Governance and Public Private Partenership - The Aguas de La Rioja Case

Embed Size (px)

Citation preview

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    1/27

    1

    Universidad del CEMA

    Doctorate in Business Administration

    The Governance of Public - Private Partnerships

    The case of Aguas de La Rioja SA

    Author: Mr. Juan Ignacio Recabeitia (MBA)[email protected]

    Director of the monograph: Dr. Rodolfo Apreda

    Buenos Aires, February 15, 2011

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    2/27

    2

    ABSTRACT

    The purpose of this study is to identify some suggestions for improvement in the

    implementation of public service concessions from the analysis of the water servicesand sanitation concession in the province of La Rioja (Argentina).

    This analysis was done from the point of regulatory governance applied to public-

    private partnerships following the conceptual framework proposed by Kuo-Tai Cheng

    (2006).

    From this perspective, we identify some problems for which some solutions are

    proposed, concluding that for a successful PPP is a prerequisite the existence of a well-

    developed public governance and a change of perspective from a contracting -

    contractor relationship to a partner to partner one.

    Introduction

    In this paper we will examine the conditions required for good governance in the case of

    Public Private Partnerships (PPP) from the analysis of the particular case of the

    provision of drinking water utilities and sanitation concession in the province of La

    Rioja (Argentina).

    For this analysis will appeal to the methodology proposed by Kuo-Tai Cheng (2006) in

    his work "Researching Regulatory Governance for Privatization of Public Utilities:

    Issues and Reflections".

    In that paper he proposes an analysis methodology for structuring complex governance

    arrangements in the case of PPP, arguing that the institutional analysis of theprivatization policy and regulatory governance provides a better response than the

    traditional notion of "New Public Management" for the deficiencies in privatizing

    public services It also establishes that four key variables to develop an effective

    regulatory system are: degree of delegation of decisions to an independent agent, degree

    of independence of the agent, procedural rules and ex post monitoring.

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    3/27

    3

    Section 1 we will define the concepts of governance, public-private partnership and

    regulatory governance; present the theoretical framework for analysis and then present

    the case to analyze.

    In Section 2, we will identify some defects that occur in the regulatory structure of thecase from the point of view of the methodology adopted.

    In Section 3, we will make some proposals to avoid the defects mentioned in the

    previous section for cases similar to the analyzed.

    Keywords: regulatory governance, privatization, transparency, accountability,

    participation

    Section 1

    Governance

    The term governance covers a wide range of issues which depend on the perspective

    adopted. Apreda (2007) cites some examples, noting differences between government

    and governance.

    For example, those identified by Gerry Stoker in the sense that the term government

    refers to the formal aspects of state including the monopoly of legitimate coercive

    power while the term governance is linked to the forms and styles of government that

    take advantage of blurred boundaries and overlapping between the public and private

    sector, a perspective that pays attention to how the private sector is involved in the

    production of services and strategic decision-making processes.

    Another perspective is that of Bob Jessop that relates the term governance to the

    concept of structure for coordination between interdependent activities among multiple

    stakeholders and self-organization ways.

    He also quotes Robert Keohane who emphasizes the growing importance of procedures

    and proposes three as necessary for an acceptable system of governance: accountability,

    participation, and persuasion.

    Finally, Francois-Xavier Merrien identifies three prerequisites for the study of

    governance in the current political context: the existence of a crisis of governance; that

    this indicates that the traditional state model is in crisis and finally, the focus of

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    4/27

    4

    discussion passes through the ways of managing societies in terms of effectiveness and

    efficiency.

    According to Mohr (2004), the governance perspective challenges the traditional notion

    of state sovereignty. The powers of the state have been displaced by supranationalentities, for sub-national authorities and by institutions and organizations that influence

    the political elite.

    For the purposes of this work, we will adapt the definition of Apreda, understanding

    governance as the field of study and application which three main tasks are:

    1. The search for principles, rules, procedures and best practices that enable the

    efficient management in a permanent changing institutional context

    2. The design, implementation and monitoring mechanisms to establish the

    representation, the commitments and responsibilities, management of conflicts

    of interest, the definition of counterbalanced controls and incentives and

    performance standards of all relevant stakeholders.

    3. The distribution and exercise of authority in decision-making.

    Public-Private Partnerships

    The growth of social demands on public services traditionally provided by the states

    made them to reach the limit of its financial capacity for these purposes. This

    phenomenon, jointly with the view that the public sector was an inefficient

    administrator, led the development of Public Private Partnerships (PPP) in late 1979 as

    a more palatable alternative to the outright privatization (Mohr, 2004).

    A conceptualization of PPP is equated to a network of public and private actors that

    come together to form a cooperative and interdependent working relationship to provide

    better project management and financial solutions. This view of the PPP assumed the

    share of risks and responsibilities.

    This challenges the traditional concept of state (autonomy, centrality, hierarchies)

    introducing the concept of cooperative work, where private actors are involved not only

    in implementing state policies, but also have a degree of participation in decision

    making.

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    5/27

    5

    Sharing in some way the decision making also means sharing the responsibility to

    respond to social or economic problems that are generated between power dependent

    actors That means to share risks.

    These shared responsibilities and risks generate little clarity in determining who mustanswer for decisions and outcomes (public accountability).

