

non-paying consumers, compulsory and immediate prosecution in case of bounced cheques,

computerized monitoring system, adoption associations, cooperatives, panchayats and

franchisees for rural electricity management are some of the measures

There are many services unmetered. A large scale drive is necessary to bring all

unauthorized consumers on to the rolls. The meters tend to get sluggish over a period of

time. Old meters are to be replaced in a phased manner by high accuracy meters, especially

for high value services.

Electronic meters should be put to use. These meters with no moving parts, there is no wear

and tear in service. Due to its in-built intelligence, several features/ measurements such as

kWh, kVA, kVAR, PF, Currents, Voltages, detection of theft and tampers are possible. They

are able to withstand the harsh environments of heat, humidity, dust, shock, vibration, EMI/

EMC and magnetic field. Post processing of data can detect theft.

Use of remote metering, the remote metering also called as the AMR (Automated Meter

Reading) is an entire system that does away with manual reading and billing of consumers.

Most of manual errors due to meter reading and billing can be curtailed through proper

metering system thereby reducing the commercial losses.

CPRI-Training Notes

36

Aerial Bunched Cables (ABC):

The use of ABC avoids power pilferage due to insulation as compared to bare LT lines thus

reducing the commercial losses and provides better safety and reliability.

Effective metering, billing and collectionactivities

The commercial losses can be reduced by accurate metering, efficient billing and prompt

collection implementation, Use of Accurate Metering (A metering plan for installing meters

with sustained accuracy), Use of appropriate range of meter with reference to connected load,

Use of Electronic meters with (TOD, tamper proof data and remote reading facility) for HT &

HV services, Use of common billing software, Establish accurate data base of the network

and Consumer Indexing, Intensive inspections by pooling up staff to reduce (a) direct tapping

for power pilferage (b) defective metering, timely billing and collection activities (c) to check

on the relevant tariff of the connected category

Energy Audit:

Energy Audit practice may be adopted as a tool to pinpoint areas of high losses. Special

drives to inspect the rating of the Irrigation pump sets in the agricultural sector should be

adopted. All the un-authorized consumers are to be regularized in a phased manner to

contribute towards reducing the commercial losses.

References:

[1] ‘Modernisation of Power Distribution’ (Book) (Focus on APDRP) by M.V.S.

Birinchi, March – 2004

[2] Lecture notes from ‗DRUM Training Program’, CPRI Bangalore

[3] ‗Emerging Technologies for Distribution Loss Reduction (HVDS, ABC, Metering-

Electronic, Prepaid, SCADA & DA) by M.V.S.Birinchi, Core International Inc.

[5] ―Electricity Theft vis-avis Revenue Protection‖ a comparative analysis by Er.Vinay

Gupta, cover story IEEMA Journal, May 2014

[4]Web site: www.powermin.nic.in, www.apdrp.gov.in

CPRI-Training Notes

37

Reactive Power Management

R.A.Deshpande, Joint Director, Distribution Systems Division, [email protected]

The main objective of the power system is to meet the connected load to the maximum extent,

meeting the constraint of all the available generations in efficient, economic and reliable

manner. The power system consists of generating stations, transmission and distribution

networks and the loads. The load consists of both active and reactive parts and it absorbs

both active and reactive power. The transmission & distribution network does not generate

active power but can absorb or supply the reactive power. Some active power is lost in this

system in form of transmission/distribution losses. Generators either absorb or generate the

reactive power based on the excitation voltage.

The concept of reactive power, it’s significance and impact on overall power system, different

means to control the reactive power will be explained in this lecture.

Introduction

Real power accomplishes useful work while reactive power supports the voltage that must be

controlled for system reliability. In AC systems voltage and current pulsate at the system

frequency. Although the voltage and current frequency of pulsating may be the same, their

peak occurs at different time. The power is algebraic product of voltage and current. Real

power is the average of power over cycle and measured by volt-amperes or watt. The portion

of power with zero average value called reactive power measured in volt-amperes reactive or

vars.

In steady state operation of electrical power systems, both active power and reactive power

balances must bemaintained.

The reactive power generated by synchronous machines and shuntcapacitances must beequal

to thereactive power of the loads plus the reactive transmission losses. If the active power

balance is not kept, thefrequency in the system will be influenced, while an imbalance in

reactive power can result in abnormalvoltagesin the system much beyond permissible ones.

The voltage in a system is stronglyaffected by the reactive power flow. Consequently the

voltage can be controlled to desired values, by control ofthe reactive power. Increased

production of reactive power gives higher voltage in the vicinity of the productionsource,

while an increased absorption of reactive power gives lower voltage.

Power flow is always measured with respect to the voltage. The voltage at the point of

measurement is taken as reference vector for defining the direction of power flow. The

angular position of the current vector defines the direction of active, reactive and apparent

power flow.

CPRI-Training Notes

38

Basic Definitions

1] Real Power:

When a passive linear component is excited by sinusoidal voltage

𝑣 𝑡 = 𝑉𝑚𝑎𝑥 cos(𝜔𝑡)

The resultant current will be

𝑖 𝑡 = 𝐼 max cos(𝜔𝑡 + ∅)

The magnitude of I max and the phase shift Ø will be determined by the application of

ohms‘s law.

And fundamental definition of power is

𝑝 𝑡 = 𝑣 𝑡 ∗ 𝑖 𝑡

The typical voltage and current waveforms are shown in Fig.1

The instantaneous power will be

𝑝 𝑡 = 1

2 𝑉𝑚𝑎𝑥 𝐼 max cos ∅ + cos 2𝜔𝑡 + ∅

Fig.1: Voltage and current waveforms

Fig.2 shows waveform of power in a inductive circuit. If this waveform is seen carefully, few

interesting things can be observed. The frequency of power waveform is double that of

voltage or current. Also it is not symmetrical with respect to x-axis.

-0.80

-0.60

-0.40

-0.20

0.00

0.20

0.40

0.60

0.80

y

Voltage Current

Main : Graphs

0.210 0.220 0.230 0.240 0.250 0.260 0.270 0.280 0.290 0.300 ...

...

...

-0.020

-0.010

0.000

0.010

0.020

0.030

0.040

y

Pow er

CPRI-Training Notes

39

Fig.2: Waveform of ―Power‖

This waveform can be shown to be consisting of two distinct waveforms as shown in Fig.3,

one which is symmetrical to x-axis and the other which is always above x-axis. In other

words the avearge value of first one will be zero and that of second waveform will be always

positive. Here one should not confuse with negative sign put for the power which is to denote

the direction of power flow.

Fig 3: Apparent power consisting of active

power and reactive power

Thus the formula for different powers will be

𝑃 = 𝑃 max (1 − cos(2𝜔𝑡)

𝑄 = 𝑄𝑚𝑎𝑥 sin(2𝜔𝑡)

𝑆 = 𝑃 + 𝑗 𝑄

And in terms of voltage and current

𝑆 = 𝑉 𝐼*

The power triangle shows this concept in pictorial form.

Where P, Q and S are real, reactive and apparent power respectively; V & I are the complex

―root mean square‖ phasor representation of voltage and current and * denotes conjugation.

-1.5

-1

-0.5

0

0.5

1

1.5

2

2.5

1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37

Po

wer

time

Active Power Reactive Power

CPRI-Training Notes

40

The direction of power flow depending on angle between voltage and current is illustrated in

Fig.4

Fig.4: Active/Reactive Power Flow with

different angles between voltage and

current

Need for Reactive Power Management

When there islight loading, the system generates reactive power that must be absorbed, while

at heavy loading the systemconsumes a large amount of reactive power that must be injected.

Injecting reactive power into the system raisesvoltages, and absorbing reactive power lowers

voltages.

It is necessary to manage reactive power at all the three distinct points of power system. At

the consumer end the electric equipment are designed to operate within a range of say ± 5 %

or 10 %. At the low voltages many of these perform poorly. The simplest light bulb will glow

dimply giving poor illumination. Induction motors get overheated and get burnt. Sensitive

electronic equipment may not operate at all. Similarly high voltages can damage the

insulation and equipment and also shorten their life-time.

In the transmission network, to maximise real power flow, reactive power flow control is

important.

Reactive power production/absorption can limit a generator‘s real-power producing

capability.

Due to excessive reactive power flow in the system, total current will be higher. This will

result in excessive heating of equipment in addition to undesirable voltage levels.

Surge Impedance Loading

It is very important to refresh the basic concept of Surge Impedance Loading (SIL).The Surge

Impedance Load (SIL) of a lossless transmission line isthe amount of load delivered to a pure

resistance equal to the characteristic impedance (square root ofL/C where L and C are the

incremental distributed series inductance and shunt capacitance). A line with 1.0SIL loading

will have a flat voltage profile (same voltage at sending end and at receiving end), and the

same current all along the line. The voltage and current will be in phase along the entire line.

CPRI-Training Notes

41

The reactive powerinto the line from the shunt capacitance charging is exactly equal to the

reactive power consumed by the series inductance losses.

Table 1 : Surge Impedance Loading

The above Table.1 gives SIL loading value for different voltage levels and appropriate size

and the number of the conductors used. The information in Table 1, is taken from CEA.

There are three constrains in transmitting the power over transmission line. Thermal limit,

voltage drop limit and stability limit. For short length of lines thermal overloading is more

significant. Voltage drop constraint is important for medium length of lines. For long lengths

line, steady state stability limits the maximum power transfer. The electrical distribution lines

are never long length lines. Hence thermal heating and voltage drops are only the main

concern in planning or augmenting the electrical distribution system.

Problems of reactive Power

The extension of the above equations lead to

𝑆 = 𝑃2 + 𝑄2

Power factor = cosØ = 𝑃

𝑄

Suppose there are two loads each of 460kW but one with unity power factor (like purely

heating load) and other with power factor of say 0.5 (like induction motor). For simplicity we

will assume that both are single phase load and voltage at the load point is 230 V rms.

For load A,

S = P = 460 kW

I =S/V= 2 A rms

For load B,

S = P / cosØ = 460/0.5 = 920 kVA

I = S/V = 4 A rms

CPRI-Training Notes

42

So if power factor is low then the current increases for the same kW load. The I2R losses in

distribution line will increase four times in this example. If there is single power distribution

line between substation transformer and this load of say resistance 4 ohms, the sending end

voltage in first case will be 238 Volts rms. If 230 V is taken as limiting value then sending

end voltage will be more by 3.47 % in first case. But with low factor load, voltage will go up

by 6.96%. It may be noted that in both the cases meter at load point will be reading 460 W.

As there is no billing for reactive power, consumer pays same amount but the detrimental

effect on distribution system is very much pronounced.

When the example is extended to real electrical distribution network, calculation becomes

difficult. Standard International software and expertise to use it, can give very accurate

results by simulation of any big network. One such example is brought out in Fig.5 and

results tabulated in Table.2.

Fig 5 : Typical scaled down Feeder

Power Factor 0.95 0.75

Total losses 5.52 kW 8.52 kW

Tail End voltage 10.91 kV 10.87 kV

Table 2 : Simulation results of selected feeder

DISCOMs correct for power factor around industrial complexes, or they inform the offending

customer to do so else charge for reactive power. They‘re not worried about residential

service because the individual impact is not visible as in heavily industrialized areas. But

when many domestic consumers added together, power factor correction assists the electric

company by reducing demand for electricity, thereby allowing them to satisfy needs

elsewhere.

Means of controlling Reactive PowerShunt reactors are used to compensate for the effects of

linecapacitance, particularly to limit voltage rise on open circuit or lightload.They are usually

required for EHV overhead lines longer than 200 km.

CPRI-Training Notes

43

A shorter overhead line may also require shunt reactors if the line issupplied from a weak

system (low short-circuit capacity).

A shunt reactor of sufficient size must be permanently connectedto the line to limit

fundamental-frequency temporary over voltages toabout 1.5 pu for a duration of less than 1

second.

Additional shunt reactors required to maintain normal voltageunder light-load conditions may

be connected to the EHV bus. 50 MVAR and 80 MVAR are the typical reactor size used in

400 kV and higher system. However during heavy loading conditions, some of the reactors

may have tobe disconnected.

Shunt capacitors are used to compensate for the heavy loading conditions.Switching of

capacitor banks provides a convenient means ofcontrolling transmission system voltages.

Series capacitors are connected in series with the lineconductors to compensate for the

inductive reactance of the line.

STATCOMS, SVC etc are used in MV and EHV range. D-STATCOM, automatic power

factor correction (APFC) units are used in 11 kV and LT system. An APFC unit consists of a

number of capacitors that are switched ‗ON‘ or ‗OFF‘ by means of contactors. These

contactors are controlled by a regulator that measures power factor in an electrical network.

Depending on the load and power factor of the network, the power factor controller will

switch the necessary blocks of capacitors in steps to make sure the power factor stays above a

selected value. The optimum rating and optimum locations for given network and the cost

benefit analysis can be done in CPRI.[Annexure-1]

The most effective method of reactive power management in distribution system is by power

factor improvement by using power capacitor.

kVAr requirement calculation need measurement of actual power factor, desired power factor

and load in kW. The Table 3 gives multiplication factor to obtain required kVAr. If average

power factor is 0.5 and is to be improved to 0.94 then 180.7 kVAr capacitor is required for

100 kW load. Similarly for 500 kW load, 408.5 kVAr capacitor is required to improve the

power factor to 0.98 from 0.7.

0.9 0.92 0.94 0.96 0.98 0.99

0.4 1.807 1.865 1.928 2.000 2.088 2.149

0.45 1.500 1.559 1.622 1.693 1.781 1.842

0.5 1.248 1.306 1.369 1.440 1.529 1.590

0.55 1.034 1.092 1.156 1.227 1.315 1.376

0.6 0.849 0.907 0.970 1.042 1.130 1.191

0.65 0.685 0.743 0.806 0.877 0.966 1.027

CPRI-Training Notes

44

0.7 0.536 0.594 0.657 0.729 0.817 0.878

0.75 0.398 0.456 0.519 0.590 0.679 0.739

0.8 0.266 0.324 0.387 0.458 0.547 0.608

0.85 0.135 0.194 0.257 0.328 0.417 0.477

0.9 0.000 0.058 0.121 0.193 0.281 0.342

Table 3: Multiplication factor for kVAR requirement

After calculation of kVAr requirement, the type of capacitor is to be selected. It will be

standard duty, heavy duty etc depending upon operating life, number of operation per year

etc.

Next calculations are required to check whether this capacitor value will result in resonance

which can damage electrical equipment including capacitors. Suitable filter reactor will be

required to avoid resonance.

Based on the ratio of the rating of incoming transformer and capacitor kVAr,fixed type

capacitor or automatic power factor correction panel is selected.

Excellent test facilities have been created in CPRI for testing LV APFC panels as per IEC

61921 and IEC 61439.

The awareness about reactive power management has resulted in many states coming out

with pricing scheme for reactive power. This is listed in Appendix-A.

Appendix-A

Reactive Power Pricing scheme in different states

CPRI-Training Notes

45

Annexure-1

Optimum Capacitor banks for distribution feeder

R.A.Deshpande

Joint Director, DSD, CPRI

Abstract: This paper examines use of capacitor bank in a realistic distribution system. The

distribution system can be distinctly classified as urban, industrial and rural. The length of

feeders, type of loads and load-time curve varies widely for each of these types. The

efficiency of the feeder can be improved by use of shunt capacitors. However for already

existing distribution feeders whose length runs into tens of kilometers and also where ratio of

LT line length to HV line length is higher, the usage of capacitor bank can be very

complicated. Though it can be said very easily that I2R losses and voltage profile along the

feeder can be improved by using capacitor bank, optimum selection of capacitor bank in

terms of (i) size vis-a vis cost, (ii) number of capacitor banks and their location for reducing

energy losses on one hand and maintenance and cost on the other hand, (iii) capacitance

value and permissible rise of voltage during different load conditions (iv) limiting the

increase in short-circuit current in case of fault can be very complicated. A typical rural

feeder is considered and analysis is presented in this paper to demonstrate possibility of most

optimum solution.

Introduction

Electrical energy has become integral part of the economic development of human society.

Power is indispensable resource in today‘s high technology driven world and the power

industry is one of the main pillars of nation‘s overall development. Transmission lines and

distributions lines carrying the power are like blood vessel carrying oxygen in the human

body. However rapid growth of load centers, demands of agriculturist, transformation of

cities into big cities and metros require large power to flow long distance from widely

dispersed generating sources.

Due to nature of load i.e having less than unity power factor, requires significant amount of

reactive power (VAR) in addition to consumer‘s active power (W) requirement. If this

reactive power has to flow from the same generating sources, the transmission lines and

distribution lines, the overall reactive power flow would be much higher because of the

inductance of transmission and distribution line. This results into increase in I2R losses and

voltage reduction along the line, maximum reduction being at tail end. The shunt capacitors

act as source of reactive power. They increase the voltage at the point of connection. To

summarise, the shunt capacitors reduces the losses, improves the voltage profile, help in

reduction in conductor/transformer/protective equipment sizing. The benefits are very clear.

The task of finding out the optimum solution is tedious as many permutation and

combinations are possible.

I Distribution network under study

A typical distribution feeder as shown in Fig.1 is considered for study purpose. This is rural

type of feeder with most of the load being agricultural pump motors. The substation

CPRI-Training Notes

46

transformer from rating which this feeder emanates is 66/11 kV, 10 MVA. The total length of

11 kV feeders is about 17.5 km from one end to other end with many tap feeders along the

line. There are 108 numbers of 11 kV/433 V distribution transformers (DT) of various rating

like 25 kVA, 63 kVA and 100 kVA. The secondary load is lumped and considered at the

terminal of the secondary of the concerned DT. The value of load is 15 days average in a

particular month. The impedance value of secondary line is added in the load value and not

separately simulated. Hence there will be 108 numbers of loads. Each of these loads is three

phase balanced load and specified in terms of kW and power factor.

Fig 1. The 11 kV rural distribution feeder

The load flow analysis using Voltage Drop calculation method based on current iterations is

used as the solution algorithm. Table 1 shows the summary of load flow results. No capacitor

compensation is considered initially. It was also observed that at one particular node the

voltage is as low as 0.74 pu and at one other voltage is 0.92 pu. The voltages at all other

nodes are within 95 to 100%. There is no overvoltage on any section.

Table1. Load Flow result

kW kVAR kVA PF(%)

Sources (Swing) 711.25 343.11 789.68 90.07

Generators 0 0 0 0

Total Generation 711.25 343.11 789.68 90.07

Load

679.97 320.42 751.68 90.46

Shunt capacitors 0 0 0 0

Total Loads 679.89 320.13 751.49 90.47

Line Capacitance 0 24.68 24.68 0

Total Shunt Capacitance 0 24.68 24.68 0

CPRI-Training Notes

47

Line Losses 11.08 38.79 40.34 27.46

Cable Losses 0 0 0 0

Transformer

Losses 20.27 8.86 22.13 91.63

Total Losses 31.35 47.66 57.05 54.96

II Different Cases, Results and Discussions

For this feeder, objective will be to reduce the losses to the extent possible, improve the overall

power factor of the system and improve the voltage at the two nodes which are below

permissible limits,. The constraints will be to use minimum number of capacitor banks, to use

minimum rating of capacitor rating. Very importantly voltage at point should not increase

beyond the permissible higher limit of 105%. Based on the market conditions, the minimum

capacitor bank rating selected is 3 kVAr, maximum being 54 kVAr. The increment in

capacitor bank is 3 kVAr. The power improvement was kept as 0.98. The calculations gave

15 possible locations which are as shown in green mark in Fig.2 in the same network diagram.

The value of capacitor bank required is 9 kVAr for 13 locations and 18 kVAr at two DT

locations.

Fig.2 The same network with optimum location of capacitor bank

The load flow study was repeated with these values of capacitor. The results are tabulated in

Table.2. The losses are reduced by 4.6 % from earlier 31.35 kW to 29.91 kW. The under

voltage at the nodes is slightly improved to 0.7443 pu and 0.9375 pu respectively.

Table 2. Load Flow result after placement of capacitors

kW kVAR kVA PF (%)

CPRI-Training Notes

48

Sources (Swing)

709.86 190.53 734.98 96.58

Generators

0 0 0 0

Total Generation 709.86 190.53 734.98 96.58

Load

679.97 320.42 751.68 90.46

Shunt capacitors

0 145.31 145.31 0

Total Loads 679.94 175.08 702.12 96.84

Line Capacitance

0 25.4 25.4 0

Total Shunt Capacitance 0 25.4 25.4 0

Line Losses

9.38 32.83 34.14 27.47

Transformer Losses

20.54 8.02 22.04 93.15

Total Losses 29.91 40.84 50.63 59.09

The savings in the loss reduction is of the order of Rs.50457 per year while the cost of

installation of 13 x 9 + 2x 18 kVAr capacitor bank is Rs.28837.Due to maintenance point of

view suppose the number of capacitor location are to limited to say maximum of 5, then this

calculation gives two location with 135 kVAr capacitor bank at one node and 9 kVAr capacitor

bank at other node. Here the number of locations has been optimised , remaining very close

to main objective. The total loss in this case is 30.27 kW.

It is also possible to have distance of capacitor bank from substation as constraint. Say as a

standard practice the minimum distance of capacitor bank locations from substation is to be

maintained. Solutions for this type of constraint can be also found. With minimum distance of

5000 meters as constraint, study gave 13 locations within 500 meters distance from substation.

It also gave the capacitor bank size, in this case it is 9 kVAr incidentally at all the location. The

total losses are 30.28 kW.

III Different load conditions

In case the peak load is very much higher than normal load, the study is more useful. It gives

optimum location of fixed capacitors and optimum location of switched capacitors along with

rating of capacitor bank ratings. First normal load is considered and rating and location of

capacitor bank is determined. Then considering the peak load, the rating and location where

still the fixed capacitor can be used without violating the upper voltage limit is found. Then the

switched capacitor which needs to be switched during normal load condition location and their

rating is obtained. It is attempted to keep the rating of switched capacitor bank as low as

possible.

Peak load was taken as 170 % the normal load and the study was repeated. 36 locations with 9

kVAr rating capacitor bank is required. 14 locations are to be provided with fixed capacitors

CPRI-Training Notes

49

and 22 locations are to be provided with switched capacitor banks. It was also ensured that

even when these switched capacitor banks are not switched off during normal load flow, the

voltage rise will not be more than 105 %.

IV Conclusions

The reactive power compensation is very important to strengthen the weaker distribution

system network. It is most economical means of increasing power transfer. The key objective

of reduction of power losses, increase of power flow capacity and improvement in voltage

profile can be achieved with use of shunt capacitor. Coupled with study for optimum solution

with different constraint can give best economical choice.

References

[1] J. V. Schmill, "Optimum Size and Location of Shunt Capacitors on Distribution Feeders,"

IEEE Transactions on Power Apparatus and Systems, vol. 84, pp. 825-832, September 1965.

[2] H. Dura "Optimum Number Size of Shunt Capacitors in Radial Distribution Feeders: A

Dynamic Programming Approach", IEEE Trans. Power Apparatus and Systems, Vol. 87, pp.

1769-1774, Sep 1968.

[3] J.J. Grainger and S. Civanlar, ―Volt/var control on Distribution systems with lateral

branches using shunt capacitors as Voltage regulators-part I, II and III,‖ IEEE Trans. Power

Apparatus and systems, vol. 104, No. 11, pp. 3278-3297, Nov. 1985.

[4] M. E Baran and F. F. Wu, ―Optimal Sizing of Capacitors Placed on a Radial Distribution

System‖, IEEE Trans. Power Delivery, vol. No.1, pp. 1105-1117, Jan. 1989.

[5] M. E. Baran and F. F. Wu, ―Optimal Capacitor Placement on radial distribution system,‖

IEEE Trans. Power Delivery, vol. 4, No.1, pp. 725734, Jan. 1989.

[6] MasoudAliakbar GOLKAR, ―A Novel Method for Load Flow Analysis of Unbalanced

Three-Phase Radial Distribution Networks,‖ Turk J ElecEngin, VOL.15, NO.3 2007,

CPRI-Training Notes

50

REACTIVE POWER COMPENSATION- POWER FACTOR IMPROVEMENT

By T.BhavaniShanker, Engineering Officer Grade4, DCCD, CPRI

1.0 INTRODUCTION

This section deals with some of the basic concepts of installation of shunt capacitors for power factor improvement. Phase displacement between voltage and current in industrial loads, need for power factor correction, practical considerations of installation of capacitors, etc., are explained.

1.1POWER IN ALTERNATING CURRENT – ACTIVE AND REACTIVE POWER

In alternating current circuits, energy storage elements such as inductance and capacitance may result in periodic reversals of the direction of energy flow. The portion of power flow that, averaged over a complete cycle of the AC waveform, results in net transfer of energy in one direction is known as real power (also referred to as active power). That portion of power flow due to stored energy that returns to the source in each cycle is known as reactive power.

The relationship between real power, reactive power and apparent power can be expressed by power triangle(refer to Figure 1). Using the Pythagorean Theorem, the relationship among real, reactive and apparent power is:

(Apparent power, kVA )2 = (Real power, kW)2 + (Reactive power, kvar)2

Figure 1: Power triangle: The components of AC power

IMPEDANCE AND REACTANCE

Circuits in which current is proportional to voltage are called linear circuits. The ratio of voltage to current in a resistor is its resistance (R). Resistance does not depend on frequency, and in resistors V and I are in phase. However, in majority of the practical circuits the loads are not pure resistors and the ratio of voltage to current does depend on

CPRI-Training Notes

51

frequency and in general there is a phase difference. Impedance (Z) is the general name given to the ratio of voltage to current. Resistance is a special case of impedance. Another special case is that in which the voltage and current are out of phase by 90°: this is an important case because when this happens, no power is lost in the circuit. In this case where the voltage and current are out of phase by 90°, the ratio of voltage to current is called the reactance (X).

Capacitive reactance XC is the ratio of the magnitude of the voltage to magnitude of the

current in a capacitor.

Capacitive reactance,Xc = 1/ωC = 1/2πfC

There will be a phase difference between voltage and current: Voltage is 90° behind the

current as shown in Figure 2. In other words, capacitor current leads the voltage by 90°.

Capacitor reactance (the ratio of voltage to current) decreases with frequency.

Figure 2: Capacitor in AC circuit

Inductive reactance XL is the ratio of the magnitudes of the voltage and current.

Inductive reactance, XL = ωL = 2πf L

There will be a phase difference between voltage and current. Voltage across the ideal

inductor is 90° ahead of the current as shown in Figure 3. In other words, inductive current

lags the voltage by 90°. Inductive reactance is frequency dependent and increases with

frequency.

Figure 3: Inductance in an AC circuit

Impedance is the general term for the ratio of voltage to current. The table below

summarizes the impedance of the different components. The same information is given

graphically in Figure 4.

CPRI-Training Notes

52

Figure 4: Dependency of Impedance on frequency

RLC SERIES COMBINATIONS

Consider a circuit having resistors, capacitors, and inductors connected in series in one

circuit. If all three components are present, the circuit is known as an RLC circuit (or LRC)

as shown in Figure 5. If only two components are present, it's either an RC circuit, an RL

circuit, or an LC circuit.

Figure 5: RLC Series circuit

The overall resistance to the flow of current in an RLC circuit is known as the impedance,

symbolized by Z. The impedance is found by combining the resistance, the capacitive

reactance, and the inductive reactance. Unlike a simple series circuit with resistors, however,

where the resistances are directly added, in an RLC circuit the resistance and reactance are

added as vectors. This is because of the phase relationships. In a circuit with just a resistor,

voltage and current are in phase. With only a capacitor, current is 90° ahead of the voltage,

and with just an inductor the reverse is true, the voltage leads the current by 90°.

CPRI-Training Notes

53

Series impedance (Zseries): the ratio of the voltage to current in an RLC series circuit.

Reactances and resistances add according to Pythagoras' law (Refer to Figure 6) are related

by the following formulae:

Zseries2 = R2 + Xtotal

2

= R2 + (XL - XC)2.

Figure 6: Phasor diagram

Inductive and capacitive phasors are 180° out of phase, so their reactances tend to cancel. The power dissipated in an RLC circuit is given by:

Note that all of this power is lost in the resistor; the capacitor and inductor alternately store

energy in electric and magnetic fields and then give that energy back to the circuit.

Setting the inductance term to zero gives back the equations for RC circuits, though note that phase is negative, meaning that voltage lags the current. Similarly, removing the capacitance terms gives the expressions that apply to RL circuits.

Figure 7 shows the special case where the frequency is such that VL = VC.

Figure 7: Series resonance

Because vL(t) and vC are 180° out of phase, this means that vL(t) = - vC(t), so the two reactive voltages cancel out, and the series voltage is just equal to that across the resistor. This case is called series resonance.

