Upload
steven-brady
View
87
Download
1
Embed Size (px)
Citation preview
Graded Unit: Fuel
Purification
System
Final Design Date: April 2016
2016
STEVEN BRADY
5/5PB 30140732
FUSILIER FUELS LTD.
Graded Unit: Fuel Purification System
1
Executive Summary
This report was commissioned by the client to provide them with a new design for a Fuel Purification
System for a new marine vessel.
The report draws attention to the best options available for fuel and lube oil purification in a marine
environment, the new regulations involved in commissioning such a design, the features that must be
included for the design to work, an estimated cost and all the calculations used within the process of
choosing the design which will be available in the appendices.
There were three alternative solutions for fuel purification units and after an extensive evaluation
process throughout this report one was chosen as the best option, Alfa Laval. The reasons are all
mentioned within this report. Overall Alfa Laval are seen as not only a possible choice for the design but
also commercially viable, profitable for the client and the best technical solution for the system.
Acknowledgements
Although the documentation provided was all written and put together by myself, it must be noted that
acknowledgements need to be made to the following people for the help with any random questions I
had pertaining to this document
John McInally, Lecturer, City of Glasgow College
Robert Thresher, 2nd Engineer, Global Marine
Aleksandr Nikolajenko, 2nd Engineer, Guardline
Jonny Tailford, 3rd Engineer, Global Marine
Fiachre Hoey, 3rd Engineer, Princess Cruises
Sean Ross, 3rd Engineer, Hansons Dredging
Keith Phillips and Jon Christmas, Sales and Tech, Alfa Laval
Graded Unit: Fuel Purification System
2
CONTENTS
Abbreviations Page 4
Project Summary Page 5
Project Deliverables Page 7
Summary of Purification
Process Page 10
Main Components Page 11
Main Engine Page 11
Auxiliary Engine Page 12
Oils Page 13
HFO Page 13
LO Page 13
DO Page 13
Purifier Manufacturers Page 15
Alfa Laval Page 15
Mitsubishi Page 17
Westfalia Page 18
Decision Matrix Page 20
Purifier Selection Page 22
HFO Page 22
LO Page 23
DO Page 24
System Diagrams Page 25
HFO Page 25
LO Page 26
DO Page 27
Graded Unit: Fuel Purification System
3
CONTENTS Continued
Room Layouts Page 28
Layout 1 Page 29 Layout 2 Page 29 Layout 3 Page 30 Decision Matrix Page 31
Piping Page 33 Ventilation Page 33 Sludge Tank Page 35 Electrics Page 36
Cable Sizes Page 36 Lighting Page 36 Emergency Lighting Page 37 Electrical Isolations Page 38
Maintenance Facilities Page 39 I-Beam Page 39 Trolley/Chain Block Page 39 Maintenance Area Page 42
Fire Safety Page 43 Fire Detectors Page 43 Fire Extinguishers Page 43 Fixed Systems Page 44 Room Protection Page 46
Verification Strategy Page 47
Cost Estimations Page 50
Novel Feature Page 51
Knowledge and Skills Gained Page 52
Evaluation Page 53
Mind Map
Appendices Gantt Charts
Bibliography
Progress Reports Project Proposal Technical Specification
Graded Unit: Fuel Purification System
4
Abbreviations
COGC – City of Glasgow College
FSS Code – International Code for Fire Safety Systems
HFO – Heavy Fuel Oil
IEC – International Electro technical Commission
IMO – International Maritime Organisation
ISO – International Organization for Standardization
LO – Lube Oil
LSFO – Ultra Low Sulphur Fuel Oil
MARPOL - International Convention for the Prevention of Pollution from Ships
MCR – Maximum Continuous Rating
MDO – Marine Diesel Oil
SDOC – Specific Diesel Oil Consumption
SFOC – Specific Fuel Oil Consumption
SOLAS – Safety of Life at Sea
Graded Unit: Fuel Purification System
5
Fuel Purification System: Final Design
Prepared for City of Glasgow College and MAERSK
By Steven Brady, Project Manager
Fusilier Fuels Ltd.
Project Summary
MAERSK shipping company have contacted Fusilier Fuels Ltd. and has asked for the design
of an entire fuel purification system for their brand new ship the MAERSK Braveheart. The
objective of this document is to provide the client with the final design for the project, the
reasoning behind the design choices through calculations and regulations and to give the
client an estimated cost of the project. This entire project will be overseen and assessed by
the City of Glasgow College (COGC) for the Project Manager Steven Brady to complete his
HND in Marine Engineering.
This design will incorporate 3 different purification methods. A Heavy Fuel Oil (HFO)
purification method, a Lube Oil(LO) purification method and a Diesel Oil(DO) purifications
method. The HFO system will consist of two purifying units, the LO system will also consist
of two units and the DO system will consist of one purification unit. The purification systems
will all operate in partner with a large 2 stroke marine engine designed for deep sea vessels.
The companies being looked at for the purification units are Alfa Laval, Westfalia and
Mitsubishi who are all world leaders in supplying marine fuel purification units. They offer
brand new and top of the range products and, combined with their extensive knowledge
and expertise in design, should be exactly what the client is looking for. Throughout this
report the products will be compared to see what unit would be best for this design and
justification for the choices made will be shown with research and calculations.
The client has explained that they would like this design completed in an efficient and timely
manner with dates given through the hand in schedule provided by the client.
To ensure a sense of order throughout this project it has been made clear by Fusilier Fuels
Ltd. that a Gantt chart will be used to keep details on the progress of the project and to be
used as a tool to monitor where the project team needs to focus at certain times
Graded Unit: Fuel Purification System
6
throughout the project. It will also help serve as a verification strategy for the client for the
timeous completion of the project.
Throughout the entirety of the project a logbook will also be getting updated to help verify
the project team’s progress. It will be written in a personal diary format and will be
published with the final design.
Safety is key when thinking about the design of system like this on board a marine vessel.
The project team will be looking at several safety aspects of the system, such as fire
systems, isolations, etc. to provide the client with the safest design possible.
Throughout the project it must also be mentioned that several maritime organisations will
be mentioned such as the Lloyd’s Register Classification Society who are primarily
concerned with the safety of the vessel and the vessels structural integrity. Lloyd’s Register
provide independent assurance to companies that work within the transportation sectors,
with their main goals being the safety of life, property and the environment. They are seen
is the world leaders in assessing ships to internationally recognized standards.
Another organisation mentioned frequently is the International Maritime Organisation
(IMO). The IMO was created by the United Nations and is a specialised agency that is
responsible for the safety and security of shipping and the prevention of marine pollution by
ships. They create a lot of the legislation and regulations that will dictate what will happen
with the design process.
Graded Unit: Fuel Purification System
7
Project Deliverables
For this design to be successful it was found that certain deliverables must be attained
throughout the entirety of the project:
System Diagrams –
o Heavy Fuel Oil – this must include all of the components for the HFO system
such as the purifiers, service and settling tanks and all other components.
Must inlcude detailed descriptions for the system.
o Lube Oil – this must include all of the components for the LO system, both
the main engine systems and the auxiliary engine systems. Must include all
sump tanks, purifiers and renovating tanks. Detailed descriptions to the
system to be included.
o Diesel Oil – again this must include all of the components necessary for the
running of the DO system. Including the service and settling tank, purifier and
any other components. Descriptions will also be included.
The size of any tanks will be included and the calculations shown in the appendix
System Selections –
o One main option will be selected and two other fall back options shall be
chosen for the client. The decision will be shown by rational description to
the client during this design.
The Gantt Chart will accompany the final design. Keeping track of time taken to
complete the work.
A mind map of the entire project will be included in both the proposal and the final
design.
Graded Unit: Fuel Purification System
8
Design of the Purifier Room –
o Free Volume of the room – this calculation must accommodate for the
purifiers and other associated machinery within the room itself
o Access for proper operations in the room and high performance of the
system also to be accommodated in this process
o Ventilation to and from the room must be calculated and then a drawing
made for the placement of vents within the room
o Tanks – System drawings will be made for the orientation of the tanks and
caluclations made for the capacities
o Components list made for every component within the purifier room. This
will also include detailed descriptions on the components as to give the client
a firm idea of how it all fits into place.
o Plan drawings will be included with the design as to give the client the right
orientation of everything within the room
o Calculations to be made for wiring for the motors within the purifier room
o Maintenance and overhaul facilities to be accounted for within the room.
This will include lifting equipment and calculations, cleaning facilities for the
cleaning of purifiers and storage areas for the spares and tools.
o Luminaries – This will involve calculating the luminaries necessary in the
room and drawing a plan for the luminaries within the room. These will
adhere to SOLAS requirements
Safety –
o Fire Safety-
Graded Unit: Fuel Purification System
9
Fire Isolations – all fire isolations will be installed within SOLAS
requirements
Quick Closing Valves to be noted on the plan for the tanks
Fixed fire fighting systems to be chosen and detailed rational
descriptions to be given
Fire protection insulation
Fire detection and alarm systems will be selected
o Electrical isolations to be selected and descriptions to be included
o Risk Assessment to be provided with regards to the instillation of the plant
and when the plant is running
Estimated Project Cost-
o Will not include engine costs, that will be dealt with by the client.
o Will include purifier cost, component costs and design costs. Instillation costs
will be added by a contractor.
Graded Unit: Fuel Purification System
10
Summary of Purification Process
This section is just to give an overview of the purification process to give anyone outside of
the technical fields an idea of what the system is necessary for.
The purification of fuel process on board marine vessels is used to remove impurities and
solids from the oil. It is done in the form of a centrifuge system. Clean oil is crucial for the
safe, reliable and economical operation of virtually all kinds of equipment that use the oils
for either fuel or lubrication. Clean oil reduces wear and corrosion on all equipment
installed downstream, thus helping to avoid breakdowns and cutting back on downtime
throughout a plant or installation. Solids within the fuels has been known to cause serious
damage to engine plants so it is of the upmost importance that the fuel be clean to the best
possible standards.
The function of a purifier unit is to separate different density liquids and solids i.e. fuel, lube
oil, water and sludge. The purifier works on the principal of centrifugal force. Lower density
liquids (oil) remain on the inside as the bowl rotates whereas higher density liquids (water)
and solids are forced to the outside to be discharged.
Oil is fed into the purifier through the inlet pipe where it flows to the bottom of the bowl, it
then travels up through the disk stack where the centrifugal force forces and water and
solids to the outside of the bowl for discharge. The rotation of the bowl forms an oil and
water interface which lies outside of the bowl stack but inside of the outer circumference of
the top disk. The position of the interface is governed by the gravity disk. The clean oil then
flows to the paring chamber where it is pumped back to the sump/tank. The separated
water is discharged through the drain. The separated solids build up on the outside of the
bowl until the discharge cycle begins. The bowl opening water slides the bowl downwards
opening the discharge ports and the sludge is discharged to the sludge tank.
The benefits of clean oil include lower operating costs due to a reduction in the
consumption from the plants, lower disposal costs and improvements in the quality of work
from the plants using the oils.
Graded Unit: Fuel Purification System
11
Main Components
Main Engine
The client has chosen the MAN B&W 8G95ME – C9 as the main propulsion for the MAERSK
Braveheart. The engine technical particulars are as follows:
Model MAN B&W 8G95ME-C9
No. of Cylinders 8
Stroke (mm) 3460
Bore (mm) 900
MCR Output (kw) (100%) 61,830
Shaft Speed (rpm) (100%) 80
MCR BHP 84,065
Fuel SFOC (g/kWh) 166
Fuel Consumption (m3/hr) * 10.357
LO Nominal Required Capacity of
Separator (l/kwh)
0.136
LO Throughput (m3/s)** 2.34x10-3
FO Nominal Required Capacity of
Separator (l/kwh)
0.23
FO Throughput (m3/s)*** 3.95x10-3
*Fuel Consumption Calculations are in Appendix 1
**LO Throughput Calculations in Appendix 1.1
*** FO Throughput Calculations in Appendix 1.2
Graded Unit: Fuel Purification System
12
Auxiliary Engines
The client has chosen two Auxiliary engines for the MAERSK Braveheart, they are as follows:
Model MAN B&W 8L27/38
No of Generators 2
No. of Cylinders 8
Stroke (mm) 380
Bore (mm) 270
MCR Output at 60Hz (kw) 2800
Shaft Speed at 60Hz (rpm) 720
Fuel SFOC (g/kWh) 184
Fuel SDOC (g/kwh) 186
SLOC (g/kWh) 0.6
Fuel Consumption DO (m3/hr)* 0.5981
*DO Consumption Calculation is in Appendix 2
Graded Unit: Fuel Purification System
13
Oils
All oil based fuels must not have a flash point that is less than 60oC. This is to keep in
accordance with the SOLAS Chapter II-2 Part B Regulation 4
MARPOL Annex VI Chapter 3 – Regulation 18 also states that Fuel Oil must confirm to
certain standards.
HFO
Heavy Fuel Oil which is used in the Main Engine is pumped on board from a bunker barge
and is transferred through the bunker station to the storage tanks at either side of the
vessel. From the storage tanks the HFO transfer pump will transfer the fuel to the settling
tank where it will be heated. The purifier feed pump will then draw the fuel from the
settling tank to the purifier centrifugal separator, purification unit, where any solids and
impurities will be removed and clean oil will then be produced. The clean oil produced will
normally passed through an extra heating system and a viscometer, before being pumped
through to the HFO daily service tanks. From the service tank the feed pump transfers the
fuel to each cylinder before fuel injectors spray the fuel in the form of a fine misty spray into
each cylinder and, due to the purification unit doing a good job, the clean oil will create
perfect combustion.
LO
Lubricating oil is essential for the engines to run for any period of time as it will protect the
working mechanical mechanisms from damage through harsh metal to metal contact. Good,
clean LO will improve the efficiency of the ships main engine and the Generators. The LO
running through the engine is not only for the crankshaft, but also for all bearings, journals,
slippers and guides. Like HFO and DO, LO must be brought to a certain temperature and
viscosity prior to its usage. LO is stored in the Sump Tanks where it is drawn through a series
of suction strainers, filters and heaters before it is purified and delivered to the Engine.
DO
Diesel Oil will go through the same purification process as the HFO on board the vessel and
is also procured through the same means, Bunker Barge. The only difference between DO
and HFO is that diesel will for emergencies on board. The main reason for this is the cost of
DO compared to that of the HFO. However although the vessels main engine will be run by
HFO, it is also possible to run it using Diesel Oil, so consideration must be given to this prior
Graded Unit: Fuel Purification System
14
to installation. Diesel Oil is pumped to the Diesel Oil Settling Tank and then pumped
through the DO purification unit via the DO Purifier Feed Pump. It will then be pumped
through to the DO Service Tank.
Graded Unit: Fuel Purification System
15
Purifier Manufacturers
In this section the selection of which Purifiers to use in this design will be rationalised
descriptively. All three manufacturers mentioned in this section were able to cope with the
clients technical specifications. The choices of manufacturers are made below:
1. ALFA LAVAL
Alfa Laval have been around since 1883 with over 1900 patents under their name. This
makes them one of the most reputable companies in the entire world. They work with
separation, heat transfer and fluid handling technologies for heavy industries involved in
food and water supply, pharmaceuticals, energy and environmental protection. Their
company is well distributed globally which for international shipping gives us an extremely
practical solution.
The range Fusilier Fuels felt were best suited to the design were the Alfa Laval S and P Flex
Range. The differences between the two being that the P flex models are conventional and
use manually controlled gravity discs which process oils of a maximum 991 kg/m3 at 15oC.
This allows for more finely defined oils such as DO or LO to run through the separator.
The S Flex range use the Alfa Laval Clarifier and Purifier (ALCAP) technology which will
automatically adjust for the nature of the oil being put through the separator. This means
that oils of a maximum density of 1010 kg/m3 at 15oC can be processed through the
separator. Factors like the oils density, viscosity, temperature or feed flow rate can affect
the oil-water content interface with a much denser oil so this system is very useful for the
Graded Unit: Fuel Purification System
16
processing of HFO. It will use a water transducer when the clean oil reaches the outlet which
will operate the flow control disc.
Although different in process both the S and P Flex range are very energy efficient, this
meaning that they have a low environmental impact in comparison with other brands,
which will help MAERSKs company image, and also save the company money in the long
run.
Alfa Laval sell both ranges as a modular unit, which would include the preheaters, feed
pumps, changeover valves and control cabinets. They are available for customer
customization meaning they can put the maximum of 4 units together in line. This means
that the piping arrangements and cabling are much more simplified when it comes to the
instillation of the product. The feed water, air and oil all will only need one connection
running through the system. Alfa Laval are the only manufacturer found through extensive
research with this option for customization.