    Regulatory Governance

    There is a particular challenge when designing governance schemes for activities that go

    from the pure state level to the PPP relationship were confluence the regulatory,

    bureaucratic aspects, peculiars of the public sphere, with the market mechanisms of the

    private sector.

    According to Kuo-Tai Cheng (2006) in connection with the privatization and regulatory

    governance, there are several challenges ahead.

    First, it is necessary to disaggregate governance mechanisms for the regulation of public

    utilities which have entered the market mechanism (having previously been state owned

    enterprises and monopoly). Secondly, it is necessary to explore the paradox of

    liberalization and privatization on the one hand and "re-regulation" or regulation on the

    other. However, Cheng said, many aspects of privatization and regulation are not

    obvious enough to be observed and these not observed aspects are often the most critical

    in the process.

    He also notes that research related to privatization and regulation is multidisciplinary,

    studies on the subject found in a variety of academic disciplines such as political

    science, economics, sociology, organizational theory, the management and even cultural

    studies.

    Finally, he indicates that it is more difficult to investigate the regulatory mechanisms inthe context of developing countries because the regulatory governance is relatively new

    to them and generally seen as the product of the post-privatization.

    Cheng notes that the key variables to develop an effective regulatory system are:

    1. The extent to which decisions are delegated to an independent agent rather than

    being taken by the main (political)

    2.

    The nature of the structure of governance, to determine the degree ofindependence from the political process agent,

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    6/27

    6

    3. The rules that specify the procedural framework, such as requirements for

    accountability, consultation processes, the ability of political principal to

    overrule the agent, the relative autonomy of financial resources

    4. The magnitude of ex post monitoring, e.g. legislative oversight, judicial review,reviewing citizen complaint procedures.

    Concludes that it is necessary to recognize that the problem is to move between a

    narrow concept of the instruments and regulatory procedures and a wide political scope.

    A theoretical framework for analysis

    Cheng identifies a number of interrelated issues that represent the main characteristics

    of a system of governance for PPP. These aspects are:

    Clarity of Roles

    When identifying the need to implement a policy of privatization and regulation the first

    step is to clarify the policy objectives and the roles of the participants, in particular the

    relationship between the government's proper agencies and regulatory agencies. This

    tends to clarify roles and functions that are characteristic of regulatory agencies and

    which of the ministries or other government agencies.

    Appears here a delicate balance between rigidity and flexibility with regard to socio-political objectives of the policies of PPP (that are not easy to define and vary with the

    societys preferences) and with respect to decision making If left too much discretion in

    the hands of regulators, it could endanger these goals, as the decisions of the agencies

    can not meet the expectations of society.

    Moreover, the democratically elected government is in a better position to make these

    judgments and therefore the legislative framework should provide clear guidance in this

    area, eliminating or minimizing the extent of administrative discretion.

    Participation

    This criterion concerns the extent to which interested parties are allowed to participate

    in the process of privatization and regulation.

    One can see that "participation" and "involvement" may be more mere phrases those

    real solutions. Participation has become fashionable in the current debate about the

    quality of modern society, as many interest groups do not participate in makingdecisions and there is a large gap (potentially dangerous) between rulers and ruled.

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    7/27

    7

    Participation exists when all stakeholders contribute effectively to the process of

    privatization and regulation, improving the quality of decisions and increasing the

    likelihood that agencies receive support and cooperation of businesses, consumers and

    others.

    Participation or at least relevant stakeholders consultation is as important as

    determining the economic and social issues, so that accurate assessments can be made.

    Without it, there is no guarantee that decisions are truly representative of the public

    interest. It is also significant that the agencies give reasoned basis for its decisions to

    ensure fairness. Ultimately, the benefits of participatory processes must be confronted

    with the administrative costs of implementation.

    Independence of the regulator from political power

    If the Regulatory Agency has a direct relationship with the government, it could be

    argued that their decisions are more likely to be compatible with the objectives of

    government.

    Moreover, the delegation of power to set standards or the independence of these

    specialized institutions ensures political fairness, promoting confidence in the

    privatization and regulatory regime, avoiding political interference.

    Keep regulatory intervention beyond the political will to help ensure that agencies are

    free to carry out their functions in the manner they consider best meets the stated

    objectives.

    The delegation in politically independent bodies is an important mean by which

    governments can commit to policies that would not be credible in the absence of such

    delegation. This also ensures greater continuity and stability in policy formulation and

    implementation. Independence is even more necessary if it is a highly specialized field

    that requires expertise.

    Accountability

    Cheng refers here to the accountability of control agencies before the political power

    and society. Considers it desirable that the decisions of regulatory agencies could be

    challenged, if it believes are unfair or show incompetence, but it couldnt be to an extent

    which made ineffective regulation. This challenge can encourage greater openness in

    decision-making process and ensure that there would be fewer opportunities for abuseand capture.

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    8/27

    8

    The lack of control and accountability would create the opportunity for inconsistency

    and unpredictability in decisions, causing uncertainty among the actors who are affected

    by those decisions. It could also undermine the investment potential and the confidence

    of the actors and affect their ability to formulate long term business objectives.

    Transparency

    Cheng notes that it is clear that transparency is closely related to the notion of

    accountability, although the two are not identical.

    Transparency is about the following aspects:

    Public availability of the most important documents

    Publication of important decisions

    Clear and open access to participation

    Definition of the extent to which institutional mechanisms of transparency are

    ethically desirable or even necessary in the process of privatization and

    regulation.

