Upload
aiswarya-sreekumar
View
216
Download
0
Embed Size (px)
Citation preview
7/29/2019 Green Project Risks
1/57
April 10, 2012
Managing Contract Risks onProjects
7/29/2019 Green Project Risks
2/57
April 10, 2012October 14, 2010
The Rise of Green Buildings
Project Delivery Methods Mastering Form Agreements
Drafting and Negotiating Contract Terms
Understanding Insurance and Bonding
OverviewManaging Contract Risks on Green Projects
7/29/2019 Green Project Risks
3/57
April 10, 2012
The Rise of Green Building
7/29/2019 Green Project Risks
4/57
April 10, 2012
Rise in Green Building
Approximately $8 billion worth of greenconstruction in 2006
Grew to approximately $60 billion in 2010 Estimated $100-140 billion in 2013 Next three years:
$554 billion to the national economy
Green jobs will quadruple to 7.9 million By 2015
Green construction to represent almost half ofnonresidential market McGraw-Hill
7/29/2019 Green Project Risks
5/57
April 10, 2012
Rise in Green Building Regulations
International Code Council International Green Construction Code released last March
ASHRAE Standard 189.1 Released last winter - commercial green building standard Replaces Standard 90.1-2007
7/29/2019 Green Project Risks
6/57
April 10, 2012
Project Delivery Methods
Design-Bid-Build Design-Build Integrated Project Delivery
7/29/2019 Green Project Risks
7/57
April 10, 2012
Why Is Delivery Method Important? Delivery method typically owner-driven
Considerations:
Early involvement of contractor and subcontractors?
Single point responsibility
Responsibility for overseeing satisfaction of greenobjectives
Understanding alignment of parties is critical to
understanding potential risks.
7/29/2019 Green Project Risks
8/57
April 10, 2012
1. Design-Bid-Build (D-B-B)
2. Design-Build (D-B)
3. Construction Manager @ Risk
4. Integrated Project Delivery (IPD)
Project Delivery Methods
7/29/2019 Green Project Risks
9/57
April 10, 2012
Design-Bid-Build
Discourages green value engineering
Less collaborative
Delayed contractor involvement
Expensive post-award changes
Design-Build
Who is the owners ally/advisor? Single point responsibility
Owner typically less-involved
Project Delivery Methods
7/29/2019 Green Project Risks
10/57
April 10, 2012
CM at-Risk
Requires experienced CM
Disconnect from some trades
Integrated Project Delivery
The ultimate collaborative delivery method
Early involvement of contractor and trades Value engineering encouraged and facilitated
Needs strong owner and trusting participants
Shared incentives for LEED certification
Project Delivery Methods
7/29/2019 Green Project Risks
11/57
April 10, 2012
Managing Contract Risks on Green Projects
Mastering Contract Forms
Drafting and Negotiating Contract TermsUnderstanding Insurance and Bonding
7/29/2019 Green Project Risks
12/57
April 10, 2012
Mastering Contract Forms
7/29/2019 Green Project Risks
13/57
April 10, 2012
Importance of Contract Forms Design and construction organizations are moving
quickly to prepare standardized forms
Promote an industry standard
Increase revenue
Forms vary significantly from organization toorganization
Hasty preparation = missing terms and concepts Understanding forms means opportunity to avoid
green pitfalls
7/29/2019 Green Project Risks
14/57
April 10, 2012
AIA
B211-2007 Architects Services: Commissioning
B214-2007 Architects Services: LEED Cert.
D503-2011 - Guide for Sustainable Projects
New Sustainable Projects Documents
ConsensusDOCS
DOC 310 Green Building Addendum DBIA
Sustainable Project Goals Exhibit
Whats Out There?
7/29/2019 Green Project Risks
15/57
April 10, 2012
AIA B211-2007 - Commissioning Covers architects services for commissioning
Requires architect to: Develop a Commissioning Plan, Design Intent
Document, and Commissioning Specifications; Review the contractors submittals related to the
systems to be commissioned;
Observe and document performance tests;
Train operators; and
Prepare a Final Commissioning Report.
