49
1 THE ENERGY OF MILLON PEOPLES. ON SITE DISASTER /EMERGENCY PLAN OF GIRAL LIGNITE POWER LIMITED BARMER.

Giral lignite power plant barmer

Embed Size (px)

DESCRIPTION

full description about plant

Citation preview

  • 1

    THE ENERGY OF MILLON PEOPLES.

    ON SITE

    DISASTER /EMERGENCY

    PLAN OF

    GIRAL LIGNITE POWER LIMITED

    BARMER.

  • 2

    INDEX. DESCRIPTION.

    1. General Information. 2. Brief Description of the plant and process involved in power Generation 3. Out Line of Disaster Plan.

    1.0 Background and Introduction. 2.0 On site emergency plan.

    2.1 Objective. 2.2 Distribution. 2.3 Categorization of Disaster. 2.4 Emergency teams. 2.5 Protection and prevention of fire. 2.6 Fire prevention system. 2.7 Communication.

    4. Chapter 1 ONSITE EMERGENCY RESPONSE PLAN.

    1.1 Objective. 1.2 Scope of planning 1.3 Co-Ordination requirement. 1.4 Distribution of OSER Plan. 1.5 List of Address Telephone Nos of key personals. 1.6 Training 1.7 Staff Education. 1.8 Fire Safety Staff. 1.9 Training to fire & Security Staff.

    5. Chapter 2 2.0 ORGANISTION & CONTROL 2.1 Address & Telephone Nos of key persons. 2.2 Internal & External Help. 2.3 Site Management. 6. Chapter-3

    3.0 Emergency teams. 3.1 Categories of Disasters. 3.1.1 Mechanical Disaster 3.1.2 Electrical Disaster 3.1.3 Chemical Disaster 3.1.4 Natural Disaster 3.2 Emergency Teams for various areas. 3.3 Name & Address of various teams In charge and

    7. Chapter-4 4.0 Fire Fighting.

    4.1 Fire Fighting Equipments. 4.1.1 Hydrant System.

  • 3

    4.1.2 HVW &MNW spray system. 4.1.3 Mechanical foam system. 4.1.4 Fire detection system for misc.Building. 4.1.5 Fire Tenders 4.1.6 Portable Fire Extinguishers. 4.1.7 Fire Hooter.

    4. 2 Fire Fighting Operation. 8. Chapter-5 5 Transportation. 9. Chapter-6 6.0 Communication. 6.1 Communication by phone and PA Systems. 6.2 Communication by Sirens. 6.3 Communication in case of failure of power supply and phones. 10. Chapter-7 (SECTION A) MECHNICAL DISASTER.

    7.1 Fire in Boiler Area. 7.2 Fire in Turbine Area 7.3 Fire in turbine main oil tank, Dirty /clean oil tanks and pressuring pump house. 7.4 Fire and Explosion in FO/HSD tanks. 7.5 Fire in coal storage/ conveyor belt in Lignite area. 7.6 Spillage of FO/LO in tanks farm area. (SECTION B) ELETRICAL DISASTER. 7.7 Fire in Switch Gear Area. 7.8 Fire in Switch Yard Area. 7.9 Fire in cable galleries. (SECTION C) CHEMICAL DISASTER. 7.10 Introduction. 7.11 Emergency and Hazards. 7.12 Caustic Soda lye leakage from storage tank. 7.13 Chlorine leakage. (SECTION D) NATURAL DISASTER. 7.14 Introduction.

    11. Chapter-8 HAZARDS AND MEDICAL MANAGEMENT.

    12- vkikrdkyhu fLFkfr ,oa izkFkfed mipkj 13 Personal Protective Equipments.

  • 4

    GENERAL INFORMATION.

    1- Name & Address of the Power Station :- Giral Lignite Power Ltd. Village-Thumbali,

    Tehsil- Shiv, Distt: Barmer

    2- Name Address & Telephone No of Occupier : - Sh. J. C. Detwal, Chief Engineer, Ph:-02987-271001.

    (Mob. No.) 94140-65899, 99822-30913

    3- Name Address & Telephone No of safety

    Officer : - Sh. Ashok Parakh, Executive Engineer (F.F),

    GLPL, Barmer 9413349778 (M)

    4- Installed Capacity :- 2x125 MW.

    5- Product Manufactured :- Power Generation.

    6- Intermediate Product :- NIL.

    7- Location of hazardous Stores :- Mostly with plant area.

    8- Emergency Control Center :- Control Room Unit-I Tel:-02987-271011.

  • 5

    BRIEF DESCRIPTION OF THE

    PLANT & PROCESSES

    INVOLVED IN POWER

    GENERATION.

  • 6

    PLANT INSTALLED CAPACITY 250MW

    UNIT WISE DETAILS. Stage Unit Rating Date of Synchronization

    Stage-I

    Stage-II

    125MW

    125MW

    28.02.2007 26.12.2008

  • 7

    Brief Description of the Plant Giral Lignite Power Limited is situated about 12Kms from village Bhadka at Barmer-Jaisalmer

    National Highway. Total installed capacity of the plant is 2x125 MW.The principal raw material is lignite and

    light diesel oil and furnance oil is also used to start & to maintain temperature as and when required. 1- Process Involved in Power Generation:- Lignite having 6% sulphur from near by RSMM mines are

    unloaded at stock pile area through dumpers. The lignite is crushed in crusher and is transported

    through conveyer belt to lignite bunkers from which lignite is feed in to combustor. This lignite with the

    help of air supplied through PA &SA fans, is burn in the combustor in which temperature of 800-850oC is

    being maintained during the operation of the unit.

    This is circulating fluidized bed combustion (CFBC) based technology wherein large portion

    of flue gases with heavy particles are returned beck to combustor with the help of 2 nos of cyclones. The

    combustor is having sufficient quantity of bed material, which is being fluidized with the help of the

    primary air, which helps in combustion of lignite and flue gases from the furnace are extracted by

    induced draft fan which maintains balance draft in the furnace. These flue gases emits their heat energy

    to water tubes located in combustor, and in the second pass and finally passes through air pre heater

    and goes to electro static precipitator where the ash particles are extracted. Electro-Static Precipitator

    consists of metal plates which are electrically charged. Ash particles are attracted on to these plates, so

    that they do not pass through the chimney to pollute the atmosphere. Regular mechanical hammers

    blows cause the accumuled of ash to fall to the bottom of the precipitator where they are collected in a

    hopper for disposal.

    2- STEAM TO POWER:- A steam pipe conveyers steam to the turbine through a stop valve (Which can be used to shut off steam in emergency ) and through control valve that automatically regulate the supply of

    steam to the turbine. Stop valve and control valves are located in a steam chest and a governor driven,

    shaft operates the control valves to regulate the amount of steam used. (This depends upon the speed

    of the turbine and the amount of electricity required from the generator).

