Upload
annahuynh
View
244
Download
0
Embed Size (px)
Citation preview
8/10/2019 GL Plumbing Engineering Services Design Guide
1/249
)9d121z.
Plumbing
Engineering
Services
Design
Guide
The Institute of
Plumbing
Compiled
and
published by
The
Institute of
Plumbing
64 Station
Lane, Hornchurch,
Essex
RM12
6NB.
Telephone:
+44
(0)1708
472791
Fax: +44
(0)1708
448987
www.plumbers.org.uk
Fl
8/10/2019 GL Plumbing Engineering Services Design Guide
2/249
Project
Co-ordinator
Stan
Tildsley
Secretary
&
ProjectManager
Dale Courtman
Eng
FlOP RP
loP
Technical Manager
Administration
Support
Emma
Tolley
LorraineCourtman
JaniceGrande
Jenni Cannavan
Technical Editors&
Designers
-Tarot
Milibury
Printers
-
Saunders&
Williams
PrintersLtd
ISBN
1
871956 40
4
Published 2002
The nstitute of
Plumbing
The Institute
of
Plumbing
cannot
acceptresponsibility
for
any
errors
and omissions
n this
publication
thliiiihite
The nstitute of
Plumbing
/
f
Plumbing
64Station
Lane, Hornchurch,
Essex RM12 6NB.
)
elephone:
+44
(0)1708
472791
Fax: +44
(0)1708
448987
www.pIumbers.org.uk
www.registeredplumber.com
8/10/2019 GL Plumbing Engineering Services Design Guide
3/249
Amendments
This
document
incorporates
the
following
amendments
Ref
Amendment
Date
1O
Corrynum
vt 10/02
2
Corrtcurii
'2
0L4/o3
8/10/2019 GL Plumbing Engineering Services Design Guide
4/249
DTLR
TRANSPORT
LOCAL
GOVERNMENT
REGIONS
Foreword
It is
my pleasure
to
provide
the
foreword
for this
edition
of
the
Plumbing Engineering
Services
Design
Guide. For
many
years
now,
the
Institute of
Plumbing
has
supported
the
construction
industry
on the wide
range
of
issues
that are
concerned
with
plumbing engineering
services
and
this
design guide
has
been
key
to the
success
of
that support.
As with other
sectors
of
the
construction
industry, plumbing
engineering
services
s
an
area that is
rapidly developing
with
new,
improved
and
innovative
technologies
and
the
role
of the
Institute
of
Plumbing
in this
is
an
important
one.
The Guide has
needed to
evolve
with
the
advances
in
industry
practice
and
techniques.
Since
the
guide
was first
launched
in
1977
it has
continued
to
be
an
indispensable
reference source
for
designers, engineers
and
trades-persons
and
this
is reflected
by
the
constant demand
for
it,
both
from
home and abroad.
This new
edition
will
provide
additional information and
guidance
on current
echnologies
and
practices
and
will,
no
doubt,
continue
to be a
valuable source
of
information
for those
engaged
in the
design, approval,
and installation
of
plumbing engineering
services.
I commend
it to the
plumbing industry.
Dr
Alan
Whitehead
MP
Dr
Alan
Whitehead
MP
Ministeror
Building Regulations
Department
for
Transport,
Local Government
and the
Regions
May
2002
Note:
On 29
May
2002
the
Department
of
Transport,
Local
Government
and the
Regions
(DTLR)
was disbanded and
responsibility
for
Building
Regulations
in
England
andWales
was transferred
to
he
Office
of
he
Deputy
Prime
Minister.
8/10/2019 GL Plumbing Engineering Services Design Guide
5/249
Acknowledgements
In
oday's
fast
moving
world,
alented volunteers
are hard to come
by.
The Institute is most fortunate
in
having
benefitted from
he
expertise
of a
number of
such
people
who
have
stepped
forward to make contributions
to
the
contents
of this
Design
Guide.
They
have been
ably
led
by
Institute
Past
President,
Stan
Tildsley,
an
engineer
of distinction in
plumbing
engineering
services,
who
has
acted
as
project
co-ordinator. He
has
been
helped
by
several loP head
office staff
members,
in
particular,
Dale Courtman and Emma
Tolley
who deserve
special
mention for their
hard
work and
commitment
to
the
project.
We
greatly appreciate
the assistance received from
contributing
organisations.
These nclude
Government
Departments
and
Agencies;
sister
professional
bodies,
research establishments and commercial
companies.
We
also
thank
printers, Saunders
and
Williams
and
echnical
editors,
Tarot
Milbury
for
their
co-operation
and
professionalism.
During
the
lifetime of
this
Guide,
it
will becomecommon
place
for
the
dissemination of
up-to-date
technical information
to take
place
hrough
fastbroadband connections to the Internet accessible
via
either
static
computers
or wireless handheld devices.As a
result,
this is
probably
the
last
time the
Guide
will be
available
as a
complete
work
n
bound,
hard-cover
printed
format.
We
pay
tribute
o
all
those
who
have contributed.
They
can be
justifiably
proud
of
their
efforts.
Andy
Watts MBE
EngTech
MIP RP
Chief Executive
and
Secretary
Onbehalf
of
he Board
ofTrustees of
The Institute
of
Plumbing
June 2002
Contributing
Organisations
ARUP
British Standards Institution
Brook
Water
Management
Building
Research Establishment Ltd
copper
Development
Association
Department
for
Environment,
Food
&
Rural Affairs
Department
for
Transport,
Local
Government
and the
Regions
Donald
Smith, Seymour
&
Rooley
Energy
Efficiency
Best Practice
Programme
Grundfos
Pumps
Ltd
Hepworth Plumbing
Products
Her
Majesty's
Fire
Service
Inspectorate (DTLR)
Marley Plumbing
and
Drainage
Spirax
Sarco
Ltd
The
Council
for
Registered
Gas
Installers
The
Institution of
Electrical
Engineers
Uponor
Ltd
Vernagene
Resource Efficient
Design: Energy
Efficiency (excluding
section
on
Plate
Heat
Exchanger):
this has
been
contributed
by
he
government's
Housing
Energy
Efficiency
Best
Practice
Programme,
and
Crown
Copyright
is eserved.
Contributing
Authors
G
F
Baker
L
C Bassett
lEng, FIDIagE,MIP, MIHEEM,
ACIBSE
M
Bates
AIR,
RP
G
Bell
MCIM, EngTech,MIP,
AR
E
Blundell
AlP,ACIBSE
I0
Boyd
lEng, FlOP,
AR
P
Cook
CEng,
FlEE, MCIBSE
A
J
Goodger
BSc, MSc,CEng, MIM,
MIC0rrST
J C
Griggs
FlOP
R
A
Hanson-Graville
MA,
FlOP
0
Harper
EngTech,
MIHEEM,
FWMSoc,MIP, MIlE,
MASEE
N
Hay
BSc
(Hons)
G
Henderson
MSc, CEng,
MIEE
N Howard
BEng Hons),CEng,
FlOP, MCIBSE,MCIWEM
D
EHuckett
S
Ingle
MSc,
lEng,
FlOP, ACIBSE,LCG,
AR
J C
Lane
AlP,
AR
P
Lang
FISPE
J
K
Love
CEng, FCIBSE,FIP, FIDHE,MInstR,
FConsE
A
J
Malkin
Eng
Tech,MIP,
AP
G
L
Puzey lEng,
FlOP,
AP, MASH,
MIHEEM
M C Shouler
BSc, MSc,
COMP P
S
Tildsley
Eng
Tech,
HON
FlOP,
MIP,
AP
C
P
Topp lEng,
FlOP, FIHEEM, MASH, MAE,
RP
M
Vint
J
S
Walley
Eng
Tech,
LCGI,
MIP,
MWMSoc,AP
S
A
Walsh
CEng,
FCIWEM, FlOP,
MCIBSE,
MIOSH, MAE,MEWI
P
JWhite
EngTech, FlOP,
RP
B
F Whorlow
lEng,
FlOP, RP
P
M Williams
8/10/2019 GL Plumbing Engineering Services Design Guide
6/249
Preface
This
Design
Guide
2002
replaces
the
previous
edition
published
in 1988.
