Grfc2007 Tk2 Mr.rakesh

Embed Size (px)

Citation preview

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    1/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 1

    INTRODUCTION OF

    HEAVY AXLE LOAD OPERATION ONINDIAN RAILWAYS

    Presentation

    By

    Rakesh Chopra and H L Suthar

    ADDITIONAL MEMBER,and DIRECTOR

    Indian Railway Board

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    2/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 2

    STRUCTURE OF PRESENTATION

    1. GROWTH: _ NATIONAL.

    _ INDIAN RAILWAYS.

    2. INITIATIVES:_ EXISTING TRACK AND STRUCTURES._ MODERNISATION OF TRACK AND STRUCTURES.

    _ RESIDUAL CAPACITY AND DESIGN REVIEWS.

    3. DEVELOPMENT OF INITIATIVES: _ INCREASE VOLUMES.

    _ PILOT PROJECTS ON HIGHER AXLE LOADS. _ IMPROVE THROUGHPUTS.

    4. EXPERIENCE GAINED.

    5. CONCLUSIONS.

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    3/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 3

    GROWTHCORE INFRASTRUCTURE INDUSTRY IN INDIA COMPRISES :

    CRUDE, REFINED PETROLEUM PRODUCTS, COAL,

    ELECTRICITY, STEEL AND CEMENT.

    ON IR ABOUT 75% OF FREIGHT COMPRISES COAL, STEELCEMENT AND PETROLEUM PRODUCTS

    GROWTH OF THESE 05-06 06-07

    5.8% 8.4%

    GDP GROWTH 9% 9.2%

    INFLATION 4.4% 5.12

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    4/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 4

    TREND OF EARNING 0N IR

    0

    2

    4

    6

    8

    10

    12

    14

    16

    2001-

    02

    2002-3 2003-4 2004-5 2005-6

    %ANNUAL GROWYH

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    5/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 5

    TRACK UTILISATION

    Increase in Traffic DensityTraffic Density GMTKM per Running Track KM

    15.3515.55

    16.34

    16.85

    17.46

    18.34

    18.83

    15

    15.5

    16

    16.5

    17

    17.5

    18

    18.5

    19

    19.5

    1999-00 2000-01 2001-02 2002-03 2003-04 2004-05 2005-06

    Year

    AnnualGMT

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    6/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 6

    Freight Projections

    Freight Projections

    600

    650

    700

    750

    800

    850

    900

    950

    1000

    1050

    1100

    2006-07 2007-08 2008-09 2009-10 2010-11

    Year

    GMT

    Scenario1

    Scenario2

    Scenario3

    Scenario4

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    7/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 7

    Track structureconventional modern

    RAILS 90R/52KG 72UTS 52/60KG 90UTS HHON CURVES

    SLEEPERS WOOD/STEEL/CST PRC1310/1540 /PKM 1540/1660/PKM

    FITTINGS RIGID ELASTIC

    BALLAST 150/200mm 250/300mm

    JOINTS FISH PLATED WELDED WITH SEJs

    SWITCHES STRAIGHT CURVED/TWS

    XINGS BUILT CMS

    SUBBALLAST NONE DESIGNED BLANKET

    MAINTENANCE MANUAL MECHANISED

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    8/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 8

    CAPACITY AND DESIGN

    REVIEWS

    TRACK MODULAS

    RAIL STRESSES

    SLEEPER DESIGNS

    FATIGUE IN RAILS

    IMPACT FACTOR

    BRIDGES SUPERSTRUCTURE

    SUBSTRUCTURE

    BEARINGS

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    9/43

    IR-UIC-GRFC-22/23-03-07 DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 9

    Relationship between axleload and rail section

    used

    45

    50

    55

    60

    65

    70

    75

    80

    10 15 20 25 30 35Axleload (t)

    Rail

    Section(kg/m

    Survey of current practices, carried out by JRP-2, initiated byWorld Executive Council of UIC indicates the followingrelationship between Rail Section and Axle Load:

    Track Structure

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    10/43

    IR-UIC-GRFC-22/23-03-07 DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 10

    Relationship between axleload and rail hardness

    (tangent track)

    200

    250

    300

    350

    400

    450

    10 15 20 25 30 35

    Axleload (t)

    RailHardness

    (HBN)

