Global Design Effort - CFS
10-15-09 1CLIC 09 Workshop - WG 5 Technical Systems
CLIC 09 WORKSHOPWorking Group 5 - Technical Systems
ILC REBASELINE
ILC CONVENTIONAL FACILITIESAND SITING GROUP
V. Kuchler, J. Osborne, A Enomoto
Global Design Effort - CFS
10-15-09 2CLIC 09 Workshop - WG 5 Technical Systems
Overview• Review of Conventional Facilities
Milestones• Main Linac Tunnel Configuration
Comparison• Update on Accelerator Design and
Integration (AD&I) Effort• Life Safety and Egress
Global Design Effort - CFS
10-15-09 3CLIC 09 Workshop - WG 5 Technical Systems
CFS Responsibilities and Milestones• The ILC R&D Plan Provides Milestones for CFS
to Review Regarding Specific Aspects of the Reference Design to be Reviewed with
Respect to Value Engineering for the RDR Design
• The Accelerator Design and Integration Effort Is a Separate Overall Review of Alternatives to the Original RDR Design
• As a Result of the AD&I Process (Eliminating the Twin Tunnel Scheme in Favor of a Single Tunnel Design) Life Safety and Egress is
Also Being Reviewed as Part of the AD&I Process
Global Design Effort - CFS
10-15-09 4CLIC 09 Workshop - WG 5 Technical Systems
CFS R&D Plan Milestone Status• Process Water Value Engineering
Completed• Alternative Tunnel Configuration
Preliminary Work was Completed by Hanson Engineering in July 2009
2-Day Workshop was Held at Fermilab on Aug 3-4, 2009 to Review Progress and Begin to Develop Cost Estimates
A Second 2-Day Workshop was Held at FNAL to Internally Review the Final Configuration Analysis and Cost Estimates on August 24-25, 2009 at Fermilab
Global Design Effort - CFS
10-15-09 5CLIC 09 Workshop - WG 5 Technical Systems
CFS R&D Plan Milestone Status• Life Safety and Egress Global Document
Hughes and Associates has Reviewed the Alternative Tunnel Configurations and has Developed Life Safety and Egress Plans for Each Alternative
CLIC Document Is Complete XFEL Document has been Translated into English LHC Document is being Developed Asian Document has been Completed All Individual Documents will be Compiled into a Single
Comprehensive Document with an Executive Summary Which will Describe Commonalities and Distinctions in the Various Reports The Executive Summary will be Added to Complete the Document Prior to the AAP Review in January, 2010
• Surface Building Criteria Review Not Scheduled for Completion Until July, 2010
Global Design Effort - CFS
10-15-09 6CLIC 09 Workshop - WG 5 Technical Systems
Main Linac Tunnel Configurations• Tunnel Cross Sections are Complete• Detailed Cost Estimates Based on the Americas Region
Criteria for Each Alternative are Complete
Global Design Effort - CFS
10-15-09 7CLIC 09 Workshop - WG 5 Technical Systems
AD&I Progress to Date• The First Collaboration Wide ILC Accelerator Design and
Integration Meeting was Held at DESY on May 27-29 • The First Conventional Facilities and Siting (CFS) Group
Meeting was Held at SLAC on July 20-21• A Second Meeting is Planned at the Daresbury Laboratory,
UK on September 3-4• The ALCPG 09 Meeting, Held in Albuquerque NM on
Sept 28 – Oct 2, Also Devoted a Considerable Portion of the Agenda to the AD&I Effort
