Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Master’s Degree
Qualification
Grid Code Proposal for
Solar Photovoltaics Power Plant in Indonesia
REPORT
Author: INDRA Pratama Supervisor: ANDREAS Sumper & EDUARD Bullich-Massagué
Completion date: June 2019
Barcelona School of Industrial Engineering
Page 2 Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 3
Abstract
This master thesis deals with the grid code design for solar photovoltaics power plant (PVPP).
For this purpose, three approaches are identified: (1) Several sets of international grid codes
for large scale solar PVPP are studied from operational perspective such as voltage and
frequency boundaries, active power and frequency support, reactive power and voltage
support and fault-ride-through. The chosen sets of grid codes are of Puerto Rico, Germany,
Denmark and European Union since they are mature enough and well-developed to study.
Additionally, the core of this master thesis is to study the existing electricity transmission and
distribution system in Indonesia along with current grid codes. The aforementioned research
of international grid codes serves as a foundation to propose suitable grid code design or
update existing grid code for solar PVPP in Indonesia. (2) the introduction and characteristics
of solar photovoltaics power plant (PVPP) in which the basic electrical components (e.g. PV
panel, PV inverter and transformer) are discussed. Besides, inverter topology (e.g. central
inverter topology, string inverter topology, multistring inverter topology, etc.) and internal
collection grid configuration (e.g. radial configuration, ring configuration, star configuration) is
explained. In addition, the brief modelling approach for each electrical component is given in
this chapter. (3) In the later part of this master thesis, a 1 MW solar PVPP along with the
electrical grid is modelled and simulated to test the proposed grid code for solar PVPP in
Indonesia. The proposed grid codes that are tested and simulated are active power and
frequency regulation particularly absolute production (i.e. power curtailment) through
maximum power point tracking (MPPT) function in PV inverter as well as reactive power and
voltage support regulation such as function of voltage control, reactive power control and
power factor control.
Page 4 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Contents
ABSTRACT ___________________________________________________ 3
LIST OF FIGURES _____________________________________________ 7
LIST OF TABLES _____________________________________________ 10
THESIS OUTLINE _____________________________________________ 16
NOMENCLATURE ____________________________________________ 18
INTRODUCTION __________________________________________ 19
Overview ...................................................................................................... 19
REVIEW OF INTERNATIONAL GRID CODES __________________ 22
Necessity of Grid Code ................................................................................ 22
Contents of Grid Code ................................................................................. 27
Voltage and Frequency Boundaries ................................................................ 28
Active Power and Frequency Control Functions ............................................. 28
Reactive Power and Voltage Control Functions .............................................. 30
Fault-Ride-Through (FRT) Capability .............................................................. 32
Grid Codes of Puerto Rico ........................................................................... 35
2.3.1 Voltage and Frequency Boundaries ................................................................ 35
2.3.2 Active Power and Frequency Support ............................................................. 36
2.3.3 Reactive Power and Voltage Support ............................................................. 39
2.3.4 Fault-Ride-Through Requirement ................................................................... 39
Grid Codes of Germany ............................................................................... 41
2.4.1 Voltage and Frequency Boundaries ................................................................ 41
2.4.2 Active Power and Frequency Support ............................................................. 42
2.4.3 Reactive Power and Voltage Support ............................................................. 44
2.4.4 Fault-Ride-Through Capability ........................................................................ 45
Grid Codes of Denmark ............................................................................... 46
2.5.1 Voltage and Frequency Boundaries ................................................................ 47
2.5.2 Active Power and Frequency Support ............................................................. 48
2.5.3 Reactive Power and Voltage Support ............................................................. 50
2.5.4 Fault-Ride-Through Capability ........................................................................ 52
2.6 Grid Codes of European Union .................................................................... 52
2.6.1 Voltage and Frequency Boundaries ................................................................ 54
2.6.2 Active Power and Frequency Support ............................................................. 55
2.6.3 Reactive Power and Voltage Support ............................................................. 57
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 5
2.6.4 Fault-Ride-Through Capability ........................................................................ 57
2.7 Summary ...................................................................................................... 59
GRID CODE PROPOSAL FOR SOLAR PVPP IN INDONESIA _____ 63
3.1 Existing Electricity Transmission and Distribution System ........................... 64
3.2 Current Grid Codes of Indonesia .................................................................. 66
3.2.1 Voltage and Frequency Boundaries ................................................................ 67
3.2.2 Active Power and Frequency Support ............................................................. 68
3.2.3 Reactive Power and Voltage Support ............................................................. 68
3.2.4 Fault-Ride-Through Capability ........................................................................ 69
3.3 Grid Code Proposal ...................................................................................... 70
3.3.1 Voltage and Frequency Boundaries ................................................................ 73
3.3.2 Active Power and Frequency Support ............................................................. 74
3.3.3 Reactive Power and Voltage Support ............................................................. 76
3.3.4 Fault-Ride-Through Capability ........................................................................ 78
INTRODUCTION AND CONTROL OF SOLAR PHOTOVOLTAICS
POWER PLANT __________________________________________ 81
Introduction ................................................................................................... 81
PV Panels ..................................................................................................... 84
PV Inverters .................................................................................................. 86
4.3.1 Local Control of PV Inverter ............................................................................ 88
Master Control by Power Plant Controller .................................................... 91
MODELLING AND SIMULATION OF SOLAR PVPP _____________ 95
PV Arrays ..................................................................................................... 95
PV Inverters ................................................................................................ 101
5.2.1 Aggregated PV Inverter Model .......................................................................... 104
PV Plant Model ........................................................................................... 104
RESULTS AND DISCUSSION ______________________________ 106
Maximum Power Point Tracking (MPPT) ................................................... 106
6.2.1 Maximum Power Point (MPP) Mode ............................................................. 106
6.2.1 Active Power Setpoint Mode (i.e. Power Curtailment) ................................... 108
Voltage Control and Reactive Power Regulation Action ............................ 110
6.2.2 Reactive Power Control ................................................................................ 115
6.2.3 Power Factor Control .................................................................................... 117
CONCLUSION __________________________________________ 120
BIBLIOGRAPHY _________________________________________ 122
Page 6 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 7
List of Figures
Figure 1. 1 Global cumulative PV installation in 2014 and 2017 [9] ...................................... 20
Figure 2. 1 Puerto Rico’s electricity generation mix in 2014 and 2017 [14] [15] .................... 23
Figure 2. 2 Germany’s electricity generation mix in 2010 and 2017 [16] [17] ....................... 24
Figure 2. 3 Denmark` electricity generation mix in 2010 and 2016 [18] ................................ 24
Figure 2. 4 EU’s electricity generation mix in 2000 and 2016 [19] ........................................ 25
Figure 2. 5 EU´s installed power capacity in 2005 and 2017 [20] ......................................... 26
Figure 2. 6 Frequency response or control [adapted from [12]] ............................................ 29
Figure 2. 7 Absolute production, delta production and power gradient [adapted from [27]] .. 30
Figure 2. 8 Voltage control with droop function [adapted from [28]] ...................................... 31
Figure 2. 9 Automatic power factor control [adapted from [27]] ............................................ 32
Figure 2. 10 Normal operating zones as functions of power factor and reactive power ........ 32
Figure 2. 11 LVRT Capability [12] ........................................................................................ 33
Figure 2. 12 HVRT capability [12] ......................................................................................... 34
Figure 2. 13 Reactive current injection ................................................................................. 35
Figure 2. 14 FRT requirement [adapted from [29]] ............................................................... 46
Figure 2. 15 The map of synchronous areas in Europe [36] ................................................. 54
Figure 2. 16 LVRT requirement due to symmetrical fault ..................................................... 58
Figure 3. 1 Indonesia´s installed power capacity .................................................................. 63
Figure 3. 2 Indonesia´s energy mix by 2025 [39] .................................................................. 64
Figure 3. 3 Illustrative single line diagram of generation, transmission and .......................... 65
Page 8 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 4. 1 PV inverter topologies [adapted from [58]]. ........................................................ 82
Figure 4. 2 Radial collection grid topology [58] ..................................................................... 83
Figure 4. 3 Ring collection grid topology [58] ........................................................................ 83
Figure 4. 4 Star collection grid topology [58]......................................................................... 84
Figure 4. 5 General model of solar cell circuit [adapted from [[64]] ....................................... 85
Figure 4. 6 General equivalent circuits of PV [64] ................................................................. 86
Figure 4. 7 Electrical scheme of on-grid solar PVPP under study [adapted from [70]] .......... 87
Figure 4. 8 Electrical scheme of average on-grid solar PVPP model under study [adapted from
[45]] ...................................................................................................................................... 88
Figure 4. 9 Electrical scheme of average PV inverter model under study [adapted from [45]]
............................................................................................................................................. 88
Figure 4. 10 General control scheme of PV inverter ............................................................. 89
Figure 4. 11 Typical LS-PVPP layout including power plant control scheme [28] ................. 93
Figure 4. 12 Voltage control function [28] ............................................................................. 94
Figure 5. 1 V-I and V-P characteristic curves of PV module at T = 25oC and G = 1000 W/m2
............................................................................................................................................. 97
Figure 5. 2 V-I and V-P characteristic curves of two (2) PV arrays ....................................... 97
Figure 5. 3 PV arrays characteristics in function of working temperature (T) ........................ 99
Figure 5. 4 PV arrays characteristics in function of irradiance (G) ........................................ 99
Figure 5. 5 Max PV power in function of temperature (T) and ............................................ 100
Figure 5. 6 Max PV power in function of irradiance (G) and ............................................... 100
Figure 5. 7 The layout of PV inverter model ...................................................................... 102
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 9
Figure 5. 8 The layout of PV plant simulation model .......................................................... 105
Figure 6. 1 PV power in function of working temperature (T) and ....................................... 107
Figure 6. 2 PV power in function of irradiance (G) and ....................................................... 107
Figure 6. 3 Option 1 in active power setpoint mode ............................................................ 109
Figure 6. 4 Option 2 in active power setpoint mode ............................................................ 110
Figure 6. 5 Response to voltage control function ................................................................ 113
Figure 6. 6 Response to voltage control function with different parameters ....................... 114
Figure 6. 7 Response to maximum allowable reactive power setpoint ............................... 116
Figure 6. 8 Response to minimum allowable reactive power setpoint ................................ 117
Figure 6. 9 Response to maximum allowable power factor setpoint ................................... 118
Figure 6. 10 Response to minimum allowable power factor setpoint .................................. 119
Page 10 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
List of Tables
Table 2. 1 International grid codes under study .................................................................... 27
Table 2. 2 Range of normal operating frequency ................................................................. 36
Table 2. 3 Range of normal operating voltage ...................................................................... 36
Table 2. 4 Active power and frequency support requirements .............................................. 36
Table 2. 5 Parameter in case 1 ............................................................................................ 37
Table 2. 6 Parameter in case 2 ............................................................................................ 38
Table 2. 7 Constraint functions ............................................................................................. 38
Table 2. 8 Reactive power and voltage support requirements .............................................. 39
Table 2. 9 Parameters in voltage control function................................................................. 39
Table 2. 10 Fault-ride-through requirement .......................................................................... 40
Table 2. 11 Parameters in LVRT requirement ...................................................................... 40
Table 2. 12 Parameters in HVRT requirement ..................................................................... 40
Table 2. 13 Parameters in reactive current injection requirement ......................................... 41
Table 2. 14 The scope of the latest Germany´s regulation for grid code .............................. 41
Table 2. 15 The range of normal operating frequency .......................................................... 42
Table 2. 16 The range of normal operating voltage .............................................................. 42
Table 2. 17 Active power and frequency support requirements ............................................ 42
Table 2. 18 Parameters in frequency response or control .................................................... 43
Table 2. 19 Constraint functions ........................................................................................... 44
Table 2. 20 Reactive power and voltage support requirement ............................................. 44
Table 2. 21 Parameters in voltage control function............................................................... 44
Table 2. 22 Parameters in reactive power control ................................................................ 45
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 11
Table 2. 23 Fault-ride-through requirement .......................................................................... 46
Table 2. 24 Voltage level and nominal output power for each type of power plants ............. 47
Table 2. 25 Nominal voltage, minimum voltage (Umin) and maximum voltage (Umax) ............ 48
Table 2. 26 Active power and frequency support requirements ............................................ 48
Table 2. 27 Parameters in frequency response or control .................................................... 49
Table 2. 28 Constraint functions ........................................................................................... 50
Table 2. 29 Reactive power and voltage support requirements ............................................ 50
Table 2. 30 Parameters in reactive power control ................................................................ 51
Table 2. 31 Parameters in automatic power factor control function ...................................... 52
Table 2. 32 Fault-ride-through requirement .......................................................................... 52
Table 2. 33 Capacity range .................................................................................................. 53
Table 2. 34 Range of normal operating frequency ............................................................... 55
Table 2. 35 Active power and frequency support requirements ............................................ 55
Table 2. 36 Parameters in frequency response or control .................................................... 56
Table 2. 37 Constraint functions ........................................................................................... 57
Table 2. 38 Reactive power and voltage support requirement ............................................. 57
Table 2. 39 Fault-ride-through requirement .......................................................................... 57
Table 2. 40 Parameters in LVRT .......................................................................................... 58
Table 2. 41 Classification based on type and voltage level at PCC ...................................... 59
Table 2. 42 Normal operating frequency .............................................................................. 60
Table 2. 43 Normal operating voltage .................................................................................. 61
Table 2. 44 Active power and frequency support requirement ............................................. 62
Table 2. 45 Reactive power and voltage support requirement ............................................. 62
Page 12 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Table 2. 46 FRT requirement ............................................................................................... 62
Table 3. 1 Electrically Synchronous Area ............................................................................. 66
Table 3. 2 Regulation and grid code under study ................................................................. 67
Table 3. 3 The scope of regulation for grid code .................................................................. 67
Table 3. 4 Range of normal operating frequency ................................................................. 68
Table 3. 5 Range of normal operating voltage ...................................................................... 68
Table 3. 6 Active power and frequency requirement ............................................................ 68
Table 3. 7 Reactive power and voltage support requirements .............................................. 69
Table 3. 8 Parameters in reactive power control .................................................................. 69
Table 3. 9 Fault-ride-through requirement ............................................................................ 70
Table 3. 10 The geographic condition of Indonesia [49] ....................................................... 70
Table 3. 11 The geographic condition of Puerto Rico [50] .................................................... 70
Table 3. 12 The geographic condition of Denmark [51] ........................................................ 71
Table 3. 13 The geographic condition of Germany [52] ........................................................ 71
Table 3. 14 The geographic condition of European Union [53] ............................................. 71
Table 3. 15 Solar power percentage in electricity generation ............................................... 72
Table 3. 16 Status of Indonesia´s electricity interconnection system [46] [47] ...................... 72
Table 3. 17 Status of Puerto Rico´s electricity interconnection system [54] .......................... 72
Table 3. 18 Status of Denmark´s electricity interconnection system [55] [56] ....................... 72
Table 3. 19 Status of Germany´s electricity interconnection system [56] .............................. 73
Table 3. 20 Status of EU´s electricity interconnection system [56] ....................................... 73
Table 3. 21 Normal operating frequency for major islands ................................................... 73
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 13
Table 3. 22 Normal operating frequency for minor islands ................................................... 74
Table 3. 23 Normal operating voltatge for small islands ....................................................... 74
Table 3. 24 Active power and frequency support requirements ............................................ 74
Table 3. 25 Parameters in frequency response or control for major islands and small islands
............................................................................................................................................. 76
Table 3. 26 Types of constraint functions ............................................................................. 76
Table 3. 27 Reactive power and voltage support for solar PVPP in major islands and small
islands .................................................................................................................................. 77
Table 3. 28 Parameters in voltage control function ............................................................... 77
Table 3. 29 Parameters in reactive power control ................................................................ 78
Table 3. 31 Fault-ride-through requirement .......................................................................... 79
Table 3. 32 Parameters in LVRT requirement ...................................................................... 79
Table 3. 33 Parameters in HVRT requirement ..................................................................... 80
Table 3. 34 Parameters in reactive current injection requirement ......................................... 80
Table 5. 1 Characteristics of PV module [71] ....................................................................... 95
Table 5. 2 Simulation results of PV module .......................................................................... 98
Table 5. 3 Simulation results of two (2) PV arrays ................................................................ 98
Table 5. 4 Characteristics of PV inverter model.................................................................. 103
Table 5. 5 Equivalent grid data ........................................................................................... 105
Table 6. 1 Maximum PV power in function of working temperature (T) and at constant
irradiance (G) of 1000 W/m2 ............................................................................................... 108
Table 6. 2 Maximum PV power in function of irradiance (G) and at constant working
temperature (T) of 1000 W/m2 ............................................................................................ 108
Page 14 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Table 6. 3 Parameters in response to voltage control function ........................................... 113
Table 6. 4 Parameters in determinate points for each period ............................................. 114
Table 6. 5 Parameters in response to another voltage control function .............................. 115
Table 6. 6 Parameters in determinate points for each period ............................................. 115
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 15
Page 16 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Thesis Outline
Objectives
The main objective of this master thesis is to propose grid code design or update existing grid
codes for 1 MW solar photovoltaics power plant (PVPP) connected to medium voltage (MV)
level network in Indonesia. The following tasks are carried out to attain this objective:
• Study some sets of international grid code such as grid codes of Puerto Rico, Germany,
Denmark and European Union which permits to analyze the correct trends of
connection requirement.
• Describe the existing structure of electricity transmission and distribution system as
well as current grid code of Indonesia. Then propose grid code design or update on the
existing grid code.
• Discuss the introduction and characteristics of solar PVPP that contains the basic
electrical components, inverter topologies as well as internal collection grid
configuration.
• Model and simulate a 1 MW solar PVPP together with associated devices to test the
proposed grid code design for solar PVPP in Indonesia in terms of active power
regulation (absolute production) and reactive power regulation.
Scope
The scope of study in this master thesis are.
• The grid code in this master thesis is presented from operational perspective. It
basically consists of requirement of voltage and frequency boundaries, active power
and frequency support, reactive power and voltage support and fault-ride-through
(FRT) for 1 MW solar PVPP connected to medium voltage (MV) network. In other
words, grid codes pertaining to low voltage (LV) network is out of scope of this master
thesis.
• In order to test the proposed grid code, a simplified 1 MW solar PVPP with its
associated devices is modelled and simulated in Matlab and Simulink.
Organization
This master thesis is organized as follows.
• Chapter 1: introduction to the recent developments of renewable energy sources
worldwide including solar power is described along with objectives and scopes of this
master thesis.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 17
• Chapter 2: this chapter begins with the necessity of grid code for solar PVPP. In
addition, some international grid codes such as grid code of Puerto Rico, Germany,
Denmark and European Union are discussed. In the end of this chapter, the summary
of operational requirements such as voltage and frequency boundaries, active power
and frequency support, reactive power and voltage support and fault-ride-through of
each international grid code is given
• Chapter 3: here, the general structure of electrical generation, transmission and
distribution system in Indonesia as well as the existing grid code of Indonesia for solar
PVPP are discussed. Also, the proposed update on existing grid code for solar PVPP
is described.