    Transparency means that the policy objectives are clearly expressed, which brings as a

    corollary that clear expectations must be cultivated in the minds of the public in whose

    name the regulation is established.

    Cheng also said that in the broadest sense, transparency requires that citizens can

    influence the way public services are provided, based on their opinions or preferences,

    as well as learn about the decisions that are made. In other words, when the agency

    makes decisions, do it in a reasonable manner, taking into account all relevant issues

    and ensure that they provide a fair and equal treatment to all those affected by the

    decision.A mechanism of transparency is important in itself, since the requirement of regulatory

    agencies to explain their decisions should reduce the likelihood of injustice or

    incompetence

    In addition, transparent decisions made by agencies must meet public interest

    objectives, but doing so should be open and consistent approaches to ensure that there is

    stability and predictability of decision making. It also means that companies can be

    reasonably sure that "ground rules" will not change suddenly, either through a change in

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    9/27

    9

    the overall legal and regulatory framework, or through a change in the way that

    regulators behave within this framework.

    The Case of Aguas de La Rioja SA

    Chronology

    The provision of water and wastewater services in the city of La Rioja was from its

    inception until 1980 made by the National Government through the company Obras

    Sanitarias de la Nation and its predecessors.

    In 1980 through the issuance of the Act N 18586 these services were transferred to the

    provinces. From then until 1988 the services in the city of La Rioja were provided by a

    state agency, the Direccin Provincial de Servicios Sanitarios (Sanitary Services

    Provincial Direction).

    In 1988, was established the Empresa Provincial de Obras Sanitarias of La Rioja

    (EPOSLAR) by provincial Act N 5146 as a legal person under public law with autarky.

    In 1994 and 1995 were authorizing the sale or privatization of EPOSLAR by different

    mechanisms1.

    Only in the year 1996 through the Act N 6281 were established the regulatory

    framework for the provision of water and sanitation services in the province. This

    regulatory framework is of particular interest since it was the rule (along with the

    concession contract) that defined the terms of governance of Aguas de La Rioja SA in

    its different stages.

    In 1999, after failing the EPOSLAR privatization process, was created by Act N 6763

    Aguas de La Rioja SA (ALARSA) as a corporation of the federal Act N19550. By the

    same law is given in concession for 30 years the provision of water and sanitation

    services in the cities of La Rioja, Chilecito and Chamical.

    ALARSA partners were the provincial government (99%) and EPOSLAR (1%).

    ALARSA incorporated documents contained a transitional provision which authorized

    its board to hire a private management for a period of 6 months, with option to purchase

    all the shares that were in state hands.

    The private management of ALARSA was extended to the year 2002 when occurs the

    sale of 100% equity to two companies, Latinaguas SA (10% stake) and Aguas del1 Provincial Acts N 5977 and 6057

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    10/27

    10

    Sudoeste SA (90% of the shares). Both companies, according to the prosecutor's

    impeachment2 were chaired by the same person.

    In 2007 the economic emergency is issued by the Act N 8211 which in practice frozen

    public utility rates. As a result, ALARSA enters in a state of financial distress andrequires financial assistance from the Provincial State.

    This financial assistance (granted by decree N 1011/09) was conditional on the creation

    in the ALARSA structure of a department with the function of manage the financial

    resources (UCI), been chaired by a person proposal by the Province. Similarly, the same

    instrument provides that the Ente nico de Control de Privatizaciones (EUCOP

    Regulatory Agency) conduct an audit of the last 3 years.

    Following the findings and reports by the UCI and the audit ordered, the intervention of

    the service during 90 days was decided, as provided in Article 13 of the Regulatory

    Framework. At the expiration of the intervention (January 2010) was decided the

    termination of the concession contract and created Aguas Riojanas SAPEM 90% share

    of the Provincial Government and 10% employee participation.

    Finally, in October 2010, the General Prosecutor makes a criminal impeachment against

    the ALARSA board members, denouncing a series of fraudulent acts allegedly

    committed during the term of the contractual relationship between ALARSA and the

    Provincial State.

    Facts contained in the prosecutors impeachment

    The most relevant aspects included in the prosecutor's impeachment are:

    Signing of a technical assistance contract with a company apparently linked

    (Latinaguas Operaciones y Servicios SA), when one of its shareholders of

    ALARSA (Latinaguas SA) had the technical background necessary for theprovision of service.

    Contracts with other companies for legal and accounting advice when the

    contract with Latinaguas Operaciones y Servicios included them.

    Maintenance contract with another company (UNISER SA) appears to be related

    (as its president was in some moment president of ALARSA) and which

    2 See prosecutors impeachment in anexe

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    11/27

    11

    representative was at the same time member of the supervisory board of

    ALARSA.

    Financial assistance agreement with UNISER SA for witch ALARSA delivery

    one and a half million pesos to cover accrued liabilities by UNISER in theexecution of works. This financial assistance is contemporary with ALARSAs

    application for financial assistance from the provincial government for the

    maintenance of public service.

    Payment by ALARSA of UNISERs expenditures on account of contributions

    when the object of ALARSA did not involve investments of this type.

    Making unreasonable and unnecessary expenses, including payment of certain

    non-ALARSA cars, cellular telephones, rents and services for people not

    connected with the company.