The
object
of
the Guide s
to advance
knowledge
of
plumbing technology
to
those
engaged
in
plumbing
design
and
system
nstallation.
The
Guide
has
been
considerably
enhanced
utilising
an
easier
to
read
three-column
format,
bound
withina
silver cover
to
celebrate
the
25th
Anniversary
since the
original
Data Bookwas
published.
Technology
in the
plumbing
industry
has
changed considerably
in the
14
years
since
the
guide
was last
published.
Thisedition seeks
to
include
as much information as
possible,
on new
technologies.
Indeed,
the Guide
reflects as
many
of the
changes
related to
UK
plumbing technology
of
which we
are aware.
Throughout
the
publication,
several British Standards
have been
replaced
by
European
Harmonised Standards.
Many
BS/EN Standards have now
been
brought
together
within the
standards,
codes and
miscellaneous
data
section.
The
water services
section
has
been
greatly
expanded
to
include
many
additional
design
considerations
and to take
account
of
the
statutory
requirements
of the
Water
Supply
(Water Fittings) Regulations
1999 in
England
and Wales and
the
Water
Byelaws
2000 in Scotland.
The
heating
section
has
been
completely
re-written
to
concentrate on
gas,
as the most
widely
used
heating
medium. It also includes
information on
systems
and
heating appliances currently
in
use,
including condensing
boilers
and
wet under
floor
heating systems.
The
sanitary plumbing and drainage
section haschanged
significantly
to
reflect
the
requirements
of
BS
EN
12056,
which
replaced
BS
5572.
This
section has also been extended
to
include information
on
he
technologies
involved in vacuum
drainage
and
syphonic
rainwater
disposal systems.
The
piped
gases
section has
undergone
a
major
review
and
the
section
on
steam
now includes condensate
recovery
information.
Information
on the
design
and
installation
of
residential
sprinkler
systems
is
included
for the first
time,
along
with
completely
new sections on
resource
efficient
design
and
swimming
pools.
As
co-ordinator of
this
Guide,
I
acknowledge
the
unstinting
voluntary
work
of
the
many people associated
with
its production. I'm especially grateful
to the
Institute's
full time
head
office
echnical
team,
consisting
of
Dale
Courtman and
Emma
Tolley.
Finally,my
thanks
also
go
to the
authors,
manufacturers and
professional
organisations
who
have contributed
to
this
publication.
Their
essential
participation
should be
appreciated
by
all
who
adopt
the Guide as a
source
of
reference for
the
design
of
plumbing engineering
services.
Stan
Tildsley
Eng
Tech HON FlOP
MIP
RP
Design
Guide
Project
Co-ordinator
Past President
The Instituteof
Plumbing
June2002
8/10/2019 GL Plumbing Engineering Services Design Guide
7/249
Contents
Hot
and
cold
water
services
1
Legionnaires
disease
41
Heating
47
Resource efficient
design
67
Piped gas
services 81
Sanitary
plumbing
and
drainage
105
Pumps
and
pumping
161
fire
protection
services 169
Steam
and
condensate 179
Pipework expansion
191
Mechanical ventilation
197
Designing
for
the
disabled
205
Domestic
swimming
pools
215
Electrical
earihing
and
bonding
of
building
services 221
Standards,
codes
and
miscellaneousdata
227
8/10/2019 GL Plumbing Engineering Services Design Guide
8/249
Hot
and cold
water
supplies
Sources
ofwater
Waler
supply companies
Water demand
Waler
storage
Water distribution
Hot waler
production
Hot water
generators
Control of
Legionella
Safe
waler
temperatures
Water conservation
Water
regulations
Distribution
pipe
sizing
Hard
water
treatment
Water
supply
installations
Disinfection
Water
quality
Corrosion
Effectsofcorrosive environments
Prevention ofcorrosion
2
2
3
3
4
6
8
9
10
10
11
12
24
24
27
28
29
32
36
1
8/10/2019 GL Plumbing Engineering Services Design Guide
9/249
Hot and cold water
supplies Plumbing Engineering
Services
Design
Guide
Sources
of water
The
source
ofwater
varies
dependant
on
which areaof he British Islesa
supply
is
required.The types are:
1.
Upland
catchment
(reservoir)
2. Groundwater
(borehole/artisan)
3.
River
extraction.
These sources
provide
water or
supply
purposes,
each
withawide
range
of
physical,
and bacterial
quality
differences,
i.e.
1.
Hardness
2.
Bacteria count
3. Minerals.
The
quality
of
water
supplied
for
distribution
to,
and or
use
by persons
and
properties
is
controlled
by
an Act of
Parliament,
theWater
Supply
(Water
Quality) Regulations
1989,
and
subsequent
amendments. The
enforcement
of he Act is
undertaken
by
the
Drinking
Water
nspectorate (DWI),
who
regulate
a
wide
range
of
key
elements
to
attain
and
maintain the water
supplyquality.
See
Table
1.
The standards cover
colour,
alkalinity,
taste,
odour,
undesirable
and
toxic
substances,
and
micro-organisms
to
specified parameters.
The standards are
called
Prescribed Concentrate values'
(PCV's)
to either
maximum, minimum,
average
or
percentage
levels.
These standards
are
imposed
on
all
water
supply
companies,
with relaxation
only
considered under
emergency
situations,
i.e.
extreme
drought
or
flooding,
but under
no
circumstances
if
there is
a
riskto
public
health.
Water
supply
companies
The water
supply
companies operate
under
he
requirements
of he
Water
Industry
Act
1991,
enforced
by
he
Office
of
Water Services
(OFWAT).
Water
supply companies
are
responsible
for
the catchment
or
abstraction
of
raw
water;
it's
conditioning,
treatment
and
distribution
to
consumers
within
their
region.
Thecharacteristics of he water
supplied varies,
region
to
region and
within
regions dependant
upon
he
actual
source, single
or
multiple,
and he
level
of
reatment
provided
in order o
attain
the
prescribed quality
at the
point
of
connection
to he
customer's
supply.