• Chapter 4: an introduction of solar PVPP is given along with characteristics, basic
electrical components (i.e. photovoltaics (PV) arrays, PV inverters and transformer)
and inverter topologies together with collection grid configuration of solar PVPP.
Additionally, the control theory of solar PVPP is described in the present chapter.
• Chapter 5: in this chapter, the modelling approach for each electrical element in solar
PVPP is described. Then the model of each electrical element is simulated.
Additionally, a 1 MW solar photovoltaics power plant is modelled and simulated. The
model is made up of solar PV arrays, solar PV inverter, transformer and electrical grid.
• Chapter 6: here the results and discussion about grid code proposal for solar PVPP in
Indonesia along with the simulation result of a 1 MW solar PVPP for active power and
frequency support function particularly MPPT function as well as reactive power and
voltage support function are given.
• Chapter 7: in this chapter the conclusions of this master thesis are drawn.
Page 18 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Nomenclature
EU European Union
FACTS Flexible Alternating Current Transmission System
FRT Fault-Ride-Through
GHG Green House Gas
HVRT High-Voltage-Ride-Through
IEC International Electrotechnical Comission
LS-PVPP Large Scale Photovoltaics Power Plant
LV Low Voltage
LVRT Low-Voltage-Ride-Through
MV Medium Voltage
MPPT Maximum Power Point Tracking
NA Not Applicable
NS Not Stated
PCC Point of Common Coupling
PPC Power Plant Controller
PV Photovoltaics
PVPP Photovoltaics Power Plant
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 19
Introduction
Overview
It is expected that the energy demand is going to rise by 41% in the next 20 years because of
increasing industrial and residential needs [1]. In recent years, over 75% of the electricity
demand was met by using fossil fuel sources [2]. Due to its nature, fossil fuels sources cannot
be replenished in human time scale and hence it creates a need to meet the growing energy
demand using renewable energy source. Moreover, carbon dioxide (CO2) emissions from
fossil fuel combustion and industrial processes contributed approximately 78% of the total
greenhouse gas (GHG) emission increase from 1970 to 2010. Without additional efforts to
reduce GHG emissions beyond on-going efforts, emission growth is expected to continue due
to growth of economic activities and global population. It is estimated that, without additional
climate change mitigation, global mean surface temperature will increase between 3.7oC and
4.8oC in 2100 in comparison with pre-industrial level (i.e. period before 1750) [3].
In Europe, the European Union (EU) member states agreed to carry out Horizon 2020 (H2020)
plan which sets out 20% of the energy demand comes from renewable energy source, a
greenhouse gas emission reduction of 20% as well as the implementation of 20% energy
saving in a cost-efficient manner by 2020 in comparison to each respective status in 1990 [4].
In addition, Horizon (H2030) and Horizon (H2050) plan lays down the target of 27% and 75%
energy demand comes from renewable energy source, a 40% and 80% greenhouse gas
emission reduction along with the energy saving of 27% and 41% in comparison to each
respective status in 1990 [5].
Hence, renewable energy has been harnessed more and more in the recent years mainly
dominated by wind and solar energy sources. Wind power experienced the fastest growth over
the years. In fact, the aggregated wind power installation in the EU by the end of 2014 was
128.8 GW [6] whereas in Asia, US and Latin America was 115 GW [7], 65 GW [8] and 4 GW
[7] respectively.
On the contrary, PV power installations did not experience the same growth rate due to prices
of photovoltaic panels and the associated technology. According to Fraunhofer ISE, as
illustrated in Fig.1.1, the cumulative installed capacity of photovoltaics power in 2014 was
181.25 GW comprising 31.25 GW in China, 87.5 GW in Europe, 20.8 GW in North America,
25 GW in Japan, 8.3 GW in the Rest of Asia-Pacific & Central Asia, 4.2 GW in India, 2.1 GW
in Latin America & Caribbean and 2.1 GW in Middle East & Africa. By 2017 the cumulative
installed capacity of photovoltaic power rose to 414 GW (i.e. over doubled) comprising 133
GW in China, 115 GW in Europe, 58 GW in North America, 49 GW in Japan, 22 GW in the
Page 20 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
rest of Asia-Pacific & Central Asia, 20 GW in India, 9 GW in Latin America & Carribean and 8
GW in Middle East and Africa. In 2018, USA solar market expanded by 10.6 GW of PV
especially in residential sector [10].
Figure 1. 1 Global cumulative PV installation in 2014 and 2017 [9]
The dramatic increase of variable renewable energy (e.g. wind and solar energy) source poses
a challenge to the electrical grid due to its stochastic nature, particularly on the transmission
and distribution level. The wind power plant and solar PVPP is expected not to behave like
wind and solar farm (only generate electrical power) but as similar to conventional power plant
(provide grid support functions) as possible [11]. Therefore, the need for creating grid codes
or updating the existing ones which set outs the grid support requirements defined at the point
of common coupling (PCC) for wind power plant and solar PVPP arises [12]. In this sense,
32%
28%
14%
12%
5%5% 2% 2%
Global Cumulative PV Installation in 2017
17%
48%
12%
14%
5% 2% 1% 1%
Global Cumulative PV Installation in 2014
China
Europe
North America
Japan
Rest of Asia-Pacific & CentralAsia
India
Latin America & Caribbean
Middle East & Africa
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 21
wind power plants triggered the grid code development followed by grid codes applied to solar
PVPP.
Page 22 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Review of International Grid Codes
Necessity of Grid Code
Generally, a power plant can be defined as a centralized system with the objective of injecting
power to the electrical grid (i.e. not to a particular individual customer) [13]. Its main goals are
to operate independently and to meet the requirements of electrical system under some
regulations. These regulations are in the forms of grid codes and standards that define
connection requirements on the MV and LV level for these power plants to the transmission
and distribution grid with purpose of increasing its reliability, stability and security. These grid
codes were traditionally established to allow interconnection of non-renewable energy power
plants to the grid. The contribution of renewable energy power plants to electricity generation
was initially very low in comparison with non-renewable energy power plants. However, this
situation started to change dramatically in the recent years due to renewable energy sources
have been harnessed more and more. As a result, in most countries, the share of renewable
energy in electricity generation increased [12].
A couple of years ago, particularly in 2014, Puerto Rico’s electricity generation came from 19.1
TWh fossil fuel energy, 0.4 TWh controllable renewable energy (i.e. any other renewable
energy than wind and solar) and 0.48 TWh variable renewable energy (i.e. wind and solar) as
illustrated in Fig. 2.1. It is seen that the in 2014 variable renewable energy source held nearly
0% of the Puerto Rico’s electricity generation [14]. However, in 2017 variable renewable
energy source emerged in Puerto Rico’s electricity generation up to 0.336 TWh (i.e. 2% of
Puerto Rico’s electricity generation) and the rest of Puerto Rico’s electricity generation was
composed of 20.58 TWh fossil fuel energy and 0.084 TWh controllable renewable energy. The
reduction of controllable renewable energy fraction is presumed to be caused by disaster of
Hurricanes Maria and Irma that destroyed much of the electricity generating facilities in 2017
[15]. However, according to Puerto Rico’s energy road map, renewable energy fraction of
Puerto Rico’s electricity generation is expected to reach 15% and 20% by 2025 and 2035,
respectively [14].
On the other side of the world, as seen in Fig.2.2, in 2010 Germany´s electricity generation
came from 352 TWh fossil fuel energy, 193.23 TWh controllable renewable energy, 49.5 TWh
variable renewable energy (i.e. wind and solar) and 37.5 TWh others [16]. It is seen that
variable renewable energy source held 7% of Germany’s electricity generation in 2010. In 2017
the share of variable renewable energy in Germany´s electricity generation increased to 67
TWh (i.e. 10% of Germany’s electricity generation) and the rest of Germany’s electricity
generation came from 328 TWh fossil fuel energy, 224 TWh controllable renewable energy
and 30 TWh others [17].
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 23
As illustrated in Fig. 2.3, the same situation happened in Denmark where in 2010
Denmark´s electricity generation came from 5.42 TWh controllable renewable energy, 7.81
TWh variable renewable energy and 25.7 TWh fossil fuel energy. It can be observed that in
2010 the variable renewable energy source held 20% of the electricity generation in
Denmark. Then in 2016 the fraction of variable renewable energy in Denmark’s electricity
generation increased drastically to 13.5 TWh (i.e. 44% of Denmark’s electricity generation)
along with the controllable renewable energy and fossil fuel energy that contributed 5.89
TWh and 11.4 TWh, respectively [18].
Generally, such a situation happened across Europe as depicted in Fig. 2.4 where in 2000,
overall EU’s electricity generation came from 1,628 TWh fossil fuel energy, 1,382 TWh
controllable renewable energy, 22.1 TWh variable renewable energy and 1 TWh others. It is
seen that in 2000, variable renewable energy source held 1% of the EU´s electricity
generation. In contrast, in 2016 the variable renewable energy source contributed 407 TWh
(i.e. 12%) of the overall EU’s electricity generation and the rest of EU’s electricity generation
came from 1,402 TWh fossil fuel energy, 1,439 TWh controllable renewable energy and 5 TWh
from the other as described in Fig.2.5 [19].
Figure 2. 1 Puerto Rico’s electricity generation mix in 2014 and 2017 [14] [15]
Page 24 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 2. 2 Germany’s electricity generation mix in 2010 and 2017 [16] [17]
Figure 2. 3 Denmark` electricity generation mix in 2010 and 2016 [18]
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 25
Figure 2. 4 EU’s electricity generation mix in 2000 and 2016 [19]
The growing share of renewable energy in global electricity generation, especially in Europe,
is aligned with the increasing share of installed power capacity in Europe. In the last decade,
approximately 60% newly constructed power generation is of variable renewable energy
generation. As depicted in Fig.2.5, in 2005, the variable renewable energy power generation
accounted for 43 GW (i.e. 6%) of the EU´s installed power capacity. Then, the rest is made up
of fossil fuel power generation, controllable renewable energy power generation, variable
renewable energy power generation and the other type of power generation accounted for 357
GW, 258 GW and 18 GW, respectively. In 2017, the share of variable renewable energy
generation rose to 276 GW (i.e. 29%) of the EU´s installed power capacity and the rest is made
up of 365 GW fossil fuel power generation, 270 GW controllable power generation and 27 GW
other type of power generation [20].
Page 26 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 2. 5 EU´s installed power capacity in 2005 and 2017 [20]
By nature, renewable energy source, particularly variable renewable energy source (i.e. wind
and solar photovoltaics) entails intermittency which present problems to the electrical system.
These problems can be overcome by the provision of grid support function of the variable
renewable energy power generation. The grid support requirement for variable renewable
energy power plant is set out in grid codes and standards established by relevant system
operator. Therefore, it is necessary to review and update the grid code and standard regularly
as the amount of variable renewable energy penetration is growing.
The other motivation for establishment of grid codes and standards is that before the
privatization and liberation of electricity market, the electricity network of generation,
transmission and distribution could be managed by the same company. After the privatization
and liberalization of electricity market that leads to deregulation, different companies may
manage each network of transmission and distribution. Consequently, responsible system
operators worldwide have prepared grid codes and standards that set out the technical
specifications and operational characteristics at the point of connection that power generation
must comply. It has the purpose of maintaining uniformity of requirements for each power
generation. These grid codes vary by local regulation, legal and technical environment.
In this way, wind power plants first triggered the development of grid codes followed by solar
PVPP. According to the electricity system operator of the UK, grid code is the technical code
for connection and development of the National Electricity Transmission System (NETS) [21].
Additionally, grid code can be defined as a technical document containing the set of rules
governs the operation, maintenance and development of the system at the point of common
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 27
coupling (PCC) [22].
Thus, this chapter is dedicated for discussion about international grid codes for solar PVPP in
selected countries (i.e. Puerto Rico, Germany, Denmark and European Union) since they have
common trend of growing share of solar PVPP in their individual installed power capacity.
Moreover, their grid codes are mature enough and well-defined to study. Then, an analysis of
the main grid code requirements for solar PVPP connected to the electrical system is
performed. This analysis is carried out from viewpoint of frequency and voltage boundaries,
active power and frequency control, reactive power and voltage control along with fault-ride-
through capability.
In following sections, as described in Table. 2.1, each set of grid codes of Germany, Denmark,
Puerto Rico and European Union for LS-PVPP connected to medium voltage network
managed by relevant system operator in respective country is discussed.
Country /
Territory
Organization Title Version
USA
(Puerto Rico)
PREPA Technical Requirements for
Interconnecting Wind and Solar
Generation
August, 2012
Germany VDE Summary of the Draft VDE-AR-N
4110:2017:02 – Connection and
Operation to Medium Voltage Grid
February, 2017
Denmark Energinet Technical Regulation 3.2.2. for PV
Power Plants Above 11 kW
July, 2016
European Union European
Comission
EU Directive 2016/631
Establishing a Network Code on
Requirements for Grid Connection
Generators
April, 2016
Table 2. 1 International grid codes under study
Contents of Grid Code
In this section, the basic contents of grid code from operational viewpoint are discussed. The
first regulations that established the connection requirement for solar PVPP to the electrical
Page 28 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
network are IEEE 1547 and EN 50160. They are intended for small scale solar PVPPs
interconnected to the distribution network for residential, commercial and industrial purpose.
In fact, these regulations prevented small scale solar PVPPs from providing ancillary services
such as frequency and voltage support as well as reactive power support [23]. However, as
discussed earlier, in the coming years the large amount of solar power is expected to penetrate
into the electrical grid. This may cause problems due to its intermittency, lack of voltage
support, variable active power and power mismatching. Therefore, the grid codes for
interconnection of solar PVPP to the electrical network have been developed in a way that
capability of fault-ride-through, active power and frequency support along with reactive power
and voltage support is required.
Germany is the first country that launched grid codes for solar PVPP connected to MV and HV
level network in 2008 [22]. 4 years after Denmark´s grid code for wind power plant was
released. This grid code has been an inspiration for the other grid codes by several other
countries in Europe. After Germany´s grid code, South Africa [24], China [25] and Romania
[26]
Grid code from operational perspectives basically contains voltage and frequency boundaries,
active power and frequency control function, voltage and reactive power control function, and
FRT capability and they are summarized one by one in following subsections.
Voltage and Frequency Boundaries
Grid code essentially states the electrical boundaries under which the solar PVPP must
operate continuously. The electrical boundaries consist of range of normal operating voltage
and frequency at the PCC. Each range consists of several sub-ranges in which the solar PVPP
must remain online for particular period of time. The voltage and frequency boundaries are
established uniformly by relevant system operator for each solar PVPP.
Active Power and Frequency Control Functions
As the solar energy varies throughout the day, the need for controlling the active power of solar
PVPP arises. Active power and frequency control is essentially made up of function of
frequency response or control, absolute production (i.e. power curtailment), delta production
(i.e. power reserve) and power gradient (i.e. ramp rate). Frequency response or frequency
control can be defined as the capability of a solar PVPP to adjust its active power output (P) in
response to a measured deviation at the point of common coupling of system frequency (Δf)
from a setpoint with a view to stabilize the grid. The permissible variation of active power due
to the change of frequency is described by droop. Droop constant is expressed by the ratio of
change in frequency (Δf) over nominal frequency (fn) to change of actual active power output
(ΔP) over nominal output power (Pn) or actual active power output (Pac) depending on the grid
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 29
code. The frequency response or control is illustrated in Fig.2.6. The frequency response or
control is composed of upward droop (line from f2 to f1), dead band (the range where no change
in active power), downward droop (line from f3 to fmax) and control band (the range comprises
upward droop, dead band and downward droop). In addition, the active power output is allowed
to rise again after the frequency f4 is reached. Please note that fn represents nominal
frequency.
Absolute production is the adjustment of active power (P) to maximum level at the point of
common coupling as indicated by setpoint. The purpose of absolute production is to protect
the electrical grid from overloading in critical situations. Then, delta production is the power
reserve that a solar PVPP creates out of the difference between the available active power
output (Pav) and actual active power output (Pac). The purpose of delta production is to establish
a regulating reserve for upward regulation related to the delivery of ancillary service (i.e.
frequency response or control). In addition, power gradient is used to limit the maximum speed
by which the active power (ΔP) can be changed in the event of changes in power or the set
points for a plant. Its unit is power over time. The purpose of power gradient is to prevent the
changes in active power from adversely impacting the electrical grid. Fig.2.7. Illustrates the
function of absolute production, delta production and power gradient.
Figure 2. 6 Frequency response or control [adapted from [12]]
Page 30 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 2. 7 Absolute production, delta production and power gradient [adapted from [27]]
Reactive Power and Voltage Control Functions
Solar PVPP must be capable of overcoming voltage deviations and providing reactive
support to the grid as conventional power plants. Thus, grid codes establish the minimum
reactive power requirement that solar PVPP must comply with. In the past, PV inverters
were not designed considering this requirement but recently some PV inverter
manufacturers considering this requirement in PV inverters specification. The capability of
reactive support in PV inverters varies in function of the solar irradiance and temperature.
To accommodate the connection of solar PVPP to the electrical network and collaborate
smoothly, the relevant system operator encounters two challenges: (1) the voltage has to
be kept inside within the dead band regulated by relevant system operator. (2) the solar
PVPP must follow the capability curve given by the relevant system operator that defines
the relation between reactive and active power [12].
There are four methods to regulate the reactive power and voltage: (1) voltage (V) control, (2)
power factor (PF) control, (3) automatic power factor (PF) control and (4) reactive power (Q)
control. Voltage control regulates the voltage based on the droop function that is defined as
the ratio of variation of voltage (ΔV) over nominal voltage (Vn) due to the change of reactive
power (ΔQ) over instantaneous power (actual power (Pac) in case no delta production) as
illustrated in Fig.2.8. The power factor control regulates the reactive power (Q) based on the
value of active power (P) whereas automatic power factor (PF) control regulates the reactive
power with a variable PF depending on the generated active power as illustrated in Fig.2.9.
When the ratio of actual power (Pac) to available power (Pav) reaches X1 then the solar PVPP
starts supplying reactive power (Q) following a linear gradient until it reaches power factor (PF)
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 31
of 1. And the last method is reactive power control that regulates directly the reactive power
(Q) at the PCC. The solar PVPP must be capable of regulating the reactive power and voltage
using any of these controls. The most commonly used functions are combination of voltage
control and reactive power control as well as voltage control and power factor control.