Incorporated into Owner-Architect Agmt.
Not a stand alone document.
7/29/2019 Green Project Risks
16/57
April 10, 2012
Not a stand alone document
Covers only LEED Services for architects
Intended for use with B102-2007 Not for contractors
Architect Handles Certification Process:
Conducts Pre-design Workshop
Creates LEED Certification Plan
Organize and Manage certification process
Provide LEED specifications
AIA B214-2007 LEED Certification
7/29/2019 Green Project Risks
17/57
April 10, 2012
AIA B214-2007 Continued Missing Terms:
Disclaimer of guarantees or warranties
Disclaimers of any implied guarantees
Remedy provisions for failed certification
Completion
End of certification process?
7/29/2019 Green Project Risks
18/57
April 10, 2012
D503-2011 Sustainable Projects Guide Not a contract document, exhibit, or addendum
that can be incorporated in whole into projectcontracts.
Provides an overview of some of the key legal andcontractual issues that can arise on projects thatincorporate sustainable goals.
Includes model contract language that can be added
to: B101-2007 Owner-Architect Agreement A101-Owner-Contractor Agreement
A201-2007 General Conditions
7/29/2019 Green Project Risks
19/57
April 10, 2012
AIA New Sustainable Projects Documents Set to be released in April or May 2012
Incorporation of model language into:
A101-2007 SP Owner/Contractor
B101-2007 SP Owner/Architect
A201-2007 SP General Conditions
C401-2007 SP Architect/Consultant
A401-2007 SP Contractor/Subcontractor
7/29/2019 Green Project Risks
20/57
April 10, 2012
Not a stand alone contract
Assumes design-bid-build
Invents new nomenclature:
Green Building Facilitator Default = Architect
Green Measures Physical those incorporated in Plans and Specs as part of
design. Procedural means and methods in performance of work.
ConsensusDOCS - 310
7/29/2019 Green Project Risks
21/57
April 10, 2012
ConsensusDOCS - 310 Remedy Provision:
Moves all tax and financial consequences (i. e. thecost savings) into the category of consequential
damages that are subject to waivers of such damagesin other construction documents.
Missing Terms:
Green Guarantee
Disclaimer of warranties
Payment of GBF
Completion Issues
7/29/2019 Green Project Risks
22/57
April 10, 2012
Not a stand alone contract
Assumes Design-Build Delivery
Addresses:
Green Standard Art. 1
Art. 4 - Remedies section offers menu of options ifproject fails to meet green goals
Waiver
Liquidated damages Limited obligation to cure
Art. 6 Sub. and Final Completion not contingent oncertification.
DBIA Sustainable Project Goals Exhibit
7/29/2019 Green Project Risks
23/57
April 10, 2012
Requires retention of independent CommissioningAuthority
Missing Terms: Payment
Fails to Adequately Address: Other project delivery options
Obligation for determining regulatory requirements
DBIA Sustainable Project Goals Exhibit
7/29/2019 Green Project Risks
24/57
April 10, 2012
Drafting and Negotiating Green Contracts
7/29/2019 Green Project Risks
25/57
April 10, 2012
Conceptual Risks on Green Building Projects
Impossible Promises Ambiguous/Overlapping Responsibility
Increased Standard of Care
Using traditional contract mechanisms andconcepts on a green project
Lack of precedent
Benefits well-known and well-documented
Conceptual Risks
7/29/2019 Green Project Risks
26/57
April 10, 2012
Risks on Green Building Projects Inexperience
Increased risk of design/construction defectsUnrealized Expectations
Learning Curve: Products and ConstructionMethods
Building Performance Issues
Regional issues not always considered
Failed Green Certifications
Green construction is regular construction riskwith a twist.
7/29/2019 Green Project Risks
27/57
April 10, 2012
Lack of Precedent No appellate case law to date.