2
Table
1
Drinking
water
standards
Temperature
25C
PH 5.5-9.5
Colour
20
Hazen units
Turbidity
4
Formazin units
Qualitative odour
All odour
nvest
Qualitative taste
All taste
investg
Dilution odour Dilution No
3at25
Dilution taste
Conductivity
lSOOus/cm20c
Total hardness
Applies
only
if
softened
Alkalinity
Free chlorine
Comparison
against averageotal chlorine
Faecal coliforms
0/100
ml
Clostridia 1/20 ml
Faecal
streptococci
0/100
ml
Total coliforms
0/100 ml
(95%)
Colony
count,
2day Comparison
against average
Colony
count,
3
day
Oxidisability
5
mg/I
Ammonia
0.5
mg/I
Nitrite 0.1
mg/I
Nitrate
50
mg/I
Chloride
400
mg/I
Fluoride 1500
ug/l
Phosphorus
2200
ug/l
Sulphate
250
mg/I
Magnesium
50
mg/I
Iron
200
ug/l
Manganese
50
ug/l
Aluminium
200
ug/I
Calcium
250
mg/I
Potassium 12
mg/I
Sodium 150
mg/I
Copper
3000
ug/l
Zinc
5000
ug/l
Lead
50
ug/I
Silver 10
ug/l
Antimony
10
ug/l
Arsenic
50
ug/l
Barium 1000
ug/l
Boron
2000
ug/l
Cyanide
50
ug/I
Cadmium
5
ug/g
Chromium
50
ug/l
Mercury
1
ug/l
Nickel
50
ug/l
Selenium
10
ug/l
Total
organic
carbon
Comparisons
Trihalomethanes 100
ug/l
Tetrachloromethane
3
ug/I
Trichloroethene
30
ug/l
Tetrachloroethene
10
ug/I
Benzo
3,4
pyrene
10
ng/l
Fluoranthene,
benzo
3,
4,
11,
12, fluoranthene,
benzol,
12
perylene
indeno (123cd) pyrene
Individual
testing
of hese
substances
to
provide total
Total PAH's
0.2
ug/I
Anionic
detergents
200
ug/l
Pesticides &
Comp'ds
5
ug/I
total
From
this
connection,
which
generally
incorporates
a
water
company
meter,
the
consumer
is
responsible
for all
aspects
of
the
supply
and distribution ofwater.
Consumers'
rights
Every
consumer
has the
right
to
be
supplied
with water or
domestic
purposes
from he water
supply
company's
distribution network. New or
modified
existing
connections
can ncur
a
charge
by
he water
company
for
the
following
services
1. Newor
replacement supply
2.
Meter installation
3.
Supply
network reinforcement
4.
Infrastructure charge.
All these
charges
relate to he
anticipated
daily
demand
m3),
peak
low
rate
(Its),
and numberof
draw-off
fittings
being
served
from the
supply.
Water
regulations
Consumers
water
supply
nstallations are
required
to
comply
o he
Water
Supply
(Water
Fitting) Regulations
1999,
and
The Water
Supply
(Water Fitting)
(Amendments) Regulations
1999
(2) (the
Water
Byelaws
2000
(Scotland)).
These
regulations
are
enforced
by
the
water
company
that
supplies
waterto
he
consumer.
The
regulations govern
the
wholeof
the
consumer's installation
from
the
connection
to the water
company's
communication
pipe
and meter
termination,
to
all
the
draw-off
ittings,
inclusive
of
any
alterations.
The
regulations require
that no
water
fitting
shall be
installed, connected,
arranged
or
used n such
a
manner,
or
by
reason
of
being
damaged,
worn
or
otherwise
faulty hat it
causes,
or s
ikely
to
cause:
1.
Waste
2.
Misuse
3. Undue
consumption
4.
Contamination
5.
Erroneous measurement.
The
water
supplycompanies
are
required
to
benotified ofcertain
proposed installations,
which
may
be
subject
o
inspection
and
acceptance
prior
to
receiving
the water
company's
supply
connection.
The
regulations
are
a
statutory
instrument,
which
is
supported by
an
interpretation
of he
regulations.
The
water
supply companies
have the
authority
to
apply
o
he
Regulator
for
8/10/2019 GL Plumbing Engineering Services Design Guide
10/249
Services
Design
Guide
Hot and cold water
supplies
of
any
part
of he
regulation
inappropriate
to a
particular
regulations guide
Water
Regulations
Advisory
Scheme
(WRAS)
publish
a
guide
which
provides
guidance
and recommendations
how the
regulations
should be
applied
he
actual
water
nstallations and
include
the
Water
Byelaws
2000
(Scotland).
demand
fora
building
is
dependant
on a numberof actors.
1.
Type
of
building
and it's
function
2.
Number
of
occupants, permanent
or
transitional
3.
Requirement
for fire
protection
systems.
4.
Landscape
and water
eatures.
In
dwellings
the
resident's water
consumption
isdividedbetween the
many
appliances.
A
ypical percentage
break down provided
by he
Environment
Agency
is:
1. WCsuite
2.
Washing
machine
3.
Kitchen sink
4. Bath
5.
Basin
6.
Shower
7. Outside
supply
8.
Miscellaneous
32%
12%
15%
15%
9%
5%
3%
no,
/0
Overall consumption increases
by
around
10%
during
warmermonthswhen
out
door
usage
increases toover25%.
In
general, consumption
per
person
decreases
with an
increase
in
dwelling
size
given
the
shared facilities.
For
guidance
on the total waterdemand
for
typical ypes
of
buildings
refer toTable
2
or
daily
water
demand.
The
igures
stated
have
been
assembled
froma
numberof
sources,
including
BS
6700,
Chartered Institute of
Building
Services
Engineers (CIBSE)
and
Environmental
Agency
studies
and
can
be
used
as
a
basis or good
practice.
Water
storage
The
storing
ofwater hasanumberof
purposes,
1.
Providing
for an
interruption
of
supply
2.
Accommodation
peak
demand
3.
Providing
a
pressure (head)
for
gravity supplies.
Design
Codes recommend
that
storage
is
provided
to cover he
interruption
ofan
incoming
mains
supply,
in order o
maintain
a water
supply
o he
building.
Water
supply companies
are
empowered
to insist on
specific
terms,
including
the
volume
or
period
of
storage,
within the
term of their
supply agreement
with
a
consumer. However
manywater
supply
companies
only
recommend
that
storage
be
provided
inaccordance with the
BS
6700, placing
the
responsibility
and
decision
firmly
on the
consumers.
Table
2
provides guidance
on
typical
water
usage
within
buildings
overa 24
hour
period.
In
designing storage capacities,
account
needs o
be
takenof the
building
and
its
location.
1.
Period and hours
of
occupation
2.
Pattern
of
water
usage
3. Potential for an
interruption
of
supply
4.
Available mains
pressure,
and
any
inadequacies during
the hours
of
building
use
5. Health &
Safety, prevention
of
bacteria, including legionella.
If
a
building
is
occupied
24 hoursa
day,
then an
interruption
of
supply
will have a
greater
mpact
than
that or
say
an
office,
which
may only
be
occupied
for
eight
o
ten
hours.
Where
a
building
is
occupied
by elderly
or
infirmed
people
then
avoiding
any
disruption
of
he
water
supply
s
an
important
consideration as
they
would
be
unable
to
easily
leave the
building
should
water
become
unavailable.
Clients,
such as the
National Health
Service, require
their
buildings
tobe
provided
with
storage
o
safeguard
against
an
interruption
of he
mains
supply.
Industrial
clients
may
well
require
storage
to ensure
theirbusiness and/or
production
is not
nterrupted.
If
water
ceases
tobe
available
withina
building
then the
occupiers
will
eventually
leave
as toilet
acilities
will
become unusable. It
is
ikely
hat when
an
interruption
of
supply
occurs
then
the water
available
would
be
conserved
as
much
as
possible, thereby extending
the
time of
occupancy beyond
that
anticipated
under
normal
usage
rates.