However, in some grid code the reactive power control, power factor control and voltage
control are mutually exclusive which implies that only one of the three functions can be
performed at a time [27]. Fig.2.10 depicts normal operating zones of solar PVPP as functions
of power factor (PF) and reactive power (Q). There are two types of operating zones: (1)
rectangular-shaped zone in which solar PVPP must be capable of providing reactive power
between Q1 and Q2 with no regard to power factor (2) triangle-shaped zone in which solar
PVPP must be capable of providing reactive power between Q1 and Q2 with regard to power
factor in the range of PF1 and PF2. Additionally, in some international grid codes, below
particular active power (P1) solar PVPP is not required to deliver reactive power (Q).
Figure 2. 8 Voltage control with droop function [adapted from [28]]
Page 32 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 2. 9 Automatic power factor control [adapted from [27]]
Figure 2. 10 Normal operating zones as functions of power factor and reactive power
[adapted from [12]]
Fault-Ride-Through (FRT) Capability
Fault-ride-through (FRT) capability is a capability normally possessed by solar PVPP to
remain online in the event of symmetrical and/or asymmetrical fault. FRT capability is
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 33
composed of low-voltage-ride-through (LVRT) capability and high-voltage-ride-through
(HVRT) capability along with reactive current injection (Iq) capability.
Low-voltage-ride-through (LVRT) capability is a capability by which solar PVPP remains
online in undervoltage situation for certain period of time. This capability is illustrated in
Fig.2.11. In case of the normal voltage profile at the PCC (i.e. in zone A) the solar PVPP
must remain online continuously whereas in case of voltage profile is located in zone B the
solar PVPP must remain online for certain period of time and perform reactive current
injection to help stabilizing the network. In addition, the solar PVPP is not required to remain
online in case the voltage profile is located in zone C.
High-voltage-ride-through (HVRT) capability is a capability by which solar PVPP remain
online in overvoltage situation for certain period of time. This capability is required in several
international grid codes. Fig.2.12 depicts this capability. In case the voltage profile at the
PCC is located in zone A then the solar PVPP must stay connected to the network
continuously. In contrast, in case the voltage profile is located in zone B then the solar PVPP
must remain online for determinate periods of time. Additionally, in case the voltage profile
is located in zone C then the solar PVPP is not required to remain online.
Figure 2. 11 LVRT Capability [12]
Page 34 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 2. 12 HVRT capability [12]
Besides LVRT capability and HVRT capability, reactive current injection capability is required
in undervoltage situation in several international grid codes. This requirement defines the
reactive current injection in function of voltage as shown in Fig.2.13. This capability essentially
consists of deadband (i.e. a range without reactive current injection), droop constant (i.e. ratio
of change of reactive current (ΔIq) over nominal current (Iq) to change of voltage (ΔV) over
nominal voltage (Vn), voltage deviation setpoint 1 (X1) where solar PVPP begin injecting 100%
reactive current as well as the voltage deviation setpoint 2 (X2) where the solar PVPP start
absorbing 100% reactive current.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 35
Figure 2. 13 Reactive current injection
Grid Codes of Puerto Rico
2.3.1 Voltage and Frequency Boundaries
According to the latest regulation of Puerto Rico, the range of normal operating frequency
along with minimum duration to remain online of a solar PVPP and the range of normal voltage
are listed in Table 2.2 and Table 2.3, respectively.
Nominal Frequency,
fn (Hz)
Range of Normal
Operating Frequency
(Hz)
Minimum Duration
60
x<56.5 Instantaneous trip
56.5≤x<57.5 10 sec
Page 36 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
57.5≤x≤61.5 Continuous
61.5<x≤62.5 30 sec
x>62.5 Instantaneous trip
Table 2. 2 Range of normal operating frequency
Range of Normal
Operating Voltage (pu)
Minimum Duration
0.85-1.15 Continuous
Table 2. 3 Range of normal operating voltage
2.3.2 Active Power and Frequency Support
Table 2.4 outlines the active power and frequency support requirements for solar PVPP.
Requirements for a 1 MW solar PVPP Response
Frequency response or control. frequency
response or control is detailed below
Yes
Absolute production. absolute production or
power curtailment is detailed below
Yes
Delta production. delta production or power
reserve is detailed below
Yes
Power gradient. power gradient or ramp rate or
is detailed below
Yes
Table 2. 4 Active power and frequency support requirements
Frequency Response
In the latest Puerto Rico´s grid code, there are two cases in regards to frequency response or
control.
(1) For small frequency deviations (i.e. less than 0.3 Hz), the parameters illustrated in
Fig.2.6 are listed in Table 2.5.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 37
Parameter Value
fmin 56.5 Hz
f1 ≥59.694 Hz
f2 59.994 Hz
f3 60.006 Hz
f4 ≤60.306 Hz
fmax 62.5
Upward droop constant 5% as a function of
nominal output
power (Pn)
Downward droop constant 5% as a function of
nominal output
power
Response time for both
droops
<1 s
Actual power NS
Table 2. 5 Parameter in case 1
NS : not stated
(2) For large frequency deviations (i.e. greater than 0.3 Hz), the parameters illustrated
in Fig.2.6 are illustrated in Table 2.6.
Parameter Value
fmin 56.5
f1 <59.694 Hz
f2 59.994 Hz
f3 60.006 Hz
Page 38 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
f4 >60.306 Hz
fmax 62.5
Upward droop constant 5% a function of
nominal output power
Downward droop
constant
5% a function of
nominal output power
Response time for both
droops
<1 s
Settling time for both
droops
NS
Actual power ≥10% of nominal output
power
Table 2. 6 Parameter in case 2
Constraint Functions
The type of constraint functions is listed in Table 2.7.
Type of Constraint Functions Value
Absolute production aw-TSO
Delta production 10% nominal output power ≤ x
≤ 100% nominal output power
Ramp rate
Rate of increase of power Rate of decrease of power Rate of increase of power when an absolute production constraint turns off Rate of decrease of power when an absolute production constraint turns on
10% of nominal output power
per minute with tolerance of
10%
Table 2. 7 Constraint functions
*aw-TSO: agreed with transmission system operator
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 39
2.3.3 Reactive Power and Voltage Support
Table 2.8 summarizes the reactive power and voltage support requirements for a solar PVPP
according to the latest Puerto Rico´s regulation.
Requirements for a 1 MW solar PVPP Response
Voltage control. voltage control is detailed below Yes
Reactive power control. No
Power factor control. No
Automatic power factor control. No
Table 2. 8 Reactive power and voltage support requirements
Voltage Control
Table 2.9 illustrates parameters with regards to voltage control function as depicted in Fig.2.8.
Parameters Value
Deadband 0.999pu≤x≤1.001pu
Upward droop function 0%<x≤10%
Downward droop function 0%<x≤10%
Time response 1s for 95% total reactive power
Upper limit of reactive power
delivery
0.62 of actual active power (Pac)
Lower limit of reactive power
delivery
-0.62 of actual active power (Pac)
Table 2. 9 Parameters in voltage control function
2.3.4 Fault-Ride-Through Requirement
Table 2. 10 lists the requirement of FRT for a 1 MW solar PVPP.
Requirements for a 1 MW solar PVPP Response
Page 40 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
LVRT capability due to symmetrical and
asymmetrical fault
Yes
HVRT capability due to symmetrical and
asymmetrical fault
Yes
Reactive current injection Yes
Table 2. 10 Fault-ride-through requirement
Table 2.11 explains the parameters in LVRT requirement described in Fig.2.11.
Parameters Value
V1 0
V2 0.1 pu
V3 0.85 pu
t1 600 ms
t2 3 s
Table 2. 11 Parameters in LVRT requirement
In addition, Table 2.12 describes the parameters with regards to high-voltage-ride-through
requirement depicted in Fig. 2.12.
Parameters Value
V1 1.4 pu
V2 1.3 pu
V3 1.15 pu
t1 150 ms
t2 1 s
t3 3 s
Table 2. 12 Parameters in HVRT requirement
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 41
During undervoltage fault condition, solar PVPP must operate on reactive current injection
mode as parameters listed in Table 2.13 and depicted in Fig.2.13.
Parameters Value
Droop constant 1%≤x≤5%
Deadband 15%
X1 aw-TSO
X2 NS
Table 2. 13 Parameters in reactive current injection requirement
*aw-TSO: agreed with transmission system operator
NS: not stated
Grid Codes of Germany
The latest regulation of Germany for grid codes for power plants connected to MV level
network is based on that for HV level network. The scope of this regulation is explained in
Table 2.14.
Parameter Value
Grid Voltage (kV) [29] 1-60
Type of Power Generation
[30]
Type 1 – power generation with synchronous generation and its associated storage
Type 2 – power generation with asynchronous generator and its associated storage
Typical Size of Power Generation [31]
500 kW to 100 MW
Table 2. 14 The scope of the latest Germany´s regulation for grid code
In this section the requirements for type 2 is focused since in this master thesis, emphasis is put on a 1 MW solar PVPP.
2.4.1 Voltage and Frequency Boundaries
The range of normal frequency and voltage for solar PVPP connected to MV level network
is described in Table 2. 15 and Table 2. 16, respectively [29].
Nominal Frequency (Hz)
Range of Normal Operating Frequency (Hz)
Minimum Duration
50 x<47.5 Instantaneous trip
47.5≤x<49 30 minutes
Page 42 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
49≤x≤51 Continuous
51<x≤51.5 30 minutes
x>51.5 Instantaneous trip
Table 2. 15 The range of normal operating frequency
Range of Normal Operating Voltage (pu)
Minimum Duration
x<0.85 Instantaneous trip
0.85≤x<0.9 60 seconds
0.9≤x≤1.1 Continuous
1.1<x≤1.15 60 seconds
x>1.15 Instantaneous trip
Table 2. 16 The range of normal operating voltage
Normal operation is defined as the condition where voltage gradient is less than 5% per
minute and frequency gradient is less than 0.5% per minute. In addition, voltage gradients
over 5% is acceptable in the voltage range of 0.9 pu - 1.1 pu.
2.4.2 Active Power and Frequency Support
Table 2. 17 outlines active power and frequency support requirement.
Requirements for a 1 MW Solar PVPP Response
Frequency response or control. frequency
response or control is specified below
Yes
Absolute production. absolute production or
power curtailment is detailed below
Yes
Delta production. delta production or power
reserve is detailed below
Yes
Power gradient. power gradient or ramp rate or
is detailed below
Yes
Table 2. 17 Active power and frequency support requirements
Frequency Response
The relevant parameters in frequency response or control function depicted in Figure 2. 6 is
listed in Table 2. 18.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 43
Parameter Value
fmin 47.5 Hz
f1 48.8 Hz
f2 49.8 Hz
f3 50.2 Hz
f4 50.1 Hz
fmax 51.5 Hz
Upward droop constant 5% as a function
of nominal
output power
(Pn)
Downward droop constant 5% as a function
of actual output
power (Pn)
Response time for both
droops
2 s
Settling time for both
droops
20 s
Actual power NS
Table 2. 18 Parameters in frequency response or control
Constraint Functions
Table 2. 19 describes the types of available constraint function.
Type of Constraint Functions Value
Absolute production aw-TSO
Delta production aw-TSO
Page 44 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Ramp rate
Rate of increase of power Rate of decrease of power Rate of increase of power when an absolute production constraint turns off Rate of decrease of power when an absolute production constraint turns on
19.8% of nominal output power
per minute ≤ x ≤39.6% of
nominal output power per
minute
Table 2. 19 Constraint functions
2.4.3 Reactive Power and Voltage Support
Table 2. 20 summarizes reactive power and voltage support requirement for solar PVPP.
Requirements for a 1 MW solar PVPP Response
Voltage control. voltage control is detailed below Yes
Reactive power control. reactive power control is detailed below Yes
Power factor control. power factor control is detailed below Yes
Automatic power factor control. No
Table 2. 20 Reactive power and voltage support requirement
Voltage Control
Table 2. 21 illustrates parameters with regards to voltage control function as depicted in Figure
2. 8.
Parameters Value
Deadband NA
Upward droop function 0%<x≤8.333%
Downward droop function 0%<x≤8.333%
Ramp rate aw-TSO
Table 2. 21 Parameters in voltage control function
*NA : not applicable
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 45
Reactive Power Control
Solar PVPP must be capable of providing the reactive power from Q1 to Q2 with regard to the
power factor between PF1 to PF2 (i.e. zone 2). In fact, solar PVPP is not required to supply
reactive power below determinate active power (P1). Table 2. 22 establishes the parameters
illustrated in Figure 2. 10.
Parameters Value (pu)
PF1 0.9
PF2 -0.9
Q1 0.48
Q2 -0.48
P1 0.05
Time Response NS
Table 2. 22 Parameters in reactive power control
Power Factor Control
Solar PVPP must be capable of delivering reactive power as a function of active power. As
listed in Table 2. 22, solar PVPP must be capable of operating at power factor between PF1
and PF2 depicted in Figure 2. 10.
2.4.4 Fault-Ride-Through Capability
Table 2. 23 outlines the FRT requirement.
Requirements for a 1 MW Solar PVPP Response
LVRT capability due to symmetrical and
asymmetrical fault
Yes
HVRT capability due to symmetrical and
asymmetrical fault
Yes
Reactive current injection Yes
Page 46 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Table 2. 23 Fault-ride-through requirement
Figure 2. 14 FRT requirement [adapted from [29]]
Figure 2. 14 depicts FRT requirement comprising HVRT for both symmetrical and
asymmetrical fault as well as LVRT for individual symmetrical and asymmetrical fault. The
criteria for fault start are voltage at PCC ≥ 1.1 of nominal voltage (Un) or ≤ 0.9 Un. Furthermore,
the criteria for fault end is 5 s after the fault starts and all line-to-line voltages should be restored
in the range between 0.9 Un and 1.1 Un.
For reactive current injection requirement, it is set out in the latest grid code of Germany.
However, its value is not explicitly specified.
Grid Codes of Denmark
Denmark’s regulations classify power plants based on the voltage at the PCC and nominal
output power (i.e. active power) into 5 types. Table 2. 24 lists the voltage level and nominal
output power for each type of power plants.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 47
Parameters Type A1 Type A2 Type B Type C Type D
Rated power x ≤11 kW 11 kW < x ≤
50kW
50 kW < x ≤
1.5 MW
1.5 MW < x ≤
25 MW
x>25 MW
Voltage level x≤100 kV x≤100 kV x≤100 kV x≤100 kV x>100 kV
Table 2. 24 Voltage level and nominal output power for each type of power plants
Moreover, the Denmark’s regulations are made up of five technical regulation according to the
nature of power plant as follows.
• The first technical regulation applies to all generation plants (excluding battery plants) that
are up to and including 11 kW [32].
• The second technical regulation applies to connection requirement pertaining to solar
PVPP over 11 kW [27].
• The third technical regulation describes connection requirement for thermal power plants
over 11 kW [33].
• The fourth regulation defines the connection requirement for wind power plants above 11
kW [34].
• The fifth regulation details the connection requirement for battery plants [35].
In this section, the second technical regulation that defines that connection requirement for
power plants type B is more focused since this master thesis deals with a 1 MW solar PVPP.
2.5.1 Voltage and Frequency Boundaries
The range of normal operating voltage at the PCC is Un±10% and the nominal frequency is 50
Hz as well as the range of normal operating frequency is from 47.00 Hz to 52.00 Hz in which
the solar PVPP must remain connected to public electricity grid.
The range of normal operating voltage is derived from nominal voltage (Un) as listed in Table
2. 25. The operating voltage should lie between the minimum (Umin) and maximum voltage
(Umax) listed in Table 2. 25.
Voltage Level
Descriptions
Nominal Voltage
Un [kV]
Minimum Voltage
Umin [kV]
Maximum
Voltage
Page 48 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Umax [kV]
High voltage
[HV]
60 54 72.5
50 45 60
Medium voltage
[MV]
33 30 36
30 27 36
20 18 24
15 13.5 13.5
10 9 12
Low voltage
[LV]
0.69 0.62 0.76
0.4 0.36 0.44
Table 2. 25 Nominal voltage, minimum voltage (Umin) and maximum voltage (Umax)
2.5.2 Active Power and Frequency Support
Table 2. 26 outlines the active power and frequency support requirements.
Requirements for a 1 MW Solar PVPP Response
Frequency response or control. frequency
response or control is detailed below
Yes
Absolute production. absolute production or
power curtailment is detailed below
Yes
Delta production. No
Power gradient. power gradient or ramp rate is
detailed below
Yes
Table 2. 26 Active power and frequency support requirements
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 49
Frequency Response
The relevant parameters in frequency response or control function described in Figure 2. 6 is
listed in Table 2. 27.
Parameter Major Islands
fmin 47.0 Hz
f1 NA
f2 NA
f3 50.0-52.0 Hz
(aw-TSO)
50.2 Hz
(standard value)
f4 NA
fmax 52.0 Hz
Upward droop constant NA
Downward droop constant 2-12%
(aw-TSO)
4% as a function
of actual output
power
(standard value)
Response time for
downward droop
2 s
Settling time for downward
droop
15 s
Actual power NA
Table 2. 27 Parameters in frequency response or control
Page 50 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Constraint Functions
Table 2. 28 describes the constraint functions stated in the technical regulation.
Type of Constraint Functions Value
Absolute production aw-TSO
Delta production NA
Ramp rate
Rate of increase of power Rate of decrease of power Rate of increase of power when an absolute production constraint turns off Rate of decrease of power when an absolute production constraint turns on
100 kW/s
Table 2. 28 Constraint functions
The response and settling time for both absolute production and ramp rate constraints are 2
seconds and 10 seconds, respectively.
2.5.3 Reactive Power and Voltage Support
Table 2. 29 lists the reactive power and voltage support requirements. In fact, the control
functions of voltage control, reactive power control and power factor control are mutually
exclusive, meaning only one of the three functions can be activated at a time.
Requirement for a 1 MW solar PVPP Response
Voltage control No
Reactive power control*. reactive power control is detailed below Yes
Power factor control*. power factor control is detailed below Yes
Automatic power factor control*. automatic power factor control is detailed
below
Yes
Table 2. 29 Reactive power and voltage support requirements
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 51
Nb : *reactive power control, power factor control and automatic power factor control must not
be performed in the absence of agreement with transmission system operator
Reactive Power Control
Solar PVPP is responsible of providing the reactive power from Q1 to Q2 with regard to the
power factor between PF1 to PF2 (i.e. zone 2). Table 2. 30 establishes the parameters
illustrated in Figure 2. 10.
Parameters Value (pu)
PF1 0.9
PF2 -0.9
Q1 0.48
Q2 -0.48
P1 NA
Time response (100% of
steady-state response)
10 s
Table 2. 30 Parameters in reactive power control
Power Factor Control
Solar PVPP must be capable of delivering reactive power as a function of active power. As
listed in Table 2. 30, solar PVPP must be capable of operating at power factor between PF1
and PF2 depicted in Figure 2. 10. Additionally, the solar PVPP must reach power factor setpoint
by 10 s (i.e. time response of 10 s).