CPRI-Training Notes

54

1.2 ENERGY STORED IN CAPACITANCE AND INDUCTANCE

One of the main differences between resistors, capacitors, and inductors in AC circuits is in

what happens with the electrical energy. With resistors, power is simply dissipated as heat. In

a capacitor, no energy is lost because the capacitor alternately stores charge and then gives it

back again. In this case, energy is stored in the electric field between the capacitor plates.

The amount of energy stored in a capacitor is given by:

Energy Stored in Capacitor:Ec = ½ CV2

There is also no energy lost in an inductor, because energy is alternately stored in the

magnetic field and then given back to the circuit. The energy stored in an inductor is:

Energy Stored in inductor: 𝑬𝑳= 𝟏

𝟐(𝑳𝑰𝟐)

POWER RELATIONSHIPS IN AC CIRCUITS

AC power flow has the three components:

Real power(Active power)(P), measured in watts (W);

Apparent power (S), measured in volt-amperes (VA); and

Reactive power (Q), measured in reactive volt-amperes (var)

For power factor of cosΦ as shown, by definition Active power (kW) taken by the load = EI cosΦ 10-3

Reactive power (kvar) taken by the load = EI sinΦ 10-3

Apparent power (kVA) taken by the load = EI × 10-3

Power factor load = Active power (kW) / Apparent power (kVA) = cosΦ

Active power (kW) = √kVA2 – kvar2 = kVA cosΦ

Reactive power (kvar) = √ kVA2 – kW2 = kVA sinΦ = kW tanΦ

Apparent power (kVA) = √ kW2 + kvar2 = kW/cosΦ

1.3 POWER-FACTOR CORRECTION

Most ac electric machines draw from the supply apparent power in terms of kilovolt-amperes (kVA) which is in excess of the useful power, measured in kilowatts (kW), required by the machine. The ratio of these quantities (kW/kVA ) is called the power factor cosΦ and is dependent on the type of machine in use.

𝑷𝒐𝒘𝒆𝒓 𝑭𝒂𝒄𝒕𝒐𝒓 (𝐜𝐨𝐬∅) =𝑼𝒔𝒆𝒇𝒖𝒍 𝒑𝒐𝒘𝒆𝒓 (𝒌𝑾)

𝑨𝒑𝒑𝒂𝒓𝒆𝒏𝒕 𝑷𝒐𝒘𝒆𝒓 (𝒌𝑽𝑨)

A large proportion of the electric machinery used in industry has an inherently low pf, which means that the supply authorities have to generate much more current than is theoretically

CPRI-Training Notes

55

required. In addition, the transformers and cables have to carry this high current. When the overall pf of a generating station’s load is low, the system is inefficient and the cost of electricity correspondingly high. To overcome this, and at the same time ensure that the generators and cables are not loaded with the wattless current, the supply authorities often impose penalties for low pf.

Some of the machinery or equipment with low pf are listed below:

1. Induction motors of all types 2. Power thyristor installations 3. Welding machines 4. Electric arc and induction furnaces 5. Choke coils and induction furnaces 6. Neon signs and fluorescent lighting.

The method employed to improve the pf involves introducing reactive (kvar) into the system in phase apposition to the wattless or reactive current. This is achieved either with rotary machines (synchronous condenser) or static capacitors.

The apparent power (kVA) in a.c. circuit can be resolved into two components, the in-phase component which supplies the useful power (kW), and the wattless component (kvar) which does no useful work. The phasor sum of the two is the kVA drawn from the supply. The cosine of the phase angle between the kVA and the kW represents the power factor of the load. This is shown by the phasor diagram in Figure 9 (a).

To improve the power factor, equipment drawing kvar of approximately the same magnitude as the load kvar, but in phase opposition (leading), is connected in parallel with the load. The resultant kVA is now smaller and the new power factor (cosine Φ2) is increased (Figures 9(a) and (b)). Cosine Φ2 is controlled by the magnitude of the kvar added. Thus any desired power factor can be obtained by varying the leading kvar. A typical arrangement of shunt capacitor connected in parallel with a load is shown in Figure 10.

Figure 9(a): Phasor diagram of a plant operating at a lagging power factor

Figure 9(b): Power factor correction by adding leading kvar

CPRI-Training Notes

56

Figure 10: Capacitor connected in parallel with load

CALCULATION OF CAPACITOR kvar FOR PF CORRECTION

Capacitor kvar required to correct power factor from cosΦ1 to cosΦ2 is given by the formula as depicted in Figure 11.

Capacitor (kvar) = (kvar1 – kvar 2)

= kW(tanΦ1 – tanΦ2)

Figure 11: Phasor diagram for finding the size of capacitor

required to correct to a given power factor.

This value of capacitor kvar can be determined either by drawing the phasor diagram to the scale or by calculation using the values from trigonometric tables.

As example is illustrated below:

Given, 100 kW load to be improved from 0.77 to 0.95.

Capacitor (kvar) = kW (tanΦ1 – tanΦ2)

= 100 ( 0.5) = 50 kvar

That means, for improving the pf from 0.77 to 0.95 for a load of 100 kW, capacitor of 50 kvar to be connected.

1.4 DETERMINATION OF LOAD CONDITIONS

The first step in designing any practical power factor correction scheme must be to obtain accurate details of the load conditions with values of kW, kVA, Power factor at light, average and full load, together with type and details of load and presence or absence of harmonics. This may be achieved by conducting a system study at the proposed site of installation of capacitors with the help of a suitable power analyzer for a period of minimum 24 hours. From this information, conditions of the existing power factor can be calculated. Such study also helps to assess power quality particularly with reference to harmonics, type of loads, loading patterns, etc.

CPRI-Training Notes

57

1.5 RATED VOLTAGE OF CAPACITOR:

As IEC 60871 and IEC 13925, HV capacitors can take only rated voltage continuously. Also, capacitor design shall accommodate 10 % over voltage for a period of 12 hours in a day. For example, for a 11 kV system, if the voltage variation is 10 %, capacitors shall be rated to 12.1 kV. This will ensure proper performance from capacitors.

When reactors are used in series with capacitors, it gives voltage rise at capacitor terminals. For example, a 6 % reactor will increase the capacitor voltage by approximately 6 %. Therefore, capacitor rated voltage should be corrected by raising the rated voltage further to that extent.

INCREASE IN BUS VOLTAGE DUE TO CAPACITORS

Capacitor gives boost to the voltage where they are connected to a circuit, on account of reduction in line current and resultant drop in I (line current) x Z (system impedance). In most of the cases, rise in voltage is normally limited to 2 to 3 %.

For example, 1 MVAr capacitor is connected to a 5 MVA incoming transformer with 6 % impedance, then voltage rise can be calculated as

% over voltage = % Impedance x (capacitor MVAr / Transformer MVA)

= 6 x (1/5)

= 1.2

When large capacitors are connected to system through dedicated transformers, over voltage

will be large and shall be taken into account while deciding the rated voltage of capacitor

bank.

1.6 SIZING OF CAPACITOR BANK

Capacitor output (kvar) is proportional to the square of the voltage and frequency. For example, consider installation of 1MVAr capacitor to a 11 kV system. As explained earlier, rated voltage of the capacitor should be 12.1 kV (=1.1x 11 kV). For this increased voltage, corrected output rating of the capacitor will be

1 MVAr x (12.1 x 12.1)/(11 x 11) = 1.21 MVAr

When capacitor bank is provided with series reactor, say 6%, the rating of capacitor needs to be corrected for loss in series reactor. For the same requirement of 1 MVAr at 11 kV, the voltage is chosen as

Rated voltage = 11 x 1.1 / (1- 0.06) kV

= 12.87 kV

Capacitance impedance at 11 kV bus,

Xc = (11 x 11)/ 1 = 121 ohms

CPRI-Training Notes

58

Corrected capacitor impedance

X’c = Xc / (1- 0.06) = 121 / 0.94 = 128.72 Ohms

Therefore,

Capacitor Output = (kV x kV )/ X’c = 12.87 x 12.87 / 128.72 = 1.28 MVAr

Series Reactor impedance = 0.06 x X’c = 7.73 Ohms

Therefore, 1.28 MVAr, 12,87 kV capacitor bank with 6 % series reactor will give 1 MVAr at 11 kV bus.

1.7 LOCATIONS FOR INSTALLATION OF CAPACITORS

Normally capacitors can be installed at the distribution boards but if it is required to reduce loading on feeders, or if the metering is at high tension and it is required to install low voltage capacitors, then it is necessary for sub-circuit tests to be made to determine the point of connections of the capacitors. This is especially important in average power factor installations. These clip-on tests are usually made using clip-on ammeters, kW meters and kvar meters.

For average industrial consumers, the capacitors are normally connected to the low voltage side of the transformers irrespective of whether the supply is taken at high voltage or low voltage. This relieves the transformer of unnecessary load and also helps compensate for the transformers magnetizing current.

1.8 ECONOMIC CONSIDERATIONS

While considering the economics for power factor (pf) correction, it is most important to remember that any pf improving plant, in general, compensate for losses and reduce the current loadings on supply equipment, i.e., cables, transformers, switchgears, generating plant, etc.

The rating of the capacitors required to improve pf depends largely on the tarrif. Savings obtained from installing pf correction equipment depends on the tariff structure, like , kVA-hours, kvar-hours, maximum demand kVA, all of which quantities are reduced by installing pf correction capacitors.

The points to be considered in any installation are:

1. Reliability of the equipment to be installed

2. Probable life

3. Capital cost

4. Maintenance cost

5. Running cost

6. Space required and ease of installation

CPRI-Training Notes

59

The power capacitors owing to their low dielectric losses, compact size, simplicity and high efficiency, are considered almost universally for pf correction. It is usually found that the expenses of correcting a low pf by means of capacitors is less than the savings effected in the first 18 months: subsequent annual savings are thereafter clear profit.

1.9 PROTECTION OF HV CAPACITOR BANKS

A broad summary of the classes of protection employed for HV capacitor banks is given in Table 1. For larger capacitor banks all three classes are employed. These classes of protection are complementary to one another and are not alternatives.

Table 2: Summary of Classes of High voltage capacitor protection

Class of Protection

Method Location Type Comments

prrimary Fuse link External at unit terminal

HRC

For delta connected or single –phase banks only

External at unit terminal

Expulsion

For star –connected banks only

Internal-buried in element

TC wire Inside each unit

Secondary Relay Energized from CTs between star pointed interconnection of bank

or

Out-of-balance current

or

To provide alarm and trip facilities in conjunction with capacitor control switch

Relay Energized from CTs across capacitor phases or between star point and earth

Out-of-balance current

To provide alarm and trip facilities in conjunction with capacitor control switch

Line Relays Main incoming supply to complete bank

O/C and E/L protection

To protect system and complete bank and connections from short circuits

Relays Main incoming Close current To prevent excessive

CPRI-Training Notes

60

supply to complete bank

o/load protection

current o/loading especially from harmonics

Relays Main incoming supply to complete bank

Overvoltage protection

To prevent over voltages including effects of voltage wave distortion

CPRI-Training Notes

61

POWER CAPACITORS

2.0 INTRODUCTION

In spite of the phenomenal growth of power generation in the country during the last two decades, the demand has always outgrown the supply. To meet this increasing demand, continued efforts are needed not only for more generation but also for conservation of generated energy and improvement in system design. Transmission and distribution losses have risen considerably due to various reasons. One of the measures to reduce the system losses is to connect capacitors across individual inductive devices and / or at various strategic points of the system. Application of power capacitors is increasing rapidly in the Industries (both heavy and small scale), which use motors, transformers, electric furnaces, etc., in order to compensate for the inductive loads and consequently improve the power factor close to unity and also improve the voltage profile.

Power Capacitor Industry has seen a phenomenal growth during past 10 to 15 years. Capacitors of unit rating up to 1000 kvar 15 kV AC are being manufactured. With the availability of high dielectric strength and low loss materials like polypropylene (PP) film and improved processing techniques, high voltage capacitors with very low dielectric losses are

being manufactured. The design stress is in the range of 60 V/m to 80 V/m. The motive behind these phenomenal changes is to achieve compactness, minimum dielectric loss, low cost and importantly, improved reliability.

Although the performance of power Capacitors in service is generally satisfactory, several instances of premature failures of power capacitors have been reported by utilities. Capacitor failures have been experienced during laboratory testing also. While most of the Capacitor failures are generally attributed to the poor material quality, there are also some reports of spurious capacitors in operation. Capacitor failures have been observed due to selection of wrong type of capacitors and presence of system disturbances like harmonics, transients etc.

This article covers some of the details like scenario of capacitor technology, construction and material details of capacitors, importance of testing, a general sequence of testing for HT shunt capacitors, maintenance of capacitor banks and facilities CPRI for research, testing and certification of power capacitors.

2.1 INTERNATIONAL SCENARIO OF CAPACITOR TECHNOLOGY

Power capacitor industry has seen a phenomenal growth during the past 10 to 15 years. New developments in materials, design, processing, construction etc., have taken place, which aim towards higher unit rating and compact size. These changes are summarized in Table 1 along with

their effect on capacitor dissipation factor (tan ) and design stress.

CPRI-Training Notes

62

With the availability of high insulation strength and low loss dielectric materials and improved processing techniques, high voltage capacitors with very low insulation losses are being manufactured as indicated in Table 1. PP film impregnated with suitable synthetic oil has become the most commonly employed insulation for power capacitors, with the design stress as high as 80

V/m. Due to these developments, the power rating of shunt capacitors has reached as high as 1000 kvar per unit.

Table 1: Evolution of capacitor technology

Capacitor material

and construction

LT capacitor HV capacitor

Present status of technology

Year tan

%

Stress

V/m

Year tan

%

Stress

V/m

Paper- Al foil Polychloro-biphenyl (PCB) impregnant

1940 0.3 18 1940 0.3 18 Not in use due to toxic nature of PCB

PP-Paper-Al foil

PCB impregnant

1972 0.3 18 1965 0.05 49 Not in use due to toxic nature of PCB

PP-Paper-Al foil

Synthetic impregnant

1977 0.05 55 Finds application in CVTs and for some special application

Metallised PP film 1977 0.02 45 Widely used for 400 V range

Metallised PP film, Synthetic impregnant

1977 0.02 50 Used in 650 V range

All PP film(Hazy)-Al foil synthetic impregnant

1979 0.02 70 Widely used

All PP film (Hazy)-Embossed Al foil, Synthetic impregnant

1980 0.02 70 Not widely used

All PP film (Hazy)-Folded edge Al foil Synthetic impregnant

1990 0.02 75-80 Widely used

All PP film (Hazy)- Laser cut Al foil, Synthetic impregnant

1995 0.02 75 Under trial

The basic raw materials presently being employed for HV capacitors are listed below:

(1) Solid insulation: Bi-axially oriented polypropylene film (BOPP) is the most commonly employed insulation for HV capacitor. To facilitate the process of impregnation, the

CPRI-Training Notes

63

surface of PP film is made hazy by corona treatment. Wide application of PP film in HV capacitors is mainly due to its good electrical and mechanical properties like:

High electric strength of the order of 250 –300 V/m ac Low dissipation factor less than 0.0002 Thermally and electrically compatible with insulating oils employed as capacitor

impregnants. Good machinability

Electrical grade PP film is generally available in thickness in the range of 8, 10, 12, 15 and 18 m. The requirement of PP film for power capacitor application is specified in IEC 674 (equivalent Indian Standard is IS 11298 (Part 3/Sec 1): 1991 as given in Table 2.

Table 2: Requirements of PP film for HV capacitor application

Sl. No.

Property Clause Ref. of IS 11298 (part 2)-

1987

Requirements Tolerance

1 Thickness in m

(Preferred thickness)

4.5 8,9,10,11,12,14,15.2,16.5,18 &20

6%

2 Space factor for hazy film (%)

4.5

10 2%

3 Width in mm 8 Preferred width not specified

1%

4 Density (gm/cm2) 6.1.2 0.905 0.005 %

5 Tensile strength at break (N/mm2)

12 140 Minimum

Specified

6 Elongation at break (%)

Both along machine direction (MD) and

cross machine direction (CMD)

12 40 Minimum

Specified

7 Heat shrinkage (%)

i) along MD

ii) along CMD

24

4

2

Average

8 DC Dielectric strength

(volts/m)

19.2 6m: 250

8-11m: 300

>12m: 450

9 Volume resistivity 16 1x1016 Maximum

CPRI-Training Notes

64

( cm) at 2720 C and

605%

specified value

10 Dissipation factor at 270C, 48-52 Hz and

500volts ac

17 2 x 10-4 Maximum specified value

11 Dielectric constant at 270 C, 48-52 Hz

17 2.2 0.05

12 Electrical weak spots (counts/m2)

20 6m: 6

8-9m: 4

10-11m: 3

12 m: 2

>14m: 1

Maximum specified

Value

(2) Capacitor impregnant: The most commonly employed capacitor impregnants are Phenyl Xylyl Ethane (PXE) (Dielektrol III) DOP (Dielektrol II) Isopropyl Biphenyl (IPB) Benzyl Neocaprate (Faradol) Di Isopropyl Napthalene Jarylec (blend of benzyltoluene and di benzyltoluene)

The important properties, which decide the selection of capacitor impregnant are, dielectric constant, breakdown strength, viscosity, aromatic content, flash point and pour point. Compatibility of the impregnant with PP film also plays an important role, particularly with respect to swelling of PP film. The impregnants should be biodegradable and non-toxic, unlike PCBs (Polychloro-biphenyl). The characteristics of capacitor impregnant shall comply with the requirement of Clause 4.2 of IS 13067:1991.

The capacitor units used in the present study are generally impregnated with PXE. The key properties of PXE are listed below:

Property Value

Dielectric constant, 25 C : 2.5

Breakdown voltage, kV/25 mm gap

: 80

Flash point : 148C

Pour point : -48C

Viscosity, 38C : 6.1 cs

CPRI-Training Notes

65

PP film swelling, % : 12

Aromatic content, % : 75

2.2 CONSTRUCTION OF HV CAPACITORS

High Voltage power capacitors consist of a number of basic elements, which are constructed by winding two layers of Aluminium foil interleaved by two or three layers of PP film. HV capacitors are generally constructed with extended foil arrangement where Aluminium foils extend beyond the edge of PP film. After completion of winding process, the elements are assembled into parallel group consisting of generally 12 elements. Such stacks are connected in series to achieve

the required voltage and output. After assembling, discharge devices and internal

fuses (for internally fused capacitors) are provided. Inter element connections are generally made by soldering a metal strip on the extended Aluminium foil. A mild steel or stainless steel lid, drilled with two holes to allow impregnation, is then mounted on the capacitor elements pack. Connection leads are brought out to bushings on the lid. This assembly of capacitor elements is fitted into a mild steel or stainless steel case and the lid is welded in position. Once assembled, the capacitor undergoes a vacuum drying process and impregnation and on completion of this process the holes in the lid are sealed. Winding of capacitor element and impregnation process are usually computerized for accurate control.

Construction details of HV capacitors, from element to finished product, are shown in Figure 1.

Figure 1: Internal construction of HV capacitor - Schematic

Typical output ratings (kvar) of HV capacitors are, 181, 200, 220, 350, 400, 770, 1000, etc. and Typical voltage rating of HV capacitors are, 3.3 kV, 6.6 kV, 7.3 kV, 12 kV, 18 kV.

Most generally accepted parameters for construction of a HV capacitor are given below with typical dimensions of PP film and Aluminium foil for a rating of 200 kvar, 7.3 kV.

Number of series group / unit : 4

Source: M/s. ABB Ltd.

CPRI-Training Notes

66

Number of parallel elements / Series. group : 12

Width of PP film : 320 mm

Active width of Al. Foil : 320 mm

Edge folding : 5 mm

End folding : 20 mm

Active width of foil : 296 mm

Exposed foil : 6 mm

Discharge device : Internally fitted

Active length of the element : 14 meters

Thickness of Al foil : 6 m

Thickness of PP film : 10 m

Number of PP layers : 3 numbers

Element Connection : Soldered type

Internal fuses : Present in internal fuse type capacitors

Installation of Capacitor Banks

A typical layout of a 1.5 x 3 Mvar, 13.8 kV shunt capacitor bank along with the adjacent distribution load are shown in Figure 2 The capacitor banks are designed to switch on and off automatically based on power factor, vars, and /or voltage.

Figure 2 Typical drawing showing a 13.8 kV, 4.5 Mvar and adjacent distribution loads.

CPRI-Training Notes

67

A view of MV capacitors installed indoor in a APFC panel is shown in Figure 3. A view of HV capacitor bank is shown in Figure 4.

Figure 3. Capacitor Bank Installed (APFC Panel)

in an Industrial site.

Figure 4. A View of HV Capacitor Bank

3.0 SCENARIO OF INDIAN CAPACITOR INDUSTRY

The effective load power factor in our transmission and distribution system is 0.8 or below, whereas world-wide practice is to compensate the reactive loads to an extent that the power system operates at a power factor of the order 0.98.

One of the effective remedies to overcome this problem is to improve the load power factor by installing shunt capacitors. The responsibility of installation of capacitors lies with State Electricity Boards (SEB) and power utilities. As per one of the estimates of POWERGRID, there is a shortage of over 10,000 MVAR [2].

Seeing the huge quantum of backlog, Central Electricity Authority (CEA), New Delhi, has made it compulsory to install shunt capacitors at strategic points. CEA has instructed SEBs to expedite capacitor installation program. Very encouraging results were brought out by an indicative cost benefit analysis, which states that the entire cost of installation of capacitors is recovered within a brief period of 12-13 months by way of savings in T&D loss alone. It is heartening to note that, some of the SEBs are taking necessary steps for installation of shunt capacitors, including Karnataka Power Transmission Corporation Ltd (KPTCL).

Thus, application of shunt power capacitors is increasing rapidly for reactive compensation to improve power factor and the voltage profile. The major utilities of shunt power capacitors in the country are State Electricity Boards, Indian Railways, NTPC, PGCIL, BSES, BEST, Steel Industry, Textile industry, etc.

Presently, there are about 15 major HV capacitor manufacturers in the country. Single phase and three phase capacitors of unit rating 736.64 kvar and 14.82 kV ac are being manufactured

CPRI-Training Notes

68

indigenously. Capacitors of unit rating up to 1000 kvar 14.4 kV AC is the highest unit rating single phase HT capacitor manufactured in India as on July 2009.

The Capacitors Laboratory of CPRI, Bangalore is playing an important role in the growth of Indian Capacitor Industry. The laboratory has established full-fledged facilities for carrying out tests as per National and International specifications. Also, the facilities are being upgraded continuously to meet the requirement of industries and test specifications. In addition to testing, the laboratory is also engaged with applied research work in the field of power capacitors. Some of the research investigations have been carried out in association with the capacitor industry for providing facilities and expertise for enhancing the reliability of power capacitors.

CPRI-Training Notes

69

Energy Accounting and Segregation of Technical & Commercial loss in

Distribution System – Case Studies

R. Sudhir Kumar, Engg. Officer, Distribution Systems Division, CPRI

1.0 INTRODUCTION

Growth of economy is invariably liked to infrastructure and energy plays the most vital role

for a vibrant economy. It‘s a well known fact that the financial health of the utilities is a

matter of grave concern. Out of the total energy generated only about 55 % is billed and 41 %

realized. The present situation is characterized by extremely high technical and commercial

losses, poor quality of supply, tardy record in billing and revenue collection etc.

Transmission and Distribution losses in Indian power Systems are higher than those in

developed countries. The losses in India for different states vary between 21 to 43 % with a

national average of 30 %. Reduction of energy losses in transmission and distributions

system has been a matter of great importance to electric power utilities in India.

Losses in general can be identified in Distribution system as 1) Technical losses and 2)

Commercial losses. There are various determinants for high T&D loss and to name a few are

a. Losses in the conductors which can be minimized but cannot be nullified

b. Overloaded feeders.

c. Losses in the Transformers which is a matter of design of the manufacturer and also

loading pattern.

d. Under loaded transformers.

e. Illegal connections such as hooking, tapping, meter tampering, etc

f. False recording or failure to record actual consumption due to faulty meter or improper

meter reading.

Future distribution system will be far more complex then those of today due to fast

urbanization and exponential load growth. This means that the power system generation and

planning task will be more complex. If the system being planned is to be optimal with respect

to construction cost, performance and operating efficiency better planning and analysis are

required. This can be achieved by load flow analysis, short circuit analysis, stability analysis

and power system control. By improving the quality of supply in the distribution system the

overall system performance is improved.

1.1 AT & C LOSSES

The parameters which are of importance to determine the health of a distribution system

(both technical and commercial) are the AT&C losses, the DT failure rates and the average

duration of outages of the 11 kV feeders. The AT&C losses and the DT failures are

invariably linked to each other. For estimation of the AT&C losses, the feeder input to the

town is considered along with the revenue billed and is given by the formula

𝐴𝑇&𝐶 𝐿𝑜𝑠𝑠 = 𝐼 − 𝐵. 𝐸 × 𝐶. 𝐸 ∗ 100 %

𝐶. 𝐸 =𝑅𝑒𝑣𝑒𝑛𝑢𝑒 𝐶𝑜𝑙𝑙𝑒𝑐𝑡𝑒𝑑 𝑖𝑛 𝑅𝑢𝑝𝑒𝑒𝑠

𝐸𝑛𝑒𝑟𝑔𝑦 𝐵𝑖𝑙𝑙𝑒𝑑 𝑖𝑛 𝑅𝑢𝑝𝑒𝑒𝑠

𝐵. 𝐸 =𝐸𝑛𝑒𝑟𝑔𝑦 𝑆𝑜𝑙𝑑

𝐼𝑛𝑝𝑢𝑡 𝑒𝑛𝑒𝑟𝑔𝑦

CPRI-Training Notes

70

Where B.E = Billing Efficiency

C.E = Collection Efficiency

The AT&C losses in India vary from a low 8-10 % in AP and TN to a high of 70-80 % for

Jharkhand and Bihar.

2.0 ENERGY ACCOUNTING TECHNIQUES

Energy accounting gives the overall picture of energy availability and its use. Energy audit

would enable to analyse the data in meaningful manner to evolve measures and introduce

checks and balances in the systems to reduce losses and improve technical performance.

Following would be the main objectives of Energy Audit

The review and up gradation of procedure for energy accounting.

Reviewed of technical efficiency of system elements in sub-transmission and distribution

system.

Analysis of techniques for measuring energy receipt, energy billed and revenue

collection.

Reviewed of performance of equipment, meters, DTC etc.

Audit the segregation of the technical and non-technical losses.

Establishment of norms for checking the consumption of various categories of

consumers and overall energy balance.

To achieve consumer satisfaction by reducing tariff with reduction in loss level.

There are mainly two methods of determining the energy losses in T&D system:-

DIRECT METHOD: - In this method losses are found out on the basis of difference of units

sent out and receipt at the end of each element in power system. All though this method helps

in correct determination technical and commercial losses, it is quite expensive to install

energy meters at all location in power system.

IN-DIRECT METHOD: - In this method the losses are determined by simulation of the

network through any software. The advent of powerful computers and good models for

simulations of T&D loss have render this job easy. Some of the software extensively used for

load flow studies and to estimate losses are the ―ETAP‖ and ―CYMDIST‖. The Energy

Profile Module (EPM) of CYMDIST is especially suited for Distribution Systems in which

the energy meter data (Load Survey data) of Distribution Transformers Centers (DTC) can be

directly interfaced with the EPM module to carry out load flow and arrive at energy loss for a

given period of time (E.g. Daily, Monthly and annually)

3.0 CASE STUDIES

3.1 CASE STUDY - 1

ESTIMATIONS OF LOSSES FOR A TYPICAL TOWN-A SIMPLE STUDY

A simple energy accounting study was carried out in a typical town in order to find the

AT&C (Aggregate Technical and Commercial) loss. This town has are four sections and

Three substations feeds this town.

3.1.1. METHODOLOGY USED:

CPRI-Training Notes

71

The Input energy of feeder is collected directly from feeder meters available at Substations

and Output energy required for loss calculation is taken directly from metered energy of

consumers. With the above calculations and assumptions, the total input and total output of

the town scheme is estimated.

Following were the steps used for energy loss calculations

3.1.1.1 Consumer energy billed:

The Consumer energy billed for the months of November and December for this typical town

is evaluated by considering the HT and the LT energy billed which are billed separately.

Table 1 shows the LT energy billed and Table 2 shows the HT energy billed along with the

revenue billed and collected.