    Steam from the control valve enter the high pressure cylinder of the turbine, where it passes

    through a ring of stationary blades fixed to the cylinder wall. These act as nozzle and direct the steam in

    to a second ring of moving blades mounted on a disc secured to the turbine shaft. This second ring turn

    the shaft as a result of the steam. The stationary and moving blades together constitute a Stage of the

    turbine and in practice many stages are necessary, so that the cylinder contains a number of ring of

    stationary blades with ring of moving blades arranged between them.

    The steam passes through each stage in turn until it reaches the end of the high pressure

    cylinder and in its passage some of its heat energy is changed into mechanical energy.

    The steam leaving the high pressure cylinder goes back to the boiler for reheating and returns

    by a further pipe to the intermediate pressure cylinder. Here it passes through another series of

    stationary and moving blades.

    Finally the steam is taken to the low pressure cylinder, in which it enters at the center flowing

  • 8

    outwards in opposite directions through the rows of turbine blades (An arrangement known as double

    flow) to the extremities of the cylinders. As the steams give up its heat energy to drive the turbine its

    temp., and pressure fall and it expands. Because of this expansion the blades are much large and longer

    towards the low pressure end of the turbine.

    The turbine shaft usually rotates at 3000 RPM (Revolution Per Minutes).This speed is

    determined by the frequency of the electrical system used in the country and is the speed at which a-2-

    polegenerator must be driven to generate alternate current at a frequency of 50 cycle per second.

    When as much energy as possible has been extended from the steam it is exhausted directly to

    the condenser. Cold water is circulated through these tubes and as the steam from the turbine passes

    round them it is rapidly condensed into water (Condensate).Because water has a much smaller

    comparative volume then steam, a vacuum is created in the condenser. This allow the steam to reduce

    down to pressure below that of the normal atmosphere and more energy can be utilized.

    From the condenser, the condensate is pumped through low pressure heaters by the extraction

    pump, after which its pressure is raised to boiler pressure by the boiler feed pump. It is passed through

    further feed heater to the economizer and the boiler reconversion into steam

    3- SWITCHING AND TRSANSMISSION. The electricity is usually produced in the stator winding of large modern generator at 11000V and is fed through terminal connections to on side of a generator

    transformer that steps up to the voltage to 220000 volts. From here conductors carry it to a series of

    there switches comprising as isolator, a circuit breaker and another isolator. The circuit-breaker, which is

    a heavy duty switch capable of operating in a fraction of a second, is used to switch of the current

    flowing to the transmission lines. Once the current has been interrupted the isolators can be opened.

    These isolate the circuit-breaker from all out-side electrical sources, so that there is no chance of any

    high voltage being applied to its terminals. Maintenance or repair work can then be carried out in safety. Circuit-breaker work like combined switches and fuses but they have certain special features and are very different from the domestic switch and fuse. When electrical current is switched off by separating two contacts an arc is created between them. At the voltage used in the home the arc is very small and only lasts for a fraction of a second but at the high voltages used for transmission, the size and power of the arc is considerable and it must be quickly quenched to prevent damage. One type of circuit-breaker has its contact immersed in insulating oil so that when the switch

    is opened, either by powerful electrical coils or mechanically by springs the arc is quickly extinguished by

    the oil. Another type works by compressed air which operate the switch and at same time blow-out the

    arc.

    Three wires are used in a Three Phase system for large power transmission as it is

    cheaper than the two wire Single Phase system that supplies the home.

    The center of the power station is the control room. Here Engineers monitor the out put of

    electricity, supervising and controlling the operation of generating plant and high voltage switch gear

    and directing power to the grid system as required. Instruments on the control panels show the out put

    and conditions which exists on all the main plant and a miniature diagram indicate precise state of the

    electrical system.

  • 9

    ON SITE EMERGENCY PLAN.

  • 10

    OUT LINE OF DISASTER PLAN OF GIRAL LIGNITE POWER LIMITED.

    BACKGROUND AND INTRODUCTION : 1.01 Unfortunate devastation and disaster always come suddenly and unnoticed as happened in Bhopal in

    December-1984 on leakage of poisonous Methyl ISO Cyanide Gas from Union carbide company proved fatal to thousands of human beings who, came in contact and those who remained alive, their eyes, lungs, stomach, respiratory system damaged fully or partly. Earthquake in Bhuj (in Gujarat on dt. 26.01.2001) created heavy devastation in near by cities / Towns in redius of 200 KM in which thousands of people died.

    1.02 Therefore, to cope up the situation arised by any disaster, an On Site Emergency Response Plan have been prepared.

    2.0 ON SITE EMERGENCY PLAN:- 2.01. OBJECTIVE: The objective of the On Site Emergency Response Plan line with the requirement of

    Factories Act as amended in 1987 to safe guard the health and safety of personnel at the plant site and surroundings in the event of any emergency arising out of accidental explosion blasting or spillage, leakage of Toxic gases or any other bursting of equipment in the plant. On Site Emergency Response Plan as out lined and prepared to achieve the aforesaid objective will come into force automatically for minimizing the risk and loss of lives as well as damages to the properties of the plant.

    2.02DISTRIBUTION: Copy of this plan have been distributed among district authorities, Tehsil Authorities Dy. Inspector (F&B) for Information and with request to send their suggestion / comments. Couples of above plan were also circulated among the officers and staff of GLPL for educating them and to how they should response to the occurrence any disaster in the plant.

    2.03 CATEGORIZATION OF DISASTER: To achieve the sole objective of the ON Site Emergency Response Plan all type of disaster are distributed broadly in to four categories according to the working jurisdiction of the emergencies team:

    A. Mechanical Disaster B. Electrical Disaster C. Chemical Disaster D. Natural Disaster

    2.04 EMERGENCY TEAMS:

    For each identified category as given above, where the disaster situation can anticipated, the corresponding emergency team has been constituted. These in all 15 emergency teams have been finalized by nominating the concerned staff of the jurisdiction as per annexure enclosed.

    2.04.1 In all emergency team the Superintending Engineer of the jurisdiction concerned has been nominated as the Incharge of the team and the concerned Superintending Engineer, Executive Engineer, Assistant Engineer, Sr. Chemist, Chemist are the member of the team to handle the disaster. 2.04.2 In almost all disaster the emergency team nominated from the fire fighting wing has to participate in all type of disaster, whatever type or nature of disaster it may be. 2.04.3 A Crew of the fire staffs remain on duty round the clock and all controllable hazard or fire break down are being handled competently by them to prevent the hazard from becoming disaster. Two Supervisor, two fire fighter driver & eight firemen are performing duty per shift round the clock in the plant.

  • 11

    2.05 PROTECTION & PREVENTION OF FIRE: 2.05.1 In Thermal plant, the chances of break out of fire in different areas are very high and if these are timely

    not controlled, then these hazard can possibly turn in to the disaster. So to avoid such situation in GLPL, the protections and preventions against fires have been given special attention.

    2.06 FIRE PROTECTION SYSTEM: 2.06.1 The following fire fighting systems have been installed and working satisfactorily in the plant.

