Upload
ruchi-kumari
View
219
Download
0
Embed Size (px)
Citation preview
8/2/2019 Grfc2007 Tk2 Mr.rakesh
1/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 1
INTRODUCTION OF
HEAVY AXLE LOAD OPERATION ONINDIAN RAILWAYS
Presentation
By
Rakesh Chopra and H L Suthar
ADDITIONAL MEMBER,and DIRECTOR
Indian Railway Board
8/2/2019 Grfc2007 Tk2 Mr.rakesh
2/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 2
STRUCTURE OF PRESENTATION
1. GROWTH: _ NATIONAL.
_ INDIAN RAILWAYS.
2. INITIATIVES:_ EXISTING TRACK AND STRUCTURES._ MODERNISATION OF TRACK AND STRUCTURES.
_ RESIDUAL CAPACITY AND DESIGN REVIEWS.
3. DEVELOPMENT OF INITIATIVES: _ INCREASE VOLUMES.
_ PILOT PROJECTS ON HIGHER AXLE LOADS. _ IMPROVE THROUGHPUTS.
4. EXPERIENCE GAINED.
5. CONCLUSIONS.
8/2/2019 Grfc2007 Tk2 Mr.rakesh
3/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 3
GROWTHCORE INFRASTRUCTURE INDUSTRY IN INDIA COMPRISES :
CRUDE, REFINED PETROLEUM PRODUCTS, COAL,
ELECTRICITY, STEEL AND CEMENT.
ON IR ABOUT 75% OF FREIGHT COMPRISES COAL, STEELCEMENT AND PETROLEUM PRODUCTS
GROWTH OF THESE 05-06 06-07
5.8% 8.4%
GDP GROWTH 9% 9.2%
INFLATION 4.4% 5.12
8/2/2019 Grfc2007 Tk2 Mr.rakesh
4/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 4
TREND OF EARNING 0N IR
0
2
4
6
8
10
12
14
16
2001-
02
2002-3 2003-4 2004-5 2005-6
%ANNUAL GROWYH
8/2/2019 Grfc2007 Tk2 Mr.rakesh
5/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 5
TRACK UTILISATION
Increase in Traffic DensityTraffic Density GMTKM per Running Track KM
15.3515.55
16.34
16.85
17.46
18.34
18.83
15
15.5
16
16.5
17
17.5
18
18.5
19
19.5
1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06
Year
AnnualGMT
8/2/2019 Grfc2007 Tk2 Mr.rakesh
6/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 6
Freight Projections
Freight Projections
600
650
700
750
800
850
900
950
1000
1050
1100
2006-07 2007-08 2008-09 2009-10 2010-11
Year
GMT
Scenario1
Scenario2
Scenario3
Scenario4
8/2/2019 Grfc2007 Tk2 Mr.rakesh
7/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 7
Track structureconventional modern
RAILS 90R/52KG 72UTS 52/60KG 90UTS HHON CURVES
SLEEPERS WOOD/STEEL/CST PRC1310/1540 /PKM 1540/1660/PKM
FITTINGS RIGID ELASTIC
BALLAST 150/200mm 250/300mm
JOINTS FISH PLATED WELDED WITH SEJs
SWITCHES STRAIGHT CURVED/TWS
XINGS BUILT CMS
SUBBALLAST NONE DESIGNED BLANKET
MAINTENANCE MANUAL MECHANISED
8/2/2019 Grfc2007 Tk2 Mr.rakesh
8/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 8
CAPACITY AND DESIGN
REVIEWS
TRACK MODULAS
RAIL STRESSES
SLEEPER DESIGNS
FATIGUE IN RAILS
IMPACT FACTOR
BRIDGES SUPERSTRUCTURE
SUBSTRUCTURE
BEARINGS
8/2/2019 Grfc2007 Tk2 Mr.rakesh
9/43
IR-UIC-GRFC-22/23-03-07 DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 9
Relationship between axleload and rail section
used
45
50
55
60
65
70
75
80
10 15 20 25 30 35Axleload (t)
Rail
Section(kg/m
Survey of current practices, carried out by JRP-2, initiated byWorld Executive Council of UIC indicates the followingrelationship between Rail Section and Axle Load:
Track Structure
8/2/2019 Grfc2007 Tk2 Mr.rakesh
10/43
IR-UIC-GRFC-22/23-03-07 DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 10
Relationship between axleload and rail hardness
(tangent track)
200
250
300
350
400
450
10 15 20 25 30 35
Axleload (t)
RailHardness
(HBN)
The Survey also indicates that rails with Higher BHN arebeing used for higher axle loads:
Track Structure
8/2/2019 Grfc2007 Tk2 Mr.rakesh
11/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 11
Brief History of HAL introduction
Original design of wagons is with 20.32 tonne axle load
Carrying Capacity (CC) of wagons is derived from above axleload and same is stenciled on each wagon
Later Loading Tolerance (LT) was permitted upto 2T
Carrying Capacity has been enhanced by 2T, the PermissibleCarrying Capacity (PCC) thus became CC+2T and total load(TL) including LT as CC+2+2T i.e. axle load as 21.32T
PCC was enhanced further by 2T in November, 2004,universally for all wagons designed for 20.32T axle load andhaving air brake system i.e. TL as CC+4+2T and AL 21.82T