Limited LEEDigation: Only a few reported casescontaining green issues:
Southern Builders v. Shaw Development(MD) Tax credits
Poor contract drafting
DestinyUSA (NY)
Tax/Bond credits, False promises
ACHRI v. City of Albuquerque(NM) ACHRI sued to prevent ordinance imposing energy eff. stds.
Gidumal v. Site 16/17 Development(NY)
Misrepresentation of LEED goals and energy performance
7/29/2019 Green Project Risks
28/57
April 10, 2012
What does Green mean?
Defining the Green Standard
7/29/2019 Green Project Risks
29/57
April 10, 2012
Defining the Green Standard When you get down to it, whether a work of
architecture is green is usually a shade of gray Christopher Hawthorne, Architectural Record, April 2008
Is it an objective standard?
It should be!
7/29/2019 Green Project Risks
30/57
April 10, 2012
Use Specificity:
Sample Provision:
Owner's Desired LEED Certification is LEEDCertification at the Gold Level under the USGBCsLEED forNew Construction Rating System, version3.0 - 2009.
The LEED Responsibility Matrix [Dated/Version],
which is attached hereto as Exhibit A identifies thePrerequisites applicable to the Project as well as theCredits the Owner has decided topursuefor theProject.
Defining the Green Standard
7/29/2019 Green Project Risks
31/57
April 10, 2012
Green Guarantees Owners Perspective:
A guarantee is ideal (but may not be realistic)
Designers Perspective: Any contract with the word guarantee creates
an uninsurable risk and cannot be accepted.
Contractors Perspective: Do not guarantee any level of certification.
There are too many factors outside the
contractors control. At most, contractors should accept responsibility
for the contractor responsible credits.
7/29/2019 Green Project Risks
32/57
April 10, 2012
Green Guarantees Often guarantees are not express or clear:
Example: Southern Builders, Inc. v. Shaw Development LLC Project Specs: Project is designed to comply with a Silver
Certification Level according to the U.S. Green Building
Councils Leadership in Energy & Environmental Design (LEEDRating System, as specified in Division 1 Section LEEDRequirements.
AIA D503 Recommendation A201: 3.5.2 The Contractor shall perform the Sustainable Measures
required to be performed by the Contractor in accordancewith the Contract Documents, however, nothing contained inthis Section 3.5 shall be construed as a guarantee or warrantyby the Contractor that the Project will achieve the SustainableObjective.
7/29/2019 Green Project Risks
33/57
April 10, 2012
Waiver of Consequential Damages Losses or injuries that do not flow directly and immediately
from the act of the party, but only from some of theconsequences or results of such act.
Must be reasonably foreseeable at the time the contract was
made. Typical examples:
lost rents, loss of tax credits, damage to reputation, down oridle time, interest and finance charges, material escalationcosts, depreciation, rental costs, additional energy costs, loss of
productivity and efficiency Waiver must be clear and unmistakable
7/29/2019 Green Project Risks
34/57
April 10, 2012
Waiver of Consequential Damages
Owners Perspective:
Try not to waive consequential damages they aretypically owners biggest risk.
Designers Perspective:
Insist upon a mutual waiver Standard in AIA forms B101 Owner-Architect
Contractors Perspective:
Contractors should insist upon a mutual waiver ongreen projects. Shaw Developmentis a good example ofthe exposure a contractor may face (i.e. tax credits)
7/29/2019 Green Project Risks
35/57
April 10, 2012
Waiver of Consequential DamagesSample provision Notwithstanding anything contained in Project agreements or this
Rider, the Contractor shall only be responsible for commerciallyreasonable efforts to achieve the LEED credits shown in the LEED
Responsibility Matrix.
Contractor is not liable or responsible for the failure of the Project toachieve the Desired LEED Certification or any intended financialand/or environmental benefits.
Notwithstanding any other provision in Project agreements or thisRider, in the event that the Project fails to achieve the Desired LEEDCertification, the Contractor will not be liable for any special,indirect or consequential damages arising in any manner from suchfailure.
