Wiring Terminals Inside Boiler
230VIN
230VOUT
FR FS LR LR
LNLN LN LN LN
Optional 240VAC Frost Thermostat for Pipework in unheated air space on External Boilers
Frost ThermostatPipe Thermostat
Greenstar Heatslave II Combi ErP1H-R-P
All electrical work should be carried out by a registered engineer. Wiring must comply with the latest IET wiring regulations. Isolate the mains electricity supply before starting any work and observe all relevant safety precautions. Refer to all relevant product installation manuals for safety and installation instructions. Whilst it is always our intention to fully assist, it is essential to recognise that all information given by the company is provided in good faith and based upon the information available. Connection labels may not match those of the products installed on site. We recommend that advice should always be checked with your installer, electrician or the manufacturer of the product in question. Consequently, the company cannot be held responsible for any liability relating to the use or repetition of such information or part thereof. In addition, whilst making every reasonable effort to monitor the performance and quality of our supply, installation and service network, we do not accept responsibility for the workmanship or operation of any third party company.
WG HS-C-1H-R-P a (2016/12)
Programmable Room Thermostat only
L LIVE N NEUTRAL EARTHE
The following labels and those like them are used to denote generic connections (such as the live supply to components) in order to simplify the diagram:
230V MainsVoltage
Double PoleFused Spur
1 2 3 4 5 7 8 9 106
Legend:LNLRECSDMCH DHW D
= Live Supply= Neutral Supply= Live Return= Earth= Common= Satisfied= Demand= Motor= Central Heating Demand= Hot Water Demand
Programmable ThermostatThe Link between the live (L) and common (C)
may already be fitted as part of the programmablethermostat, if not then a link must be wired in.
N L C NC NO
Wiring Centre
LN
E
EL N
LN
Wiring Terminals Inside Boiler
230VIN
230VOUT
FR FS LR LR
LNLN LN LN LN
Greenstar Heatslave II Combi ErP2H-R-E
All electrical work should be carried out by a registered engineer. Wiring must comply with the latest IET wiring regulations. Isolate the mains electricity supply before starting any work and observe all relevant safety precautions. Refer to all relevant product installation manuals for safety and installation instructions. Whilst it is always our intention to fully assist, it is essential to recognise that all information given by the company is provided in good faith and based upon the information available. Connection labels may not match those of the products installed on site. We recommend that advice should always be checked with your installer, electrician or the manufacturer of the product in question. Consequently, the company cannot be held responsible for any liability relating to the use or repetition of such information or part thereof. In addition, whilst making every reasonable effort to monitor the performance and quality of our supply, installation and service network, we do not accept responsibility for the workmanship or operation of any third party company.
WG HS-C-2H-R-E a (2016/12)
2 Heating Zones
L LIVE N NEUTRAL EARTHE
The following labels and those like them are used to denote generic connections (such as the live supply to components) in order to simplify the diagram:
Programmer
~ ~
Room Thermostat 1
CH1 D
Heating Zone 2 Valve
HeatingZone 1 Valve
230V MainsVoltage
Double PoleFused Spur
1 2 3 4 5 7 8 9 106
C D
Legend:LNLRECSDMCH DHW D
= Live Supply= Neutral Supply= Live Return= Earth= Common= Satisfied= Demand= Motor= Central Heating Demand= Hot Water Demand
CH2 D
Room Thermostat 2
C D
Wiring Centre
LN
E
EL N
N
L
N N
EN
L EN
L
Wiring Terminals Inside Boiler
230VIN
230VOUT
FR FS LR LR
LNLN LN LN LN
Greenstar Heatslave II Combi ErP2H-R-I
All electrical work should be carried out by a registered engineer. Wiring must comply with the latest IET wiring regulations. Isolate the mains electricity supply before starting any work and observe all relevant safety precautions. Refer to all relevant product installation manuals for safety and installation instructions. Whilst it is always our intention to fully assist, it is essential to recognise that all information given by the company is provided in good faith and based upon the information available. Connection labels may not match those of the products installed on site. We recommend that advice should always be checked with your installer, electrician or the manufacturer of the product in question. Consequently, the company cannot be held responsible for any liability relating to the use or repetition of such information or part thereof. In addition, whilst making every reasonable effort to monitor the performance and quality of our supply, installation and service network, we do not accept responsibility for the workmanship or operation of any third party company.
WG HS-C-2H-R-I a (2016/12)
2 Heating Zones (Integral Programmer)
L LIVE N NEUTRAL EARTHE
The following labels and those like them are used to denote generic connections (such as the live supply to components) in order to simplify the diagram:
~ ~
Room Thermostat 1
HeatingZone Valve 2
HeatingZone Valve 1
230V MainsVoltage
Double PoleFused Spur
1 2 3 4 5 7 8 9 106
C D
Legend:LNLRECSDMCH DHW D
= Live Supply= Neutral Supply= Live Return= Earth= Common= Satisfied= Demand= Motor= Central Heating Demand= Hot Water Demand
Room Thermostat 2
C D
Wiring Centre
LN
E
EL N
EN
L EN
L
N N
Wiring Terminals Inside Boiler
230VIN
230VOUT
FR FS LR LR
LNLN LN LN LN
Greenstar Heatslave II Combi ErP3H-U-E
All electrical work should be carried out by a registered engineer. Wiring must comply with the latest IET wiring regulations. Isolate the mains electricity supply before starting any work and observe all relevant safety precautions. Refer to all relevant product installation manuals for safety and installation instructions. Whilst it is always our intention to fully assist, it is essential to recognise that all information given by the company is provided in good faith and based upon the information available. Connection labels may not match those of the products installed on site. We recommend that advice should always be checked with your installer, electrician or the manufacturer of the product in question. Consequently, the company cannot be held responsible for any liability relating to the use or repetition of such information or part thereof. In addition, whilst making every reasonable effort to monitor the performance and quality of our supply, installation and service network, we do not accept responsibility for the workmanship or operation of any third party company.