    ALRSA investment in companies allegedly related, funded in part with tax

    deferrals

    For the purposes of this paper, we consider these issues as an example of flaws in the

    regulatory system, whether ultimately occurred or not as stated in the impeachment.

    The mechanisms of control in regulation

    Regulation of PPP that related the Provincial State with ALARSA was materialized by

    the following instruments:

    The Regulatory Framework for the provision of water and sanitation services

    The Concession Agreement

    Federal act for commercial companies and related legislation

    The regulator (EUCOP)

    We will see below witch control and governance elements and mechanisms exist in

    those instruments.

    Regulatory Framework

    The Regulatory Framework is a piece of legislation which basically establishes the

    conditions under which it must provide the service: who is the holder, in witch way the

    service provision of the service may be delegated, which conditions must meet the

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    12/27

    12

    service, who set the tariff regime, which are the quality standards, who monitors

    compliance with the provisions of the Regulatory Framework.

    It also establishes the rights and obligations of providers and users of the service, the

    property regime and the sanctions regime.

    In the case of the province of La Rioja, the regulatory framework was established by

    provincial act N 6281 in 1996. Its objectives, as specified in Article 4 are as follows.

    Establish a regulatory system to ensure a quality and efficient provision and a

    fair and reasonable price for the regulated service.

    Promote proper maintenance of facilities and the optimization and cheaper

    services.

    Regulate the actions and responsibilities of providers and adequately protect the

    rights and responsibilities of owners and users of the service and monitor

    compliance with the obligations of those involved.

    Promote the efficient delivery of service, according to quality standards that are

    established.

    Protect public health, water resources, environment and rational use of natural

    resources involved.

    To encourage the establishment of effective procedures for preventing and

    resolving conflicts.

    We will see in the next section, to what extent the regulatory framework provisions are

    appropriate to forming an efficient regulatory framework of governance.

    Concession Agreement

    The concession contract defines the rights and obligations of the concessionaire and the

    grantor, sets goals to be met by the concessionaire in terms of investment, quality and

    service coverage.

    It also establishes a system of sanctions in case of failure to meet targets or minimum

    levels of service quality.

    Corporations Act

    There are two aspects of interest in the federal act for commercial companies on thegovernance of a PPP.

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    13/27

    13

    First, it should be noted the provisions to the management bodies (Art. 255 to 279) and

    control (art. 280 to 298). Basically, these provisions place the responsibility of the

    administration in the persons of the directors (elected by the shareholders) and the

    responsibility of the audit in the persons of the trustees (also elected by the

    shareholders).

    Second, in Article 299 paragraph 5 provides that the company must be subject to the

    audit of the Control Authority of her settlement when operating concessions or public

    services.

    Regulator

    The regulator, which as we saw above is a key component of regulatory governance, in

    the case under study presents the following background:

    In December 1995, the Act N 6120 approving the budget for 1995 of the provincial

    government, Article 22 required that:

    "Create in the field of the Treasury Department the "Single Privatization Control

    Entity" with scope above all privatizations performed and that will be performed by the

    Provincial Executive .-

    Entitle the Executive Branch for by Decree, in General Agreement of Staff, determineresponsibilities, structures and other instances of the entity created. "

    Decree N 145/95 3 established powers, structures and other aspects of this entity.

    In 1999, the Act N 6786 amended this article in the sense that one of the agency board

    members should be appointed by "the first electoral minority representation in

    parliament, and for the political party's proposal".

    Later in 2000, Act N 7010 was sanctioned, which states that the entity created by Act

    N 6120 will be an "independent agency of the Provincial Government will have

    operational, technical and economic financial autonomy" and set attributes,

    organization, etc. However, this act was vetoed and we didnt found records indicated

    that the issue has been re-addressed in the provincial legislature.

    We can see that a key to regulatory governance was created and organized with little

    careful. In addition to this chronology is the fact that there isnt an electronic repository

    of decrees and other documents of the Executive of the Province of La Rioja, which

    3 We can not found it in the web

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    14/27

    14

    makes it difficult to make a deeper analysis of the structure, formation, functions and

    other Regulatory Agency relevant aspects.

    Fortunately, there is a paper (Azpiazu et al, 2008) dealing with regulatory problems

    within the Argentina that we used as reference for the analysis of the EUCOP.

    Section 2

    Matters not covered in the regulation

    e will compare the four basic instruments of governance of ALARSA case with the

    requirements of the institutional analysis model proposed by Cheng: Clarity of Roles,

    Participation, Independence of the Regulator of Political Power, Accountability and

    Transparency

    Clarity of Roles

    Cheng said that is a key issue that policy objectives and roles of participants are clearly

    established. It also notes the need for balance between the Regulatory Agency and

    Political Power in terms of discretion in making decisions.

    In the Regulatory Framework there are a number of objectives (Article 4, see above)

    that can be assumed as to achieve policy objectives regarding the provision of sanitary

    services.

    The Concession Agreement states in its Article 2 (Object of the concession) that the

    granting of the concession is to provide the service as specified in the contract itself and

    in the Regulatory Framework, there is no reference by which to discover what the

    political objectives were for who decided to implement the concession. Nor any of the

    issues covered in the Concession Agreement, express political objectives.

    Moreover, with regard to clarity of roles, one example is enough to see that so clearlydoes not exist: the power to set rates.

