Mitsubishi Electric Automation, Inc. 500 Corporate Woods Parkway, Vernon Hills, IL 60061 phone: 847.478.2100 An ISO9001 Certified Company
1 | P a g e R 7 2 - 1 2 1 - S L S A S G - 0 0 5
How To Procedure
GOT Program Restore using GT Designer 3
Revision: A
Purpose: To restore all program files to the GOT
Required Tools:
PC with GT Designer 3 installed Generic USB Mini B cable
Consumable Parts:
None
Mitsubishi Electric Automation, Inc. 500 Corporate Woods Parkway, Vernon Hills, IL 60061 phone: 847.478.2100 An ISO9001 Certified Company
2 | P a g e R 7 2 - 1 2 1 - S L S A S G - 0 0 5
Task 1: Connect the USB MINI B cable between PCs USB port and GT1000 Front USB port. When cable is connected for the first time the USB Driver will automatically be installed.
.
Pull here to access the USB port
Pull here to access the USB port
Mitsubishi Electric Automation, Inc. 500 Corporate Woods Parkway, Vernon Hills, IL 60061 phone: 847.478.2100 An ISO9001 Certified Company
3 | P a g e R 7 2 - 1 2 1 - S L S A S G - 0 0 5
Task 2: Open the GT Designer3 back up saved Project File from hard drive location and double click on the [*.GTW] file.
Task 3: Select the communication method
Step1: Follow this step to set the communication Method to connect the personal computer to the GOT with a USB cable.
a) Select [Communication Configuration] from the Communication Menu.
Mitsubishi Electric Automation, Inc. 500 Corporate Woods Parkway, Vernon Hills, IL 60061 phone: 847.478.2100 An ISO9001 Certified Company
4 | P a g e R 7 2 - 1 2 1 - S L S A S G - 0 0 5
b) Select [USB]
c) Click on the [Test] Button
d) The following Window should appear. If it does not, disconnect the USB cable from PC and reconnnect to try again. Click on the [OK] button to close.
e) Click on the [OK] button to close Communication Configuration Window.
b
c e
Mitsubishi Electric Automation, Inc. 500 Corporate Woods Parkway, Vernon Hills, IL 60061 phone: 847.478.2100 An ISO9001 Certified Company
5 | P a g e R 7 2 - 1 2 1 - S L S A S G - 0 0 5
Task4: Write to GOT Step 1: From the [Communication] Menu, Select [Write to GOT]
Step 2: Click the [OK] Button, USB should be the Communication method selected.
Mitsubishi Electric Automation, Inc. 500 Corporate Woods Parkway, Vernon Hills, IL 60061 phone: 847.478.2100 An ISO9001 Certified Company
6 | P a g e R 7 2 - 1 2 1 - S L S A S G - 0 0 5
Step 3: Click the [GOT Write] button. All other items should be kept at Default as shown here except the
two items below.
1. If a Compact Flash Card is installed and the Project Files are too large to fit in the [C: Built-in Flash Memory], Select [A: Standard CF Card] in the Destination Drive Selection. Item a.
2. If this is a NEW GOT, the selection [Include required OS in the project data] must also
be selected. Item b.
a b
Mitsubishi Electric Automation, Inc. 500 Corporate Woods Parkway, Vernon Hills, IL 60061 phone: 847.478.2100 An ISO9001 Certified Company
7 | P a g e R 7 2 - 1 2 1 - S L S A S G - 0 0 5
Step 4: The following Window will appear.
Click the [YES] button to continue When Finished the following window will appear and the GOT Hardware will Reboot itself.
Click the [OK] button to continue
Mitsubishi Electric Automation, Inc. 500 Corporate Woods Parkway, Vernon Hills, IL 60061 phone: 847.478.2100 An ISO9001 Certified Company
8 | P a g e R 7 2 - 1 2 1 - S L S A S G - 0 0 5
The Communicate with GOT Window will now appear and show you the Write Data Size and the Write Drive Information.
Step 5: Click the [Close] button
Task5: Recycle the GOT Power
If the GOT prompts you to Cycle Power do so at this time. Otherwise the Restore procedure is