The costs of the purifiers in terms of the units themselves is quite high, but not the highest
out of the manufacturers on this list and in the long run the savings made with Alfa Laval are
quite high.
These Long running costs include:
Lowest power consumption – with a smaller, lighter bowl designed for lower speeds, the
power demand is reduced on the motor.
Less oily waste and less HFO/LO losses – with a unique discharge control system operated
by the EPC 60 process controller the oil that is usually wasted on other models is in fact
saved. This also helps reduces the environmental impact of the system.
Maintenance – Less frequent maintenance is required and fewer parts are needing
replaced. This is done with less metal to metal contact throughout the system.
Graded Unit: Fuel Purification System
17
2. MITSUBISHI
Mitsubishi, or now Samgong-Mitsubishi, are one of the bigger manufacturers on this list.
Not only do Mitsubishi deal in big industry but they deal in everyday products also. They
have over 60 years of experience in industry technologies and have now teamed with
Samgong Ltd. to create oil purification units for heavy industry.
Their Samgong-Mitsubishi’s “Selfjector” series are a brand of purifiers produced specifically
for marine applications. These purifiers are commonly found on ships due to the amount of
vessels that are produced in South Korea which are almost exclusively fitted with purifiers
and other ancillary equipment manufactured by Samgong-Mitsubishi.
The Selfjector series features the G-HIDENS system. As opposed to the conventional method
of directly measuring the water content of purified oil, the G-HIDENS purifier is capable of
detecting water in the oil accumulated in the purifier bowl, thereby preventing water from
mixing in with purified oil.
One of the positives of these purifiers is the price. As a unit the initial costs are quite low but
because they do not make a modular configuration available it means there will be much
higher costs on the instillation of the units.
This model will also mean that because of the non-modular configuration there will be more
space taken up by the units meaning higher costs overall.
Through a lot of research it has been found that these purifiers are highly reliable but the
maintenance on the purification units can be very tricky. Engineers have stated that when
Graded Unit: Fuel Purification System
18
an overhaul or minor maintenance is required it can be quite time consuming and very
difficult due to the amount of threaded parts used in the unit.
The company is very poor in global distribution meaning that for the shipping industry this is
highly unpractical. The access to spare parts and technicians is very poor meaning a lot of
down time if the unit was to fail.
3. WESTFALIA
GEA Westfalia are another highly reputable company with over 120 years of experience with
producing separators, decanters, homogenizers, valves, etc. for various industries. One of
the areas they focus on is the marine sector. For this they produce engineering solutions for
bilge water, oil, seawater and sludge.
The separator looked at from GEA Westfalia is the Westfalia CatFineMaster series. This
product was first introduced in 2014 and is now in application in the marine industry for
purification of fuel oil, lube oil and hydraulic oil. The main feature of the CatFineMaster is
that it is the first marine fuel separator unit engineered to the mechanical specifications that
ensure maximum cat fine removal and maximum fuel quality in every situation possible.
Graded Unit: Fuel Purification System
19
Catalyst fines – cat fines for short – remain in marine fuels during refining, as a part of the
mandatory cracking practice and the aim of reducing sulphur levels to ecological standards.
Unfortunately, cat fines are highly abrasive and difficult to remove from on-board fuel even
with diligent cleaning and purification procedures. Embedding in engine parts, they cause
wear and destruction. This unit provides maximum removal of these qualities in the fuel,
meaning less damage to engine parts throughout the entirety of the system.
Due to the international distribution of GEA Westfalia as a company the spare parts and
specialized technicians needed, if there were maintenance required, are readily available
globally.
Using the same technologies as the EagleClass range with a high G force for separation
these units are highly efficient in separation. They are designed for automated separation
usin the ‘unitrolplus’ system Westfalia used on their EagleClass separators previously. This
consists of sensors which will monitor the sludge and water content at the outlets, and then
adjusting the solenoid valves accordingly. The temperature is also automatically controlled
by the ‘ViscoBoosterUnits’ technology which controls not only the temperature but the
viscosity and pressures of the oils to meet the engines specifications. It can have three
different modes activated automatically creating the finest fuels possible or creating a fuel
specific to the vessel. The functions are “Maximum CatFine Separation”, “Maximum Cost
Saving” and “Optimum Bowl Cleaning”.
Westfalia offer a modular design option for instillation, they can manufacture the design in
their factory and then fit it as an entire unit on board the vessel. This means less space used
and optimum design required for less pipe fittings.
The CatFineMaster, although not long in production and in use, comes with good reviews
with engineers claiming the system is quite easy for maintenance and reliable.
The cost of these units is very high, for first instillation but the savings in cost overall for
maintenance, engine maintenance and power efficiency are so good that it is hard to argue
with the instillation price.
Graded Unit: Fuel Purification System
20
Decision Matrix A Decision Making Matrix will be used to choose the manufacturer that best suits the needs of the client. The Decision matrix will consist of a table of information. That information includes factors that affect the choice of the manufacturer such as cost and reliability and then they will be weighed up against the importance of that factor between 1 to 5 (1 being the lowest and 5 being of highest importance). A number will then be placed in each factor for each manufacturer between 1 and 5 (1 being poor and 5 being excellent in this instance). Once the numbers have been put down for each factor by each manufacturer the manufacturers number will be multiplied by the importance factor and then all factors will be added together to create a total number. The manufacturer with the highest number will be chosen.
Factors Importance Alfa Laval Mitsubishi Westfalia
Unit Price 5 4 2 4
Instillation Cost 3 5 3 4
Reliability 5 5 5 5
Ease of Maintenance 4 5 3 5
Spares and Technician Availability 4 4 2 5
Environmental Impact 4 5 5 5
Ease of Use 3 5 4 4
Overall Weight 2 4 4 4
Size of the System 3 5 2 4
Need for Ancillaries 2 4 3 5
TOTAL 162 116 159
Graded Unit: Fuel Purification System
21
The Decision Matrix has shown that Alfa Laval would be the best choice for the client’s
needs with a total score of 162.
*All the maths is in APPENDIX 3
Graded Unit: Fuel Purification System
22
Purifier Specifications
HFO
Now that the Manufacturer has been selected for this design it is now time to find out
which models would be best used in the system for this design. Alfa Laval designed the S
Flex Range specifically for HFO purification in a marine environment. For this system, due to
the total fuel consumption of 10,357* litres per hour from the main engine it was necessary
to pick a purification unit that had a flow capacity to match that. The S976 was by far the
best option for this system as it has a flow capacity range of 10,000 to 15,000 litres per
hour. Although it is possible to achieve almost 145% of the required amount of purified oil
through one of these units alone, it is still absolutely necessary to make sure there is a stand
by purification unit available in this system. This is in preparation in case one purifier needs
to have any maintenance done or if one unit should break down.
The Alfa Laval S976 Flex Series self-cleaning centrifugal separator technical Specs are as
follows: (Alfa Laval, 2015)
Name Alfa Laval S976
Dimensions (mm) 1766 x 1250 x 1525
Flow Capacity (l/hr) 10,000- 15,000
Main Supply Voltage 3 phase, 440V
Control Voltage 1 phase, 230V
Weight (kg)
1490
Frequency (Hz) 60
Control Air (bar) Min 5 bar, Max 8
Water Pressure (bar) Min 2 bar, Max 8
Heater Type EHM 100 (Electric)
Feed Pump Type ALP 0075
*Calculations in Appendix 2.3
Graded Unit: Fuel Purification System
23
LO
The manufacturer for the LO purification units will also be Alfa Laval, it means that the manufacturer is going to be dealing with the entirety of the system and will make the system more efficient and will save the client money. It also means that the system would be using all of the same control panels, making it user friendly. The LO purification system will also consist of an S Flex range Purifier due to the large quantities of LO necessary for this system to run at full efficiency. The total capacity from this system of LO is at: Total LO requirement from both the Main Engine and Aux. Engines = 9,672.82 Litres/hour*. This is due to the size of the main engine being as large as it is and the two generators also having quite a large capacity for lubrication. The Alfa Laval S966 Flex Series self-cleaning centrifugal separator technical specs are as follows: Name Alfa Laval S966
Dimensions (mm) 1405 x 1000 x 1325
Flow Capacity (l/hr) 8,000 – 10,700
Main Supply Voltage 3 phase, 440V
Control Voltage 1 phase, 230V
Weight (kg)
893
Frequency (Hz) 60
Control Air (bar) Min 5 bar, Max 8
Water Pressure (bar) Min 2 bar, Max 8
Heater Type EHM 100 (Electric)
Feed Pump Type ALP 0075
Calculations in APPENDIX 2.2
Graded Unit: Fuel Purification System
24
DO
Although the main engine and auxiliary engines will be running at all times on HFO there will
need to be a DO purification unit in case the ship goes into Emission Controlled Areas where
the ship is not allowed on HFO.
For this we would need a purifier that runs through the total DO amount for both the Main
Engine and the Auxiliary Engines:
Total DO = 11.53 + (2 x 0.526) = 12.13 m3/hr = 12130 litres/hour*
With this in mind we would need a purifier with this capacity for MDO.
The choice made below is again an Alfa Laval Purifier, S Flex range, due to the large capacity
of MDO needed for the system to run efficiently. This means the system will all work nicely
together and the instillation will be much easier.
Name Alfa Laval S956
Dimensions (mm) 1291 x 1000 x 1325
Flow Capacity (l/hr) 9,500 – 12,700
Main Supply Voltage 3 phase, 440V
Control Voltage 1 phase, 230V
Weight (kg)
728
Frequency (Hz) 60
Control Air (bar) Min 5 bar, Max 8
Water Pressure (bar) Min 2 bar, Max 8
Heater Type CBM (Electric)
Feed Pump Type ALP 0115
*Calculations in APPENDIX 2.4
Graded Unit: Fuel Purification System
25
System Diagrams In this section there is a description on each piping arrangement that is designed for each of
the oil systems provided. The diagrams will be referenced from the Appendices so it is
advised that while reading the description to follow the diagram referenced.
HFO
Please make reference to APPENDIX 4 - Drawing 1A
The HFO will be introduced into the system when it is pumped into the settling tanks from
the fuel tanks on board. In the settling tanks there will be vast amounts of water or minerals
that will drain off in the tank due to gravity.
From this point the HFO will leave the tanks via the Quick Closing Valves (QCVs) 1 or 2 which
will be fitted at the lowest possible point on the tank to make sure that there is a maximum
pressure throughout the system. The reason that there is QCVs fitted at the inlets and the
outlets of the fuel tanks, settling and service tanks are in case of an emergency such as fire.
This gives the crew a chance to isolate the tanks from a remote location as to stop any injury
or death occurring on board.
After leaving the tank the fuel will pass through a duplex filter, this is to remove large
impurities within the oil and maintenance is very easy on these filters. They just have to be
isolated and bypassed quickly for cleaning. The oil will then enter the purifier modules, one
running and the other on stand-by in case of maintenance or performance dips in the
system.
The purifier module will consist of the pumps, pre heater, valves and the sensors included in
the dotted line areas. The system starts with the oil being pumped through the horizontal
gear pump then travelling through the electric pre heater which will heat the oil so it is at
the right viscosity to travel through the purifier. The pre heater is controlled by a
temperature sensor which will automatically control the oils temperature before passing
into the purifier itself. The oil will be heated to roughly 95oC which will aid in separation
through the purifier. There are also pressure sensors throughout the module which will be
used to detect pressure drops across the system, this will help the engineers find any
blockages or malfunctions through the system. The 3 way valve can be used to recirculate
the HFO to the Settling Tanks if there is a need to bypass the purifier.
Once the HFO has travelled to the purifier the purification process mentioned above will
begin. Sludge will be drained during the automatic intervals set by the control panel and the
sludge will pass from the purifier module to the sludge tank. Clean oil will be separated out
and pass through to the Service Tanks. From the Service Tanks the oil will go through to the
Graded Unit: Fuel Purification System
26
Fuel Booster unit and then the Main Engine. There will be an overflow line fitted to the
Service Tanks which will then feed back into the Settling Tanks. Stops any waste through the
system. There is also a sampling point fitted to the Purifier module.
LO
Please make reference to APPENDIX 4 – Drawing 2A
Lube oil will leave the main engine and generator sump tanks and to the purification
modules. The idea would be that one sump will be purified at a time, hence the isolation
valves are available at each sump. This will stop any contamination between the different
lube oil systems.
From here the LO will flow through to the duplex filters, same as the HFO system, these are
to take out any impurities early before going through the modules. The lube oil will then
pass through the purifier and usually go back through to the correct destination at the sump
tank the oil was taken from. The idea would be that the engineer would need to isolate the
other sump tanks and open the valves to the correct tank when that is needing clean oil.
There are changeover valves connecting the inlet and outlet of the purifier modules, these
will be closed or open depending on which purifier is in service.
When the oil reaches the module it will be pumped through the electric heater which will
heat the oil to roughly 80-85oC which is lower than that of the HFO. There are pneumatic 3
way valves to lead the oil to the renovating tank if need be. This tank is used for the storing
of oil when any heavy maintenance is needing provided on any of the main parts of the
system.
After the oil has left the renovating tank it will have to repeat the process of going through
the filters in case there is carry over of impurities from the renovating tank. The oil will then
pass through the purifiers and any other water or unwanted minerals in the oil will be
separated out. The oil will then run back to the tanks where necessary. The tanks will be
topped up manually from the LO storage tanks, but this is not part of this system.
There are Quick Closing Valves again in this system for emergency reasons, same as stated
before in the HFO section. The purifiers are also fitted with pressure and temperature
indicators and a sample point.
Graded Unit: Fuel Purification System
27
DO
Please make reference to APPENDIX 4 – Drawing 3A
The DO system is the simplest of the three. It is very similar to the HFO system but only has
one purification module in the system. It is not really essential but it is recommended not
only by the manufacturers for performance improvement but regulations state that within
ECA’s around the world the main engine and generator plants must run on Ultra Low
Sulphur Fuels (ULSF) and DO is the better of them.
The system works very simple, the DO leaves the settling tank through the QCV placed again
at the lowest point possible to gain the maximum pressure possible in the system. The oil
will then pass through the duplex filters, again to filter impurities and then through the
purifier module. The globe valves at either end of the module will isolate the purifier if
maintenance is required. Again the oil goes through the pump to the heater where it will be
heated slightly as DO does not need to be heated too much for the viscosity to be perfect
for separation. There is yet again a pneumatic 3 way valve to recirculate the oil back to the
settling tank, a drain to the sludge tank and a sampling point fitted in the system. Once the
oil runs through the purifier module then the clean oil will travel to the DO Service Tank
where it will then run to the engines clean. The Service Tank is fitted with an overflow line
to head back to the Settling Tank to again stop wastage in the system.
The QCVs are fitted once again for safety reasons, the same as mentioned above for the
HFO and LO systems.
Graded Unit: Fuel Purification System
28
Room Layouts This section of the project will be dealing with how the components are configured when
installed in the room. The design will be incorporating many different aspects that were
mentioned in the technical specifications. There will need to be ease of maintenance, piping
simplicity, fire safety, tank arrangements, ventilation and evacuation plans. The instillation
costs will be estimated below but will be rough as the client has not decided which
instillation company to deal with.
There will be three different designs described below with reference to the drawings and
then a decision making matrix once again will decide the best design out of the three.
The purifier schematic is below:
And all the S flex range purifiers can be put into a customized position where all purifiers are
together, this will cut down on piping materials and make the instillation process much
easier.
The design will look similar to this:
Graded Unit: Fuel Purification System
29
Room Layout 1
Please make reference to APPENDIX 6 – Drawing 4A
Room Layout 1 was the most spacious of the three drawings. It has a footprint of 39.1m2
and this in turn allows for a lot of space for maintenance on the purifier modules. The
purifiers are all connected in a custom design from Alfa Laval as mentioned earlier.
Obviously due to the width difference of the two HFO purifiers the purifiers are all
connected in an L shape. There is quite a bit of space on all sides of the purifiers, this allows
for a fair bit of personnel access, even whilst there is maintenance being provided on any of
the purifiers. The sludge tank is placed underneath the modules and deck panels. There will
be a small lid on the tank to view safely the amount in the tank. Also due to the purifiers
being close together and the tanks being underneath there would be slightly less piping
needed in the instillation process.
The maintenance area consists of a storage area, a worktop for working on and storing
underneath and a sink to clean any of the necessary equipment properly and to a high
standard. There is also a storage are for spares onto the bulkhead.