Table
2
Daily
water
demand
Type
of
Building
Litres
Criteria/Unit
Dwellings
-
1 bedroom 210 Bedroom
-
2
bedroom 130 Bedroom
-
3+
bedrooms 100
Bedroom
-
Student en-suite
100 Bedroom
-
Student,
communal 90
Bed
space
-
Nurses Home 120 Bed
space
-
Children's Home 135
Bed
space
-
Elderly
sheltered
120 Bedroom
-
Elderly
Care
Home
135 Bed
space
-
Prison
150 Inmate
Hotels
-
Budget
135
Bedroom
-
Travel
Inn/Lodge
l5Oav Bedroom
-
4/5 Star
Luxury
200 Bedroom
Offices
&
general
work
places
-
with
canteen
45 Person
(1)
-
without canteen
40 Person
(1)
Shops
with canteen 45 Person
-
without canteen 40
Person
Factory
-
with canteen
45 Person
-
without canteen
40 Person
Schools
-
Nursery
15
Pupil
-
Primary
15
Pupil
-
Secondary
20
Pupil
-
6th
Form
College
20
Pupil
-
Boarding
90
Pupil
Hospitals
-
District
General 600 Bed
-
Surgical
ward 250 Bed
-
Medical ward 220 Bed
-
Paediatric ward 300 Bed
-
Geriatric ward 140 Bed
Sports Changing
-
Sports
Hall 35 Person
-
Swimming
Pool 20
Person
-
Field
Sports
35
Person
-
All
weather
pitch
35 Person
Places
of
Assembly (ex
cl.staff
-
Art
Gallery
6
Person
-
Library
6
Person
-
Museum
6
Person
-
Theatre
3
Person
-
Cinema
3
Person
-
Bars
4
Person
-
Night
Club
(3)
4
Person
-
Restaurant
7
Cover
SUPPORTING INFORMATION
If
he number
of
building occupants
are not
accurately
known hen
asa
guide
the
following
criteria
can
be
used.
Offices,
one
person
per
14m2
of he
gross
building
floor
area.
Sports
hall,
four
persons
per
badminton
court
area
per
hour
open,
maximum.
Swimming
pool,
one
person
per
cubical
per
hour
open,
with a
actor
of
0.6
for
diversity.
Field
sports changing,
persons
per
eams
per
number
of
pitches,
per
day
3
8/10/2019 GL Plumbing Engineering Services Design Guide
11/249
Hot and cold
water
supplies Plumbing Engineering
Services
Design
Guide
AllWeather
Field,
persons per
eams
per
hours used.
Museums,
Art
Galleries, Libraries,
One
person
per
30m2
of he
gross
building
floor
area.
Restaurants,
One
person
per
1.0m2
of
he
dining area.
Bars,
One
person
per
O.8m2
of he
public
bar/seating
area..
When
the water
supply companies,
regulations,
or client
requirements
do
not
specifically
dictate he
period
tocover
an
interruption
of a mains
supply
henTable
3
provides
recommendations
for
reasonable
periods
of
storage, expressed
as
a
percentage
of the
daily
water
demand.
Table3
Period
of
storage
Type
of
Building
%
of
the
daily
demand
Hospitals
50%
Nursing
Homes 50%
Dwellings
0
-
50%
Hotels,
Hostels 50%
Offices
0
-
50%
Shops
0
-
25%
Library, Museum,
Art
Galleries 0
-
25%
Cinema,
Theatre
0
-
25%
Bars,
night-club
0
-
25%
Sports
Facilities
0
-
25%
Schools, Colleges,
Universities
50%
Boarding
Schools 50%
Water distribution
The water
distribution installation
requires
tobe able o deliver
he correct
flow andvolume of hot and coldwater
when
and where
t
is
needed. The mains
pressure
can
provide
the
initial means
of
delivering
water
nto
the
building.
The
water
supply companies
are
required
to
deliver heir water
o
the
boundary
with
a
minimum
pressure
of
1.0
bar. Often their
delivery pressure
can be
higher,
however
at imesof
high
demand,
the
pressure
will be closer to theminimum
provision.
Type
of
system
The
type
and
style
ofwater
distribution
needed
fora
particular building
will
depend mainly
on the
building
height
and
its
use.
a. The
building
height
will determine
whether
pumping
will
be
required
to
deliverwater
o
the
highest
level
b. The
building
use
will determine
he
amount
of
storage
that will
be
required.
4
The
type
of water
system
will
need o
be
oneor a
combination
of he
following:
a. Directmains fed
b.
High
level
storage
with
gravity
down
feed
c.
Pumped
froma
break cistern
or
storage provision.
Potentially
aone or two
storey
building
in
a
locality
where
an
interruption
of
water
supply
is
very
nfrequent
and
causing
little
nconvenience,
there isan
option
for
the water
supply
to
be direct rom
the
mains
without
storage being provided.
If
the
provision
of
storage
is
possible
at
high
evel then he
system
could
be
enhanced to
provide
storage coupled
with it
becoming
a
gravity
down
feed
system.
See
Figure
1.
Figure
1
Supply
o
a
two
storey
building
Storage
anks
A
building requiring
a
large
water
storage
provision
may
not
be able o
accommodate
itat
high
level,
n which
casea
low level location will
be
needed,
in
conjunction
witha
pumped
distribution
system.
A
combination
of
highand
ow storage
can
be
considered
if a
gravity
distribution
is
preferred
for all or
part
of he
building.
This
has
an
advantage
of
providing
some
storage
in
the eventof an
interruption
of
the
water
supply,
or
power
supply
o
he
pumps.
A
storage
ratio of 2: 1
low/high
level
is
a
typical arrangement.
Storage
can
comprise
of wo
compartments
or
cisterns/tanks in
order
thatmaintenance can be carried out
without
nterrupting
distribution.
For small
storage quantities
one
piece
cisterns can
be
used,
which
generally
are
of a
low height construction. For
storage
of
2500 itres or
more,
sectional
panel
anks
may
be
considered more
appropriate
withacentre
divide.
Above 4000 itres
storage
twin
cisterns/tanks
may
be
considered
appropriate.
See
Figure
2.
Figure
2
Storage
cistern/tank
layout
Sectional
tanks
commonly
have
flanges,
being
nternal
or
external. External
flanges
permit tightening
without
needing
to
enter
he
tank,
and on the
base
permit
the
tank to be self
draining
through
a
single
drain
point,
without
urther
draining
of
any
entrapped
waterbetween
flanges.
Such a feature reduces maintenance and
assists
the
prevention
of
water
stagnation
which
can lead o
harmful bacteria
growth, including legionella.
In
calculating
the
storage capacity
a ree
board allowance is
necessary
to
accommodate the
float
valve,
over
low
installations
and
anyexpansion
from
the
hot
water
system. Depending
on
pipe
sizes,
commonly
a250
300 mm ree
board
depth
s
required
on
ciserns/tanks
having
a
capacitygreater
han
2500
litres. Raised
ball
(float)
valve
housings
in
conjunction
withaweir overflow
an
provide
an increased
depth
of water
stored
over he
main
area
of the
cistern/tank(s).
The
ocation
of he nlet and
outlet
connections is
important.
Across low
through
the
cistern/tank
needs
o be
achieved
to
assist
the
complete regular
turn overofwater
hroughout
the
storage
period.
Sub
divided,
twin and
multiple
cisterns/tanks
ideally
should
be
installed
in
parallel
to
each other. The inlets
require
to be
positioned
at he same evel
to
ensure
hey
supply
the
cisterns/tanks
in
unison,
andas aras
possible
the
same low
rate
toassista
balanced
throughput.