    2.06.2 A. Hydrant System: 137 Nos. Hydrant point, 45 First Aid hose reels and 16 water monitor have been provided at required locations.

    2.06.3 B .Medium Velocity water spray system: All cable galleries, cable vaults, conveyor belt FO/LO tanks have been protected against fire through M.V.W. spray system.

    2.06.4 Mechanical foam system: These systems have been provided to pour foam to extinguish fire in side the FO/LO tanks.

    2.06.5 Fire detection, Annunciation and alarm system: System have been provided to detect fire in Main plant Control Room / MCC Room / SWGR/ Cable Galleries / Vaults / Battery / Lignite Control Room and conveyors.

    2.06.6 Fire Tenders: Three Nos. fire tenders are available in plant to look after the Emergency. 2.06.7 500 Nos. of Portable fire extinguisher have been deployed over various locations of plant to deal with

    any fire emergency.

    2.07 COMMUNICATION: 2.07.1 The communication also play very role to achieve the objectives of OSER Plan promptly and

    accordingly in the Giral Lignite Power Ltd, Barmer the following mode of communication are available between plant and city to deal with the situation immediately: A. P&T Telephones. B. PA system (Public Address system) C. Siren in Plant D. PLCC (Power Line Carrier Communication).

    2.07.2 Through above mentioned systems of communication, the shift Incharge Engineer can promptly pass on the information to the In charge and members of the emergency team, accordingly to the disaster, in the plant, so that the situation may be controlled at the earliest possible.

    2.07.3 Thus, concluding that On Site Emergency Plan of GLPL has covered almost all types of disaster and emergencies of Mechanical, Electrical, Chemical & General etc. so as to educate the concerned

    staff for pre-acquaintance and training to deal with the emergence promptly.

  • 12

    ON SITE EMERGENCY RESPONSE PLAN CHAPTER-I

    1. GENERAL: 1.1 Objective: In line with requirement of factories acts, as amended in 1987, to safeguard the health and safety of personnel at the plant site and surrounding in the event of any spillage / leakage of toxic gases or any other type of bursting of equipment in the plant, then the On Site Emergency Plan as out lined and prepared will come into force automatically, for implementation and bringing various activities co- ordinate quickly for minimizing risk and loss of life and properties of the plant, consequently achieving some object of On Site Emergency Response Plan.

    1.2. Scope of Planning: An Emergency in the context of present On Site Plan is an emergency at the facilities or premises of Giral Lignite Power Ltd.Barmer 1.3 Co-ordination requirement:

    1.3.1 The success of the implementation of On Site Emergency Response Plan largely depends on the effective co-ordinations and Co-operation of various agencies at fast pace and participation fully in the incidence / accident emergencies. 1.3.2 For expeditious action all the concerned authorities shall work as ONE TEAM under the direction of

    the On Site Emergency Controller. 1.3.3 Even though the operations of the power are carried out according to the stringent safety standard

    but even then the remote possibility of Mechanical failure, human error or sabotage can not be over ruled in totality and accordingly the basis of On Site Emergency Plan has been felt and given due importance in our plant.

    1.3.4 Distribution of the OSER plan: Numbered copies of the authorized plan will be issued to all concerned as per requirement. A few copies shall also be kept as spare and will be made available to others who may need it subsequently or whenever they feel the requirement.

    1.3.5 List of address and telephone Nos. Key personnels: A separate list of address and telephone numbers of the key personnel as well as other connected with emergency response shall maintained by the site emergency controller. List shall be updated /maintained once in the three months and shall be circulated to all members and other concerned of emergency response. 1.6 TRANING: i. Training of personnel including study course. ii. Notification and assembly exercise for emergency organization.

    iii. Mock exercise at the emergency centers to practice the operating produce. iv. Mock exercise for field staff / fire staff / personnel / Security staff. v. Full scale mock exercises in which all aspect on (OSER Plan) are to be participate.

    1.7 Staff Education: All the staff of various section likely to be effected on occurrence of any emergency in the plant must be made aware of possible hazards in anticipation through training as per para 1.6 so that they can help in minimizing the exposures and to check / control maximum adverse effect of the situation. The people living in the close vicinity of chemical facilities or working in such in the plant must be provided to the norms of On Site Emergency response Plan.

  • 13

    1.8 Fire and Security staff:- All the fire, safety & Security staff shall be required in participating in all types of occurrence of emergencies and accidents in the plant. The shift Incharge Engineer of Unit-I Control Room shall switch on the siren placed at the top of service building from control room to alarm the fire staff and he shall also intimates on PA system at various locations to rush up, to fire site for additional help. Security staff posted in Service Bay Unit-I and 13.5 Mtr. Elevation will rush along with fire staff and one person will attend telephone of fire control room Emergency Tel No. of Fire Control Room is 9783082563.

    Security staff / Drivers in barrack will also rush to location as soon as informed. They must get themselves prepared and trained with all safety tools equipments to

    deal with the emergency as per the situation. They are thus have to develop sufficient experience and Knowledge to safe guard themselves and other while confronting and handling such situation by avoiding exposure and ill effect to toxic gases or hazardous chemicals.

    All attention shall be focused / concentrated on safety of men, materials and properties of plant while struggling the situations.

    1.9 Training to Fire and Security staff: Fire and Security staff must be deputed for short training programs as per Sr. No. 1.6 to improve the over all performance in dealing with the emergency in the plant efficiently.

  • 14

    CHAPTER-2

    2.00 Organization and Control:- 2.01 Address and Phone No of key persons. The following officers are controller of Disaster for their areas:-

    S. No

    Name

    Designation

    Office Address

    Office Phone

    Office Phone

    Mobile

    VPN

    P&T EPBX

    1

    Sh. J.C. Detwal

    M.D Adm. Building. 9414065899 2716 02987-271010

    2

    Sh. J.C. Detwal

    C.E Adm. Building. 99822309132716 02987-271001

    3 Sh. A. K. Mathur

    Dy. C.E (Opr. & Elect)

    Adm. Building. 9414065895 9982230914 2713

    4

    Sh. N. C. Gupta

    Dy. C.E (L&L)

    Adm. Building. 94140650689982230920 2710

    5

    Sh. Om Prakash Padonia

    S.E(Boiler) Adm. Building. 94133851779982200526 2788

    6 Sh. P. R. Arora

    S.E(AHP)

    Adm. Building. 94140648499982200523 2849

    7

    Sh. M.L. Choudhary

    Dy. C.E ( Civil )

    Adm. Building.