    The Survey also indicates that rails with Higher BHN arebeing used for higher axle loads:

    Track Structure

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    11/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 11

    Brief History of HAL introduction

    Original design of wagons is with 20.32 tonne axle load

    Carrying Capacity (CC) of wagons is derived from above axleload and same is stenciled on each wagon

    Later Loading Tolerance (LT) was permitted upto 2T

    Carrying Capacity has been enhanced by 2T, the PermissibleCarrying Capacity (PCC) thus became CC+2T and total load(TL) including LT as CC+2+2T i.e. axle load as 21.32T

    PCC was enhanced further by 2T in November, 2004,universally for all wagons designed for 20.32T axle load andhaving air brake system i.e. TL as CC+4+2T and AL 21.82T

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    12/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR 12

    Pilot Projects

    In May 2005, PCC was further enhanced by 4T for BOXNwagons on identified iron ore routes as a Pilot Project forone year i.e. TL as CC+8+2T and AL 22.82T

    Following precautions have been taken

    Maximum speed restricted to 60 kmph Introduced USFD examination to detect Gauge CornerFatigue (GCF) defects

    Planned, installation of in-motion weigh bridges asloading points to prevent over loading

    Instrumentation of Bridges, planned, to measure

    longitudinal forces and stresses in members Installation of Wheel Impact Load Detectors (WILD) Quarterly review at PHODs level

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    13/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    13

    Pilot Projects contdIn November, 2005 Pilot Project was extended forCoal routes of CR in BOXN wagons, TL in this

    case was kept as CC+6+2T keeping loadability inview (AL 22.32T).

    Conditions were same as for CC+8+2T

    Pilot Project period extended by one more year

    i.e. upto Jun 2007.More routes have been included gradually in boththe above projects, more commodities andwagons have also been included

    Presently CC+6+2T is in operation nearly on26000 route kms and CC+8+2T on 5000 kms

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    14/43

    IR-UIC-GRFC-22/23-03-07DELHI DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    14

    Growth of axle loads

    19

    19.520

    20.5

    21

    21.5

    22

    22.5

    23

    AXLE LOAD

    ORE

    ORECOAL,CEMENT+ALL COMMODITIES

    PASTNOV O4

    MAY 05NOV 05

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    15/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    15

    TRENDS

    19

    19.5

    20

    20.5

    21

    21.5

    22

    22.5

    23

    TONNES

    ORE

    0

    2

    4

    6

    8

    10

    12

    14

    16

    2001-

    02

    2002-3 2003-4 2004-5 2005-6

    %ANNUAL GROWYH

    NOV 04MAY 05

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    16/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    16

    Experience gained from Pilot Project

    Rapid wear of points and xingsExcessive wearof rails on curves

    Faster crushing of rubber pads

    New formation problem locationsRail head pitting because iron ore fall

    Increase in cases of wheelscabbing/wheel burnt rails

    Increase in rail/weld failures especiallyin weld failures

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    17/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    17

    WAGON PROBLEMS

    There has been increase in wagon

    defects.

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    18/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    18

    Experience from Pilot Project yet to becompleted

    Wheel Impact Load Detectors are tobe installed to know the impact loadsand to decide the dynamic coefficient

    Longitudinal forces on bridges andstresses in members ofsuperstructure of girder bridges are

    yet to be measured

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    19/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    19

    HAL future scenario

    It is envisaged that 25T axle load operation willstart from this year (2006-07)

    Presently in BOBS wagons which are designed for22.9T axle load

    Future plans

    Nearly 7000 route km on iron routes havebeen identified for upgradation for 25T AL

    Nearly 4200 route km identified as feederroutes to DFC. These will also be upgraded for25T AL

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    20/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    20

    Provision in XIth five year plan

    Age cum condition basis renewals are planned(costing Rs 23085cr)

    Upgradation of iron ore routes and feeder routesto DFC costing Rs 1800 cr are also planned

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    21/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    21

    Integrated Railway Modernization Plan

    Modernisation of track structure along with track

    renewals

    Cent percent mechanisation of track maintenanceand renewal activities

    Improved and mechanised USFD technology(SPURT cars)

    Data loggers on existing SRT and DRT

    Improved AT weld technology

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    22/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    22

    STRATEGY FOR THE FUTURE

    Improve through put

    Take care of Pilot Project experiences

    Create future capacity.