The outlet
connections
and
manifold
pipe
workneeds to be
arranged
with
symmetrical
and
equal
engths,
also
to
provide,
as aras s
possible
a
balanced
flow rom the
tanks.
The
use
of
a
delayed action
float
valve
may
also be
considered to
ensure
a
greater
urn overof
water.
Incoming supply
(balancedpipes
not
critical)
Cisterns, ectangular,
in
parallel
Outlets,
rom
opposite
corners
of
nlet,
and
strictly
balanced
n
ength
and
configuration
NOTE
Valves
to be
provided
to
enableone cistern/tank o
be isolated
whilst
other remains
open.
Option
of
gravity
tank at
high
level
Rising main,
and
drop
to
draw-off
points
Ground
evel
Utility
Co.
_____________
mains
0
8/10/2019 GL Plumbing Engineering Services Design Guide
12/249
Plumbing Engineering
Services
Design
Guide
Hot and
cold water
supplies
Access
to
storage
cisterns/tanks
Access
for
installation
and
maintenance
is
required.
Table
4
is
a
guide.
For
largebuildings,
accommodation
for
water
storage
has an
significant impact.
Table
5
provides
an
outline
guide
o
he
space
that
may
be
required.
Table
4
Access
o
storage
cisterns/tanks
Location
(mm)
Around 750
Between,
tanks 750
Above, allowing
beams to ntrude 1000
Below,
between
supports
600
For outlet
pipe work,
md.
access 1500
Tank construction thickness 100
Insulation
(may
form
part
of
ank)
25
Raised
float
valve
housing
300
Entry
o ank
800
dia
Table5
Water
storage
plant
room area
Storage
(Litres)
1.5metre
Tank
Height
2 metre 3 metre
5,000
18m2 18m2
10,000
31m2 23m2
20,000
50m2
40m2
40,000
72m2 60m2 50m3
60,000
80m2 60m2
100,000
10m2
80m2
Gravity supplies
For
gravity supplies
tobe
effective,
the
storage requires
to
be
at a
sufficient
height
o
deliver
he waterto he
draw-off
point
at
he
required
flow
rate and
pressure.
The available head
is
he
dimension between
the
bottom
of
the
storage cistern/tank(s)
and he
highest
draw-off
point,
or
draw-off
point
with
the
greatest head/pressure
oss.See
Figure
3.
The
advantages ofgravity supplies
are:
a.
Availability
of
water n the eventof
watermains or
power
ailure
Figure
3
Gravity
upplies
available
head
b.
No
pump running
costs
c.
Potentially
less
noise
due
o
lower
pipe
lowvelocities.
The
disadvantages
are:
a.
Greater
structural support
b.
Larger
pipe
sizes due
o
limited
available
head,
when
compared
to
pumps
c. Lower
delivery
pressures.
Pumped
supplies
The
delivery
ofwater
by
pumping
will
provide flexibility
in the
positioning
of
he
storage
cisterns/tanks.
The
delivery
flow
rate and
pressure
demanded
by
the
system
are
met
entirely
by
selecting
the
correctduty or the
pumps.
The
pump set
is
required
todelivera
constantly varying
flow
rate
as
draw-off
points
are
randomly
used
by
he
occupants.
The
useof
multi-
stage
variable
duty
and/or inverters
is
an
advantage.
See
Figure
4.
Generally
a
minimum
of
wo
pumps
are
used,
each
having
100%
system duty
and
controlled
to
enable
them
to
be a
stand
by
oeach
other. To
prevent high
pressure
overrun when
demand s
less
than he
design demand,
a
pressure
limiting
or
variable control
flow
device
needs
to
be fitted on the outlet rom the
pumps.
For
high buildings
a
combination of
pumped
and
gravitymay
be
appropriate.
The
advantage
of
his
is to
provide
a
proportion
of
he
daily
water
usage
n a
cisterns/tank(s)
at
roof
level,
which would
provide
a
gravity
down feed
service,
and
continue to
provide
water n the eventof
a
ailure
of
he
pump.
See
Figure
5.
Such
a
system
would
comprise
of:
a.
An
incoming
main
b. Low level
breakor
storage
cistern/tank
c.
Pump
set
d.
High
level
cistern/tank(s)
Figure
4
Pumped
upply
ayout
e.
Cold
waterand hot water cold
eed
gravity
distribution.
The low evel
pump
set can be sized to
provide
a
low
volume,
more
frequent
operation
and
high
head
to
deliver
he
water
o
he
tanks
at
roof level.
If
a
mains'water
supply
s
required
to
be
provided specifically
for
drinking
water
points
or
drink
making
equipment,
then
either
of
hese can be
supplied
from
he
incoming
main
up
to
the number
of
loors
that he
available mains
pressure
will
reach,
and from the
pumped
ising
main
above
that
level;
or
entirely
from
he
pumped
rising
main.
See
Figure
6.
Whilstall water
supplied
for
domestic
useshas to be suitable for
drinking
purposes, supplying drinking
water
points
direct rom
ncoming mains
or
pumped
mains
provides acooler,
more
oxygenated supply
for taste
purposes.
5
Cisterns/tank(s)
on
roof or
roof
plant
room
level
Low
evelbreak
or
storage
tank
Figure
5
Combined
pump
and
gravity
Figure
6
'Mains'water
or
drinking
Head
of
water
pressure
available
n
metres
Duty
of
pumps
=
static
ift
plus
distribution
loss and
delivery
pressure,
n
metres
Pumped
mains'
to
drinking
points
and
drinks machines
Utility
mains' to
drinking points
and drinks
machines
Low
level
cistern/tank
Incoming
main
8/10/2019 GL Plumbing Engineering Services Design Guide
13/249
Hot
and
cold
water
supplies Plumbing Engineering
Services
Design
Guide
Hot water
production
Hot water
can
be
generated
by
a
differing
numberof
methods,
and the
selection
will
depend mainly
on the
quantities
of
hot
water
required
and he
types
of
energy readily
available.
The demand for hot waterwill
vary
considerably
between
types
of
buildings,
governed
by
their
occupants
and he
activities
taking place.
For
example:
Office
buildings
will
require
small
quantities frequently
and
regularly
throughout
he normal'
working
day,
and
availability
at
other
times
as
and
when
occupant's 'overtime'
working
hours
demand.
A
actory
witha
production
line
will
require
sufficient
hot water
to
meet
he
demand
at
breaks in
the
shift when the
work orce
may
all wish
o
wash
hands
etc.
A
sports
pavilion
will
need
to
be
able
o
provide
large
quantities
of hot water or
team's
showering
needsover
a
short
period
of ime
following games,
whenever
they
occur.
Selection
of
hot
water
production
In the selection
of
he
type
of
hot water
production,
the time
available
for
re-
heating
is an
important
consideration.
If
a
high
volume
or
rapid
re-heat rate
is
required
then it would be
necessary
to
ensure
that
a
sufficient
energy
capacity
is
available.
If
he
energy
capacity
needed
is
not available
thena
greater
volume
of
water
storage
wouldhave to
be
provided
to
ensure
hot water s
available
during
theslower re-heat
period.
Hot water
production
and
storage
temperatures
are
required
to
comply
to
the Health
&
Safety
equirements
for the
minimisation
of
egionella
bacteria.
This
demands
a
minimum
storage
temperature
of
6000
o
be
attained,
with
a
minimum
secondary
return
(if
provided)
temperature
of
50C.