3.1.1.2. Input Energy:

There are twenty 11 kV feeders feeding this town scheme, Out of twenty feeders, 15 feeders

are independent i.e. they feed only one section and therefore input energy read directly from

the feeder meters. The other 5 feeders feed more than one section,. Therefor load sharing

calculations us based on kVA and the input energy to the concerned section computed and

shown in Table 3

TABLE 1

LT UNITS (KWH) FOR THE MONTH OF

NOVEMBER AND DECEMBER

Sl.

no

Section

Name November December

1 Section-1 1847000 2299000

2 Section-2 989000 1399000

3 Section-3 1076000 1145000

4 Section-4 1121000 1127000

Total LT units 5033000 5970000

TABLE 2

HT DATA COLLECTED

Section Name Month Metered

energy

Revenue

billed

Revenue

Collected

excluding arrear

Revenue

collected

including arrear

Section-1

November

6406691 24681623 18227851 18227851

Section-2 181487 917168 889226 889226

Section-3 2337956 9955800 8176012 8665459

Section-4 9570 54735 54735 54735

Total 8935704 35609326 27347824 27837271

Section-1 December 6541634 24964519 17944027 17944027

CPRI-Training Notes

72

Section-2 190482 939975 887050 914992

Section-3 2594144 10794331 7107122 7118707

Section-4 9502 53443 53443 53443

Total 9335762 36752268 25991642 26031169

TABLE 3

TOTAL INPUT ENERGY

Sl. no Section Name Input (KWH), Nov Input (KWH), Dec.

1 Section-1 8560359.899 9481472.406

2 Section-2 1653488.836 1733845.982

3 Section-3 3120751.265 3468311.612

4 Section-4 3785000 4012000

Total 17119600 18695630

3.1.1.3. AT&C Loss:

Using the data tabulated in Table 1, Table 2. The Table 4 below shows the energy status

data of typical Town. The AT&C loss for the month November and December is given in the

Table 4 below

TABLE 4

ENERGY STATUS DATA CALCULATED BY CPRI

Descriptions Nov Dec

1 Input energy(kWh) 17119600 18695630

2 Metered Energy(kWh) 13968704 15305762

3 Billed energy(kWh) 13968704 15305762

4 Revenue billed in Rs 54009326 59652268

5 Revenue collected including arrear (LT) Rs 46637271 48831169

6 Revenue collected excluding arrear HT Rs. 46147824 48791642

1 Energy Loss% 18.41 18.13

2 Collection efficiency 86.35 81.86

3 Metering efficiency 81.59 81.87

4 Billing efficiency 81.59 81.87

5 ARR 2.72 2.61

6 AT&C loss 29.54 32.98

Excluding Arrear of HT

1 Collection efficiency excluding Arrear in HT 85.44 81.79

2 ARR 2.70 2.61

3 AT&C loss 30.28 33.04

CPRI-Training Notes

73

3.2 CASE STUDY -2

TECHNICAL LOSS ESTIMATION OF A FEEDER USING ETAP SOFTWARE

This study deals with Technical and Commercial losses in 11 kV feeder from A College 110

kV Substation which feeds a prominent Section of city in India through underground cables.

There are 12 transformers connected to this feeder. The feeder length is estimated to be 4.5

km.

3.2.1. ESTIMATION OF AT&C LOSSES

For estimation of AT&C losses, the feeder input is considered along with the revenue billed

and the revenue collected. The input energy of feeder is collected directly from feeder meter

available at substation and the output energy is taken directly from the

billed energy of the consumer and the revenue collected. Table 1 shows the list of

transformers and the energy billed for the particular transformer along with the revenue

collected for the study duration which is two months (Dec-06 and Jan-07). Table 2 shows the

results of the study. As shown in the Table AT& C is estimated to around 8.95 %. This feeder

is an urban feeder catering to both commercial and domestic consumers. DT meters have

been installed in this feeder.

TABLE 1

TRANSFORMER WISE ENERGY BILLED AND REVENUE COLLECTED

Sl. no Transformers Consumption in kWh Revenue billed

in Rs

Revenue

Collected in Rs

1 X-1 189942 674048 631583

2 X-2 218249 1180703 1098053

3 X-3 122486 450503 436989

4 X-4 139382 514319 496317

5 X-5 223147 822296 816181

6 X-6 138228 507987 494588

7 X-7 333824 734256 724523

8 X-8 167281 200117 195674

9 X-9 33126 187741 165986

10 X-10 203269 632974 622336

11 X-11 197465 612617 588112

12 X-12 73518 328396 304253

Total 2039917 6845957 6574595

TABLE 2

ESTIMATION OF AT&C LOSSES

Sl. No Particulars Dec-06 & Jan-07

1 Energy Input 2151520

2 Energy Billed 2039917

3 Revenue Billed 6845957

4 Revenue Collected 6574595

5 Collection Efficiency 96.04

6 Metering Efficiency 94.81

7 ARR (Rs/unit) 3.27

8 AT&C Losses % 8.95

CPRI-Training Notes

74

3.2.2 METHODOLOGY FOR TECHNICAL LOSSES

ETAP power system software is used for the load flow study of Kumarapuram feeder. Since

the software requires the exact length of UG cables, the mapping of the Kumarapuram 11 kV

feeder was conducted with the help of Global Positioning System (GPS 12). The distance

between the transformers is mapped to get the exact length of the feeder. Details of each

element in the feeder installed were collected. To run the load flow study, the

ETAP software requires the single line diagram of the feeder. The single line diagram is

drawn, showing Grid, Transformer, load on each transformer and exact length of UG Cable

etc. Following procedure is followed.

1. The load of the feeder is the peak load of the feeder obtained from the data

downloaded from the energy meter installed at this feeder.

2. Transformer data is collected from the name plate of the transformer available at site

and peak load of the transformer is measured during the peak time.

3. Transformer load is assumed as lumped load.

4. The type of cable installed is XLPE of 300mm² cross sectional area.

5. The tapping on secondary side of transformer is given from the data provided by the

utility

3.2.2.1 TECHNICAL LOSSES ESTIMATION

The technical energy losses of the distribution network were estimated by simulating the peak

load conditions on ETAP. The peak power losses for the network were assessed based on

load flow studies. The loss load factor was worked out from the daily load curve. The peak

power loss is converted to average energy loss by applying the loss load factor and the time

period of study. The feeder is simulated in the ETAP software by providing the Cable

lengths, the transformers installed along with their ratings and also the ratings of the

conductors etc. The peak load loss obtained by this simulation is taken to calculate the

average technical loss of the feeder along with Load Factor (LLF).

The Loss Load Factor is defined below

N

iNLLF

1

1Li² /Lmax²

Where N=48*31 = 1488

Li = Energy at Half an hour

Lmax = Maximum energy incident on the feeder / cable during the recording period

Table 3 shows the loss load factor calculation which is found to be around 0.37.

The Average Technical loss is calculated as I²Rt *LLF. The quantity I²R is available from the

load flow report of ETAP. The time parameter is taken as whole duration of study. Here it is

taken for 31 days. i.e. is 31*24 hours. Table 4 shows the technical loss calculations. The

average technical loss is 1.47 % and the peak load technical losses are around 1.54 %.

TABLE 3:

LOAD LOSS FACTOR CALCULATION

LLF Calculation

Lmax 909.94

CPRI-Training Notes

75

Lmax2 827990.8

∑Li2 460658120.7

N 1488

LLF=(∑Li2/Lmax)/N 0.37

TABLE 4

TECHNICAL LOSS CALCULATION

Peak input of feeder, P 2559 kW

Instantaneous peak load loss from ETAP,L1 39.4 kW

Peak technical loss in %=(L1/P)*100 1.54 %

Loss load factor,LLF 0.37

Average technical loss in kWh,L2=L1*31*24*LLF 10846 kWh

Total outgoing energy of feeder, S 737666 kWh

Technical energy loss %=(L2/S)*100 1.47 %

CPRI-Training Notes

76

3.3 CASE STUDY 3

TECHNICAL LOSS ESTIMATION OF A FEEDER USING CYMEDIST SOFTWARE

This study shows the load flow of a feeder carried out using the CYMEDIST software

3.3.1 INITIAL SURVEY:

A Pole to Pole survey of the feeder was carried out along with the GPS survey for HT lines.

The data so collected was digitised using Auto CAD with GPS Co-ordinates. The Auto CAD

drawing is imported through Attach Map Module in CYMEDIST Software and the network

simulated.

3.3.2 INPUTS FOR THE NETWORK

Following data the transformer obtained from the field study is given as an input to the digitised

feeder in the software

Conductors defined (Type of conductor, resistance & reactance, capacity etc.)

Transformers ( kVA rating, %Z, X/R ratio), Tap Position

Source (Zero sequence Impedance [Z0], Positive sequence Impedance [Z1])

Base MVA and base voltage is defined

3.3.3 SIMULATION METHODS

Popular methods of simulation are the kVA-pf and Amp-pf method. Current- power factor

method is used for this feeder and the Peak current on the sample feeder is used as the input

for the analysis for ―ampere-power factor method‖

A snapshot of the feeder is shown in figure below

FIGURE 1: SNAPSHOT OF THE FEEDER

CPRI-Training Notes

77

3.3.4 RESULTS

The results obtained using Amp-pf is tabulated below

4.0 CONCLUSION

Adoption of proper energy accounting and audit facilitates increased revenue realisation,

identification of areas and causes of high energy losses and cutting down on operational

inefficiencies. It also helps in bringing accountability and efficiency to the Utility. This also

helps in pinpointing losses due to technical reason and commercial reasons

Energy accounting and auditing could be carried out either directly with that data available

(viz. Input energy, Billed energy, energy sales etc.) or can be computed with the aid of

software(s) which would not only give the losses figures continually, but also throw up

problem areas in the distribution system like over loaded conductors, Transformers etc.

5.0 REFERENCE

1. Guidelines for development if Sub-Transmission and Distribution System‖ by Central

electricity Authority, Ministry of Power, Govt.Of India.

2. Estimation of Technical and Commercial Losses for Energy Accounting in

Distribution system, M M Babu Narayanan, Proc. of Best Practices in Distribution

Loss Reduction, DRUM Training Program, 2005

3. Estimation of AT&C losses for a typical losses for a typical town in Kerala, R. Sudhir

Kumar, M. M. Babu Narayanan et. al. , 22nd

National Convention Of Electrical

Engineers, Kochi, 2006

Trails Current(A) %Losses %

Loading

1. 120 1.4 17.4

2. 200 2.3 28.8

3. 300 3.4 42.6

4. 400 4.5 56

CPRI-Training Notes

78

Reliability&quality of power supply&reliability indices

P Chandrasekhar

Distribution Systems Division

Central Power Research Institute

Bangalore-India

Abstract--The electrical utilities are facing market conditions and therefore have to plan and operate their distribution systems in a cost effective way. This implies that the customer’s requirement on reliability i.e. availability has to be balanced towards the cost for obtaining the same. An effective way to solving this issue is by the use of quantitative assessment of reliability, i.e. reliability indices, which is based on probability theory. However these methods require input data that defines the condition for the system and its components. is to predict the future behaviour based on collected data and measured performance. The system Average Interruption Frequency Index (SAIFI) for Industrial feeder is 391.470interruptions/cust.yr and the System Average Interruption Duration Index(SAIDI) for Industrial feeder is 757.488 hrs/cust-yr.The system Average Interruption Frequency Index(SAIFI) for urban feeder is 578.761interruptions/cust.yr and the System Average Interruption Duration Index(SAIDI) for urban feeder is 731.342 hrs/cust-yr.The other indices are also evaluated.

The reliability assessment is normally used to evaluate performance of the distribution system network. The reliability of power Distribution system can be calculated by different reliability indices.This paper describes the reliability indices for two feeders of one is an industrial feeder and another one is an urban feeder. A software module (Reliability Assessment Module-RAM) has been used and the results of two practical distribution feeders are compared to benchmark the performance and operation of the power distribution system.

CPRI-Training Notes

INTRODUCTION

The distribution system is an important part of the total electrical supply system, as it is

provides the final link between a utility’s bulk transmission system and its customers. It has

been reported in some literature that more than 80% of all customer interruption s occur due

to the failure in the distribution system Though a single distribution system reinforcement

scheme is relatively inexpensive compared to a generation or a transmission improvement

scheme, an electric utility normally spends large sum of capital and maintenance budget

collectively on a huge number of distribution improvement projects [6].

Directly and indirectly customer satisfaction is concerned with thisImprovement and

modernization schemes of the transmission and distribution network. Reliability assessment

which was rarely an issue some time back is now generating waves in the management of

utilities. The customers who were tolerant earlier has become demanding more. Customers are

becoming conscious about the interruptions free service. They are started realizing that how

should get electricity in which they are also stakeholders of the entire system.

Reliability of a power distribution system is defined as the ability to deliver uninterrupted

service to customer. Distribution system reliability indices can be presented in many ways to

reflect the reliability of individual customers, feeders and system oriented indices related to

substation. To evaluate reliability in distribution system, two different approaches are normally

used; namely, historical assessment and predictive assessment. Historical assessment involves

the collection and analysis of distribution system outage and customer interruption data [4]. It

is essential for electric utilities to measure actual distribution system reliability performance

levels and define performance indicators in order to assess the basic function of providing cost

effective and reliable power supply to all customer types.

Historical assessment generally described as measuring the past performance of a system by

consistently logging the frequency, duration, and causes of system component failure and customer

interruptions. The historical data is very useful when analyzed to ascertain what went wrong in the past

and therefore correct it, and also as input to predict future service reliability [2]. Historical models

summarize the actual performance of a distribution system during some time period, for example,

quarterly, half-yearly or annually. The basic data item in this case is a system failure, which is a

component outage or a customer interruption. Each failure event is taken into consideration and

analyzed according to causes of failure, duration of outage, area of the system affected. A variety of

customer and load oriented system performance indices can be derived by analyzing the recorded data.

The reliability indices are very useful for assessing the severity of interruption events Assessment of

past performance is useful in the sense that it helps to identify weak areas of the system and the need

for reinforcement [6]. It enables previous predictions to be compared with actual field experience as

well as it can serve as a guide for acceptable values in future reliability assessments. The predictive

CPRI-Training Notes

reliability assessment can also help to predict the reliability performance of the system after any

expansion and quantify the impact of adding new components to the system.

The interruptions and duration of data is collected for Complete feeder

RELIABILITY INDICES

The most commonly used system indices

are [1].

System Average Interruption Frequency Index (SAIFI)

SAIFI = Total number of customer interruptions

Total number of customers served

SAIFI is the average number of interruptions

per customer served.

System Average Interruption Duration Index (SAIDI)

SAIDI =Sum of customer interruption duration

Total number of customers served

SAIDI is the average duration of a customer interruption, per customer served.

Customer Average Interruption Duration Index (CAIDI)

CAIDI =Sum of customer interruption durations

Total number of interrupted customers

CAIDI measures the average duration of a customer interruption within the class of customers that

experienced at least one sustained interruption.

Momentary Average Interruption Frequency Index (MAIFI)

MAIFI =Total no. of customer momentary interruptions

Total number of cutomers served

CPRI-Training Notes

Average Service Availability Index

ASAI = 1 − SAIDI

8760 ∗ 100

ASAI is the ratio of total customer hours that service was available, divided by the total customer

hours in the time period for which the index is calculated.

This paper describes the reliability indices SAIFI, SAIDI, CAIDI, MAIFI and ASAI etc., for

two practical feeders (industrial feeder & urban feeder) of an Indian utility.

METHODOLOGY

A. Historial Reliability Assessment

The basic techniques used inpower systemreliabil ityevaluationcanbe dividedinto two types-

analyticaltechniqueand numerical simulation technique. Analyticaltechniquesrepresentthe

systemby a simplifiedmathematicalmodel andevaluatethereliability indicesfrom

thismodelusingdirect mathematicalsolutions. In numerical simulation techniques; i t e s t i m a t e s

thereliabilityindices bysimulatingtheactual processandrandombehaviorofthe system. The

methodthereforetreats the problemas aseries ofrealexperimentsconductedinsimulatedtime.

Itestimates probabilityandotherindicesbycountingthenumberoftimes an eventoccurs. The

solutiontime foranalyticaltechniquesisrelatively short; as c o m p a r e d with numerical

s i m u l a t i o n techniquesthis is usually extensive.This disadvantagehas been partially

overcomebythedevelopmentof recentcomputationalfacilities. To evaluate reliability indices in

power system, some of the following methods are listedbelow

Network reduction

Markov modeling

Cut-Set method

Monte Carlo simulation

In this paper Cut-Set method based on failure modes has been used to evaluate the reliability

indices. The cut-set method is a powerful one evaluating the reliability of a system for two main

reasons.

It can be easilyprogrammed on a digital computer for the fast and efficient solution of any general

network.

The cut-sets are directly related to the models of system failure and therefore identity the distinct

&discreteways in which a system may fail.

CPRI-Training Notes

It can be defined as, a cut-set is a set of system components which, when failed, causes failure of the

system. In terms of reliability network or block diagram, the above definition can be interpreted as a set

of components which must fail in order to disrupt all pathsbetween the input and output of the

reliability network.

Figure.1 Minimal cut set of the system

The minimum subset of any given set of components which causes system failure is known as

a minimal cut-set. It can be defined as, minimal cut-set is a set of system components which,

when failed, causes failure of the system but when any one component of the set has not failed

does not causes system failure. The definition means that all components of a minimal cut-set

must be in the failure state to cause system failure.

TABLE.I MINIMAL CUT-SET OF THE FIG.1

Number of the minimal cut-set

Components of the cut-set

1 AB

2 CD

3 AED

4 BEC

B . Predictive Reliability Assessment

Predicting distribution system reliability performance is normally concerned with the electric supply adequacy at the customer load point. The basic indices used in practice are load point average failure rate (𝜆), average outage duration (r), and the average annual outage time (U). For a radial system, the basic equations for calculating the reliability indices at each load point “p” in a radial circuit are [2]

A C

E

D B

CPRI-Training Notes

𝜆𝑝 = 𝜆𝑖

𝑛

𝑖=1

𝑓𝑎𝑖𝑙𝑢𝑟𝑒𝑠/𝑦𝑒𝑎𝑟

𝑈𝑝 = 𝜆𝑖

𝑛

𝑖=1

× 𝑟𝑖 𝑕/𝑦𝑒𝑎𝑟

𝑟𝑝 =

𝑈𝑝

𝜆𝑝 𝑕/𝑓𝑎𝑖𝑙𝑢𝑟𝑒

Where n is the number of outage events affecting load point “p.” The steps associated with the predictive reliability calculation approach are summarized as follows.Calculate the reliability of each load point being serviced by a given distribution system configuration considering all interruption events and system constraints contributing to its unreliability for each year of the system.Calculate the system reliability indices with the help of calculated load point average failure rate, average outage duration and the average annual outage duration.

Repeat both the stepsfor all load points of the distribution system configuration under study and obtain the all the system indices SAIFI, SAIDI, CAIDI, ASAI, ENS, AENS etc.

CASE STUDIES

(1) Industrial feeder network

The practical distribution feeder which is taken from one of the Indian utility. This feeder network has

been modeled and simulated using CYMDIST-RAM software. It is an industrial feeder starting from

220/66/11kV substation, consisting of 74 Distribution transformers (DT’s) having 140 number of total

customers served with a total feeder length of 8.64 km.

(2) Urban feeder network

This urban distribution feeder is taken from one of the Indian power distribution utility which is

modeled and simulated using CYMDIST-RAM software.It is an urban feeder starting from 66/11kV

substation, consisting of 118 Distribution transformers (DT’s) having 6966 number of total customers

served with a total feeder length of 17.78 km.

(3) Outage data & Network data collection

Electric utilities have maintained LDC’s (Load Despatch Centre) for schedule & to despatch generated

power to the distribution utilities.The distribution Utilities are maintaining log books to interruption

details for all the feeders which are coming out from a particular substation and LC (Line Clearance)

book to enter the line clearance data.We have verified and collected the interruption details for a period

of one year from respective LDC’s and the substations, which includes the number of interruptions,

duration of the interruptions, cause for interruption, Location of fault in the feeder and equipment’s

failure data for both Industrial and Urban practical distribution feeders.. Feeder network has been

modeled in CYMDIST software module and Interruption details of the components are entered in the

feeder network at appropriate places, simulation carried out successfully and results are obtained.

CPRI-Training Notes

Figure 1 Single line diagram of typical industrial feeder network

Figure 2 Single line diagram of typical urban feeder network

CPRI-Training Notes

RESULTS AND ANALYSIS

The CYMDIST Reliability Assessment Module software is validated with IEEE-RBTS

Bus-Two system network. This is more significant to evaluate the performance of our

practical distribution feeders.

Table. II result shows the reliability indices of practical industrial feeder, urban feeder and describes the performance of the practical distribution networks. These results are helpful to the local utilities to provide quality of power supply at consumer end in reliable and cost effective manner. From fig.6 the SAIFI, SAIDI values give the system frequency and duration of interruptions per year per customer basis.MAIFI gives the momentary average interruptions per year per customer. Average system availability Index (ASAI), Average energy not supplied (AENS) and energy not supplied (ENS) indices will be helpful to the utilities for proper energy and asset management with respective kilowatt hour (kWh) loss. Reliability indices can vary from one place to another place according to the network configuration, geographical and weather conditions [6].

Table. II Historical Reliability Indices of

typical distribution feeders.

Sl.

No

Historical Reliability Indices

Industrial Feeder

Urban Feeder

1 SAIFI

(Intr/cust.yr) 403.430 757.441

2 SAIDI

(hr/cust-yr) 375.159 587.148

3 CAIDI

(hr/cust.Intr) 0.930 0.775

4 MAIFI

(Intr/cust.yr) 119.238 612.739

5 ASAI 0.9572 0.93302

6 ENS( kWh/yr) 816178.9 704517.0

7 AENS

(kWh/cust-yr) 5834.016 101.137

8 No.of Customers 140 6966

9 Line Length(km) 8.64 17.78

Table III shows the Predictive reliability indices for the Industrial and Urban feeder with the help of the historical data. One year historialinterruption data is used here to get the prédictive indices.

CPRI-Training Notes

Table III Predictive Reliability Indices of

typical distribution feeders.

Sl. No

Predictive Reliability Indices

Industrial Feeder

Urban Feeder

1 SAIFI

(Intr/cust.yr) 391.470 757.488

2 SAIDI

(hr/cust-yr) 578.761 731.342

3 CAIDI

(hr/cust.Intr) 1.479 0.965

4 MAIFI

(Intr/cust.yr) 48.064 612.723

5 ASAI 0.933398 0.91657

6 ENS( kWh/yr) 1259125.4 877447.1

7 AENS

(kWh/cust-yr) 9000.181 125.961

8 No.of Customers 140 6966

9 Line Length

(km) 8.64 17.78

Fig.3 indicates the comparison of SAIFI and SAIDI ofHistorical and Predictive Reliability assessment

for Industrial feeder.

Figure 3 Comparison of SAIFI and SAIDI for Industrial feeder.

0

100

200

300

400

500

600

700

Historical Predictive

SAIFI SAIDI

CPRI-Training Notes

Fig.4 indicates the comparison of SAIFI and SAIDI of Historical and Predictive Reliability assessment for Urban feeder.

Figure 4Comparison of SAIFI and SAIDI for Urban feeder

Fig. 5 shows the Energy Not Supplied (ENS) of both the Industrial and Urban feeders in Historical and Predictive assessment. The results shows that the value of ENS in Industrial Feeder is higher than those of Urban feeder due to the higher MW rating of Industrial feeder even though the SAIFI and SAIDI of Industrial feeder is low when compared to the Urban feeder.

Figure 5 Comparison of ENS in Historical and Predictive Reliability Assessment.

0

100

200

300

400

500

600

700

800

Historical Predictive

SAIFI

SAIDI

0

200000

400000

600000

800000

1000000

1200000

1400000

Industrial Feeder Urban Feeder

ENS

(MW

h/y

r)

Historical Predictive

CPRI-Training Notes

Conclusion

The out put of the results will be useful for planners of utility to decide whether new technologies or automation to be introduced for improving reliability system.

The results will be useful to keep the track of reliability indices for future expansion.

The results shows that it needs attention for the both industrial and urban feeders to improve reliability indices in future expansion of network.

The performance can be improved by proper system planning and analysis studies to

provide switches, sectionalizers and other protective devices at appropriate places.

Acknowledgment The authors are very grateful to the organization (CPRI) for permitted to do this research

work. The authors thankful officers and associates of the Distribution Systems Division

(DSD)who are directly or indirectly helped in execution of this project.

The authors also thankful to the local utilities for their cooperation and help to get

valuabledata and information in the field for the practical distribution network.

References [1] IEEE Guide for Electric Power Distribution Reliability Indices, IEEE Std 1366, 2011Edition. [2] A.A.Chowdhury, D.O.Koval, and S.M.Islam”Areliabilitybased model for electricitypricing” 2008

AustralasianUniversities Power Engineering Conference (AUPEC’08). [3] R.N.Allan, R.Billinton, I.Sjarief, L.Goel, and K.S.So “A reliability test system for

educationalpurposes-basic distribution system data and results”IEEE Transactions on Power Systems, Vol.6, No.2, May 1991.

[4] O.Shavuka,K.OAwodele,S.P.Chowdhury and S.Chowdhury “Reliabilityanalysis of distribution network” 2010 International Conference on Power System Technology.

[5] T.K.Vrana, Johansson, “Overview of power system reliabilityassessment Techniques”21, rue d’artois, F-75008 PARIS, Cigre-RECIFE2011.

[6] V Ashok, Harikrishna K V, P.Chandrasheksr, T.Raghunatha, ‘Performance Assessment in Power Distribution System based on ReliabilityIndices’, ICPES, Kaulampur-Malaysia 2013.

CPRI-Training Notes

ROCUREMENT POLICIES AND PROCEDURES

By: Praveen Shrivastava, Joint Director (Purchase), CPRI

1. Introduction:

Procurement is defined as the acquisition of appropriate goods in relation to goods /

services at the best possible total cost of ownership. The factors of quality and quantity

are taken into account in the act of procurement. Procurement is done to meet the

needs of the owner in terms of time and location.

2. Procurement Policies:

Policy is a statement of those principles and rules that are set by management as guides.

These are the general principles laid down for the guidance of executives who are

responsible for the procurement.

3. Procurement procedures:

3.1 Procedures is a series of steps to be followed during the process of procurement. The

procurement procedure to be followed plays vital role in reducing the financial outlay

of an organization or a company. It should be economically viable, with defined

period and with high level of transparency.

3.2 The procurement involves well defined procedure such as to collect technical

information from proper sources, to collect details pertaining to the manufacturer and

supplier with their back ground and to indenting, estimation of budgetary sanction and

estimated cost to identify goods according to the end use and application, to prepare

technical specifications, floating of NIQ/NIT.

4. Procurement Manual:

4.1 Organization policies and procedures are spelt out in the form of manual. It makes

policies and procedures authoritative and free from ambiguity. It defines

responsibilities and authorities and standardizes procurement procedures.

4.2 The procurement is broadly categorized as follows:

1) Indigenous procurement (in Indian rupees)

2) Import procurement (in Foreign currency)

4.3 The indigenous procurement is done within India and all the payments is done in Indian

rupees. An import is goods procured from foreign countries and the payments are

generally made through a letter of credit under various foreign currencies.

5. Import Procedure :

5.1 All goods are imported to India through air / sea transport.

5.2 All goods imported to India have to pass through procedures of customs department for

proper examination, appraisal, assessment and evaluation. This helps the custom

authorities to charge the proper duties, taxesand also to check the goods against illegal

import. Also, it is important to note that no import to India is allowed if the importer

CPRI-Training Notes

does not have the IEC Number issued by the DGFT (Directorate General of Foreign

Trade).

6. Types of contracts:

6.1 Project management contracts : The project management contracts are mainly divided

into two types viz., Rigid contracts and Flexible contracts.

The rigid contract is the type of contract most widely used by project management

consultants. This concept identifies a clear set of deliverables that the project manager

is expected to complete and submit to the client. These deliverables have a set time

table for when they must be completed. Using rigid contracts requires the ability to

accurately forecast the cost of project, as well as the ability to make sure the project

comes in under budget allocated.

The flexible contract offers a significant degree of flexibility on part of the client and

project manager alike. Flexible contracts are largely used by start-up companies which

try to cut costs where ever applicable as well as by companies who have projects that

involve a number of unknown and / or unpredictable variables. The below mentioned

contracts may be rigid or flexible.

6.1.1 Lump sum contract: When scope of work can be estimated in full detail.

6.1.2 Unit price contract: Where either contract or quantity is not clear or volume of work

cannot be precisely estimated.