    9414048032

    2720

    In Charge Control Room Unit-I

    02987-271011

    In Charge Control Room Unit-II

    02987-271016

    2.1.2 Name and address of Fire Fighting Staff:-Operation Duties: In charge Control RoomUnit-1. General Duties

    S.No Name Desig Office Phone

    Mobile VPN

    1

    Sh.Ashok Parakh

    X.En (F.F) 9413349778 22778

    2

    Sh.U.C.Chobisa

    A.En( F.F) 9413349779 22779

  • 15

    2.1.3 Security Staff.

    S. No

    Name

    Desig

    Office Phone P&T VPN

    1 Sh. Ashok Chalana

    X.En(Sec.) 9413385652 2852

    2 Sh. Tikam Chand Deora J.En (Sec) 9413342810 242810

    3 Sh.Narendra Gour J.En (Sec) 9413342756 242756

    4 Sh.Swaroop Singh Security Officer. 9413385695 2695

    Detail of duty location of ASOs/Security Guards in each shift in Giral Lignite Power Ltd. Station Barmer

    Locations ASO in shift Security Guards in shift I II III I II III 1 Main Gate a For making entries, issuing

    visitor Gate Passes and misc. record works

    1 1 1

    b Gate 1 1 1 For - Out vehicle checking 1 1 1 For - In vehicle and gate pass

    checking 1 1 1

    At - Barmer 1 1 1 2 Gate No. 2 (Security Office for

    vehicle parking) 1 1 1

    3 Gate No. 3 (Lime & Lignite Entry gate)

    1 1 1 2 2 2

    4 0 mtr Area (Service bay) Unit-I

    1 1 1 1 1 1

    Unit-II 1 1 1 5 Boiler Area Unit-I

    1 1 1

    Unit-II 1 1 1 6 Lime mill bldg. & Lignite

    Hopper (Unit I & II) 1 1 1

    7 Compressor, Blower & DG Set area

    1 1 1

    8 Switch gear Room (3.5 mtr. Area)

    Unit-I

    1 1 1 Unit-II 1 1 1 9 Cable Galary (8.5 mtr. Area) Unit-I

    1 1 1

    Unit-II 1 1 1 10 12 Mtr. (Turbine Floor area) Unit-I

    1 1 1

    Unit-II 1 1 1

  • 16

    11 18 Mtr. Area Unit-I

    1 1 1

    Unit-II 1 1 1 12 Bunker 33 mtr. Unit-I

    1 1 1

    Unit-II 1 1 1 13 ESP, Chimney and nearby area Unit-I

    1 1 1 1 1 1

    Unit-II 1 1 1 14 Switch Yard 1 1 1 15 Crusher House, DM Plant WTP

    area & Adm. Bldg. 1 1 1

    16 Raw water pump house and cooling tower I & II

    1 1 1

    17 Raw water reservoir II 1 1 1 18 CW pump house & office area 1 1 1 19 Fuel Oil pump house 1 1 1 20 Store shed area 1 1 2 21 Civil & Mechnical Office area 1 1 1 22 Front boundry wall (Gate No. 2

    of left corner near Guard Pond upto Cooling tower.)

    1 1 1

    23 Front boundry wall & steel storage yard.

    1 1 2

    24 Back side wall (gate No. 3 to raw water resorvior-II)

    2 2 2

    25 Left side boundary wall (towards mine road upto gate No. 3)

    1 1 1

    26 Right side boundary wall 1 1 1 27 Patrolling Duty (Inside &

    outside Plant site with vehicle) 1 2 2 2

    28 Erector Hostel area 1 1 2 29 Labour Colony 1 1 2

    30 MD Office, Barmer 1 1 1 31 Barmer Colony 1 1 1 32 Barmer Rest House 1 1 1 33 Jalipa Colony a Main Gate 1

    ASO 1

    Supr. 1 1 1

    b Gate No. 2 (towards TALAI/Pond)

    1 1 1

    c Gate towards Barmer City 1 1 1 d Along complete boundary

    including petrolling 1 1 2

    Total 6 5 6 48 49 54

  • 17

    Deployment Of Home guard

    Location ShiftInchargeHomeGuards

    Inshift LocationareatUnitIareaonly I II III I II III1 maingate0.00mtr. 1 1 1 2 SwitchGearRoom(3.5mtr.) 1 1 13 CableGalary(8.5mtr.) 1 1 14 turbinefloorArea(12.0mtr.) 1 1 15 BoilerArea(12.0mtr.) 1 1 16 BunkerFloor(18.0mtr.) 1 1 17 DGSetarea 1 1 18 LimeHasndingPlant(mill) 1 1 19 Boiler&ESParea(0.0mtr.) 0 1 110 CompressorandBlowerrooms 1 1 1 LocationareatUnitIIareaonly 1 maingate0.00mtr. 1 1 12 CableGalary(8.5mtr.) 1 1 13 Boiler&ESParea(0.0mtr.) 1 1 1

    Total 1 1 1 11 12 12

    NAME AND ADDRESS OF VARIOUS TEAM INCHARGE AND MEMBERS. Emergency team A Location whole plant.

    S. No

    Name

    Design

    Telephone P&T

    Office

    VPN

    1.

    Sh. J. C. Detwal

    C.E.

    9414065899 9982230913

    2716

  • 18

    SUB EMERGENCY TEAM A-1 AREA COMPLETE PLANT INCHARGE. In charge:-Sh. A. K. Mathur Dy. C.E (Opr.)

    S.No Name Design Telephone P&T

    Office VPN

    1

    Sh. A. K. Mathur Dy. C.E (Opr.) 9414065895 2713

    2

    Sh. Ashok Parakh X.En(F.F) 9413349778 22778

    3

    Sh. U. C. Chobisa A.En(F.F) 9413349779 22779

    SUB EMERGENCY TEAM B LOACTION WHOLE TG BOILER AREA INCHARGE In charge:- Sh. Om Prakash Padonia

    S.No Name Design Telephone P&T

    Office VPN

    1 Sh. Om Prakash Padonia

    S.E (B&T) 9413385177 2788

    2 Sh. Rakesh Verma X.En (Boiler) 9413385635 2635

    3 Sh. Sanjay Mishra A.En(Boiler) 94133-49831 22831 4 Sh. Virendra Singh

    J.En (Boiler) 9413342722 242722

    5 Sh. Praveen Gupta J.En(Boiler) 9413342718 242718

    SUB EMERGENCY TEAM B-2 TURBINE AREA INCHARGE: Sh.O.P. Padoniya. SE (B&T)

    S.No Name Design Telephone P&T

    Office VPN

    1. Sh. Om Prakash Padonia S.E (B&T) 9413385177 2788

    2. Sh. A.K. Beniwal XEn (Turbine) 9413384561 2754

    3. Sh.Mukesh Paliwal A.En(Turbine) 9413342711 242711

    4. Sh.Mukesh Borana J.En(Turbine) 9413342771 242771

  • 19

    SUB EMERGENCY TEAM B-3 AREA COM. AUXILIARY INCHARGE:-Sh. J. C. Detwal SE (CA-M)

    S.No Name Design Telephone P&T

    Office VPN 1

    Sh.J.C.Detwal

    SE(CA )

    9414065899

    2716

    2

    Sh.Shyam Veer Singh

    X.En(C.A)

    9413385633

    2633

    3

    Sh.Salam Singh

    A.En(C.A)

    9413342712

    242712

    4

    Sh.Bharat Kumar

    J.En(C.A)

