Group2 Turner 1

Embed Size (px)

DESCRIPTION

turner pt

Citation preview

  • 5/19/2018 Group2 Turner 1

    1/14

    Group2

    Rupa Murudkar 092

    Ankit Verma 185

    Ankur Zutshi 186

    Manoj Kumar 210

    Chandan Bharambe 078

  • 5/19/2018 Group2 Turner 1

    2/14

    Introduction: Turner Construction Company

    28 territories, eachheaded by a TGM

    Autonomy to TGM, improle: prospecting for new

    work

    Project managers---3-6project executives(eachheaded 5-6 projects at atime)---TOM-- TGM

    1/5 VP3 divisionexecutive vice-presidents

    Only 10% own workforce

    Communication withowner, architect, largeno. of suppliers and

    subcontractors

    Cost estimation by: ownestimating staff,

    subcontractor inputs,database of past

    experience

    GMP, turners earnings-fixed

    Gain and decrease in costmethods

  • 5/19/2018 Group2 Turner 1

    3/14

    Case facts

    Pressure from Top Management to release contingency to earnings.

    Need to meet Turners quarterly corporateearnings projections

    Because of loss of sale of a developmentbuilding, division has to come up withadditional$200 000 earnin s in the uarter

    Savings Participation Contract

    Once a contingency is released as savings it is

    shared- 75% to the owner + 25% for Turner asadditional project earning

    Once money is released unforeseen problems and

    developments can cut into the feeearnings ofTurner

    Project

    Wants to reinvest in additional project upgradesUnspent contingency reserve not likely to be

    needed, therefore returned.

    Kent Square Office Tower

    One of the biggest construction project atPhiladelphia

    Owner wants Turner to release $500,000 inprojects savings

  • 5/19/2018 Group2 Turner 1

    4/14

    The $500,000 Dilemma

    To decide whatportion of $500,000 to

    be released to KentSquare

    Once the earnings arebooked, it will lookbad if the division

    falls short ofprojection in thesubsequent quarter

    Estimated bill of theproject $29 million

    RemainingConstructionContingency

    $511,000 = 1.8% oftotal job cost

    C holds = $328,000,

    E holds =$471,000

    The scope changes arestill taking place

    $215,000 havealready been released

    from contingencyaccount

    Possible local strike in oneof the trades, legitimateneed for extra clean up,

    several contractors workingon the same floor which can

    get messy- needs E holdsfor that

    New client- so cantgo back to him askingfor new money once

    they return thecontingency

    Its 80% complete andnot 95%

    Turners reputation onstake

  • 5/19/2018 Group2 Turner 1

    5/14

    Releasing $500,000 will solve two problems

    Owner would getthe spending

    money

    Turner would be

    able to book$100,000 in

    quartersearnings

  • 5/19/2018 Group2 Turner 1

    6/14

    1. What is Turnersbusiness strategy? How does its strategy differ

    from competitors?

    Turners Business Strategy: To makethe owner as partnerin managing the project

    thus a way of getting repetitive business opportunity from the same client

    Prediction at anypoint of time thetotal expected costand earningscontribution of acompleted project

    Identify theproblems andoptions in theproject

    IOR

    Ability to shareaccurate informationwith the owner duringthe progress of theproject

    Projecting itself asquality work and notcompeting on price

    Use of GMP whichleads to sharingof savings

    Communication with

    client

    Turner shows thatthey are expertmanagers and canspend moneyefficiently

    Selected

    knowledgeableclients to workwith

    Decentralizedorganizationstructure

    Organization

  • 5/19/2018 Group2 Turner 1

    7/14

    2. What contingencies could threaten or invalidate the viability of

    Turners strategy?

    Cost

    After releasing thesavings somesituation like strike,

    overtime demand,etc might occur

    Cost overruns thatoccur becauseof improper costestimates whichhappen because ofdifficulty inestimating

    Time

    Lot of time beinginvested inupdating IOR and

    decision makinglater on. This timeis waste if IOR isnot estimatedproperly

    Not all costengineers areequally adept atmaking IOR

    Needs executiveswho have beenexposed to all partsof business

    Owners experienceand knowledge in

    making criticaldecisions

    Demands of ownerto release savingsprematurely -

    thinking they couldinvest the savingselsewhere and thuspressurizing thecompany leads tounexpectedchanges in scope

    Pressure not torelease savings and

    later reducing projectfee earnings

    This leads toholding the fundsfor a long time and

    not informing thesituation to owner

  • 5/19/2018 Group2 Turner 1

    8/14

    3. Evaluate the IOR system and related reports and meetings.

    Does the IOR system force managers and project team to address

    the contingencies you have identifies in previous question?

    Heart of management system at Turner

    Backbone of formal reporting systems

    Project executive, Jim Verzellasview: Real business is riskmanagement and IOR do that effectively

    Project manager, Bill Rantanensview: Forward looking projectmanagement tool

    Senior manager, Division executive Vice President, DonKerstettersview: IOR system drives projection of quarterly

    earnings and reported income to shareholders

    IOR System

  • 5/19/2018 Group2 Turner 1

    9/14

    Ctd..