6.1.3 Turn-key contract: A turnkey contract is a contract in which one party takes full

responsibility for the construction and commissioning of a plant. This also includes

the delivering of the plant in full working condition. The contractor assumes

responsibility from beginning to the end.On completion of the contract, the complete

system is handed over to the owner as per the terms and conditions of the contract.

In turn-key project, price adjustment clause is applicable because during this period the

commodity cycle may change due to National and International economical situation

such as fall and rise in Purchase Manager‘s Index (PMI),Core inflation, consumer

inflation growth cycle, labour consumption, variation in price for ferrous and non-

ferrous metal etc.. Price adjustment is eligible if the goods are delivered within the

scheduled delivery period. The price adjustment amount can be positive or negative.

If it works to be positive, the same is payable to the contractor by the owner. If it

works to be negative, the same is recovered by owner from the contractor.

7. Work schedule:

It should be given by the contractor in the form of bar chart for theentire period of

contract. The progress can be monitored accordingly. The bar chart should be self-

explanatory about the difference phases or area of work. The beginning of the work

schedule should be from the date of award of contract.

8. Quantity variation:

Generally 10 to 20% of quantity variation is permitted in turn-key projects due to

change in price of commodities.

9. Payment terms in turn-key projects:

CPRI-Training Notes

Generally the payment in the turn-key project is made in several stages depending on

the terms and conditions of the contract and progress of the work as per the bar chart

appended with the contract. The general stages of payment remitted is as follows:

a) Advance payment:10% against bank guarantee for the equivalent amount.

b) On shipment: 70% ex-works value of goods on proof of shipment.

c) Payment after commissioning: 10% after satisfactory installation and

commissioning.

d) Balance 10% after satisfactory and successful handing over of the system and

submission of performance bank guarantee to cover the guarantee / warranty

period.

10. Value of the contract:

The large contracts should be ordered preferably to single entity in order to avoid co-

ordination among different agencies which could cause time and cost over run.

11. Advertising:

Invitation to bid shall be advertised at least in one newspaper of general circulation.

The copies of such invitations or advertisement shall be sent to the local

representative of the eligible source countries .Advertisement should include all

necessary information such as subject matter of the bid, contract address, schedules,

funding source etc. It is essentially required to advertise in the following:

a) National news paper with high circulation in English.

b) National news paper with high circulation in Hindi.

c) Local news paper with high circulation

d) On website of organization, on the portal of Ministry of Power and Ministry of

State Government.

e) Information to all the Embassies which are widely participating in the tender.

f) Physical information and sending e-mails to all the known prospective bidders.

12. Qualification requirement to participate in bidding process:

12.1 The qualification requirement is an eligibility criteria to take part in the bidding

process such as to have the Company Registration, Sales Tax / VAT / CST number,

TIN Number, PAN Number, Service Tax Number, Registered Office, License of

import etc..

12.2 This also helps to assess the financial condition of the supplier so as to avoid delay in

supplies and other hurdles that may come. In view of the non-availability of the

above documents, the firm is not allowed to participate in the bidding process.

13. Pre-qualification requirement of Bids:

The Pre-qualification requirements are stipulated so as to get competitive bids from

experienced bidders for sophisticated and high value procurements. The pre-

qualification conditions are generally as follows:

a) Turnover of the company and number of similar orders that have been executed

in last three years or so.

CPRI-Training Notes

b) Strength of Organization set-up in case of contracts for services.

c) Branches / Service Centres in the country

d) Income tax returns for last three years or so to ensure healthy regular business.

e) Excise Duty / Sales Tax paid during last three years or so to the concerned

authoritiesetc, to assess volume growth of the company and to know

continuation of the business.

f) Performance Certificate of atleast few companies for last three years or so for the

similar contracts. Any additional conditions if deemed necessary may be

included.

14. Vendors qualification and development :

14.1 The organization with a sound vendor data base is successful in identifying the

appropriate vendor to procure the specific goods at a competitive price. The data

base is prepared with the help of web search, company profiles received from

various vendors, industrial product finders etc..

14.2 To create a data base, the organization can also publish advertisement inviting for

registration. The list of vendors can also be obtained from commercial department

and DGS&D. The introduction letters, mails, visiting / business cards, personal

interaction also helps to upkeep the records.

15. Preparation of Bid Documents:

15.1 The preparation of bid documents is an essential task to compile the documents viz.,

description of equipment, its technical specifications along with relevant drawings if

required, the general terms & conditions, commercial terms & conditions, special

conditions if any, bid security form, format for Performance Bank Guarantee,

Government taxes, duties, incidentals etc..

15.2 The correct sequence of preparing the bid document will result in getting the

competitive offers avoiding the ambiguity as far as possible thereby comparing the

techno-commercial bids becomes easy for evaluation.

16. Tendering / Bidding:

16.1 Single Envelope Bidding:

16.1.1 Generally, for NIQ also called Limited Tender Enquiry, Single envelope bidding is

invited for certain defined value of procurement, generally low which depends on

procurement procedure of an organization.

16.2 Two envelope bidding:

For works, machinery and equipment for which complete technical specifications

are prepared in advance this type of bidding is adopted. Under this procedure,

bidders will be invited to submit technical and price proposals simultaneously in

two separate envelopes.The technical proposals are opened first and reviewed to

determine that they confirm to the specifications. After technical evaluation the bids

of only technical suitable offers will be opened publicly with bidders or their

CPRI-Training Notes

representatives allowed to be present. Price proposals of technically non suitable

offers shall promptly returned un opened.

16.3 Three Envelop Bidding:

The three envelope bidding is similar to the two envelope bidding except that the

first envelop consisting of Tender Fee and EMD is opened. Subsequently, the

technical proposals of only such tenderers will be opened who have submitted the

requisite tender fee and EMD.

16.4 Two stage bidding:

16.4.1 This type of bidding is adopted in the case of turnkey contracts for large and

complex plants or procurement of equipment which is subject to rapid technological

advances for which it may be impractical to prepare complete technical

specifications.

16.4.2 Under this procedure, technical bids will be first invited without prices on the basis

of the minimum operating and performance requirements. After commercial and

technical clarifications and adjustments followed by amended bidding documents

the bidder will be invited to submit final technical proposals and price bid in the

second stage.

17. Earnest Money Deposit (EMD):

EMD will usually be required, but they shall not be set to so high as to discourage

suitable bidders. EMD shall be released to unsuccessful bidders as soon as possible

after the bids have been opened. The internationally accepted amount of bid security

is around 2% of the estimated cost.

18. Requirement of Addendum:

In case where there is a need to change the specification due to some technical

reason by bid issuing authority, then these modifications are necessarily be sent to

all those bidders who have bought the tender and are requested to sendthe addendum

to the main bids before due date of opening or extended date of opening.

19. Bid Opening and Evaluation:

19.1 Duration to submit Bids:

19.1.1 The time allowed for preparation of bids shall be determined with due consideration

of the circumstances of the project and the size and complexity of the contract.

Generally, not less than 45 days shall be allowed for any type of NIT and for NIQ

minimum 15 to 30 days shall be allowed.

19.1.2 For Open Tender (Worldwide Publicity) where large civil works or complex items of

equipment are involved, generally not less than 90 days shall be allowed to enable

bidders to investigate at the site before submitting their bids.

19.2 Procedure to open bids:

19.2.1 The date, time and place of receipt and opening of bids shall be indicated in the

invitations to bids. All the bids shall be opened publicly at the stipulated time and

place by tender opening committee in the presence of representative of the bidders.

CPRI-Training Notes

Bids received after the time shall be returned unopened. The name of the bidder and

total amount of each bid should be read and recorded.This record shall be confirmed

and signed by all bidders or their representatives present at the time of opening of

bids.

19.2.2 No bidders shall be permitted to alter his bid after the bids have been opened. Only

clarifications not changing the substance of the bids are acceptable as and when

required.

19.2.3 Except as may be required by a law, no information relating to the evaluation of bids

and recommendation concerning awards shall be communicated to any persons until

a contract has been awarded to a bidder.

20. Examination of bids:

20.1 Examination shall be made in respect to formality, in areas such as material errors in

computation; conformity to specifications required in the bidding documents, proper

signatures and required EMDs. If any deviation from the above requirements or

when large discrepancies are found the bid concerned should be rejected in light of

the fundamental rules of bidding.

21. Rejection of Bids:

21.1 Rejection of all bids may be justified when (a) no bid is substantially responsive to

the bidding documents or (b) there is a lack of competition.

21.2 If all bids are rejected, buyer shall review factors that made such rejection necessary

and consider either revision of the specifications or modification of the project.

23. Evaluation and Comparison of Bids:

23.1 Among the bids which confirms to the technical specifications, the bid with the

lowest evaluated cost , not necessarily the lowest submitted price, shall be selected

for award.

23.2 Bids evaluation should be consistent with the terms and conditions set forth in the

bidding documents. Factors which may be taken into consideration include, inland

transportation, payment schedule, time of completion, operating costs, compatibility

of the equipment, availability of service and spare parts,safety,environmental

benefits etc.Provisions for price adjustment included in a bid shall not be taken in to

consideration, particularly for the procurements pertaining to non-works items.

23.3 Bidders will be required to state in their bids the CIF port of entry price for imported

gods or the Ex-factory price for other goods.

Customs duties and import taxes and similar taxes shall be taken in to account in the

evaluation of the bid.

The cost of inland freight and other expenditures incidental to the transportation and

delivery of the goods shall be included if this is specified in the bidding document.

23.4 An inspection of bidder‘s factories during the bid evaluation is acceptable provided

the buyer pays the entire cost of such inspection or as agreed between the buyer and

the bidder.

CPRI-Training Notes

24. Award of contract:

The contact is to be awarded to the bidder whose bid has been determined to be

technically meeting the requirement of specification and also to be the lowest

evaluated bid and who meets appropriate standards of capability and financial

resources.An example of factors constituting a contract is: Contract agreement,

Letter of Acceptance, Bid and Appendix to bid, conditions of contract,

Specifications, Drawings, Bill of Quantities.The award of a contract is notified to the

successful bidder by a Notice of Award, Letter of Intent, or Letter of Acceptance.

25. Currency conversion for Bid comparison:

For the purpose of comparing prices, all bid prices shall be converted to a single

currency selected by the buyer and stated in the bidding documents. The buyer shall

effect this conversion by using the exchange rate (selling) quoted by an official

source (such as the central Bank). The date prescribed in the bidding documents

should be used to prevent an arbitrary decision.

26. Currency of payment in case of imported goods:

Payment of the contract price shall be made in the currency is expressed in the bid of

of the successful bidder. The exchange rate to be usedfor the purpose of payment

shall be that specified by the bidder in the bid.

27. Price Adjustment clauses:

Is generally applicable in turn-key project whose Bidding documents shall clearly

state whether firm prices are required or adjustment of bid price is acceptable.

Specific formula for price adjustment shall be clearly stated in the bidding

documents. There should normally be no price adjustment provision for goods

pertaining to supply of non-works items. The bid with price variation clause when a

fixed price was called, may be treated as disqualified and rejected.

28. Guarantees, Performance Bank Guarantee and Retention money:

Bidding documents shall insist a performance security in the form of Bank

Guarantees to protect the buyer from default by the supplier. The amount may vary

depending on the case and is between 5 and 15% of the contract price and the

validity period normally about one year after completion of work and

commissioning or may be more as mentioned in the Bid document.

29. Liquidated damages:

Liquidated damages clause shall be included in the bidding documents for delays in

completion of delivery resulting in extra cost, loss of revenue etc.The percentage of

liquidated damages should be about 0.5% per week to a maximum of 5% of the

contract price.

30. Closing of contracts:

The contract is considered as closed when it is handed over to the owner after

successful installation and commissioning of the complete project. However, the

contractor shall furnish the Performance Bank Guarantee for the period defined in

the contract so as to cover the guarantee / warranty of the project.

CPRI-Training Notes

31. Force Majeure:

The conditions of contract included in the bidding document shall contain clauses

stipulating that failure on the part of supplier to perform their obligations under the

contract will not be considered as default if such failure is the result of force majeure

in the conditions of the contract.

32. Language:

Bidding documents should be prepared in English for International contracts and

Bilingual for Indian contracts. If another language is useda full English text shall be

incorporated in those documents.

33. Settlement of disputes:

Provision dealing with the settlement of disputes shall be included in the conditions

of contract. It is advisable that the provision be based on the ―Rules of Conciliation

and Arbitration‖ prepared by the International Chamber of Commerce. The contract

shall stipulate which laws shall govern its interpretation and performance.

CPRI-Training Notes

Distribution Reforms in India: APDRP, R-APDRP &RGGVY

Viji Bharathi, Engineering Officer, Distribution Systems Division, CPRI

1.0 Introduction

In India, restructuring of the power sector was felt due to the scarcity of financial resources

available with Central and State Governments and the necessity of improving the technical

and commercial efficiency of the Electricity distribution. Due to lack of adequate

investment on Transmission and Distribution (T&D) works, the T&D losses had been

consistently on the higher side. To lead the reforms the Regulatory Commissions were

formed in 1998 under the Electricity Regulatory Commissions Act 1998 (Central Law) to

promote competition, efficiency and economy in the activities of the electricity industry.

Ministry of Power, Government of India has undertaken reforms in power sector with a step

by the Electricity Act 2003 and then during the X five year plan, the ―Accelerated Power

Development Programme‖ (APDP) was launched in 2001-02 and was renamed as

―Accelerated Power Development and Reforms Programme (APDRP)‖ was launched in

2002-03. Another scheme,―Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY)‖ was

launched during April 2005. The main aim of APDRP was restoring the economic viability

of the state utilities and that of RGGVY is to provide Rural Electrification Infrastructure and

Household electrification.

2.0 Overview

The objective of reforms is to bring in commercial viability in the power sector so as to

ensure power supply on demand to all consumers at reasonable rates. The main features of

the reforms strategy involve [2]:

i) Functioning of Regulatory commissions in the states. A credible independent

Regulatory commission is a primary requisite for generating confidence for private

investment on a significant scale.

ii) Full audit of energy flow at all levels so as to accurately identify where the energy is

being consumed or lost. This would require metering at all substations and feeders.

iii) Effective elimination of power thefts. All consumers of power need to be metered in a

time bound programme.

iv) Tariffs which provide for commercial viability. The state governments would need to

provide explicit subsidies for large groups as cross subsidy beyond a point is not

sustainable.

v) Design and implementation of cost-effective investment for improving the sub

transmission and Distribution network to reduce avoidable technical losses.

CPRI-Training Notes

3.0 Accelerated Power Development and Reforms Programme (APDRP)

The Accelerated Power Development Reforms Programme (APDRP) was launched in 2002-

03 with additional central financial assistance to the states to strengthen and upgrade the

sub-transmission and distribution systems of high-density load centres like towns and

industrial areas with main objectives of reduction in AT& C losses; improve quality and

reliability of power supply. Total 574 projects at the cost of Rs.17329.07 Crore were

sanctioned in 10th Plan APDRP. On implementation of APDRP, the AT & C losses could

be brought down below 20% in 215 towns (163 towns less than 15% & 52 towns between

15-20%) in the country.

3.1 Main Objectives

The main objective of APDRP was to bring down the AT&C losses to below 15% in urban

and high density areas.The other objectives being: improving customer satisfaction,

increasing reliability of power supply, improving quality of supply, adopting systems

approach with MIS, and bringing transparency through computerisation.

The concept of Aggregate Technical and Commercial (AT&C) losses was introduced as the

T&D loss was not able to capture all the losses in the network.

3.2 Initiatives/ Inventions for achieving the objectives:

Commercial: Commercial activities target reduction of commercial losses and

improvement of revenue through Indexing of consumers to distribution transformers,

installation of tamper proof meters at all levels of transformation of electricity and for all

consumers, Operationalizing energy audit & accounting up to LT feeder level by index

linking, de-centralized billing & collection.

Technical: Technical activities required detailed system analysis to evaluate cost-effective

options for system up gradation and improvement, technical loss reduction and voltage

profile improvements. This involved augmenting/ upgrading over loaded/ failure prone

network elements like transformer, feeder, capacitor etc., to minimize interruptions, moving

towards LT less system with the object of progressively achieving high voltage distribution

system (HVDS), installation of small capacity energy efficient distribution transformers, re-

conductoring of over loaded lines, power factor correction, IT aided monitoring and control

(MIS), GIS mapping etc.

Organizational: This involved reorganizing the manpower at the circle level from the

Superintending Engineer to Junior Engineer and fixing duties, responsibilities and

accountability at each level with a clear line of command. It also involved the activities like

integration of technical, commercial and administrative functions at the circle and 11kV

feeder level to enable circles and feeders to operate as profit centres and business units

CPRI-Training Notes

respectively. The billing collection mechanism was to be decentralized to the feeder level

with a system of incentives for the staff at the circle and the feeder level for efficiency in

billing and collection targets.

Capacity Building:To assist the State Electricity Boards (SEBs)/ Utilities in technical and

management skills to enable them to formulate and implement circle level distribution

projects, Ministry of Power had appointed National Thermal Power Corporation Ltd.,

(NTPC) and Power Grid Corporation of India Ltd., (PGCIL) as lead Advisor-cum-

Consultants (AcCs). Their responsibilities were to assist in capacity building in the SEBs

by focusing on the activities required for undertaking the commercial, technical &

organizational measures required in the short terms and long terms in addition to

supervising the project implementation.

3.3 Projects sanctioned under APDRP

Projects included major towns and industrial areas across the country including various

states in addition to the 63 circles which were originally identified in 2000-01 to be

developed as centres of excellence. These circles had certain short & long term measures to

be considered essential to meet the objectives of the programme. These are to be developed

as pilot projects and made suitable for replication in the other parts of the country.

During 2002-03, projects involving major towns and industrial areas were sanctioned to

fulfil the short-term objectives i.e., revenue increase and outage reduction.

3.4 Steps for implementation of APDRP

The following steps were involved the following through Memorandum of Understanding

(MoU) and Memorandum of Agreement (MoA):

(i) Setting up of State Electricity Regulatory Commission (SERC)

(ii) Restructuring of State Electricity Boards (SEB)

(iii) Administrative measures for improvement

(iv) Delegation of powers & duties

(v) Metering up to 11 kV feeder level and energy accounting

(vi) 100% Metering of all consumers

(vii) Computerisation of SEB commercial and technical functions

(viii) Adoption of turnkey contracts for APDRP implementation

(ix) Agricultural tariff policy and subsidy by State Government and

(x) Adoption of unit wise commercial accounting practices.

Preparation of DPR: The Detailed Project Report (DPR) was prepared containing the data

in accordance with the ―Guidelines for strengthening of sub-transmission & distribution

system‖ issued by the Committee of experts. The DPR included the methodology and time

schedule for execution of the works, fund flow requirements, prevailing benchmark

parameters for assessing the performance etc. The DPR was to show the cost benefit

CPRI-Training Notes

analysis and sensitivity analysis on critical parameters assumed for financial viability of the

project. The same approved by MoP and checked by the Financial Institutions was

forwarded to Ministry of Finance (MoF) for release of the sanctioned funds based on the

MoA.

3.5 Funding Mechanism

Projects worth Rs.15,642Cr approximately were sanctioned initially which were to be

implemented within 2-3 years. The APDRP investment component was estimated to be

around Rs.20,000 Cr. Additional Rs.20,000 Cr was considered for incentive for cash loss

reduction to encourage the State Utilities and disbursed pro-rata based on actual

performance on ground.

The funding modalities were:

Sl.No. Category of States % of Projects/ Scheme Cost

from APDRP as

% of Projects Scheme

Cost from PFC/ REC/

Own/Other Sources Grant Loan

1 Special Category States 90 10 -

2 Non-special Category

States 25 25 50

APDRP was used as an instrument to leverage reforms in the State power sector. Thus the

funds under APDRP were released only to those States which had executed a MoU with the

Ministry of Power (MoP) committing to a time-bound reforms and restructuring process in

the State power sector.

3.6 Advisor cum Consultants

In the first phase AcCs were appointed to assist States in formulation of DPR and oversee

the implementation of the project. During November 2001, NTPC and Power Grid were

identified as the lead AcCs where CPRI, MECON, WAPCOS, NPC and ERDA were

brought under them as AcCs.

3.7 Status of APDRP

The APDRP scheme fell short of expectations, with the result of over Rs.176.12 billion

worth of projects sanctioned till March 2005, total investment was only Rs.57.68 billion or

just 32.75 per cent. Also, it was seen that while the target of reducing AT&C losses was

CPRI-Training Notes

from around 40 per cent to 15 per cent over five years, the actual reduction was not more

than 5 per cent, that is 35 per cent. Even then, the AT&C losses varied widely between

states from 18 per cent to as much as 60 per cent.

It was because of this that the Central Government came out with the R-APDRP scheme,

with the aim of restoring the commercial viability of the distribution sector by putting in

place mechanisms that lead to a substantial reduction in Aggregate Technical and

Commercial (AT&C) losses on a sustainable basis.

3.8. Conclusions

The success of APDRP in establishing the financial viability of the distribution system can

be improved depending on the choice of elements to be funded, speed of execution,

organizational commitment and public, political as well as administrative support. A

scientific result oriented approach is to be adopted while formulation of the schemes for

funding. Since the programme is result oriented, necessity for setting up of the bench marks

to be achieved and the mechanism for achieving the same arises. The six level interventions

for implementation were not really successful at all levels. There was a delay in release of

funds from the states to the utilities. The results of the programme could not be measured to

a reliable extent due to lack of baseline data. Realizing the shortcomings of APDRP, the

Government came up with another programme, the ―R-APDRP‖ to overcome the

shortcomings of APDRP.

4.0 Restructured APDRP (R-APDRP)

The Govt. of India proposed to continue R-APDRP during the XI Plan with revised terms

and conditions as a Central Sector Scheme. The Programme started during 2008-09 with the

main objective of reducing the Aggregate Technical and Commercial (AT&C) losses with a

focus on actual, demonstrable performance in terms of sustained loss

reduction.Establishment of reliable and automated systems for sustained collection of

accurate base line data and the adoption of Information Technology in the areas of energy

accounting will be essential before taking up the regular distribution strengthening projects.

4.1Programme Coverage

It is proposed to cover urban areas - towns and cities with population of more than 30,000

(10,000 in case of special category states). In addition, in certain high-load density rural

areas with significant loads, works of separation of agricultural feeders from domestic and

industrial ones and of High Voltage Distribution System (11kV) will also be taken up.

Further, towns / areas for which projects have been sanctioned in X Plan R-APDRP shall be

considered for the XI Plan only after either completion or short closure of the earlier

sanctioned projects.

4.2Proposed Scheme

CPRI-Training Notes

Projects under the scheme shall be taken up in Two Partsi.e. Part-A and Part-B. Part-A shall

include the projects for establishment of baseline data and IT applications for energy

accounting/auditing & IT based consumer service centres. Part-B shall include regular

distribution strengthening projects. The activities to be covered under each part are as

follows:

Part - A: Preparation of Base-line data for the project area covering Consumer Indexing,

GIS Mapping, Metering of Distribution Transformers and Feeders, and Automatic Data

Logging for all Distribution Transformers and Feeders and SCADA / DMS system (only in

the project area having more than 4lakhs population and annual input energy of the order of

350 MU). It would include Asset mapping of the entire distribution network at and below

the 11kV transformers and include the Distribution Transformers and Feeders, Low Tension

lines, poles and other distribution network equipment. It will also include adoption of IT

applications for meter reading, billing & collection; energy accounting & auditing; MIS;

redressal of consumer grievances; establishment of IT enabled consumer service centres etc.

The base line data and required system shall be verified by an independent agency

appointed by the Ministry of Power.

Part- B: Renovation, modernization and strengthening of 11 kV level Substations,

Transformers/Transformer Centres, Re-conductoring of lines at 11kV level and below, Load

Bifurcation, feeder separation, Load Balancing, HVDS (11kV), Aerial Bunched

Conductoring in dense areas, replacement of electromagnetic energy meters with tamper

proof electronic meters, installation of capacitor banks and mobile service centres etc. In

exceptional cases, where sub-transmission system is weak, strengthening at 33 kV or 66 kV

levels may also be considered.

Part - C: An enabling component for the implementation of APDRP and for facilitating the

process of reforms in the power sector. This part, to be implemented by Ministry of Power/

PFC, will include:

Preparation of a template for System Requirement Specifications for sub-division

automation and for customer relations management module, as well as for automated

baseline data collection systems.

Validation of the Baseline Data System to be done by independent agencies identified

through bidding process by the Ministry or its nominee. Independent agencies will also

verify the AT&C losses and monitor quality of works to be executed under Part-B.

Project Advisors and Project Management Consultants – Project advisor and project

management consultants will be appointed to assist the Ministry in monitoring of

APDRP and to validate the project proposals submitted by the Distribution companies.

They will also facilitate in standardisation of bidding/contract documents, monitoring of

progress, quality assurance etc. They will also facilitate the Management Information

System.

CPRI-Training Notes

Project Evaluation by Third Part Introduced in the X Plan will continue and will be the

basis of computation of the extent of conversion of loan into grant for the specific

project. A panel of Project evaluators will be finalized through a bidding process.

Capacity Building and development of franchisees in Distribution sector will be a major

focus area to provide training to employees of the Distribution companies and existing

&prospective franchisees in management, technical, commercial and consumer related

areas, exposure to latest developments in electricity distribution, loss reduction, theft and

pilferage control within India and abroad, dissemination of knowledge through Best

Practice Workshops and Conferences, standardization of specifications of equipment

required in electricity distribution network, standardisation of contractual documents for

outsourcing project management, turnkey jobs, franchising etc.

Consumer Attitude Survey will be carried out to assess the impact of the measures taken

in the distribution sector towards improving of services, improving the reliability and

quality of power supply.

4.3Eligibility Criteria for R-APDRP assistance

The States / Utilities will be required to:

1) Constitute the State Electricity Regulatory Commission for availing assistance under re-

structured APDRP.

2) Achieve the following target of AT&C loss reduction at utility level:

a) Utilities having AT&C loss above 30%: Reduction by 3% per year

b) Utilities having AT&C loss below 30%: Reduction by 1.5% per year

3) Commit a time frame for introduction of measures for better accountability at all levels

in the project area

4) Submit previous year's AT&C loss figures of identified project area as verified by an

independent agency appointed by Ministry of Power (MoP).The independent agency

would verify that:

a) All input points are identified and metered with downloadable meters for energy

inflow accounting in scheme area

b) All outgoing feeders are to be metered in substation with downloadable meters

c) Scheme area should be ring fenced i.e. export and import meters for energy

accounting shall be ensured besides segregating the rural load of the scheme area by

ring fencing if not on separate feeder

CPRI-Training Notes

d) The above shall provide the input energy and corresponding cash collected for

calculating AT&C losses. The same shall be carried out for at least for three billing

cycles and got verified by the independent agency. This loss level will be the

baseline for considering conversion of loan into grant for Part B projects

5) Devise a suitable incentive scheme for staff in the project area linked to achievements of

milestones.

4.4Funding Mechanism

Part – A: Initially 100% funds for the approved projects shall be provided through loan

from the Government of India on the terms decided by Ministry of Finance. The loan shall

be converted into grant once the establishment of the required system is achieved and

verified by an Independent agency.The interest on the converted loan shall be capitalised.

No conversion to grant will be made in case Part A is not completed within 3 years from the

date of sanctioning of the project. The project will be deemed to be completed on the

establishment of the required system duly verified by an independent agency appointed by

Ministry of Power(MoP).

Part – B: Initially upto 25% funds for the projects shall be provided through loan from the

Government of India (GoI) on the terms decided by Ministry of Finance. For special

category States, GoI loan would be 90%. However, the project-wise requirement of Gross

Budgetary Support will be decided by the Steering Committee. The balance funds shall be

raised from Financial Institutions (FIs). All other conditions/ methodology applicable to

non-special category states shall also be applicable to the special category states. If

distribution Utilities achieve the target of 15% AT&C loss on a sustained basis for a period

of 5 years in the project area and the project is completed within the time schedule fixed by

the Steering Committee, which shall in no case exceed five years from the date of project

approval upto 50% (90% for special category states) loan against Part B projects will be

convertible into grant in equal tranches, every year for 5 years starting at the latest one year

after the year in which the Part A of the project area concerned is established and verified

by the Independent Agency appointed by MoP. If the Utility fails to achieve or sustain the

15% AT&C loss target in a particular year, that year‘s tranche of conversion of loan to grant

will be reduced in proportion to the short fall in achieving 15% Aggregate Technical and

Commercial (AT&C) loss target from the starting baseline assessed figure. The interest on

the converted loan from GoI and FIs will be capitalized on an annual basis. Illustration is

given through a typical example as shown below:

Typical Example:

Take the example of a distribution utility from a non –special category state whose starting

AT & C loss figure is 60% in the year 2008-09, the year in which the base line data system (

Part A ) is established and verified by the independent agency appointed by MoP .If this

distribution utility archives and sustains the 15% AT & C loss level for a period of 5 years

after the grace period of one year i.e. 2009-10,one fifth of the 50% loan shall be converted

into grant each year from the year 2010-11 onwards. However, if this distribution utility

CPRI-Training Notes

could only achieve AT & C loss figures of 30%, 40%, 30%, 15% and 20% in 1st, 2

nd, 3

rd,

4th

& 5th

year respectively of the period in question, the year wise loan conversion into grant

shall be as follows:

2010-11 1st year: (60-30)/60-15) i.e 2/3 of annual tranche (1/5 of 50% loan i.e

10% of project cost) shall be converted into grant.