    Wagon design.

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    23/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    23

    IMPROVE THROUGH PUTS

    1. FASTER TRAINS ON EXISTING SECTIONS

    2. HIGHER SPEEDS ON TURNOUTS

    3. REMOVAL OF PERMANENT SPEED RESTRICTIONS PROGRAMME

    4. MECHANISATION OF TRACK WORKS AND REDUCTION OF

    WORK SITES

    5. HIGHER SPEEDS AFTER WORKINCREASE OF TRAIN PATHS

    6. REDUCTION IN NUMBER OF LEVEL CROSSINGS

    7. GO FOR NEED BASED MAINTENANCE-IMLPEMENT ON LINETRACK AND BRIDGES MANAGEMENT INFORMATION SYSTEMS

    8. IMPROVE TERMINAL HANDLING FACILITIES.

    Take care Pilot Project experiences

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    24/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    24

    Take care Pilot Project experiences

    AT welds reduced,

    Roll longer rails

    Thick Web Switches

    Cleaner rails

    Introduce Rail grinding

    Contd

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    25/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    25

    Contd---Proper power needs to be provided for trains toprevent cases of stalling/scabbing etc

    To identify these trains from Normal goods trainsspecial name (SUMO) is being given

    Induct new materials and technology

    Improve wagon designs

    Redo Feeder routes for above wagons and DFC

    Need Based Track maintenance and 6 hrpossessions for track works

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    26/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    26

    Create Future Capacity

    Construction of Dedicated FreightCorridor.

    Eastern

    Western

    -Expected Investment Rs 30,000 cr

    -Expected period ofcompletion 5 yrs from start dt

    PROPOSED FREIGHT

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    27/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    27

    PROPOSED FREIGHT

    CORRIDORS

    MUMBAI

    DELHI

    CHENNAI

    KOLKATA

    LUDHIANA

    VIJAYAWADA

    Sanctioned projects

    VASCO

    Dedicated Freight Corridors

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    28/43

    IR-UIC-GRFC-22/23-03-07DELHI

    DO NOT USE WITHOUT PERMISSION OFAUTHOR AND IR

    28

    Dedicated Freight Corridors-Planning Parameters

    First Phase Eastern and WesternRoutes

    2700 km Double Line Corridor

    Fit for Speeds up to 100 KmphCapable of 30-32.5 Tonnes Axle Load

    Capable of Double Stack Containeroperation.

    Computerized Train Control System

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    29/43

    IR-UIC-GRFC-22/23-03-07

    DELHIDO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    29

    Dedicated Freight Corridors- PlanningParameters

    Adoption of liberal MMD

    Tare to pay load ratio of 4-5Longer loops of 1.5 km

    Feeder routes fit for 25 tonne axle load

    Mineral routes for 25 tonne axle load

    Wagon design

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    30/43

    IR-UIC-GRFC-22/23-03-07

    DELHIDO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    30

    Wagon design

    Presently most of the wagons are designed with20.32T AL

    Wagons are being designed with 22.9T and 25TAL

    To maximise the output track loading density(TLD) is being enhanced (from

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    31/43

    IR-UIC-GRFC-22/23-03-07 DELHI DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    31

    MINIMUM HEIGHT FOR CONTINUOUS

    COVERING IN PASSENGER STATIONS.

    Maximum Moving Dimension

    Fixed Structure For Non Electrifiction

    Fixed Structure For Electrifiction

    STRUCTURE

    SCHEDULE I,EXISTING WORK PROFILE

    SCHEDULE I NEW WORKS PROFILE

    MAX HEIGHT FOR A LOW PASSENGER PLATFORM

    MAX & MIN HEIGHT FOR A HIGH PASSENGER PLATFORM

    MAX HEIGHT FOR GOODS PLATFORM

    LEVEL

    MINIMUM HEIGHT WHERE ELECTRICTRACTION IS IN USE OR LIKELY TO BE

    INTRODUCED [ITEM 10 (II)]

    MINIMU

    MFIXED

    Infringements onFeeder Routes, InsideStations

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    32/43

    IR-UIC-GRFC-22/23-03-07 DELHI DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    32

    Proposed MMDfor Dedicated

    freightCorridor

    9 FEET 6 INCHCONTAINERHT =6.81mtWHEEL DIA 860mm?

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    33/43

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    34/43

    IR-UIC-GRFC-22/23-03-07 DELHI DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    34

    SCHEDULE I,EXISTING WORK PROFILE

    MINIMUM HEIGHT WHERE ELECTRICTRACTION IS IN USE OR LIKELY TO BE

    INTRODUCED

    FIXED STRUCTURE FOR

    NON-ELECTRIFIED TERRITORY

    Proposed SOD forDouble StackContainers on FeederRoutes

    7300

    7300

    Clearance forElectrificationis yet to bedecided?