There are also two exits to this room which are required for fire safety. The first is a door
which will be the main entrance to the room, the other is a protected ladder and hatch
which can be used if someone is in the maintenance area when a fire breaks out. There are
two fire extinguishers in this room, one by the door and the other by the emergency ladder
exit. This means a fire can be tackled by the nearest exits which is regarded as the safest
practice possible.
Due to the way the purifiers are sitting and where the maintenance area sits in the room the
I-Beam could be fitted in a straight line allowing for very efficient and quick maintenance.
Room Layout 2
Please make reference to APPENDIX 6 – Drawing 5A
Room Layout 2, is a little smaller than Layout 1, with a footprint of 34m2, uses the same
purifier customization as room layout 1. It has the purifiers sitting in an L position.
Graded Unit: Fuel Purification System
30
The differences are that the maintenance area sits directly in front of the purifiers meaning
that the I-Beam may need to be fitted in a sort of U bend formation. Also with the
maintenance area sitting directly in front and with the room not being as wide then there is
less room for access if maintenance is being provided on any of the purifiers. It also means
that there is a lot of unused space behind the purifiers.
The sludge tank sits slightly more forward in Layout 2, with it sitting in front of the purifier
modules. This would possibly make it easier to access the tank but also using slightly more
piping than Layout 1.
Access is the same with one door facing the purifiers, this would allow for quick inspections
in passing for rounds. There is also an emergency exit hatch at the back of the purifier room
if a fire was to break out. There are fire extinguishers near both exits as to make tackling the
fire easier and more effective.
Room Layout 3
Please make reference to APPENDIX 6 – Drawing 6A
Like Layout 2, Room Layout 3 is a little smaller than Layout 1. This Layout has a footprint of
34.5m2 and is smaller length wise rather than width. It again has the same purifier module L
shape in the design but like Layout 2 lacks the space that Layout 1 gives when talking about
maintenance and access of personnel.
Layout 3 has the maintenance station sitting again in front of the purifier modules but unlike
keeping the spares on the bulkhead at the side it puts the spares on the bulkhead nearest
the entrance to the room. This can make a store check easy but could open the rubber o
rings to a temperature difference from the door if stupidly left open. This could warp them
slightly. Again the I-Beam would have to be fitted in a U bend also.
The entrance is in the corner of the room but the escape hatch has been moved closer to
the forward bulkhead. The fire extinguisher is placed near the entrance for tackling the fire
from the door but the other fire extinguisher is awkwardly place away from the exit, this will
be for anyone doing maintenance, this gives them a chance to grab the extinguisher and
head for the exit.
The sludge tank is moved behind and underneath the purifier modules, this is like Layout 1
and will provide less pipe in the instillation.
Graded Unit: Fuel Purification System
31
Layout Decision Matrix Using a Decision Matrix once again the final room layout will be chosen. It will be like the
previous matrix although slightly smaller.
The Decision matrix will consist of a table of information. That information includes factors
that affect the choice of the layout, such as piping complicity and the footprint area, and
then they will be weighed up against the importance of that factor between 1 to 5 (1 being
the lowest and 5 being of highest importance). A number will then be placed in each factor
for each layout between 1 and 5 (1 being poor and 5 being excellent in this instance).
Once the numbers have been put down for each factor by each layout the layouts number
will be multiplied by the importance factor and then all factors will be added together to
create a total number. The layout with the highest number will be chosen.
Factors Importance Layout 1 Layout 2 Layout 3
Footprint 4 5 3 4
Piping Complicity 4 5 3 4
Maintenance Access 5 5 5 4
Tank Access 3 3 4 3
Evacuation Safety 5 5 5 4
I Beam Instillation 2 5 4 4
Instillation Cost 3 4 3 4
Total 121 103 101
Graded Unit: Fuel Purification System
32
The highest Score is Room Layout 1, this will be the final design layout for the purification
room on the MAERSK Braveheart.
Graded Unit: Fuel Purification System
33
Piping Pipes are known as the silent ‘workers’ of the vessels. They convey fluids or allow air to
enter or to leave a space and are the means through which many control systems on board
operate. They go unnoticed until pipe failure tends to occur and a machine stops, a space is
flooded or oil is spilled. Pipes will penetrate almost every enclosed space on board. There is
no system on a ship that has such enormous potential to cause fire, pollution, flooding or
even total loss. For this reason, the choice of piping is extremely important.
It is required on merchant shipping vessels for the fuel systems that the piping on board be
made of mild steel or other fire resistant materials. Due to cost steel is the best option for
the purifier room. It is a strong and yet versatile metal and can be bought in vast amounts
for rather low prices.
It is calculated in APPENDIX 5 as to what diameter the pipes should roughly be used for each
system. This comes down to the flowrate used in the manuals from Man B&W.
The thickness of the pipes will be compared to the table put forth by Lloyd’s Register for the
classification of piping on ships.
For the HFO system a pipe diameter of roughly 46.3mm should be used.
For the LO system a pipe diameter of roughly 22.9mm should be used.
For the DO system a pipe diameter of roughly 37mm should be used.
Graded Unit: Fuel Purification System
34
When instillation is in process it is advised that the pipe alignment be as straightforward as
can be with a minimum of complication as to minimize the amount of “locked in” stress as
possible. Again it should be mentioned that since they are carrying flammable liquids it
would be best to have as little joints as possible.
Ventilation Capacity of the System In IMO Regulations 2009 it states that “As far as practicable, purifiers and associated components should be placed in a separate room, enclosed by bulkheads having effective construction and rooms should be provided with an independent mechanical ventilation or a ventilation arrangement which can be isolated from the machinery space ventilation” Annex 3.1.1 (IMO 2009) This requires that adequate ventilation of machinery spaces such as the purifier room be of high importance. It should not just be for the crews comfort. Within rooms like the purifier room there is a high likelihood of oil vapour accumulating, this would pose not only a fire risk but also a risk of oxygen depletion for personnel within the engine room. Making sure that there is an adequate ventilation system will also ensure that machinery operates at maximum efficiency no matter what climate changes happen around the vessel. Using the Calculations in APPENDIX 7, specifically APPENDIX 7.2 where the calculated safe ventilation flowrate is 7741.8 m3/hour. Using this flowrate to then find the correct ventilation system required and using a well-known manufacturer in the shipping industry will give this room a great flow of air. The manufacturer chosen to provide the room with fans for the ventilation system is Vent Axia power-line fans. The reason Vent Axia were chosen were because their fans are robustly constructed from galvanised sheet steel and the system is proven to be some of the most reliable in the industry. The model chosen is the Axia LCA1003416 due to its large capacity of air charge. The LCA1003416 has a maximum capacity of 82,800m3/hour and can handle the safe capacity of this room with no problems whatsoever. Its flowrate can be customised to meet the system requirements demanded for this room. It does this using a manually controlled adjustable impeller and can be used in a range of temperatures from -35oC to 56oC and in 95% humidity. (Vent Axia website) This will be of serious benefit in deep sea going vessels due to the environmental challenges ships face. Pictured to the right is the Vent Axia LCA1003416
Graded Unit: Fuel Purification System
35
System Layout
Please make reference to APPENDIX 7.4 – Drawing 7A
Looking at the plan view of the room layout it is shown that the inlet section of the
ventilation system is in blue. This will be placed above head height and behind the purifier
modules to provide the system with good air circulation. There are 4 duct outlets sitting
behind the machinery providing the room with air. On the other side of the room sitting in
front of the purifier modules is the extraction side of the ventilation system. This is shown in
the drawing in Red. There are four extraction ports fitted to the duct. They will be placed
lower than the inlet section of the ventilation due to the oil vapour build up in the room. Oil
vapour tends to be heavier than air so will sit lower in the room, this would make this
position best for the outlet section.
All Ventilation systems come under the ISO 9001 and 14001 and all environmental Policy
put forth by the British government.
Graded Unit: Fuel Purification System
36
Sludge Tank All of the purifier modules used in this design work on the principal of automatic sludge
discharge. This will be happening on continuous operation of the machinery. The sludge that
is separated from the HFO, LO or DO will discharge from the separator to a sludge tank
below the room deck.
In MARPOL it explains what calculations must be done to calculate the capacity of sludge
tanks. It is mentioned in Annex 1, Regulation 10.15.
The capacity of the sludge tank for this system is 81.40 m3 *
The Regulation also states that if the vessel has an incinerator fitted then this volume should
in fact be 50% of this value so for this system a Sludge Tank with a capacity of 40.7m3 or for
ease of construction
*Calculations in APPENDIX 8
Graded Unit: Fuel Purification System
37
Electrics
Cable Sizes
One of the most important aspects of the system is the cable sizes for the power cables that
will supply power to the purifier motors. Using a cable with the wrong rating could spell
disaster for the vessel. This is due to a risk of overheating and then ignition of fire. This is
why it is so important that the correct cable rating is calculated.
The rating calculated for this system has been calculated as 36.90A *
This figure must be taken as the minimum rating that the cable chosen must exceed. A
company that would be advisable to use would be BATT CABLES, they supply a cable that
would be perfect for this system.
The BATT BS5467 SWA/PVC Cable IEC 60502 600/1000V
Name BS5467 SWA/PVC Cable
Operating Temperature 0 - 90 Core No. 3 Size (Square Meter) 6 Current Rating 69
When choosing the cable it was deemed that a cable was needed that had a safety factor
that was between the values of 1.5 – 2.0. This cable has a safety factor of 1.86 which means
it meets the criteria expected. This cable is also armored and made of PVC material, this
means it will be more damage resistant in an engine room where a room can reach higher
temperatures and has a higher chance of not being physically damaged by anything being
dropped on it or hitting it.
*All Cable Calculations to be found in APPENDIX 9.1
Graded Unit: Fuel Purification System
38
Lighting Please make reference to APPENDIX 9 – Drawing 8A
It is absolutely essential for the safety of the crew working in the purifier room that it be
illuminated adequately. The levels for illumination on ships were first put forward by the
IMO in 1998 and since then the UK Government stated in the Safe Working Practices that
they agreed with the number put forward by the IMO. They believe that the lighting levels
for engine rooms be 22 dekalux which is 220 lux. As the purifier room is situated in the
engine room this is the level of illumination expected in the room for the safest possible
environment for the crew to work.
The next thing to look for when selecting lighting fixtures for a shipping vessel is making
sure that the fixture can handle the environment. Due to the purifier room being in the
engine room it is seen as a hazardous environment so the light fitting must be able to
handle this. For this reason the fixture chosen is the RS Pro – XN258/HF light fitting from RS
Components. It is a hazardous area light fitting so would suit this room. The technical
specifications are below:
Name RS Pro – XN258/HF
Type Anti-Corrosive Temperature Classification T4 Wattage 2 x 58 Lamp Type Flueroescent Length 1620mm Width 170mm No of Bulbs 2
The number of lights needed for this room will be 4.12 lights, due to this number it would be
safe to round up to 5 lights. Just because personnel safety is of the highest importance in
the shipping industry.
Graded Unit: Fuel Purification System
39
Emergency Lighting In addition to the main illumination there needs to be emergency exit signs installed into
the purifier room. The emergency lighting needs to still illuminate even in the event of
complete power failure. The model chosen is the RS Pro - NA8/NM3/L19 by RS Components.
The Technical Specifications of the light fixture are as follows:
NAME RS PRO - NA8/NM3/L19
TYPE Down Arrow LAMP TYPE Fluorescent WATTAGE 8W TEMPERATURE CLASSIFICATION T5 LENGTH 420mm WIDTH 221mm DEPTH 58mm
These lighting fixtures will be placed above the exits and a graphic bought with an Up arrow
for the emergency ladder hatch exit to be put over the light fixture there.
Electrical Isolations In case of an emergency, shutdown isolation buttons (in red) will be necessary on all of the
electrical equipment. The Purifier modules come with emergency shutdowns and brakes on
the bowls, it is not advised to do so as it could damage the equipment but in emergencies
damage to equipment trumps the loss of human life.
The room will have an electrical isolation button at the outside of the room, this will be in
case of an emergency which will involve needing to electrically isolate the room. The usual
reasons for this could be flooding or fire.
All Electrical Equipment meets the Electrical Standards and approved codes of practice set
forth by the Health and Safety Executive of the British Government, the highest standards in
the industry.
Graded Unit: Fuel Purification System
40
Maintenance Facilities
Please make reference to APPENDIX 9 – Drawing 9A
All machinery used in industry has to at some point have maintenance done to it, whether it
be regular maintenance that is advised by the manufacturer of the item, regular
maintenance ordered by the chief engineer or even surprise maintenance when a piece of
machinery breaks down for whatever reason. Purifiers have a lot of moving parts within
them therefore will need regular maintenance, these are known as overhauls. During these
overhauls it is usually necessary to move heavy components and doing this with manpower
alone is dangerous and could result in severe injury. For this reason it is advised to install a
means of lifting by some form of mechanical arrangements.
I-Beam An I-Beam is a feature of many engine rooms, it is a strong solid steel beam that is designed
to run above the machinery so that a trolley can run along it. The I-Beam will usually be
configured so as to make the job easier on the crew doing the maintenance. It will run in a
path that is designed to help.
In this design it has been decided that the I-Beam would be best to run directly above the
purifiers running straight from the door with a slight curve at the HFO purifier. There is then
a direct straight over the purifiers to make for easier lifts until a slight curve at the end of
the DO purifier then ending at the maintenance area. This would make overhauls a much
more efficient and easier task.
Trolley and Chain Block Now the I-Beam needs equipment for it to be useful and the equipment needed is a travel
trolley to sit on the beam and the appropriate chain block to lift the purifiers up.
The purifier modules in the room are heavy but the heaviest one there is the HFO purifier
which weighs in at 1490kg which means the equipment needs to be able to lift that at the
maximum for the safest working practice to occur.
The best equipment suited for the job is the Tiger Push Travel Trolley which will sit on the I-
Beam and run the equipment up and down the steel beam. It has a maximum lifting
capacity of 2000kg so it can more than handle the HFO purifier modules and will have no
problem lifting the LO and DO purifiers if necessary. It can be found at the LES store if a
supplier needs found.
Graded Unit: Fuel Purification System
41
The Chain Block is also available from that store. It is the Tiger 2000kg Chain Block. This
means that both the trolley and the chain block have a safety factor of 1.34 which is more
than enough for regular overhauls.
They are both tested to meet the EC Declaration of Conformity.
Graded Unit: Fuel Purification System
42
Maintenance Area
At the end of the I-Beam there is a maintenance area for the purifier modules when there
are overhauls taking place. This is an area where all the pieces of the module can be placed
without having pieces all over the decking. This area will consist of a worktop that will be
clear for the purifier module components to be placed on it, underneath will be some
shelves where common cleaning equipment can be sat for the components can be taken
apart properly without damage. This would stop people scraping at components with
screwdrivers constantly.
Next to the worktop and shelfed area there will be a rather large sink, this means that the
sink can be filled with proper de greasing liquid or cleaning liquid that means the discs can
be sat in there and soak properly before being scrubbed clean. A lot of vessels do not have
this area and will end up with plastic boxes by the purifier but this sink will stop anything
having to be sat on the deck. This will, in the long run, save the company money on
damaged components or components being lost into the bilges. It also means that the
company puts the crew first, an area which makes an overhaul safe and easy makes for
happy and efficient working. The idea is to make overhauls easier and stopping any mistakes
made by engineers who may drop or damage equipment.
Further down the wall is a section for storing spares. This is a good way of keeping a room
organized and clutter free. Simple things such as o rings and spare components that are not
as heavy can be stored here for quick and efficient overhauls.
If the company truly want an efficient cleaning system for the purifier modules then Alfa
Laval offer a Clean In Position (CIP) cleaning module which can be plugged into the
separators and will flush them through with cleaning agents. The speed at which the
cleaning agents are pushed through make for a nice clean finish. This is not a necessity but it
would help strengthen the longevity of the modules lifespans as it is designed by the exact
same technicians and engineers who made the modules.
Graded Unit: Fuel Purification System
43
Fire Safety Please make reference to APPENDIX 10 – Drawing 10A
The most important thing about working at sea, as stated earlier, is the Safety of Life. This means that everything must be done to assure that no one loses their life or is injured whilst working at sea. The biggest cause of death and injury at sea is fire. There is a multiple of factors that cause this but in this day and age it should not be happening. This design will incorporate up to date technologies to assure the safety of all the lives of the crew and to limit the spread of fire as much as possible.
Fire Detectors First of all, preventing a fire is only possible if the fire is known about. This is possible with
the instillation of fire detection equipment. Not only is it a good idea but it is law, SOLAS
states in Chapter II-2, Section 7 that;
“An efficient and effective fire detection system should be fitted in all machinery spaces
which are periodically unattended or which are under manned supervision from a control
room. It is strongly recommended that each system should employ two different types of
detector and it is preferable for at least one flame detector to be included”
For this reason there has to be two types of detectors in this room. The room will have
smoke and flame detectors installed, this means that if one does not work then the other
will detect the fire.