• The Final Collaboration Wide AD&I Meeting will be Held at DESY on Dec 2-3
• The AD&I Effort will Culminate in a Proposed Revised ILC Baseline Layout that will be Presented for Review to the ILC Accelerator Advisory Panel at Oxford on Jan 6-8
Global Design Effort - CFS
10-15-09 8CLIC 09 Workshop - WG 5 Technical Systems
SB 2009 Working Assumptions (WA)
Global Design Effort - CFS
10-15-09 9CLIC 09 Workshop - WG 5 Technical Systems
Progress on AD&I Central Region Layout• While All Area Systems were Affected by Some of the Alternate
Suggestions, Each Suggestion had a Definite Impact on the Conventional Facilities Layout
• New Criteria Regarding the Various Area System Design Changes was Needed from Each Area System in Order to Develop an Integrated Machine Layout
• The Weekly CFS Meeting has been Used for Direct Discussion with Area System Representatives to Finalize Area System Criteria and Layout Requirements
• Initial 2D Drawings are Being Prepared at FNAL with Consultant Support and will be Used as the Basis for the Revised Baseline Proposal
• 2D Drawings Consist of Overall Layouts, Larger and More Detailed Drawings of Specific Areas and Cross Sections Taken at
Various Points to Analyze Beamline Locations and Conflicts• 3D Layout Drawings are Beginning to be Prepared at CERN with
Efforts at FNAL and KEK to Follow
Global Design Effort - CFS
10-15-09 10CLIC 09 Workshop - WG 5 Technical Systems
Global Design Effort - CFS
10-15-09 11CLIC 09 Workshop - WG 5 Technical Systems
Global Design Effort - CFS
10-15-09 CLIC 09 Workshop - WG 5 Technical Systems 12
SB 2009 CFA WA Status• WA 1 – Dependent on Technical Decision• WA 2a & 2b
Americas Region - Klystron Cluster is Complete, DRFS Still to be Completed. Tunnel Diameter Still needs Optimization
European Region - Both Schemes are Being Worked on by Amberg Consulting Asian Region - Both Schemes have been Investigated. Cost estimates Need to be
Updated
• WA 3 – Undulator-Based e+ Source has been Incorporated into the New CFS Machine Layout
• WA 4 – Low Power Option is Reflected in the New Area System Criteria and CFS Machine Layout
• WA 5 – 3.2 km Damping Ring has been Incorporated into the New CFS Machine Layout
• WA 6 – Single Stage Bunch Compressor has been Incorporated into the RTML and New CFS Machine Layout
• WA 7 – Coordination of the Central Region Beam Layouts are Being Developed and will be Incorporated into the New CFS
Machine Layout. Specific Lattice Information is Still Needed
Global Design Effort - CFS
10-15-09 13CLIC 09 Workshop - WG 5 Technical Systems
Current Status of Codes and Regulations• There are No Codes that Directly Address Underground
Accelerator Complexes• Most Initial Approaches Review Experience with Traffic
Tunnels and Their Associated Guidelines and Regulations for Designs
• Most Recognized Codes Evolve Over Time and are Revised, Based in Part, in Response to Fire and/or Catastrophic Failures
• But Traffic Tunnel Requirements are Based on Fuel Loads that Far Exceed Those Found in Actual Accelerator Installations (i.e. Gasoline, Diesel Fuel, Oil, etc.)