Automatic Power Factor Control
The activation and deactivation levels for this function are normally 105% and 100% of the
nominal voltage (Un), respectively and they both must be adjustable via setpoints. Table 2. 31
lists the parameters in automatic power factor control function depicted in Figure 2. 9.
Parameter Value
Page 52 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
X1 0.5
Y1 0.9
Table 2. 31 Parameters in automatic power factor control function
2.5.4 Fault-Ride-Through Capability
Table 2. 32 lists the FRT requirement.
Requirement for 1 MW solar PVPP Response
LVRT capability due to symmetrical and
asymmetrical fault
No
HVRT capability due to symmetrical and
asymmetrical fault
No
Reactive current injection No
Table 2. 32 Fault-ride-through requirement
The FRT requirements for solar PVPP type B are not set out in the second technical regulation.
2.6 Grid Codes of European Union
In the latest grid codes of European Union, power plants are essentially classified into four
types on the basis of voltage level at PCC along with their nominal output power listed in Table
2. 33.
• Type A : the voltage level at PCC is below 110 kV and the capacity is below limit stated in Table 2. 33.
• Type B : the voltage level at PCC is below 110 kV and the capacity is located within the range defined in Table 2. 33.
• Type C : the voltage level at PCC is below 110 kV and the capacity falls within the range stated in Table 2. 33.
• Type D : the voltage level at PCC is equal to or above 110 kV or the capacity is stated within the range stated in Table 2. 33.
Synchronous
Area
Capacity Range
of Type A
Capacity Range
of Type B
Capacity Range
of Type C
Capacity Range
of Type D
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 53
Continental
Europe
x<0.8 kW 0.8 kW≤x≤1
MW
1 MW<x≤50 MW 50 MW<x≤75
MW
Great Britain x<0.8 kW 0.8 kW≤x≤1
MW
1 MW<x≤50 MW 50 MW<x≤75
MW
Nordic x<0.8 kW 0.8
kW≤x≤1.5MW
1.5 MW<x≤10 MW 10 MW<x≤30
MW
Ireland and
Northern
Ireland
x<0.8 kW 0.8
kW≤x≤0.1MW
0.1 MW<x≤5 MW 5 MW<x≤10
MW
Baltic x<0.8 kW 0.8
kW≤x≤0.5MW
0.5 MW<x≤10 MW 10 MW<x≤15
MW
Table 2. 33 Capacity range
Synchronous area is defined as an area covered by synchronously interconnected TSOs, for
instance synchronous areas of Continental Europe, Great Britain, Ireland-Northern Ireland and
Nordic along with the power system of Lithuania, Latvia and Estonia which forms Baltic
synchronous area. This is illustrated in Figure 2. 15.
Page 54 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 2. 15 The map of synchronous areas in Europe [36]
2.6.1 Voltage and Frequency Boundaries
In regards to range of normal operating voltage and frequency, the relevant solar PVPP must
be capable of remaining online and operate normally when the voltage decreases to 0.85 pu
and in ranges of normal operating frequency with minimum duration as listed in Table 2. 34.
Synchronous Area Nominal
Frequency (Hz)
Range of Normal
Operating Frequency
Minimum
Duration
European Union
(Continental
Europe)
50 x<47.5 Instantaneous trip
47.5≤x<48.5 Not less than 30
minutes [a]
48.5≤x<49 Not less than
period for
47.5Hz≤x<48.5Hz
Baltic
Ireland and
Northern Ireland
Great Britain
Nordic
Continental
Europe
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 55
49≤x≤51 Unlimited
51<x≤51.5 30 minutes
x>51.5 Instantaneous trip
Table 2. 34 Range of normal operating frequency
[a] : to be agreed with relevant system operator
2.6.2 Active Power and Frequency Support
Table 2. 35 outlines active power and frequency support requirement.
Requirements for a 1 MW solar PVPP Response
Frequency response or control.
frequency control is detailed below
Yes
Absolute production. No
Delta production. No
Power gradient.
power gradient or ramp rate is detailed below
Yes
Table 2. 35 Active power and frequency support requirements
Frequency Response or Control
In the latest grid code of European Union, the parameters in frequency response or control
function described in Figure 2. 6 is listed in Table 2. 36.
Parameter Value
fmin 47.5 Hz
f1 NS
f2 aw-TSO
Page 56 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
f3 50.2-50.5 Hz
(aw-TSO)
f4 NA
fmax 51.5 Hz
Upward droop constant 2% as a function of
nominal output power
(Pn)
(in case f2 < 49 Hz)
10% as a function of
nominal output power
(Pn)
(in case 49 Hz < f2 <
49.5 Hz
Downward droop constant 2-12% as a function of
actual active power
(Pac) or nominal output
power (Pn)
(aw-TSO)
Response time for
downward droop
≤ 2 s
Settling time for downward
droop
NS
Actual power NS
Table 2. 36 Parameters in frequency response or control
Constraint Functions
Table 2. 37 describes the constraint functions.
Type of Constraint Functions Value
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 57
Absolute production NA
Delta production NS
Ramp rate
Rate of increase of power
NS
Table 2. 37 Constraint functions
2.6.3 Reactive Power and Voltage Support
Table 2.38 lists the reactive power and voltage support requirement.
Requirement for a 1 MW solar PVPP Response
Voltage control. No
Reactive power control. reactive power control is detailed below Yes
Power factor control. No
Automatic power factor control. No
Table 2. 38 Reactive power and voltage support requirement
Reactive Power Control
In the latest grid code of EU, reactive power control requirement is set out. However, the
provision range of reactive power and the time response are not specified.
2.6.4 Fault-Ride-Through Capability
Table 2. 39 outlines the FRT requirement.
Requirement for a 1 MW solar PVPP Response
LVRT capability due to symmetrical and
asymmetrical fault
Yes
HVRT capability due to symmetrical and
asymmetrical fault
No
Reactive current injection Yes
Table 2. 39 Fault-ride-through requirement
Page 58 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
The LVRT requirement due to symmetrical fault is depicted in Fig.2.16 below.
Figure 2. 16 LVRT requirement due to symmetrical fault
Table 2. 40 lists parameters in Fig.2.16.
Voltage Parameters (pu) Time Parameters (seconds)
V1 0.05-0.15 t1 0.14-0.25
V2 V2-0.15 t2 t1
V3 V2 t3 t2
V4 0.85 t4 1.5-3.0
Table 2. 40 Parameters in LVRT
In addition, the LVRT requirement due to asymmetrical fault must be specified by relevant TSO
on case-by-case basis. The reactive current injection requirement is set out in the latest grid
code of EU. However, its details are not specified.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 59
2.7 Summary
In the present section, the summary of grid codes of Puerto Rico, Germany, Denmark and
European Union pertaining to 1 MW solar PVPP connected to medium voltage (MV) level
network is given from different perspectives as follows.
• Classification based on type and voltage level at PCC is listed in Table 2. 41
Country Type Voltage
Level
Lower
Limit (kV)
Upper
Limit (kV)
Puerto Rico NS NS NS NS
Germany 2 Medium
Voltage
1 60
Denmark B Medium
Voltage
- 33
European Union B for
Continental
Europe,
B for Great
Britain,
B for Nordic, C
for Ireland and
Northern
Ireland &
C for Baltic
NS - 110
Table 2. 41 Classification based on type and voltage level at PCC
• Table 2. 42 describes normal operating frequency based on each grid code
Grid code Frequency (Hz) Limits (Hz) Minimum Duration
Puerto Rico 60
x<56.5 Instantaneous trip
56.5≤x<57.5 10 sec
57.5≤x≤61.5 Continuous
Page 60 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
61.5<x≤62.5 30 sec
x>62.5 Instantaneous trip
Germany 50
x<47.5 Instantaneous trip
47.5≤x<49 30 minutes
49≤x≤50 Continuous
50<x≤51 30 minutes
x>51.5 Instantaneous trip
Denmark 50
x<47 Instantaneous trip
47≤x≤52 Continuous
x>52 Instantaneous trip
European Union 50
• Continental Europe
x<47.5 Instantaneous trip
47.5≤x<48.5 Not less than 30
minutes [1]
48.5≤x<49 Not less than period
for
47.5Hz≤x<48.5Hz
49≤x≤51 Unlimited
51<x≤51.5 30 minutes
x>51.5 Instantaneous trip
[1] Specified by relevant system operator
Table 2. 42 Normal operating frequency
• Table 2. 43 illustrates normal operating voltage in each grid code
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 61
Grid code Range of Voltage
(pu)
Minimum Duration
Puerto Rico
x<0.85 Instantaneous trip
0.85<x≤1.15 Continuous
x>1.15 Instantaneous trip
Germany
x<0.85 Instantaneous trip
0.85≤x<0.9 30 minutes
0.9≤x≤1.1 Continuous
1.1<x≤1.15 30 minutes
x>1.15 Instantaneous trip
Denmark
x<0.9 Instantaneous trip
0.9≤x≤1.1 Continuous
x>1.1 Instantaneous trip
European Union
(Continental Europe)
x<0.85 Instantaneous trip
x≥0.85
Continuous
Table 2. 43 Normal operating voltage
• Table 2. 44 summarizes the active power and frequency support requirement in each grid code
Requirements for 1 MW
Solar PVPP
Puerto Rico’s
regulation
Germany’s
regulation
Denmark’s
regulation
EU’s
regulation
Frequency response or
control
Yes Yes Yes Yes
Absolute production Yes Yes Yes No
Delta production Yes Yes No No
Page 62 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Power gradient Yes Yes Yes Yes
Table 2. 44 Active power and frequency support requirement
• Reactive power and voltage support requirement are outlined in Table 2. 45.
Requirement for 1 MW solar
PVPP
Puerto Rico’s
regulation
Germany’s
regulation
Denmark’s
regulation
EU`s
regulation
Voltage control Yes Yes No No
Reactive power control No Yes Yes Yes
Power factor control No Yes Yes No
Automatic power factor
control
No No Yes No
Table 2. 45 Reactive power and voltage support requirement
• FRT requirement is listed in Table 2. 46.
Requirement for 1 MW
solar PVPP
Puerto Rico’s
regulation
Germany’s
regulation
Denmark’s
regulation
EU´s
regulation
Low-voltage-ride-through
capability due to symmetrical
and asymmetrical fault
Yes Yes No Yes
High-voltage-ride-through
capability due to symmetrical
and asymmetrical fault
Yes Yes No No
Reactive current injection Yes Yes No Yes
Table 2. 46 FRT requirement
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 63
Grid Code Proposal for Solar PVPP in Indonesia
In chapter 3 the growing share of renewable energy in electricity generation and installed
power capacity in Puerto Rico and Europe is discussed. As depicted in Figure 3. 1 Indonesia´s
installed power capacityFigure 3. 1, an opposite situation happened in Indonesia where in
2009 Indonesia´s installed power capacity was made up of 4.9 GW controllable renewable
energy power generation (i.e. 16%) and 26.5 GW fossil fuel power generation [37]. Then in
2015 the share of controllable renewable energy power generation in Indonesia´s installed
power capacity increased slightly in size to 7 GW (i.e. 14%) and fossil fuel power generation
held 43 GW of Indonesia´s installed power capacity [38].
Figure 3. 1 Indonesia´s installed power capacity
in 2009 and 2015 [adapted from [37] and [38]]
However, according to Indonesia´s energy policy by 2025 the energy demand is planned to
Page 64 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
be met by 332 TWh fossil fuel energy, 95.3 TWh controllable renewable energy (i.e. 21%) and
4.3 TWh solar (1%) and 4.3 TWh wind (1%) as illustrated in Figure 3. 2 [39].
Figure 3. 2 Indonesia´s energy mix by 2025 [39]
Recently a number of solar PVPPs came into operation in Indonesia amounts to 17.02 MW
[40] and on average each solar PVPP has capacity of 300 kW [41].
Since Indonesia´s government begun to construct a large number of solar PVPPs to follow
their energy policy and by nature solar PVPP entails intermittency, it is necessary to review
the current regulation and existing grid code of Indonesia to ensure the integration of large
amount of solar power into the grid smoothly.
3.1 Existing Electricity Transmission and Distribution System
Generally electrical power system is made up of
1. Power station
This is the place where electrical power is generated in which turbine (i.e. prime mover)
and generator in case of conventional power plant and PV array, PV inverter and LV-
MV transformer in case of solar PVPP can be found. The generated electricity has a
medium voltage level in the range of 6 kV to 24 kV with frequency of 50 Hz.
2. Electricity transmission system
Is a system whose function is to transmit electrical power from power station to electricity
distribution system.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 65
Figure 3. 3 Illustrative single line diagram of generation, transmission and
distribution system in Indonesia [Adapted from [42]]
Figure 3. 3 illustrates the single line diagram of power generation, transmission and distribution
system. It starts with two power stations (G1 and G2) where the electricity is generated. Then
the electricity is forwarded to transmission system comprising primary and secondary
transmission substations, tie-line and transmission customer. The transmission system serves
to adjust and regulate the voltage in transmitted electricity. According to International
Electrotechnical Comission (IEC), extra high voltage is characterized by any nominal voltage
above 245 kV and high voltage is any nominal voltage in the range of 35 kV to 230 kV. Besides,
medium voltage is any nominal voltage in the range of 1 kV to 35 kV as well as low voltage is
any nominal voltage below 1 kV [43]. Indonesia’s regulation defines the voltage level in the
same manner with IEC [44]. In electric power system, long distance between power station
and load causes instability which creates the need for utilization of ancillary services such as
flexible alternating current transmission system (FACTS) or capacitor banks [45]. In electricity
transmission system, transmission substations serve to connect multiple transmission lines.
The simplest case is where all transmission lines operated at the same voltage. In such cases,
substation houses high-voltage switches that enables lines to be connected or isolated for fault
clearance or maintenance. A small substation may be a little more than a bus and several
circuit breakers. A normal size substation may houses transformer, voltage control or power
factor correction devices such as FACTS as well as phase shifting transformer to regulate
power flow between two adjacent power systems and some circuit breakers.
Page 66 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Indonesia’s electricity transmission system is not interconnected across the nation [46] [47]. In
fact, Indonesia is currently split into several electrically synchronous areas as listed in Table 3.
1.
No. Electrically Synchronous Area
1. Sumatra island
2. Java island, Madura Island and Bali island
Table 3. 1 Electrically Synchronous Area
While the other major islands such as Sulawesi island, Kalimantan island, Papua island
don´t have individual electricity interconnection system across the island. In addition,
smaller islands have their own transmission electricity and disconnected from each other
[46].
3. Electricity distribution system
The present system serves to deliver electricity from electricity transmission system to end-
user. In addition to changing the voltage, the task of distribution substation is to isolate faults
in either the transmission or distribution system. At primary distribution substation, the
voltage is stepped down from high voltage level to medium level. Then, the electrical power
is forwarded from primary distribution substation to secondary distribution system via
primary distribution line at medium voltage. The electricity reaches small industrial and
commercial customers in the form of three phase at low voltage via secondary distribution
line. In case of residential customer, the electricity reaches them in the form of single phase
via secondary distribution line at low voltage. One of main elements in electricity
transmission and distribution system is power line. Two most widely used types of
transmission and distribution line in Indonesia: (1) Overhead lines which has upsides such
as low initial and repairment cost. On the other hand, it has downsides such as prone to
storm and wind as well as has low aesthetics. (2) Underground lines which offer advantages
like not affected by storm and wind and high aesthetics. On the other hand, it has
disadvantages such as high initial and repairment cost and vulnerable to storm surge and
flooding from corrosive saltwater, rainfall or melting ice and snow [42].
3.2 Current Grid Codes of Indonesia
The regulation of Indonesia for renewable energy power plant connected to electricity
distribution system is based on IEEE technical guidance. One of them is IEEE 1547 [48].
Moreover, the summary of Indonesia´s grid code is based on regulations stated in Table 3.
2.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 67
Organization Title Version
PLN
(TSO & DSO
in Indonesia)
Pedoman Penyambungan Pembangkit
Listrik Energi Terbarukan ke Sistem
Distribusi PLN
(Guideline for Renewable Energy Power
Plant Connected to Electricity Distribution
System of PLN)
July, 2014
PLN
(TSO & DSO
in Indonesia)
Persyaratan Umum dan Metode Uji Inverter
Untuk Pembangkit Listrik Tenaga Surya
(PLTS)
(General Requirement and Compliance Test
Methodology for PV inverter)
November, 2012
Table 3. 2 Regulation and grid code under study
The scope of above-mentioned regulation is explained in Table 3. 3.
Parameter Value
Grid Voltage (kV) Up to 20 kV
Collection Grid Topology of Network Radial
Size of Power Generation Up to 10 MW
Table 3. 3 The scope of regulation for grid code
3.2.1 Voltage and Frequency Boundaries
The range of normal operating frequency and voltage along with minimum duration to remain
online are listed in Table 3. 4 and Table 3. 5, respectively.
Nominal Frequency,
fn (Hz)
Range of Normal
Operating Frequency
(Hz)
Minimum Duration
50
x<49 0.2 s
49≤x≤51 Continuous
x >51 0.2 s
Page 68 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Table 3. 4 Range of normal operating frequency
Range of Normal
Operating Voltage (pu)
Minimum Duration
x<0.5 0.1 s
0.5≤x<0.85 2 s
0.85-1.10 Continuous
1.1<x≤1.35 2 s
x≥1.35 0.1 s
Table 3. 5 Range of normal operating voltage
3.2.2 Active Power and Frequency Support
Table 3. 6 outlines the active power and frequency support requirements. It can be deduced
that active power and frequency support requirement is not stated in Indonesia’s regulation.
Requirements for a 1 MW solar PVPP Response
Frequency response or control. No
Absolute production. absolute production or
power curtailment is not stated
No
Delta production. delta production or power
reserve is not laid down
No
Power gradient. power gradient or ramp rate
or is not stated
No
Table 3. 6 Active power and frequency requirement
3.2.3 Reactive Power and Voltage Support
Table 3. 7 outlines the reactive power and voltage support requirements.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 69
Requirements for a 1 MW solar PVPP Response
Voltage control. No
Reactive power control. No
Power factor control. power factor control is detailed
below
Yes
Automatic power factor control. No
Table 3. 7 Reactive power and voltage support requirements
Power Factor Control
Solar PVPP must be capable of providing the reactive power from Q1 to Q2 with regard to the
power factor between PF1 to PF2 (i.e. zone 2). Table 3. 8 establishes the parameters
illustrated in Figure 2. 10.
Parameters Value (pu)
PF1 0.85
PF2 -0.9
Q1 0.62
Q2 -0.48
P1 NA
Table 3. 8 Parameters in reactive power control
3.2.4 Fault-Ride-Through Capability
Table 3. 9 lists fault-ride-through requirement. It is deduced that fault-ride-through requirement
is not stated in Indonesia’s regulation.