See
Figure
7.
Therefore
in
calculating
the hot water
demand
for
a
building
it
s
necessary
to
ensure
that he
output
water
emperature
from
he
hot
water
production plant
s
never
less
than 60C,and never
less
than
50C
hroughout
he
distribution
system.
The HSC
'Controlof
Legionella'
CodeL8
states hat 50C
should
be
achieved
within
60
seconds
at
all outlets.
Type
of
building Daily
Stored Unit
(litres) (litres)
Dwellings
-
1
bedroom 115 115 Bedroom
-
2bedroom 75 115 Bedroom
-
3
+bedrooms 55 115 Bedroom
-
Student en-suite 70
20
Bedroom
-
Student,
comm 70 20
Bedspce
-
Nurses home 70
20
Bedspce
-
Children's home 70 25
Bedspce
-
Elderly
sheltered 70 25 Bedroom
-
Elderly
care
home 90 25
Bedspace
-
Prison Inmate
Hotels
-
Budget
115 35 Bedroom
-
Travel
Inn/Lodge
115 35 Bedroom
-
4/5 Star
Luxury
135
45
Bedroom
Offices
&
general
worK
places
-
with canteen 15
5
Person
-
without
canteen 10 5 Person
Shops
-
with
canteen 15
5
Person
-
without
canteen 10 5 Person
Factory
-
with
canteen 15
5
Person
-
without
canteen 10
5
Person
Schools
-
Nursery
15 5
Pupil
-
Primary
15
5
PupilI
-
Secondary
15
5
Pupil
-
6th form
college
15
5
Pupil
-
Boarding
114 25
Pupil
Hospitals
-
District
General 200 50 Bed
-
Surgical
ward 110 50 Bed
-
Medical ward 110 50 Bed
-
Paediatric ward 125 70 Bed
-
Geriatric ward 70
40
Bed
Sports changing
-
Sports
Hall 20
20
Person
-
Swimming
Pool 20
20
Person
-
Field
Sports
35
35
Person
-
All
weather
pitch
35
35
Person
Places
of
assembly
(excLsta__
-
Art
Gallery
2
1 Person
-
Library
2
1 Person
-
Museum 1 1 Person
-
Theatre
1 1
Person
-
Cinema 1 1 Person
-
Bars
2
1 Person
-
Night
Club
-
Restaurant
1
6
1
6
Person
Cover
SUPPORTING INFORMATION
The
storage figures
statedare basedona re-
heat
period
of wo
hours,
an nlet
emperature
of
10C
and
a
stored
emperature
of
65C.
If
he number
of
building occupants
are not
accurately
nown hen
asa
guide
he
following
criteria
can
beused.
Offices,
One
personper
14m2of
he
gross
building
floor
area.
Sports
hall,
Four
persons
per
badminton
court
area
per
hour
open,
maximum.
Swimming
pooi,
One
person
per
cubical
per
hour
open,
with
a
actor
of
0.6
for
diversity.
Field
sports
changing,
persons
per
eams
per
number
of
pitches,
per
day.
Allweather
field,
personsper
eams
per
hours
used.
Museums, art
galleries,
ilbraries, One
person
per
30m2
of
he
gross
building
floor
area.
Restaurants,
One
person
per
1.0m2of he
dining
area.
Bars,
One
person
per
O.8m2
of
he
public
bar/seating
area.
When
a
conventional
bulk hot water
vessel
is
used
it
is
necessary
o
ensure
that
the contents
of he whole
vessel
achieves
the correct
stored water
temperature
as
stratification canoccur.
To
overcome
this
situation
the
storage
vessel
should
ncorporate
the
following
features:
a.
Base inlet hot
watercold feed
supply
b.
Top
outlet hot water outlet
low
c.
Convex ends
to
vessel
d.
Provide
a
'shunt'
pump
to
move
he
hot water rom the
top
of
hevessel
to
he
base
to
avoid stratification.
Hot water
demand
When
assessing
the hot water
production
requirements
for
a
building
it is
necessary
o
determine the
peak
demand. The
peak
demand s the
volume
of
hot water
required during
the
building's
period
of
greatest
usage.
This
may
be
over an
hour,
or
shorter
period
dependant
on the
occupants
and
activities
taking place.
Having determined
the peak
demand the
volume
of hot water
needing
to be
stored
can
be
selected,
the
rate
of
recovery
and
theassociated
energy nput
needed can
be
established.
The
buildings
total
daily
hot water
usage
is
relevant
to
the assessment
of the
peak
Table
6
Hot water
demand
Store
8/10/2019 GL Plumbing Engineering Services Design Guide
14/249
Plumbing Engineering
Services
Design
Guide
Hot and
cold
water
supplies
demand. Once
the
daily usage
is
determined then the more critical
peak
demand can
be
assessed.
Traditionally
hot
water
peak
usage
was
based
on
a
wo hour
storage
re-heat
period
and his
has generally proved
to
be
a
satisfactory
benchmark
for
peak
demands
for that
period.
Table
6
schedules
a
compilation
of
figures currently
recommended
by
he
water
ndustry's
design
codes,
with
additional
categories
added as
considered useful.
The
recommended
storage
volumes
are
based
on a65C
storage temperature
and
a
wo hour
re-
heat
period,
i.e.a
bulk
storage
vessel.
This data should be
considered
as
representative
of
capacities,
which have
not
given
rise
to
complaints
of
inadequacy.
Two hourre-heat
The
two hour e-heat
storage
volume
figures
can
provide
a
guide
o the
peak
water
volume used
during
a
peak
wo
hour
usage period.
The same
hot water
output
could also be
achieved
by
he
use
of
ow
volume/rapid
reheat
'semi-storage'
types
of
hot water
generators,
if
the
energy
input
capacity
is available.
The
semi-storage'
type
of
hot
water
heaters can
meetshorterpeak
demand
periods
i.e.
1
hour,
or
ess, although
detailed
secure
nformation
about
peak
period
demands
during
periods
of
ess
that 1
hourare not
sufficiently available,
and
herefore
a
design
risk
margin
will
be
required.
The
established
two hour
peakusage
figures
cannot
simply
be
evenly
sub-
divided into shorter
periods
without
he
risk
of
seriously
under
estimating
the
actual
hot water
volume
that
will be
required during
thatshorter
period.
The
shorter he
period,
the
greater
he
dis-
proportion
of
he two hour
peak storage
figure
will
be
required.
For
example,
the recommended twohour
re-heat
period storage
volume
for
a
budget
hotel
is 35 litres
per
bedroom. For
a
50
bedroom hotel
the
stored volume
wouldneed
to
be 1750
itres,
which when
supplemented
by
he
re-heated water
during
the
envisaged
peak
wo hour
draw-off
period,
ess he
loss
(25%)
of
hot waterdue to the
mixing
effect
of
he
incoming
cold
water
eed,
s
capable
of
providing
a
notional
2625
itres,
should
that demand
occur.
This s
because 1750
litres
of
65Chot water s
notionally
available
at he startof he
notional
peak
draw-off
period,
and whilst he
stored hot
water s
being
drawn
off it is
also
being
re-heated
at a
rate
of
1750 itres
per
two
hours,
less
the
loss
through
the
mixing
of
incoming
cold water and he
stored hot
water
(25%).
Therefore itcan
be
seen
that
the stored
water s there
to
provide
for
a
peak
1750
litre draw-off
occurring
over
any period
from,
say
ten minutes
upwards.