    9413342792

    242792

    5

    Sh.Bagendra Singh

    J.En(C.A)

    9413342716

    242716

    SUB EMERGENCY TEAM B-4 AREA CLARIFIER DM PLANT

    INCHARGE: - Sh. Anant Amitabh (Sr. Chemist)

    S.No

    Name

    Design

    Telephone P&T

    Office VPN 1

    Sh. Anant Amitabh

    Sr. Chemist

    9413349784

    22784

    2

    Sh. U. C. Chobisa

    A.En (F.F)

    9413349779

    22779

    3

    Sh. Jitesh Chouhan

    Jr. Chemist

    9413342704

    242704

    EMERGENCY TEAM C LOCATION WHOLE C&I AREA INCHARGE Sh. Suresh Chandra SE (C&I)

    S.No

    Name

    Design

    Telephone P&T

    Office VPN

    1

    Sh. Suresh Chandra

    S.E(C&I)

    94133-85674

    25674

    2

    Sh. R. P. Meena

    X.En(C&I)

    94133-85632

    2632

    3

    Sh. M.S. Rathore

    A.En(C&I) 9413349961 22961

    4

    Sh. Aakash. Tayal

    A.En(C&I) 9413349963 22963

  • 20

    SUB EMERGENCY TEAM C-1 WHOLE ELECT AREA INCHARGE: Sh. A. K. Mathur Dy. CE (Elect.)

    S.No

    Name

    Design

    Telephone P&T

    Office VPN 1

    Sh. A. K. Mathur

    DY. C.E (Elect.)

    9414065895

    2713

    2

    Sh. P. Dhariwal

    X.En ( Elect )

    9414049718

    2735

    3

    Sh. M. L. Sharma

    A.En( Elect )

    9413385649

    2649

    4

    Sh. Vasim Khan

    J.En( Elect )

    9413342755

    242755

    EMERGENCY TEAM D LOCATION LIGNITE & FUEL OIL / HANDLING PLANT.

    INCHARGE:-

    S.No

    Name

    Design

    Telephone P&T

    Office

    VPN

    1

    Sh. N. C. Gupta

    Dy. C E (L&L)

    9414065068

    2710

    2

    Sh. A. K. Agarwal

    X.En (Fuel)

    9414063231

    2531

    SUB EMERGENCY TEAM D-1 WHOLE LIGNITE AREA

    INCHARGE:-Sh. N. C. Gupta Dy. CE (L&L)

    S.No

    Name

    Design

    Telephone P&T

    Office VPN 1

    Sh. N. C. Gupta

    Dy. C E (L&L)

    9414065068

    2710

    2

    Sh. Bigul Jain

    X.En (Lignite)

    9414049719

    2736

    3

    Sh. L. L. Koli

    X.En ( Lignite )

    9413385634

    2634

    4

    Sh. Keshav Khatwani

    X.En ( Lime )

    9413385651

    2651

    5

    Sh. U. S. P. Srivastav

    A.En ( Lime )

    9413349910

    22910

    6

    Sh. Harish Ladher

    A.En ( Lime )

    9413342809

    242809

  • 21

    EMERGENCY TEAM E LOCATION STORE AREA.

    INCHARGE :-Suresh Chandra S.E( STORE )

    S.No

    Name

    Design Telephone P&T

    Office VPN

    1

    Sh. Suresh Chandra

    X.En(Store)

    9413385674

    25674

    2

    Sh. R. K. Sharma

    A.En(Store)

    9413385645

    2645

    3

    Sh. Vijay Parihar

    J.En(Store)

    9413342714

    242714

    EMERGENCY TEAM F FOR ADMINISTRATION. INCHARGE: Sh. Raj Singh Assistant Secretary

    S.No

    Name

    Design Telephone P&T

    Office VPN

    1

    Sh. Raj Singh

    Asst. Secretary

    9414049813

    2741

    2

    Sh. Surendra Vyas

    Personal Officer

    9413385967

    2367

    3

    Sh. Rakesh Salvi

    A.P.O

    9413342813

    242813

    4

    Sh. Pankaj Chouhan

    A.P.O

    9413342814

    242814

  • 22

    2.2 Site Management: - The above officers in serial wise will be responsible for general Co- Ordination during emergencies and one out of them will designated as The Emergency Controller on occurrence of emergency. Shift in-charge Engineer (Control Room), Unit-I, II and Lignite handling plant Control Room will arrange to inform the respective officers on telephone in order of priority. They will also pass on the instructions security in charge. 2.3 The shift in-charge Engineer of concerning area will function as emergency controller. The significance of the emergency /disaster shall be evaluated by the concerning shift in-charge Engineer & accordingly he will intimate /start functioning. The concerning members of the emergency team are to be informed on telephone to attend the plant / specified site location, immediately and take over the control of the situation.

  • 23

    CHAPTER-3 3..00 EMERGENCY TEAM:- For each identified area of the plant where disaster situation can arise or anticipated emergency teams have been constituted. 3.01 The disaster are broadly categorized according to area.

    A. Mechanical Disaster. B. Electrical Disaster. C. Chemical Disaster. D. Natural Disaster.

    4.1.8 Mechanical Disaster:- The area of Boiler, Turbine, Pump House, FO/DO Tanks, MOT Clean/Dirty oil tanks, Lignite conveyors and other auxiliaries are covered in Mechanical disaster area. A few Mechanical disaster have been covered in this section for guide lines and according to these guide lines and also looking to the risk and type of emergency, the consequences of uncovered disaster can be safely dealt and handled by team A,B &C. 3.1.2 Electrical Disaster:-All the power cables and control cables have been laid in the different areas of boiler, turbine, along the conveyers, switch gears, cables galleries, cable ducts, EHT and service transformer, generator, DG sets etc. These cables are also prone to fire on account of short circuit or back up of fire out side. To attend such fire hazard emergencies we have constituted electrical emergency team C and C1.

    3.1.3 Chemical Disaster:- To deal with hazards like leakage of toxic gases leakage of acids Alkalies etc, the chemical emergency team has been constituted as team B-4.

    3.14 Natural Disaster:- Disaster due to earth quake , flood, storms which may cause heavy devastation of man and material and effect different areas at a time in such situation action is to be taken according to SectionD.

  • 24

    CHAPTER-4

    4.0 FIRE FIGHTING:

    4.01 Fire fighting: The following fire fighting systems are in operation for fighting the fire in the plant.

    4.01.1 HYDRANT SYSTEM: About 137 Nos. Hydrant points, 16 water monitors and 45 First Aid hose reels are available in the plant. These points are being fed through 2x410 m3 / Hrs. 8 kg / cm2. Hydrant pumps, Diesel Engine operated pumps 2x410 M3 / Hr., at 8 kg / cm2.

    4.01.2 High Velocity spray system: All EHT transformers, coal yard, ESP transformers, clean / dirty oil tanks, main oil tanks have been provided with H.V.W. spray system. The cable galleries, coal conveyor have been provided with spray system are through 1x410M3 / Hrs, 8 kg / cm2 Electric pump. The pump mentioned in hydrant system shall also be utilized for spray system.