Scott Safety UK Ltd. provide some of the best smoke and flame detectors known to the
marine industry. They also provide manually operated fire alarms that can be placed outside
of the room so crew can trip the fire detection system if the automatic system has not
picked up on the fire, for whatever reason.
Fire Extinguishers Fire Extinguishers are some of the most important firefighting media a seafarer can use, this
can stop a small fire turning into a big one. Within this purifier there are certain types of fire
likely to occur, Class B (ones which involve flammable liquids) as the entire system is
purifying fuel, and Class E (Electrical Fires) from the systems electrics.
The reason that the correct fires must be identified is that tacking the fire with the wrong
medium could make a bad situation even worse. For instance if there is an oil fire starting
and you use a water extinguisher to tackle the fire, the oil will react with the water and
spread the fire, also a water extinguisher on an electrical fire is natural selection at its best.
This means that it would always be best practice to make sure the correct firefighting
Graded Unit: Fuel Purification System
44
medium is available and that the wrong medium is not anywhere near-by. Panic causes
confusion and you do not want someone picking up the wrong medium by accident.
With this information the best firefighting medium is dry powder or foam. IMO Fire Safety
Systems Code suggests these two mediums also. On this recommendation it is suggested
that two 4.5kg dry powder extinguishers would best be fitted where the extinguishers are
shown in Room Layout 1. It is suggested that a 45litre foam applicator is placed in the room
also but best practice would be to have that just outside the door for fighting the fire at the
door in case of escape.
The foam will smother the fire and the dry powder separates and breaks up the fire, thus
extinguished by either medium in the safest manner possible.
Fixed Firefighting Systems Fixed firefighting systems depending on the medium can either stop a fire from starting or
can snuff a fire that is too dangerous for the crew out very quickly.
In this design it is believed that two fixed systems would be best for the safety of the crew.
A fire suppression hi-fog system and a CO2 firefighting system are the two chosen for this
design.
Hi-Fog System
Hi-Fog firefighting systems are a ground breaking firefighting system that rapidly tries to get
the fire under control and suppresses or extinguish it by discharging an extremely fine water
mist at high velocity that will effectively cool the surrounding temperature and thus
minimize any heat-related damage to the room. In this room the sprinkler heads will sit
above the purifiers and be set to a temperature between 57-141oC. The temperature will be
defined after an ambient temperature is set by the client on their vessel. The sprinkler
Graded Unit: Fuel Purification System
45
heads burst and spray out microscopic droplets of water which suppress the fire. The Hi-fog
system is highly effective in neutralizing a fire. It will cause a small amount of damage to the
electrical systems but nowhere near as much damage as a fire or a traditional sprinkler
system. Marioff systems are the best in the business and they are familiar with marine
environments so they would be the best supplier for this system.
CO2 System
When a fire becomes far too dangerous for the crew to tackle from the engine room there is
the CO2 firefighting system. This system is highly effective in extinguishing all classification
of fires but needs to be used as a last resort. The reason for this is that the high
concentration of CO2 destroys the oxygen in the room and therefore is toxic to any person
in the room.
The CO2 system in the purifier room will be in addition to the main CO2 system for the
entire vessel. To do so there will need to be three additional bottles added to the system to
accommodate the purifier room.*
The piping must also be of small-bore hot-dipped galvanised mild steel piping that is
designed to withstand the surge pressures and low temperatures that occur with the
release of CO2.
Graded Unit: Fuel Purification System
46
*Calculations for this are in APPENDIX 10
Room Protection
The engine room is specifically made with A60 bulkheads, decks and doors this means that
the purifier room will be built with these too. The term "A” class means that bulkheads,
decks and doors must resist the passage of the fire (integrity) for 60 minutes. An A60 fire
item must do this and also prevent an increase of 140/180°C of heat on the cold side for 60
minutes.
The prevention of fire does not stop at the bulkhead or doors, there must also be a system
in place to isolate the ventilation system inside the room. Heat, smoke and debris can travel
through the ventilation system and fire will then move through the vessel. Installing fire
dampers where the ducting meets the bulkheads, inlet and outlet, that are also made of an
A60 standard is the best move for this design. Making them automatic is the best option,
this means that putting a temperature sensor at them can shut them down before a fire
even has a chance to get out of hand. They would also be manual in case of a malfunction in
the system. Not only will it stop the spread of fire but it will also stop the fire taking in
oxygen from other areas of the vessel.
Quick Closing Valves are fitted to the oil tanks, these are controlled manually from local and
automatically from another safer area of the vessel.
Graded Unit: Fuel Purification System
47
Verification Strategy
APPENDIX 11 contains all of the theory used to complete this section
After the systems are all installed into the purifier room and the entire thing is completed,
tests must all be made of the equipment and the systems to make sure that they all perform
within the expected parameters. It is also to check that the system operates safely and
according to all regulations set forward by the IMO, Lloyds and all Quality Standards.
All these tests will take place during the pre-sea trials and sea trials by specialist technicians.
Lloyd’s Register call this a Condition Assessment Program (CAP) and this program covers hull
assessment, machinery assessment and cargo systems assessment. A CAP takes 3 months
and every time the vessel passes one of the tasks in the program the company is given a
certificate for each one and these certificates add up to make the vessel cheaper to insure.
Test Purpose Method Completed
Pressure The purpose of this is to make sure there are no leaks throughout the system. Tanks should be checked also when filled to the top.
The method is to gradually bring the pressure up to the full pressure of the system. Then all lines should be traced to check for leaks. Best pay attention to the flanges and the joints in the piping. Valves must be checked also
Electrical equipment
To make sure that all electrical systems are in working order and nothing is overheating which could cause a fire. This also means making sure nothing trips the system.
Motors, Cables and heaters all to be tested. The resistance insulation in the electrical systems need to have the values verified by the use of a megger tester.
Lights To make sure that the lighting is adequate within the purifier room.
The room will be tested by a light meter. This must be done throughout the entire room and the amount needs to be the legal requirement of 220 lux.
Smoke detectors
To make sure the smoke detectors are in working order and have the ability to detect smoke.
The smoke detectors must be tested using an aerosol spray that meets the fire industry standard, to simulate smoke in the detector.
Graded Unit: Fuel Purification System
48
Flame detectors
To make sure the flame detectors are in working order and have the ability to detect flame.
The flames detectors must be tested using a special torch that meets fire industry standard. The torch emits a light frequency that simulates flames in a fire.
Quick closing valves
To make sure the Quick Closing Valves close off completely and register on the system.
The valves operations must be tested locally and remotely. This may be a two person job.
Ventilation To make sure the ventilation system is working correctly.
Check the fan motor for excessive vibration or noise. Check with thermometers after a period of running to make sure temperatures are correct. Make sure air is passing through all of the ducts and make sure the extractor is running correctly also.
Vent Fire Dampers
To make sure the fire dampers are in correct working condition
Closing off the fire dampers manually and remotely should check to make sure the system is in working condition. Fire Dampers are tested to the highest ISO standards possible before being fitted to make sure they work.
Purifiers To test the purifier module and make sure it meets all the specifications required.
The purifier must be started according to manufacturer’s guidelines. All parameters must be inspected with the engineer keeping an eye out for any excessive vibration, noise or leaks from the bowl. All control functions must also be tested.
Purifier Motor
To test that the purifier motor is in working order and not overheating.
Run the purifier up to full speed paying particular attention to the motor. Using a vibration scanner to get all the correct readings to make sure the parameters meet the guidelines set forth by the manufacturer.
Graded Unit: Fuel Purification System
49
Emergency Stops
To test that the emergency stop mechanisms actually stop the machinery intended.
Run the purifiers up to top speed and then activate the emergency stop. The stop time must be timed by an engineer to make sure the shutdown is adherent to manufacturers guidelines.
Preheater To test the preheater is in correct working order.
Run up the system and then make sure the preheater is working within the manufacturers parameters.
Feed pump To make sure that the feed pump is delivering the correct capacity.
Run up the system and take a vibration scan of the pump to make sure it is within parameters. Also check the pressures and make sure they are also within parameters. The tanks must be monitored also to make sure the pump is delivering the correct amount as put forth by the manufacturer.
Drains
To make sure the save-alls and drains are in working order.
Check all save-alls and drains, make sure there are no blockages or leaks.
General Safety
This is to make sure that the purifier room meets the Health and Safety Standards put forth by the British Government. General safety issues to be considered.
Inspect every aspect of the room to be ensured of its safety certification. Hazards must be addressed and remedied as quick as is possible. Hazards to watch for are trips, head injury risks, any hot surfaces, etc.
Graded Unit: Fuel Purification System
50
Cost Estimations The Cost estimations below are taken from research and also from e-mailing Keith Phillips and Jon Christmas at Alfa Laval, they never sent out a receipt but gave rough estimations for me to get a rough idea of the cost. The estimations given were in Euros so the exchange rate at the current time was taken into account. Exchange Rate April 2016 – 1 Euro = 0.79 GBP Item Price (£) Quantity Estimated Total Cost (£)
HFO Purifier Modules – Alfa Laval S976
118212.92 2 236425.84
LO Purifier Modules – Alfa Laval S966 94570.34 2 189140.68
DO Purifier Modules – Alfa Laval S956
78808.61 1 78808.61
Frame Customization 30,000 1 30,000 Valves 500
(average) 50 25000
Tanks 2500 11 27500 Ventilation System 5000 1 5000
Cables (Per one metre) 1.35 150 202.50 Light Fittings 144.43 5 722.15 Emergency Exit Signs 10.19 2 20.38 Trolley 115 1 115 Chain Block 188 1 188 Smoke Detectors 290 2 580 Flame Detectors 320 2 640 Dry Powder Extinguisher 15.54 1 15.54
Foam Extinguisher 45L 900 1 900 Hi-Fog System 30000 1 30000
Co2 Bottles 180 3 540 Total 625798.70
Piping costs were not added. Below is the price range per 3m for the piping. This would be
added later.
£9.89 – £23.26 per 3m
Graded Unit: Fuel Purification System
51
Novel Feature In my experience as a cadet on three different types of shipping vessels I have found a few
features missing from the Fuel Purification systems on board. Personally I feel that some of
these might be useful for all using the system. If the client can find a manufacturer who can
create them then it would be advised to do so.
Alarm for Blocked Water Ports
It would be advised to create a transducer on the outlet side of the water port that could
detect the flow, or lack thereof. Maybe something that could detect in increase in pressure
inside the chamber. The problem found was that a lot of LO was being lost to sludge
discharge.
Adding a Magnetic Flow Straightener in the piping
Magnetic flow Straighteners can be used to reduce swirl and asymmetrical flow profiles
created by elbows in the piping, valves and any other disrupters in the pipe. Sometimes
adding long straights of piping is impractical, un-feasible or uneconomical. A Flow
conditioner, referred to as a straightener, could be cost effective and a solution to reducing
consumption over all within the system.
Back Pressure control from Engine Control Room (ECR)
In experience it has been shown that controlling the flow is a possible option from the ECR.
The problem with this is that when you change the flow you need to then go and adjust the
back pressure for the purifier. This can sometimes mean changing the flow in the ECR and
then running down two flights of stairs to manually change the back pressure. If there was
some way of changing both from the ECR there would be time saved for the engineer to
focus on more important tasks needing completed.
Graded Unit: Fuel Purification System
52
Knowledge and Skills Gained The task was given at the beginning of this project to design a fuel purification system for a
sea going vessel. The fuel purification system was to operate in cooperation with a large 2
stroke engine. The Project Deliverables were the customer’s requirements and they are
found at the beginning of this project. Now at the end of this report it is safe to say that all
those objectives were met for the client as best as possibly can be.
Throughout this project I personally have grown as an engineer and manager, learning new
pieces to add to my knowledge and brand new skills I never knew I would have. These things
are all listed below:
Project Management
Time Management
Drawing Software
Technical Research
Finance Research
Verification Strategy Theory
Further knowledge of the purification system as a whole
How to contact suppliers
Metallurgy on board ships
Rules and Regulations I had no idea about
Greater understanding of how the Hi Fog system works
Floorplan drawing software
Understanding the need for Quality Assurance and Certificates of Conformity’s
Technical Specification writing and understanding
Assessing performance of a system
Breaking down a project
Breaking down a system
Ventilation systems and the calculations
Graded Unit: Fuel Purification System
53
Evaluation Mentioned previously are the knowledge and skills I have learnt during this project but this
section is the overall Evaluation on the project.
Project Management - First of all it is safe to say my knowledge in Project
Management has expanded by the bucket loads. I have learnt how to look at a
project in smaller parts, which makes it less daunting as a task. Putting all these
smaller parts together to create a cohesive piece of work was also a very tough skill I
had to learn. It was easy to do each part individually but to make sure it had
reference to previous sections or drawings was very difficult but I persevered and
got through it.
Gantt Chart - I had no idea before this project what a Gantt Chart was. Now not only
do I understand what a Gantt chart is, I now know how to create one in quite a
stylish manner.
Research Skills – At the start of this project I had quite good research skills, or so I
thought, and I thought this project was so big that I would be in the library, reading
books, searching the internet and emailing my ship contacts all the time. It turned
out quite differently, I found myself only really immersing myself in the internet and
books throughout the technical specifications section as that was the real beefy
section of this entire project. Once the regulations were all picked out I found it
quite easy to find the calculations set forth by these bodies. What made my research
skills extremely good was being able to go back into what we had learnt throughout
our college phases to find calculations to make decisions on this system. This for me
was the toughest aspect of the project.
System Drawing and Floor Plans – I had not looked at engineering drawing software
since high school and that was over 8 years ago. No matter what anyone says about
things, if you do not use specialized skills for quite some time you will take a lot of
time to get back to where you were. I understood this and also understood I would
never be that good so I had to research a good drawing software plan that did most
of the work for me. I found Edraw Max and for this I was so thankful. It had
everything and anything it didn’t have I could make in the programme. This took a
huge weight off my shoulders as this was the section I was dreading the most, I could
have done it manually but it would have looked terrible. Relearning how to do these
drawings and plans is a skill I hope I don’t forget.
Formal Writing – As shown from this section of the report I am not a very formal
person. This project has forced me to reassess how I write reports and technical
design portfolios. For me this was another very difficult task as I have written and
talked this way for several years. To reassess and change that has been a mighty big
Graded Unit: Fuel Purification System
54
task but I personally feel that I have done quite a good job of it. I had to look at
examples of report writing to do this. Taking note of what was written in manuals
and engineering books to try and sound more professional.
Purifier System – This aspect has been quite easy for me, not in a bragging way but
because I believe I had a good knowledge base on this system. I worked very hard
whilst at sea to understand the systems on board and was very lucky to have an
extremely helpful 2nd Engineer Robert thresher who also helped me come up with
topics for the purifier manufacturer Decision Matrix. Although this section was not
necessary I believe it helps to have two contingency plans in this design as you never
know what could happen. The system diagram for me was only going to work one
way as on all three different types of ship, that I sailed on, had this exact design on
the diagram. It made sense for me to make it this way.
The Project as a whole – I worked very hard on this project, harder than I have ever
worked on anything in my entire life and the truth is that I hope it makes the top
criteria. It helps that my classmates have asked me for advice throughout the project
and helps with my confidence in the subject. I doubt I will make their
acknowledgements but I am actually not upset as I really enjoyed this. It opened up a
part of my mind that I had left dormant for so long. The part of my mind that just
loves problem solving and this project was a problem needing solved from start to
finish. No budget meant you made your own, and depending on the type of person
you are you chose an economical project or an expensive lavish one. I opted for Alfa
Laval, they are the most well-known purifier modules in the business. They are not
cheap but they are not the most expensive for sure. They are widely available
meaning parts are cheap and the truth be told it was the best choice for saving
money in the long term and that’s what shipping is about. Saving a company money
so they can still be around in 100 years.
At first I doubted my own ability and was intimidated by the task set in this project. I
have never done anything like this in my entire life, using skills I had not even learnt
yet. Over time that fear diminished with each page I typed out.
Overall I believe this project has been educational and a success. I now have a
respect for the designing stage of the systems on board of the ships we work on. It is
incredible how much goes into one aspect of such a large thing. I feel I have further
my knowledge in project management and my skills on making economical, smart
and effective decisions.
Mind Map This mind map was given in the Project Proposal
Mind Map Revised This mind map below is the final mind map for the project.