Requirements for a 1 MW Solar PVPP Response
Low voltage fault-ride-through capability No
Page 70 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
due to symmetrical and asymmetrical fault
High voltage fault-ride-through capability
due to symmetrical and asymmetrical fault
No
Reactive current injection No
Table 3. 9 Fault-ride-through requirement
3.3 Grid Code Proposal
There are there approaches for proposing grid code design:
1. Geographic approach Table 3. 10 summarizes the geographic condition of Indonesia based on relevant
parameters.
Parameter Response
Type of Nation Archipelago
Number of Major Islands
Five (5) Sumatera island (land area of 480,793
km2) Java island (land area of 129,438 km2) Kalimantan island (land area of 544,150
km2) Sulawesi island (land area of 188,522
km2) Papua island (land area of 418,707
km2)
Number of Small Islands 17,504 (average land area per island of 5,000 km2)
Number of Land Borders
Three (3) With Malaysia in Kalimantan island With Timor Leste in Nusa Tenggara
island With Papua New Guinea in Papua
island
Table 3. 10 The geographic condition of Indonesia [49]
Furthermore, Table 3. 11 and Table 3. 12 summarize the geographic condition of Puerto Rico and Denmark based on relevant parameters, respectively.
Parameter Response
Type of Nation Archipelago
Number of Major Islands One (1) with land area of 8,868 km2
Number of Small Islands Three (3) with average land area per island of 30 km2
Number of Land Borders None
Table 3. 11 The geographic condition of Puerto Rico [50]
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 71
Parameter Response
Type of Nation Archipelago
Number of Major Islands One (1) with land area of 42,916 km2
Number of Small Islands Four hundred (400)
Number of Land Borders One (1) with Germany in the south
Table 3. 12 The geographic condition of Denmark [51]
In addition, Table 3. 13 and Table 3. 14 summarize the geographic condition of Germany and European Union based on relevant parameters, respectively.
Parameter Response
Type of Nation Non-archipelago
Number of Major Islands One (1) (land area of 357,104 km2)
Number of Small Islands Ten (10)
Number of Land Borders
Ten (10) countries with the Netherlands,
Belgium, Luxemburg, France, Switzerland,
Liechteinsten, Austria, Czechia, Poland and
Denmark.
Table 3. 13 The geographic condition of Germany [52]
Parameter Response
Type of Nation Non-archipelago
Number of Major Islands One (1) (land area of 4,369,364 km2)
Number of Small Islands Hundreds
Number of Land Borders Five (5) countries that are Russia, Belarus,
Ukraine, Moldova and Turkey
Table 3. 14 The geographic condition of European Union [53]
Based on description above, it is noted that Puerto Rico and Denmark have similar geographical condition with Indonesia´s geographical condition.
2. Electricity generation mix approach
Table 3. 15 summarizes the fraction of solar power in electricity generation described in
chapter 2. It is expected that Indonesia´s landscape of electricity generation by 2025 will be
similar to Puerto Rico´s electricity generation in 2017 and Denmark´s electricity generation in
2016.
Nation Percentage of Solar Power in Electricity Generation
Indonesia 1% based on Energy Policy by 2025
Puerto Rico 1% in 2017
Denmark 1% in 2016
Germany 3% in 2017
Page 72 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
European Union 3% in 2016
Table 3. 15 Solar power percentage in electricity generation
Electricity interconnection system approach Table 3. 16 summarizes the status of Indonesia´s electricity interconnection system.
Parameter Response
Domestic interconnection One (1) interconnection that links Java
island, Madura island and Bali island
International interconnection None
Table 3. 16 Status of Indonesia´s electricity interconnection system [46] [47]
Table 3. 17 and Table 3. 18 list the status of Puerto Rico and Denmark´s electricity
interconnection system.
Parameter Response
Domestic interconnection Interconnection across the nation
International interconnection None
Table 3. 17 Status of Puerto Rico´s electricity interconnection system [54]
Parameter Response
Domestic interconnection Interconnection across the nation
International interconnection Three (3) interconnections that links the
nation to Norway, Sweden and Germany
Table 3. 18 Status of Denmark´s electricity interconnection system [55] [56]
And Table Table 3. 19 and Table 3. 20 summarizes the status of Germany’s and EU’s
electricity interconnection system.
Parameter Response
Domestic interconnection Interconnection across the nation
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 73
International interconnection
Nine (9) interconnections that link the
nation to Poland, Czechia, Austria,
Switzerland, Luxemburg, Belgium, the
Netherland, Denmark and Sweden
Table 3. 19 Status of Germany´s electricity interconnection system [56]
Parameter Response
Domestic interconnection Interconnection across the region
International interconnection
Five (5) interconnections that connects
the region to Russia, Belarussia,
Ukraine, Turkey and Morocco
Table 3. 20 Status of EU´s electricity interconnection system [56]
Considering above approaches, international grid codes under study that suits the most
current condition of Indonesia´s electricity system during the transition period to renewable
energy are grid codes of Puerto Rico and Denmark. Moreover, both sets of grid codes are
aligned with Indonesia´s energy policy to attain 1% solar power in electricity generation by
2025. Accordingly, the grid code proposal for solar PVPP in Indonesia especially in major and
small islands will be based on grid codes of Denmark and Puerto Rico. Note that Denmark
and Puerto Rico have an average closest individual area of the higher and smaller islands in
Indonesia and similar electricity generation mix to the expected one of Indonesia in 2025.
3.3.1 Voltage and Frequency Boundaries
Table 3. 21 and Table 3. 22 summarize the range of normal operating frequency for major
islands and small islands, respectively.
Nominal Frequency (Hz)
Range of Normal Operating Frequency (Hz)
Minimum Duration
50
x<47 Instantaneous trip
47≤x≤52 Continuous
x>52 Instantaneous trip
Table 3. 21 Normal operating frequency for major islands
Nominal Frequency (Hz)
Range of Normal Operating Frequency (Hz)
Minimum Duration
50 x<47.1 Instantaneous trip
47.1≤x<47.9 10 sec
Page 74 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
47.9≤x≤51.3 Continuous
51.3<x≤52.1 30 sec
x>52.1 Instantaneous trip
Table 3. 22 Normal operating frequency for minor islands
Table 3. 23 lists the normal operating voltage for major island and small islands.
Range of Normal Operating Voltage (pu)
Minimum Duration
Major Islands Small Islands
0.90-1.10 0.85-1.15 Continuous
Table 3. 23 Normal operating voltatge for small islands
3.3.2 Active Power and Frequency Support
Table 3. 24 summarizes the active power and frequency support for solar PVPP in major
islands and smalls islands.
Requirements for a 1 MW Solar PVPP Major islands Small islands
Frequency response or control. frequency
response or control is detailed below
Yes Yes
Constraint functions. absolute production or
power curtailment is detailed below
Yes Yes
Constraint functions. delta production or power
reserve is detailed below
No Yes
Constraint functions. power gradient or ramp
rate is detailed below
Yes Yes
Table 3. 24 Active power and frequency support requirements
Frequency Response
Table 3. 25 lists the parameters for frequency response or control depicted in Figure 2. 6 for
solar PVPP in major islands, small islands with small frequency deviation (i.e. less than 0.25
Hz) and large frequency deviation (i.e. larger than 0.25 Hz).
Parameter Major Islands Small Islands Small Islands
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 75
(small frequency
deviation)
(large frequency
deviation)
fmin 47.0 Hz 47.1 Hz 47.1 Hz
f1 NA ≥49.745 Hz <49.745 Hz
f2 NA 49.995 Hz 49.995 Hz
f3 50.0-52.0 Hz
(aw-TSO)
50.2 Hz
(standard value)
50.005 Hz 50.005 Hz
f4 NA ≤50.255 Hz >50.255 Hz
fmax 52.0 Hz 52.1 52.1
Upward droop constant NA 5% as a function of
nominal output
power (Pn)
5% as a function of
nominal output
power (Pn)
Downward droop
constant
2-12%
(aw-TSO)
4% as a function of
actual output
power (Pac)
(standard value)
5% as a function of
nominal output
power (Pn)
5% as a function of
nominal output
power (Pn)
Response time for both
droops
2 s (only downward
droop is
applicable)
<1 s <1 s
Settling time for both
droops
20 s (only
downward droop is
applicable)
NS NS
Page 76 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Actual power NA NS ≥10% of nominal
output power
Table 3. 25 Parameters in frequency response or control for major islands and small islands
Constraint Functions
Table 3. 26 describes the types of constraint functions applied to solar PVPP in major islands
and small islands.
Type of Constraint Functions Major Islands Small Islands
Absolute production aw-TSO aw-TSO
Delta production NA 10% nominal output
power ≤ x ≤ 100%
nominal output power
Ramp rate
• Rate of increase of power
• Rate of decrease of power
• Rate of increase of power when an absolute production constraint turns off
• Rate of decrease of power when an absolute production constraint turns on
100 kW/s 10% of nominal output
power per minute with
tolerance of 10%
Table 3. 26 Types of constraint functions
*aw-TSO: agreed with TSO
3.3.3 Reactive Power and Voltage Support
Table 3. 27 lists the reactive power and voltage support for solar PVPP in major islands and
small islands, respectively. For the major islands, the control functions are exclusive
meaning only one of three functions can be activated at a time.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 77
Requirement for a 1 MW solar PVPP Major Islands Small Islands
Voltage control. voltage control is detailed below No Yes
Reactive power control*. reactive power control is
detailed below
Yes Yes
Power factor control*. power factor control is
detailed below
Yes Yes
Table 3. 27 Reactive power and voltage support for solar PVPP in major islands and small
islands
Nb: * for solar PVPP in major islands, reactive power control, power factor control and
automatic power factor control must not be performed in the absence of agreement with
transmission system operator
Reactive power and power factor control requirements are thought to be also needed for solar
PVPP in small islands to ensure security, stability and reliability of the electrical grid as
electrical grid in small islands are naturally less robust than that in major islands.
Voltage Control
Table 3. 28 illustrates parameters with regards to voltage control function for small islands as
depicted in Figure 2. 8.
Parameters Value
Deadband 0.999pu≤x≤1.001pu
Upward droop function 0%<x≤10%
Downward droop function 0%<x≤10%
Time response 1s for 95% total reactive power
Upper limit of reactive power
delivery
0.62 of actual active power (Pac)
Lower limit of reactive power
delivery
-0.62 of actual active power (Pac)
Table 3. 28 Parameters in voltage control function
Page 78 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Reactive Power Control
Table 3. 29 lists the parameters in reactive power control depicted in Figure 2. 10 for solar
PVPP in major islands and small islands.
Parameters Value
Type of zone 2
PF1 0.9
PF2 -0.9
Q1 0.48
Q2 -0.48
P1 NA
Time response
(100% of steady-
state response)
10 s
Table 3. 29 Parameters in reactive power control
Steady-state mode turns on under the condition where voltage droop is not taking action
whereas dynamic mode turns on under the condition where voltage droop is being applied.
Power Factor Control
As illustrated in Table 3. 29, solar PVPP in both major and small islands must be capable of
operating at PF between 0.9 and -0.9. In addition, the solar PVPP must reach power factor
setpoint by 10 s (i.e. time response of 10 s).
3.3.4 Fault-Ride-Through Capability
Table 3. 30 lists the fault-ride-through requirement for solar PVPP in major islands and small
islands.
Requirement for 1 MW solar PVPP Major
Islands
Small
Islands
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 79
Low-voltage-ride-through capability due
to symmetrical and asymmetrical fault
No Yes
High-voltage-ride-through capability due
to symmetrical and asymmetrical fault
No Yes
Reactive current injection No Yes
Table 3. 30 Fault-ride-through requirement
Table 3. 31 explains the parameters in low-voltage-ride-through (LVRT) requirement described
in Fig.2.11 for solar PVPP in small islands.
Parameters Value
V1 0
V2 0.1 pu
V3 0.85 pu
t1 600 ms
t2 3 s
Table 3. 31 Parameters in LVRT requirement
Furthermore, Table 3. 32 describes the parameters with regards to high-voltage-ride-through
(HVRT) requirement depicted in Fig. 2.12 for small islands.
Parameters Value
V1 1.4 pu
V2 1.3 pu
V3 1.15 pu
t1 150 ms
t2 1 s
Page 80 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
t3 3 s
Table 3. 32 Parameters in HVRT requirement
During undervoltage fault condition, solar PVPP in small islands must operate on reactive
current injection mode depicted in Figure 2. 13 with parameters listed in Table 3. 33.
Parameters Value
Droop constant 1%≤x≤5%
Deadband 15%
X1 aw-TSO
X2 NS
Table 3. 33 Parameters in reactive current injection requirement
*aw-TSO: agreed with transmission system operator
NS: not stated
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 81
Introduction and Control of Solar Photovoltaics
Power Plant
Introduction
Solar photovoltaics power plant is generally split into three sizes which are small scale, large
scale and very large scale. According to International Energy Agency, the power rating of small
scale photovoltaics power plant (PVPP) ranges from 25 kW to 1 MW, large scale photovoltaics
power plant (LS-PVPP) from 1 MW to 100 MW and very large scale photovoltaics power plant
(VLS-PVPP) from 100 MW to GW [57]. Electrical components are the basis of solar PVPP.
They are basically assigned to [58]: (1) to transform solar energy into electricity. (2) to connect
the PVPP to electrical grid in grid-connected PVPP application. (3) to ensure appropriate
performance.
The basic electrical components basically deployed in solar PVPP are: PV panels, PV inverters
and transformers. PV panel is a block where the sunlight arrives on. A PV string is a set of PV
panels that are electrically connected in series whereas a PV array is a set of PV strings that
are electrically connected in parallel. The objective of PV string and PV array structure is to
generate desired current and voltage that a single PV panel might not.
PV inverter is an electrical component whose function is to transform the dc current to ac
current. Basically, there are four (4) basic inverter topologies in solar PVPP as shown in Figure
4. 1. Inverter topology number one is called central inverter in which the whole set of PV arrays
is linked to a single PV inverter. Inverter topology number two is called string inverter where
each PV string is connected to a single PV inverter. Inverter topology number three is called
multistring topology in which each PV string is linked to a single dc-dc converter then several
dc-dc converters are connected to a single PV inverter (dc-ac inverter). And the last inverter
topology is called module integrated inverter in which each PV panel is connected to a single
PV inverter. As for central topology inverter, since a lot of PV strings are connected in parallel
it will create high dc voltage variation. However, due to its robustness and low number of
inverters needed in central inverter topology, it makes central inverter topology most widely
used in solar PVPP. Therefore, most solar PVPPs are based on central inverter topology [58].
Page 82 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
1) central inverter 2. string inverter 3. multistring inverter 4. module integrated
Figure 4. 1 PV inverter topologies [adapted from [58]].
Solar PVPP is also classified based on the internal collection grid and how the PV generator
is connected to electrical grid. A PV generator is referred to a set of PV arrays and PV
inverters along with the transformers. In radial collection topology, several PV generators
connected to one feeder as shown in Figure 4. 2. This topology is most used in LS-PVPPs
since it is the cheapest and simplest. However, its disadvantage is low reliability. In case a
PV inverter fails, the total power production will not be affected significantly [58].
In order to improve the reliability of LS-PVPPs in general, ring collection topology is used.
The connection is built on radial collection topology but it adds another feeder that connects
the other side of PV generators (Figure 4. 3). In case one of the PV generators is lost, then
the PV generators connected to the other side of the feeder can still give power to the LS-
PVPP. The downside is the cost and complexity of the installation.
In star collection topology, each PV generator is connected to the main collector. Normally, the
collector is placed in the middle of the LS-PVPP to have the same proximities with all PV
generators that result in the same losses between them (Figure 4. 4). The star collection
topology has the highest reliability among the grid collection topologies. Its downside is one
feeder for each generator results in high total cost.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 83
Figure 4. 2 Radial collection grid topology [58]
Figure 4. 3 Ring collection grid topology [58]
Page 84 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 4. 4 Star collection grid topology [58]
To understand more about function of each electrical component and modelling approach in
solar PVPP, following sections are devoted to describe basic electrical components one by
one in solar PVPP.
PV Panels
PV panel is composed of solar cells. The function of solar cells is to transform solar energy
into electricity [59]. A set of solar cells are connected in series and then enclosed in a special
frame to build the PV panel [60].
There are various materials of solar cells that have different overall efficiencies of the PV
panels. The elementary type, crystalline (c – Si) and multicrystalline (m – Si) silicon, offers
efficiency of approximately 20 % [61]. Other type, thin film solar cells constituting
amorphous silicon (a-Si) offer efficiency approximately from 6.9% to 9% [61] [62]. Thin film
solar cells constituting other material like copper indium diselenide (CuInSe2 – CIS) and
Cadmium telluride (Cd-Te) presents efficiency approximately 15% [59] and 12% [61]
respectively.
The power generation by solar PVPP starts with the incidence of light on the solar cell. It results
in charge carriers that originates an electric current if the cell is short-circuited [63] Adequate
energy of the incident photon produces the charges that lead to the detachment of the covalent
electrons of the semiconductor - this phenomenon depends on the semiconductor material
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 85
and on the wavelength of the incident light.
The general model of solar cell circuit is illustrated in Figure 4. 5. This circuit is made up of the
photovoltaic current (Ipv), a diode, a series resistance (Rs) and a parallel resistance (Rp).
Figure 4. 5 General model of solar cell circuit [adapted from [[64]]
The generated current (I) can be obtained by
𝐼 = 𝐼𝑝𝑣 − 𝐼𝑜 [𝑒𝑥𝑝 (𝑉+𝑅𝑠𝐼
𝑉𝑡𝑎) − 1] −
𝑉+𝑅𝑠𝐼
𝑅𝑝 (4.1)
Where Ipv and I0 represents the photovoltaic (PV) and saturation currents, respectively of the
array and V is the working voltage, Vt = NsskT/q is the thermal voltage of the array and Nss is 1
in case of solar cell and Nss is number of series-connected cells in case of solar panel, T is the
working voltage, q (= 1.6 ×10−19C) represents the electron charge, k (= 1.38 ×10−23J/K) is a
Boltzmann’s constant, α is ideality diode factor.
The solar radiation and temperature affects linearly the light-generated current of the PV cell
as expressed by Eq.4.2. [65]-[68]
𝐼𝑝𝑣 = (𝐼𝑝𝑣,𝑛 + 𝐾𝐼∆𝑇)𝐺
𝐺𝑛 (4.2)
Notice that Ipv,n (in amperes) is the light-generated current under normal condition (normally
25◦C and 1000 W/m2), KI is short circuit temperature coefficient, ΔT =T − Tn (T and Tn being
the working and nominal temperatures [i.e. 25◦C], respectively), G (watts per square meters)
is the irradiance on the device surface, and Gn is the nominal irradiance [i.e. 1000 W/m2] [69].