    4.01.3 Fire detection system for Misc. Building: Fire detection system has been provided for main control room / cable Galleries, MCC room / DM Plant / Lignite control room / coal conveyors.

    4.01.4 Fire Tenders: Three Nos. of Fire tenders are available round the clock and being utilized for extinguishing fire in the plant.

    4.01.5 Portable Fire Extinguishers: Around 500 Nos. of portable fire extinguisher of various type have been kept at different locations in the plant.

    4.01.6 Fire Hooters: One siren has been installed at the top service building which can be Switch ON from Control Room Unit-I to intimate the fire staff to the fire site. The siren available in PA systems shall also be Switch on.

    FIRE FIGHTING OPERATION:

    4.2.1 In each shift 2 nos of Fire Supervisor, responsible for fire fighting along with other fire fighting staff are available to handle the situation, in case of break of fire in the plant. The Fire Supervisor for fire fighting posted in each shift are available in the Fire Fighting Control Room. The movements and where about of Fire Supervisor will be known to shift inch Engineer (Unit-I) for coordination, with internal and external agencies. Whenever the information of any fire hazard is received through shift charge Engineer (Unit-I) or directly by the Fire Supervisor he will direct / inform the fire fighting staff immediately.The Fire Supervisor will provide all necessary details of the location where the fire hazard taken place to in- charge of the fire gang on PA system to avoid any delay in reaching the site. The Fire Supervisor will also rush to the site for extinguishing the fire as early as possible with the available staff. The Fire Supervisor will request shift Inchrage Engineer to provided assistance of additional staff under him and arranging security persons for extinguishing the fire in the minimum possible time. The shift charge Engineer shall intimate on PA system the location of fire incident and advise site for additional help. The Assistant security officer at ZERO point (service Building of Unit-I) shall also rush the fire staff in extinguishing the fire. The operators identified to assist the fire staff will rush to fire location.

    4.2.2 The Shift Incharge & Fire Supervisor on Duty will also decide after inspecting the site for calling additional fire tenders from RSMM Giral, Rajwest Power, Bhadresh etc and concerning area who will manage to use the fire tenders immediately or receipt, without loss of time.

    4.2.3 The Fire Supervisor will report to senior Disaster controller (SDC) on this arriving at site and

  • 25

    will apprise him about the efforts made for extinguishing the fire, and for additional help if required to meet the situation. The senior emergency controller will handle the situation thereafter as per demand of situation.

    CHAPTER-5

    5.0 TRANSPORTATION:- 5.1 Superintending Engineer (Opr.) / X.En Support-I / shift in charge will provide all necessary

    assistance to the Shift charge, Engineer in arranging transport to meet out emergency. They will provide BUS/JEEP on priority by shift Inchrage Engineer in additional to one Ambulance and the control room will also spare their JEEPS immediately so as to meet emergency.

    5.2 Shift incharge Engineer will alert the medical team to co-ordinate for hospitalizing in Barmer Hospital and giving first aid to victims in Thumbali / Bhadka Dispensary as well as at plant site.

    5.3 All the staff of the plant and concerned staff are supposed to rush to the site of the emergency accident with fellow colleagues to the plant immediately on receipt of intimation or by sound of siren. No excuse for any slackness shall be considered in case of defying the situation.

    5.4 Security Staff assist the staff for traffic control as per instruction of shift In charge. They shall also assists to shift the victims to near by dispensary at Bhadkha / Barmer Hospital.

  • 26

    CHAPTER-6

    6.0 COMMUNICATION: In case of a Disaster in plant, shift charge Engineer unit Control Room-I will act as disaster controller till the Superintending Engineer of that area or any authority

    nominated as disaster controller reaches at the spot. 6.1 Communications by Phones and PA system: 6.01 The Public address (PA) system have been extended to cover almost the entire plant. P&T

    telephone No. Control Room I 02987-271011, Control Room-II 02987-271016, Additional P&T telephone are available in the various office chambers established in the Disaster situation / devastation.

    6.02 A list of telephone numbers and address of the persons to be informed in each type of emergency have been kept in the main Control Room Unit-I, II, and Lignite Control Room.

    6.03 Shift charge Engineer Control Rom Unit-I, II, Lignite area will be responsible for informing all concerned through local / P&T telephones / mobile phones. The reliability of telephones therefore, be checked in each shift and should be made to restore the faulty telephone of Control Room. All the Staff of GLPL, up to the rank of JENs has been provided deptt. Mobile phones and they shall use there mobile phones for communications. On hearing siren, the security guard of each area will rush to the location of disaster & help the disaster team to control the Fire Station.

    6.02 Communication by Sirens: 6.3.1 Communication in case of failure of power supply and phones: 6.3.2 In case of phones are faulty or out of order JEEP available in shift can be used by charge

    Engineer Control Room (UnitI to II, Lignite Control Room) on duty will arrange to intimate through helpers/Operators available in the control room (runner messenger) to the all concerned about the disaster. Two or more security persons deployed on one location may also spare the guards to reach at disaster place. ASO/ Guards deployed at service bay unit-I will rush up with fire staff immediately and one guard will be left in fire control room for attending telephone.

  • 27

    Section A Mechanical Hazards

    CHAPTER-7 7.0 MECHANICAL DISASTER:

    7.01 Fire in Boiler Area: Shift Incharge Engineer of control Room unit-I & II of the affected area,

    after inspecting the intensity and potentiality of the disaster shall inform the boiler fighting wing available on duty along with staff of the boiler area in the shift, for commencing proactive measures as well as controlling / extinguishing the fire to the extent possible. Simultaneously, the shift charge Engineer will also try to inform all concerning members of emergency team to arrive at site immediately to control the situation. In case of acute emergency, the shift charge Engineer / Fire Supervisor will instruct to sound up the siren. The shift Engineer of concerning area will also direct the additional staff as per gravity to the situation to control the fire as quickly as possible. The assistance of

    the following persons may be taken as per requirement: a. Operators , Helpers and contractors workers available in the Boiler area of Unit-I & II b. Security guards available in the plant area. c. Staff working in the other area, such as TG, Lignite handling etc. d. Fire Fighting staff residing nearby, not on duty.

    7.01.2 ACTION TO BE TAKEN: 1. After having assessment of the situation and intensity of fire hazards at site, it will be seen /

    assessed by the shift charge Engineer and Fire Supervisor that sufficient number of fire tenders, Fire Fighting equipments are available, shall be.

    2. It will be seen that man power available is sufficient to control the situation; otherwise additional man power shall be asked from other sections of plant.

    3. For any technical assistance, the concerned authority shall be contacted on phone and called on.

    4. If medical assistance is required, the medical officer of General Hospital, Barmer should be contacted.

    7.01.3 DETAILS OF DRILL: 1. Cordon off the area and keep un-authorized persons away. 2. Keep all approach road clear. 3. Provide proper protective equipments as required. 4. Extinguish the fire with appropriate fire extinguishers, fire hydrant and fire tenders, such as

    foam, DCP powder, water etc. 5. Restrict the fire in a limited area. 6. Ensure that all personnel in the area are safe. 7. Do not permit any one to enter the affected area without proper protective equipments.