APPENDICES APPENDIX 1
Fuel Consumption Calculation
Cl (Fuel Consumption – m3/hr) = C (Specific Consumption – g/kwh) x P (Power – kw) x (1 / ρ
(Density of Fuel – kg/m3)
Assume 100% Load
Specific Consumption = 166 kg/kWh
Power = 61830 Kw
Density = 991 kg/m3 (estimation used on recommended Fuel from manual RMH 380)
Fuel Consumption = 0.166 x 61830 x 1/991
= 10.357 m3/hr
= 10357 litre/hr
Daily Consumption = 10.357 x 24 = 248.568 m3/day
258.568 x 0.991 (density) = 246.33 m3/day = 246330 litres/day (approx.)
APPENDIX 1.1
Throughput Calculation
Throughput (m3/s) = (Centrifuge (l/kwh) x Power (kW)) / (3600 x 1000)
Centrifuge value taken from Section 7.05 of the MAN B&W Manual for the Main Engine
LO Centrifuge = 0.136 l/kWh
Power = 61830 Kw
LO Throughput = (0.136 x 61830) / (3600x 1000)
= 2.34 x 10-3 m3/s
APPENDIX 1.2
Centrifuge Value taken from Section 7.05 of the MAN B&W Manual for the Main Engine
Graded Unit: Fuel Purification System
1
FO Centrifuge = 0.231 l/kWh
Power = 61830 Kw
FO Throughput = (0.231 x 61830) / (3600 x 1000)
= 3.95 x 10-3 m3/s
APPENDIX 1.3
Main engine lubrication oil purification requirement:
To calculate the main engines lubrication requirement this calculation is required
LO Purification (litres/hour) = Power (kW) x LO Centrifuge (l/kWh)
LO Purification = 61830 x 0.136 = 8408.88 litres / hour
APPENDIX 1.4
DO Consumption on Main Engine
Cl = C x P x 1/ρ
Specific Consumption = 166 kg/kwh
Power = 61830 Kw
Density = 890 kg/m3 (estimation used on recommended Fuel from manual RMH 700)
Fuel Consumption = 0.166 x 61830 x 1/890
= 11.53 m3/hr
= 11530 litres/hour
Daily Consumption = 276.72 m3/day = 276720 litres/day
Graded Unit: Fuel Purification System
2
APPENDIX 2
Generator Fuel Consumption Calculation
Cl (Fuel Consumption – m3/hr) = C (Specific Consumption – g/kwh) x P (Power – kw) x (1 / ρ
(Density of Fuel – kg/m3)
Assume 100% Load on generator
Specific Consumption = 186 kg/kWh
Power = 2800 Kw
Density = 991 kg/m3
CI = 0.186 x 2800 x 1/991
= 0.526 m3/hr = 12.61 m3/day
= 526 litres/hr = 12624 litres/day
This number is per Engine so total consumption would be for two generators running:
12.61 x 2 = 25.22 m3/day = 25220 litres/day
APPENDIX 2.1
Auxiliary engine lubrication oil purification requirement:
According to the MAN B&W manual, to calculate the lubrication oil purification rate
required for the generator engines, the following equation has to be used:
𝑄 = 𝑃 × 1.36 ×𝑛
𝑡
Q = required operational flow (litres/hour)
P = Maximum Engine Power (kW)
n = number of turnovers per day of the theoretical oil volume corresponding to 1.36 [l/kW]
or 1 [l/HP] (for HFO = 6)
t = Separating time per day (usually accounted as 23.5 hours and 0.5 hour given for sludging
time on separator)
Q = 2800 x 1.36 x 6/23.5 = 972.26 litres/hour
Graded Unit: Fuel Purification System
3
On board cargo vessels the number of engines running simultaneously must be taken into
account. The Power demand average of many of these vessels is around 40 – 50%, if we use
the average of 43% of the total power of the three auxiliary engines combined then we will
be looking at 1.3 times the total power of one of the auxiliary engines.
So
972.26 x 1.3 = 1263.94 litres/hour
APPENDIX 2.2
Total LO purification requirement from both the Main Engine and Auxiliary Engines:
Main Engine LO Requirements + Auxiliary Engine LO Requirements = Total LO Requirement
8408.88 + 1263.94 = 9672.82 litres/hour
APPENDIX 2.3
Total FO Purification Requirement from both the Main Engine and Auxiliary Engines:
Main Engine FO requirements + Auxiliary Engine FO Requirements = Total FO Requirement
10357 + 1052 = 11409 litres/hour
APPENDIX 2.4
DO Total for M/E and Aux/E
Cl (Aux Engines) = 0.186 x 2800 x 1/890 = 0.585 m3/hr = 585 litres/ hr
Total DO = 11.53 + (2 x 0.526) = 12.13 m3/hr = 12130 litres/hour
Graded Unit: Fuel Purification System
4
APPENDIX 3
Decision Matrix Maths
Factors Importance Alfa Laval Mitsubishi Westfalia
Unit Price 5 20 10 20
Instillation Cost 3 15 9 12
Reliability 5 25 25 25
Ease of Maintenance 4 20 12 20
Spares and Technician Availability 4 16 8 20
Environmental Impact 4 20 20 20
Ease of Use 3 15 12 12
Overall Weight 2 8 8 8
Size of the System 3 15 6 12
Need for Ancillaries 2 8 6 10
TOTAL 162 116 159
Graded Unit: Fuel Purification System
5
APPENDIX 4
SYSTEM DRAWINGS
All of these system drawings were selected as the most appropriate system layouts as
moving any valves meant the system not working.
DRAWINGS:
Drawing Symbol Index
1A . HFO SYSTEM
1B. HFO SYSTEM PARTS LIST
2A . LO SYSTEM
2B. LO SYSTEM PARTS LIST
3A . DO SYSTEM
3B. DO SYSTEM PARTS LIST
Graded Unit: Fuel Purification System
6
DRAWING SYMBOL INDEX
Double Bottom Tank
Heater
Quick Closing Valve Non Return
3 Way Valve
Quick Closing Valve
Purification Unit
Duplex Filter Cock
Globe Valve
Pneumatic Valve
Pressure Indicator
Single Wall Tank
Temperature Indicator
Pump
Hand Operated Gate Valve Non Return Valve
Heater 1
PI
TI
Pump 1
Item No. Component Material Quantity
QCV 1,2,3,4 Non Return Quick Closing Valves
CS 4
QCV 5,6,7,8 Quick Closing Valves CS 4
V15 V16 Hand operated Gate Valves
CS 2
Globe Valves CS 2
Hand Operated Gate Valves
CS 4
Pump ALP 0075 1
Heater EHM 100 1
Pressure Indicators 8
Temperature Indicators
2
Tank Sludge Tank SS 1
Double Bottom Tank Settling and Service SS 4
3 Way Valve 3 Way Control Valve SS 2
Pneumatic Valves CS 2
Sample points Cocks SS 2
Purifier S976 2
Piping Diameter 46.3mm
GRADED UNIT PARTS LIST 1B
STEVEN BRADY HFO SYSTEM
Item No. Component Material Quantity
QCV 1 Non Return Quick Closing Valves
CS 1
QCV 2 Quick Closing Valves CS 1
V 10,11,12,13,14,16 Hand operated Gate Valves
CS 6
V 17,19,20 Hand Operated Gate Non Return Valves
CS 3
Globe Valves CS 2
Hand Operated Gate Valves
CS 4
Pump ALP 0075 1
Heater EHM 100 1
Pressure Indicators 8
Temperature Indicators
2
Tank Sludge Tank SS 1
Double Bottom Tank Settling and Service SS 4
3 Way Valve 3 Way Control Valve SS 2
Pneumatic Valves CS 2
Sample points Cocks SS 2
Purifier S966 2
Piping Diameter = 22.9mm SS
GRADED UNIT PARTS LIST 2B
STEVEN BRADY LO SYSTEM
Graded Unit: Fuel Purification System
1 PARTS LIST 2B
Item No. Component Material Quantity
QCV 2,4 Non Return Quick Closing Valves
CS 2
QCV 1,3 Quick Closing Valves CS 2
Hand operated Gate Valves
CS 1
Globe Valves CS 1
Pump ALP 0115 1
Heater CBM 1
Pressure Indicators 4
Temperature Indicators
1
Tank Sludge Tank SS 1
Double Bottom Tank Settling and Service SS 2
3 Way Valve 3 Way Control Valve SS 1
Pneumatic Valves CS 1
Sample points Cocks SS 1
Purifier S956 1
Piping Diameter = 37mm
GRADED UNIT PARTS LIST 3B
DO SYSTEM STEVEN BRADY
Graded Unit: Fuel Purification System
2
APPENDIX 5
Pipe Calculations
Flow rate Velocities taken from Manuals
HFO – V= 0.6 m/s-1
LO – V = 1.8 m/s-1
DO – V = 1.0 m/s-1
APPENDIX 5.1
HFO Pipe Diameters
Q = Volumetric Flow rate = 11.409/3600 = 3.17x10-3 (usually a large V with a dot)
Area = Q (Volumetric Flow rate) / v (Velocity)
= 3.17x10-3/ 0.6 = 5.28x10-3
Radius = √Area/ π
= √5.28x10-3/π = 0.02313
Diameter = 2 x Radius
= 2 x 0.02313= 0.0463m = 46.3mm roughly
APPENDIX 5.2
LO Pipe Diameters
Q = 9672.82 litres/hour = 9.67 m3/hour = 8.41/3600 = 0.002336
Area = Q/v = 0.002336/1.8 = 0.001297 Radius = √A/π = √0.001297/π = 0.01147 Diameter = 2 x Radius = 2 x 0.01147 = 0.0229m = 22.9mm roughly
Graded Unit: Fuel Purification System
3
APPENDIX 5.3
DO Pipe Diameters Q = 12130 litres /hour = 12.13 m3/hour = 12.13/3600 = 3.37x10-3
Area = Q/v = 3.37x10-3/1.0 = 3.37x10-3
Radius = √A/π = √3.37x10-3/π = 0.0185 Diameter = 2 x Radius = 2 x 0.0185 = 0.037m = 37mm roughly
APPENDIX 6
Room Layout Drawings
Index
4A Room Layout 1
5A Room Layout 2
6A Room Layout 3
Appendix 6.1
The Maths behind the Room Layout Decision Matrix:
Factors Importance Layout 1 Layout 2 Layout 3
Footprint 4 20 12 16
Piping Complicity 4 20 12 16
Maintenance Access 5 25 25 20
Tank Access 3 9 12 9
Evacuation Safety 5 25 25 20
I Beam Instillation 2 10 8 8
Instillation Cost 3 12 9 12
Total 121 103 101
Graded Unit: Fuel Purification System
1
Graded Unit: Fuel Purification System
2
APPENDIX 7
Ventilation
In Lloyd’s Register Chapter 21 Section 10 it states that the ventilation system must be
capable of 30 charges of air per hour.
APPENDIX 7.1
Volume of the Purifier Room
Volume = Length x Width x Height
= 4.6 x 8.5 x 4.4
= 172.04 m3
APPENDIX 7.2
Ventilation Flowrate
Ventilation Flowrate = Volume of Room x Charges of air per hour
= 172.04 x 30
= 5161.2 m3/hour
This would be the legal requirement of air needed but with companies now playing it safer
than years before it is wise to try and make sure the room is ventilated by a factor of 1.5.
So…
Safe Ventilation Flowrate = Legal Flowrate x Safe Factor
= 5161.2 x 1.5
= 7741.8 m3/hour
APPENDIX 7.3
System Layout
7A Vent System Layout
APPENDIX 8
Sludge Tank
In MARPOL it explains what calculations must be done to calculate the capacity of sludge
tanks. It is mentioned in Annex 1, Regulation 10.15
“1. For ships which do not carry ballast water in oil fuel tanks, the minimum sludge tank
capacity (V1) should be calculated by the following formula:
V1 = K1CD (m3)
where: K1 = 0.01 for ships where heavy fuel oil is purified for main engine use, or 0.005
for ships using diesel oil or heavy fuel oil which does not require purification
before use,
C = daily fuel oil consumption (tonnes); and
D = maximum period of voyage between ports where sludge can be discharged
ashore (days). In the absence of precise data a figure of 30 days should be
used. “
Previously the HFO system consumption was shown in m3 and litres
So using further calculations to find the tonnes/day for the entire system
APPENDIX 8.1
Total HFO Calculations in Tonnes
Rough calculations show that 11409litres/hour = 11.306 tonnes/hour
11.306 x24 = 271.34 tonnes/day
APPENDIX 8.2
Using the calculation set forth by MARPOL we can say that:
V = KCD
= 0.01 x 271.34 x 30
= 81.40 m3
Graded Unit: Fuel Purification System
1
APPENDIX 9
System Layout
8A Lighting System Layout
9A I-Beam Layout
APPENDIX 9.1
Cable Calculations
The first thing needing done is the calculation of the Line Voltage. This is shown with
VL = V (Supply Voltage to system) /√3
Where
V = 440V
VL = 440/√3
= 254.034V
Then the next step is to calculate the apparent Power. This is done with the formula
kVA = P (Rated Power of motors) / Pf (Power Factor of the ship)
Where
P = 7.5 kW (This is for all purifiers)
Pf = 0.8
kVA = 7.5 / 0.8
= 9.375 kVA
The last step after that is to calculate the line current. This is done by
IL = kVA / VL
= 9375/254.034
= 36.90 A
APPENDIX 9.2
Lighting Calculations
Watts to lumens calculation formula
The luminous flux ΦV in lumens (lm) is equal to the power P in watts (W), times the luminous
efficacy η in lumens per watt (lm/W):
ΦV(lm) = P(W) × H(lm/W)
So
Graded Unit: Fuel Purification System
2
lumens = watts × H
or
lm = W × H
LIGHT TYPE
TYPICAL LUMINOUS EFFICACY (LUMENS/WATT)
TUNGSTEN INCANDESCENT BULB 12.5 – 17.5 HALOGEN LAMP 16 -24 FLUORESCENT LAMP 45-75 LED LAMP 30-90 METAL HALIDE LAMP 75-100 HIGH PRESSURE SODIUM VAPOR LAMP 85-150 LOW PRESSURE SODIUM VAPOR LAMP 100-200 MERCURY VAPOR LAMP 35-65
Using this table we can say that the fluorescent lamp uses a luminous efficacy of around 60
therefore:
Lm = W x H
= 58 x 60
= 3480 lm
So calculating the number of lights we need to use the lumen method.
The lumen method uses the following equation:
N = (E x A) / ( F x UF x MF)
Where
N = number of lights required
E = required level of illumination of the room (lux)
A = Area of the room (m2)
F = Light given off from each bulb (lm)
UF = Utilization factor for bulb distribution (set at 0.4)
MF = Maintenance Factor for deterioration of bulbs (taken as 0.75)
Therefore:
N = (220 x 39.1) / ( (3480 x 2) x 0.4 x 0.75)
= 4.12 Lights
Graded Unit: Fuel Purification System
1
APPENDIX 10
System Layout
10A Fire Plan
Drawing Index
Smoke Detector
Flame Detector
Extinguishers
Escape Ladder
Fire Alarm
Emergency Exit
Emergency Phone
Hi Fog Sprinkler Head
Firefighting System Calculations
To add the purifier room to the vessels purifier system the number of additional CO2 bottles
that are required to be added to the system to accommodate the room must be calculated.
The Fire Safety Systems Code Chapter 5, section 2.2.1.2 shows how to calculate this:
“For machinery spaces the quantity of carbon dioxide carried shall be sufficient to give a
minimum volume of free gas equal to the larger of the following volumes, either:
40% of the gross volume of the largest machinery space protected, excluding the
casing
35% of the gross volume of the largest machinery space protected, including the
casing (IMO, 2001)
It goes on to state in chapter 5, section 2.2.1.4 that “For the purpose of this paragraph the
volume of free carbon dioxide shall be calculated at 0.56 m3/kg” (IMO, 2001). “
Graded Unit: Fuel Purification System
1
The Volume of the room was calculated earlier in APPENDIX 7.1
Volume = 172.04 m3
40% of the room volume:
Volume x 0.4 = 172.04 x 0.4 = 68.816 m3
To calculate required mass of CO2:
68.816 / 0.56 m3/kg = 122.89kg
To calculate how many 45kg CO2 cylinders are required:
122.89 / 45 = 2.7 bottles
Rounding up to three means that three additional bottles will be required to accommodate
the purifier room into the system
APPENDIX 11
VERIFICATION STRATEGY THEORY
To complete a verification strategy it is first best to understand the theory behind how we
get round to creating a verification strategy for an engineering system. The theory it is based
on is the verification action theory. The diagram below explains the process of understand
what it is you are reference to or the element (item in the system) that you are going to
verify. You then pick the verification action to put the item through which would then define
what you expect before it is installed on ship. Then you run it through after it is installed on
the ship and as you already have the parameters or definitions you will get an obtained
result. You compare the two and it will tell you whether or not the system is working.