For consideration
purposes
1750 litres
equates
to 35
baths, each
using50
litres
of
60C
stored
hot
water.
Dependant
on
the
bath
usage
ratio
ofeither
1200, 2400,
or
4800
seconds
frequency
of
use
(see
simultaneous demand
data)
the hot
water
stored
could be used
up
after
a
63
minute
period. Alternatively
1750 litres
could
provide
for 73
persons having
a
shower,
each
lasting
5
minutes
using
24
litres
of
60C
of
stored
hot water
(mixed
with
cold).
Dependant
on the shower
usage
rate
of
900, 1800,
or
2700
seconds
frequency
of
use,
the hot water
stored could
be
used
up
aftera
45
minute period.These
two
examples are
based
on a
peak
statistical
usage
which
would
ikely
not reoccur
during
the
remaining
timeof he two hour
re-heat
period.
A
semi-storage'
hot water
generator
requiring
to
meet he samedemand for
baths
would
need
o
be
capable
of
providing, approximately
a
3.3 litre
per
second
flow
rate
of
65C
continuous hot
water
output,
assuming
an
initial stored
volume
capacity
of500
itres.
These
potential peak
demands couldbe
considered
as
being
extreme
examples.
However
they
clearly demonstrate the
demands
capable
of
being
put
on
hot
water
generation,
when
aking
accountof
the maximum simultaneous
usage
that is
imposed
on draw-off
ittings
by
he
building occupants,
and
accordingly
has
to be
considered
for
design purposes.
Whatever
the
building,
the
likely
pattern
of
hot water
usage
should
be assessed
and
considered. The
hot water
usage
will
be
directly
related
to
he
building
function,
its
occupancy
and
the
type
of
Figure
8
Typical
demand
pattern
histogram
activity
hat
is
ikely
o
take
place.
In
determining
the
pattern
of
usage,
it s
important
to
differentiate between a
maximum
daily
demand and an
average
daily
demand,
so that
the
implications
of
the
system not meeting
the
buildings hot
water
requirements
can be
recognised,
and he maximum
requirements
designed
for where
necessary.
Measured
quantities
of hotwater
consumption
should
not standalone
as a
sizing guide.
The rate
at
which these
amounts
are
drawn
off
must
also
be
considered.To
project
thedemand
pattern
over
the
operating period
of
he
building,
an hour
by
hour
analysis
of
likely
hot
water
usage
should be
made,
taking
into account
the
numberof
occupants,
the
type
and
evel
of
activity
and
any other factors
thatmayaffect
hot
water
demand.
The
projected pattern
of
demand should
be
recorded
in
the form
of a
histogram profile.
Typical examples
of
daily
demand
n
various
types
of
buildings
are
illustrated
in
Figures
8
and
9.
By
establishing
a
hot
water
demand
histogram
a
representative
peak
demand
volume can
be
established.
Typically
the
peak
hour s between 15-20%
of
he
day's
total
usage.
When
selecting
a
semi-storage'
hot
water
production unit(s)
it
needs
to
be
recognised
that the small
stored volume
is there
o
meet he short
period peak
draw-offs
that occur
n
any
water
supply
system.
The
shortest
of these
peak
draw-
offs
is the
maximum' simultaneous
demand
litre
per
second
flow
rate
figure
calculated from he sum
of
he drawoff
'demand'
or
loading'
unitsused
or
pipe
sizing. However,
periods
of
ime that
these low rates occurare
very
short,
and
are
based
on
the
period
of
individual
draw-
off,
i.e.
length
of ime to fill a
basin,
7
3500
3000
2500
-
2000
E.
1500
1000
500
0
0 6 12 18
Period
24
8/10/2019 GL Plumbing Engineering Services Design Guide
15/249
Hot
and cold
water
supplies
Plumbing Engineering
Services
Design
Guide
w
'?
0
0.
E
C
0
t.1
U
U
sink,
or
bath,
have
a
shower,
and
he
number
of
imes he draw-off
s
used
during
the
peak
demand
period,
i.e.
every
5,
10,
or
20
minutes,
or
more. The
'maximum simultaneous
demand'
must
not
be
applied to
periods
greater
than
the
period
and
frequency
of
maximum
simultaneous
demand.
Hot water
generators
The
production
of
hot
watercan
be
achieved
by
avaried
number
of
energy
sources.
1.
Electric, generally
with
direct
immersed elements
2.
Gas,
either
direct,
or
ndirect
by
a
dedicated circulator
3.
Low
Temperature
Hot Water
LTHW)
boiler
plant,.
dedicated
or more
ikely
forming
part
of
he
space heating
plant
4.
Steam,
whenavailable from
a
central
plant facility.
Energy
forms,
which
provide
a
direct
means
of
heating
hot
water,
i.e. electric
and
gas
in
particular,
are themost
effective in
tems
of
efficiency
because
of
least oss
of
heat
during
the heat transfer
process. Sharing
hot water
generation
with
space heating
plant
candecrease
the
energy efficiency through
the
8
additional
transfer
process
and
ess
efficient
operation
when
space heating
is
not
needed.
Solar
heating,
whenavailableandviable
is
an
excellent supplementary heat
source andeffective in
reducing
annual
energy
ariffs.
Commonly
used
formsof
hot
water
heating
are:
Dwellings
and small
buildings:
Electric,
or
gas
combination
(HWS
&
Heating)
boilers.
Offices:
Electric,
local
or
'point
of
use'water
heaters.
Larger premises
and
sports
acilities:
Gas direct ired water
heaters.
Local or
central
plant
The
adoption
of
local
or
central
plant
is
generally dependant
on the
type
of
building,
where
hot
water s
needed and
the
volume
required.
For
toilet
wash
basin hand
rinse'
purposes only,
where
relatively
little hot water s
required
then
a
local
heater
positioned adjacent
to
the
draw-off
ittings
would
be
appropriate.
This
may
be
considered
particularly
suitable
for
office andschool toilets. The
advantages
of
his
type
of
nstallation can
be low
nstallation,
energy consumption,
and
maintenance
costs,
plusalleviating
the need for
secondary
circulation
pipework
and
pump
o
maintain
distribution
temperatures.
Vented
or
unvented
generators
A
vented
hot water
generator
is
supplied
bya
gravity hot
waterdown eed
and
expansion pipe
and
having
an
open
vent
pipe
over
the
feed cistern/tank
to
provide
for
pressure relief,
in
addition
to
500
School
-
Service
00
0
Catering
00
E
200
0
)
100
fl
I
18 24
5
6
Time
(hours)
12
1OC
Restaurant
-
80
'
a60
E
40
0
)
24
0
r
18
12
Time
(hours)
3000
Hotel
,
2
2000
E
81000
0
06
I
Time
(hours)
24
Figure
9
Examples
of
daily
demand
patterns
or ommercial
premises
12
Time
(hours)
Reproduced
from
CIBSE Guide G:
PublicHealth
Engineering,by
permission
of he
Chartered Institution
of
Building
Services
Engineers.
Option
of
combined
cold
eed
and
open
vent
Rot water
cold
eed
Figure
10
Vented
hot water
generator
Figure
11
Unvented
hot water
generator
HWS distribution
Check
valve
Pressure
reliefvalve
8/10/2019 GL Plumbing Engineering Services Design Guide
16/249
Plumbing Engineering
Services
Design
Guide
Hot
and cold
water
supplies
demand. Once the
daily usage
s
determined then he more critical
peak
demand can
be
assessed.