    Note: The requirement of protective and safety T&P equipment as per enclosed annexure must be arranged to deal with the emergency with due safety.

  • 28

    FIRE IN TURBINE AREA: The Shift charge Engineer of Main Control Room Unit-I & II of the affected area after inspection of the intensity and potential of the situation shall inform the incharge of turbine area in the shift for commencing the protective measures as well as extinguishing / controlling the fire up to the extent possible. Simultaneously, the Shift charge Engineer will inform all concerning members of emergency team as detailed hereunder.

    The Shift charge Engineer will also direct the additional staff of other area, contractors staff, if the situation so demands. He will also take the action as detailed in the fire in boiler area.

    DETAILS OF DRILL: 1. Cordon off the area keep un-authorized persons away. 2. Keep all approach road clear. 3. Provide proper protective equipment as required. 4. Extinguish the fire with appropriate fire extinguishers with plain water as the case may be. 5. Restrict the fire in a limited area. 6. Ensure that all area of fire is safe.

    7.03 FIRE IN TURBINE MAIN OIL TANKS, DIRTY / CLEAN OIL TANKS: Water spray system have been provided far all MOT and Dirty / Clean oil tanks. Foam compound I

    drums and Zerrycans has been placed at Zero Mtr. elevation to spray foam though hydrant system in bulk quantity.

    On receiving intimation of fire in MOT, following action are to be taken by Shift Incharge Control Room-I&II.

    1. Intimate fire staff by sounding siren from Control Room and tell location of fire on phone / PA system. Mean while, Fire Supervisor along with other Control Room staff should rush up to location. 2. Operate water spray system of the MOT. 3. Isolate the electric supply system of the MOT & its room with the help of electric staff. 4. Fire staff will spray foam on MOT from 8.5 Mtr. Elevation as well as from ground floor in the tank.

    Foam compound drum / Zerrycans of near by area will be brought by the help of security staff / of the available staff.

    5. Call security staff from main gate / Barracks. 6. Siren in Control Room -I will be switched on by instructing Shift Engineers to call help of fire staff

    residing in plant. 7. Inform the emergency teams and their Incharge.

    7.03.2 DETAILS OF DRILL: 1. Cordon of the area and keep un authorized persons away with help of security staff. 2. Available staff should be ready for extinguishing fire with help of extinguisher from Spreading foam and dry chemical powder in near by area and try to restrict the fire in limited area. 7.04 FIRE Explosion in F.O. / L.D.O. tanks:

    Location-FO Tanks, FO pump House, LDO tanks, dirty oil tanks: The Shift charge Engineer Control Room-I, II & Lignite Control Room after receiving the information about explosion / fire in the FO / HSD tanks area will immediately rush up to the site after alarming the fire fighting staff

  • 29

    available on duty. The Shift charge Engineer Lignite Control Room being nearer to the tank Area, will direct all available staff to reach the site for controlling the situation effectively. To suppress the fire in FO / LO tanks mechanical foam protection system is available. Ensure that hydrant pumps has been started for better pressure. Open the gate valve of foam line and water line of that particular tank. In additions to above medium velocity water spray nozzles have been provided for FO tank. LDO tanks and dirty oil tanks Hydrant valves and water monitors have been provided around the dyke wall of tanks. Water may be sprayed on tank surface though hydrant valves and water monitors to keep it cool to avoid bulzing out of tank walls. Shift charge Engineer Control Room-I & II will inform all concerning members of emergency team mentioned hereunder.

    7.04.2 Explosion in tank area may cause casualties and effect large area of the plant. Some exploded parts, may hit some working persons in side the plant. So, according to the situation, arrangements have to be made for ambulance / Jeeps for transportation of the victims to the hospital or dispensary. In charge of dispensary / hospital shall also be intimated on telephone for arranging essential medical / First. Aid in due course.

    For extinguishing the fire the foam type fire extinguisher or foam is required in this area in a large quantity. Keeping in view the alarming situation the concerning without loss of time wing should be informed immediately without loss of time by Switching On the siren from Control Room. The foam available in Zerricans should be mixed in water tanks of Fire tender and this mixture should be sprayed on fire. One no. fire tender filled with foam permanently shall be used.

    7.04.3 Details of Drill: 1. Cordon off the area keep un-authorized persons away. 2. Keep all approach passage clear. 3. Use the appropriate personnel protective equipments. 4. Restrict the fire in limited area. 5. Count all personnel and ensure that everybody is safe.

    7.04.4 Properties of Light Diesel Oil: General Information: Description - Brown, Slightly viscous liquid Flash Point - 125o F Density - Less then 1 Auto ignition Temp. - 494o F Distillation temp. - 675o F 90% point Viscosity at 100o F - Min. 1.8 Kinematic, Centistokes - Max.5.8 Centane Number - 40 Hazard analysis - Toxicity- Moderate If may produce irreversible as well as reversible change in the human body. These changes are not of such severity as to threaten life or produce serious permanent physical impairment.

  • 30

    Fire Hazard: Moderate, when exposed to heat or flame. In case of fire blanketing or something effect is essential to put the fire out. The effect of keep-oxygen away from the Fuel and it can be obtained with carbon-di-oxide, dry chemical (essentially sodium bicarbonate), foam or a vaporizing liquid type of extinguishing agent. Water is most effective used as a fine spray or must. Explosion Hazard: Moderate, when exposed to heat or flame. Counter Measures: To fight fire foam, carbon-di-oxied, dry chemical powder, carbon tetrachloride and halon.

    7.05.1 Fire in coal storage / Conveyor Belts in CHP area: (i) Location: conveyor Belts, Bunker House, crusher Houses, Transfer points. (ii) Primary Crusher area.

    (iii) Coal stock.

    7.05.2 The following fire protection arrangements are available for conveyor belts, transfer points, Crusher Houses, Bunker House etc.

    i. Medium Velocity Water Spray System: Fire in conveyor belts will be detected through infrared

    detectors and alarm, annunciation will appear in Lignite Control Room as well as in Control Room I. Linear heat sensing cable will also detect fire of that area and send signal to stop the conveyor belt. Water may be started spraying on effect area by operating deluge valve of that area locally or by pushing push button in Lignite Control Room for operation of deluge valve of that area.

    ii. Hydrant valves and water monitors: Hydrant valves are available along the conveyor belts and in

    transfer points. Where conveyor belts are higher level (More than 15 meters) Water monitors have been provided to fight fire from ground.

    7.05.3 Operators / helpers / Mazdoors working in Lignite should be called for help. Help may be asked from security staff by informing at plant gate No. 1& 2 Help may be asked from operators / helpers / Mazdoors working in the other area, if situation warrants.