The definition of a verification action applied to an engineering element includes the following:
Identification of the element on which the verification action will be performed
Identification of the reference to define the expected result of the verification action (see
examples of reference in Table 1)
The performance of a verification action includes the following:
Obtaining a result by performing the verification action onto the submitted element
Comparing the obtained result with the expected result
Deducing the degree of correctness of the element
Regulations and Standards It is important to note the regulating bodies and works cited within this booklet, for further
referencing or studying to be made for the project by the project team. Below are the
regulatory bodies cited in this report.
SOLAS
MARPOL
Lloyd’s Register
IMO
ISO
Electrical Standards by Health and Safety Executive
Fire Systems Safety Code
International Code for the application of fire test
Graded Unit: Fuel Purification System
12
Bibliography Websites Used:
www.alfalaval.co.uk
http://www.gea.com/global/en/productgroups/centrifuges-
separation_equipment/index.jsp
http://www.kakoki.co.jp/english/products/
https://www.dieselnet.com/standards/inter/imo.php
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/282659/c
oswp2010.pdf
http://marine.man.eu/docs/librariesprovider6/technical-papers/tier-iii-two-stroke-
technology.pdf?sfvrsn=12
https://www.dieselnet.com/standards/inter/imo.php
Rules_and_Regulations_for_the_Classification_of_Ships.pdf
http://www.imo.org/en
http://www.marpoltraining.com/MMSKOREAN/MARPOL/
https://www.dnvgl.com/maritime/
http://www.batt.co.uk/industry2
www.shipserv.com
http://www.marioff.com/
http://www.liftingequipmentstore.com/
http://sebokwiki.org/
www.steeltubedirect.co.uk
http://www.viscopedia.com/viscosity-tables/substances/bunker-oil-marine-fuel-oil/
Graded Unit: Fuel Purification System
12
Documents Used:
IMO, (2001), FSS Code, London: IMO Publishing.
IMO, (2009), Guidelins For Measures To Prevent Fires In Engine-Rooms, London: IMO
Publishing.
IMO, (2014), SOLAS Consolidated Edition, 2014, London: IMO Publishing.
MAN B&W, (2011), MAN B&W G95ME – C, MAN B&W.
MAN B&W, (2014), L27/38 Project Guide – Marine, MAN B&W.
Maritime and Coastguard Agency, 2015, International Management Code for the Safe
Operation of Ships and for Pollution Prevention
Taylor, D.A, 1996, Introduction to Marine Engineering, 2nd edition, Oxford, Butterworth-
Heinemann
MSC/Circ.834, 1998, IMO
Alfa Laval. (2015). Flex separation systems, P-separators 626/636 - Alfa Laval.
Alfa Laval. (2015). Flex separation systems, S-separators 921–987
Graded Unit: Fuel Purification System
12
Graded Unit: Fuel
Purification
System
Progress Report 1 Covering dates: From 04/01/2016 to 29/01/15
2016
STEVEN BRADY
FUSILIER FUELS LTD.
Graded Unit: Fuel Purification System
12
Contents
Research Completed….Page 2
Next Jobs…………………….Page 3
Graded Unit: Fuel Purification System
12
Research Completed
During the period of 04/01/2016 to 29/01/2016 I have carried out the following research:
MAN B&W website as I have chosen the engine
MAN B&W 8S90ME-C9 2 stroke slow speed engine
Emailed Alfa Laval for product guide as their website is not very detailed
Researched software for this project – Inventor Pro, SmartDraw, AutoCad, Edraw
Max
Installed Microsoft office for my home laptop, using Microsoft project in college for
my Gantt charts and also using mindmaple for my mind maps back home.
Have completed roughly 50% of the project proposal and am on track to get that in
on time
Looked up new IMO regulations regarding NOx emissions to see if this will interfere
with our designs, it turns out it kind of does, but the engines can be fitted with new
parts to stop that
Auxiliary Engines – MAN B&W 7L27/38’s – medium speed engines
The three manufacturers chosen for my fuel purification units
Alfa Laval
Mitsubishi
Westfalia
Next jobs
I plan to now carry on with the following deliverables:
Start system Diagrams to be completed for the system design
Complete rough Gantt chart for project
Complete mind map for project
Select all systems equipment
Capacity of the tanks must be decided
Lighting to be decided
Graded Unit: Fuel Purification System
12
Fire isolations to be noted
Fixed firefighting systems and detection to be designed
Metallurgy to be studied to make the right decision for valves and pipes
All costs to be noted and reported to the customer
Regular Progress reports to be handed in
Maintenance and Overhaul facilities need to be considered
A risk assessment to be provided
Focus on time management and keep delivering to the customer on time
Cost estimations for equipment
Finding specifications for my chosen engine
Fuel Calculations
Graded Unit: Fuel Purification System
12
Graded Unit: Fuel
Purification
System
Progress Report 2 Covering dates: From 29/01/2016 to 26/02/15
2016
STEVEN BRADY
FUSILIER FUELS LTD.
Graded Unit: Fuel Purification System
12
Contents
Research Completed….Page 2
Next Jobs…………………….Page 3
Graded Unit: Fuel Purification System
12
Research Completed
This has been handed in 4 days earlier than the proposal and business case.
During the period of 29/01/2016 to 26/02/2016 I have carried out the following
research:
Proposal submitted on the 15/02/2016
Business Case submitted on the 15/02/2016
System design diagrams have been researched as the team needed a revise in their
knowledge of industry standards
Gannt Chart completed
Mind map completed for proposal and business case
System equipment selected:
- The Alfa Laval S976 Flex Series self cleaning centrifugal separator
- The Mistubishi SJ-H series self cleaning centrifugal separator
- The Westfalia OSE - 80 self cleaning centrifugal separator
Some of the fixed fire fighting systems have been decided:
- Hi Fog
Progress Report 1 was handed in on the 29/01/2016
Engine choice was changed after conversation with the client. They felt the option
they had chosen before was not meeting their needs to be environmentally
conscious.
Engine is now the Man B&W 8G95ME-C9
The Auxiliary Engines are still the same as before.
Fuel Consumption was roughly estimated at:
o 166 g/kwh
o 10263.8 l/hr
o 255m3/day
Software costs were submitted in the proposal
Engine specs found
Risk Assessment made for business case but not yet for main design
Graded Unit: Fuel Purification System
12
Time Management is on point at this moment in time
Schedule table made for hand in dates
Deadline Date
Progress Report(s) 1 29/01/2016
2 26/02/2015
3 28/03/2016
4 18/04/2016
5 26/04/2016
Proposal Submission 15/02/2016
Specification Submission 29/02/2016
Final Design Submission 09/05/2016
Evaluation Submission 16/05/2016
Presentation 23-30/05/2016
Cost estimations were found for each manufacturer. The costs below were costs per
purifying unit:
o Alfa Laval £48,000 per unit
o Mitsubishi £80,000 per unit
o Westfalia £50,000 per unit
Client is happy with communication from fusilier fuels ltd and that everything is on
track
Next jobs
I plan to now carry on with the following deliverables:
System Diagrams to be completed for the system design
Select the rest of the systems equipment
Capacity of the tanks must be decided
Graded Unit: Fuel Purification System
12
Lighting to be decided
Fire isolations to be noted
The Fixed firefighting systems and detection to be decided and designed
Metallurgy to be studied to make the right decision for valves and pipes
All costs to be noted and reported to the customer
Regular Progress reports still to be handed in
Maintenance and Overhaul facilities need to be considered
A risk assessment to be provided
Graded Unit: Fuel Purification System
12
Graded Unit: Fuel
Purification
System
Progress Report 3 Covering dates: From 26/02/16 to 28/03/2016
2016
STEVEN BRADY
FUSILIER FUELS LTD.
Graded Unit: Fuel Purification System
12
Contents
Research Completed….Page 2
Next Jobs…………………….Page 3
Graded Unit: Fuel Purification System
12
Research Completed
This has been handed in 4 days earlier than the proposal and business case.
During the period of 26/02/2016 to 28/03/2016 I have carried out the following
research:
Proposal submitted on the 15/02/2016
Business Case submitted on the 15/02/2016
PID Submitted
Progress Report 1 was handed in on the 29/01/2016
Progress Report 2 was handed in on the 26/02/2016
System design diagrams have been researched as the team needed a revise in their
knowledge of industry standards
Gannt Chart completed and being updated as the project progresses
Decision Making Processes researched and Decision Making Matrix chosen to be
best option
Mind map completed for proposal and business case
System HFO Purifier equipment selected:
- The Alfa Laval S976 Flex Series self cleaning centrifugal separator
- The Mistubishi SJ-H series self cleaning centrifugal separator
- The Westfalia OSE - 80 self cleaning centrifugal separator
Some of the fixed fire fighting systems have been decided:
- Hi Fog
Engine choice was changed after conversation with the client. They felt the option
they had chosen before was not meeting their needs to be environmentally
conscious.
Engine is now the Man B&W 8G95ME-C9
The Auxiliary Engines are still the same as before.
Fuel Calculations Completed
Lube Oil Calculation Completed
Diesel Calculations Completed
Software costs were submitted in the proposal
Graded Unit: Fuel Purification System
12
Time Management has had issues, hard copy progress report 2 was handed in on
time, electronical later.
Schedule table still being met for all the hand in dates otherwise
Updates on the Cost estimations were found for each manufacturer. The costs below
were costs per purifying unit:
o Alfa Laval £48,000 per unit
o Mitsubishi £80,000 per unit
o Westfalia £60,000 per unit
Client is happy with communication from fusilier fuels ltd and that everything is on
track
Decision Matrix table was set up, no numbers input as of yet
Executive Summary, Project Summary, Purification Process Summary and
Manufacturer sections written on final design
Next jobs
I plan to now carry on with the following deliverables:
System Diagrams to be completed for the system design, a start has been made
but problems with software have left it static at this moment in time. By the next
progress report the client will know if this is still on track.
Select the rest of the systems equipment in particular the Lube Oil and Diesel Oil
Purifiers
Capacity of the tanks must be calculated and decided upon
Lighting to be calculated and also the type decided
Fire isolations to be noted
The Fixed firefighting systems and detection to be decided and designed
Metallurgy to be studied to make the right decision for valves and pipes
All costs to be noted and reported to the customer
Regular Progress reports still to be handed in
Maintenance and Overhaul facilities need to be considered
A risk assessment to be provided
Graded Unit: Fuel Purification System
12
Graded Unit: Fuel
Purification
System
Progress Report 4 Covering dates: From 28/03/2016 to 18/04/2016
2016
STEVEN BRADY
FUSILIER FUELS LTD.
Graded Unit: Fuel Purification System
12
CONTENTS
Research Completed….Page 2
Next Jobs…………………….Page 2
Graded Unit: Fuel Purification System
12
Research Completed
This has been handed in 4 days earlier than the proposal and business case.
During the period of 28/03/2016 to 18/04/2016 I have carried out the following research:
Systems Diagrams completed
Software used was Edraw Max
Systems done – HFO, LO, Do
Room layouts Finished also, 3 done
Decision matrix completed
Piping calculations done
Metallurgy studied and mild steel the chosen material
Piping calulations completed
Ventilation Chosen Vent Axia
Ventilation calculations completed
Sludge tanks calculated according to MARPOL regs
Fire Safety started
Fixed systems chosen, hi fog and Co2
Detectors chosen, smoke and flame needed due to regulations
All maintenance section completed
Chain block and trolley selected for I beam
I beam layout chosen
Lighting Calculations completed
Lighting chosen
Lighting Layout completed
Emergency lighting and isolations complete
PID, all sections bar the cost section completed
Next jobs
I plan to now carry on with the following deliverables:
Fire section still to be completed
Layout to be completed, might do a fire evacuation plan for extra work
Verification strategy to be completed
Sections thought of are – Pressure Test, Electrics, Fire Detectors, Lights, QCVs, Vents,
Fire Dampers, Motors, Pumps, Drains, Safety features, Isolations, Purifiers??
Also Evaluation section needs started
Novel Feature?? Not sure what to choose but will work very hard to find one
Final document still needs put together
Gantt Chart needs updated with resources and costs
Section 4 of PID needs done to complete the document
Graded Unit: Fuel Purification System
12
Graded Unit: Fuel
Purification
System
Progress Report 5 Covering dates: From 18/04/2016 to 03/05/2016
2016
STEVEN BRADY
FUSILIER FUELS LTD.
Graded Unit: Fuel Purification System
12
CONTENTS
Research Completed….Page 2
Next Jobs…………………….Page 2
Graded Unit: Fuel Purification System
12
Research Completed
During the period of 18/04/2016 to 03/05/2016 I have carried out the following research:
Systems Diagrams completed
Systems diagrams done – HFO, LO, Do
Room layouts Finished also, 3 done
Decision matrix completed
Piping calculations done
Piping calculations completed
Ventilation completed
Sludge tanks completed
Fire Safety section completed
Fixed systems chosen, hi fog and Co2
All maintenance section completed
Lighting Calculations completed
Lighting Layout completed
Emergency lighting and isolations complete
PID, all sections bar the cost section completed
Fire Evacuation Plan completed
Verification Strategy complete
Evaluation Completed
Novel Features Completed
Final Document Pieced together
Gantt Charts completed
PID Completed, costs updated
Next jobs
I plan to now carry on with the following deliverables:
Hand in all Documents
Submit Electronic Copies Online
Graded Unit: Fuel Purification System
12
Graded Unit: Fuel
Purification
System
Proposal
2016
STEVEN BRADY 30140732 5/5PB
FUSILIER FUELS LTD.
Graded Unit: Fuel Purification System
12
CONTENTS
1. Project Brief……………Page 2
2. Description of Task….Page 3
3. Objectives………..……..Page 3
4. Planning…………………..Page 7
a. Engine Specs…........Page 7
b. Research……………...Page 8
5. Deadline Dates.………Page 9
6. Mind Map……….……..Page 10
7. Projected Costs……...Page 11
8. Research Resources.Page 11
9. Client Review…………Page 12
Abbreviations…………….Page 13
References………………..Page 14
Graded Unit: Fuel Purification System
12
Fuel Purification Design Proposal
Prepared for City of Glasgow College and MAERSK
By Steven Brady, Project Manager
Fusilier Fuels Ltd.
1. Project Brief
It is known that MAERSK are one of, if not thee, biggest shipping company in the world at
the moment. They have therfore come to Fusilier Fuels Ltd to provide them with an Oil
Purification Design for their newly built ship the MAERSK Braveheart.
Being Project Manager at Fusilier Fuels Ltd and still at college finishing my HND and PD in
marine engineering, this project has been handed to me to further my skills and knowledge
on the subject as a whole. The project will be not only given to MAERSK for their new build
but handed in to City of Glasgow College for review.
The client has asked that the design be related to their specified two stroke slow speed
marine engine (which will be indentified as just “the engine” pretty regularly throughout
this document) and two electrical generators. The design must include Heavy Fuel Oil (HFO),
Diesel Oil (DO) and Lube Oil (LO) purification systems.
The design will consist of two HFO purifiers which must be capable of performing as
clarifiers, two LO purifiers and a DO purifier.
For this design MAERSK have stated that the Braveheart will have three phase 440 Volts AC
supply at 60Hz as to give us a good way of calculating any pumps or any other electrical
equipment.
Graded Unit: Fuel Purification System
12
2. Description of Task
This proposal document is going to be used as a strategy for tackling the final design portion
of this project and all the relevant information that has been researched. The research will
take place over the sea phase and the 5th college phase.
The information included within this document are:
A list of all the items to be delivered to the client
A rough delivery schedule for the deliverables to the client
An outline specification of the fuel purification systems limits and parameters
A schedule of payment for the amount and time that it has taken for the team to get
this project completed
3. Objectives
To complete this project both efficiently and affectively then there must be objectives with
which to satisfy the brief previously mentioned in the proposal. Below are the following
deliverables for this project:
System Diagrams –
o Heavy Fuel Oil – this must include all of the components for the HFO system
such as the purifiers, service and settling tanks and all other components.
Must inlcude detailed descriptions for the system.
o Lube Oil – this must include all of the components for the LO system, both
the main engine systems and the auxiliary engine systems. Must include all
Graded Unit: Fuel Purification System
12
sump tanks, purifiers and renovating tanks. Detailed descriptions to the
system to be included.
o Diesel Oil – again this must include all of the components necessary for the
running of the DO system. Including the service and settling tank, purifier and
any other components. Descriptions will also be included.