    Each quarterly update,extensive series of

    discussions andmeetings happen with

    all members of a projectteam included

    Updating of exposureinvolves intuition and

    gut feeling

    1 or 2 months consumedto do detailed work by

    estimators and costengineers to develop

    new IOR for a new job

    After that, quarterlyupdating process takes

    3-4 weeks by cost engg(3 projects at a time)

    C.E. dintreport to P.E.,or TOM, independent,quasi- staff capacity

    Philadelphia Senior Cost Engineer, Jayne Murphysview of IOR:

  • 5/19/2018 Group2 Turner 1

    10/14

    IOR updating process:

    C.E. carefully reviewsvariety of document

    logs with newtransactions ( new

    work orders by sub-contractors)

    For specific answers,the CE made therounds among

    project tem memberswho worked on site

    CE- industry logisticsand project specificconsiderations:costof uncompleted work

    and interpret team

    members assumptionsand explanations

    After this updation,available toeveryone

    for a formal IORreview meeting- Ledby PE- included the

    project

    superitendent,project engg, CE,

    accountant

    Assistant engineersattended to review

    their particular

    trade(eg. Masonry)

    Team membersexplained PE/managerall significant changes

    in project conditionsand Indicated Costsand causes of those

    changes

    CE documented all

    the revised partiallyupdated draft

    Discussion focusedon major variances(

    versus previous IOR)and on E-holds which

    tended to be morecontroversial than

    committed subcontractworks and activities in

    progress

    CE prepared finalupdated version

    from IOR Reviewmeeting

    Reviewed withterritorys senior

    CE, teammanagement signs

    Send new IOR to

    TGM for finalapproval

    TGM- substantialri sk to cost, earn ingsor cli ent r elations.Additional i terationsbefor e approving

    IOR

    Then published byterritory cost dept

    Copies- group VP, hiscost staff, the division

    executive VP andcorporate cost dept

    Problems withproject, unusual forAl McNeil, Chairmanof Turner, to discussdetails contained in

    IOR

    Automated TFS:summary of numbers

    from every IOR inmonthly territoryearnings report

    Eventually in thecorporate income

    statement andcorporate earnings

    projections

  • 5/19/2018 Group2 Turner 1

    11/14

    Advantages of IOR to help solving the contingencies more effectively

    Training

    All the costengineers arecross trained

    vigorously The quality of

    data is very high

    Appraisals

    Appraisals ofmanagers not tiedto performance in

    the IOR Appraisals based

    on performanceof individualemployee andirrespective of theproject

    Hence, honestreporting withoutfear of hiding anybad news

    Reporting

    Cost engineers donot report to anyline management

    They can makerounds in variousprojects to getinformation

    Precaution

    Early warningsabout the criticaltasks

    Helps in decidingwhere riskmanagement ismost critical

  • 5/19/2018 Group2 Turner 1

    12/14

    Amount to be released

    Kent square project estimated cost= $29,000,000, CC = 511,000

    (CC= 1.8%), C-hold= 328,000 and E- hold= 471,000, 5 months remaining,

    Total= CC+CH= 839,000 = 2.9% of $29,000,000( this represents we are in a good position)

    Going smooth so asked $500,000 Already released $215,000 OCC to owners saving pool

    We are in a great shape with good buffer

    Gary tends to be conservative in his projections

    Need to understand owner

    Total project cost (adjusted estimate) = $29,000,000

    20% remaining = 29,000,000*.20= $5,800,000 Total E hold= $471,218

    Total C hold= $328,000

    Total CC = $511,000

    2.5% of 5,800,000= $145,000

    Thus we can easily release amount= $366,000

    Earning for the company= 366,000*.25*.8= $73,200

    Thus contributing 73200/200= 36.6% from one territory

    Amount Given to owner= 366,000 (73.2% of what he demanded)

    Assumptions:

    Proportion method is valid for cost estimates

    Any fluctuation due to labor strike, would be addressed by $145,000+C-hold

  • 5/19/2018 Group2 Turner 1

    13/14

    4. If you were Gary Thompson, what would you say about the $50,000

    contingency to:

    Senior management,(Les, Don)

    The client is new and so cantgoback to him asking for new moneyonce they return the contingency

    We have maintained Constructioncontingency- 2.5% which will

    serve as a bottom line reserve forlater on changes

    C hold has not been compromisedto take care of uncertainty due tolabor strike, scope developmentetc. along with CC

    Earning for the company=366,000*.25*.8= $73,200

    Thus contributing 36.6% fromone territory

    These measures are taken in orderto maintain good clientrelationship and Turnersreputation, which are our primeobjectives

    The owners of Kent square

    Amount Given to owner=366,000 (73.2% of what hedemanded)

    Further exceeding the

    amount given will not be infavor of owner as we willloose all buffer which hasbeen kept for any uncertainty

    Hence for timely completionof the project, we haveestimated the releasedamount very conservatively

    Project team (i.e. Jim, Bill)

    Due to limited availability ofcontingency funds, situations needto be monitored more closely

    All precautions should betaken tokeep overshooting of costs to theminimum

    The smooth running of the projectshould be continued at any cost

  • 5/19/2018 Group2 Turner 1

    14/14