8/2/2019 Grfc2007 Tk2 Mr.rakesh
12/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 12
Pilot Projects
In May 2005, PCC was further enhanced by 4T for BOXNwagons on identified iron ore routes as a Pilot Project forone year i.e. TL as CC+8+2T and AL 22.82T
Following precautions have been taken
Maximum speed restricted to 60 kmph Introduced USFD examination to detect Gauge CornerFatigue (GCF) defects
Planned, installation of in-motion weigh bridges asloading points to prevent over loading
Instrumentation of Bridges, planned, to measure
longitudinal forces and stresses in members Installation of Wheel Impact Load Detectors (WILD) Quarterly review at PHODs level
8/2/2019 Grfc2007 Tk2 Mr.rakesh
13/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
13
Pilot Projects contdIn November, 2005 Pilot Project was extended forCoal routes of CR in BOXN wagons, TL in this
case was kept as CC+6+2T keeping loadability inview (AL 22.32T).
Conditions were same as for CC+8+2T
Pilot Project period extended by one more year
i.e. upto Jun 2007.More routes have been included gradually in boththe above projects, more commodities andwagons have also been included
Presently CC+6+2T is in operation nearly on26000 route kms and CC+8+2T on 5000 kms
8/2/2019 Grfc2007 Tk2 Mr.rakesh
14/43
IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
14
Growth of axle loads
19
19.520
20.5
21
21.5
22
22.5
23
AXLE LOAD
ORE
ORECOAL,CEMENT+ALL COMMODITIES
PASTNOV O4
MAY 05NOV 05
8/2/2019 Grfc2007 Tk2 Mr.rakesh
15/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
15
TRENDS
19
19.5
20
20.5
21
21.5
22
22.5
23
TONNES
ORE
0
2
4
6
8
10
12
14
16
2001-
02
2002-3 2003-4 2004-5 2005-6
%ANNUAL GROWYH
NOV 04MAY 05
8/2/2019 Grfc2007 Tk2 Mr.rakesh
16/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
16
Experience gained from Pilot Project
Rapid wear of points and xingsExcessive wearof rails on curves
Faster crushing of rubber pads
New formation problem locationsRail head pitting because iron ore fall
Increase in cases of wheelscabbing/wheel burnt rails
Increase in rail/weld failures especiallyin weld failures
8/2/2019 Grfc2007 Tk2 Mr.rakesh
17/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
17
WAGON PROBLEMS
There has been increase in wagon
defects.
8/2/2019 Grfc2007 Tk2 Mr.rakesh
18/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
18
Experience from Pilot Project yet to becompleted
Wheel Impact Load Detectors are tobe installed to know the impact loadsand to decide the dynamic coefficient
Longitudinal forces on bridges andstresses in members ofsuperstructure of girder bridges are
yet to be measured
8/2/2019 Grfc2007 Tk2 Mr.rakesh
19/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
19
HAL future scenario
It is envisaged that 25T axle load operation willstart from this year (2006-07)
Presently in BOBS wagons which are designed for22.9T axle load
Future plans
Nearly 7000 route km on iron routes havebeen identified for upgradation for 25T AL
Nearly 4200 route km identified as feederroutes to DFC. These will also be upgraded for25T AL
8/2/2019 Grfc2007 Tk2 Mr.rakesh
20/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
20
Provision in XIth five year plan
Age cum condition basis renewals are planned(costing Rs 23085cr)
Upgradation of iron ore routes and feeder routesto DFC costing Rs 1800 cr are also planned
8/2/2019 Grfc2007 Tk2 Mr.rakesh
21/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
21
Integrated Railway Modernization Plan
Modernisation of track structure along with track
renewals
Cent percent mechanisation of track maintenanceand renewal activities
Improved and mechanised USFD technology(SPURT cars)
Data loggers on existing SRT and DRT
Improved AT weld technology
8/2/2019 Grfc2007 Tk2 Mr.rakesh
22/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
22
STRATEGY FOR THE FUTURE
Improve through put
Take care of Pilot Project experiences
Create future capacity.