The design of any tanks will be included
System Selections –
o One main option will be selected and two other fall back options shall be
chosen for the client. The decision will be shown by rational description to
the client during this design.
o Main Engine selection has been made by the client but the Auxiliary engines
are still to be decided. Once decided then the system diagrams can begin.
The Gantt Chart will accompany the final design. Keeping track of time taken to
complete the work.
A mind map of the entire project will be included in both the proposal and the final
design.
Design of the Purifier Room –
o Free Volume of the room – this calculation must accommodate for the
purifiers and other associated machinery within the room itself
o Access for proper operations in the room and high performance of the
system also to be accommodated in this process
o Ventilation to and from the room must be calculated and then a drawing
made for the placement of vents within the room
Graded Unit: Fuel Purification System
12
o Tanks – System drawings will be made for the orientation of the tanks and
caluclations made for the capacities
o Components list made for every component within the purifier room. This
will also include detailed descriptions on the components as to give the client
a firm idea of how it all fits into place.
o Plan drawings will be included with the design as to give the client the right
orientation of everything within the room
o Calculations to be made for wiring for the motors within the purifier room
o Maintenance and overhaul facilities to be accounted for within the room.
This will include lifting equipment and calculations, cleaning facilities for the
cleaning of purifiers and storage areas for the spares and tools.
o Luminaries – This will involve calculating the luminaries necessary in the
room and drawing a plan for the luminaries within the room. These will
adhere to SOLAS requirements
Safety –
o Fire Safety-
Fire Isolations – all fire isolations will be installed within SOLAS
requirements
Quick Closing Valves to be noted on the plan for the tanks
Fire evacuation plans will be drawn up for the room
Fixed fire fighting systems to be chosen and detailed rational
descriptions to be given
Fire protection insulation
Fire detection and alarm systems will be selected
Graded Unit: Fuel Purification System
12
o Electrical isolations to be selected and descriptions to be included
o Risk Assessment to be provided with regards to the instillation of the plant
and when the plant is running
Estimated Project Cost-
o Will not include engine costs, that will be dealt with by the client.
o Will include purifier cost, component costs and design costs. Instillation costs
will be added by a contractor.
A floor plan will be given for the final construction of the purifier room.
Graded Unit: Fuel Purification System
12
4. Planning
a. Engine Specifications
I have decided that the best option for the client is to go with the
MAN B&W 9G90ME-C9 for the Engine plant.
MAN B&W 8G95ME-C9
Stroke (mm) 3460
Bore (mm) 900
MCR Output (kw) 61,830
MCR BHP 84,065
Fuel SFOC (g/kWh) 166
b. Research
Regulations:
First thing that has been noticed before anything had begun on this project is that there is a
need for Ultra Low Sulphur fuels in certain Emission Controlled Areas (ECAs). The new
International Maritime Organisation (IMO) emission standards or well known as the Tier I-III
regulations state that in these ECA’s Ultra Low Sulphur Fuel is a must as of January 2016.
For engine designers this means that their engines now need to hit these requirements:
An 80% NOx-cycle value reduction, compared to the Tier I level
A 150% mode cap on each load point in the cycle (the “not to exceed limit”)
Tier III applies when operating the engine in a NOx emission control area. This is to
drop the NOx levels from ships.
Graded Unit: Fuel Purification System
12
Man B&W are aware of the changes in regulations so they provide an option to add an SCR
(Selective Catalytic Reduction) Reactor to their engines. Due to the design of a large
container vessel the client may well want to enter these areas. This has therefore put
forward the fact that there may be need to add this engine part to sustain entering these
areas.
It may add to the costs projected so more research will be required during the design stage.
Design Specs:
The client has not specified which auxiliary engines they require with this as of yet. What
the design team will require will be the engine models and numbers. It would be beneficial
for the project team to know the electric requirement of the vessel, in kw or class and
capacity would work. It would give the project team a more accurate account of what is
required from the engine, both in terms of fuel or lube oil. This could mean that inaccurate
information would be provided and this could spill over into production or design costs.
The Design team will look at three different manufacturers of marine oil purification
systems as to give the client a varied choice in the design. The project team will pick a
design they see fits the mould the best for the vessel and all aspects will be considered to
suit the client, such as cost, technical specifications, etc. but the client will see all three
options to show the design team are doing what is in their best interests. The three
manufacturers being looked at are:
Alfa Laval
Mitsubishi
Westfalia
Graded Unit: Fuel Purification System
12
5. Deadline Dates
Deadline Date
Progress Report(s) 1 29/01/2016
2 26/02/2015
3 28/03/2016
4 18/04/2016
5 26/04/2016
Proposal Submission 15/02/2016
Specification Submission 29/02/2016
Final Design Submission 09/05/2016
Evaluation Submission 16/05/2016
Presentation 23-30/05/2016
32
Graded Unit:
Fuel Purification System
Software
Research
Plan
Objectives
Gantt Chart
Mind Map
Regulations
Engines
Purifiers
Costs
Mind Mapping
Written Documents
Technical Drawings
MARPOL
LLOYDS
COSWP
MAN website
Alfa Laval
Edraw Max
Microsoft Office
Microsoft Project
Materials
Purifiers
List Objectives
Allocate Time
Allocate Costs
Fire Safety
Regulations
Meeting needs of customer
Metallurgy
Engine Choice
Lighting
3 Purifiers
Capacity of Tanks
System Diagrams
Ventilation System
Isolations
Fixed systems
Detection
Room
Purifiers
Lighting
Fire Fighting/ Detection
Sludge Tanks
Dipping Arrangements
Pipes
Valves
Financially
Business
Environmentally
Technically
MAN
Mitsubishi
GEA
System Design
AL -35000 to 50000
MAN B&W 8S90ME-C9
MAN 7L27/38 x 2
AutoCad?
Inventor Pro?
SmartDraw?
6. Mind Map
Within this proposal I have attached a copy of the mind map for this project. If there are any changes they will be mentioned in the
final design and the client will be informed.
0
7. Projected Costs
This Rough Order of Magnitude (ROM) will provide the client with a basis as to what the
estimated costs of the design are.
ROMs will usually come with a percentage of accuracy and for this specific ROM there will
be a roughly +- 40% as there may still be some research that may need to be done and the
contingency plan costs are not set in stone.
When the costs are updated the client will be informed, this way they are constantly kept in
the loop.
Item Cost
Software £4034 Training for Software £1500 Research £3750 Regulation Research £225
Planning £1875 Development £7500 Contingency Plan £3000
Subtotal £21884 VAT @ 20%* £4377
Total Estimated Cost £256261
*Business tax rate provided by HMRC February 2016
8. Research Resources
Due to MAERSK using Windows throughout their fleet the client has requested the software
used be windows compatable software.
List of software used for this project:
Microsoft Word
Microsoft Project
Edraw Max
Microsoft Powerpoint
AutoCad
Graded Unit: Fuel Purification System
12
Microsoft Visio
SmartDraw
Due to the fact this project also requires me getting to information requiring regulations and
engine, purifier particulars I have contacted the companies regarding using their
information online. Fusilier Fuels will also be using the IMO website to gain any information
we don’t already have.
Due to the fact that the Project Manager, me, is also a cadet access to the College Library
has been confirmed as a possibility so information may also come from there.
9. Client Review
This proposal was created to produce a brand new fuel purification system for a container
vessel for the MAERSK shipping company. By selecting this design you, the client, will be
selecting a contempary, upmarket design that will meet your needs to keep you at the top
of the market for another 100 years.
This design will be within the new regulations stated previously and will keep the working
condition of their vessel at a high for years to come and keep the waste to a minimum,
which will keep with MAERSK’s goal of environmental conservation.
The design of the room will be efficient to help with maintenance, meaning the vessel will
not be out of action for too long if maintenance is needing to be done on the unit. This will
cut losses across the board.
The entire design process will be completed with regular feedback to the client throughout
the process. This covers both design and cost implications.
Graded Unit: Fuel Purification System
12
Abbreviations
HND – Higher National Diploma
PD – Professional Diploma
HFO – Heavy Fuel Oil
LO – Lube Oil
DO – Diesel Oil
ECA – Emission Controlled Areas
IMO – International Maritime Organization
SOLAS – Safety of Life at Sea
ROM – Rough Order of Magnitude
NOx – Nitrogen Oxide (in this case emissions)
HMRC – Her Majesty’s Revenue and Customs
BHP – Brake Horse Power
MCR – Maximum Continuous Rating
Kw – Kilowatt
Graded Unit: Fuel Purification System
12
References
http://marine.man.eu/two-stroke/project-guides
MAN B&W G95ME-C9.5-TII.pdf
http://www.alfalaval.co.uk/
http://www.gea.com/global/en/productgroups/centrifuges-
separation_equipment/index.jsp
http://www.mkkeurope.com/
http://marine.man.eu/docs/librariesprovider6/technical-papers/tier-iii-two-stroke-
technology.pdf?sfvrsn=12
http://www.imo.org/en/Pages/Default.aspx
SOLAS: consolidated edition 2009
http://strikingprojectmanagement.com/project-estimation/
Graded Unit: Fuel Purification System
12
Graded Unit: Fuel
Purification
System
Technical Specification Date: 04/03/15
2016
STEVEN BRADY
5/5PB 30140732
FUSILIER FUELS LTD.
Graded Unit: Fuel Purification System
12
CONTENTS
Project summary……………….Page 3
Main Components……………..Page 4
Main Engine..………...Page 4
Auxiliary Engines….…Page 5
Fuels……………………....Page 5
Service Tanks…….…...Page 8
Sludge Tanks……….....Page 8
HFO/LSFO Purifier.….Page 8
LO Purifier………..…….Page 9
MDO Purifier……..…..Page 9
Heaters……………..……Page 9
Pumps………………..…..Page 10
Valves………………..…..Page 10
Piping………………..……Page 10
Electrical Wiring…....Page 11
Operating Environment…..…Page 12
Inclination of Ship.….Page 12
Graded Unit: Fuel Purification System
12
CONTENTS Continued
Room Requirements…Page 12
Lighting…………………….Page 13
Noise………………………..Page 15
Ventilation………………..Page 15
Fire Regulations.…………………..Page 16
Fire Detection…………..Page 16
Fire Containment……..Page 16
Fire Fighting……………..Page 17
Means of Escape………………….Page 18
Maintenance………………………..Page 19
Regulations and Standards…..Page 20
Bibliography…………………….…..Page 21
Abbreviations………………….……Page 22
Graded Unit: Fuel Purification System
12
Fuel Purification Design Proposal
Prepared for City of Glasgow College and MAERSK
By Steven Brady, Project Manager
Fusilier Fuels Ltd.
Project Summary
MAERSK shipping company have contacted Fusilier Fuels Ltd. and has asked for the design of an entire
fuel purification system for their brand new ship the MAERSK Braveheart. This design will in corporate 3
different purification methods. A heavy fuel oil(HFO) purification method, a lube oil(LO) purification
method and a diesel oil(DO) purifications method. The purification system will operate in partner with a
large 2 stroke marine engine designed for deep sea vessels.
The objective of this document is to provide the client with a technical specification that suits the
requirements the client has provided. The technical specification document will provide the client with
the parameters which components and vicinities will satisfy. The defining parameters are a combination
of the requirements of the client, the rules and regulations in place in the shipping industry and those
given by the City of Glasgow College(COGC) who are overseeing the design due to my involvement with
the professional diploma course.
Graded Unit: Fuel Purification System
12
Main Components
Main Engine
The client has chosen the MAN B&W 8G95ME – C9 as the main propulsion for the MAERSK Braveheart.
The engine technical particulars are as follows:
Model MAN B&W 8G95ME-C9
No. of Cylinders 8
Stroke (mm) 3460
Bore (mm) 900
MCR Output (kw) (100%) 61,830
Shaft Speed (rpm) (100%) 80
MCR BHP 84,065
Fuel SFOC (g/kWh) 166
LO Nominal Required Capacity of
Separator (l/kwh)
0.136
LO Throughput (m3/s) 2.34x10-3
FO Nominal Required Capacity of
Separator (l/kwh)
0.23
FO Throughput (m3/s) 3.95x10-3
Graded Unit: Fuel Purification System
12
Auxiliary Engines The client has chosen two Auxiliary engines for the MAERSK Braveheart, they are as follows:
Model MAN B&W 8L27/38
No. of Cylinders 8
Stroke (mm) 380
Bore (mm) 270
MCR Output at 60Hz (kw) 2800
Shaft Speed at 60Hz (rpm) 720
Fuel SFOC (g/kWh) 184
Fuel SDOC (g/kwh) 186
Fuels
All oil based fuels must not have a flash point that is less than 60oC. This is to keep in accordance
with the SOLAS Chapter II-2 Part B Regulation 4
“.1 except as otherwise permitted by this paragraph, no oil fuel with a flash point of less than 60oC
shall be used;*”
MARPOL Annex VI Chapter 3 – Regulation 18 also states that Fuel Oil must confirm to certain
standards:
“ Fuel Oil Quality
(1) Fuel oil for combustion purposes delivered to and used on board ships to which this Annex applies
shall meet the following requirements:
(a) except as provided in sub-paragraph (b):
(i) the fuel oil shall be blends of hydrocarbons derived from petroleum refining. This shall
not preclude the incorporation of small amounts of additives intended to improve some
aspects of performance;
(ii) the fuel oil shall be free from inorganic acid;
(iii) the fuel oil shall not include any added substance or chemical waste which either:
Graded Unit: Fuel Purification System
12
(1) jeopardizes the safety of ships or adversely affects the performance of the
machinery, or
(2) is harmful to personnel, or
(3) contributes overall to additional air pollution; and
(b) fuel oil for combustion purposes derived by methods other than petroleum refining shall not:
(i) exeed the sulphur content set forth in regulation 14 of this Annex;
(ii) cause an engine to exceed the NOx emission limits set forth in regulation 13(3)(a) of
this Annex;
(iii) contain inorganic acid; and
(iv)
(1) jeopardize the safety of ships or adversely affect the performance of the
machinery, or
(2) be harmful to personnel, or
(3) contribute overall to additional air pollution. “
Due to new regulations in place as of this year, the fuel used on the MAERSK Braveheart will
have to be Ultra Low Sulphur Fuels (LSFO) that are in accordance with the ISO 8217 standards.
IMO Tier III is now mandatory for engines installed on vessels that are constructed after 1st of
January 2016 when operating inside an Emission Control Area (ECA). This means for the MAERSK
Braveheart who will surely be operating in these ECAs it will need to use LSFO. The Tier III
Regulations consists of three main requirements:
1. An 80% NOx-cycle value reduction, compared to the Tier I level
2. A 150% mode cap on each load point in the cycle (the “not to exceed limit”)
3. Tier III applies when operating the engine in a NOx emission control area.
Each of the three requirements is important when we are discussing the fuel regulations for the
fuel purification system. This means that we will need to use new technology necessary for Tier
III engines.
It is believed that the client is looking at fitting a Selective Catalytic Reducer (SCR) to the main
engine. SCR’s meet the IMO Tier III standards and beyond by removing roughly 95% or more of
NOx in the exhaust gas of the engine.
Graded Unit: Fuel Purification System
12
Above are how the technology might fit onto the engine.
Graded Unit: Fuel Purification System
12
Service Tanks
All the service tanks will conform to Lloyd’s Register standards, Part 5 – Chapter 14 Section 4.18
“4.18 Fuel oil service tanks
4.18.1 A fuel oil service tank is a fuel oil tank which contains only the required quality of fuel
ready for immediate use.
4.18.2 Two fuel oil service tanks, for each type of fuel used on board, necessary for propulsion
and generator systems, are to be provided. Each tank is to have a capacity for at least eight
hours' operation, at sea, at maximum continuous rating of the propulsion plant and/or
generating plant associated with that tank.
4.18.3 The arrangement of fuel oil service tanks is to be such that one tank can continue to
supply fuel oil when the other is being cleaned or opened up for repair “
Sludge Tanks In accordance with MARPOL Annex 1 Chapter 3 – Regulation 12 there shall be sludge tanks fitted:
“1 Every ship of 400 gross tonnage and above shall be provided with a tank or tanks of adequate capacity, having regard to the type of machinery and length of voyage, to receive the oil residues (sludge) which cannot be dealt with otherwise in accordance with the requirements of this Annex, such as those resulting from the purification of fuel and lubricating oils and oil leakages in the machinery spaces.”