    CONCLUSION

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    35/43

    IR-UIC-GRFC-22/23-03-07

    DELHI

    DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    35

    CONCLUSION

    1. PENDING COMPLETE VALIDATION OF PILOT PROJECTS PATHCHOSEN APPEARS CORRECT

    2. CONSOLIDATE PILOT PROJECT RESULTS AND PREPARE FUTUREACTION PLAN

    3. QUICK INDUCTION OF TRIED AND TESTED TECHNOLOGY

    4. PUT IN PLACE QUICKLY CIVIL ENGINEERING MIS ON LINESYSTEMS.

    5. DEVELOP NEW DESIGNS FOR COSTRUCTION, OPERATION ANDMAINTENANCE OF DEDICATED FREIGHT CORRIDOR AND FEEDERROUTES.

    6. PLAN AND MAKE AVAILABLE RESOURCE INPUTS FOR ABOVE.

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    36/43

    IR-UIC-GRFC-22/23-03-07

    DELHI

    DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    36

    Thank you for listening

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    37/43

    IR-UIC-GRFC-22/23-03-07

    DELHI

    DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    37

    Track structure design

    For 25T AL operation following areconsidered

    Rails 60kg 90UTS (HH on curves)

    Sleepers PSC with 1660nos per kmFastening- elatsic fastening (ERC, GRP,

    liners)

    P&C - fan shaped (PSC) layoutcurved switches (TWSprefered)

    Ballast cushion- 300mm, 350mm

    (recommended)

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    38/43

    IR-UIC-GRFC-22/23-03-07

    DELHI

    DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    38

    Track structure design

    To achieve economy existing trackstructure consisting of following trackstructure is considered adequate for

    speeds upto 60kmphRails 52kg 90UTS

    Sleepers PSC with 1540 nos per km

    Ballast cushion-250mm

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    39/43

    IR-UIC-GRFC-22/23-03-07

    DELHI

    DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    39

    Structure of presentation

    Track structure

    Track modulus and Rail stresses

    Brief history of HAL

    HAL operationPlanning in XIth five year plan and IRMP

    Wagon design

    Experience gained

    Track structure design for 25T AL

    Track Management System

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    40/43

    IR-UIC-GRFC-22/23-03-07

    DELHI

    DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    40

    Track modulus

    As the track structure has undergonelot of changes, it become necessaryto reassess the track modulus

    Studies were conducted by RDSOand based on results track modulushas been modified as under

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    41/43

    IR-UIC-GRFC-22/23-03-07

    DELHI

    DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    41

    Rail stresses

    Based on modified track modulus,track stresses have been calculated

    Different methodology is adopted tofind suitability of existinginfrastructure and design for newstructures

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    42/43

    IR-UIC-GRFC-22/23-03-07

    DELHI

    DO NOT USE WITHOUT PERMISSION OF

    AUTHOR AND IR

    42

    Track structure change

    Change in track structure could bepossible due to creation of SRSF fund(2001-02) and sufficient provision offunds under DRF thereafter

    In previous 6-7 years large number oftrack renewal works have beenexecuted.

    Modern track structure is provided alonwith renewals, depending on routeclassification and annual traffic density

    Especially during Primary renewals

  • 8/2/2019 Grfc2007 Tk2 Mr.rakesh

    43/43

    IR-UIC-GRFC-22/23-03-07 DO NOT USE WITHOUT PERMISSION OF 43

    Track Mangement System

    IR has introduced Track ManagementSystem (TMS) quite early (1990-91)

    It was introduced as Pilot Project

    It however could not be implementedfully

    Lot of changes has taken place in ITand communication technology, sincethen

    Now proposes to introduce TMS cum