WG HS-C-3H-U-E a (2016/12)
3 Heating Zones (Underfloor Heating)
L LIVE N NEUTRAL EARTHE
The following labels and those like them are used to denote generic connections (such as the live supply to components) in order to simplify the diagram:
Programmer
~ ~
Room Thermostat 1
CH1 D CH2 D
HeatingZone Valve 2
HeatingZone Valve 1
230V MainsVoltage
Double PoleFused Spur
1 2 3 4 5 7 8 9 106
C D
Legend:LNLRECSDMCH DHW D
= Live Supply= Neutral Supply= Live Return= Earth= Common= Satisfied= Demand= Motor= Central Heating Demand= Hot Water Demand
Room Thermostat 2
C D
Wiring Centre
Underfloor Wiring Centre
Timer Demand
~
UFHZone Valve
LN
E
L N E
EL N
EL N
N
L
EN
L EN
L
NN
EN
L
Wiring Terminals Inside Boiler
Legend:LNLRFR FS ECSDMCH DHW D
= Live Supply= Neutral Supply= Live Return= Frost Return= Frost Supply = Earth= Common= Satisfied= Demand= Motor= Central Heating Demand= Hot Water Demand
230VIN
230VOUT
FR FS LR LR
LNLN LN LN LN
Greenstar Heatslave II Combi ErP------FB
All electrical work should be carried out by a registered engineer. Wiring must comply with the latest IET wiring regulations. Isolate the mains electricity supply before starting any work and observe all relevant safety precautions. Refer to all relevant product installation manuals for safety and installation instructions. Whilst it is always our intention to fully assist, it is essential to recognise that all information given by the company is provided in good faith and based upon the information available. Connection labels may not match those of the products installed on site. We recommend that advice should always be checked with your installer, electrician or the manufacturer of the product in question. Consequently, the company cannot be held responsible for any liability relating to the use or repetition of such information or part thereof. In addition, whilst making every reasonable effort to monitor the performance and quality of our supply, installation and service network, we do not accept responsibility for the workmanship or operation of any third party company.
WG HS-C-------FB a (2016/12)
Frost Protection (to System Bypass)
L LIVE N NEUTRAL EARTHE
The following labels and those like them are used to denote generic connections (such as the live supply to components) in order to simplify the diagram:
230V MainsVoltage
Double PoleFused Spur
ExternalFrost Thermostat
C DReturn
Pipe Thermostat
C D
We recommend that the Frost Thermostat is installed at the coldest location. Frost Thermostat to be set on at 5°C and the Pipe Thermostat to be off at 15°C.
Wiring Terminals Inside Boiler
Legend:LNLRFR FS ECSDMCH DHW D
= Live Supply= Neutral Supply= Live Return= Frost Return= Frost Supply = Earth= Common= Satisfied= Demand= Motor= Central Heating Demand= Hot Water Demand
230VIN
230VOUT
FR FS LR LR
LNLN LN LN LN
230VIN
230VOUT
FR FS LR LR
LNLN LN LN LN
Wiring Terminals Inside Boiler
Greenstar Heatslave II Combi ErP------LLH
All electrical work should be carried out by a registered engineer. Wiring must comply with the latest IET wiring regulations. Isolate the mains electricity supply before starting any work and observe all relevant safety precautions. Refer to all relevant product installation manuals for safety and installation instructions. Whilst it is always our intention to fully assist, it is essential to recognise that all information given by the company is provided in good faith and based upon the information available. Connection labels may not match those of the products installed on site. We recommend that advice should always be checked with your installer, electrician or the manufacturer of the product in question. Consequently, the company cannot be held responsible for any liability relating to the use or repetition of such information or part thereof. In addition, whilst making every reasonable effort to monitor the performance and quality of our supply, installation and service network, we do not accept responsibility for the workmanship or operation of any third party company.
WG HS-C-------LLH a (2016/12)
Cascade boilers with Low Loss Header
L LIVE N NEUTRAL EARTHE
The following labels and those like them are used to denote generic connections (such as the live supply to components) in order to simplify the diagram:
230V MainsVoltage
Double PoleFused Spur
C
NC
Header Limit Thermostat
230V ACDouble Pole Relay
IMPORTANT NOTE:
The Relay should be mountedwithin a suitable electrically safehousing.
C C
NO NC
Coil Neutral
NONC
Coil Live
Example relay shown is a doublePole Mains Voltage Relay. Thisdisables the boilers electrically incase of a fault condition.
Junction Box / Wiring CentreDL N E
Wiring From Zone/s Controls
C C
LN
E
LN
E
LN
E
L N E
N