Green Project Risks

Embed Size (px)

Citation preview

  • 7/29/2019 Green Project Risks

    1/57

    April 10, 2012

    Managing Contract Risks onProjects

  • 7/29/2019 Green Project Risks

    2/57

    April 10, 2012October 14, 2010

    The Rise of Green Buildings

    Project Delivery Methods Mastering Form Agreements

    Drafting and Negotiating Contract Terms

    Understanding Insurance and Bonding

    OverviewManaging Contract Risks on Green Projects

  • 7/29/2019 Green Project Risks

    3/57

    April 10, 2012

    The Rise of Green Building

  • 7/29/2019 Green Project Risks

    4/57

    April 10, 2012

    Rise in Green Building

    Approximately $8 billion worth of greenconstruction in 2006

    Grew to approximately $60 billion in 2010 Estimated $100-140 billion in 2013 Next three years:

    $554 billion to the national economy

    Green jobs will quadruple to 7.9 million By 2015

    Green construction to represent almost half ofnonresidential market McGraw-Hill

  • 7/29/2019 Green Project Risks

    5/57

    April 10, 2012

    Rise in Green Building Regulations

    International Code Council International Green Construction Code released last March

    ASHRAE Standard 189.1 Released last winter - commercial green building standard Replaces Standard 90.1-2007

  • 7/29/2019 Green Project Risks

    6/57

    April 10, 2012

    Project Delivery Methods

    Design-Bid-Build Design-Build Integrated Project Delivery

  • 7/29/2019 Green Project Risks

    7/57

    April 10, 2012

    Why Is Delivery Method Important? Delivery method typically owner-driven

    Considerations:

    Early involvement of contractor and subcontractors?

    Single point responsibility

    Responsibility for overseeing satisfaction of greenobjectives

    Understanding alignment of parties is critical to

    understanding potential risks.

  • 7/29/2019 Green Project Risks

    8/57

    April 10, 2012

    1. Design-Bid-Build (D-B-B)

    2. Design-Build (D-B)

    3. Construction Manager @ Risk

    4. Integrated Project Delivery (IPD)

    Project Delivery Methods

  • 7/29/2019 Green Project Risks

    9/57

    April 10, 2012

    Design-Bid-Build

    Discourages green value engineering

    Less collaborative

    Delayed contractor involvement

    Expensive post-award changes

    Design-Build

    Who is the owners ally/advisor? Single point responsibility

    Owner typically less-involved

    Project Delivery Methods

  • 7/29/2019 Green Project Risks

    10/57

    April 10, 2012

    CM at-Risk

    Requires experienced CM

    Disconnect from some trades

    Integrated Project Delivery

    The ultimate collaborative delivery method

    Early involvement of contractor and trades Value engineering encouraged and facilitated

    Needs strong owner and trusting participants

    Shared incentives for LEED certification

    Project Delivery Methods

  • 7/29/2019 Green Project Risks

    11/57

    April 10, 2012

    Managing Contract Risks on Green Projects

    Mastering Contract Forms

    Drafting and Negotiating Contract TermsUnderstanding Insurance and Bonding

  • 7/29/2019 Green Project Risks

    12/57

    April 10, 2012

    Mastering Contract Forms

  • 7/29/2019 Green Project Risks

    13/57

    April 10, 2012

    Importance of Contract Forms Design and construction organizations are moving

    quickly to prepare standardized forms

    Promote an industry standard

    Increase revenue

    Forms vary significantly from organization toorganization

    Hasty preparation = missing terms and concepts Understanding forms means opportunity to avoid

    green pitfalls

  • 7/29/2019 Green Project Risks

    14/57

    April 10, 2012

    AIA

    B211-2007 Architects Services: Commissioning

    B214-2007 Architects Services: LEED Cert.

    D503-2011 - Guide for Sustainable Projects

    New Sustainable Projects Documents

    ConsensusDOCS

    DOC 310 Green Building Addendum DBIA

    Sustainable Project Goals Exhibit

    Whats Out There?

  • 7/29/2019 Green Project Risks

    15/57

    April 10, 2012

    AIA B211-2007 - Commissioning Covers architects services for commissioning

    Requires architect to: Develop a Commissioning Plan, Design Intent

    Document, and Commissioning Specifications; Review the contractors submittals related to the

    systems to be commissioned;

    Observe and document performance tests;

    Train operators; and

    Prepare a Final Commissioning Report.