2011-12 2nd

year:(60-40)/(60-15) i.e. 4/9 of annual tranche (1/5 of 50% loan i.e. 10%

of project cost)shall be converted into grant.

2012-13 3rdyear: (60-30)/(60-15) i.e. 2/3 of annual tranche (1/5 of50% loani.e.10% of

project cost) shall be converted intogrant.

2013-14 4th

year: (60-15)/(60-15) i.e.full annual tranche (1/5 of 50% loan i.e.

10% of project cost) shall be converted into grant.

2014-15 5th

year : ( 60-20)/(60-15) i.e. 8/9 of annual tranche ( 1/5 of 50% loan i.e.

10% of project cost ) shall be converted into grant.

4.5Sanction Process

The sanction process and other formalities for execution of Part A and Part B components

can be taken up simultaneously except that Part B activities are likely to start 3-6 months

after the start of Part A for making arrangements of ring fencing for the project area and

verification of the starting figure of AT&C loss of the project area by Independent Agency

appointed by MoP with three billing cycle data. This may not be necessary where ring

fencing of the project area has already been done by the state utilities except for the time

required for verification of the starting figure of AT&C loss of the project area. This would

help the utilities to reduce the overall project execution cycle.

Conversion into grant will take place annually based on AT&C loss figures of the project

area as on 31st Mar duly verified by the Independent Agency appointed by MoP.

Incentive Scheme for Utility Staff: Scheme also envisages incentive for Utility staff in

towns where AT&C loss levels are brought below 15%. Each Distribution company will be

required to implement an incentive programme for utility employees of the specific project

area. Details of the incentive scheme and the milestones/achievements that trigger incentive

payments shall be agreed to project proposals presented by each utility. A maximum

amount equivalent to 2% of the grant for Part B project is allocated for this purpose. The

utility is expected to match these funds and disburse the total amount among its employees

according to a suitably devised incentive scheme. Each utility must submit a duly approved

incentive scheme prior to seeking disbursements under Part-B. State Governments and

distribution companies will work with the concerned regulator to ensure that a part of the

financial benefits arising out of the AT&C loss reduction are also passed on to the

consumers of the project area.

CPRI-Training Notes

4.6The modalities of formulating / implementing projects under the

programme are as under:

1. Project Formulation: The utilities shall prepare Detailed Project Reports (DPRs) in two

parts (i.e. Part –A & Part-B) for each of the project areas and while forwarding the DPRs

to the Nodal Agency indicate the order of priority of the projects. Utilities may appoint

IT Consultants through bidding from an open bidding process from the panel of IT

consultants prepared by the Nodal Agency for preparing DPRs of Part-A projects. IT

consultants shall be empanelled by the Nodal Agency / MoP after observing formalities.

Utilities may also prepare DPRs for Part-A on their own in case they feel that they have

the skill and expertise to do so. Hiring charges of the IT Consultant may be included in

the project cost of Part-A only if an IT consultant is appointed from the panel prepared

by the Nodal Agency and same is appointed through competitive bidding. DPRs for Part-

A shall be submitted by utilities along with an undertaking indicating that the DPR is

duly verified either by the IT Consultant so appointed or else by the utility itself. These

DPRs shall be submitted to PFC, the Nodal Agency. These DPRs will be validated and

appraised techno- commercially by PFC and will then be submitted to the APDRP

Steering Committee for approval. Further guidelines as required for formulation of

projects would be issued by Ministry of Power from time to time.

2. Implementation: SEBs / State utilities shall implement projects sanctioned under this

programme on a turnkey basis by appointing the IT Implementing Agencythrough a

bidding process only from the Panel of IT implementing Agenciesnotified by the Nodal

Agency to ensure quality and expeditious implementation. IT implementing agencies

shall be empanelled by the Nodal Agency / MoP after observing nodal formalities.

Further guidelines as required for implementation of projects would be issued by

Ministry of Power from time to time.

3. Quadripartite Agreement: A Quadripartite Agreement will be entered into between

SEBs / Utilities, GoI, PFC and the State Government to implement the re-structured

APDRP. Signing of Quadripartite Agreement is a prerequisite for release of funds under

re-structured APDRP. The Ministry of Power / PFC will monitor implementation of

precedent conditions agreed to in the Quadripartite Agreement before releasing funds. If

considered necessary, Ministry of Power may impose such conditional ties as it deems fit

for the implementation of re-structured APDRP from time to time.

The programme would be of the size of Rs.51,577Crores under Central Sector Scheme.

Initially Rs.50,000Crores will be provided / arranged as loan from GoI/ FI‘s out of which as

estimated amount of Rs.30,000 Crores would be converted into grant. The total grant from

GoI is estimated as Rs.31,577 Crores. However the actual requirement would depend on the

achievements of targets by the utilities.

a) Rs.50,000 Crore for Part A and Part B of the projects.

Rs.10,000 Crore for Part A activities

CPRI-Training Notes

Rs.40,000 Crore for Part B activities

b) Rs.1,177 Crore for enabling activities to be implemented by MoP (Part-C)

Rs.850 Crore for the services rendered by the Nodal agency

Rs.200 Crore for capacity building and franchisee development exposure to latest

developments in electricity distribution within India and abroad

Rs.50 Crore for few pilots for adopting new innovations

Rs.77 Crore for miscellaneous activities such as ―Best Practices‖ workshops and

conferences; Consumer Attitude survey, Project Specific Evaluation; Standardisation of

specifications of equipment and contractual documents

c) Rs.400 Crore for incentive to Utility Staff of the project areas for establishment of

baseline data and for achieving targeted reduction in AT&C loss.

4.7General terms and conditions for utilisation of funds

The funds under the programme will be provided to the State Power Utility/Distribution

Company through PFC, the Nodal Agency. Budget provision for the funds shall be made

annually.

State Power Utility/Distribution Company receiving APDRP assistance will have to open a

separate account/ sub account head immediately, for separate accounting classification, both

on the receipt and expenditure side for enabling proper Audit Certification, including

escrow account in the bank.

The reduction of T&D losses as part of overall AT&C losses would also enable the utilities

to claim carbon credits for avoiding power generation under CDM mechanism subject to

necessary approvals. The state utilities will be encouraged to take advantage of CDM

benefits for reducing the cost of the scheme and making it financially viable. A cell for

facilitating the same shall be created in the Nodal Agency.

The loan under the programme through GBS from GoI shall be subject to the terms and

conditions laid down by the Ministry of Finance/ GoI at the time of release.

Funds provided to the State Power Utility/ Distribution Company under APDRP cannot be

diverted to any other scheme or used for any other purpose.

The State Governments/ State Power Utilities would be required to submit to PFC/MoP

monthly progress report in respect of the progress of execution of project, fund Utilization

by the State Power Utility/Distribution Company etc.

CPRI-Training Notes

4.8 Status of R-APDRP

A total of 30 projects (States & Union territories) with 1412 towns costing

Rs.5347.38Crores have been sanctioned and Rs.2527.30Crores of loan is disbursed under R-

APDRP Part A.

A total of 19 projects (States & Union territories) with 72towns costing Rs.1601.28Crores

have been sanctioned and Rs.424.17Crores of loan is disbursed under R-APDRP SCADA.

A total of 26 projects (States & Union territories) with 1244 towns costing

Rs.31139.48Crores have been approved and Rs.4311.58Crores of loan is disbursed under R-

APDRP Part B.

5.0 Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY)

RGGVY is a scheme of Rural Electricity Infrastructure and Household Electrification for

the attainment of the National Common Minimum Programme (NCMP) goal of providing

access to electricity to all households in five years. Rural Electrification Corporation (REC)

is the nodal agency for the programme. RGGVY was launched in April-05 by merging all

on-going schemes. Under the programme, 90% grant is provided by Government of India

and 10% as loan by REC to the State Governments.

Under the 10th

plan, a capital subsidy of Rs.5000Cr is approved for Phase I of the scheme.

5.1 RGGVY aims at: Electrifying all villages and habitations as per new definition

Providing access to electricity to all rural households

Providing electricity connection to Below Poverty Line (BPL) families free of charge.

5.2 Scope of RGGVY

Under the scheme, projects could be financed with capital subsidy for provision of:

Rural Electricity Distribution Backbone (REDB) with 33/11 KV or 66/11 KV sub-

stations of adequate capacity and lines in blocks where these do not exist

Creation of Village Electrification Infrastructure (VEI) with provision of distribution

transformers of appropriate capacity in electrified villages / habitation(s). (Habitations with

a population of above 100 for XI-Plan)

Decentralised Distributed Generation (DDG) system based on conventional&non-

conventional energy sources where grid supply is not feasible or cost-effective.

CPRI-Training Notes

5.3 Implementation Methodology and conditions:

Preparation of District based detailed project reports for execution on turnkey basis.

Involvement of central public sector undertakings of power ministry in implementation

of some projects.

Certification of electrified village by the concerned Gram Panchayat.

Deployment of franchisee for the management of rural distribution for better consumer

service and reduction in losses.

Undertaking by States for supply of electricity with minimum daily supply of 6-8 hours

of electricity in RGGVY network.

Making provision of requisite revenue subsidy by the state.

Determination of Bulk Supply Tariff (BST) for franchisee in a manner that ensures

commercial viability.

Three tier quality monitoring Mechanism for XI plan Schemes made mandatory.

Web based monitoring of progress

Release of funds linked to achievement of pre-determined milestones

Electronic transfer of funds right upto the contractor level

Notification of Rural Electrification Plans by the state governments

REDB, VEI and DDG would also cater to the requirement of agriculture and other

activities including

• irrigation pumpsets

• small and medium industries

• khadi and village industries

• cold chains

• healthcare

• education and IT

This would facilitate overall rural development, employment generation and poverty

alleviation.

5.4 Rural Household Electrification of Below Poverty Line Households:

Electrification of un-electrified Below Poverty Line (BPL) households would be financed

with 100% capital subsidy as per norms of Kutir JyothiProgramme in all rural habitations.

Households above poverty line would be paying for their connections at prescribed

connection charges and no subsidy would be available for this purpose.

CPRI-Training Notes

The over-all subsidy should be kept within 90% of the over-all project cost.

In the management of rural distribution through franchisees who could be Non-

Governmental Organisations (NGOs), Users Association, Cooperatives or individual

entrepreneurs, the Panchayat institutions would be associated. The franchisees arrangement

could be for system beyond and including feeders from substation or from and including

Distribution Transformer(s).

5.5 Franchisees :

In the management of rural distribution through franchisees who could be Non-Governmental Organisations (NGOs), Users Association, Cooperatives or individual entrepreneurs, the Panchayat institutions would be associated. The franchisees arrangement could be for system beyond and including feeders from substation or from and including Distribution Transformer(s).

5.6 Revenue Sustainability

Based on the consumer mix and the prevailing consumer tariff and likely load, the Bulk

Supply Tariff (BST) for the franchisee would be determined after ensuring commercial

viability of the franchisee. Wherever feasible, bidding may be attempted for determining the

BST. This Bulk Supply Tariff would be fully factored into the submissions of the State

Utilities to the State Electricity Regulatory Commissions (SERCs) for their revenue

requirements and tariff determination. The State Government under the Electricity Act is

required to provide the requisite revenue subsidies to the State Utilities if it would like tariff

for any category of consumers to be lower that the tariff determined by the SERC. While

administering the scheme, prior commitments may be taken from the State Government

regarding –

a) Determination of bulk supply tariff for franchisees in a manner that ensures their

commercial viability.

b) Provision of requisite revenue subsidy by the State Government to the State Utilities as

required under the Electricity Act.

5.7 The capital subsidy for eligible projects under the scheme would be given through

REC. These eligible projects shall be implemented fulfilling the conditionality‘s

indicated above. In the event the projects are not implemented satisfactorily in

accordance with the conditionality‘s indicated above, the capital subsidy could be

converted into interest bearing loans.

CPRI-Training Notes

5.8 The services of Central Public Sector Undertakings (CPSUs) have been offered to the

states for assisting them in the execution of Rural Electrification Projects as per their

willingness and requirement. With a view to augment the implementation capacities for

the programme, REC has entered into Memorandum of Understanding (MOUs) with

NTPC, POWERGRID, NHPC AND DVC to make available CPSUs‘ project

management expertise and capabilities to states wishing to use their services. This is

being operationalised through a suitable Tripartite Agreement.

5.9 Upto 1 per cent of the total subsidy under the scheme would be used for associated

works / efforts of the programme linked to research, technology development, capacity

building, information system development, awareness and other administrative and

associated expenses and undertaking of pilot studies and projects complimentary to this

rural electrification scheme.

5.91 This scheme merges the existing ―Accelerated Electrification of one lakh Villages and

one crore Households‖ and the Minimum Needs Programme for rural electrification.

6.0 RGGVY in the XI plan

Continuation of RGGVY- Scheme of Rural Electricity Infrastructure and Rural Household

Electrification has been sanctioned in the XI-Plan for attaining the goal of providing access

to electricity to all households, electrification of about 1.15lakh un-electrified villages and

electricity connections to 2.34 crore BPL households by 2009. The approval has been

accorded for capital subsidy of Rs.28000 crores during the XI-Plan period.

Unlike the RGGVY of the X-Plan where the scope of the scheme remains, the funding

mechanism will be on same pattern for 90% subsidy while 10% can be from REC or from

own funds of the state/loan from financial institutions. The Monitoring committee on

RGGVY, while sanctioning DDG projects shall coordinate with MNRE to avoid any

overlap. The provision for subsidy requirement for DDG is Rs.540crores.

REDB, VEI and DDG would indirectly facilitate power requirement of agriculture and other

activities including irrigation pump sets, small and medium industries, khadi and village

industries, cold chains, health care, education and IT etc. This would facilitate overall rural

development, employment generation and poverty alleviation.

The rate of reimbursement for providing free connections to BPL households would be

Rs.2200 per household. Households above poverty line are to pay for their connections at

prescribed connection charges and no subsidy would be available for this purpose.

Wherever SC/ST population exists among BPL households and subject to being eligible

otherwise, they will be provided connection free of cost and a separate record will be kept

CPRI-Training Notes

for such connection.

Three-Tier Monitoring Mechanism: The Quality Control Mechanism would be governed by

the Quality Control Manual prepared by REC for the Scheme.

7.0RGGVY in the XII & XIII plan

Continuation of RGGVY - Scheme of Rural Electricity Infrastructure and Rural Household

Electrification in the 12th

& 13th

plan for:

Completing spillover works of projects sanctioned in the 10th

& 11th

plan

Continuing the scheme for covering all remaining census villages and habitations

with population of above 100

Providing free electricity connections to BPL households at the rate of Rs.3000 per

connection in villages and habitations with population of above 100

Extending DDG to grid connected areas to supplement the availability of power in

areas where power supply is less than six hours a day.

The villages and habitations which have not been covered under RGGVY in 10th

& 11th

plan

projects would be eligible for consideration in 12th

plan. Besides these, villages and

habitations covered in 10th

& 11th

plan projects would also be eligible for the purpose of

covering the remaining BPL households.

CPRI-Training Notes

Progress report of village electrification as on 31.05.2014 as per 2011

Sl. No

States/ UTs

Total in habited

villages as per 2011 census

villages electrification as

on 31.03.2014 (provisional)(#)

Cumulative achieve-

ment as on 31.05.2014

%age of villages

electrified as on

31.05.2014

Un-electrified villages as

on 31.05.2014

Numbers %age

1 Andhra Pradesh 26286 26286 100 26286 100 0

2 Arunachal Pradesh 5258 3586 68.2 3586 68.2 1672

3 Assam 25372 24404 96.2 24404 96.2 968

4 Bihar 39073 37002 94.7 37316 95.5 1757

5 Chattisgarh 19567 19055 97.4 19055 97.4 512

6 Goa 320 320 100 320 100 0

7 Gujarat 17843 17843 100 17843 100 0

8 Haryana 6642 6642 100 6642 100 0

9 Himachal Pradesh 17882 17880 99.9 17880 99.99 2

10 Jammu & Kashmir 6337 6224 98.2 6224 98.2 113

11 Jharkhand 29492 27142 92 27142 92 2350

12 Karnataka 27397 26704 97.47 26704 97.5 693

13 Kerala 1017 1017 100 1017 100 0

14 Madhya Pradesh 51929 50381 97 50394 97 1535

15 Maharashtra 40956 40920 99.9 40920 99.9 36

16 Manipur 2379 2061 86.6 2061 86.6 318

17 Meghalaya 6459 5132 79.5 5132 79.5 1327

18 Mizoram 704 650 92.3 650 92.3 54

19 Nagaland 1400 1261 90.1 1261 90.1 139

20 Odisha 47677 38920 81.6 38920 81.06 8757

21 Punjab 12168 12168 100 12168 100 0

22 Rajasthan 43264 39036 90.2 39036 90.2 4228

23 Sikkim 425 425 100 425 100 0

24 Tamil Nadu 15049 15049 100 15049 100 0

25 Tripura 863 837 97 837 97 26

26 Uttar Pradesh 97813 96515 98.7 96515 98.7 1298

CPRI-Training Notes

Annexure-I

Sl. No

States/UTs

Total in habited

villages as per 2011 census

villages electrification as

on 31.03.2014 (provisional)(#)

Cumulative achieve-

ment as on 31.05.2014

%age if villages

electrified as on

31.05.2014

Un-electrified villages as

on 31.05.2014

Numbers %age

Union Territories

1 A&N Island 396 308 77.8 308 77.8 88

2 Chandigarh 5 5 100 5 100 0

3 D&N Haveli 65 65 100 65 100 0

4 Daman & Diu 19 19 100 19 100 0

5 Delhi 103 103 100 103 100 0

6 Lakshadweep 6 6 100 6 100 0

7 Pondicherry 90 90 100 90 100 0

Total (UTs) 684 596 87.1 596 87.1 88

Total 597464 571155 95.6 571482 95.7 25982

(^) villages in forest area

(#) The figures are provisional and subject to confirmation from States.

27 Uttarkhand 15745 15638 99.3 15638 99.3 107

28 West Bengal 37463 37461 99.99 37461 99.99 2

Total (States) 596780 570559 95.6 570886 95.7 25894

CPRI-Training Notes

Annexure-II

SCHEME ON RURAL ELECTRICITY INFRASTRUCTURE

AND VILLAGE ELECTRIFICATION

COST ESTIMATES OF THE SCHEME

Rs. In crore

1. Electrification of 125,000 un-electrified villages

which includes interalia development of backbone

networkcomprising Rural Electricity Distribution

Backbone (REDB)and Village Electrification

Infrastructure (VEI) and last mileservice connectivity

to 10% Households in the village @Rs. 6.50

lakh/village

8,125

2. Rural Households Electrification (RHE) of

populationunder BPL i.e. 30% of 7.8 crore. Un-

electrifiedHouseholds/ i.e. 2.34 crore households @

Rs.1500/H/H asper Kutir Jyothi dispensation

3,510

3. Augmentation of backbone network in already

electrifiedvillages having un-electrified inhabitations @

Rs./1 lakh/village for 4.62 lakh villages

4,620

Total (1 + 2 + 3) 16,255

Outlay for the scheme 16,000

Subsidy component @ 90% for items 1 & 3 and 100%

foritem 2

14,750

CPRI-Training Notes

Component of subsidy to be set aside for enabling

activities including technology development @ 1%

ofoutlay

160

Annexure -III

Status of Village Electrification as on 31.3.2004

Sl. State Total No. of Total No. of Balanc % age of

No.

inhabited villages Balance electrified

villages as per electrified

unelectifie

d villages

1991 census Unelec

villages

1 Andhra Pradesh 26586 26565 $ 100

2. Arunachal Pradesh 3649 2335 1314 64

3. Assam 24685 19081 5604 77.30

4. Bihar 38475 19251 19224 50

5. Jharkhand 29336 7641 21695 26

6. Goa 360 360 - 100

7. Gujarat 18028 17940 $ 100

8. Haryana 6759 6759 - 100

9. Himachal Pradesh 16997 16891 106 99.38

10 J&K 6477 6301 176 97.28

11. Karnataka 27066 26771 295 98.91

12. Kerala 1384 1384 - 100

13. Madhya Pradesh 51806 50474 1332 97.43

14. Chattisgarh 19720 18532 1188 94

15. Maharashtra 40412 40351 - 100

16. Manipur 2182 2043 139 93.63

17. Meghalaya 5484 3016 2468 55

18. Mizoram 698 691 7 99

CPRI-Training Notes

19. Nagaland 1216 1216 - 100

20. Orissa 46989 37663 9326 80.15

21. Punjab 12428 12428 - 100

22. Rajasthan 37889 37276 613 98.38

23. Sikkim 447 405 42 90.60

24. Tamil Nadu 15822 15822 - 100

25. Tripura 855 818 37 95.67

26. Uttar Pradesh 97122 57042 40080 58.73

27. Uttaranchal 15681 13131 2550 83.73

28. West Bengal 37910 31705 6205 83.63

Total (States) 586463 47382 11241 80.80

Total UTs 1093 1090 $ 100%

All India 587556 474982 112401 80.80%

$ Balance villages are not feasible for electrification. * As per the new definition of village electrification (effective from 2004-05) total number

of unelectrified villages is estimated to be around 1,25,000.

CPRI-Training Notes

RURAL HOUSEHOLDS ELECTRIFICATION - 2001 CENSUS

Annexure -IV

S.

No. S t a t e

Total no. Of

Rural

Households

Households

Having

Electricity

% electrified

House-holds

% un-electrified

Households

1 Andhra Pradesh 12,676,218 7,561,733 59.65 40.35

2

Arunachal

Pradesh 164,501 73,250 44.53 55.47

3 Assam 4,220,173 697,842 16.54 83.46

4 Bihar 12,660,007 649,503 5.13 94.87

5 Chhattisgarh 3,359,078 1,548,926 46.11 53.89

6 Delhi 169,528 144,948 85.50 14.50

7 Goa 140,755 130,105 92.43 7.57

8 Gujarat 5,885,961 4,244,758 72.12 27.88

9 Haryana 2,454,463 1,926,814 78.50 21.50

10 Himachal Pradesh 1,097,520 1,036,969 94.48 5.52

11

Jammu &

Kashmir 1,161,357 868,341 74.77 25.23

12 Jharkhand 3,802,412 379,987 9.99 90.01

13 Karnataka 6,675,173 4,816,913 72.16 27.84

14 Kerala 4,942,550 3,238,899 65.53 34.47

15 Madhya Pradesh 8,124,795 5,063,424 62.32 37.68

16 Maharashtra 10,993,623 7,164,057 65.17 34.83

17 Manipur 296,354 155,679 52.53 47.47

18 Meghalaya 329,678 99,762 30.26 69.74

19 Mizoram 79,362 35,028 44.14 55.86

20 Nagaland 265,334 150,929 56.88 43.12

21 Orissa 6,782,879 1,312,744 19.35 80.65

22 Punjab 2,775,462 2,482,925 89.46 10.54

23 Rajasthan 7,156,703 3,150,556 44.02 55.98

24 Sikkim 91,723 68,808 75.02 24.98

CPRI-Training Notes

Union Territories

S.

No.

Union Territory

Total no. of

Rural

Households

Households

Having

Electricity

% electrified

House-holds

% un-electrified

Households

1

A.& Nicobar

Islands 49,653 33,807 68.09 31.91

2 Chandigarh 21,302 20,750 97.41 2.59

3

D.& Nagar

Haveli 32,783 27,088 82.63 17.37

4 Daman & Diu 22,091 21,529 97.46 2.54

5 Lakshadeep 5,351 5,337 99.74 0.26

6 Pondicerry 72,199 58,486 81.01 18.99

ALL INDIA 138,271,559 60,180,685 43.52 56.48

12.0 References

[1] Ministry of Power, Government of India Website

(www.powermin.nic.in)

[2] Central Electricity Regulatory Commission Website:

(http://www.cercind.gov.in) [3] ‗Indian Power Sector: Challenge and response‘ (Book), R.V. Shahi,

25 Tamil Nadu 8,274,790 5,890,371 71.18 28.82

26 Tripura 539,680 171,357 31.75 68.25

27 Uttar Pradesh 20,590,074 4,084,288 19.84 80.16

28 Uttaranchal 1,196,157 602,255 50.35 49.65

29 West Bengal 11,161,870 2,262,517 20.27 79.73

CPRI-Training Notes

Excel Books, New Delhi, 2005

[4] Published in Gazette of India The Electricity Act, 2003. India:

Universal Law Publication Company Pvt. Ltd.

[5] ‗National Training policy for power sector’, Ministry of Power,

Government of India, New Delhi, June 2002.

[6] Central Electricity Authority of India Website (http://www.cea.nic.in). [7] ‗Modernization of power Distribution’, (Book), M.V.S. Birinchi,

National Power Training Institute, New Delhi, March 2004.

[8] Ministry of Power, APDRP website: ‗http://www.apdrp.gov.in‘

CPRI-Training Notes

BASIC PRINCIPLES OF ELECTRICAL SAFTEY & RULES

Rajashekar P. Mandi, Engineering Officer

Energy Efficiency & Renewable Energy Division, Central Power Research Institute, Bangalore, India, E-

mail:[email protected]

1.0 INTRODUCTION

Safety means the state or condition of freedom from danger or risk. Safety can also be termed as freedom of persons from injury and of property from damage. The year 1789 is of great historical importance. It saw the outbreak of French Revolution and also ushered in the era of Industrial Revolution. The philosophy of that time was that accidents are an inevitable by-product of industrialization and that worker is responsible for his own safety. However, in the year 1833, world’s first Factory’s Act was enacted in UK. It was an important milestone in the evolution of the safety. The first successful Workmen’s Compensation Law was enacted in the USA in 1911 which was another leap forward for mankind. The Factory’s Act and Workmen’s Compensation Act constitute the first phase of safety.

2.0 ELECTRICAL SAFETY

Electrical Safety is essential tools for day to day life of human beings. The electrical safety can

be ensured by conducting electrical safety audit and implementation of electrical safety audit

measures.

The Electrical safety audit (ESA) is a systematic approach to evaluate potential hazards and to

recommend suggestions for improvement. ESA is an important tool for identifying deterioration

of standards, areas of risks or vulnerability, hazards and potential accidents in plants for

determining necessary action to / minimize hazards and for ensuring that the whole safety effort

is effective & meaningful.

Although electrical hazards will be identified and assessed in general safety audits,

comprehensive electrical safety audits can provide a thorough review of the electrical system.

This could identify potential electrical hazards, flaws in design system, maintenance system, etc.

3.0 HAZARDS OF ELECTRICITY

The primary hazards associated with electricity and its use are:

a) Shock: Electric shock occurs when the human body becomes part of a path through which electrons can flow. The resulting effect on the body can be either direct or indirect.

Direct. Injury or death can occur whenever electric current flows through the human body. Currents of less than 30 mA can result in death.

CPRI-Training Notes

Indirect. Although the electric current through the human body may be well below the values required to cause noticeable injury, human reaction can result in falls from ladders or scaffolds, or movement into operating machinery. Such reaction can result in serious injury or death.

b) Burns: Burns can result when a person touches electrical wiring or equipment that is improperly used or maintained. Typically, such burn injuries occur on the hands.

c) Arc Blast: Arc-blasts occur from high-amperage currents arcing through air. This abnormal current flow (arc-blast) is initiated by contact between two energized points. This contact can be caused by persons who have an accident while working on energized components, or by equipment failure due to fatigue or abuse. Temperatures as high as 35,000 o F have been recorded in arc-blast research. The three primary hazards associated with an arc-blast are:

d) Thermal Radiation. In most cases, the radiated thermal energy is only part of the total energy available from the arc. Numerous factors, including skin color, area of skin exposed, type of clothing have an effect on the degree of injury. Proper clothing, work distances and overcurrent protection can improve the chances of curable burns.