7/29/2019 Green Project Risks
36/57
April 10, 2012
Substantial Completion Owners Perspective:
Will try to tie certification to substantial completion.
Designers Perspective:
LEED Certification is on a different timeline frombuilding completion and occupancy.
Contractors Perspective:
Contractors should not allow substantial completion tobe tied to certification. Certification could take monthsand include appeals. This may occur while the owner isoccupying the building and receiving the benefit of itsuse.
7/29/2019 Green Project Risks
37/57
April 10, 2012
Substantial Completion Sample provision:
Substantial Completion: This provision specifically overrides any and all
provisions dealing with Substantial Completion inother Contract Documents. Substantial Completion isthe stage in the progress of the Project when theProject or designated portion thereof is sufficientlycomplete so that the Owner can occupy or utilize the
Project for its intended use. Substantial Completiondoes not depend upon achieving the Desired LEEDCertification.
7/29/2019 Green Project Risks
38/57
April 10, 2012
Final Completion and Payment
Owners Perspective: Make certification part of final completion.
Designers Perspective:
De-couple LEED Certification from final completion bynegotiating additional Post-Completion Phase services. Contractors Perspective:
Same as substantial completion do not tie finalcompletion to certification. The certification processcan take months.
All certification requirements should be handledthrough the punch-list and warranty obligations.
Lien rights
7/29/2019 Green Project Risks
39/57
April 10, 2012
Sample provisions: Final Completion:
Final Completion occurs when the Project reaches
final completion under the Contract Documents,however, Final Completion does not depend uponachieving the Desired LEED Certification.
The Owner may retain 2.5% of the entire Project costuntil the Green Building Certification Institute
determines Certification, if any. Only agree to part two if the owner insists upon
some protection.
Final Completion and Payment
7/29/2019 Green Project Risks
40/57
April 10, 2012
Liquidated Damages vs. LEED Bonus
Owners Perspective:
Add liquidated damages if possible
LEED Bonuses may incentivize wrong behavior
Designers Perspective:
No liquidated damages. Contractors Perspective:
Contractors should discuss a LEED bonus with the owneralternative to LDs or green guarantees.
If the parties agree to share the benefits and risks of LEEDcertification, more likely to result in a successful project.
The LEED bonus concept will encourage a collaborativeatmosphere.
7/29/2019 Green Project Risks
41/57
April 10, 2012
Standard of Care
Changes with the profession as practices and competencieschange.
Best practices ofyesterday are the minimum standards of
today As green products and processes surge, A/Es saddled with
working knowledge of these
New AIA ethics standard: promote sustainable design anddevelopment principles in their professional activities.
Single ply TPO roof (10 years) vs. BUR (30 years)
7/29/2019 Green Project Risks
42/57
April 10, 2012
Standard of Care
Derived from statute:
P.E. must use reasonable professional skill, judgment anddiligence normally rendered by professional engineers in thepractice of professional engineering
implied in every contract
Attempts to minimize standard of care:
Expect sophisticated parties to reject Enforceable?
Possibly against contracting party; not third parties
7/29/2019 Green Project Risks
43/57
April 10, 2012
Material Substitutions Do not allow material substitutions without written
change from all necessary parties (Owner/Architect).
Risk of inadvertently losing LEED credits.
Designers and Contractors - be cautious in proposingmaterial changes.
Make sure you know how it will affect credits.
Proposed language in AIA - D503:
Burden on contractor to determine affect Architects entitled to rely on contractors statements
Contractors should get specific approval from Owner andDesignerBEFORE substituting materials.
7/29/2019 Green Project Risks
44/57
7/29/2019 Green Project Risks
45/57
April 10, 2012
LEED Certification Responsibility Matrix Should be prepared by Owner or Designer at beginning of
project.
Tied to green standard definition.
Matrix outlines LEED Credit responsibilities and assignsdocumentation and credit responsibility.
If you are a contractor or consultant, ask whether a matrixhas been prepared and get a copy.