Traditionally
hot
water
peak usage
was
based
ona wo hour
storage
re-heat
period
and this
has generally proved
to
bea
satisfactory
benchmark
for
peak
demands for that
period.
Table
6
schedules
a
compilation
of
figures
currently
recommended
by
he
water
ndustry's
design
codes,
with
additional
categories
added
as
considered useful.
The
recommended
storage
volumes
are
based
ona
65C
storage temperature
anda wo hour
re-
heat
period,
i.e.
a
bulk
storage
vessel.
This data
should be considered as
representative
of
capacities,
which have
not
given
rise
to
complaints
of
inadequacy.
Two hour re-heat
The two hour
re-heat
storage
volume
figures
can
provide
a
guide
o
the
peak
water
volume
used
during
a
peak
wo
hour
usage
period.
The same hot water
output
could
also be
achieved
by
he
use
of low
volume/rapid
reheat
'semi-storage'
types
of
hot
water
generators,
if
the
energy
nput
capacity
s
available.
The
semi-storage'
type
of
hot water
heaters can
meet
shorter peak demand
periods
.e.
1
hour,
or
less, although
detailed
secure information
about
peak
period
demands
during
periods
of
ess
that 1 hourare not
sufficiently available,
and
therefore
a
design
risk
margin
will
be
required.
The
established
two hour
peak usage
figures
cannot
simply
be
evenly
sub-
divided
nto
shorter
periods
without the
risk
of
seriously
under
estimating
the
actual
hot water
volume
that
will be
required during
that shorter
period.
The
shorter he
period,
he
greater
he
dis-
proportion
of
the
two hourpeak
storage
figure
will
be
required.
For
example,
the recommended
two
hour
re-heat
period storage
volume
for
a
budget
hotel
is
35
litres
per
bedroom. For
a50
bedroom hotel the stored volume
wouldneed
to
be 1750
itres,
which when
supplemented
by
he
re-heated
water
during
the
envisaged peak
two hour
draw-off
period,
less
the
loss
(25%)
of
hot
waterdue
o
the
mixing
effect
of
he
incoming
cold
water
eed,
s
capable
of
providing
a
notional
2625
itres,
should
that
demand occur.
This is
because
1750
litres
of
65Chotwater s
notionally
available
at he start of the
notional
peak
draw-off
period,
and whilst hestored hot
water
s
being
drawn
off it is
also
being
re-heated
at a
rate
of
1750 itres
per
wo
hours,
less he loss
hrough
he
mixing
of
incoming
cold water and he
stored hot
water
(25%).
Therefore
it
can
be seen that he
stored
water s there
to
provide
for
a
peak
1750
litre draw-off
occurring
over
any period
from,
say
ten minutes
upwards.
For
consideration
purposes
1750 litres
equates
to 35
baths, each using
50
litres
of
60C
stored hot water.
Dependant
on
the bath
usage
ratio of either
1200, 2400,
or 4800
seconds
frequency
of
use
(see
simultaneous demand
data)
the hot
water
stored
could
be used
up
after
a
63
minute
period. Alternatively
1750 litres
could
provide
or 73
persons having
a
shower,
each
asting
5
minutes
using
24
litres
of
60C of
stored hot
water
(mixed
with
cold). Dependant
on the
shower
usage
rate
of
900, 1800,
or
2700
seconds
frequency
of
use,
the
hot
water
stored could
be
used
up
aftera
45
minute
period.
These
two
examples are
based
on a
peak
statistical
usage
which
would
likely
not reoccur
during
the
remaining
time of
the
two hour
re-heat
period.
A
semi-storage'
hot water
generator
requiring
to
meet he samedemand or
bathswould need o be
capable
of
providing, approximately
a
3.3
litre
per
second
flow rateof65C
continuous hot
water
output, assuming
an
initial stored
volume
capacity
of500
itres.
These
potential
peak
demands could be
considered
as
being
extreme
examples.
However
they
clearly demonstrate the
demands
capable
of
beingput
on hot
water
generation,
when
taking
accountof
the
maximum simultaneous
usage
hat is
imposed
on draw-off
ittings
by
the
building occupants,
and
accordingly
has
to
be
considered
for
designpurposes.
Whatever
the
building,
the
likely
pattern
of
hot water
usage
should be assessed
and
considered.
The
hot
water
usage
will
be
directly
elated
to the
building
function,
its
occupancy
and he
type
of
Figure
8
Typical
demand
pattern
histogram
activity
that is
likely
o
take
place.
In
determining
the
pattern
of
usage,
it is
important
to
differentiate between
a
maximum
daily
demandand an
average
daily
demand,
so
that he
implications
of
the
system
not
meeting
the
buildings hot
water
equirements
can be
recognised,
and
the
maximum
requirements
designed
for
where
necessary.
Measured
quantities
of
hot water
consumption
should
not
stand
alone
as
a
sizing guide.
The rate
at
which these
amounts
are
drawn
off
must also
be
considered. To
project
the demand
pattern
over he
operating period
of
the
building,
an
hour
by
hour
analysis
of
likely
hot water
usage
should be
made,
taking
nto account
he
numberof
occupants,
the
type
and
evel
of
activity
and
anyother
actors
thatmayaffect
hot
water
demand.
The
projected pattern
of
demand should
be
recorded
in the
form
of a
histogram profile.
Typical examples
of
daily
demand
in
various
types
of
buildings
are
illustrated
in
Figures
8
and
9.
Byestablishing
a
hot
water
demand
histogram
a
epresentative peak
demand
volume can
be
established.
Typically
the
peak
hour
s
between 15-20%
of
he
day's
otal
usage.
When
selecting
a
semi-storage'
hot
water
production unit(s)
it
needs
to
be
recognised
that
the
small
stored volume
is there
to
meet
he
short
period peak
draw-offs that occur n
any
water
supply
system.
The shortest
of
these
peak
draw-
offs is the 'maximum' simultaneous
demand
itre
per
second low
rate
figure
calculated from the sum
of
he draw off
'demand'
or
loading'
unitsused
or
pipe
sizing.
However, periods
of
ime that
these low ratesoccur are
very
short,
and are
based
on
the
period
of
ndividual
draw-
off,
i.e.
length
of time
o fill a
basin,
7
3500
3000
2500
-
2000
E.
1500
1000
500
0
0 6 12 18 24
Period
8/10/2019 GL Plumbing Engineering Services Design Guide
17/249
Hot
and
cold
water
supplies
Plumbing Engineering
Services
Design
Guide
The
Code
dentifies
specific practical
guidance
on
how
this
is to
be
achieved
in
water
supply systems.
The
key
aims
being:
1.
Maintain
cold water
below 25C
2.
Maintain stored hot waterbetween
60-65C
3.
Maintain
hot water
distribution above
50C,
and
preferably
at
55C
4.
Insulate all
cold and hot water
storage
vessels anddistribution
pipework
5.
Minimise
the
length
of
un-circulated
and none
race
heated
hot
water
pipes
6.
Avoid
supplies
to
little
or
unused
draw-off
ittings
7.
Maintain
balanced
use and
flows
through multiple
cold water
cisterns/tanks and hot watervessels.
See
Figure
13.
NOTE:
For
urtherdetails
please
see
legionella
section',
containedwithin his
guide.
Safe water
temperatures
Safe
water
emperatures
need to
be
considered
for
hot
water
supplies
to
appliances
used
by
he
elderly,