4.0 EFFECTS OF ELECTRICITY ON THE HUMAN BODY

The effects of electric shock on the human body depend on several factors. The major factors are:

1. Current and Voltage

2. Resistance

3. Path through body

4. Duration of shock

The muscular structure of the body is also a factor in that people having less musculature and more fat typically show similar effects at lesser current values.

4.1 Current and Voltage

Although high voltage often produces massive destruction of tissue at contact locations, it is generally believed that the detrimental effects of electric shock are due to the current actually flowing through the body. Even though Ohm's law (I=E/R) applies, it is often difficult to correlate voltage with damage to the body because of the large variations in contact resistance usually present in accidents. Any electrical device used on a house wiring circuit can, under certain conditions, transmit a fatal current. Although currents greater than 10 mA are capable of producing painful to severe shock, currents between 100 and 200 mA can be lethal.

With increasing alternating current, the sensations of tingling give way to contractions of the muscles. The muscular contractions and accompanying sensations of heat increase as the current is increased. Sensations of pain develop, and voluntary control of the muscles that lie in the current pathway becomes increasingly difficult. As current approaches 15 mA, the victim cannot let go of the conductive surface being grasped. At this point, the individual is said to "freeze" to the circuit. This is frequently

CPRI-Training Notes

referred to as the "let-go" threshold. As current approaches 100 mA, ventricular fibrillation of the heart occurs. Ventricular fibrillation is defined as "very rapid uncoordinated contractions of the ventricles of the heart resulting in loss of synchronization between heartbeat and pulse beat." Once ventricular fibrillation occurs, it will continue and death will ensue within a few minutes. Use of a special device called a de-fibrillator is required to save the victim. Heavy current flow can result in severe burns and heart paralysis. If shock is of short duration, the heart stops during current passage and usually re-starts normally on current interruption, improving the victim's chances for survival.

4.2 Resistance

Studies have shown that the electrical resistance of the human body varies with the amount of moisture on the skin, the pressure applied to the contact point, and the contact area. The outer layer of skin, the epidermis, has very high resistance when dry. Wet conditions, a cut or other break in the skin will drastically reduce resistance. Shock severity increases with an increase in pressure of contact. Also, the larger the contact area, the lower the resistance.

4.3 Path through Body

The path the current takes through the body affects the degree of injury. A small current that passes from one extremity through the heart to the other extremity is capable of causing severe injury or electrocution. There have been many cases where an arm or leg was almost burned off when the extremity came in contact with electrical current and the current only flowed through a portion of the limb before it went out into the other conductor without going through the trunk of the body. Had the current gone through the trunk of the body, the person would almost surely have been electrocuted. A large number of serious electrical accidents in industry involve current flow from hands to feet. Since such a path involves both the heart and the lungs, results can be fatal.

4.4 Duration of Shock

The duration of the shock has a great bearing on the final outcome. If the shock is of short duration, it may only be a painful experience for the person. If the level of current flow reaches the approximate ventricular fibrillation threshold of 100 mA, a shock duration of a few seconds could be fatal. This is not much current when you consider that a small light duty portable electric drill draws about 30 times as much. At relatively high currents, death is inevitable if the shock is of appreciable duration; however, if the shock is of short duration, and if the heart has not been damaged, interruption of the current may be followed by a spontaneous resumption of its normal rhythmic contractions.

CPRI-Training Notes

8.0 ELECTRICAL SAFETY RULES

Some of the electrical safety rules are as follows:

1. Do not renew a blown fuse until you are satisfied as to the cause and have rectified the

irregularity.

2. Do not close any switch unless you are familiar with the circuit which it controls and know

the reason for its being open.

3. Do not work on the live circuit without the express orders of the supervisor. Make sure that

all safety precautions have been taken and you are accompanied by a second person

competent to render First Aid and Artificial Respiration.

4. Do not touch or tamper with any electrical gear or conductor unless you have made sure that

it is DEAD and EARTHED.

5. Do not disconnect earthing connections or render ineffective the safety gadgets installed on

mains and apparatus.

6. Do not open or close switch or fuse slowly or hesitatingly. Do it quickly and positively.

7. Do not use wires with poor insulation.

8. Do not touch any electrical circuit when your hands are wet or bleeding from a cut or an

abrasion

9. Do not work on energized circuit without taking extra precaution such as the use of rubber

gloves.

10. Do not disconnect a plug by pulling a flexible cable when the switch is on.

11. Do not use fire extinguisher on electrical equipment unless it is clearly marked for that

purpose. Use sand and blanket instead.

12. Do not throw water on live electrical equipment in cases of fire.

13. Do not attempt to disengage a person in contact with a live apparatus, which you cannot

switch off immediately. Insulate yourself from earth by standing on rubber mat or dry board,

before attempting to get him clear. Do not touch his body; push him clear with a piece of dry

wood.

14. Do continue artificial respiration until recovery or death certified by doctor.

15. Do not allow visitors and unauthorized person to touch or handle electrical apparatus or come

within the danger zone of HV apparatus.

16. Do not test circuit with bare fingers

17. Do not make any temporary joints in the wiring without proper insulation.

18. Do not provide fuse on neutral circuit.

19. Do not allow children to play with sockets, plugs, wires and other electrical appliances.

20. Keep all switches OFF even when no lamps are installed in the holders.

21. Fused bulb may be replaced only when switch is OFF.

22. Treat all circuits alive until they are proved to be dead.

23. All wiring works should be done through licensed wiring contractor only.

24. Take proper permit from authorized official and provide earth discharge rods on H.T. lines

before commencing work.

25. Place rubber mats in from of electrical switch boards.

CPRI-Training Notes

26. Use safety appliances, like insulated pliers, rubber hand gloves, insulated screw drivers while

working on live L.T. lines.

27. Clear all persons working, remove all earth discharge rods, before charging any L.T./H.T.

lines.

9.0 INDIAN ELECTRICITY RULES 1956

The IE Rules initially framed during 1922 and amended in 1956. This rule consists of 11 chapters and 143 rules. The extracts of IE rules are discussed below:

Rule 1: Short title and commencement

Rule 2: Definitions of the terms used in the rules

Rule 3: No person shall be authorized to operate or under take maintenance of any part or whole of a generating station of capacity 100 MW and above together with the associated sub-station unless he is adequately qualified and has successfully undergone the type of training specified in Annexure XIV of IE Rules, 1956.

Rule 4: Refers to the qualification of Inspector.

Rule 4A – Refers to appointment of officers to assist an Electrical Inspector.

Rule 4B – Refers to the qualification of the officers appointed.

Rule 5: Entry & Inspection:

Where EI has reason to believe that there is any appliance / apparatus used in generation, transformation, conversion, distribution or use of energy.

Every supplier, consumer, owner or occupier to afford all reasonable facilities. E.I. to serve any order for any test.

Rule 6: An appeal against the order of E.I. is produced under Rule 6.

Rule 7: Fee towards inspection as specified by the court.

Rule 8: In case of dispute or difference is required to be decided by an E.I., he should decide who has to remit the fee.

CPRI-Training Notes

Rules 11 to 28 pertains to License. The procedure for applying and obtaining licenses are explained in these rules

Rule 29: All electric supply lines and apparatus shall be constructed, installed, worked and maintained in such a manner as to ensure safety of personnel and property.

Rule 30: Service lines and apparatus on consumer’s premises; must be owned by the consumer and provide necessary protection.

Rule 31: Cut-out on consumer’s premises; individual cut-out for more than one consumers.

Rule 32: Identification of earthed and earthed neutral conductors and position of switches and cut outs. In the double pole switches, link should be provided instead of fuse carrier on the neutral conductor.

Rule 33: Earthed terminal on consumer's premises. Earth pits should be constructed and maintained strictly as per IS:732. The earth resistance of earth electrodes shall not exceed 5 ohms.

Rule 34: Accessibility of bare conductors; safety measures for bare conductors.

Rule 35: Danger Boards as per IS:2551 should be affixed permanently in conspicuous position on every motor, generator, transformer and other electrical equipment.

Rule 36: Handling of lines & equipments: Before handling, the same to be discharged & to ensure use of gloves, etc.

Rule 37: Supply to vehicles, cranes, etc.-

Rule 38: Cables for portable or transportable apparatus-

Rule 39: Cables protected by bituminous materials

Rule 40: Street boxes: Street boxes shall not contain gas pipes, and precautions shall be taken to prevent, as far as reasonably possible, any influx of water or gas.

Rule 41: Distinction of different circuits- The owner of every generating station, sub-station, junction-box or pillar in which there are any circuits or apparatus, whether intended for operation at different

CPRI-Training Notes

voltages or at the same voltage, shall ensure by means of indication of a permanent nature that the respective circuits are readily distinguishable from one another.

Rule 42: Accidental charge- AC & DC circuits should be charged separately and no mixing of two or more supplies.

Rule 43: Provisions applicable to protective equipment-

a) Fire protection equipment

b) First aid box

c) Gas masks

Rule 44: Refers to the instructions for restoration of persons suffering from shock. Page 4 of 18

Rule 44 A - refers to the requirement by any person to intimate the occurrence of an electrical accident within 24 hours of the knowledge of the accident and within 48 hours in writing.

First Aid and Fire Safety

Authorized person appointed under Rule 3 shall be conversant with first aid measures restoration / resuscitation etc.,

Fire buckets filled with sand shall be maintained Fire extinguishers shall be maintained and tested once in a year First aid boxes must be replenished periodically. Gas masks: 2 Nos. for every 5 MW enclosed generating station and substation transforming 5 MVA

above for use in case of fire smoke. If more than one Generator of 5 MW, two gas masks each / generator.

Rule 45: This rule requires that every person intending execution of electrical work shall have it carried out only by a licensed Electrical contractor.

Rule 46: Periodical inspection and testing of consumer's installation: Every 5 years by E.I. or any officer appointed by Govt.

Rule 47: Supplier to test the installations before connection or reconnecting. If unsatisfied, he has to serve notice to the consumer & not service it until the defects are rectified.

Rule 47: Generators

CPRI-Training Notes

A generator shall be installed with a minimum all ground clearance of 750 mm. 4 pole Change over switch (COS); with provision to break neutral. When two generators are installed clearance between two shall be min. 1.8 m Frames of generators shall be earthed. Neutral to be provided with an isolator Neutral to be earthed with two separate & distinct earth connections HV generator (above 650 V) neutral earthing by NGR or an earthing transformer. When parallel operation & neutral switches is adopted interlock to be provided. All HV generators of 100 KVA & above shall have earth fault protection. Generators of 1000 KVA & above shall be protected again E.F. or diff Cable generator to panel in conduct and the conduct earthing. Control panel earthing With clearance of 1 M in-front and 750 mm all around Provision for metering Switch fuse / breaker for control of generator First aid and fire buckets. If sub switch boards, distributions transformers fuse boards are at a distance more than 3 M

another incoming MCB control or switch fuse. Each outgoing feeder enter MCB / cut out If higher rating board is used, interlock arrangement to isolate supply to the distribution fuse board

before renewing the fuses shall be provided. Distribution fuse boards shall be from main switchboard only. Lighting and power shall be distinct. Labeling / identification marks / danger boards shall be provided. ELCB above 5 KW

DG Sets under Rate 47 A

Prior approval of E.I. Minimum ground clearance of 750 mm & 1.8 m between

> 100 KVA , Earth fault protection

> 1000 KVA REF / Diff protection or both

COS of 4 pole Neutral Isolator & Earthing

Rule 48: Precaution against leakage before serving. Supplier to check the I.R. values. For LV & MV if 500

V DC (Megger) is applied between live card and earth for 1 minute min. 1 M . If 2.5 KV supply is applied

for 1 min. the IR shall be minimum 5 M in case of HV equipment.

Rule 49: After servicing of E.I. / supplier has reason to believe the installation earth leakage which could be dangerous, he may direct the consumer to provide facility for inspection, who shall provide the facility. The installations may be disconnected on direction from E I until the leakage is plugged.

Rule 50: Supply and use of energy

CPRI-Training Notes

Transformer Installation

HT up to 999 KVA – switch with fuse. 1000 & > 1000 kVA at 11 KV - breaker. 2500 kVA at 33 KV – Breaker All EHT installation – Breaker

Down stream transformers

< 1000 KVA – Linked switch / fuse

1000 KVA & > 1000 KVA - Breaker

All transformers of 1000 KVA & above installed shall be with breaker.

All Transformers secondary with LT breaker.

Only supplier transformer < 630 KVA linked switch and fuse

> 630 breaker

Rule 50 A: M.S. Buildings – Addnl. Provision

a) All buildings which are in height of 15 M are MSB covered under R 50A b) Electrical duct –2 rising main with COS & sealing between ducts. c) 3rd point earthing. d) Fire alarm 15 M e) Fire hydrant above 24 M. f) LD Protection g) Essential load on DG h) Location of transformer in GF outside i) Main incoming at GF at conspicuous place at a height not more than 2.75 M above ground level. j) No service pipes in ducts for power. k) Fire barrier between alternate floors.

Rule 51: Provisions applicable to medium, high or extra-high voltage installations

A. Provisions applicable to medium / high / EHV installations.

a) Space of 1 M for the board in front. b) Less than 200 mm or more than 750 mm behind. c) If 750 mm behind, passage way of 1.8 Mtrs ht.

B. Supplier to ensure compliance of Rule 50, 63 & 64 before servicing any installation.

C. If supplier proposes to connect a MV installation he shall give notice of his intention to E.I

CPRI-Training Notes

D. If supplier finds any defect he shall intimate to the consumer and E.I. with reasonable time. If consumer fails – disconnection, unless inspector directs otherwise.

Rule 52: Appeal to Inspector in regard to defects

Provision for consumer to appeal against the direction of disconnection of defeat by the supplier. Supplier shall not disconnect if directed by E.I. Reconnection within 24 hrs if disconnected.

Rule 53: Cost of inspection and test of consumer’s installation

Rule 54: Declared voltage of supply to consumer

Voltage Variation

LV ±6 %, HV + 6 % and – 9 %,

EHV + 10 % & - 12.5 %

Rule 55: Declared frequency of supply to consumer Frequency Variation: ±3%,

Rule 56: Supplier to provide seal and no one to break it

Rule 57: Meters in consumers premises :

a) All meters shall be within ±3 % accuracy b) EHV ±1 % c) Supplier to maintain equipments as approved by E.I. d) Supplier shall test all meters at intervals as directed by the Govt. e) Maintain the results of tests for examination by E.I. f) When supplier fails to test or keep records E.I. to test & seal the meters.

Rule 58: Point of commencement of supply

Rule 59: Precautions against failure of supply: Notice of failures:

a) Supplier to send notice of failure of supply. b) If the consumer not able to rectify the defects, E.I. directs disconnection

Rule 60: Test for resistance of insulation

Rule 61: a) Earthing of Neutral and body.

CPRI-Training Notes

b) Frame of motor generator to be provided earth.

Rule 61 A: Above 5 KW load, all installation with ELCB

Rule 62: System at medium voltage; earth to any conductor voltage must be less than low voltage

Rule 63: Supplier to await approvals of E.I. before putting HT/EHT into service.

Rule 64: Requirements of HT / EHT

All equipment in a separate room and inaccessible except to authorised person. All operations to be carried out by D.P

* Highest system voltage Safe working clearance

12 KV 2.6 Mtrs

36 KV 2.8 Mtrs

72.5 KV 3.1 Mtrs

145 KV 3.7 Mtrs

245 KV 4.5 Mtrs

420 KV 6.4 Mtrs

800 KV 10.3 Mtrs

Rule 64: Requirements of HT / EHT

Substation or switch station with more than 2000 ltrs (oil capacity) shall not be located in the basement.

Where sub station or switch station having more than 2000 lts either indoor or outdoor, following :

a) Baffle wall of 4 hours fire rating b/w apparatus b) Provision for soak pit

If more than 9000 lts

Draining arrangement. Authorised person to maintain records Only dry type transformer to be used inside the residential / Commercial building. Adequate fire protection arrangement to quench fuel.

If substation / switch station is in the basement , following :

Room to be at 1st basement at periphery of basement Entrance to room with fire resisting door of 2 Hr rating.

CPRI-Training Notes

Curb (sill) to prevent the flow of oil Direct access to the transformer room from outside Fire fighters BCF / BTN Oil filled transformers not above ground or below 1st basement Cable trenches to be filled with pebbles non inflammable material etc., EHV apparatus to be provided with LA protection as well as switching over voltages

Rule 64A: Additional provisions for use of energy at HV / EHV

Interlocks b/w isolators and circuit breakers. Earthing switches to be closed only when isolator is open Parallel transformer to have facility of tripping of secondary breaker when primary breaker trips Capacitor Bank doors to have interlock Protective device of C./E.F/Prot > 1000 KV Diff. protection above 10 MVA

Rule 65: Testing, Operation and Maintenance

Manufacturer’s test certificates shall be produced for all the routine tests as per ISI. No new HV or EHV apparatus, cable or supply line shall be commissioned with relevant standards All apparatus, cables and supply lines shall be maintained in healthy conditions , tests shall be

carried out and records keeping Responsibility of the owner of all HV and EHV installations

Rule 66: Metal sheathed electric supply lines. Precautions against excess leakage

Rule 67: Connection with earth – proper connection and resistance values. Neutral earthing and voltage between neutral and earth conductors

Rule 68: General conditions as to transformation and control of energy

Voltage step down sub-station where energy at high or extra-high voltage is transformed, converted, regulated or otherwise controlled in sub-stations or switch-stations

Rule 69: Pole type sub-stations- Where platform type construction is used for a pole type sub-station and sufficient space for a person to stand on the platform is provided a substantial hand rail shall be built around the said platform and if the hand rail is of metal, it shall be connected with earth.

Rule 70: Condensers- Suitable provision shall be made for immediate and automatic discharge of every static condenser on disconnection of supply.

Rule 71: Additional provisions for supply to high voltage luminous tube sign installation (Neon signs)

All live parts of the installation shall be inaccessible to unauthorised persons

CPRI-Training Notes

No part of any conductor of such circuit shall be in metallic connection with any conductor of the supply system or with the primary winding of the transformer.

All live parts of an exterior installation shall be so disposed as to protect them against the effects of the weather and fire.

The secondary circuit shall be permanently earthed at the transformer and the core of every transformer shall be earthed.

A special “caution” notice shall be affixed in a conspicuous place on the door of every high voltage enclosure

When static condenser is used the same shall be used on low voltage side and provision to discharge when supply in cut off.

Rule 72: Additional provisions for supply to high voltage electrode boilers:

Earthing of metal sheathing and metallic armouring (if any) of the high voltage boiler. Shall be controlled by a suitable circuit-breaker with an inverse time element device The owner or user of any high or extra-high voltage electrode boiler shall not bring the same into

use without giving the Inspector not less than 14 days’ notice in writing of his intention so to do.

Rule 73: Supply to X-ray and high frequency installation-

Mechanical barrier to prevent access to HV parts X-Ray tubes shall be mounted in metal enclosure which is earthed ELCB on low voltage side to detect leakage Railing platform earthing EHV generator operating at 300 KV or more shall be in a separate room, with door interlock to be

open unless the door is locked.

Rule 74: Material and strength

All OH Conductor shall have breaking strength if not less than 350 Kgs. In a low voltage consumer installations outer 15 Mtrs span length, the breaking strength could be

not less than 150 Kgs.

Rule 75:

Not more than 2 joints in a span Joints to have 95 % of the strength of a conductor

Rule 76: Maximum stresses: Factors of safety-

Owner of every OH line shall ensure the following factor of safety :

For metal – support : 1.5 For Mechanical processed concrete support : 2.0 For hand mould concrete support : 2.5 For wood support : 3.0

CPRI-Training Notes

Rule 77: Clearance above ground of the lowest conductor-

Sl. No.

Clearances Low & MV

HV Above 11 kV

1 Anywhere other than along or across

4.6 4.6 5.2

2 Along 5.5 5.8 -

3 Across 5.8 6.1 -

For EHV lines – 0.3 Mtrs for every 33 KV & Part there off.

Rule 78: Clearance between conductors and trolley wires-

Low and medium voltage lines : 1.2 m High voltage lines up to and including 11 kV : 1.8 m High voltage lines above 11 kV: 2.5 m Extra-high voltage lines: 3.0 m

Rule 79: Clearances from buildings of low and medium voltage lines and service lines-

For any flat roof, open balcony, verandah roof and lean-to-roof-

When the line passes above the building a vertical clearance of 2.5 m from the highest point When the line passes adjacent to the building a horizontal clearance of 1.2 m from the nearest point

For patched roof-

When the line passes above the building a vertical clearance of 2.5 m immediately under the lines When the line passes adjacent to the building a horizontal clearance of 1.2 m.

Rule 80: Clearances from buildings of high and extra-high voltage lines-

Where a high or extra-high voltage overhead line passes above or adjacent to any building or part of a building

(a) For high voltage lines upto and including 33 kV: 3.7 m (b) For extra-high voltage lines: 3.7 m plus 0.30 m for every additional 33 kV or part thereof.

The horizontal clearance between the nearest conductor and any part of such building shall

CPRI-Training Notes

(a) For high voltage lines upto and including 11 kV: 1.2 m (b) For high voltage lines above 11 kV – 33 kV: 2.0 m (c) For extra-high voltage lines: 2.0 m plus 0.30 m for every additional 33 kV or part thereof.

Rule 81: Conductors at different voltages on same supports-

Rule 82: Erection of / alteration of buildings.

Structures flood banks and elevation of roads. Any person / contractor is to give notice to the supplier and E.I. with drawings. Supplier has to verify and estimate. Person to remit the estimate amount Dispute regarding estimate or cost to E.I. for decision. No further work until E.I. certifies. Supplier to execute within one month from the date of deposit or as allowed by the E.I.

Rule 84: Routes: Proximity to aerodromes- Overhead lines shall not be erected in the vicinity of aerodromes until the aerodrome authorities have approved in writing the route of the proposed lines.

Rule 85: Maximum interval between supports- All conductors shall be attached to supports at intervals not exceeding the safe limits based on the ultimate tensile strength of the conductor and the factor of safety prescribed in Rule 76.

Rule 86: Conditions to apply where telecommunication lines and power lines are carried on same supports-

Every overhead telecommunication line erected on supports carrying a power line shall consist of conductors and proper guard wire.

Where a telecommunication line is erected on supports carrying a high or extra-high voltage power line arrangement shall be made to safeguard persons.

Rule 87: Lines crossing or approaching each other-

Minimum clearances in metre between lines crossing each other

Sl. No.

Nominal System Voltage

11 – 66 kV

110 –

132 kV

220 kV

400 kV

800 kV

1 Low & Medium

2.44 3.05 4.58 5.49 7.94

2 11 – 66 2.44 3.05 4.58 5.49 7.94

CPRI-Training Notes

kV

3 110 – 132 kV

3.05 3.05 4.58 5.49 7.94

4 220 kV 4.58 4.58 4.58 5.49 7.94

5 400 kV 5.49 5.49 5.49 5.49 7.94

6 800 kV 7.94 7.94 7.94 7.94 7.94

Rule 88: Guarding-

Every guard-wire shall be connected with earth at each point at which its electrical continuity is broken.

Rule 89: Service-lines from Overhead lines- No Service-line or tapping shall be taken off an overhead line except at a point of support.

Rule 90: Earthing-

Rule 91: Safety and protective devices-

Rule 92: Protection against lightning-

Rule 93: Unused overhead lines-

Rules 94 – 108: Electric traction

Rules 109 – 132: Additional Precautions to be adopted in mines and oil fields

Rule 133: Relaxation by Government-

Rule 134: Relaxation by Inspector

Rule 135: Supply and use of energy by non-licensees and others-

Rule 136: Responsibility of Agents and Managers

CPRI-Training Notes

Rule 137: Mode of entry-

Rule 138: Penalty for breaking seal- Rs. 200/- as penalty

Rule 139: Penalty for breach of Rule 45-

Rule 140: Penalty for breach of Rule 82- Person / Contractor deemed to have committed the breach.

Rule 141: Penalty for breach of Rules- Any person other than an Inspector or any officer appointed to assist the Inspector who being responsible for the observance of any of these rules commits a breach thereof, shall be punishable for every such breach with fine which may extend to Rs. 300/-

Rule 142: Application of rules- these rules shall be binding on all persons, companies and undertakings to whom licenses have been granted or with whom agreements have been made with the sanction of Govt. supply or use of electricity.

Rule 143: Repeal- The Indian Electricity Rules, 1937, are hereby repealed.

10.0 CONCLUSIONS

The electrical safety is very essential in work every part of life. Safety is team work and is every ones responsibility. The organization or employer will provide the facilities to the employees but responsibility of safety lies with individual. The overconfidence will kill the people. Use of proper insulated tools, proper joints, use of appropriate MCBs, RCCBs, Fuses, Relays, standard electrical appliances, following the safety norms, working with the presence of mind will help in reducing the accidents.

CPRI-Training Notes

ELECTRICAL SAFTEY EQUIPMENTS, PROCEDURES FOR

LINE CLEARANCE AND SAFE WORKING PROCEDURES

Rajashekar P. Mandi, Engineering Officer

Energy Efficiency & Renewable Energy Division,

Central Power Research Institute, Bangalore, India,

E-mail:[email protected]

1.0 INTRODUCTION

Electrical energy is the most commonly used form of energy because it is a rich form of energy. One cannot imagine the life without electricity in modern society. Using electricity is very simple, but, little does one know about how electricity really works. Such a situation is not good because electricity is a good servant but a very bad master. It can cause instantaneous death, lifelong disability due to severe burns or devastating fires turning crores of rupees worth assets to ashes.

It is, therefore, absolutely essential that one should know what precautions to take while using electricity.

To overcome all these safety problems, Indian Government, introduced lot of electrical safety norms in Indian Electricity Rule 1956 and amended in the Indian Electricity Act 2003.

The major objective of a safety audit / procedure is to determine the effectiveness of the company‘s

safety and loss prevention measures. It is an essential requirement of an audit system that it should

originate with the policy-making executive and a consensus should be arrived at regarding the safety

audit and its objectives.

Factories Act, 1948 (Section 7A) makes the occupier responsible for providing a safe working

environment for the employees. Safety audit is one method of evaluating the safe environment provided

in the plant, although safety audit is not a direct requirement by Factories Act. Considering the changing

international legislature trends, safety audits could become mandatory in India too in the near future.

Our experience shows that either the top management or the electrical department initiates ESAs and not

the safety department. The reason could be the lack of in depth knowledge of safety officers in electrical

aspects coupled with their limited involvement in electrical department‘s day-to-day functions.

Although electrical hazards will be identified and assessed in general safety audits, comprehensive

electrical safety audits can provide a thorough review of the electrical system. This could identify

potential electrical hazards, flaws in design system, maintenance system, etc.

CPRI-Training Notes

2.0 ELECTRICAL SAFETY EQUIPMENT

The following items of Personnel Protective Equipment (PPE) are to be worn by all personnel, at all times whilst working in on power station sites, irrespective of whether electrical related hazards are present in the tasks that are being undertaken:

safety helmet,

long sleeved high visibility (day visibility) shirt (100% cotton – 185 g/m2 ),

long pants (100 % cotton - 185 g/m2),

safety footwear,

safety glasses in and around plant, and designated workshop areas,

ear plugs/muffs in designated hearing protection areas.

Personal protective equipment (PPE) additional to the items listed above is to be used and selected in accordance for the activity. Working near energized exposed parts requires specialized PPE to be worn. Protective clothing worn by electrical workers when working live and/or others in proximity to exposed energized conductors shall be appropriate for the purpose, fit correctly and be in good condition while the work is being performed. To protect personnel from electrical hazards, each Power Station is to provide a supply of personal protective equipment that is maintained and tested in accordance with the National Standards.

Personnel required to wear items of PPE are not to modify, damage or use PPE in a way contrary to manufacturer’s instructions or the training provided for that particular item of PPE. Items of PPE that are defective or out of test date are to be immediately withdrawn from service and tagged as out of service, until repaired and/or tested by a competent person. During the performance of live electrical work, testing de-energized, fault finding or when in close proximity to energized exposed parts, personnel are not to wear or carry conductive items such as pens, mobile phones, radios, tools (unless suitably insulated), metal belt buckles, buttons, chains, studs, jewelry, body piercing, metal rimmed glasses, bracelets, rings, neck chains, exposed metal zips, watches, etc.

When working live, testing to prove de-energized, fault finding, commissioning, as a safety observer or in proximity to energized conductors electrical workers and others are to wear suitable flame retardant/arc flash protective clothing.