Contractors can use it as a tool with subcontractors,even if the owner or designer has not prepared one.
7/29/2019 Green Project Risks
46/57
April 10, 2012
Sample Matrix
7/29/2019 Green Project Risks
47/57
April 10, 2012
Sample Matrix #2
Could be as simple as:
Documentation
Responsibility
Owner ResponsibilityContractor
Responsibility
Design ResponsibilityPrerequisite or Credit
EXHIBIT A
LEED CERTIFICATION RESPONSIBILITY MATRIX
7/29/2019 Green Project Risks
48/57
April 10, 2012
Flow Down Provisions
7/29/2019 Green Project Risks
49/57
April 10, 2012
Flow Down Provisions
Provide that a subcontractor/subconsultant is bound to thecontractor/DPOR in the same fashion as thecontractor/DPOR is bound to the owner in the primecontract.
Help to ensure that the subcontractor's obligations to thecontractor mirror the contractor's obligations to the owner.
Flow Down Mistake: Subcontractor brings high VOC paint on site; Unable to obtain EQ Credit 4.2 which costs the project Silver
Certification; Owner needed at least LEED Silver for tax credits and sues; If Sub was not bound to same standards, contractor may end up
holding the bag
7/29/2019 Green Project Risks
50/57
April 10, 2012
Flow Down Provisions
If you are upstream party, looking to include flow-down: make available in writing any documents you are flowing down
identify what contract obligations are flowing down
include acknowledgment statement
better to include a separate flow down for green obligations
defeats arguments that green risks didnt flow down
If you are downstream party: narrow any flow down to scope of work
make written request for documents to which you are bound
understand the risks that your contracting party is taking on withother project participants
Dont sign acknowledgements that you cant or dont know
7/29/2019 Green Project Risks
51/57
April 10, 2012
Flow Down Provision
Sample:
The subcontractor acknowledges that the work under thissubcontract is for a project seeking LEED certification. The
subcontractor hereby assumes toward the contractorall thesame obligations, rights, duties and redress that thecontractor assumes toward the ownerandarchitect/engineer under the prime contract, LEED projectrequirements, and/or LEED responsibility matrix as they
relate to the subcontractors work.
7/29/2019 Green Project Risks
52/57
April 10, 2012
Indemnification Provisions Owners unrealized expectations = claims and lawsuits
Attempt to pass liability to the party most responsiblefor the loss
Indemnify: To protect against damage, loss, or injury
Best used in conjunction with a flow down provision
Be aware of embedded indemnification provisions
7/29/2019 Green Project Risks
53/57
April 10, 2012
Indemnification Provisions
Green/Sustainable Project. Subcontractor shall defend andindemnify Contractor against all costs, expenses, damagesand liability, including without limitation, legal fees andexpenses resulting from any failure of the Project to achieve
the Owners desired green or sustainable buildingcertification or goals, but only to the extent that such failureto achieve certification or goals results from any fault orneglect or act of the Subcontractor in the performance ofthe Work, or the fault or neglect or act of any entity for
whose work the Subcontractor is responsible.
7/29/2019 Green Project Risks
54/57
April 10, 2012
Understanding Insurance and Bonding
7/29/2019 Green Project Risks
55/57
April 10, 2012
Insurance and Bonding Review and understand insurance policies and bonds.
Are you covered for failure to obtain certification?
Dont count on it.
Read your policy. Call your broker.
Bond companies are taking position that greencertifications are not covered by bonds.
Insurance companies are taking position of wait andsee according to the 2010 Marsh Report
Coverage for green product failures?
7/29/2019 Green Project Risks
56/57
April 10, 2012
Questions?
7/29/2019 Green Project Risks
57/57
A il 10 2012
Thank YouLogan A. Hollobaugh, LEED AP
Ogletree, Deakins, Nash,Smoak & Stewart, P.C.
(312) [email protected]
Matthew J. StraubOgletree, Deakins, Nash,
Smoak & Stewart, P.C.(312) 558-1424