Wagon design.
8/2/2019 Grfc2007 Tk2 Mr.rakesh
23/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
23
IMPROVE THROUGH PUTS
1. FASTER TRAINS ON EXISTING SECTIONS
2. HIGHER SPEEDS ON TURNOUTS
3. REMOVAL OF PERMANENT SPEED RESTRICTIONS PROGRAMME
4. MECHANISATION OF TRACK WORKS AND REDUCTION OF
WORK SITES
5. HIGHER SPEEDS AFTER WORKINCREASE OF TRAIN PATHS
6. REDUCTION IN NUMBER OF LEVEL CROSSINGS
7. GO FOR NEED BASED MAINTENANCE-IMLPEMENT ON LINETRACK AND BRIDGES MANAGEMENT INFORMATION SYSTEMS
8. IMPROVE TERMINAL HANDLING FACILITIES.
Take care Pilot Project experiences
8/2/2019 Grfc2007 Tk2 Mr.rakesh
24/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
24
Take care Pilot Project experiences
AT welds reduced,
Roll longer rails
Thick Web Switches
Cleaner rails
Introduce Rail grinding
Contd
8/2/2019 Grfc2007 Tk2 Mr.rakesh
25/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
25
Contd---Proper power needs to be provided for trains toprevent cases of stalling/scabbing etc
To identify these trains from Normal goods trainsspecial name (SUMO) is being given
Induct new materials and technology
Improve wagon designs
Redo Feeder routes for above wagons and DFC
Need Based Track maintenance and 6 hrpossessions for track works
8/2/2019 Grfc2007 Tk2 Mr.rakesh
26/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
26
Create Future Capacity
Construction of Dedicated FreightCorridor.
Eastern
Western
-Expected Investment Rs 30,000 cr
-Expected period ofcompletion 5 yrs from start dt
PROPOSED FREIGHT
8/2/2019 Grfc2007 Tk2 Mr.rakesh
27/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
27
PROPOSED FREIGHT
CORRIDORS
MUMBAI
DELHI
CHENNAI
KOLKATA
LUDHIANA
VIJAYAWADA
Sanctioned projects
VASCO
Dedicated Freight Corridors
8/2/2019 Grfc2007 Tk2 Mr.rakesh
28/43
IR-UIC-GRFC-22/23-03-07DELHI
DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR
28
Dedicated Freight Corridors-Planning Parameters
First Phase Eastern and WesternRoutes
2700 km Double Line Corridor
Fit for Speeds up to 100 KmphCapable of 30-32.5 Tonnes Axle Load
Capable of Double Stack Containeroperation.
Computerized Train Control System
8/2/2019 Grfc2007 Tk2 Mr.rakesh
29/43
IR-UIC-GRFC-22/23-03-07
DELHIDO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
29
Dedicated Freight Corridors- PlanningParameters
Adoption of liberal MMD
Tare to pay load ratio of 4-5Longer loops of 1.5 km
Feeder routes fit for 25 tonne axle load
Mineral routes for 25 tonne axle load
Wagon design
8/2/2019 Grfc2007 Tk2 Mr.rakesh
30/43
IR-UIC-GRFC-22/23-03-07
DELHIDO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
30
Wagon design
Presently most of the wagons are designed with20.32T AL
Wagons are being designed with 22.9T and 25TAL
To maximise the output track loading density(TLD) is being enhanced (from
8/2/2019 Grfc2007 Tk2 Mr.rakesh
31/43
IR-UIC-GRFC-22/23-03-07 DELHI DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
31
MINIMUM HEIGHT FOR CONTINUOUS
COVERING IN PASSENGER STATIONS.
Maximum Moving Dimension
Fixed Structure For Non Electrifiction
Fixed Structure For Electrifiction
STRUCTURE
SCHEDULE I,EXISTING WORK PROFILE
SCHEDULE I NEW WORKS PROFILE
MAX HEIGHT FOR A LOW PASSENGER PLATFORM
MAX & MIN HEIGHT FOR A HIGH PASSENGER PLATFORM
MAX HEIGHT FOR GOODS PLATFORM
LEVEL
MINIMUM HEIGHT WHERE ELECTRICTRACTION IS IN USE OR LIKELY TO BE
INTRODUCED [ITEM 10 (II)]
MINIMU
MFIXED
Infringements onFeeder Routes, InsideStations
8/2/2019 Grfc2007 Tk2 Mr.rakesh
32/43
IR-UIC-GRFC-22/23-03-07 DELHI DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
32
Proposed MMDfor Dedicated
freightCorridor
9 FEET 6 INCHCONTAINERHT =6.81mtWHEEL DIA 860mm?
8/2/2019 Grfc2007 Tk2 Mr.rakesh
33/43
8/2/2019 Grfc2007 Tk2 Mr.rakesh
34/43
IR-UIC-GRFC-22/23-03-07 DELHI DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
34
SCHEDULE I,EXISTING WORK PROFILE
MINIMUM HEIGHT WHERE ELECTRICTRACTION IS IN USE OR LIKELY TO BE
INTRODUCED
FIXED STRUCTURE FOR
NON-ELECTRIFIED TERRITORY
Proposed SOD forDouble StackContainers on FeederRoutes
7300
7300
Clearance forElectrificationis yet to bedecided?