Arc flash energies are to be managed for electrical work and the selection of correct PPE is to be addressed based on the identified arc flash energies (ATPV) for the electrical equipment being isolated, tested or worked on. Other measures to control the risk may include working at a greater distance from the incident arc source, using longer handles to rack out equipment, using remote isolation or test equipment and modifying protection settings by engineering to reduce the arc flash potential energy.

CPRI-Training Notes

3.0 SAFETY PROCEDURES AND ACCIDENT PREVENTION

Accident can be defined as an unexpected or unforeseen occurrence and course of employment of a person resulting in an injury/damage to the persons/equipment or may not cause any such damage.

3.1 Earthing

Majority of electrical accidents are electrocution. One of the main causes of electrocution is improper earthing. Therefore, a proper attention to earthing can help in preventing majority of electrical accidents. Most of the fatal accidents are also due to electrocution.

Proper earthing is necessary to ensure safety of personnel as well as equipment.

3.2 Causes of Accidents

The causes of accidents may be broadly divided into following two categories:

3.2.1 Direct causes.

a) Unsafe Act: Violation from the commonly accepted safe procedures of the work is called Unsafe Act. b) Unsafe condition: The conditions with potential of causing injury to a person or damage to equipment are

called Unsafe Conditions.

3.2.2 Indirect Causes.

a) Lack of knowledge and skill. Incorrect knowledge Incomplete knowledge. Unskilled/low degree of skill. Misunderstanding job instructions.

b) Improper Physiological/ Anatomical characteristics. This relates to persons of:- Poor eye-sight. Hard of hearing. Over-age. Ill Allergic.

c) Improper Psychological Characteristics. Persons who are: Arrogant.

CPRI-Training Notes

Lazy. Fearful. Nervous. Egoistical. Absent-minded. Over-confident.

4.0 UNSAFE ACTS

Generally there are two types of unsafe acts

1. Know better with over confident 2. Without knowing

4.1 Some of the unsafe acts are

1. Failure to de-energize the circuit or switch off the circuit, 2. Lockout & tag out hazardous during maintenance, repair or inspection work may be due to over confident or

due to urgency. 3. Use of defective and unsafe tools. 4. Use of tools or equipment too close to energized parts or live parts. 5. Not discharging stored energy in capacitors while doing maintenance. This may give high electrical shock

due to charge stored in capacitor banks. 6. Using 3-wire cord with a 2-wire plug without using earth. 7. Using the jointed electrical cord to raise or lower equipment. 8. Overloading outlets with too many appliances. 9. Not verifying or ensuring power is put-off while taking of maintenance work. 10. Removing the third pin (ground pin) to make a 3-pin plug fit a 2-pin outlet. 11. Working in an elevated position near overhead live lines.

4.2 Hazardous environment

1. Flammable vapours, liquids and gasses 2. Combustible dusts or cotton waste 3. Poor housekeeping: blocked electrical boxes, flammable materials stored in equipment rooms, lack of

proper hazard signs 4. Corrosive atmospheres 5. Explosive environments 6. Special care is also need in wet or damp locations – water and electricity are a bad combination. If the wire

is frayed or damaged, a fatal electrical shock can result.

CPRI-Training Notes

4.3 Some common causes of unsafe equipment

1. Loose connection 2. Faulty insulation 3. Improper grounding (removal of 3rd pin) 4. Use of “homemade” extension cords 5. Defective parts 6. Unguarded love parts- -for example: 7. Bare conductors or exposed terminals

4.4 Risk Assessment

1. Identification and location of hazardous 2. Whether the Hazardous is harmful to any body 3. Assess the risk arising from Hazards 4. Decide whether the precautions are alright 5. Record the significant findings 6. Review the situation periodically and necessary action

4.5 Aggravating the risk of hazards

1. Wet surrounding 2. Water clogging 3. Grass around the electrical equipments in Sub-station 4. Water leakages on equipments 5. Cramped spaces

5.0 BEST PRACTICES

Some of the best practices to minimize the hazards are

1. Provide better illumination and ventilation system 2. Use of copper lugs for end terminations and cable glands for the cable terminations. 3. All the cable glands and panel boards have to be provided with earths. 4. Transformer must be provided with two separate earths for body and two earths for neutral grounding.

The earth pits must be monitored on regular basis. The char coal & salt are to be put on bi-annually basis. 5. The lightning arrestor of appropriate size may be installed for transformers. 6. The over current relay (OCR), under voltage relay (UVR) and earth fault relay are to be provided and are to

be tested annually. 7. The load factor of transformer must be maintained within 40 – 60 % and not to overload the transformers 8. The transformer winding temperature must be maintained below 55oC over the ambient and oil

temperature less than 50oC over ambient temperature. 9. The transformer oil is to be tested annually for healthiness of transformer.

CPRI-Training Notes

10. The condition of silica gel must be blue in colour. 11. The grass in transformer yard and sub-station must be cleared and stone jellies have to be spread in yard. 12. Maintaining earth resistance to minimum (i.e., 2 – 10 ohm) 13. Providing earthing to all equipment 14. Use of standard Electrical equipments confirming to IS standards 15. Periodic preventive maintenance 16. The cables must be laid in the cable trays or trench with proper identification. 17. The safety chart must displayed at the main entrance. 18. First aid box must be provided at main electrical room. 19. The list of operators may be displayed at the electrical room. 20. The log books for main incoming, DG sets and UPS are to be maintained. 21. At all the LDBs, UDBs, AC panels and UPS panels have to be provided with Danger Notice Board as per IE

rule 35. 22. Panel board identification name boards must be provided on all the panels. 23. For DG sets two separate earths must be provided for body and neutral. 24. For DG sets, the sound proof enclosures are to be provided. 25. Earth fault protections as per IE Rule 47 A are to be provided. 26. Use of separate 3-pin sockets of appropriate rating for individual appliances 27. Avoid use of multi point sockets for electrical appliance. 28. Use of proper sized MCBs or fuses in the circuit. 29. Proper end terminations 30. Use of lock out tags during maintenance work 31. Removing fuse and keeping safely during maintenance work. 32. Safety Chart in sub-station and at important places 33. Single line diagram of electrical system 34. Identification of feeders including cable size, MCB rating, etc. 35. Rubber mats in-front of panels 36. Earthing of all electrical panels and cable glands 37. Maintaining the proper clearances in-front and back of panels as per IE rule 38. Updating the drawings periodically 39. Use of correct size fuse and record keeping 40. Display of names of maintenance staff at sub-station or electrical room

6.0 ELECTRICAL SAFETY GUIDELINES

6.1 Transformers

Some of the safety guidelines for transformers are:

a) The transformers must be provided with two separate earths for transformer body and two earths for neutral grounding. The earth pits must be marked, clean all the earth pits regularly. The sand and char coal must be filled till the cup of earth pipe. The cup should be visible and the joint also should be visible. The water has to be put in pipe to reduce the earth resistance.

b) Lightning arrestors of appropriate size may be installed for transformers. c) The over current relay (OCR), under voltage relay (UVR) and earth fault relay are to be installed and

monitored regularly.

CPRI-Training Notes

d) Sharp edged blue jelly or pebbles may be spread at transformer bottom. e) The load factor of transformers must be maintained in the range of 40 – 60 % for better operation. f) The cables must be laid properly in the cable trench and markings must be made. g) The transformer body temperatures must be monitored at regular intervals and maintained in the range of

40 – 60 oC. h) The transformer winding and oil temperature gauges must be maintained in good condition. i) The transformer oil has to be got tested from a standard lab to ascertain the oil quality. j) The condition of silica gel must be blue in colour. If it becomes white, it has to be replaced.

6.2 Cables, panel boards and electrical room

Some of the safety guidelines for cables, panel boards & electrical room are:

a) All the cables must be terminated with proper lugs and cable glands. b) The cable glands and panel boards have to be properly earthed. c) At all panels, the cable identification, size, number of runs, etc must be marked for easy identification. d) The end termination joint temperature must be measured by using noncontact type temperature

indicators. e) The cable loading must be maintained below 60 % for better operation. Refer Table 1 for cable rating.

Table 2 gives rating of Electrical equipment and its accessories. Table 3 gives the selection of tinned copper fuse wire (as per IEE Regulations 12th Edition 1950 table 21). Table 4 gives the current ratings of rectangular copper bus bars.

f) The cables must be laid in the cable trays. g) The safety chart is to be displayed at the main entrance. h) First aid box is to be provided at main electrical room. i) The list of operators, linemen, supervisor, etc must be displayed at the electrical room. j) The log books have to be maintained at main electrical room. The log book can contain incoming voltage,

current, power factor and energy meter reading for both the incomings. k) At all the LDBs, UDBs, AC panels and UPS panels have to be provided with Danger Notice Board as per IE

rule 35. l) Panel board identification name boards must be provided on all the panels.

6.3 Diesel Generator Sets

Some of the safety guidelines for DG sets are:

a) For each DG set two separate earths must be provided for body and neutral. b) For both the DG sets, the sound proof enclosures must be provided. c) These DG sets must start automatically whenever the power failure through AMF panels. d) The sufficient illumination level and ventilation must be provided in DG room. e) Earth fault protections as per IE Rule 47 A are provided but are bypassed. These earth fault relays have to

be taken in the circuit.

CPRI-Training Notes

6.4 Motors and lift

Some of the safety guidelines for motors & lifts are:

a) The lift motor body must be earthed. b) Limit switches must be in service in the lift. c) Telephone must be provided inside the lift and important five emergency numbers must be displayed. d) Power and lighting circuits must be maintained separately. e) Buffers springs must be in good condition. f) Lighting level must be good inside the lift. g) Exhaust fan must be provided in the lift. h) Earthing must be provided for all DBs.

7.0 PERMIT SYSTEM IN SUB-STATION

7.1 Procedure for permit to work (line clear)

Line clear is a permit to work Issued by a authorized person to a authorized person only. More than one gang under the same supervisor working simultaneously – separate line clear for each gang Line clear is required by self, he can take selfline clear by following the same procedure & precautions. Line clear book is very important document. Pages must be numbered and pages should not be used for other purpose or teared-off If any page is missing, the custodian will be responsible and attest his signature with date and reason of

missing of page. Line clear book shall be reviewed by the Higher officials like Asstt. Executive Engineer or equivalent Line clear can also be issued / received over telephone. But it is desirable that the issuer / receiver recognizes each other’s voice. A secret code number shall be followed in such cases

7.2 Procedure before issue of line clear

Approval of the competent authority for shut-down of line/equipment should be verified Line/equipment shall be switched off No back feed certificates, wherever necessary shall be obtained The issuer must be ensured that the breaker / GOS are opened and breaker panel is locked The line/equipment is earthed by discharge rods A ‘Danger Do not operate’ or ‘ Men on line’ board shall be exhibited All operations for issue of line clear shall be done personally by the issuer or it shall be done under his

personal supervision. After following all the precautions the line clear book shall be filled up and signed with date & time by the

issuer and receiver.

7.3 Responsibilities of receiver

Receiver should indicate the specific equipment/line which he wants to work when requisitioning for L.C.

CPRI-Training Notes

If the receiver is at the same place as that of the issuer he shall follow all the operations being conducted so as to ensure that line clears are being issued on the correct line/equipment.

At the work spot, after receiving line clear, he shall earth the line/equipment on either side of the workspot ( in case of line sending end & receiving end)

In case if any other power lines are crossing near to work spot of the line on which LC is received he shall also obtain LCs on all such lines to avoid induction.

He shall write down on the duplicate form the number of persons engaged on the work.

7.4 Rules followed while returning LC

Persons who have received the LC only return it. He shall personally ensure that there are no men, material or earth on the line He shall inform all the workmen that it is no longer safer to work on the line as the line clear is being

returned Line/equipment shall not be charged until the LC is cancelled

7.5 Precautions before cancel LC

Returned LC shall be carefully examined. It shall be ensured that all the certificates required are furnished ‘Men on line’ or ‘Danger do not operate’ boards shall be removed It shall be ensured that no other LC is pending. All men material removed.

Earthing is removed All no back fed certificates shall be returned After charging the line/equipment check should be made for unusual sound/noise All the workmen/supervisor shall be permitted to leave the work spot only after the normalcy is restored.

8.0 RECOVERY AND RESUSCITATION

There are scientifically approved methods to resurrect a person who met with an electrical accident.

8.1 Neilsen’s Method

Position 1

Place the victim face downwards with his arms folded one over the other and the head resting on them.

Kneel at the victim’s head on one or both knees. Place your hands on the back of the victim away from the armpits with your fingers spread out downwards and thumbs touching each other.

CPRI-Training Notes

Position 2

As you count one, two, three, rock forward, keeping arms straight until they are nearly vertical thus steadily pressing the victim’s back. This completes expiration.

Position 3

As you proceed to count four, rock backwards releasing pressure and slide your hands downwards along the victim’s arms and grasp his upper arm just above the elbows. Continue to rock backwards.

Position 4

As you rock back counting five, six, seven, raise and pull the victim’s arm towards you until you feel tension in his shoulders. This expands his chest and results in inspiration.

CPRI-Training Notes

As you count eight, lower the victim’s arms and move your hands up for the initial position. Repeat this cycle twelve times a minute. When the victim starts breathing, synchronize your steps with his breathing until he breathes strongly. Then stop.

8.2 Schafer’s Method

Lay the patient on his stomach one arm extended directly overhead the other arm bent at elbow and with the face turned outward and resting on hand and forearm so that the nose and mouth are free for breathing. Kneel over the patient, rest the hands flat on the small of his back with fingers resting on the ribs, the little finger just touching the lowest rib with the thumb and other fingers in a natural position and the tips of the fingers just out of sight.

With arms straight swing forward slowly and gently over the patient so that the weight of your body is gradually brought to bear on the patient exerting a steady pressure downward. The shoulder should be directly over the heel of the hand at the end of the forward swing. Do not bend your elbows.

yourself gently backwards so as to completely remove the pressure

After two seconds, swing forward again. Continue these two movements twelve to fifteen times a minute. The object is to keep expanding and contracting the casualty’s lungs so as to initiate slow breathing.

8.3 Silvester‟s Method

CPRI-Training Notes

The patient is laid on his back. His arms are grasped above the wrists and drawn first upward and then above the head until they touch the floor.

Bring back the arms to the chest and exert pressure in a downward direction.

The tongue is to be pulled out and held in that position so that it does not obstruct the throat. Otherwise a large thick pad may be placed behind the shoulders, so that the head lies dangling downwards and the tongue does not obstruct.

8.4 Artificial Respiration

9.0REPORTING

The procedure for reporting an occurrence of accidents shall be laid down. Example…

• Dept. / Non dept.

• Fatal / non fatal

• Preliminary investigation report – 5 days (DE)

• Detailed investigation report – 15 days (DE)

• Remarks on investigation report – 30 days (SE)

Immediate to superior

next higher superior

CPRI-Training Notes

• Compensation payable

There shall be standard formats for reporting, guidelines for investigation and fixing responsibility for accident. The investigation reports shall clearly indicate the measures for avoiding recurrence of such accidents.

10.0 CONCLUSIONS

The electrical safety is very essential in work every part of life. Safety is team work and is every ones responsibility. The organization or employer will provide the facilities to the employees but responsibility of safety lies with individual. The overconfidence will kill the people. Use of proper insulated tools, proper joints, use of appropriate MCBs, RCCBs, Fuses, Relays, standard electrical appliances, following the safety norms, working with the presence of mind will help in reducing the accidents.

CPRI-Training Notes

POWER QUALITY ISSUES, MEASUREMENTS AND MITIGATION

Rajashekar P. Mandi, Engineering Officer

Energy Efficiency & Renewable Energy Division,

Central Power Research Institute, Bangalore, India,

E-mail:[email protected]

1.0 INTRODUCTION

With the use of modern high-tech microprocessor based technology in industries for various applications, the power quality is being polluted. To produce the quality of products, the power supply should be of high quality. The power electronic based equipment will present a non-linear load characteristic to the network and producing the harmonics in the system. The harmonic currents increase the RMS value of the current and create the neutral current to circulate in the distribution network. The presence of harmonics decrease the distribution capacity and increase the losses.

The voltage sags, swells and surges affect the performance of the equipment. Voltage unbalance between three phases created by the unbalanced loading on 3-phases will reduce the motor efficiency and rating.

The use of power conditioning equipment will reduce the harmonic distortions, voltage unbalance, power factor corrections, etc..

This paper presents the affect of power quality on the equipment and increased losses in the distribution system. The power quality issues are discussed in detail.

2.0 POWER SUPPLY ISSUES

The utility had to supply the good quality of power supply to the consumer with allowable limits of voltage and frequency variation, voltage harmonics, etc. But due to the increased gap between supply and demand and more and more usage of power electronic equipment, the power quality is being polluted. Various power quality issues are discussed below.

2.1 Voltage variation

In industries, the incoming voltage variation band is very high compared to the developed countries. Since the transformers in industries are of off-load tap changers, the required voltage cannot be met adequately.

CPRI-Training Notes

To overcome the voltage variation, on-load tap changers for transformers may be used for incoming voltage levels above 66 kV. For the voltage below 66 kV, the OLTC is not economically feasible. The use of regulating transformers will improve the voltage quality, the techno-economics are attractive for large scale industries. The use of voltage stabilizers in LT side is also proves to be economical in some instances where the voltage dip is more than 10 % of rated voltage. The use of captive generation (DG sets) during peak hours (for low voltage) also proves to be economical.

2.2 Voltage sags and swells

The voltage sags are being created by switching transient of heavy loads. The voltage sag can occur in one phase or in all the 3-phases based on the switching and type of the equipment. Generally, the voltage sags will last for 100 to 500 ms and dip by about 30 % [1]. If the sag sustains more than this values corrective action may be taken.

When the capacitor banks are directly charged, the inrush current will be in the range between 7 to 9 times of the normal current which will create the transients. This can be avoided by installing the series reactor in phase or in neutral conductor.

The voltage surge and swells are being created by switching off certain heavy equipment.

The voltage sags, swells and surges can be mitigated by the use of surge arrestors and uninterrupted power supply units which will inject the voltage whenever voltage sag takes place and control the voltage during surge and swell.

The earth current developed in the equipment due to the voltage drop between the equipment and true earth. This noise voltage will be significant compared with the signal voltages. The computer hardware is designed to minimize sensitivity to this kind of disturbance but it cannot be eliminated entirely. The earth reference plane of different computers on different floors will be no longer at the same potential. Currents will flow along the shields of data cables connected to earth at both ends for EMC compliance.

Short duration voltage changes, resulting from switching, short-circuits and load changing can result in light flicker. The excessive flicker can cause migraine and is responsible for some instances of the so called ‘sick building syndrome’.

2.3 Voltage unbalance

The voltage unbalance between 3-phases is caused by load unbalance, dissimilar voltage drops in distribution equipment and different power factors in three phases. The voltage unbalance will cause negative sequence current in the motor winding which will increase the motor loss and the negative sequence current will create the

CPRI-Training Notes

negative sequence torque which will oppose the normal torque. This negative sequence torque will reduce the motor capacity. Figure 1 gives the variation of computed increased losses for 18.5 kW motor. The total losses are as high as 33 % at voltage unbalance of 5 %. The motor capacity will reduce 75 % at a voltage unbalance of 5 % as per the IEEE standard.

The voltage unbalance at the motor terminal can be overcome by the use of active line conditioner [2]. In this case voltage unbalance is achieved by injecting a correcting voltage in the phases. The magnitude of the injecting voltage is computed by evaluating the negative sequence voltage, which will become the input to the PWM inverter.

2.4 Harmonics Distortion

The power electronics

technology

based equipment

like compu

ters, electr

onic ballast

s, variabl

e speed

drives, arc

furnaces

etc., draw the non-sinusoidal current from the utility and distort the utility voltage waveforms, which will break the empirical relationship between the peak and Root Mean Square (RMS) value (i.e. RMS value of pure sine wave is

1/2 times of its peak value). The distorted non-sinusoidal currents are built up of sinusoidal currents of different frequencies and of various magnitudes. These currents are termed as harmonics. These harmonics are expressed as Total harmonic distortion (THD). The THD is the ratio of the root mean square of the harmonic contents to the root mean square value of the fundamental 50 Hz signal. THD is expressed as a percentage and is computed as:

100*lfundamentaofamplitudeofSquare

harmonicsofamplitudesofsquaresofSumTHD

Figure 1: Variation of motor current and losses with

voltage unbalance at motor terminals.

0

5

10

15

20

25

30

35

0.0 1.0 2.0 3.0 4.0 5.0

Voltage unbalance, %

Incre

ased

un

bala

nced

cu

rren

ts &

losses in

mo

tors

, %

NO LOAD CURRENT

FULL LOAD CURRENT

LOSS

CPRI-Training Notes

100*.............

)(2

1

22

5

2

4

2

3

2

2

I

IIIIIcurrentTHD n

100*.............

)(2

1

22

5

2

4

2

3

2

2

V

VVVVVvoltageTHD n

The harmonics are classified according their frequencies.

The THD in industries are vary in the range of 5 % and 35 % whereas the individual voltage and current harmonics are (especially odd harmonics i.e., 3rd, 5th, 7th, etc.,) measured as high as 59 %. As per the IEEE-519-1992, the THD be limited to a maximum value of 5 % with no individual voltage or current harmonic to exceed 3 %, for the voltage level up to 69 kV. In different countries the harmonic limits have been specified . Similar guide lines may be introduced in India also.

The effects of harmonics are :

1. Flickering screens: Triple-N harmonic currents sum in the neutral conductor. The neutral and protective conductor are combined and connected to the structure of the building. As a result, neutral return currents can flow anywhere in the metal structure of the building and create controllable magnetic fields. These fields can result in flicker of computer screens. Neutral current always needs to be returned to the point of common coupling using a separate conductor.

2. Overheating of transformers: Transformers are affected in two ways. Firstly, the eddy current losses which are about 10 % at full load are being increased with the square of the harmonic number. These eddy current losses will double for the transformer which are catering the power supply to power electronic equipment loads. This will increase the operating temperature much higher and a shorter life. Secondly, the triple-N harmonic currents in delta winding will circulate in the winding. The circulating current increase winding loss. The triple-N harmonics are absorbed in the winding of delta connected transformer and do not propagate onto the supply but non-triple-N harmonics pass through.

3. Induction motors: Voltage harmonics cause extra losses in induction motors. The 5th, 11th, 17th,….. harmonics create a counter-rotating field [4], whereas the 7th harmonic creates a rotating field beyond the motor’s synchronous speed. The resulting torque pulsing causes wear and tear on couplings and bearings. Since the speed is fixed, the energy contained in these harmonics is dissipated as extra heat, resulting in premature ageing. Harmonic currents are also induced into the rotor causing further excess heating. The additional heat reduces the rotor/stator air gap, reducing efficiency even further. Variable speed devices cause their own range of problems. They tend to be sensitive to dips, causing disruption of synchronised manufacturing lines. They are often installed some distance from the motor and cause voltage spikes due to the sharp voltage rise times. Special care has to be taken at start-up of motors after a voltage dip when the motor is normally operating at close to full load. The extra heat from the inrush current at start-up may cause the motor to fail.

4. Overheating of conductors due to skin effect: The alternating current tends to flow on the outer surface of a conductor. This is known as skin effect and is more pronounced at high frequencies. Skin effect is normally

CPRI-Training Notes

ignored because it has very little effect at power supply frequencies but above 350 Hz, i.e. the 7th harmonic and above, skin effect will become significant, causing additional loss and heating. Where harmonic currents are present, designers should take skin effect into account and de-rate the cables accordingly. Multiple cable cores or laminated busbars can be used to overcome this problem.

5. Correct functioning of process control equipment: Severe harmonic distortion can create additional zero -

crossings within a cycle of the sine wave, affecting sensitive measurement equipment. Synchronisation of

process control equipment in continuous manufacturing may be disturbed and PLC devices may lock up.

6. Problems with power factor correction equipment: Power factor correction capacitors are generally used to

draw the current with leading power factor to offset lagging current of inductive load. The impedance of PFC

capacitor reduces as the frequency increases, while the source impedance is generally inductive and increases

with frequency. The capacitor is therefore likely to carry a quite high harmonic currents and, unless it has

been specifically designed to handle them, damage can result. A potentially more serious problem is that the

capacitor and the stray inductance of the supply system can resonate at or near one of the harmonic

frequencies (which, of course, occur at 100 Hz intervals). When this happens very large voltages and currents

will be generated, often leading to the catastrophic failure of the capacitor system. Harmonic frequencies may

coincide with resonant frequencies of the combined stray inductance and power factor correction (PFC)

equipment, creating excessive voltage or current and leading to premature failure. Moreover, as a general

problem, measurement devices may not correctly measure the loading of the PFC, as they incorrectly measure

the harmonic content in the current.

7. Overloaded neutrals: In a 3-phase 4 wire system, there are 3-phase conductors and a neutral conductor,

which carries the unbalance between the 3-phases. When there are harmonics in the system and the loads on

all phases are equal, the fundamental currents cancel out, but the harmonic currents do not cancel out,

especially triple-N harmonics add together. The effective third harmonic neutral current will increase. For

example 70 % third harmonic current in each phase increases the neutral current by 210 %. In most of the

installations, 3½ core cables are used. This half sized neutral is getting overloaded due to the presence of

triple-N harmonics and getting burnt. At many places the neutral currents were measured in the range of 150 –

180 %. In order to avoid the failure of neutral conductor, the de-rating of cable can be adopted based on the

IEC 60364-5-523 standard. At 70 % of 3rd

harmonics the cable de-rating factor will be 0.6.

8. Nuisance tripping of protective relays: Residual current circuit breakers (RCCB) operate by summing the

current in the phase and neutral conductors and, if the result is not within the rated limit, disconnecting the

power from the load. Nuisance tripping can occur in the presence of harmonics for two reasons. Firstly, the

RCCB, being an electromechanical device, may not sum the higher frequency components correctly and

therefore trips erroneously. Secondly, the kind of equipment that generates harmonics also generates

switching noise that must be filtered at the equipment power connection. The filters normally used for this

purpose have a capacitor from line and neutral to ground, and so leak a small current to earth. This current is

limited by standards to less than 3.5 mA, and is usually much lower, but when equipment is connected to one

circuit the leakage current can be sufficient to trip the RCCB. Nuisance tripping of miniature circuit breakers

(MCB) is usually caused because the current flowing in the circuit will be higher than that expected from

calculation or simple measurement due to the presence of harmonic currents. Most portable measuring

instruments do not measure true RMS values and can underestimate non-sinusoidal currents by 40 %.

9. The flow of harmonic current in the network system increases the distribution network I2R losses and increase the voltage drop at the farthest end by increasing distribution circuit impedance.

CPRI-Training Notes

The harmonics can be suppressed by the use of filters as discussed below [5] :

i. Incorporation of current waveshaping circuits within the equipment to draw the sinusoidal line currents from the supply will suppress the harmonics.

ii. Installation of filters to clean the distorted current waveforms drawn by the loads.

The filters are of three type:

a. Active filters which can be connected either in series or in shunt mode. This technique is well suited for low and medium power levels. These filters are compact. The load current is flowing from load in to the network is separated in to fundamental (50 Hz) and harmonic components. The filter prevents an undesired flow of harmonic current into the network by injecting the required current portions.

b. Passive filter can also be connected either in series or shunt mode. Shunt filter will serve as a short circuit for load harmonic current where as series filter consists of an impedance connected in series with the utility and acts as an open circuit to load harmonic currents. The passive filters are bulky.

c. Hybrid filters combine the passive filter with active filters. In this scheme, the active portion of the filter is connected in series with a passive impedance which is used to block the utility [6].

3.0 MEASUREMENT OF TRUE RMS COMPONENTS

The Root Mean Square is the magnitude of an alternating current which is equivalent to the direct current that

would produce the same amount of heat in a fixed resistive load. The amount of heat produced in a resistor by an

alternating current is proportional to the square of the current averaged over a full cycle of the waveform. In other

words, the heat produced is proportional to the mean of the square, so the current value is proportional to the root of

the mean of the square or RMS. For a perfect sinewave, the RMS value is 0.707 times the peak value (or the peak

value is 2 or 1.414 times the RMS value. If the magnitude of the waveform is simply averaged (inverting the

negative half cycle), the mean value is 0.636 times the peak or 0.9 times the RMS value.

When measuring a pure sinewave, a simple measurement of the mean value (0.636 x peak) and multiply the result by the form factor i.e., 1.11 (form factor=RMS value / mean value = 1.11) making 0.707 times peak and call it the RMS value. This is the approach taken in all analogue meters (where the averaging is performed by the inertia and damping of the coil movement) and in all older and most current, digital multimeters. This technique is described as ‘mean reading, RMS calibrated’ measurement.