    Incorporated into Owner-Architect Agmt.

    Not a stand alone document.

  • 7/29/2019 Green Project Risks

    16/57

    April 10, 2012

    Not a stand alone document

    Covers only LEED Services for architects

    Intended for use with B102-2007 Not for contractors

    Architect Handles Certification Process:

    Conducts Pre-design Workshop

    Creates LEED Certification Plan

    Organize and Manage certification process

    Provide LEED specifications

    AIA B214-2007 LEED Certification

  • 7/29/2019 Green Project Risks

    17/57

    April 10, 2012

    AIA B214-2007 Continued Missing Terms:

    Disclaimer of guarantees or warranties

    Disclaimers of any implied guarantees

    Remedy provisions for failed certification

    Completion

    End of certification process?

  • 7/29/2019 Green Project Risks

    18/57

    April 10, 2012

    D503-2011 Sustainable Projects Guide Not a contract document, exhibit, or addendum

    that can be incorporated in whole into projectcontracts.

    Provides an overview of some of the key legal andcontractual issues that can arise on projects thatincorporate sustainable goals.

    Includes model contract language that can be added

    to: B101-2007 Owner-Architect Agreement A101-Owner-Contractor Agreement

    A201-2007 General Conditions

  • 7/29/2019 Green Project Risks

    19/57

    April 10, 2012

    AIA New Sustainable Projects Documents Set to be released in April or May 2012

    Incorporation of model language into:

    A101-2007 SP Owner/Contractor

    B101-2007 SP Owner/Architect

    A201-2007 SP General Conditions

    C401-2007 SP Architect/Consultant

    A401-2007 SP Contractor/Subcontractor

  • 7/29/2019 Green Project Risks

    20/57

    April 10, 2012

    Not a stand alone contract

    Assumes design-bid-build

    Invents new nomenclature:

    Green Building Facilitator Default = Architect

    Green Measures Physical those incorporated in Plans and Specs as part of

    design. Procedural means and methods in performance of work.

    ConsensusDOCS - 310

  • 7/29/2019 Green Project Risks

    21/57

    April 10, 2012

    ConsensusDOCS - 310 Remedy Provision:

    Moves all tax and financial consequences (i. e. thecost savings) into the category of consequential

    damages that are subject to waivers of such damagesin other construction documents.

    Missing Terms:

    Green Guarantee

    Disclaimer of warranties

    Payment of GBF

    Completion Issues

  • 7/29/2019 Green Project Risks

    22/57

    April 10, 2012

    Not a stand alone contract

    Assumes Design-Build Delivery

    Addresses:

    Green Standard Art. 1

    Art. 4 - Remedies section offers menu of options ifproject fails to meet green goals

    Waiver

    Liquidated damages Limited obligation to cure

    Art. 6 Sub. and Final Completion not contingent oncertification.

    DBIA Sustainable Project Goals Exhibit

  • 7/29/2019 Green Project Risks

    23/57

    April 10, 2012

    Requires retention of independent CommissioningAuthority

    Missing Terms: Payment

    Fails to Adequately Address: Other project delivery options

    Obligation for determining regulatory requirements

    DBIA Sustainable Project Goals Exhibit

  • 7/29/2019 Green Project Risks

    24/57

    April 10, 2012

    Drafting and Negotiating Green Contracts

  • 7/29/2019 Green Project Risks

    25/57

    April 10, 2012

    Conceptual Risks on Green Building Projects

    Impossible Promises Ambiguous/Overlapping Responsibility

    Increased Standard of Care

    Using traditional contract mechanisms andconcepts on a green project

    Lack of precedent

    Benefits well-known and well-documented

    Conceptual Risks

  • 7/29/2019 Green Project Risks

    26/57

    April 10, 2012

    Risks on Green Building Projects Inexperience

    Increased risk of design/construction defectsUnrealized Expectations

    Learning Curve: Products and ConstructionMethods

    Building Performance Issues

    Regional issues not always considered

    Failed Green Certifications

    Green construction is regular construction riskwith a twist.

  • 7/29/2019 Green Project Risks

    27/57

    April 10, 2012

    Lack of Precedent No appellate case law to date.

