Page 1: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

G.O.D.I.S Complex:“Gaurdian of Defense, Intelligence & Surveillance”

Project Advisor: Dr. James Lang

Team Leader: Dan Dalton

Chief Engineer: Eugene Mahmoud

Propulsion Specialist: Caitlin Smythe

Page 2: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Motivation:Northrop Grumman-Bird of Prey

U.S. Patent:5984231 June 19th, 1998

Image from: www.area51zone.com

Page 3: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Outline of Presentation

• Mission Profiles & Prioritization

• Preliminary Vehicle Configurations

• Downselect Criteria

• GODIS Configuration

• GODIS Performance

• Aerodynamics, Stability & Control

• Engine Integration

• Weights & Sub-systems

• Cost and Supportability

• Conclusion

Page 4: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Mission #1

Mission #2

Mission Profiles

Page 5: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Mission #5

Mission #4

Mission #3

Page 6: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Mission PrioritiesMission #1

Mission #2

Mission #4

With Fallouts:

Mission #3

Mission #5

Page 7: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Vehicle ConfigurationsConfiguration #1

Endurance/Performance

Configuration #3High-Speed Fighter

Configuration #2High-Altitude Bomber

Configuration #4Dolphin

Configuration #5Low-Altitude Bomber

Configuration #6Crowd Control

Page 8: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

JLFANG Concepts:Endurance/Performance (Config. #1)

High-Speed Fighter (Config. #2)High-Altitude Bomber (Config #3)

Preliminary Researchon Supersonic Performance

and High-Technology

Mission 5:De-prioritized Comparative Study

Conducted to DetermineMissions Prioritization

and Optimal Compatibility

Mission Priorities:Counter Air

& High-AltitudeInterdiction

G.O.D.I.S COMPLEX

“Gaurdian of Defense,Intelligence, and Surveillance”

Subsonic UAV Concepts: Dolphin (Config. #4),

Low Alt. Bomber (Config #5),Crowd Control (Config #6)

Significant Factors in Design

Page 9: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

GODIS configuration

Page 10: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Maneuver Weight Performance(G.O.D.I.S. Complex alpha @ 0.9 Mach, 15000 feet)

• Max. Mach Number @ Military Thrust = 1.61M• Specific Excess Thrust:

1-g Max. Thrust = 903 feet/sec 5-g Max. Thrust = 674 feet/sec

• Maximum Sustained Turn = 15.73 deg/sec• Maximum Sustained Loading = 9.0+• Max. Instantaneous Turn Rate = 20.64 deg/sec

Page 11: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

0

10

20

30

40

50

60

70

0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8

Mach Number

Alt

itu

de

(103

fee

t)

1-g Cl Max Ps=100 Ps=300 Ps=500 Q Max Ps=700 Ps=1000

1-g Specific Excess Power(G.O.D.I.S Complex alpha at Maneuver Weight)

Page 12: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Aerodynamics

• Area = 760 ft2

• Aspect Ratio = 5.45

• Sweep angle (L.E.) = -28° (extended), 50° (swept)

• Taper Ratio = 0.14 (extended), 0.05 (swept)

• t/c = 0.14 (extended), 0.04 (swept)

• Wing Root : NACA 64210.68

• Wing Tip : NACA 64209.80

• L/Dmax subsonic = 15

• CL,max subsonic = 1.43

• CDo subsonic = 0.016

• Mcrit = 0.88

Mach number vs K

-0.050

0.050.1

0.150.2

0.250.3

0.350.4

0 0.5 1 1.5 2

Mach number

K M vs K

Mach number vs Parasitic drag

00.0050.01

0.0150.02

0.0250.03

0.0350.04

0 0.5 1 1.5

Mach number

CDo M vs Cdo

Page 13: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Aerodynamics (continued)

• Canard (control)– NACA 65A009 airfoil

– 50 degree sweep

– taper ratio = 0.4

– aspect ratio = 4

• Control Surfaces– subsonic: 2 flaperons per wing:

• First: (near tip) chord = 5.0 ft; span = 19.3 ft

• Second: (closer to root) chord = 5.7 ft; span = 16.1 ft

– supersonic: 2 flaperons on rear:• chord = 4.8 ft

• span = 6 ft

Page 14: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Stability & Control

• Due to variable forward swept wings, Switchblade requires an active flight control system (AFCS)

– Switchblade will have “relaxed static stability” (i.e. - a negative static margin)

• The AFCS will maintain center of gravity (c.g.) positioning as well as canard, flaperon, and thrust vectoring interaction to achieve unparalleled performance regardless of mission type

Page 15: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Engine IntegrationTwo engines per module

• Missions 1, 2 & 4

– Afterburning turbofan

– Tmax (s.l.) = 45886 lb*

– Dmax = 3.63 ft*

• Missions 3 & 5

– High-Bypass Turbofan

– Tmax (s.l.) = 17030 lb*

– Dmax = 2.37 ft*

• External compression 2-D ramp with 3-shock inlet

– Diffuser Length = 19 ft*

– External Length = 2.1 ft*

• 3-D Thrust Vectoring Nozzle

– Exit Area = 4.35 ft *

* per engine, nozzle, or inlet

Page 16: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Weight Estimates & Center of Gravity Travel

C. G. Travel

Counter Air Missions/High-Altitude Interdiction: Complex alphaPropulsion: Afterburning Low Bypass Turbofan EngineEmpty Weight = 37,675 lbsInternal Payload = 4,000 lbsInternal Fuel = 26,730 lbsMaximum Mach number = 1.6Maximum Thrust = 91,663 lbs Engine Weight = 9,959 lbs (2)

Maritime Strike/ISR-Attack: Complex betaPropulsion: High Bypass Turbofan EngineEmpty Weight = 32,410.5 lbsInternal Payload = 4,000 lbsInternal Fuel = 25,830 lbsMaximum Mach number = 1.1 Maximum Thrust = 34,061 lbs Engine Weight = 3,918 lbs (2)

Page 17: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Cost and Supportability

• Flyaway + RDT&E

planes produced FA+RDT&E (per airplane)

50 $190 million 100 $120 million

500 $51 million

• Lifecycle Costs

planes produced Total LCC 50 $17 billion

500 $33 billion

Supportability

modular engines

variable sweep

engine height

thrust vectoring system

Cost

Page 18: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud

Conclusion: Future Work Needed

• Aerodynamics

• Center of Gravity Travel

• Stability and Controls

• Inlet Configuration & Propulsion System

• Subsystem Weights and Cost

• Sustained Loading

Page 19: G.O.D.I.S Complex: “Gaurdian of Defense, Intelligence & Surveillance” Project Advisor: Dr. James Lang Team Leader: Dan Dalton Chief Engineer: Eugene Mahmoud