CPRI-Training Notes

Figure 2: Waveform of current drawn by computer

This techniqu

e only

works for pure sine

waves and most

of the

places

pure sine

waves do not exist in the real world of an electrical installation. The waveform in Figure 2 is typical of the current waveform drawn by a personal computer. The true RMS value is still 1 A, but the peak value is much higher, at 2.6 A and the average value is much lower, at 0.55 A.

If this waveform is measured with a mean reading, RMS calibrated meter, it would read 0.61 A, rather than the true value of 1 A, nearly 40 % too low. A true RMS meter works by taking the square of the instantaneous value of the input current, averaging over time and then displaying the square root of this average. Perfectly implemented, this is absolutely accurate whatever the waveform. Implementation is, of course, never perfect and there are two limiting factors to be taken into account: frequency response and crest factor.

For the industrial power systems, it is usually sufficient to measure up to the 50th harmonic, i.e., up to a frequency of about 2500 Hz. The crest factor, the ratio between the peak value and the RMS value, is important; a higher crest factor requires a meter with a greater dynamic range and therefore higher precision in the conversion circuitry. A crest factor capability of at least three is required. It is worth noting that, despite giving different readings when used to measure distorted waveforms, meters of both types would agree if used to measure a perfect sinewave. This is the condition under which they are calibrated, so each meter could be certified as calibrated – but only for use on sinewaves.

True RMS meters features are available in many of the multimeters, power analysers, clamp on meters, but these meters are costly.

4.0 CASE STUDIES

4.1 Single phase loads

CPRI-Training Notes

The generally used single equipment that are producing the harmonic distortion are:

1. Switched mode power supply units (SMPS) 2. Electronic ballasts 3. Small UPS or inverters

4.1.1 Switched Mode Power Supply Units

Most of the modern power electronic equipments use SMPS. The SMPS draws pulses of current which contain large amounts of third & higher harmonics and significant high frequency components. A simple filter is fitted at the supply input to bypass the high frequency components from line and neutral to ground but it has no effect on the harmonic currents that flow back to the supply.

The personal computers (PC) are fitted with SMPS and generate current harmonics. Figure 3 gives the measured current harmonics for PCs. The odd current harmonics are on higher side. The current 3rd harmonics are measured in the range of 63.9 - 89.5 %, followed by 5th harmonics 63.4 - 65.7 %, 7th harmonics 39.5 – 43.5 %, 9th harmonics 19.3 - 21.7 % and so on. Because of this increased 3rd harmonics cause overheating of neutral conductors of the feeders connecting to the computers. At many installations, the neutral conductors are being burnt because the cables used are of 3½ core cables. In order to overcome this problem the neutral conductor must be of higher size.

4.1.2 Electronic ballasts

The increased awareness of conservation of energy in lighting sector, the electronic ballasts are being used for

fluorescent lamps. A fluorescent lamp operates much more effectively at a frequency above 10 kHz as compared to

its operation at 50 Hz. Moreover, an electronic ballast has fewer Watt losses and needs no capacitor for power

factor correction. As the losses in electronic ballast are less, it reduces the temperature of the air circulating around

the lamp which decreases the ambient temperature of the lamp and thereby increases the efficiency of both the lamp

and luminaire. These ballasts generate higher frequency voltage in the range of 20 – 25 kHz to ballast the

fluorescent lamp. This will cause the harmonics in the system. The conventional coil wound ballasts consume about

12 – 14 W per 40 W lamp whereas electronic ballast will consume only 0.5 – 1 W per 40 W lamp. But these ballasts

generate harmonics in the system. Figure 4 gives the measured harmonics of typical electronic ballasts without and

with harmonic filters for fluorescent lamps and compact fluorescent lamps (CFL). It can be seen from the Figure 4

that the 3rd

current harmonics of CFL are measured as high as 75.6 %, 5th harmonics 46.5 %, 7

th harmonics 39.5 %,

9th 37.6 % and so on. The current harmonics of electronic ballasts without harmonic filters (low cost) are measured

in the range of 34.2 – 56.5 %, followed by 5th harmonics 22.7 – 34.5 %, 7

th harmonics 15.9 – 24.5 %, 9

th harmonics

13.2 – 18.7 % and so on. Some manufacturers are manufacturing the electronic ballasts with harmonic filter which

are reducing the harmonic distortions but the cost of these ballasts increase by about 60 – 70 %.

CPRI-Training Notes

4.2 Three phase

loads

In 3-phase loads

like Variab

le speed

drives, UPS

units and DC

converter

s in general are usuall

y base

d on the 3-

phase

bridge,

also known as

the six-

pulse bridge because there are six pulses per cycle (one per half cycle per phase) on the DC output. The six pulse bridge produces harmonics at 6n ±1, i.e. at one more and one less than each multiple of six. The magnitude of the harmonics is significantly reduced by the use of a twelve-pulse bridge. This is two six-pulse bridges, fed from a star and a delta transformer winding, providing a 30 degrees phase shift between them. The 6n harmonics are theoretically removed, but in practice, the amount of reduction depends on the matching of the converters and is typically by a factor between 20 and 50. The 12n harmonics remain unchanged. Not only is the total harmonic current reduced, but also those that remain are of a higher order making the design of the filter much easier. Often the equipment manufacturer will have to take some steps to reduce the magnitudes of the harmonic currents, perhaps by the addition of a filter or series inductors. A further increase in the number of pulses to 24,

0

10

20

30

40

50

60

70

80

90

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Cu

rre

nt

harm

on

ics

, %

Harmonic number

Figure 3: Measurement of current harmonics at Computer (PC).

PC 1

PC 2

PC 3

PC 4

0

10

20

30

40

50

60

70

80

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Cu

rre

nt

harm

on

ics

, %

Harmonic number

Figure 4: Measurement of current harmonics at CFL, Electronic ballasts with and without filter.

CFL

Ballast 1

Ballast 2

Ballast 3 (with filter)

CPRI-Training Notes

achieved by using two parallel twelve-pulse units with a phase shift of 15 degrees, reduces the total harmonic current to about 4.5 %. The extra sophistication increases cost, of course, so this type of controller would be used only when absolutely necessary to comply with the electricity suppliers’ limits.

4.2.1 Variable speed drives

In many industries, the fluid flow elements (i.e., pumps and fans) are driven by induction motors because of their robustness, easy maintenance, less cost, etc. The speed of these induction motors will be constant. To control the fluid flow, various control devices like guide vane control, dampers, throttle valve and hydraulic couplings are being used. The efficiency of these control devices at partial flow will be very poor. In order to improve the efficiency of control at partial load and to reduce the power consumption at partial flow, the variable frequency drives are being used to control the speed of the induction motors. These controls are more efficient at partial flow. These controllers convert the 50 Hz AC power to DC and invert back to AC with variable frequency to regulate the speed of the motors. While converting and inverting the power supply, these equipment generate the harmonics in the system. The use of variable frequency drives reduce the energy consumption by 15 – 25 % for the varying flow applications. Figure 5 shows the measured current harmonics of variable frequency drives. It can be seen from the Figure 5 that the 3rd current harmonics are varying between 6.5 – 8.5 %, followed by 5th harmonics 35.6 – 76.5 %, 7th harmonics 31.4 – 63.4 %, 9th harmonics 5.4 – 11.4 %, 11th harmonics 17.8 – 35.4 %, 13th harmonics 14.5 – 24.2 % and so on.

4.2.2 Un-interrupted Power Supply (UPS) units

To cater the need of un-interrupted power supply to the equipment, UPS systems are being used. Most of the places, the grid interactive UPS are being used. Whenever the grid power supply will be there, UPS will take the grid supply as incoming and supply the power to the load by converting and inverting. Whenever the grid supply is not there, it will draw the DC power from battery bank and supply the power to load by inverting. Most of the places, the UPS power supply is being used for power electronic equipment like PCs, controllers, etc. These loads generate lot of harmonics. The good design UPS has to filter the harmonics. In many cases, it was observed that instead of filtering the harmonics the UPS generate the harmonics. Figure 6 gives the measured voltage harmonics at UPS input and output. The UPS has filtered the 5th voltage harmonics from 0.6 % to 0.4 %, 7th voltage harmonics from 2.7 % to 0.2 %. Figure 7 gives the measured current harmonics at UPS input and output. The 3rd current harmonics are reduced from 32.8 % to 6.4 %, 5th current harmonics are reduced from 25 % to 22.4 %, 7th harmonics are increased from 11.1 % to 18.4 %, 9th harmonics are reduced from 4.8 % to 0.6 %, 11th harmonics are increased from 0.8 % to 5.2 %, 13th harmonics are increased from 1 % to 6.3 % and 17th harmonics are increased from 0.2 – 5.7 %.

CPRI-Training Notes

5.0 CONCLUSIO

NS

The use of

more and

more power electr

onic equipment

in the distribution

network, the power quality

is being pollut

ed. The

polluted

power supply influe

nce more

losses in the

system,

reduction in the quality of the products and reliability of power supply.

The use of power conditioners will suppress the harmonics, control the voltage unbalance, improve the power factor, etc.. The incorporation of power conditioners in the system proves to be economically viable.

0.0

0.4

0.8

1.2

1.6

2.0

2.4

2.8

2 3 4 5 6 7 8 9 10 11 12 13

Vo

ltag

e h

arm

on

ics

, %

Harmonic number

Figure 6: Harmonic voltage measurement at UPS input and output

Input THD = 3.0 %

Output THD = 0.7 %

Figure 5: Measurement of current harmonics at variable

frequency vdrives.

0

10

20

30

40

50

60

70

80

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

Harmonic number

Cu

rren

t h

arm

on

ics,

%

VFD 1

VFD 2

VFD 3

VFD 4

CPRI-Training Notes

REFERENCES

1. R . K. Aggar

wal, M.

Weinhold and

R. Zurowski, “Pow

er qualit

y impr

ovement in distribution systems”, Proc. of International Conference on power generation, system planning and operation, at IIT, New Delhi, 12 -13, Dec., 1997, pp. 28 - 38.

2. Vijay B. Bhavaraju and Prasad N. Enjeti, “An active line conditioner to balance voltages in a three phase system,” IEEE Transactions on Industry applications, Vol.32, No. 2, March/April, 1996, pp. 287 - 292.

3. Rajanbabu, P. C. 1999. Harmonics, Proc. Training Programme on Conducting Energy Audit, Central Power

Research Institute, Energy Research Centre, Trivandrum-695017, 105-110.

4. Ramakrishnaiah R. , “ Impact of harmonics and voltage fluctuation in reactive power problems”, Electrical India, 15th Oct. 1996, pp. 25 - 27.

5. Ned mohan and Girish R Kamath , “Active power filters-Recent advance”, Sadhana, Vol.22, Part 6, Dec. 1997, pp. 723 - 732.

6. Abraham, P. 1990. Strategies for improving the quality of power supply, Proc. Conf. on Role of Innovative Technologies and Approaches for India’s power sector, PACER-TERI, 7 Jorbagh, New Delhi-110003, I ,1-9.

Figure 7: Harmonic current measurement at UPS input and

output

0

5

10

15

20

25

30

35

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Harmonic number

Cu

rren

t h

arm

on

ics,

%

Input THD = 28.8 %

Output THD = 46.5 %

CPRI-Training Notes

FIRE FIGHTING

ELECTRICAL FIRES

Any fire started by electrical equipment must be a class A, B, C or D fire. Normal procedure is to cut off

the supply of electricity and use an extinguishing method appropriate to burning material.

Special agents which are non-conductors of electricity and non-damaging to equipment should be used in

case of any doubt about positive isolation of electric supply.

FIRE- ITS ANATOMY & CLASSIFICATION

Nature of Fire

Fire is as old as human civilisation. Fire of controlled nature has been part and parcel of day to day life.

As the proverb goes ―FIRE IS A GOOD SERVANT BUT BAD MASTER‖, fire plays only constructive

role in generating electricity.

What is Fire?

Fire is an exothermic chemical reaction resulting from combination fuel, heat and oxygen.

CLASSIFICATION OF FIRES and EXTINGUISHING MEDIA FOR PARTICULAR CLASS

Classification of Fires

Fires are classified on the basis of type of fuel involved. Method of extinguishment & type of

extinguishing media depends upon the class of fire.

As per Indian Standards : IS : 2190 - 1979, fires are classified as follows :

Class

of

Fire

Type of fuel / material

involved

Method of

extinguishment

Extinguishing

Media to be used

A Ordinary Solid

Combustibles

e.g. Wood, Paper, Grass,

Plastics

Cooling fuel below

its ignition point.

Water

B Flammable Liquids,

Liquefiable solids

e.g. Fuel Oil, LSHS,

Diesel, Gasoline (Petrol),

Paints, Petrochemicals.

Blanketing fuel

surface in the bulk

fire.

Protein Foam AFFF,

Alcohol Resistant Foam

Flame Suppression

in the spillage fire.

CO2, D.C.P., Halon

C Flammable Gases

e.g. Acetylene,

Hydrogen,LPG,

Associated Gas, Natural

Gas

Starvation by the

control of fuel

supply.

No medium is required

Inhibition of the

burning fuel at fast

rate with an inert gas.

CO2, D.C.P., Halon

CPRI-Training Notes

D Combustible Metals

e.g. Magnesium,

Aluminium, Zinc, Sodium,

Potassium, etc.

Inhibition of the

chain reactions of

combustion process

Special D.C.P.

II. Smothering:

In very simple word it can be understand as cutting of O2 (air) supply.

This method can be accomplished by covering a burning surface with blanket, sand, DCP, foam,

etc.

III. Cooling:

If heat generated during combustion can be dissipated at footer rate than generation by some

means, the combustion can not sustained by proper cooling, the heat lost will be more than the

production and fire will die down.

IV. Chain Inhibition:

Fire Triangle

Fuel O2

Oxygen Heat

Heat

Fuel

Basic need of fire is these three elements in proper proportion without which fire can not

involve.With removing any of the side of fire triangle, we can extinguish fire. Depending upon

these three parts of fire triangle, there are three extinguishing methods.

V. Chemical chain inhibition combustion consists of repaid chain reactions involving hydrogen atom

and other active species and free oxygen atom. By applying proper chemicals, these chain reactions

can be arrested e.g. D.C.P.

FIRE PREVENTION

Fire safety has four legs as shown below :

1. Fire Protection : Elimination of contribution

2. Fire Prevention : Elimination of causes

3. Quality control

4. Preventive maintenance

The best way of fire safety is to eliminate the cause of fire i.e. fire prevention.

I) Good Housekeeping

II) No smoking (or separate preparation of smoking zone)

III) Use of fire resistant paint

IV) Electrical safety

V) Fire check doors

CPRI-Training Notes

VI) Compartmentalisation

VII) Separate storage of Hazardous chemicals

VIII) Naked Flame safety

IX) Use of earth leakage and current balance relays and thermostat, fireproof chokes.

Do‘s and Don‘ts for Prevention of Electrical Fire

1) Ensure that current ratings of wires, cables and accessories are equal to or higher than

maximum possible loads.

2) Ensure that all electrical wires and cables are protected by fuses.

3) Use of MCBs or cartridge fuses instead of wire fuses.

4) Ensure switch boards, terminal boards, joints etc. are not fixed close to combustible

material.

Use only those electrical equipment, cables/wires and accessories which comply with relevant I.S.

NOTE:

All portable fire extinguishers should be wall mounted (1000 mm above ground/floor level).

Types of fires are:

Class A: Wood,paper,cloth, trash,plastics—solidsthatarenot metals.

ClassB:Flammableliquids—gasoline,oil,grease,acetone.Includesflammable gases.

Class C: Electrical—energizedelectricalequipment. As long asit‘s―pluggedin.‖

Class D:Metals—potassium,sodium,aluminum, magnesium. RequiresMetal-X,foam, andother

specialextinguishingagents.

Differenttypesof fire extinguishersare designedto fight differentclassesof fire.

The three most common types of fire extinguishersare:

1. Water(APW)

2. CarbonDioxide(CO2)

3. DryChemical(ABC,BC,DC)

Howto Use aFire Extinguisher: It‘seasytorememberhowtousea fire

extinguisherifyouremembertheacronym PASS:

Pull

Aim

Squeeze

CLEANING OF PARTS

With flammable solvents

(1) Adequate ventilation must be available to avoid fire, explosion and health hazards.

(2) Avoid breathing solvent vapours.

(3) Keep open flames and sparks away from flammable liquids and their vapours.

(4) Metal nozzle of a hose for spraying flammable solvents shall be grounded.

CPRI-Training Notes

With compressed air

(5) Goggles shall be used when blowing out dust with compressed air.

PREVENTING FIRES AND EXPLOSIONS

(1) Waste paper, rags and other combustible material should not be allowed to accumulate.

(2) Flammable liquids shall be kept in approved safety cans and identified by proper labels.

(3) Varnish, paints, lacquers and thinners are highly flammable and should be stored away from all-

open flames or possible sources of ignition. Matches and open flames should not be used where

varnish, paint or lacquer is being applied with a spray gun.

(4) Open flames and smoking are prohibited in all areas where flammable liquids or gases are stored

or being used. Such areas shall be posted with appropriate warning signs.

(5) All employees should be familiar with the location and proper use of fire extinguishers in their

work area.

(6) No employee should smoke or use matches or open flames on customer‘s premises

FIRE SAFETY & EXTINGUISHER USE

OBJECTIVE

1. Understand the combustion process and different fire classes.

2. Understand fire extinguisher types, operating procedures.

3. Understand basic fire fighting concept.

THE COMBUSTION PROCESS

CPRI-Training Notes

1. Three components

2. Need all three components to start a fire

3. Fire extinguishers remove one or more of the components

FIRE CLASSES

A – Wood, Paper, Cloth, etc.

B - Liquids, Grease

C – Electrical Equipments

D – Combustible Metals

FIREEXTINGUISHER TYPES

Class “A” Fires only

2.5 gal, water (up to 1 minute discharge time)

Has pressure gauge to allow visual capacity check.

30-40 ft maximum effective range

Can be started and stopped as necessary

Extinguishes by Cooling Burning material below the ignition point.

Class “B” –Carbon Dioxide (Co2)

2.5 -100 lb of CO2 (8-30 seconds discharge time)

Has no pressure gauge, capacity verified by weight

3-8 ft maximum effective range

Extinguishes by smothering burning materials.

Effectiveness decreases as temperature of burning material increases

Class ―A‖ ―B‖ OR ―C‖ fires

1. 2.5-20 lb. dry chemical (ammoniumphosphate)

2. 8-25 seconds discharge time

3. Has pressure gauge to allow visual capacity check

4. 5-20 ft maximum effective range

5. Extinguishes by smothering burning materials

RESSURIZED

WATER COOLING CLASS ―A‖

CPRI-Training Notes

CARBON DIOXIDE SMOTHERING CLASS ―B‖ & ―C‖

MULTIPURPOSE

DRY CHEMICAL SMOTHERING CLASS ―A‖ ―B‖& ―C

SUMMARY

1. Combustion process ( Fire Triangle)

2. Class A, B, C, D, Fires

3. Types of portable fire extinguishers

4. A, B, & C,

5. Operating procedures

6. Capacity and limitations

7. Basic firefighting concepts R.A.C.E. P.A.S.S.

CPRI-Training Notes

Legal Issues of Contracts & CVC guidelines

Dr. H. N.Nagamani, CVO/ Joint Director, CPRI, Bangalore

1.0 Introduction

Corruption has become the bane of our society. It has assumed alarming proportions and encompasses all spheres of

life. There was a time when socially, a corrupt person was not considered a desirable person. But today we have

reached such a cynical stage that corruption is not only taken for granted but people with money, however ill gotten

it may be are respected by the society. The spreading cult of consumerism and a desire for an ostentatious life style

tempts many to make money by hook or crook. This not only results in vicious cycle of corruption but also

increased criminalization of the society. The recent exposes, disclosures and a spate of financial scams have very

dramatically highlighted the extent of corruption in high places, in public life.

Corruption can be tackled only by sustained and coordinated effort. In the context of Government organizations and

PSUs it is imperative and there is transparency and accountability in governance. The root cause of poor governance

lies in corruption. The poor governance in turn, affects the productivity, efficiency, image and the profitability of

the organization. One area which not only affects the bottom line of the organization considerably but is also

corruption prone is the area of contract management. Any mismanagement in the award and execution of contracts

may result in heavy leakages of revenue and adversely affect the image and profitability of the organization.

Keeping this perspective in view, the Chief Technical Examiner‘s (CTE) Organization of Chief Vigilance

Commission (CVC) has published a booklet titled as ―Common irregularities / Lapses observed in Stores / Purchase

contracts and Guidelines for improvement in procurement system‖. The booklet highlights the lapses/irregularities

in the award and execution of electrical, mechanical and other allied contracts is being issued. The lapses have been

explained and discussed with illustrations as far as possible. The aim of the booklet is not to indulge in fault finding

exercise but to help improve the systems and procedures in the organizations so that the project/contract

management is more objective, transparent and professional.

The course material covers the salient features of CVC guidelines for procurement.

2.0 Purchase Manual

The cardinal principle of any public buying is to procure the materials / services of the ‗specified‘ quality, at the

most competitive prices and in a fair, just, transparent manner and shall promote competition. To achieve this end, it

is essential to have uniform and well documented policy guidelines in the organization so that this vital activity is

executed in a well-coordinated manner with least time and cost overruns. A codified purchase manual containing

the detailed purchase procedures, guidelines and also proper delegation of powers, wherever required needs to be

made by all the organizations so that there is systematic and uniform approach in the decision-making. Such an

integrated approach is likely to put a cap on the corruption and would also ensure smoother and faster decision-

making.

3.0 Filing System

The procurement files are very important and sensitive documents and thus there is a need to have a single file

system with proper page numbering. In case of urgency, if opening of the part files is unavoidable, the same should

CPRI-Training Notes

thereafter be merged with the main file. The decisions and deliberations of the individuals or the Tender

Committees also need to be properly recorded and well documented.

4.0 Provisioning

It has been noticed that in certain cases excessive, fraudulent andinfructuous purchases were made without taking

into consideration theimportant aspects like available stocks, outstanding dues / supplies, pastconsumption pattern

and average life of the equipment / items etc.

The provisioning of the stores needs to be done with utmost care takinginto account the available stock, outstanding

dues / supplies, the pastconsumption pattern, average life of the equipment / spares. The requirementsalso need to

be properly clubbed so as to get the most competitive and bestprices. The requirements should not be intentionally

bifurcated / split so as toavoid approval from higher authorities.

5.0 Estimated Rates

As the estimated rate is a vital element in establishing the reasonableness of prices, it is important that the same is

worked out in a realistic and objective manner on the basis of prevailing market rates, last purchase prices,

economic indices for the raw material/labour, other input costs, IEEMA formula, wherever applicable and

assessment based on intrinsic value etc.

6.0 Notice Inviting Tender

Against the most preferred and transparent mode of Global tender enquiry/Advertised tender enquiry, some of the

Organizations are generally issuing limited tender inquiry to select venders, irrespective of the value of purchase. In

order to give wide publicity, generate enough competition and to avoid favoritism, as far as possible, issue of

Advertised/Global tender inquiries should be resorted to and published in ITJ and select National Newspapers. The

copies of the tender notices should be sent to all the registered/past/likely suppliers by UPC and also to the Indian

Missions /Embassies of major trading countries in case of imported stores.

7.0 Tender / Bid Document

The terms and conditions being stipulated in the bid documents by some of the Organizations are quite insufficient

and sketchy. Sometimes, the bid document contain obsolete, unwanted matter and conflicting and vague provisions,

resulting in wrong interpretation, disputes and time & cost overruns. The important clauses relating to Earnest

money, Delivery Schedule, Payment terms, Performance/Warrantee Bank Guarantee, Pre-despatch inspection,

Arbitration, Liquidated Damages/Penalty for the delayed supplies and Risk-purchase etc. are not being incorporated

in the bid documents. All these clauses are important for safeguarding the interest of the purchaser and also have

indirect financial implications in the evaluation of offers and execution of the contracts.

A proper arrangement for receipt of tenders at scheduled date and time through tender box needs to be adopted.

In order to give equal opportunity to all the bidders and to maintain sanctity of tendering system, it is of paramount

importance that any change in the tender terms & conditions, specifications and tender opening date etc. be notified

to all the bidders, sufficiently in advance of the revisedtender opening date.

Tenders shall be opened in public in the presence of bidders.

CPRI-Training Notes

8.0 Post Tender Negotiations

As post tender negotiations could often be a source of corruption, it is directed that there should be no post-tender

negotiations except with L-1, in certain exceptional situations. Such exceptional situations would include

procurement of proprietary items, items with limited sources of supply and items where there is suspicion of a cartel

formation. The justification and details of such negotiations should be duly recorded and documented without any

loss of time.

9.0 Technical Evaluation of Tenders

Once it has been established that the offers meet the laid down specifications, the question of ‗grading‘ as well as

any ‗pick and choose‘ should not arise. The contract needs to be awarded to the lowest bidder meeting the laid down

specifications.

10.0Purchase Preference to Public Sector Enterprises

The instructions / guidelines circulated by Department of Public Enterprises for granting purchase preference to the

Central Govt., Public Sector Enterprises / Joint Ventures need to be scrupulously followed as also brought out by

CVC in the instructions circulated vide letter No. 98 / Ord. / 1 dtd. 15.03.99.

11.0Consideration of Indian Agents

It is essential to verify the genuineness of the prices quoted by the Indian Agent, the nature of services which would

be available from Indian Agent and compliance of Tax Laws by the Indian Agent and, to prevent leakage of foreign

exchange. In view of this, the following aspects shall be examined:-

a. Foreign Principal‘s proforma invoice indicating the Commission payable to the Indian Agent,

nature of after sales service to be rendered by the Indian Agent.

b. Copy of the agency agreement with the foreign principal and the precise relationship between

them and their mutual interest in the business.

c. The enlistment of the Indian Agent with Director General of Supplies & Disposals under the

Compulsory Registration Scheme of Ministry of Finance.

12.0Reasonableness of Prices

It is very important to establish the reasonableness of prices on the basis of estimated rates, prevailing market rates,

last purchase prices, economic indices of the raw material / labour, other input costs and intrinsic value etc., before

award of the contract.

13.0Advance Payment & Bank Guarantee

The advance payments need to be generally discouraged except in specific cases. Wherever payment of advance is

considered unavoidable, the sameshould be interest bearing as per CVC guidelines and be allowed after getting an

acceptable Bank Guarantee for an equivalent amount with sufficient validity so as to fully protect the Govt. interest.

Some reasonable time should be stipulated for submission of Bank Guarantee so that contractual remedies could be

enforced, if required.

CPRI-Training Notes

14.0Performance Bank Guarantee

In order to safeguard the Govt. interest, it would be appropriate to take reasonable amount of Performance Bank

Guarantee valid upto warranty period for due performance of the contract. The validity of the Bank Guarantees

needs to be carefully monitored and whenever extension in the delivery period is granted, the validity of Bank

Guarantee should also be appropriately extended so as to protect the Govt. interest. The genuineness of the BGs

should be checked from the issuing bank.

15.0Stipulation of delivery period in the contract

Delivery period is the essence of any contract. The specific delivery period for supply as per the terms of delivery

such as station of dispatch / destination and completion of installation with the necessary provision for Liquidated

damages / Penalty clause in the event of delay in supplies/ installation needs to be incorporated in the contract.

16.0Guarantee / Warranty Terms

Detailed guarantee/warranty clause embodying all the safeguards be incorporated in the tender enquiry and the

resultant contract. It also needs to be ensured that in installation/commissioning contracts, the guarantee/ warranty

should reckon only from the date of installation/commissioning.

17.0Post-contract Management

After conclusion of the contract, any relaxation in the contract terms / specifications should be severely

discouraged. However, in exceptional cases where the modifications/amendments are considered to be absolutely

essential, the same should be allowed after taking into account the financial implications for the same.

It is essential to accord priority to the post contract follow up. The delivery period should be extended on bonafide

request and not in a routine and casual manner. After expiry of delivery period, the consignees should be refrained

from exchanging correspondence with the supplier. In case of delay in supplies by the supplier, the liquidated

damages to the extent possible need to be recovered. Also in case of delay attributable on the part of the supplier,

the L/C extension charges should be to supplier‘s account. In nutshell, there is a need to discipline the suppliers so

that the non-performers could be weeded out and the suppliers which can be relied upon with consistent

performance, in terms of quality and delivery schedule are encouraged.

Reference

1. Common irregularities / lapses observed in stores / purchase contracts and guidelines for improvement in the

procurement system – by Chief Technical Examiner Organization of Central Vigilance Commission, Government

of India. Year 2002.