Global Design Effort - CFS
10-15-09 14CLIC 09 Workshop - WG 5 Technical Systems
Current Regional Laboratory Approaches• Most Laboratories Rely on Examples from Previous Projects
to Develop Initial Criteria for Life Safety and Egress Design for a New Project
• This Initial Criteria is Then Supplemented by Consultant Review, Local Underground Codes where Available and Applicable as well as Regulations/Guidelines from Funding and Project Oversight Organizations
• While Most Regions do have Regulations that Directly Control Traffic Tunnel Design, in the Americas Region Two Distinct Codes have been Developed– NFPA 130-2007, Standard for Fixed Guideway Transit Systems– NFPA 520-2005, Standard for Subterranean Spaces
• It Should be Noted that All Codes are Subject to Interpretation
Global Design Effort - CFS
10-15-09 15CLIC 09 Workshop - WG 5 Technical Systems
Current Regional Designs• Life Safety and Egress Issues and RF System Selection are
Two of the Major Drivers of Main Linac Tunnel Diameter• All Three Sample Sites have Developed a Life Safety and
Egress Design for the Main Linac Single Tunnel Alternative Based on Their Local Experience and Applicable Regional Regulations
• All Three Regions have Reviewed both RF Alternatives and Selected the More Appropriate Alternative to Develop
Their Regional Main LInac Tunnel Diameter• A Global Safety Document is Currently Being Developed that
will Gather Information from All Current Accelerator Projects, Including ILC, XFEL, CLIC, LHC and Project X, for Use as a Supporting Reference to any Current or Future Accelerator Design Project
Global Design Effort - CFS
10-15-09 16CLIC 09 Workshop - WG 5 Technical Systems
Asian and European Design Approaches• Main Linac Single Tunnel is Divided into 500 m
Long Segments (i.e. Compartmentalization)• Firewall and Fire Doors Separate Adjacent
Segments• Ducted Transverse Ventilation is Used for Fresh
Air Supply and Return and Smoke Control and Exhaust• The European Region Uses the Klystron Cluster
RF System• The Asian Region Uses the Distributed RF System• Both Regions Currently Utilize a 5.2 m Main Linac
Tunnel Diameter
Global Design Effort - CFS
10-15-09 17CLIC 09 Workshop - WG 5 Technical Systems
Americas Design Approach• Based on NFPA 520, the Main Linac Single Tunnel Must
be Divided into “Building” Space (i.e. Functional or Operation Space) and “Common” Space (i.e. Space Used Only for Exit Travel to the Surface)
• A 2 hr Firewall and 1-1/2 hr Fire Doors Must be Used to Separate the Two Spaces
• Alcoves are Also Required in the Common Space to Limit the Distance to an Exit or Area of Refuge to 610 m
• The Americas Region Currently Utilizes the Klystron Cluster RF System and a 5.0 m Main Linac Tunnel Diameter
Global Design Effort - CFS
10-15-09 18CLIC 09 Workshop - WG 5 Technical Systems
Asian Region Tunnel Design
Global Design Effort - CFS
10-15-09 19CLIC 09 Workshop - WG 5 Technical Systems
European Tunnel Design
Global Design Effort - CFS
10-15-09 20CLIC 09 Workshop - WG 5 Technical Systems
European Tunnel Compartmentalization
Global Design Effort - CFS
10-15-09 21CLIC 09 Workshop - WG 5 Technical Systems
Americas Region RDR and AD&I
Global Design Effort - CFS
10-15-09 22CLIC 09 Workshop - WG 5 Technical Systems
Americas Areas of Refuge
Global Design Effort - CFS
10-15-09 23CLIC 09 Workshop - WG 5 Technical Systems
Life Safety and Egress Summary• Each Region has Developed a Sample Site Solution that Satisfies
Local Life Safety and Egress Requirements Using Both Identified RF System Alternatives
• The Development of a Single, Cost Optimized, Uniform Design for All Three Regions is Simple not Possible
– Different Geology– Different Tunnel, Shaft and Cavern Construction Means and
Methods– Different Approaches to Life Safety and Egress– Preference of RF System
• Using the Regional Sample Site Approach for the ILC CFS Design Appears to be a Sensible Model for the Development of the TDR
• The Final Life Safety and Egress Design for the ILC Cannot be Completed Until a Specific Site is Chosen and an Approving Authority ahs been Established
Global Design Effort - CFS
10-15-09 24CLIC 09 Workshop - WG 5 Technical Systems
Summary• The CFS Group is Making Good Progress on R&D
Plan Milestones and AD&I Efforts• The AD&I Baseline Proposal will be Completed and
Reviewed at the Oxford Meeting in Jan 2010• The CLIC/ILC Collaboration Efforts have
Fundamentally Contributed to the Efforts for the ILC RDR Alternative Review Process as well as the Efforts to Develop an Alternative Baseline Proposal and the Eventual Baseline Design for the ILC Technical Design Report Due to be Developed in 2012