The saturation currents with the influence of temperature is expressed as follows
𝐼𝑜 =𝐼𝑠𝑐,𝑛+𝐾𝐼Δ𝑇
𝑒𝑥𝑝((𝑉𝑜𝑐,𝑛+𝐾𝑣Δ𝑇)/𝛼𝑉𝑡)−1 (4.3)
Where KI and Kv represent short circuit current-temperature and open circuit voltage-
Page 86 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
temperature coefficient.
The PV cell efficiency is affected significantly by variation in series resistance (RS) but not by
variation in parallel resistance (Rp). The PV cells are generally connected in series
configuration to build a PV module with purpose of attaining desired working voltage in most
commercial PV products. Then PV modules are configured in parallel structure to form PV
string. Finally, the combination of PV strings and series-connected PV modules is called PV
array that results in the generation of desired output power. A general equivalent circuit for all
PV cells, module and array is illustrated in Figure 4. 6 [64].
Figure 4. 6 General equivalent circuits of PV [64]
Note that for a PV cell, Nss = Ns = Np = 1 and for a PV module Nss is number of cells per
module, Ns = Np = 1 and. For a PV array, Nss is number of cells per module, Ns represents
the number of series-connected PV module and Np represents the number of parallel
connections (i.e. PV string) of PV module. The mathematical formula of general model can be
expressed as follows.
𝐼 = 𝑁𝑝𝐼𝑝𝑣 − 𝑁𝑝𝐼𝑜[𝑒𝑥𝑝(𝑞(𝑉 𝑁𝑆⁄ + 𝐼𝑅𝑆 𝑁𝑝⁄ )/𝑁𝑠𝑠𝑘𝑇𝑎) − 1] (4.4)
PV Inverters
PV inverters are electronic devices that enable the conversion from dc to ac power and are
employed in different solar PVPP applications. Essentially a PV array produces dc power, then
the PV array is connected to a PV inverter to produce ac power [60]. PV inverter also has the
other function of connecting the PV array to internal ac grid.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 87
In this master thesis, the PV inverter is modelled according to [70]. The function of central PV
inverter is to interconnect PV arrays with the 3-phase ac grid and commonly modelled as
voltage source inverter (VSI) type. At first, a PV array produces dc current and is connected to
PV inverter whose function is to convert dc current into 50 or 60 Hz ac current using local
control. The electrical scheme is illustrated in Figure 4. 7.
Figure 4. 7 Electrical scheme of on-grid solar PVPP under study [adapted from [70]]
In this scheme, the dc side is modelled as a capacitor that acts as a voltage source and the ac
side is modelled as a filter which is made up of three phase inductance which acts as a current
source.
Due to limited resources, in this master thesis an average equivalent model as in [45] is used.
The average model is based on the concept of ideal switching modulation and particularly
technique of space vector pulse width modulation (SVPWM). Consequently, the converter
model is decoupled and has 2 (two) sides. The dc side is modelled as a capacitor which acts
as current source and the ac side is modelled as an ac voltage source. The equation that
connects dc side with ac side will be described in later part. The average model is described
in Figure 4. 8.
Page 88 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 4. 8 Electrical scheme of average on-grid solar PVPP model under study [adapted
from [45]]
In order to analyze the model of PV inverter, the PV array is represented as a current source
and the low voltage side of the transformer is represented by three voltage sources, vza, vzb
and vzc respectively as sketched in Figure 4. 9.
Figure 4. 9 Electrical scheme of average PV inverter model under study [adapted from [45]]
4.3.1 Local Control of PV Inverter
Park transformation plays an important role in the general control scheme in a way simplifying
the control algorithm. The general control of PV inverter is sketched in Figure 4. 10.
First of all, vzq component is obtained by means of phase locked loop (PLL) with PI controller
calculating the angle θ that results in vzd = 0. Considering vzd = 0, the active (Pz) and reactive
power (Qz) delivered to the grid can be calculated based on equation 4.5 and 4.6 as follows.
P𝑧 =3
2(𝑣𝑧𝑞𝑖𝑞) (4.5)
Q𝑧 =3
2(𝑣𝑧𝑞𝑖𝑑) (4.6)
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 89
Figure 4. 10 General control scheme of PV inverter
Active (Pz) and reactive power (Qz) can be controlled separately by means of control of iq and
id components, respectively. Based on the dc voltage measurement (Vdc) and the dc voltage
setpoint (𝑉𝑑𝑐∗ ), the reference computation block calculates the desired current in the q axis (𝑖𝑞
∗)
and d axis (𝑖𝑑∗ ) using PI controller as given in equation 4.7 and 4.8, respectively.
𝑖𝑞∗ =
2
3
𝑃𝑧∗
𝑣𝑧𝑞 (4.7)
𝑖𝑑∗ =
2
3
𝑄𝑧∗
𝑣𝑧𝑞 (4.8)
𝑃𝑧∗ and 𝑄𝑧
∗ are the setpoints of active and reactive power delivered to the grid, respectively.
The main function of MPPT is to generate the dc voltage setpoint (𝑉𝑑𝑐∗ ) and 𝑉𝑑𝑐
∗ is related to
the active power. It is not always the case the PV array has to work at the maximum power
point (MPP) since in some cases PV array is expected to generate necessary voltage that
leads to the desired active power.
The main function of current loop block is to compute the voltage (𝑣𝑙𝑞∗ , 𝑣𝑙𝑑
∗ ) in qd0 frame to be
applied by the PV inverter by taking into account the desired current (𝑖𝑞∗ , 𝑖𝑑
∗ ) and current
measurement (iq,id) in qd0 frame. Then the SVPWM technique is used to modulate these
voltages. In fact, these voltages are applied directly to three voltage sources by using the anti-
Page 90 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Park transformation (i.e. the technique of anti-park transformation is embedded in voltage
modulation block) since average model is used in this master thesis.
MPPT
Two functions that MPPT may have are (1) in case there is no PPC in the solar PV facility, it
is to calculate the dc voltage setpoint (𝑣𝑑𝑐∗ ) to produce maximum power based on PV array
behavior and environmental conditions (i.e. MPP mode). (2) in case there is PPC in the solar
PV facility, MPPT can perform power curtailment by computing the dc voltage setpoint (𝑣𝑑𝑐∗ )
to generate a desired active power (i.e. active power setpoint mode). MPPT algorithms are
essentially based on heuristic technique. The most widespread algorithm is so-called perturb
and observed (P&O).
Regarding the first function, this method measures the generated active power (Pz) of PV array
and changes the voltage supplied (vdc) by PV array to the PV inverter. Then, the system will
measure the generated active power again (Pz(k)) and compare it to the previous generated
active power (Pz(k-1)). In case the increment of vdc results in the increment of Pz(k) then the
system will increase vdc again until MPP is reached (vdc = 𝑣𝑑𝑐∗ ). However, in case the increment
of vdc results in the decrement of Pz(k) then the system will lower the vdc in the next step. On the
other hand, in case the decrement of vdc results in the increment of Pz(k) then the system will
decrease vdc again until MPP is reached. Then, in case the decrement of vdc results in the
decrement of Pz(k) then the system will raise the vdc in the next step.
With regards to the second function, when the PV array is expected to deliver certain amount
of active power (Pz) according to active power setpoint (Pz*) (i.e. not maximum power), the PV
array must operate outside of its MPP. It is required to operate the PV array in the right zone
of maximum power point to prevent Vdc is lower than Vdcmin. In case the active power setpoint
(𝑃𝑧∗) is lower than Pz then voltage increment must be applied. When the Pz is equal to the 𝑃𝑧
∗
the aforementioned MPPT algorithm is implemented which leads to the condition of 𝑃𝑧∗ > 𝑃𝑧
and supplied voltage (vdc) increases. The other observation is in case Pz cannot reach 𝑃𝑧∗, the
algorithm will be continuously performing the MPPT. In the end, 𝑃𝑧∗ is greater than maximum
active power (Pz) of the PV array. The corresponding flowchart for active power setpoint mode
(i.e. not MPP mode) is illustrated in Fig. 4.11.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 91
Fig.4.11 MPPT algorithm for active power setpoint mode
Master Control by Power Plant Controller
The PV inverters are capable of performing their own local controls in compliance with the
active power and reactive power setpoints established by PPC. These setpoints contain
desired value of each active and reactive power to be met at the PCC. Hence, PPC is the
responsible device to drive the active power and frequency action as well as reactive power
and voltage regulation action described below. In contrast, FRT requirement is satisfied by the
local controls built in the PV inverters.
Grid code requirements from operational perspective that are satisfied by PPC are.
1) Active power and frequency regulation action.
The frequency support is used to sustain the grid frequency in determinate ranges
around its nominal value by regulating active power output of solar PVPP. The active
power and frequency regulation action can be in the following form.
Page 92 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
• Active power curtailment: the responsible system operator sends the active power
setpoint that must be satisfied at PCC.
• Frequency regulation by droop curve: the responsible system operator establishes
a curve which preset an increase or decrease of the active power output delivered
at PCC as a function of the measured frequency.
• Ramp rate restriction: the active power variation may be limited by a ramp rate
when transitions (such as absolute production and power reserve) occur. This may
also apply to reactive power output.
2) Reactive power and voltage regulation action
The solar PVPP is required to help sustaining the grid voltage level. Hence, a minimum
reactive power capability is established and ancillary devices (e.g. FACTS or capacitor
banks) can help to meet the capability limit. The reactive power and voltage regulation
action may be in the following form.
• Reactive power setpoint: the responsible system operator sends reactive power
setpoint that must be satisfied by solar PVPP at the PCC.
• Voltage regulation by droop curve: the responsible system operator establishes a
droop curve that consists of preset the reactive power depending on the voltage
level at the PCC.
• Power factor setpoint: the responsible system operator sends power factor that
must be met by solar PVPP at the PCC.
The active power control scheme in this master thesis is adopted from [28] and limited to active
power curtailment using MPPT function in the PV inverter. As depicted in Figure 4. 11, the
control scheme is split into reference computation block, the controller and the dispatch
system. The reference computation block calculates the active power setpoints (P*) that must
be satisfied at PCC.
Once P* is calculated, the controller computes the aggregated power (Ptot) that must be
delivered by all PV inverters. This controller is based on a typical PI controller that ensures no
error (i.e. error = 0) between P* and the measured power (P) at PCC in normal operating
condition.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 93
Figure 4. 11 Typical LS-PVPP layout including power plant control scheme [28]
The reactive power control is carried out in a similar way with active power control as illustrated
in Figure 4. 11. In this master thesis, ancillary devices (i.e. FACTS device and capacitor banks)
are not employed in the model.
In contrast to the active power and frequency regulation action, the reactive power and voltage
regulation action does not require simultaneous operations such as reactive power setpoint
and voltage control. Thus, a mode selector is employed to choose the way to compute desired
reactive power setpoint (𝑄∗) from three options that are reactive power control, voltage control
and power factor control.
In case reactive power control is chosen, the responsible system operator sends a reactive
power setpoint (QTSO) and 𝑄∗ = 𝑄𝑇𝑆𝑂. In case power factor control is chosen, the
corresponding desired reactive power is expressed in Eq. 4.9.
𝑄𝑇𝑆𝑂 = 𝑃 ∙sin(𝜑)𝑇𝑆𝑂
cos(𝜑)𝑇𝑆𝑂 (4.9)
Where P represents the measured active power at PCC and cos(𝜑)𝑇𝑆𝑂 represents the power
factor setpoint.
In case the voltage control is chosen, 𝑄𝑇𝑆𝑂 is computed according to voltage droop curve
Page 94 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
illustrated in Figure 4. 12. In this context, due to the entire plant operation, it is needed to filter
the voltage measurement (V) to obtain droop input (V´).
Figure 4. 12 Voltage control function [28]
Next, the controller computes the reactive power (Qtot) that PV inverters have to deliver by
means of PI controller as depicted in Figure 4. 12. The corresponding p.u. value of β signal is
obtained by dividing Qtot by Qplant. Where Qplant represents the nominal reactive power of the
solar PVPP. Each PV inverter i receives β signal and computes its local reactive power setpoint
as follows.
𝑄𝑖𝑛𝑣,𝑖∗ = 𝛽 ∙ 𝑄𝑛𝑜𝑚,𝑖 (4.10)
Notice 𝑄𝑖𝑛𝑣,𝑖∗ and 𝑄𝑛𝑜𝑚,𝑖 represents the local reactive power setpoint and the nominal reactive
power of the inverter i, respectively.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 95
Modelling and Simulation of Solar PVPP
The modelling approach for each electrical element is described one by one below.
PV Arrays
The PV module constituting the PV arrays in this model is KC200 GT solar module from
Kyocera company. This module possesses characteristics listed in Table 5. 1 under standard
test condition (STC) in which the working temperature (T) is 25oC and solar irradiance (G) is
1000 W/m2 [71].
No. Electrical characteristics
1. Maximum power (Pm) 200 W
2. Current at maximum power point (𝐼𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒) 7.61 A
3. Voltage at maximum power point (𝑉𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒) 26.3 V
4. Short circuit current (Isc,n) 8.21 A
5. Open circuit voltage (Voc,n) 32.9 V
Thermal characteristics
6. Short circuit current – temperature coefficient (KI) 3.18x10-3 V/oC
7. Open circuit voltage – temperature coefficient (Kv) -1.23x10-1 A/oC
Physical characteristics
8. Dimensions 1425 mm x 990 mm x 36 mm
9. Weight 18.5 kg
10. PV cell type Multicristalline silicon
11. Number of cells per module 54 cells in series
Table 5. 1 Characteristics of PV module [71]
In the solar PVPP system under study, there are two (2) PV arrays and each of them consists
Page 96 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
of ninety two (92) PV strings (Np = 92) and each PV string is made up of twenty seven (27) PV
modules (Nm = 27) resulting in 4,968 pieces of PV module. The nominal power of each PV
array is expressed by equation 5.1.
𝑃𝑎𝑟𝑟𝑎𝑦 = 𝑁𝑝 ∙ 𝑁𝑚 ∙ 𝑃𝑚 (5.1)
Parray represents the nominal power of each PV array and it is 496.8 kW. Hence, two PV arrays
result in total nominal power of 993.6 kW.
The nominal short circuit current and the open circuit voltage of each PV array are given in
equation 5.2 and 5.3, respectively. They result in 755.32 A and 888.3 V, respectively.
𝐼𝑠𝑐𝑎𝑟𝑟𝑎𝑦= 𝑁𝑝 ∙ 𝐼𝑠𝑐,𝑛 (5.2)
𝑉𝑜𝑐𝑎𝑟𝑟𝑎𝑦= 𝑁𝑚 ∙ 𝑉𝑜𝑐,𝑛 (5.3)
The current and voltage at maximum power point of each PV array can be calculated by
equation 5.4 and 5.5. They give 700.2 A and 710.1 V, respectively.
𝐼𝑀𝑃𝑃𝑎𝑟𝑟𝑎𝑦= 𝑁𝑝 ∙ 𝐼𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒
(5.4)
𝑉𝑀𝑃𝑃𝑎𝑟𝑟𝑎𝑦= 𝑁𝑚 ∙ (𝑉𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒
) (5.5)
Figure 5. 1 and Figure 5. 2 illustrates characteristic curve of the PV module and PV array,
respectively under STC. The discrepancies in most important characteristics between
simulation model and information given by the PV module manufacturer for a PV module and
two (2) PV arrays are summarized in Table 5. 2 and Table 5. 3. As seen in Table 5. 2 and
Table 5. 3, the simulation results are similar to the information given by PV module
manufacturer.
Figure 5. 3 and Figure 5. 4 describe the PV array characteristics under variations of working
temperature (T) and irradiance (G), respectively. It is seen that the working temperature (T)
affects the open circuit voltage (Voc,n) and open circuit voltage at MPP (𝑉𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒) in an
inverse way as well as short circuit current (Isc,n) and current at MPP (𝐼𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒) slightly in a
linear way. On the contrary, irradiance (G) influences short circuit current (Isc,n) and current at
MPP (𝐼𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒) significantly in a linear way and the open circuit voltage (Voc,n) and open
circuit voltage at MPP (𝑉𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒) slighlty in a linear way.
As observed in Figure 5. 3 and Figure 5. 4 that maximum PV power changes with variation of
working temperature (T) and irradiance (G). This is summarized in Figure 5. 5 and Figure 5. 6
Therefore, it is needed to deploy maximum power point tracking (MPPT) function to search for
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 97
the maximum PV power under particular working temperature (T) and irradiance (G)
Figure 5. 1 V-I and V-P characteristic curves of PV module at T = 25oC and G = 1000 W/m2
Figure 5. 2 V-I and V-P characteristic curves of two (2) PV arrays
at T = 25oC and G = 1000 W/m2
Page 98 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
No. PV module Simulation
Result
Error (%)
1. Maximum power (Pm) 200.16 W 0.08
2. Current at maximum power point (𝐼𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒) 7.58 A -0.39
3. Voltage at maximum power point (𝑉𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒) 26.38 V 0.30
4. Short circuit current (Isc,n) 8.26 A 0.61
5. Open circuit voltage (Voc,n) 32.87 V -0.09
Table 5. 2 Simulation results of PV module
No. Two (2) PV arrays Simulation
Results
Error (%)
1. Maximum power (Pm) 994,389.83 W 0.08
2. Current at maximum power point (𝐼𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒) 1395.79 A -0.32
3. Voltage at maximum power point (𝑉𝑀𝑃𝑃𝑚𝑜𝑑𝑢𝑙𝑒) 712.42 V 0.33
4. Short circuit current (Isc,n) 1509.75 A -0.06
5. Open circuit voltage (Voc,n) 887.75 V -0.06
Table 5. 3 Simulation results of two (2) PV arrays
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 99
Figure 5. 3 PV arrays characteristics in function of working temperature (T)
Figure 5. 4 PV arrays characteristics in function of irradiance (G)
Page 100 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 5. 5 Max PV power in function of temperature (T) and
at constant irradiance (G) of 1000 W/m2
Figure 5. 6 Max PV power in function of irradiance (G) and
at constant working temperature (T) of 25oC
In addition, three parameters to take into account for sizing the correct inverter linked to each
PV array is (1) 𝑉𝑚𝑖𝑛𝑀𝑃𝑃𝑇≤ 712.42 V ≤ 𝑉𝑚𝑎𝑥𝑀𝑃𝑃𝑇
, (2) 𝐼𝑖𝑛𝑝𝑢𝑡𝑚𝑎𝑥≥ 697.9 𝐴 and (3) 𝑃𝑛𝑜𝑚 ≥
497,190 𝑊 [72].
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 101
PV Inverters
The solar PVPP is modelled as in Figure 4. 8 and the PV inverter model is a ready-to-use
model that can be coupled directly with the PV arrays and the integration of transformer and
electrical grid. Each PV array is linked to a single central PV inverter resulting in the total
number of PV inverters is two (2).