    Normally this is an issue that is in the hands of the Regulatory Agency, as it is one of

    the prerogatives of the economic regulation of the PPP. In the case under analysis, the

    Regulatory Framework (Art. 12 incise d) on the one hand gives the holder of the service

    (the provincial executive) power to fix rates, and in the other the Regulatory Agency to

    establish the allocation of the tariff regime (Art. 43).

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    15/27

    15

    This confusion of roles (in the same rule there are two figures who have concurrent

    powers), was clear in the Concession Agreement, the EUCOP acts as a technical

    reviewer of the proposals of the concessionaire and approval rests with the grantor (the

    Provincial Executive)

    In conclusion, the clarity of roles between the regulator and political power was not well

    established, or rather, as discussed under "independent regulator" the real decision-

    making capacity was in the executive branch, with the other parties having a minor role.

    Participation

    The Regulatory Framework establishes the obligation to hold a public hearing on the

    occasion of a tariff adjustment and gives to EUCOP the power to convene for other

    cases where it deems fit. Users can petition for a hearing is made public, but such a

    request is for consideration by the regulator. There are no mechanisms to consider the

    possibility of forcing a public hearing (for example, a request supported by a certain

    proportion of users.)

    In practice, within 7 years of the concession, was conducted one public hearing in

    November 2009, a couple of months before the termination.

    This demonstrates the lack of participation of stakeholders in decisions (even only on an

    advisory non-binding role).

    Another key stakeholder in the PPP under analysis is the legislative branch.

    Participation usually goes through the following:

    Participation in the appointment of directors of the regulatory agency.

    Award or approval of substantive law (regulatory framework, concession

    agreement, tariff changes, goal setting, structure of the regulator).

    This is a way of indirect participation of the citizenry, beneficiary or not of the service.

    In this case, the participation of the legislature has been very poor. Basically only the

    dictates of the law establishing the regulatory framework, since in practice the rest of

    the questions were plainly delegated to the executive (the sale of Aguas de La Rioja, the

    concession, the formation of EUCOP, etc.). From the formal point of view there was a

    special committee of privatization who was the link between the legislative and the

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    16/27

    16

    executive in all matters concerning these issues4, has not been possible to find evidence

    that suggest that this committee effectively worked.

    Regulator independence

    In the case under review, from the formal point of view, we can see that theconformation of the Regulatory Agency (EUCOP) went through various vicissitudes

    and that finally its conformation and organization was in practice in the hands of one

    component of Political Power (Provincial Executive).

    This defect is apparent in the following facts:

    1. The EUCOP born in an article in a budget act which in turn delegated to the

    Provincial Executive the definition of all important aspects.

    2. Just 4 years later, an act (N 6786), which comprises representatives of the

    first minority to EUCOP directory, was passed.

    3. When the Legislature passed an act (N 7010) refounding the regulator, the

    Executive vetoed it and did not treat anymore.

    Some examples of the lack of independence between the EUCOP and the Executive are:

    The Decree N. 775/00 regulating the operation of EUCOP provided that in

    the event that the agency's annual balance has losses, it would be "intervene

    immediately" (Art. 30). In practice, far from being underfunded, the EUCOP

    generated since its inception in December 1995, a savings fund. However, in

    2000, the Executive resolved, perhaps relying on the final provisions of the

    same Article 30 that left available to the Executive any surplus in excess of

    10% - take the EUCOP autonomy in the use of funds. To do so, provided

    that the rate of supervision and control, to be paid additionally providers of

    privatized public services (60%) and users (40%) (Act N. 6200, Section 17),

    instead of being charged for company and turned to EUCOP for

    administration, was "entered by general revenues to the operating account

    that the Ministry of Finance and Public Works established (Decree No.

    775/00, Art 21). Thus, forcing the body to be economically dependent on the

    amount that the Ministry will allocate according to their requests for funds

    (Azpiazu et al.)

    4 Provincial Act N 5949

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    17/27

    17

    While board members EUCOP enjoy stability (5 years) in their functions, in

    2000 was removed from office the director nominated by the largest

    minority represented in parliament (as defined in Act N 6786) without

    following the procedure established5.

    Accountability

    At this point it should be consider two situations:

    1. How is accountable the Regulatory Agency before the political power and

    society in the decisions taken

    2. How (and to whom) is the concessionaire accountable for their decisions.

    In the first case, the lack of independence of EUCOP (according to what was seen in theprevious section) adds to the fact that all of its decisions are appealable to the Executive,

    who has the last word in the proceedings. Then, if the Entity is not able to make

    decisions independently and ultimately, seems pointless to be held accountable. And

    indeed it is not expected to EUCOP board members are accountable to political power

    (nor the executive or the legislature), beyond what is established in general for

    provincial public servants.

    As seen in addressing the issue of participation, there is no specific mechanism ofaccountability to society by the EUCOP.

    Regarding the accountability of the concessionaire, the concession law establishing

    guidelines and goals related to public service concession (technical goals). This aspect,

    although improved, did not believe it is key one.

