13
ELIZABETH GIRAUT RUSO Grid Integration Manager EWEA WG on Grid Code Requirements Contact: [email protected] EWEC 2010, Warsaw Side Event on Grid Code Requirements Grid Codes Requirements: Grid Codes Requirements: THE DEVELOPERS DILEMMA THE DEVELOPERS DILEMMA

Grid Codes Requirements: THE DEVELOPERS DILEMMA...EWEA WG on Grid Code Requirements How to fulfill requirements? • If the grid integration engineer has to develop solutions for GC

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

  • ELIZABETH GIRAUT RUSO

    Grid Integration Manager

    EWEA WG on Grid Code Requirements

    Contact: [email protected]

    EWEC 2010, Warsaw

    Side Event on Grid Code Requirements

    Grid Codes Requirements:Grid Codes Requirements:

    THE DEVELOPERS DILEMMATHE DEVELOPERS DILEMMA

  • 2Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    Developer’s Responsibility

    TSO / REGULATORS / MEMBER STATES

    GCR

    Developers Responsible for Compliance on Design and Operation of WPP

    WTG Manufacturer

    Manufacturer of Additional Equipment

    Associations

    Elaborate and enforce

    Demonstrate compliance

    Provides solutiontotal / partial

    Provides complementary solution (if needed)

    Collaborate through consultation processesSUCCESSFUL SO FAR!

    Considers in design

  • 3Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    Turbine (WTG) Selection

    SITE

    Which is the network?

    How is the resource?

    Which is the best WTG?

    Which Grid Code applies?

    WTG “X”

    DOES “X”FULFILL

    GC?

    (technical info)

  • 4Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    Developer’s Situation

    • GCR development shall be linked to system needs, but this is

    not the most common scenario: since in immature markets it

    is not easy to determine them, variations in requirements in

    the same country is common over time, becoming harder

    (and sometimes falling in retroactivity and undesirable

    retrofits)

  • 5Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    Example: Evolution ofSpanish GCR

    1st WTG installed in 1981 (100 kW)

    1st WPP installed in mid-eighties

    44 GW

    in 2020?

    1997 1998 2009-

    2010

    20072006200520041999 20082000 2001 2002 2003

    > 400 MW

    installed

    > 800 MW installed, mostly in

    distribution system => low impact on system operation

    Generation Record of 12.916 MW in February

    2010

    Evolution to Ancillary Services

    > 18.6 GW

    Wind power covered 11.5 % of demand, over 40%

    occasionally

    Forecasting mandatory

    Reactive power and FRT capability optional and with

    bonus

    > 8.5 GW installed, mostly in transport system => increasingimpact on system operation

    Remote Control Centers (RCC) mandatory

    > 10 GW installed => collaboration among REE and sector to improve

    operation

    CECRE inaugurated

    PO 3.7 & PO 9 RCC

    PO 12.3 FRT Capability

    PVVC & RCC developed jointly by sector and REE

    Mandatory: Reactive power (with bonus) and

    FRT capability (with bonus for retrofit)

    > 15 GW installed

  • 6Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    Developer’s Situation

    • GCR development shall be linked to system needs, but this is not

    the most common scenario: since in immature markets it is not

    easy to determine them, variations in requirements in the same

    country is common over time, becoming harder (and sometimes

    falling in retroactivity and undesirable retrofits)

    • The main criteria to choose a WTG is rarely Grid Code compliance

    (power curve, etc.)

    • WTGs manufacturers focus their developments in their “star”

    markets, thus adapting their product to specific GCs

    • Consequently, the chosen WTG can be inadequate for complying

    the required GC, because it is “too simple” or “excessively capable”

    HENCE, THE MORE VARIATED AND DIFFERENT THE GRID CODES, THE MORE DIFFICULT TO STANDARDISE SOLUTIONS

  • 7Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    How to fulfill requirements?

    • If the grid integration engineer has to develop solutions for GC fulfillment:

    – Machine level solutions

    • Adapt additional equipment (capacitors, STATCOMS)

    • Work with manufacturer to develop new control systems

    – Substation/plant level solutions

    • Develop additional high level control systems

    • Install cap banks

    • Install STATCOMS or FACTS

  • 8Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    Example: Voltage Dips

    For instance, System Operators around the world impose FRT requirements that are significantly diverse:

  • 9Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    Example: Q & Voltage control

    A similar situation is experienced regarding reactive and voltage control worldwide, as these examples show:

    WPP following a defined PQ characteristic for “absorbed” and “produced” Q

    Q controlDK

    WPP operating within a “V” curve of PQ control with a total dynamic capability of ±30% of Qnominal (at Pnominal).

    Dynamic Q controlCanada

    Automatic control system capable of operating to a setpoint voltageDynamic V controlUSA

    WPP operating within specific “V” curves for lagging (0.835 max at 50% Pnominal) and leading (0.95 max at Pnominal)

    PF controlIR

    SpecificationVoltage Regulation requirement

    Country

    WPP may function in lagging (0.925) or leading (0.95) power factor in case of voltages outside permissible limits

    PF controlDE

    Automatic control system shall be capable of operating to a setpointvoltage between 95% and 105% with a resolution of 0.25% of the nominal voltage and defined slope profiles

    Dynamic V controlUK

    Following a PF table defined for peak, off-peak and valley conditions (in the near future, dynamic V control)

    Q scheduleES

    WPP following a defined PQ characteristic for “absorbed” and “produced” Q

    Q controlDK

    WPP operating within a “V” curve of PQ control with a total dynamic capability of ±30% of Qnominal (at Pnominal).

    Dynamic Q controlCanada

    Automatic control system capable of operating to a setpoint voltageDynamic V controlUSA

    WPP operating within specific “V” curves for lagging (0.835 max at 50% Pnominal) and leading (0.95 max at Pnominal)

    PF controlIR

    SpecificationVoltage Regulation requirement

    Country

    WPP may function in lagging (0.925) or leading (0.95) power factor in case of voltages outside permissible limits

    PF controlDE

    Automatic control system shall be capable of operating to a setpointvoltage between 95% and 105% with a resolution of 0.25% of the nominal voltage and defined slope profiles

    Dynamic V controlUK

    Following a PF table defined for peak, off-peak and valley conditions (in the near future, dynamic V control)

    Q scheduleES

  • 10Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    Dilemmas

    • Can I standardize solutions?

    • Can I always use the same WTG?

    • Or the same design for my WPP?

    • Or the same additional equipment?

    • Or the same control solution?

  • 11Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    Conclusions

    Differences in CGR lead to:

    • Different solutions are applied on different systems

    • No standardization is possible on:

    – Design of Wind Power Plant

    – O&M processes

    – Procurement processes (e.g. provider's homologation for spare parts)

    – Control systems

    – SCADA & Communications

    ~> Costs increase and optimization is not possible

  • 12Warsaw, April 2010 EWEC 2010, Side Event GCR

    EWEA WG on Grid Code Requirements

    Conclusions

    • As well as manufacturers, it is essential for developers to count on harmonization whenever possible: Concepts, definitions, format, functionalities, numbers.

    • It eases the interpretation of requirements if we have those for wind separated from those for other generators

    • It sets the proper frame for keeping consultation processes going on with industry and MS

    • It will allow developers to design WPP that provide a better product: higher quality of service with reduced costs

  • ELIZABETH GIRAUT RUSO

    Grid Integration Manager

    EWEA WG on Grid Code Requirements

    Contact: [email protected]

    EWEC 2010, Warsaw

    Side Event on Grid Code Requirements

    Thank you for your attentionThank you for your attention

    Questions? Comments?Questions? Comments?