    Limited LEEDigation: Only a few reported casescontaining green issues:

    Southern Builders v. Shaw Development(MD) Tax credits

    Poor contract drafting

    DestinyUSA (NY)

    Tax/Bond credits, False promises

    ACHRI v. City of Albuquerque(NM) ACHRI sued to prevent ordinance imposing energy eff. stds.

    Gidumal v. Site 16/17 Development(NY)

    Misrepresentation of LEED goals and energy performance

  • 7/29/2019 Green Project Risks

    28/57

    April 10, 2012

    What does Green mean?

    Defining the Green Standard

  • 7/29/2019 Green Project Risks

    29/57

    April 10, 2012

    Defining the Green Standard When you get down to it, whether a work of

    architecture is green is usually a shade of gray Christopher Hawthorne, Architectural Record, April 2008

    Is it an objective standard?

    It should be!

  • 7/29/2019 Green Project Risks

    30/57

    April 10, 2012

    Use Specificity:

    Sample Provision:

    Owner's Desired LEED Certification is LEEDCertification at the Gold Level under the USGBCsLEED forNew Construction Rating System, version3.0 - 2009.

    The LEED Responsibility Matrix [Dated/Version],

    which is attached hereto as Exhibit A identifies thePrerequisites applicable to the Project as well as theCredits the Owner has decided topursuefor theProject.

    Defining the Green Standard

  • 7/29/2019 Green Project Risks

    31/57

    April 10, 2012

    Green Guarantees Owners Perspective:

    A guarantee is ideal (but may not be realistic)

    Designers Perspective: Any contract with the word guarantee creates

    an uninsurable risk and cannot be accepted.

    Contractors Perspective: Do not guarantee any level of certification.

    There are too many factors outside the

    contractors control. At most, contractors should accept responsibility

    for the contractor responsible credits.

  • 7/29/2019 Green Project Risks

    32/57

    April 10, 2012

    Green Guarantees Often guarantees are not express or clear:

    Example: Southern Builders, Inc. v. Shaw Development LLC Project Specs: Project is designed to comply with a Silver

    Certification Level according to the U.S. Green Building

    Councils Leadership in Energy & Environmental Design (LEEDRating System, as specified in Division 1 Section LEEDRequirements.

    AIA D503 Recommendation A201: 3.5.2 The Contractor shall perform the Sustainable Measures

    required to be performed by the Contractor in accordancewith the Contract Documents, however, nothing contained inthis Section 3.5 shall be construed as a guarantee or warrantyby the Contractor that the Project will achieve the SustainableObjective.

  • 7/29/2019 Green Project Risks

    33/57

    April 10, 2012

    Waiver of Consequential Damages Losses or injuries that do not flow directly and immediately

    from the act of the party, but only from some of theconsequences or results of such act.

    Must be reasonably foreseeable at the time the contract was

    made. Typical examples:

    lost rents, loss of tax credits, damage to reputation, down oridle time, interest and finance charges, material escalationcosts, depreciation, rental costs, additional energy costs, loss of

    productivity and efficiency Waiver must be clear and unmistakable

  • 7/29/2019 Green Project Risks

    34/57

    April 10, 2012

    Waiver of Consequential Damages

    Owners Perspective:

    Try not to waive consequential damages they aretypically owners biggest risk.

    Designers Perspective:

    Insist upon a mutual waiver Standard in AIA forms B101 Owner-Architect

    Contractors Perspective:

    Contractors should insist upon a mutual waiver ongreen projects. Shaw Developmentis a good example ofthe exposure a contractor may face (i.e. tax credits)

  • 7/29/2019 Green Project Risks

    35/57

    April 10, 2012

    Waiver of Consequential DamagesSample provision Notwithstanding anything contained in Project agreements or this

    Rider, the Contractor shall only be responsible for commerciallyreasonable efforts to achieve the LEED credits shown in the LEED

    Responsibility Matrix.

    Contractor is not liable or responsible for the failure of the Project toachieve the Desired LEED Certification or any intended financialand/or environmental benefits.

    Notwithstanding any other provision in Project agreements or thisRider, in the event that the Project fails to achieve the Desired LEEDCertification, the Contractor will not be liable for any special,indirect or consequential damages arising in any manner from suchfailure.