    This is because here we are interested in how the legal entity which is the

    concessionaire is accountable for the decisions adopted within the broad area of

    discretion granted the contract. It clearly indicates that is a contract of results, not

    means. In its Article 7 states that "The powers of regulation and control under the

    GRANTOR shall be exercised so as not to interfere or obstruct the service or the

    substitution of EUCOP in the duties of the concessionaire, in particular, the

    determination of the media that will produce the results required and committed to this

    AGREEMENT. The regulation is aimed at controlling the implementation of

    quantitative and qualitative goals of the service. The GRANTOR shall not take into

    5 Source: draft resolution file 4842-D-2000, Chamber of Deputies, Parliamentary Procedure No. 111Date: 11/08/2000

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    18/27

    18

    account in meeting the goals by the concessionaire, the amount of investment made by

    it. "

    So from the standpoint of contract, the concessionaire is accountable for the results

    achieved against the targets set, have absolute freedom to choose the means it deemsappropriate Obviously, within the legal framework, primarily the Act N 19550.

    But we believe that herein lies a major failure of this PPP, the concessionaire receives

    substantial assets belonging to the state (all facilities, buildings, machinery, etc.

    necessary for a service), which is compounded by the intangible the concession itself (a

    contractually established monopoly for 30 years, a captive customer base and the right

    to a compulsive billing and collection) that are not incorporated into the company's

    assets and therefore are invisible to the law and controls established for commercialcompanies by it but have a decisive influence on economic and financial management

    of the concessionaire.

    Before whom the concessionaire is accountable for the use of this ability to maneuver?

    From a contractual point of view, it is accountable only for results, from the point of

    view of the law of commercial companies is supposed to be under permanent control of

    the Control Authority of its settlement6, although in the case under review any evidence

    hasnt been found that such control was exercised.

    This weakness in accountability is the one that would have allowed the concessionaire

    to perform the resource management questioned in the prosecutor's impeachment,

    basically, contributions and payments to other companies allegedly involved, in the

    absence of a mechanism (outside the Act N 19,550) to ensure that the application of

    these funds (from public) were applied for the maintenance and improvement of the

    service concessioned. In theory the administrative control of the company should have

    done it, but we face a corporation with a shareholder who exercises total control and has

    the ability to manage at their discretion what ultimately is public property.

    Transparency

    Throughout the process of formation and operation of the PPP can be seen a total lack

    of transparency. None of the points made by Cheng (cited above) are even partially

    established.

    6 Federal Act N 19550, article 299 incise 5

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    19/27

    19

    o public availability of documents, examples of that are that can not be found on the

    web nor the decrees of the Provincial Executive or how to get them, not corporate

    balance sheets are available, and the EUCOP lacks even a website.

    As noted above, the sole mechanism provided for civil society participation has beenused only once.

    Section 3

    Below we present a series of proposals aimed at addressing the problems identified in

    Section 2 as follows:

    1. Clarity of Roles and Independence of the Regulatory Agency

    2. Participation Mechanisms

    3. Accountability

    4. Transparency

    Clarity of roles and independence of the Regulatory Agency

    The first distinction to be made in cases like the analyzed is between political and

    Regulatory Agency (in this case the EUCOP).

    We understand that it is possible to draw a parallel between the two figures and those of

    the shareholders on the one hand and directory in the case of corporations in the other.

    Thus, political power would be comparable to shareholders as long as civil society

    representative who is the final receiver of the profits (and losses) resulting from the

    PPP. As such, its primary role as Cheng says, is to establish policy objectives so that the

    Regulatory Agency (comparable to the directory) has a frame of reference as clear as

    possible to make decisions.We are facing a "trust chain" where each link has a specific function. We view the latter

    as a waterfall, where the top level provides the necessary elements for the lower level to

    be able to carry out their duties (including the delegation of sufficient discretion):

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    20/27

    20

    Thus, in the highest part we have the Society which desires and needs have to beinterpreted by the political and translated into policy objectives and the roles of the

    participants.

    It should be remembered here that the political power in societies that have adopted the

    republican representative system is divided into three branches, two of them who should

    be actively involved in the operation of a PPP (executive and legislative), leaving the

    third (judicial) as the ultimate safeguard of the rights of the parties.

    It is imperative that these roles are clearly defined in a specific law (commonly known

    as the Regulatory Framework) and is also necessary that this definition is the result of a

    consensus of society, expressed through their representation in the legislature.

    This need arises from the fact that the horizon of a PPP is long-term (typically 20 or 30

    years) so its basic structure can not be subject to changes in political leadership.

    The Regulatory Framework should focus on clearly defining who are the actors and

    their roles, what are the policy objectives to be achieved, the mechanisms ofparticipation and accountability and transparency minimums.

    Unlike the case of the regulatory framework under analysis, should not contain

    technical matters such as service goals, the tariff regime, the property regime and the

    sanctions regime. All these issues must be dealt with by the Regulatory Agency, and

    that, unlike the Regulatory Framework, are liable to alter in the short and medium term,

    to the beat of the macroeconomic reality.

    Society

    Political Power

    Regulatory Agency

    Concessionaire

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    21/27

    21

    The structure, form of integration, defining competencies, etc. of the Regulatory

    Agency should also be subject to a law that emerged from the consensus for the same

    reasons outlined above. Regulatory Agency is for the PPP which the Board is to the

    Corporations.

    It is therefore essential that its members (directors) must meet high requirements

    (technical competence and ethical integrity) and be appointed by consensus within the

    legislature. We do not believe that the mechanism should be filling positions in the

    direction of the Regulatory Agency for "majority" and "minority" as this ends resulting

    in the transfer of political discussions of parliament to the Agency directory .