In the PV inverter model, instead of one (1) PV array of approximately 1 MW linked to a single
central PV inverter, two (2) PV arrays of each maximum PV power of 500 kW connected to
two (2) central PV inverters separately are deployed. Some underlying motives for that are (1)
easy maintenance. Solar PVPP requires less maintenance than the other power plants since
it has a few moving parts. However, solar PVPP still requires little maintenance that must be
performed for determinate intervals. In case of maintenance, one (1) PV array can be isolated
at a time. As a result, the other PV array may still be online that results in the generated
maximum PV power of approximately 500 kW. (2) Higher reliability. In the event of fault that
happens to one PV array, it results in the isolation of the corresponding PV array, the other PV
array may still be in operation and produces maximum PV power of approximately 500 kW
[73]. The PV inverter model is depicted in Figure 5. 7.
In the PV inverter simulation, the grid along with the transformer are represented by three
phase ideal voltage source 400 kV (phase to phase) at 50 Hz. The maximum active power of
the PV inverter is not limited due to an approximation model is used in this master thesis. Table
5. 4 summarizes the characteristics of the PV inverter model in this master thesis. The
simulation model is run under STC.
Page 102 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 5. 7 The layout of PV inverter model
No. Characteristics Value
Phase Lock Loop
1. Admitted peak voltage (EmPLL) 16.33x103 V
2. Kp gain (Kppll) 0.0272
3. Ki gain (KIpll) 6.0439
4. Time constant (τPLL) 4.5 ms
Current loop
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 103
5. Kp gain (Kpi) 0.0395
6. Ki gain (KIi) 0.5333
7. Time constant (τi) 1 ms
Reference computation
8. Kp gain (Kpdc) 31.1002
9. Ki gain (KIdc) 1.3817 x 104
10. Time constant (τdc) 10 ms
11. Initial dc voltage reference (Vdcref) 800 V
Table 5. 4 Characteristics of PV inverter model
Page 104 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
5.2.1 Aggregated PV Inverter Model
Due to high computer system requirements to perform simulation of two PV arrays linked to
each individual PV inverter, in this master thesis, an aggregated PV inverter model is used.
The aggregated PV inverter model is characterized by a single PV inverter connected to one
PV array of approximately 1 MW.
As explained earlier in section 4.3.1 Local Control of PV inverter particularly about MPPT that
based on dc voltage measurement (Vdc) and dc voltage setpoint (𝑉𝑑𝑐∗ ), MPPT controller
computes desired current in the q axis (𝑖𝑞∗) and d axis (𝑖𝑑
∗ ). Since dc voltage measurement
(Vdc) is dependent on the power profile of PV array (i.e. work temperature (T) and irradiance
(G)), in the simplified PV inverter model the current setpoint in the q axis (𝑖𝑞∗) can be calculated
by.
𝑖𝑞∗ =
2
3
𝑃𝑧∗
𝑣𝑧𝑞 if 𝑃𝑧
∗ ≤ 𝑃𝑎𝑣 (5.6)
Or
𝑖𝑞∗ =
2
3
𝑃𝑎𝑣
𝑣𝑧𝑞 if 𝑃𝑧
∗ ≥ 𝑃𝑎𝑣 (5.7)
Where 𝑃𝑧∗ is active power setpoint and Pav is available power.
PV Plant Model
The PV plant model is a ready-to-use model for the purpose of master control simulation. It
consists of one aggregrated PV array linked to a single central PV inverter. The PV inverter is
connected directly to electrical grid. The internal impedance of electrical grid includes the
inductor-equivalent model of LV/MV transformer. Figure 5. 8 and Table 5. 5 depicts the PV
plant model and lists the parameter in PV plant model, respectively.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 105
Figure 5. 8 The layout of PV plant simulation model
Voltage (kV) Short circuit power (MVA) Reactance to resistance
(X/R)
20 500 1/3
Table 5. 5 Equivalent grid data
Page 106 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Results and Discussion
Maximum Power Point Tracking (MPPT)
6.2.1 Maximum Power Point (MPP) Mode
In this section, the maximum power point tracking (MPPT) function of PV inverters developed
by the student is tested for each particular working temperature (T) and irradiance (G). The
simulation result of MPTT function for variation of working temperature (T) and at constant
irradiance (G) of 1000 W/m2 as well as variation of irradiance (G) and at constant working
temperature of (T) of 25oC is depicted in Figure 6. 1 and Figure 6. 2, respectively.
As seen in Figure 6. 1, due to inizialitation period that is unrelated to the observation of MPP,
the simulation result is shown from second 1. Table 6. 1 compares the maximum PV power in
function of working temperature (T) and at constant irradiance (G) of 1000 W/m2 based on PV
array characteristics depicted in Figure 5. 5 with maximum PV power based on MPPT function
in PV inverter depicted in Figure 6. 1. Additonally, Table 6. 2 compares the maximum PV power
in function of irradiance (G) and at constant working temperature (T) of 25oC based on PV
array characteristics illustrated in Figure 5. 6 with maximum PV power based on MPPT
function in PV inverter illustrated in Figure 6. 2.
As observed in Table 6. 1 and Table 6. 2, the MPPT function developed by the student fits the
PV array characteristics well. The MPPT function creates little discrepancy because of the
pertubation in MPPT algorithm during maximum power point (MPP) searching.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 107
Figure 6. 1 PV power in function of working temperature (T) and
at constant irradiance (G) of 1000 W/m2
Figure 6. 2 PV power in function of irradiance (G) and
at working temperature (T) of 25oC
No. Period (s)
Working
Temperature
(oC)
Maximum PV Power Based on
PV Array Characteristics (Watt)
Maximum PV Power Based
on MPPT function (Watt)
Discrepancy
(%)
1. 1≤t<4 0 1,115,386 1,117,000 0.14
Page 108 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
2. 4≤t<9 25 994,390 996,000 0.16
3. 9≤t<14 50 873,537 875,300 0.20
4. 14≤t<20 75 753,388 755,100 0.23
Table 6. 1 Maximum PV power in function of working temperature (T) and at constant
irradiance (G) of 1000 W/m2
No. Period (s) Irradiance
(W/m2)
Maximum PV Power Based
on PV Array Characteristics
(Watt)
Maximum PV Power
Based on MPPT function
(Watt)
Discrepancy
(%)
1. 1≤t<5 200 180,325 185,200 2.63
2. 5≤t<9 400 382,422 386,900 1.16
3. 9≤t<13 600 587,034 590,800 0.64
4. 13≤t<17 800 791,442 794,200 0.35
5. 17≤t<20 1000 994,390 996,100 0.17
Table 6. 2 Maximum PV power in function of irradiance (G) and at constant working
temperature (T) of 1000 W/m2
6.2.1 Active Power Setpoint Mode (i.e. Power Curtailment)
As mentioned in section 4.3.1 Local Control PV Inverter particularly about MPPT function,
MPPT function can carry out power curtailment by calculating the dc voltage setpoint (𝑣𝑑𝑐∗ ) to
generate a desired active power (𝑃𝑧∗). In this mode there are two (2) options which are (1) In
case active power setpoint (𝑃𝑧∗) is greater than available power (Pav) (i.e. maximum power
based on PV array characteristics), then the MPPT function computes the dc voltage setpoint
(𝑣𝑑𝑐∗ ) that corresponds to the available power (Pav). (2) In case active power setpoint (𝑃𝑧
∗) is
lower than available power (Pav), then MPPT function computes the dc voltage setpoint (𝑣𝑑𝑐∗ )
that corresponds to the active power setpoint (𝑃𝑧∗).
Option 1 is depicted in
Figure 6. 3, the active power setpoint mode is activated at second 0.5. Hence, the simulation
result is displayed from second 0.5. When the active power setpoint (𝑃𝑧∗) is set to 1.5 MW,
then the MPPT function computes the dc voltage setpoint (𝑣𝑑𝑐∗ ) of approximately 713 V that
leads to the available power (Pav) of around 1 MW under STC as verified earlier. It is observed
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 109
that at second 0.5 the measured voltage (vdc) starts to decrease gradually from initial dc voltage
reference (Vdcref) of 800 V to dc voltage setpoint (𝑣𝑑𝑐∗ ) of approximately 713 V. At second 3.4,
measured voltage (vdc) reaches dc voltage setpoint (𝑣𝑑𝑐∗ ) of approximately 713 V that makes
generated active power equal to available power (Pav) of around 1 MW.
Option 2 is illustrated in Figure 6. 4, in a similar manner, the active power setpoint mode is
engaged in second 0.5. Hence, the simulation result is displayed from second 0.5. The active
power setpoint (𝑃𝑧∗) is depicted in brown line whereas the generated active power is
represented by blue line. When the active power setpoint (𝑃𝑧∗) is set to 0.5 MW, then the MPPT
function computes the dc voltage setpoint (𝑣𝑑𝑐∗ ) of 845 V that corresponds the active power
setpoint (𝑃𝑧∗) of approximately 0.5 MW. It is seen that measured voltage (vdc) starts rising from
initial dc voltage reference (Vdcref) of 800 V to dc voltage setpoint (𝑣𝑑𝑐∗ ) of approximately 845
V. At second 2, the measured voltage (vdc) reaches dc voltage setpoint (𝑣𝑑𝑐∗ ) that makes the
generated power equal to the active power setpoint (𝑃𝑧∗) of around 0.5 MW.
Figure 6. 3 Option 1 in active power setpoint mode
Page 110 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Figure 6. 4 Option 2 in active power setpoint mode
Voltage Control and Reactive Power Regulation Action
As described in section 4.4 Master Control by Power Plant Controller, voltage control and
reactive power regulation action can be in the form of (1) reactive power control, (2) voltage
control by droop curve and (3) power factor control. In this section, the reactive power and
voltage control regulation set out in grid code proposal for solar PVPP in major islands and
small islands in Indonesia described in section 3.3.3 Reactive Power and Voltage Support is
simulated. Furthermore, the response to this regulation is observed and explained.
6.2.1 Voltage Control
As explained earlier in section 3.3.3 Reactive Power and Voltage Support especially in Table
3.28, the grid code proposal sets out voltage control regulation for solar PVPP in small islands.
The proposed voltage control is adopted from Puerto Rico´s grid code.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 111
Figure 6. 5 depicts the response to voltage control function. In this simulation, the MPPT
particularly maximum power point mode and the voltage control are engaged concurrently.
The simulation result is displayed from second 0.2 since the mode of maximum active power
in MPPT and voltage control turn on at second 0.2. Hence, initialization takes place that is
unrelated to the simulation analysis lasts until second 0.2. In order to see the response under
the strictest requirement, the maximum allowable and minimum allowable voltage droop
gradient of 10% and -10% are applied in turn. Table 6. 3 lists the parameters in response to
voltage control function.
As observed in Figure 6. 5, at second 0.2 the solar PVPP starts to produce active power from
approximately 815 kW and at second 2.5 it eventually attains the maximum power point (MPP)
of 993.6 kW. In fact, due to perturb and observe method in MPPT algorithm, the generated
active power oscillates around the maximum power point (MPP) (i.e. not remains at 993.6 kW).
Regarding the reactive power output, as stated in Table 6. 3, from second 0.2 to 3.1, by default
the solar PVPP absorbs reactive power in the range of -2.2 W to -11,020 W due to the voltage
at the PCC of between 20,030 V and 20,040 V that is supposed to be absolute 20,000 V. The
deviated voltage at the PCC is because of the existence of internal impedance that leads to
the higher voltage than nominal voltage at the PCC. From second 3.1 to 5, a voltage
perturbation is simulated that leads to the voltage at the PCC of absolutes 20,000 V that places
the operating point within the deadband in voltage droop curve depicted in Figure 2. 8. As a
result, solar PVPP delivers reactive power in the range of -10,950 W to 13 W whereas
theoretically no reactive power. From second 5 to 7, another voltage perturbation is simulated
that leads the voltage at the PCC to 19,500 V that puts the operating point in the left zone of
voltage droop curve. As a result, solar PVPP produces reactive power between 125,400 W to
236,800 W. Additionally, from second 7 to 9, another voltage perturbation is simulated that
leads to the voltage at PCC of 20,540 V that puts the operating point in the right zone of voltage
droop curve. As a result, the solar PVPP absorbs reactive power in the range of -40,080 W to
-258,300 W. The generated reactive power fluctuates since the transient condition takes place
every time a voltage perturbation is simulated and it stays oscillating due to the perturb and
oscillation method in MPPT algorithm that affects the generated reactive power.
Table 6. 4 summarizes the parameters at a determinate point for each period. It is observed
that generated reactive powers are similar to theoretical reactive powers according to the
equation for voltage droop function described in section 2.2.3 Reactive Power and Voltage
Control Functions. The proposed voltage control function gives acceptable time response
since it takes less than 1 s to reach the 95% of steady-state response (i.e. 95% of final value
of reactive power) as listed in Table 6. 4.
In the next simulation, the minimum allowable voltage at the PCC and maximum voltage droop
function of 0.85 pu and 10% as well as the maximum allowable voltage at the PCC and
Page 112 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
minimum allowable voltage droop function of 1.15 pu and -10%, respectively, are applied
separately.
As seen in Figure 6. 6, at the second 0.2, the solar PVPP starts producing active power of
814,900 kW and at second 2.5, the solar PVPP achieves the maximum power point (MPP) of
993,600 kW. In fact, due to perturb and observe method in MPPT algorithm, the generated
active power keeps oscillating around the maximum power point (MPP) (i.e. not remains at
993.6 kW).
Concerning reactive power output, as listed in Table 6. 5, the response to voltage control
function for periods of second 0.2 to 3.1 and second 3.1 to 5 remains the same as stated in
Table 6.3. Additionally, from second 5 to 7, another voltage perturbation is simulated that leads
the voltage at the PCC to 0.85 pu (i.e. 17,000 V) that puts the operating point in the left zone
of voltage droop curve. As a result, solar PVPP delivers reactive power between 370,800 W
and 618,400 W. Since stated in the grid code proposal that the upper limit of reactive power
output of solar PVPP is 0.62 of actual power (Pac). Hence, the maximum reactive power that
solar PVPP can produce is 618,400 W despite the voltage drop at the PCC is over 0.062 pu
(in fact, the actual voltage drop is 0.15 pu that corresponds to the reactive power production
of 1.49 MW). Then from second 7 to 9, another voltage perturbation is simulated that leads to
the voltage at PCC of 1.15 pu (i.e. 23,000 V) that puts the operating point in the right zone of
voltage droop curve. As a result, the solar PVPP absorbs reactive power in the range of -
241,600 W to -619,300 W. As stated in the grid code proposal that lower limit of reactive power
output of solar PVPP is -0.62 of actual power (Pac). Thus, the maximum reactive power output
that solar PVPP can absorb is -619,300 W despite the voltage spike at the PCC is greater than
0.062 pu (in fact, the actual voltage spike is 0.15 pu that corresponds to the reactive power
absorption of 1.49 MW). The generated reactive power keeps fluctuating since the transient
condition occurs every time a voltage perturbation is simulated and it keeps oscillating due to
the perturb and oscillation method in MPPT algorithm that affects the generated reactive
power.
Table 6. 6 lists parameters at a determinate point for each period. It is seen that generated
reactive powers are similar to theoretical reactive powers according to the equation for voltage
droop function described in section 2.2.3 Reactive Power and Voltage Control Functions. The
proposed voltage control function gives acceptable time response since it takes less than 1 s
to reach the 95% of steady-state response (i.e. 95% of final value of reactive power) as listed
in Table 6. 5.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 113
Figure 6. 5 Response to voltage control function
No. Period (s) Voltage at the PCC (V) Reactive Power (W) Time Response (s)
1. 3.1≤t<5 20,000 -10,950 to 13 0.7
(i.e. at second 3.8)
2. 5≤t<7 19,500 125,400 to 236,800 0.5
(i.e. at second 5.5
3. 7≤t<9 20,540 -40,080 to -258,300 0.6 (at second 7.6)
Table 6. 3 Parameters in response to voltage control function
Page 114 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
No. Time (s) Voltage at
the PCC (V)
Active
Power (W)
Theoretical
Reactive
Power (W)
Generated
Reactive
power (W)
Reactive
Power
Discrepancy
(%)
1. 3.09 20,040 995,600 -10,930 -10,970 0.037
2. 4.99 20,000 992,700 0 -14.2 -
3. 6.99 19,500 995,300 236,600 236,500 -0.04
4. 8.99 20,540 995,500 -256,800 -256,900 -0.04
Table 6. 4 Parameters in determinate points for each period
Figure 6. 6 Response to voltage control function with different parameters
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 115
Table 6. 5 Parameters in response to another voltage control function
No. Time (s) Voltage at
the PCC (V)
Active
Power (W)
Theoretical
Reactive
Power (W)
Generated
Reactive
power (W)
Reactive
Power
Discrepancy
(%)
1. 3.09 20,040 995,600 -10,930 -10,970 0.37
2. 4.99 20,000 992,700 0 -14.2 -
3. 6.99 17,000 995,000 616,100 616,200 0.02
4. 8.99 23,000 995,500 -618,300 -617,800 -0.08
Table 6. 6 Parameters in determinate points for each period
6.2.2 Reactive Power Control
As described earlier in section 3.3.3 Reactive Power and Voltage Support particularly in Table
3.29, the grid code proposal contains reactive power regulation for solar PVPP in major islands
and small islands in Indonesia.
The proposed reactive power control is adopted from Denmark´s grid code and it is applied to
solar PVPP in both major islands and small islands. As set out in the grid code proposal, the
1 MW solar PVPP must be capable of delivering reactive power ranging from 0.48 pu to -0.48
pu with respect to power factor from 0.9 to -0.9.
No. Period (s) Voltage at the PCC (V) Reactive Power (W) Time Response (s)
1. 3.1≤t<5 20,000 -10,950 to 13 0.7
(i.e. at second 3.8)
2. 5≤t<7 17,000 370,800 to 618,400 0.5
(i.e. at second 5.5
3. 7≤t<9 23,000 -241,600 to
-619,300
0.7 (at second 7.7)
Page 116 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
In this simulation, the maximum and minimum allowable reactive power setpoint of 0.48 pu
and -0.48 pu, respectively, are separately applied. At the same time, the MPPT mode
particularly maximum active power is engaged. As depicted in Figure 6. 7, the simulation
results are shown from second 0.2 because initialization that is unrelated to the simulation
analysis takes place until second 0.2. It is observed that at second 0.2 solar PVPP starts to
increase active power from 814,900 W and at second 2.5 solar PVPP attains the maximum
PVPP power of 993,600 W. Concurrently, the reactive power setpoint (𝑄∗) is set to 0.48 pu
at second 0.2 then the solar PVPP starts delivering reactive power gradually from 273,100
W. Then solar PVPP attains the reactive power setpoint (𝑄∗) of 476,928 W at second 1.8.
In other words, it takes 1.6 s for solar PVPP to attain the reactive power setpoint (i.e. time
response of 1.6 s).