These tanks will also adhere to MARPOL Annex 1 Interpretations
“2 When such ships are fitted with homogenizers, sludge incinerators or other recognized means on board for the control of sludge, the minimum sludge tank capacity (V1) should, in lieu of the above, be: V1 = 1 m 3 for ships of 400 tons gross and above but less than 4,000 tons gross tonnage, or 2 m3 for ships of 4,000 tons gross tonnage and above. “
HFO/LSFO Purifiers
The Seperator units will be able to operate in series but can also be operated as single units
when necessary. This will mean one can work as a purifier and the other can operate as a
clarifier.
For the HFO or LSFO there will be two separator units which will be able to process both fuels
without disrupting the gravity discs in the units.
The units will each individually have a supply pump and a heating unit.
The units will also have individual Emergency Stops and stops outside the room
The Separator units will be self-cleaning. They can have either partial or total discharge options.
Graded Unit: Fuel Purification System
12
LO Purifier
Like the HFO/LSFO Purifiers there will be two Separator units that should be capable of running
in parallel with one another.
There will be a power isolation switch fitted
There will be individual emergency stops fitted to the units and one emergency stop fitted out
with the purifier room itself.
The Separator’s will have their own supply pumps and heaters.
MDO Purifier There will only be one MDO separator unit.
This unit will have its own separate supply pump
There will be an Emergency stop fitted onto the unit itself and one fitted outside of the purifier
room.
A power isolation switch will need to be fitted to this unit.
This separator unit will not require a heater due to diesel oil not needing a temperature rise for
operation, but if supplied or fitted a bypass will need to be added.
Heaters The heaters required here will be either of the tube or plate type.
The heaters must have the ability to control the temperature of the output within 2 degrees of
the desired value for correct operation.
The heaters will be in accordance with Lloyd’s Register Part 5 Chapter 14 – Section 2.7
“2.7 Heating arrangements
2.7.1 Where steam is used for heating fuel oil, cargo oil or lubricating oil, in bunkers, tanks,
heaters or separators, the exhaust drains are to discharge the condensate into an observation
tank in a well lighted and accessible position where it can be readily seen whether or not it is free
from oil, see Pt 5, Ch 15, 6.4 Heating circuits.
2.7.2 Where hot water is used for heating, means are to be provided for detecting the
presence of oil in the return lines from the heating coils.
2.7.3 Where it is proposed to use any heating medium other than steam or hot water, full
particulars of the proposed arrangements are to be submitted for special consideration.
2.7.4 The heating pipes in contact with oil are to be of iron, steel, approved aluminium alloy
or approved copper alloy, and, after being fitted on board, are to be tested by hydraulic pressure
in accordance with the requirements of Pt 5, Ch 12, 8.1 Hydraulic tests before installation on
board.
2.7.5 Where electric heating elements are fitted means are to be provided to ensure that all
elements are submerged at all times when electric current is flowing and that their surface
temperature cannot exceed 220°C. “
Graded Unit: Fuel Purification System
12
Pumps There will be relief valves fitted to the pumps in accordance with MARPOL Annex 1 – Section 4.
The pumps will be fitted in a duplex manner.
Valves The valves in the system will need to be clearly marked and made of the correct material in
accordance with Lloyd’s Register Part 5 Chapter 12 – Section 6
“6.1 Design requirements
6.1.1 The design, construction and operational capability of valves is to be in accordance with an
acceptable National or International Standard appropriate to the piping system. Where valves
are not in accordance with an acceptable standard, details are to be submitted for consideration.
Where valves are fitted, the requirements of Pt 5, Ch 12, 6.1 Design requirements 6.1.2 are
to be satisfied.
6.1.2 Valves are to be made of steel, cast iron, copper alloy, or other approved material suitable
for the intended purpose.
6.1.3 Valves having isolation or sealing components sensitive to heat are not to be used in spaces
where leakage or failure caused by fire could result in fire spread, flooding or the loss of an
essential service.
6.1.4 Where valves are required to be capable of being closed remotely in the event of fire, the
valves, including their control gear, are to be of steel construction or of an acceptable fire tested
design.
6.1.5 Valves are to be arranged for clockwise closing and are to be provided with indicators
showing whether they are open or shut unless this is readily obvious. Legible nameplates are to
be fitted.
6.1.6 Valves are to be so constructed as to prevent the possibility of valve covers or glands being
slackened back or loosened when the valves are operated.
6.1.7 Valves are to be used within their specified pressure and temperature rating for all normal
operating conditions, and are to be suitable for the intended purpose.
6.1.8 Valves intended for submerged installation are to be suitable for both internal and external
media. Spindle sealing is to prevent ingress of external media at the maximum external pressure
head expected in service.
Piping The FO piping will be insulated with 20mm of mineral wool which must have a minimum density
of 150kg/m3 and covered with a glass cloth with a minimum areal density of 400g/m3.
ISO Standard 14726-1:2008 states that the piping will be colour coded to correspond with the
content of each individual pipe.
All of the Purification System piping will be in accordance with the Lloyd’s Register Part 5 Chapter
12, this chapter covers the entire piping design requirements.
Graded Unit: Fuel Purification System
12
Electrical Wiring All electrical cables must be labelled with their corresponding identity code
All electrical cabling must adhere with ISO Standard 14736-1 and IEC standards
Graded Unit: Fuel Purification System
12
Operating Environment
Inclination of Ship
According to Lloyd’s Register Part 5 Chapter 2, all Main and Auxiliary machinery must operate
satisfactorily in certain sea conditions.
All of the machinery mountings will need to confirm to the Lloyd’s Register Part 5 Chapter 1
standards. Below is the inclination of ships table:
Room Requirements The Room will contain 5 purifying units in total, 2xHFO/LSFO separating units, 2xLO separating
units and 1xMDO separating unit.
The room will have two entrances/exits, not including the emergency exits.
The bulkheads of the room will be of an A-60 standard, this will conform with the regulations
outlined in SOLAS Chapter II – 2
Any tanks with a capacity over 500 litres that contain a combustible liquid will need to be fitted
with quick closing valves. This is in accordance with SOLAS Chapter II-2 Regulation 15
The ambient environment of the room must mean that the machinery and equipment are
capable of operating correctly under certain conditions that are outlined in Lloyd’s Part 5
Chapter 1 – Section 3
Below is the Air environment table:
Graded Unit: Fuel Purification System
12
Components Arrangement Temperature (oC)
Machinery and Electrical Instillations
Enclosed Spaces 0 to +45
On Machinery Components, Boilers, In spaces Subject to Higher/Lower Temperatures
According to specific local conditions
On the Open Deck -25 to +45
Below is the Water environment table:
Coolant Arrangement Temperature (oC) Sea Water or Charge Air Coolant inlet
to Charge Air Cooler Enclosed Spaces -2 to +32
Lighting All lighting must conform with accordance to Lloyd’s Register Part 6 Chapter 2 – Section 13
“13.2 Lighting - General
13.2.1 Lampholders are to be constructed of flame retarding non-hygroscopic materials.
13.2.2 Lighting fittings are to be so arranged as to prevent temperature rises which overheat or damage
surrounding materials.
They must not impair the integrity of fire divisions.
13.3 Incandescent lighting
Graded Unit: Fuel Purification System
12
13.3.1 Tungsten filament lamps and lampholders are to be in accordance with Table 2.13.1 Lamps and
lampholders.
13.3.2 Lampholders of type E40 are to be provided with a means of locking the lamp in the lampholder.
13.4 Fluorescent lighting
13.4.1 Fluorescent lamps and lampholders are to be in accordance with Table 2.13.1 Lamps and
lampholders.
13.4.2 Fittings, reactors, capacitors and other auxiliaries are not to be mounted on surfaces which are
subject to high
temperatures. If mounted separately they are additionally to be enclosed in an earthed conductive
casing.
13.4.3 Where capacitors of 0,5 microfarads and above are installed, means are to be provided to
promptly discharge the
capacitors on disconnection of the supply.
13.5 Discharge lighting
13.5.1 Discharge lamps operating in excess of 250 V are only acceptable as fixed fittings. Warning notices
calling attention to
the voltage are to be permanently displayed at points of access to the lamps and where otherwise
necessary “
Graded Unit: Fuel Purification System
12
Noise Sufficient effort will be taken to insulate the room to keep noise to as little as possible for the
rest of the ship. Although ear defenders will be supplied to anyone working in the room. This is in
accordance with Code of Safe Working Practices for Merchant Seamen 2010
In accordance with “IMO MEPC.1/Circ.833: Guidelines for the Reduction of Underwater Noise
from Commercial Shipping to Address Adverse Impacts on Marine Life” vibration control
measures will be in place to help drop the noise levels from the room.
Ventilation In accordance with SOLAS Chapter II-2 Regulation 4 the purifier room will need ventilation to
prevent accumulation of oil vapour.
“2.2.2 Ventilation of machinery spaces
The ventilation of machinery spaces shall be sufficient under normal conditions to prevent
accumulation of oil vapour”
Also in accordance with SOLAS, because the room is seen as a category a machinery space, it will
have to be adequately ventilated including when the machinery is at full power while in
operation.
The Ventilation Ducts passing through the machinery space bulkheads will be fire insulated to an
A-60 standard in accordance with SOLAS
“2 Ventilation ducts should not pass through machinery spaces unless fire insulated to A-60 class
standard.”
Graded Unit: Fuel Purification System
12
Fire Regulations
Fire Detection There needs to be a fixed fire detection and alarm system that are in accordance with the SOLAS
Chapter II-2 – Regulation 7 which explains that:
“2 General requirements
2.1 A fixed fire detection and fire alarm system shall be provided in accordance with the
provisions of this regulation.
2.2 A fixed fire detection and fire alarm system and a sample extraction smoke detection system
required in this regulation and other regulations in this part shall be of an approved type and
comply with the Fire Safety Systems Code.
2.3 Where a fixed fire detection and fire alarm system is required for the protection of spaces
other than those specified in paragraph 5.1, at least one detector complying with the Fire Safety
Systems Code shall be installed in each such space.”
“4.2 Design
The fixed fire detection and fire alarm system required in paragraph 4.1.1 shall be so designed
and the detectors so positioned as to detect rapidly the onset of fire in any part of those spaces
and under any normal conditions of operation of the machinery and variations of ventilation as
required by the possible range of ambient temperatures. Except in spaces of restricted height
and where their use is specially appropriate, detection systems using only thermal detectors shall
not be permitted. The detection system shall initiate audible and visual alarms distinct in both
respects from the alarms of any other system not indicating fire, in sufficient places to ensure
that the alarms are heard and observed on the navigation bridge and by a responsible engineer
officer. When the navigation bridge is unmanned, the alarm shall sound in a place where a
responsible member of the crew is on duty.”
It must also conform with the FSS Code
Fire Containment In accordance with SOLAS Chapter II-2 Regulation 9 the purifier room will be able to contain a
fire if one was to break out.
“1 Purpose
The purpose of this regulation is to contain a fire in the space of origin. For this purpose, the
following functional requirements shall be met:
1 the ship shall be subdivided by thermal and structural boundaries;
2 thermal insulation of boundaries shall have due regard to the fire risk of the space and
adjacent spaces; and
3 the fire integrity of the divisions shall be maintained at openings and penetrations. “
Graded Unit: Fuel Purification System
12
Fire Fighting The purifier room will be equipped with fixed firefighting systems and portable firefighting
systems.
The portable firefighting systems will at the least contain two means of firefighting, dry foam due
to the medium that could ignite in the room.
The fixed systems will need to be two out of the following types of systems:
o High Expansion Foam
o Hi-Fog
o Fixed Gas System (CO2)
These systems will be in compliance with SOLAS Chapter II-2 Regulation 10
“1 Purpose
The purpose of this regulation is to suppress and swiftly extinguish a fire in the space of origin.
For this purpose, the following functional requirements shall be met:
1 fixed fire-extinguishing systems shall be installed, having due regard to the fire growth
potential of the protected spaces; and
2 fire-extinguishing appliances shall be readily available.”
The fixed firefighting systems will also be in compliance with Lloyd’s Part 6 Chapter 1 – Section 2,
Chapter 2 – Section 17 and Chapter 4 – Sections 1&2 which all deal with the fixed firefighting
capabilities of sea going vessels.
Graded Unit: Fuel Purification System
12
Means of Escape The room will have two means of escape due to the room being classed as a machinery space of
category A, this is to be in compliance with SOLAS Chapter II-2 Part D – Regulation 12:
“4.2.1 Escape from machinery spaces of category A
Except as provided in paragraph 4.2.2, two means of escape shall be provided from each
machinery space of category A. In particular, one of the following provisions shall be complied
with:
1 two sets of steel ladders, as widely separated as possible, leading to doors in the upper part of
the space, similarly separated and from which access is provided to the open deck. One of these
ladders shall be located within a protected enclosure that satisfies regulation 9.2.3.3, category
(4), from the lower part of the space it serves to a safe position outside the space. Self-closing
fire doors of the same fire integrity standards shall be fitted in the enclosure. The ladders hall be
fixed in such a way that heat is not transferred into the enclosure through non-insulated fixing
points. The enclosure shall have minimum internal dimensions of at least 800mm x 800mm, and
shall have emergency lighting provisions; or
2 one steel ladder leading to a door in the upper part of the space from which access is provided
to the open deck and, additionally, in the lower part of the space and in a position well separated
from the ladder referred to, a steel door capable of being operated from each side and which
provides access to a safe escape route from the lower part of the space to the open deck.”
Included in the means of escape is the fact that the room will have emergency breathing
apparatus available if a fire were to break out with personnel inside, this is in compliance with
SOLAS Chapter II-2 Part D – Regulation 13:
“4.3 Emergency escape breathing devices
4.3.1 On all ships, with in the machinery spaces, emergency escape breathing devices shall be
situated ready for use at easily visible places, which can be reached quickly and easily at anytime
in the event of fire. The location of emergency escape breathing devices shall take into account
the layout of the machinery space and the number of persons normally working in the spaces.*”
Graded Unit: Fuel Purification System
12
Maintenance It is to be noted that there should be a provision to be made for the maintenance and inspection
of any and all equipment and technical systems that could cause any hazardous situations if
there were to be any operational problems leading to failure.
Once the components of the systems are chosen, each component must have its maintenance
requirements included into the ships planned maintenance schedules.
On top of the manufacturers planned maintenance, it would be deemed wise that the company
set their own Safety Management System (SMS) to provide them with detailed procedures in the
isolation or preparation of this machinery or system that is requiring maintenance.
The reason for this is because the safety of personnel and the protection of the environment.
The inspection, testing and maintenance of any or all safety relief devices must also be included
in the planned maintenance.
All Lifting equipment in the room will conform to the regulations set out in the Lloyd’s register
Code of Lifting Appliances in a Marine Environment
The spacing between the machinery should also be following the guidelines set by Lloyd’s
Register Part 5 Chapter 1 – Section 4 which states that:
“4.1.1 Accessibility, for attendance and maintenance purposes, is to be provided for machinery
plants.”
Graded Unit: Fuel Purification System
12
Regulations and Standards It is important to note the regulating bodies and works cited within this booklet, for further referencing
or studying to be made for the project by the project team. Below are the regulatory bodies cited in this
booklet:
SOLAS
MARPOL
Lloyd’s Register
IMO
ISO
Graded Unit: Fuel Purification System
12
Bibliography Websites Used:
www.alfalaval.co.uk
https://www.dieselnet.com/standards/inter/imo.php
https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/282659/coswp2010.pd
f
http://marine.man.eu/docs/librariesprovider6/technical-papers/tier-iii-two-stroke-
technology.pdf?sfvrsn=12
https://www.dieselnet.com/standards/inter/imo.php
file:///C:/Users/Steven/Downloads/Rules_and_Regulations_for_the_Classification_of_Ships.pdf
http://www.imo.org/en
http://www.marpoltraining.com/MMSKOREAN/MARPOL/
Books Used:
SOLAS Consolidated Edition, 2014
Maritime and Coastguard Agency, 2015, International Management Code for the Safe Operation of Ships
and for Pollution Prevention
Taylor, D.A, 1996, Introduction to Marine Engineering, 2nd edition, Oxford, Butterworth- Heinemann
Graded Unit: Fuel Purification System
12
Abbreviations
COGC – City of Glasgow College
FSS Code – International Code for Fire Safety Systems
HFO – Heavy Fuel Oil
IEC – International Electro technical Commission
IMO – International Maritime Organisation
ISO – International Organization for Standardization
LO – Lube Oil
LSFO – Ultra Low Sulphur Fuel Oil
MARPOL - International Convention for the Prevention of Pollution from Ships
MCR – Maximum Continuous Rating
MDO – Marine Diesel Oil
SDOC – Specific Diesel Oil Consumption
SFOC – Specific Fuel Oil Consumption
SOLAS – Safety of Life at Sea