    From the point of view of the independence of the Regulatory Agency, we believe that

    its resolutions against the concessionaire should not be appealed before the politicalpower. From the administrative point of view, their decisions should be final.

    As noted in Section 1, this allows that government policies are credible and ensure

    greater continuity and stability of policies and their implementation.

    However, this would result, if the concessionaire feels that the decision of the Agency is

    not just, in only one alternative: argue its case before the courts.

    This is highly inconvenient, introducing an obstacle to a scheme that must be agile. The

    alternative we propose is that of arbitration.

    The contract should include a mechanism for arbitration to an arbitral tribunal appointed

    by agreement between the Regulatory Agency and the Concessionaire. The

    establishment of this court may be varied depending on the issue in dispute and its

    resolutions be accepted as final by the parties.

    This is a modern solution to disputes that arise at the corporate level, although in

    Argentina there is a mechanism that until now hasnt had great development.

    We believe that the sanctions mechanisms contained in the Regulatory Framework and

    Concession Agreement for the case under review, in addition to being completely

    ineffective, are out of place in a PPP. A PPP is a partnership, a partnership between

    public and private sector, where risks and decisions are shared. It's so absurd to think of

    a sanctions regime here as in a partnership between individuals. If the shareholders of a

    corporation have differences, negotiate and reach an agreement or separate, no penalties

    apply.

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    22/27

    22

    Recall that one of the key components of a system of governance is given by persuasion

    (Keohane 2001), separating the processes of communication and negotiation of the use

    and threat of force or punishment.

    We believe that separate the political issues from the implementation and techniquesones facilitate the use of this mechanism for conflict resolution.

    Regarding the role of the concessionaire, we believe that a key issue is the allocation of

    risks. We saw that in a PPP the public and private sector share risks and decisions. In

    the case under study is a brutal transference of risk from public to private sector

    (contract results, not means) that we believe beyond reason.

    In fact, in a corporate enterprise the entrepreneur take risk that offsets the benefits that

    hypothetically will receive. If things go wrong, he ultimately terminates the operation

    and bears the costs of their decision. But in the case of the PPP in general and in

    particular in the one under analysis, the operation should continue whatever the

    economic, political or natural disaster scenario that may arise.

    Before society, the state is responsible for the provision of public services regardless of

    the costs associated with any scenario that may arise.

    Shifting this responsibility to the concessionaire is plainly absurd. And yet, this

    condition is accepted as it is known that ultimately the state will come in relief of the

    concessionaire if necessary.

    We understand that this creates a huge agency problem with the following

    consequences:

    1. encourages the concessionaire to make less risk forecasts

    2. creates a false expectation in the society about the real responsibility of the

    concessionaire

    3. leads to the resolution of contract by the state in an arbitrary manner (under the

    pretext of default by the concessionaire)

    The solution we see is to establish contractually established not only the risks the

    concessionaire has to deal with but the mechanisms for addressing the risks that he does

    not cover and how to establish when the border between the two situations is crossed.

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    23/27

    23

    A practical example for the case under consideration would be given by the availability

    of water sources. Given that this availability depends on rainfall, there may be

    extraordinary drought conditions that are beyond what is reasonably expected to

    contract. To do this in the contract must clearly define when an extraordinary drought

    situation should be considered and which the mechanisms to implement in front of it

    are.

    Participation Mechanisms

    As outlined in Section 1, Cheng states that there is participation where all stakeholders

    contribute effectively to the process of privatization and regulation.

    The key concepts we believe are "all stakeholders" and "effective contribution." We

    believe that this does not mean that all parties are involved in all stages, but all have a

    stake in the moment they are in a position to make an effective contribution.

    In the case under analysis, the mechanism of hearing was established as a "solution" to

    the participation requirement, leaving at the sole discretion of EUCOP which in practice

    resulted in their non-use.

    On the other hand, the public hearing is generally view as a time when the

    concessionaire is accountable to users, such as sitting on the dock.

    We believe that this has nothing to do with the concept of participation outlined above.

    Therefore, we propose a structure for participation, where the different actors make their

    entrance at the time and circumstances under which everyone is able to make an

    effective contribution.

    At a basic level, the participation of society as a whole is through the political

    mechanisms of representation. The next level is given by the participation of

    representatives of society (in the legislative and executive) in the definition of policiesand roles and accountability mechanism that we will see below.

    The third level is established for technical and implementation issues. Here what is

    sought is that the decisions taken by the Regulatory Agency are the result of accurate

    assessments, with the participation or at least the consultation ofrelevant stakeholders7

    7

    It is not the whole society, is part of it that, for the case under consideration, has the ability to make aneffective contribution. For example, user groups, professional associations, chambers of commerce, etc.according to the issue to resolve.

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    24/27

    24

    so as to ensure that decisions are representative of the public interest , fair and well

    founded.

    Accountability

    Following Cheng, we believe the key is the accountability of the Regulatory Agencybefore the Political Power.

    Following the fiduciary network model proposed above, we believe that the same string

    taken in ascending way shows accountability among stakeholders.

    Clearly, the political power is accountable to the Society, according general institutional

    mechanisms. We will not stop at this point.

    Accountability of the Regulatory Agency against political power, is the key to the wholemechanism. It is therefore imperative, like previously seen, a definition and separation

    of roles and responsibilities, powers and independence well established.