CONCLUSION
8/2/2019 Grfc2007 Tk2 Mr.rakesh
35/43
IR-UIC-GRFC-22/23-03-07
DELHI
DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
35
CONCLUSION
1. PENDING COMPLETE VALIDATION OF PILOT PROJECTS PATHCHOSEN APPEARS CORRECT
2. CONSOLIDATE PILOT PROJECT RESULTS AND PREPARE FUTUREACTION PLAN
3. QUICK INDUCTION OF TRIED AND TESTED TECHNOLOGY
4. PUT IN PLACE QUICKLY CIVIL ENGINEERING MIS ON LINESYSTEMS.
5. DEVELOP NEW DESIGNS FOR COSTRUCTION, OPERATION ANDMAINTENANCE OF DEDICATED FREIGHT CORRIDOR AND FEEDERROUTES.
6. PLAN AND MAKE AVAILABLE RESOURCE INPUTS FOR ABOVE.
8/2/2019 Grfc2007 Tk2 Mr.rakesh
36/43
IR-UIC-GRFC-22/23-03-07
DELHI
DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
36
Thank you for listening
8/2/2019 Grfc2007 Tk2 Mr.rakesh
37/43
IR-UIC-GRFC-22/23-03-07
DELHI
DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
37
Track structure design
For 25T AL operation following areconsidered
Rails 60kg 90UTS (HH on curves)
Sleepers PSC with 1660nos per kmFastening- elatsic fastening (ERC, GRP,
liners)
P&C - fan shaped (PSC) layoutcurved switches (TWSprefered)
Ballast cushion- 300mm, 350mm
(recommended)
8/2/2019 Grfc2007 Tk2 Mr.rakesh
38/43
IR-UIC-GRFC-22/23-03-07
DELHI
DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
38
Track structure design
To achieve economy existing trackstructure consisting of following trackstructure is considered adequate for
speeds upto 60kmphRails 52kg 90UTS
Sleepers PSC with 1540 nos per km
Ballast cushion-250mm
8/2/2019 Grfc2007 Tk2 Mr.rakesh
39/43
IR-UIC-GRFC-22/23-03-07
DELHI
DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
39
Structure of presentation
Track structure
Track modulus and Rail stresses
Brief history of HAL
HAL operationPlanning in XIth five year plan and IRMP
Wagon design
Experience gained
Track structure design for 25T AL
Track Management System
8/2/2019 Grfc2007 Tk2 Mr.rakesh
40/43
IR-UIC-GRFC-22/23-03-07
DELHI
DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
40
Track modulus
As the track structure has undergonelot of changes, it become necessaryto reassess the track modulus
Studies were conducted by RDSOand based on results track modulushas been modified as under
8/2/2019 Grfc2007 Tk2 Mr.rakesh
41/43
IR-UIC-GRFC-22/23-03-07
DELHI
DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
41
Rail stresses
Based on modified track modulus,track stresses have been calculated
Different methodology is adopted tofind suitability of existinginfrastructure and design for newstructures
8/2/2019 Grfc2007 Tk2 Mr.rakesh
42/43
IR-UIC-GRFC-22/23-03-07
DELHI
DO NOT USE WITHOUT PERMISSION OF
AUTHOR AND IR
42
Track structure change
Change in track structure could bepossible due to creation of SRSF fund(2001-02) and sufficient provision offunds under DRF thereafter
In previous 6-7 years large number oftrack renewal works have beenexecuted.
Modern track structure is provided alonwith renewals, depending on routeclassification and annual traffic density
Especially during Primary renewals
8/2/2019 Grfc2007 Tk2 Mr.rakesh
43/43
IR-UIC-GRFC-22/23-03-07 DO NOT USE WITHOUT PERMISSION OF 43
Track Mangement System
IR has introduced Track ManagementSystem (TMS) quite early (1990-91)
It was introduced as Pilot Project
It however could not be implementedfully
Lot of changes has taken place in ITand communication technology, sincethen
Now proposes to introduce TMS cum