  • 7/29/2019 Green Project Risks

    36/57

    April 10, 2012

    Substantial Completion Owners Perspective:

    Will try to tie certification to substantial completion.

    Designers Perspective:

    LEED Certification is on a different timeline frombuilding completion and occupancy.

    Contractors Perspective:

    Contractors should not allow substantial completion tobe tied to certification. Certification could take monthsand include appeals. This may occur while the owner isoccupying the building and receiving the benefit of itsuse.

  • 7/29/2019 Green Project Risks

    37/57

    April 10, 2012

    Substantial Completion Sample provision:

    Substantial Completion: This provision specifically overrides any and all

    provisions dealing with Substantial Completion inother Contract Documents. Substantial Completion isthe stage in the progress of the Project when theProject or designated portion thereof is sufficientlycomplete so that the Owner can occupy or utilize the

    Project for its intended use. Substantial Completiondoes not depend upon achieving the Desired LEEDCertification.

  • 7/29/2019 Green Project Risks

    38/57

    April 10, 2012

    Final Completion and Payment

    Owners Perspective: Make certification part of final completion.

    Designers Perspective:

    De-couple LEED Certification from final completion bynegotiating additional Post-Completion Phase services. Contractors Perspective:

    Same as substantial completion do not tie finalcompletion to certification. The certification processcan take months.

    All certification requirements should be handledthrough the punch-list and warranty obligations.

    Lien rights

  • 7/29/2019 Green Project Risks

    39/57

    April 10, 2012

    Sample provisions: Final Completion:

    Final Completion occurs when the Project reaches

    final completion under the Contract Documents,however, Final Completion does not depend uponachieving the Desired LEED Certification.

    The Owner may retain 2.5% of the entire Project costuntil the Green Building Certification Institute

    determines Certification, if any. Only agree to part two if the owner insists upon

    some protection.

    Final Completion and Payment

  • 7/29/2019 Green Project Risks

    40/57

    April 10, 2012

    Liquidated Damages vs. LEED Bonus

    Owners Perspective:

    Add liquidated damages if possible

    LEED Bonuses may incentivize wrong behavior

    Designers Perspective:

    No liquidated damages. Contractors Perspective:

    Contractors should discuss a LEED bonus with the owneralternative to LDs or green guarantees.

    If the parties agree to share the benefits and risks of LEEDcertification, more likely to result in a successful project.

    The LEED bonus concept will encourage a collaborativeatmosphere.

  • 7/29/2019 Green Project Risks

    41/57

    April 10, 2012

    Standard of Care

    Changes with the profession as practices and competencieschange.

    Best practices ofyesterday are the minimum standards of

    today As green products and processes surge, A/Es saddled with

    working knowledge of these

    New AIA ethics standard: promote sustainable design anddevelopment principles in their professional activities.

    Single ply TPO roof (10 years) vs. BUR (30 years)

  • 7/29/2019 Green Project Risks

    42/57

    April 10, 2012

    Standard of Care

    Derived from statute:

    P.E. must use reasonable professional skill, judgment anddiligence normally rendered by professional engineers in thepractice of professional engineering

    implied in every contract

    Attempts to minimize standard of care:

    Expect sophisticated parties to reject Enforceable?

    Possibly against contracting party; not third parties

  • 7/29/2019 Green Project Risks

    43/57

    April 10, 2012

    Material Substitutions Do not allow material substitutions without written

    change from all necessary parties (Owner/Architect).

    Risk of inadvertently losing LEED credits.

    Designers and Contractors - be cautious in proposingmaterial changes.

    Make sure you know how it will affect credits.

    Proposed language in AIA - D503:

    Burden on contractor to determine affect Architects entitled to rely on contractors statements

    Contractors should get specific approval from Owner andDesignerBEFORE substituting materials.

  • 7/29/2019 Green Project Risks

    44/57

  • 7/29/2019 Green Project Risks

    45/57

    April 10, 2012

    LEED Certification Responsibility Matrix Should be prepared by Owner or Designer at beginning of

    project.

    Tied to green standard definition.

    Matrix outlines LEED Credit responsibilities and assignsdocumentation and credit responsibility.

    If you are a contractor or consultant, ask whether a matrixhas been prepared and get a copy.

