© 2013 Chevron Corporation. All rights reserved.
Gorgon Project Plant Site
Gorgon Project work continues to progress with the installation of all three amine absorbers, construction of the LNG Train 1 and acid gas removal unit (AGRU) Train 1.
2
Amine Absorbers
AGRU Train 1
LNG Train 1
© 2013 Chevron Corporation. All rights reserved. 3
Gorgon Project Plant Site
Fourteen modules are now installed at the plant site and work continues on the civil and underground scope of work.
© 2013 Chevron Corporation. All rights reserved. 4
Gorgon Project Plant Site
Pre-assembled Rack Modules
Work continues to connect the more than 180 pre-assembled rack (PARs) modules which have arrived to date. Once complete they will be the main artery of the LNG plant, carrying gas from one process unit to another.
© 2013 Chevron Corporation. All rights reserved. 5
Gas Turbine Generators
Three of the five gas turbine generators (GTGs) are now on their foundations at the plant site.
© 2013 Chevron Corporation. All rights reserved.
LNG Train 1
All four modules of the LNG Train 1 central pipe rack are on their foundations. The pipe racks are key components for process cooling within the LNG train.
6
LNG Train 1
© 2013 Chevron Corporation. All rights reserved.
Acid Gas Removal Unit (AGRU) Train 1
The AGRU Train 1 is taking shape on Barrow Island. The AGRU trains will separate the reservoir CO2 from the raw natural gas.
7
© 2013 Chevron Corporation. All rights reserved. 8
AGRU Train 1
Acid Gas Removal Unit (AGRU) Train 1
Amine Absorber AGRU process modules
Two AGRU process modules and an amine absorber have been installed for AGRU Train 1.
© 2013 Chevron Corporation. All rights reserved. 9
LNG Tanks
LNG Tank 1 LNG Tank 2
The LNG tanks continue to take shape with the concrete pours for the outer shell progressing, the walls on LNG Tank 1 are on schedule and preparations are underway for its roof pour.
© 2013 Chevron Corporation. All rights reserved. 10
Condensate Storage Tanks
Condensate Tank 1
Condensate Tank 3
The Project’s four condensate tanks are taking shape. The internal roofs have been partially raised and construction of the outer roofs on tanks 1 and 3 has commenced.
© 2013 Chevron Corporation. All rights reserved.
Permanent Operations Facility
11
Permanent Operations Facility
Operations Center
At the Permanent Operations Facility, the operations center, warehouse and laboratory buildings are the current focus of construction activity.
© 2013 Chevron Corporation. All rights reserved. 12
Carbon Dioxide Injection Project
CO2 Injection Well Drill Center C
CO2 Injection Well Drill Center B
CO2 Injection Well Drill Center A
Construction activities have commenced on the 4.3-mile (7.0-km) pipeline for the Carbon Dioxide Injection Project.
Pipeline
© 2013 Chevron Corporation. All rights reserved.
The LNG Jetty
13
Work continues on the 1.3-mile (2.1-km) LNG jetty. The roadway connecting the materials offloading facility (MOF) and 43 caissons are now in position.
© 2013 Chevron Corporation. All rights reserved.
The LNG Jetty
Work continues to lift the pre-assembled racks (left) and jetty roadways (right) into position.
14
© 2013 Chevron Corporation. All rights reserved. 15
The LNG Jetty
More than half of the 54 pre-assembled racks (PARs) are now installed. The PARs will transport LNG from the plant site to the two loading platforms at the end of the LNG jetty.