Additionally, as illustrated in Figure 6. 8, when the reactive power setpoint is established at
-0.48 at second 0.2 then the solar PVPP starts absorbing reactive power of -272,800 W.
The solar PVPP reaches the reactive power setpoint (𝑄∗) of -476,928 W at second 1.7 s. In
other words, it takes 1.5 s for solar PVPP to reaches the reactive power setpoint (i.e. time
response of 1.5 s). At the same time, at second 0.2 the MPPT mode particularly maximum
power point is engaged. The solar PVPP begin producing active power 814,900 W and
reaches the active power setpoint of 993,600 W at second 2.5. It is concluded that the
proposed reactive power controller meets the requirement as it gives time response shorter
than that in the requirement (i.e. time response of 10 s).
Figure 6. 7 Response to maximum allowable reactive power setpoint
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 117
Figure 6. 8 Response to minimum allowable reactive power setpoint
6.2.3 Power Factor Control
As explained in section 3.3.3 Reactive Power and Voltage Support, solar PVPP both in major
islands and smalls islands must be capable of operating at power factor in the range of 0.9 to
-0.9. In this simulation, the maximum and minimum permissible power factor setpoint of 0.9
and -0.9 are applied separately. At the same time, MPPT particularly MPP mode is activated.
As depicted in
Figure 6. 9, the simulation results are shown from second 0.2 because initialization that is
unrelated to the simulation analysis takes place until second 0.2. At second 0.2, it is
observed that the solar PVPP starts to increase active power from 814,900 W and at second
2.5 solar PVPP attains the maximum PVPP active power of 993,600 W. And at second 0.2,
when the power factor setpoint is established at 0.9, the solar PVPP also starts delivering
reactive power gradually from 208,400 W. Then eventually the solar PVPP attains the
desired reactive power of 476,928 W at second 2.3. Regarding the response to power factor
setpoint, at second 0.2, solar PVPP operates at power factor of 0.96 and eventually at
second 2.9, it attains the reactive power setpoint of 0.9. In other words, the solar PVPP
attains the steady-state response of power factor setpoint in 2.7 s (i.e. time response of 2.7
s).
In addition, as illustrated in Figure 6. 10, the simulation results are displayed from second 0.2
because of unrelated transient condition that lasts until second 0.2. At second 0.2, the solar
PVPP begins to deliver active power gradually from 814,900 W and at second 2.5 solar PVPP
Page 118 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
reaches the maximum active power of 993,600 W. At second 0.2, when the power factor
setpoint is established at -0.9, the solar PVPP starts to absorb reactive power from -249,100
W. Then finally the solar PVPP reaches the desired reactive power of -476,928 W at second
2.4. Concerning response to power factor setpoint, at second 0.2, solar PVPP runs at power
factor of -0.96 and finally at second 2.7, the solar PVPP attains the power factor setpoint of -
0.9. In other words, the solar PVPP reaches the steady-state response of reactive power in
2.5 s (i.e. time response of 2.5 s). It is concluded that proposed power factor controller meets
the requirement as it yields time response less than 10 s as stated in the requirement.
Figure 6. 9 Response to maximum allowable power factor setpoint
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 119
Figure 6. 10 Response to minimum allowable power factor setpoint
Page 120 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Conclusion
In this master thesis, the study of several international grid codes from operational
perspectives are performed as a foundation to create grid code proposal for 1 MW solar PVPP
in Indonesia. The grid code proposal consists of regulation of voltage and frequency boundary,
active power and frequency support, reactive power and voltage support as well as fault-ride-
through (FRT). Moreover, to comply with the grid code proposal, power plant controller (PPC)
is modelled and simulated using Matlab and Simulink to see the response. Particularly, MPPT
function in PV inverter and voltage control, reactive power control and power factor control
have been verified. Following conclusions can be drawn from all works carried out in this
master thesis.
• At present, Indonesia is using IEEE series of standard and one of them is IEEE 1547 as
the guidance on interconnection of solar PVPP to electricity grid. The current policies in
Indonesia are leading to promote the connection of new PV generation facilities, which
will change the electricity mix of the country. Accordingly, new regulations regarding the
PV power plants interconnection will be required.
• This study can serve as a starting point for developing a new regulation for the
connection of PVPP in Indonesia. From the viewpoint of geography, electricity
generation mix and electricity interconnection system those grid codes that best suit
the solar PVPP in major island and small islands are grid code of Denmark and Puerto
Rico, respectively. Moreover, based on these two international grid codes, the grid code
proposal is created along with some modifications to adapt to the existing electricity
system of Indonesia and projection of solar PV growth in the electricity mix.
• As working temperature (T) and solar irradiance (G) affects the active power output of
solar PVPP, it is necessary to use MPPT function to continuously search for the
maximum power point (MPP). Maximum power point (MPP) mode in MPPT function is
modelled and simulated under variation of working temperature (T) and solar irradiance
(G). It is validated that MPP mode helps to produce maximum active power in each
scenario.
• In order to comply with the grid code proposal such as active power and frequency
regulation as well as reactive power and voltage regulation, MPPT function and power
plant controller (PPC) is modelled and developed. MPPT function can be modified in
order to achieve a desired power production. This modification can be used to comply
with those requirements affecting the active power (e.g. power curtailment) as shown
by the simulation results.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 121
• The voltage, reactive power and power factor control requirements can be fullfilled
thanks to a central controller based on a PI controller, which have been validated
through simulations complying with the required time response.
In order to obtain more comprehensive and accurate result, the following works can be carried
out in the future.
• In order to see the dynamic response and effect of individual electrical device, the
current solar PVPP model can be developed to detailed solar PVPP model comprising
LV-MW transformer and MV-MV transformer.
• In order to see the response to active power and frequency regulation, the active power
and frequency support controller comprising function of frequency response (i.e.
frequency control), absolute production (i.e. power curtailment), delta production (i.e.
power reserve) and power gradient (i.e. ramp rate) can be modelled and simulated.
Page 122 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
Bibliography
[1] BP, “energy outlook 2035,” 2014. [Online]. Available: www.bp.com.
[2] International Energy Agency, "Energy Technology Perspectives 2012," 2012.
[3] Intergovernmental Panel on Climate Change, "Summary for Policymakers," Cambridge
University Press, Cambridge, United Kingdom and New York, NY, 2014.
[4] Comission of the European Communities, "An Energy Policy for Europe," Brussels,
2007.
[5] European Comission, "Energy roadmap 2050," Brussels, 2011.
[6] EWEA, "The European Wind Energy Association," 2014. [Online]. Available:
http://www.ewea.org/.
[7] IRENA resource, 2015. [Online]. Available:
http://www.resourceirena.org/gateway/index.
[8] American Wind Energy Association, "Wind energy facts at a glance," 2014. [Online].
Available: http://www.awea.org.
[9] Fraunhofer ISE, "Photovoltaics report," 14 March 2019. [Online]. Available:
https://www.ise.fraunhofer.de/content/dam/ise/de/documents/publications/studies/Ph
otovoltaics-Report.pdf.
[10] Solar Energy Industries Association, “U.S solar market adds 10.6 GW of PV in 2018,
residential market rebounds,” 13 March 2019. [Online]. Available:
https://www.seia.org/news/us-solar-market-adds-106-gw-pv-2018-residential-market-
rebounds.
[11] M. A. Peñalba, "Operation and control of transmission systems for offshore wind power
plants," Barcelona, 2016.
[12] E. B.-M. M. A.-P. O. G.-B. Ana Cabrera-Tobar, "Review of advanced grid requirements
for the integration of large scale photovoltaic power plants in the transmission
system," Renewable and sustainable energy reviews, 2016.
[13] International Energy Agency, “Trends 2015 in photovoltaics application,” 2015.
[Online]. Available: http://www.iea-pvps.org/fileadmin/dam/public/report/national/IEA-
PVPS_-_Trends_2015_-_MedRes.pdf.
[14] National Renewable Energy Laboratory (NREL), "Energy snapshot," March 2015.
[Online]. Available: https://www.nrel.gov/docs/fy15osti/62708.pdf.
[15] U.S. Energy Information Administration, "Puerto Rico Territory Energy Profile," 19 July
2018. [Online]. Available: https://www.eia.gov/state/print.php?sid=RQ.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 123
[16] International Energy Agency, "Electricity generation by fuel," 2018. [Online]. Available:
https://www.iea.org/statistics/?country=GERMANY&year=2016&category=Electricity
&indicator=ElecGenByFuel&mode=chart&
[17] Energy Transition, "Renewable and power exports hit record high in 2017," August
2017. [Online]. Available: https://energytransition.org/wp-
content/uploads/2018/01/cm1.png.
[18] International Energy Agency, "Electricity generation by fuel," 2018. [Online]. Available:
https://www.iea.org/statistics/?country=DENMARK&year=2016&category=Electricity&i
ndicator=ElecGenByFuel&mode=chart&dataTable=ELECTRICITYANDHEAT.
[19] Eurostat, "Electricity and heat statistics," 3 September 2018. [Online]. Available:
https://ec.europa.eu/eurostat/statistics-
explained/index.php/Electricity_and_heat_statistics#Production_of_electricity.
[20] Wind Europe, "Wind in power 2017," February 2018. [Online]. Available:
https://windeurope.org/wp-content/uploads/files/about-wind/statistics/WindEurope-
Annual-Statistics-2017.pdf.
[21] National Grid ESO, "Grid code," 2019. [Online]. Available:
https://www.nationalgrideso.com/codes/grid-code.
[22] F. P. M. R. S. N. F. S. R. N. Antonios Marinopoulos, "Grid Integration Aspects of Large
Solar PV Installations: LVRT Capability and Reactive Power / Voltage Support
Requirements," 2011.
[23] R. B. Manasseh Obi, "Trends and Challenges of Grid-Connected Photovoltaic
System," Renewable and sustainable energy reviews 58, pp. 1082-1094, 2016.
[24] K. T. Magoro B, "Grid Connection Code for Renewable Power Plants Connected to
the Electricity Transmission System or the Distribution System in South Africa,"
National Energy Regulator of South Africa, 2012.
[25] W. Y. F. W. X. F. W. C. A. Z. L. e. a. Liang J, "Comparative Study of Standards for Grid
Connected PV System in China, the US and European Countries," National energy
administration of China, 2013.
[26] I. M. M. D. P. R. Banu I., "Aspects of Photovoltaics Power Plant Integration in the
Romanian Power System," Technical University of Lasi, 2014.
[27] Energinet, Technical Regulation 3.2.2 for PV Power Plants Above 11 kW, 2016.
[28] R. F.-S.-J. M. A.-P. L. S.-S. C. P.-N. O. G.-B. Eduard Bullich-Massague, "Power Plant
Control in Large Scale PV Plants. Design, Implementation and Validation in a 9.4 MW
PV Plant," IET Renewable Power Generation, vol. 10, no. 1, pp. 50-62, 2016.
Page 124 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
[29] VDE, "Summary of the Draft VDE-AR-N 4110:2017-02," February 2017. [Online].
Available:
https://www.vde.com/resource/blob/1674522/46ee71927b557be9bd9fc7f59c2c70f7/
summary-tar-ms-data.pdf.
[30] VDE, "Summary of the Draft VDE-AR-N 4120:2017-05," May 2017. [Online].
Available:
https://www.vde.com/resource/blob/1667900/836e3781b72b3b726f509c90e35e339
d/tar-hs-summaryen-data.pdf.
[31] E. Troester, "New German Grid Codes for Connecting PV Systems to the Medium
Voltage Power Grid," 2008.
[32] Energinet, "Technical Regulation 3.2.1 for Power Plants up to and Including 11 kW,"
2016.
[33] Energinet, "Technical Regulation 3.2.3 for Thermal Plants Above 11 kW," 2017.
[34] Energinet, "Technical Regulation 3.2.5 for Wind Power Plants Above 11 kW," 2016.
[35] Energinet, "Technical Regulation 3.3.1 for Battery Plants," 2016.
[36] Entsoe, "System Operations Comittee," 2019. [Online]. Available:
https://www.entsoe.eu/about/system-operations/.
[37] Kementerian Energi dan Sumber Daya Mineral, "Indonesia Energy Outlook 2010,"
Jakarta, 2010.
[38] Dewan Energi Nasional, "Outlook Energi Indonesia 2016," Jakarta, 2016.
[39] Kementerian Energi dan Sumber Daya Alam Mineral Republik Indonesia, "Capaian
2017 dan Outlook 2018 Subsektor Ketenagalistrikan dan EBTKE," 10 January 2018.
[Online]. Available: https://www.esdm.go.id/id/media-center/arsip-berita/capaian-2017-
dan-outlook-2018-subsektor-ketenagalistrikan-dan-ebtke-.
[40] Kementerian Energi dan Sumber Daya Alam Mineral Direktorat Jenderal
Ketenagalistrikan, "Statistik Ketenagalistrikan 2017," Jakarta, 2018.
[41] Alamendah, "Pembangkit Listrik Tenaga Surya di Indonesia," 8 December 2014.
[Online]. Available: https://alamendah.org/2014/12/08/pembangkit-listrik-tenaga-
surya-di-indonesia/.
[42] M. C. B. Z. Joko Pramono, "Teknik Tenaga Listrik," Departemen teknik elektro fakultas
teknik universitas indonesia, Depok, 2010.
[43] International Electroctechnical Comission, "IEC 60038:2009 IEC Standard," 17 June
2009. [Online]. Available: https://webstore.iec.ch/publication/153.
[44] Perusahaan Listrik Negara, "Tegangan-Tegangan Standar," Jakarta, 1995.
Grid Code Proposal for Solar Photovoltaics Power Plant in Indonesia Page 125
[45] E. Bullich-Massague, "Control of Renewable Distributed Power Plants," Polytechnic
University of Catalonia, Barcelona, 2015.
[46] Perusahaan Listrik Negara, "RUPTL Rencana Usaha Penyediaan Tenaga Listrik PT.
PLN (persero) 2019-2028," Jakarta, 2019.
[47] Menteri Energi dan Sumber Daya Mineral Republik Indonesia, "Peraturan Menteri
Energi dan Sumber Daya Mineral Nomor : 03 Tahun 2007," Jakarta, 2007.
[48] Perusahaan Listrik Negara, "Inverter Untuk Pembangkit Listrik Tenaga Surya (PLTS)
Persyaratan Umum dan Metode Uji," Jakarta, 2012.
[49] Badan Pusat Statistik, "Luas Daerah dan Jumlah Pulau Menurut Provinsi, 2002-
2016," 2016.
[50] O. J. W. T. G. M. Kal Wagenheim, "Puerto Rico," Encyclopedia britannica, 8 June
2019. [Online]. Available: https://www.britannica.com/place/Puerto-Rico.
[51] C. N. M. I. L. S. V. A. H. F. Robert T. Anderson, "Denmark," Encyclopedia Britannica,
11 June 2019. [Online]. Available: https://www.britannica.com/place/Denmark.
[52] T. S. H. C. C. B. J. J. S. W. H. B. P. J. G. e. a. George Hall Kirby, "Germany,"
Encyclopedia Britannica, 12 June 2019. [Online]. Available:
https://www.britannica.com/place/Germany.
[53] Eurostat, "Land Cover Statistics," 30 October 2018. [Online]. Available:
https://ec.europa.eu/eurostat/statistics-
explained/index.php/Land_cover_statistics#Land_cover_in_the_EU.
[54] U.S. Department of Energy, "Energy Resilience Solutions for the Puerto Rico Grid,"
Washington DC, 2018.
[55] Danish Energy Agency, "Security of Electricity Supply in Denmark," Danish Energy
Agency, Copenhagen, 2016.
[56] European Network of Transmission System Operators for Electricity, "Statistical
Factsheet 2015," Brussels, 2016.
[57] K. K. N. K. K. O. K. I. M. e. a. Komoto K, "IEA PVPS Task 8: project proposals on very
large scale photovoltaic power generation (VLS-PV) systems in deserts," In: 2006
IEEE 4th World conference on photovoltaic energy conference, vol. 2, pp. 2359-62,
2006.
[58] E. B. M. A. O. G. Ana C.T., "Topologies for Large Scale Photovoltaic Power Plants,"
Renewable and Sustainable Energy Reviews, vol. 59, pp. 309-319, 2016.
[59] M. T., Solar Electricity, Southampton: Wiley, 2009.
[60] M. Tom, "Practical Handbook of Photovoltaics".
Page 126 Grid Code Proposal for Solar Photovoltaics Power Plants in Indonesia
[61] E. K. H. Y. W. W. D. E. Green MA, "Solar Cell Efficiency Tables," Prog Photovoltaics
Res Appl, vol. 20, no. 1, pp. 12-20, 2012.
[62] K. K. K. K. K. T. K. K. Ito M, "A Comparative Study on Cost and Life-Cycle Analysis
for 100 MW Very Large Scale PV (VLS-PV) Systems in Deserts Using m-Si, a-Si,
CdTe and CIS modules," Prog Photovoltaics Res Appl, vol. 16, no. 1, pp. 17-30, 2008.
[63] H. J. Moller, Semiconductor for Solar Cells, Norwood: Artech House, 1993.
[64] C.-S. T. Y.-J. S. Huan-Liang Tsai, "Development of Generalized Photovoltaic Model
Using Matlab/Simulink," Proceedings of the World Congress on Engineering and
Computer Science, 2008.
[65] R. T. P. R. D. Sera, "PV Panel Model Based on Datasheet Values," Proc IEEE Int.
Symp. Ind. Electron. (ISIE), pp. 2392-2396, 2007.
[66] S. K. W. B. W. De Soto, "Improvement and Validation of a Model for Photovoltaic Array
Performance," Solar energy, vol. 80, no. 1, pp. 78-88, 2006.
[67] S. K. W. B. Q. Kou, "A Method for Estimating the Long-Term Performance of Direct
Coupled PV Pumping Systems," Solar Energy, vol. 64, pp. 33-40, 1998.
[68] S. H. P. J. A. Driesse, "Evaluating the Effectiveness of Maximum Power Point Tracking
Methods in Photovoltaic Power Systems Using Array Performance Models," Proc.
IEEE Power Electron. Spec. Conf. (PESC), pp. 145-151, 2007.
[69] J. R. E. R. Marcelo GV, "Comprehensive Approach to Modelling and Simulation of
Photovoltaics Arrays.," IEEE Transaction on Power Electronics, vol. 24, no. 5, p. 1198,
2009.
[70] A. J.-F. O. G.-B. Agusti Egea-Alvarez, "Active and Reactive Power Control of Grid
Connected Distributed Generation System".
[71] Kyocera, "KC200GT High Efficiency Multicrystal Photovoltaic Module," [Online].
Available: https://www.kyocerasolar.com/dealers/product-center/archives/spec-
sheets/KC200GT.pdf.
[72] S. Silvestre, M.6 Grid Connected PV System, Polytechnic University of Catalonia.
[73] Solar Power Europe, "Operation & Maintenance Best Practices Guideline / Version
3.0," 2018.