    Contractors can use it as a tool with subcontractors,even if the owner or designer has not prepared one.

  • 7/29/2019 Green Project Risks

    46/57

    April 10, 2012

    Sample Matrix

  • 7/29/2019 Green Project Risks

    47/57

    April 10, 2012

    Sample Matrix #2

    Could be as simple as:

    Documentation

    Responsibility

    Owner ResponsibilityContractor

    Responsibility

    Design ResponsibilityPrerequisite or Credit

    EXHIBIT A

    LEED CERTIFICATION RESPONSIBILITY MATRIX

  • 7/29/2019 Green Project Risks

    48/57

    April 10, 2012

    Flow Down Provisions

  • 7/29/2019 Green Project Risks

    49/57

    April 10, 2012

    Flow Down Provisions

    Provide that a subcontractor/subconsultant is bound to thecontractor/DPOR in the same fashion as thecontractor/DPOR is bound to the owner in the primecontract.

    Help to ensure that the subcontractor's obligations to thecontractor mirror the contractor's obligations to the owner.

    Flow Down Mistake: Subcontractor brings high VOC paint on site; Unable to obtain EQ Credit 4.2 which costs the project Silver

    Certification; Owner needed at least LEED Silver for tax credits and sues; If Sub was not bound to same standards, contractor may end up

    holding the bag

  • 7/29/2019 Green Project Risks

    50/57

    April 10, 2012

    Flow Down Provisions

    If you are upstream party, looking to include flow-down: make available in writing any documents you are flowing down

    identify what contract obligations are flowing down

    include acknowledgment statement

    better to include a separate flow down for green obligations

    defeats arguments that green risks didnt flow down

    If you are downstream party: narrow any flow down to scope of work

    make written request for documents to which you are bound

    understand the risks that your contracting party is taking on withother project participants

    Dont sign acknowledgements that you cant or dont know

  • 7/29/2019 Green Project Risks

    51/57

    April 10, 2012

    Flow Down Provision

    Sample:

    The subcontractor acknowledges that the work under thissubcontract is for a project seeking LEED certification. The

    subcontractor hereby assumes toward the contractorall thesame obligations, rights, duties and redress that thecontractor assumes toward the ownerandarchitect/engineer under the prime contract, LEED projectrequirements, and/or LEED responsibility matrix as they

    relate to the subcontractors work.

  • 7/29/2019 Green Project Risks

    52/57

    April 10, 2012

    Indemnification Provisions Owners unrealized expectations = claims and lawsuits

    Attempt to pass liability to the party most responsiblefor the loss

    Indemnify: To protect against damage, loss, or injury

    Best used in conjunction with a flow down provision

    Be aware of embedded indemnification provisions

  • 7/29/2019 Green Project Risks

    53/57

    April 10, 2012

    Indemnification Provisions

    Green/Sustainable Project. Subcontractor shall defend andindemnify Contractor against all costs, expenses, damagesand liability, including without limitation, legal fees andexpenses resulting from any failure of the Project to achieve

    the Owners desired green or sustainable buildingcertification or goals, but only to the extent that such failureto achieve certification or goals results from any fault orneglect or act of the Subcontractor in the performance ofthe Work, or the fault or neglect or act of any entity for

    whose work the Subcontractor is responsible.

  • 7/29/2019 Green Project Risks

    54/57

    April 10, 2012

    Understanding Insurance and Bonding

  • 7/29/2019 Green Project Risks

    55/57

    April 10, 2012

    Insurance and Bonding Review and understand insurance policies and bonds.

    Are you covered for failure to obtain certification?

    Dont count on it.

    Read your policy. Call your broker.

    Bond companies are taking position that greencertifications are not covered by bonds.

    Insurance companies are taking position of wait andsee according to the 2010 Marsh Report

    Coverage for green product failures?

  • 7/29/2019 Green Project Risks

    56/57

    April 10, 2012

    Questions?

  • 7/29/2019 Green Project Risks

    57/57

    A il 10 2012

    Thank YouLogan A. Hollobaugh, LEED AP

    Ogletree, Deakins, Nash,Smoak & Stewart, P.C.

    (312) [email protected]

    Matthew J. StraubOgletree, Deakins, Nash,

    Smoak & Stewart, P.C.(312) 558-1424

    [email protected]