    Our proposal is to implement a mechanism for accountability of the board of the

    Regulatory Agency similar to that in corporate governance. There must be a plan of

    action proposed by the Agency and approved by the Legislature, updated annually and a

    yearly report also shows the degree of compliance with the plan, and any corrective

    action plan to conduct.

    The purpose of this mechanism isnt that the political power to review the technical

    aspects witch are the responsibility of the Regulatory Agency, but monitoring progress

    in meeting political objectives that were established to the Agency. Following the trust

    chain model would be similar to the memory and balance that the board submits to the

    shareholders.

    At concessionaire level accountability should be to the Regulatory Agency with target

    indicators that ideally should take the form of a scorecard with dimensions adapted to

    the particular case. Following the proposed model would be similar to the accountability

    of senior management of a corporation performs in front of the directory.

    For the problem of discretionary management of resources and their possible diversion

    of corporate purpose, we believe the solution is the proper functioning of the

    mechanism established under Federal Act N 19550 for state control of commercial

    companies providing public services or are holders of concessions. The fact that in this

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    25/27

    25

    case, these mechanisms have not been effectively applied not makes us think it is

    necessary to develop other alternatives.

    Transparency

    In the case under analysis there are none of the elements required for make transparencya reality.

    As noted above, the most basic is the public availability of the most important

    documents. From the current parameters (web access), including executive decrees are

    not public.

    For the case under review the most important issue to us is the lack of public

    information generated by the EUCOP. We believe it is imperative the existence of a

    website where find all documents and records of the concession, annual reports,

    decisions and their justification.

    It is also a key, as noted by Cheng, who are public policy objectives and the

    construction of clear expectations in the minds of the public. To do this, we consider it

    essential that the technical provisions contained in the contract and other documents are

    appropriate translated to plain language so that they can be easily understood by all

    concerned.

    Conclusions

    From the institutional analysis of key variables of the governance structure, as proposed

    by Cheng, we could make a diagnosis of ALARSA concession that gives us a key

    conclusion: the probability of success of this concession was slim.

    The main argument to support this claim is found in the huge institutional weakness of

    the provincial government in terms of public governance. While this is an aspect notanalyzed in this work, to examine the key variables of governance of the concession we

    found that key areas such as public acts and public resolutions, the independence of

    institutions, participation, etc. were practically nonexistent.

    The question is: is it possible to successfully implement a concession (or other PPP)

    where the public governance is not developed? We believe the answer is a resounding

    no. A state that lacks the internal governance mechanisms has no possibility of

    partnering with the private sector.

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    26/27

    26

    This partnership, rather than the traditional contractual relationship of the Contracting

    State and the Private Contractor - mere contract of adhesion, which involves sharing

    risks and decisions and negotiate on an equal footing, in good faith, as true partners, is

    only possible if the State has institutional mechanisms and appropriated human

    resources.

    A clear example in our opinion is given by the chapter on sanctions which appears in

    the Regulatory Framework and in the Concession Agreement. What is proper in

    construction contracts, is totally out of place in a partner relationship.

    We understand that it requires a deep change of mentality when facing a PPP. We

    believe it is futile to focus on the so-called "economic regulation" in which government

    agents seek to limit private profit and the private looks the chicane that allows him tojustify their actions and maximize their profits.

    If the way chosen is the PPP is essential to walk the path of persuasion Kehoane

    pointing us when he says that liberal democratic institutions must meet standards of

    governance and should encourage participation and persuasion instead of relying on

    coercion and bargaining based on interests.

    But this persuasion, negotiation is only possible when the rules are clear, predictable;

    when one takes into account and consider the views, needs and desires of all interested

    parties; when the expectations of those parties are realistic and when decisions are

    explained and justified.

    aybe an ideal, a utopia. Maybe so, but we believe that every step of progress in this

    direction will allow us to live in a better society.

    References

    Apreda, Rodolfo (2007); Corporate Governance, Buenos Aires, La Ley

    Azpiazu, Daniel et al (2008), Agua y energa: mapa de situacin y

    problemticas regulatorias de los servicios pblicos en el interior del pas,

    Buenos Aires, FLACSO.

    Cheng Kuo-Tai (2006), Researching Regulatory Governance for Privatization of

    Public Utilities: Issues and Reflections,Journal of National Taipei University of

    Education, Vol 19, N2, pag 133-160.

  • 8/6/2019 Governance and Public Private Partenership - The Aguas de La Rioja Case

    27/27

    Kehoane, Robert (2001), Governance in a Partially Globalized World, The

    American Political Science Review, Vol 95, N1, pag 1-13.

    Mohr, Alison (2004), Governance through public private partnerships:

    Gaining efficiency at the cost of public accountability? , Proceedings of theSummer Academy, Inter-University Research Centre for Technology, Work and

    Culture (IFZ).[Date accessed: November 12, 2010] Available at:

    http://www.ifz.tugraz.at/index_en.php/article/articleview/658/1/30/

    [Date accessed: November 19, 2010]. Available at:

    http://www.noticiasnoa.com.ar/newnoa/index.php?option=com_content&view=

    article&id=11988:el-estado-denuncio-a-aguas-de-la-rioja&catid=18:politica

    OECD (2005), Guidelines on Corporate Governance of State-owned Enterprises

    , Paris, OECD Publications.

    United Nations Economic Commission for Europe (2008), Guidebook on

    promoting good governance in public-private partnerships , New York and

    Geneva, United Nations Publications.