  • 31

    Section B Electrical - Hazards

    ELECTRICAL DISASTERS 7.07.1 Fire in switch Gear Area:

    Location: (1) 6.6KV Switch gear unit-I & II Switch gear in ESP, Ash Handling, D.M. plant, Compressor House, CW Pump house, Raw water pump house, clarifier, DC Room, FO pump house, Lignite Handling Control Room ,Primary Crusher & Crusher House etc. The shift charge Engineer Unit-I, II & Lignite control room will immediately isolate the faculty / Fire affected section from all source of supplies (i.e. from Grid, Unit-I, II and any other electrical supply from distribution line) for allowing the fire staff for extinguishing the fire without any risk and will immediately rush to the site on receipt of information of the fire in the 6.6KV switch gear area and will take action to extinguish the fire from extinguishers available at the site to prevent further spread over of the fire. In case the fire is beyond control, the information should be passed on to the control room for isolating the affected section by tripping the incoming supplies to that section. Fire fighting staff should also be directed by the shift charge Engineer to reach to the site without loss of time for commencing the protective measures as well as extinguishing the fire and simultaneously information to the following emergency teams should be passed to reach the site in case their services are required:

    7.07.2

    S.No Incharge Phone No VPN

    1 Sh.A.K.Mathur Dy.CE (Elect. ) 9414065895 9982230914

    2713

    2 Sh.Ashok Parakh X.En(F/F) 9413349778. 22778

    3 Sh.P.Dhariwal X.En (Elect.) 9414049718 2735

    7.7.03 If the fire is spreading with a faster speed the shift charge Engineer will direct the additional staff of boiler, turbine area to assist for extinguishing the fire. Care should be taken that no fire fighting (operation) should be started unless the affected section is completely isolated from all source of supplies (i.e. HT, LT, DC supply)

    7.7.04 Details of Drill:- 1. Cordon off the area keep un-authorized persons away. 2. Keep all approach passage clear. 3. Isolate the adjoining area of affected place to avoid full damage of near by place. 4. Extinguish the fire with Co2 extinguishers and D. C. P. Extinguishers. Water may only be used if power is totally disconnected and on acute emergency.

    5 Provide insulated shoes and hand gloves for all staff engaged for extinguishing the fire. 6. Restrict the fire in a limited area. 7. Do not re-charge the faulty section unless clearance from maintenance staff is received.

  • 32

    7.7.05 Fire in Switch Yard Area: As soon as the information of fire in switchyard area is received, the first action to be initiated by shift Charge Engineer is to isolate the supply of the affected. The Assistant Engineer (220KVGSS) Barmer / Jaisalmer & Executive Engineer (LD), Heerapura, Jaipur should immediately be informed about the happening in the switch yard area and request them to isolate the particular section from the sending end / receiving end. The fire fighting staff available in the shift should be directed to reach the site immediately. The Junior Engineer (Elect.) in control room of concerning areas should also be directed to assists the fire fighting staff for extinguishing fire Operation must not be, undertaken unless the affected section is completely isolated from all source of supplies.

    7.5.01 Details of Drill: 1. Cordon off the area keep un-authorized persons away. 2. Keep all approach passage clear. 3. Isolate the adjoining area of affected place to avoid full damage of near by place. 4. Extinguish the fire with Co2 extinguishers, and D. C. P. Extinguishers. Water may only be used if power is totally disconnected and on acute emergency.

    6 Provide insulated shoes and hand gloves for all staff engaged for extinguishing the fire. 8. Restrict the fire in a limited area. 9. Do not re-charge the faulty section unless clearance from maintenance staff is received.

    7.06 FIRE IN CABLE GALLERIES: Most of the Galleries are provided with spray system. When ever, the fire breaks in cable gallery one has to envisage/ anticipate very alarming situation even if fire remains for a short period. So we must act initiate with DCP, Co2 fire extinguishers immediately, if the fire is small in nature.

    7.06.1 To Extinguishers fire Manually: If fire is small nature and fire staff can extinguish fire with the help of extinguishers, the Incharge of the shift must isolate the power supply of the cables so that of the cables becomes denergized. Now commence the efforts to extinguish the fire with full strength & force available by using:

    1. Portable fire extinguishers of Co2 and DCP type. 2. Water can also be used if all the cables of the area are deenergized. 3. In case of major fire, no person should enter in gallery and water spray may be started Simultaneously with above activities the shift charge Engineer must inform to the Executive Engineer (LD), shift Engineer of 220KV GSS, Barmer / Jaisalmer, S.E (Opr), X.En (Suppt.) for the incident in the cable gallery. Fire fighting staff available in the shift should be directed to reach the site immediately. All concern AEN/JEN and other staff of control room should be directed to assist the fire fighting staff for extinguishing the fire, caution should be taken that no water or conductive media be used to extinguish the fire if the cables are energized.

  • 33

    7.06.02 Details of Drill: 1. Cordon off the area keep un-authorized persons away. 2. Keep all approach passage clear. 3. Isolate all cables from feeding end, ensure that all cables are dead. 4. Fire staff must start operating extinguishers available in cable gallery. 5. Control the fire, not allow expanding, with the help of available staff, try to restrict the fire in limited area extinguish the fire initially at the beginning and within short time so that the intensity / expansion of fire remain under check. 6. Use fire extinguishers of Co2 and DCP to quench the fire. 7. Use Water / Foam only when it is ensured that none of the cable is energized and all the dead.

    8. Use DCP powder freely on the root of the fire for better results. 9. In case of major fire, no persons be allowed to enter in cable gallery and water spray may be started

    by opening valve of spray system.

    7.06.04 To Control Fire by using water spray system: In case fire is uncontrollable by extinguishers or it is not possible for fire staff to reach at fire location due to excessive heat or dense smoke, call all persons out of galleries and operate water spray system.

  • 34

    Section C Chemical - Hazards

    CHEMICAL DISASTER

    7.07.1 Introduction: The water taken from Indira Gandhi Canal for meeting out requirement of plant needs to be clarified / filtered / diminaralised for various uses in plant. To achieve required quality of water it is treated with various chemicals. Some of the chemicals mentioned below are hazardous if not handled properly, safely and carefully.

    S.NO. Name of Chemical

    Max. Qty available at a time

    Use and place of storage

    1. Liquid chlorine

    13 Tonners Procured in 900 KG Capacity (Tonner) cylinder used for water purification at clearfiler.

    2. Acid & Alkali (Max. Qty NaOH-150 MT) 2x29 = 58M3 Na OH Two storage tank. 2x34 = 68M3 HCL Two storage tank.

    Hydrochloric Acid (30%) and caustic soda (47.5%) required for regeneration of DM plant exchange units and stored in M.S.R.L. storage tanks.

    7.08 EMERGENCIES AND HAZARDS;

    7.08.1 ACID LEAKGE FROM HYDRO CHLORIC ACID STORAGE TANKS: Location DM Plant Stage

    7.08.2 MEREGENCY TEAM TO HANDLE THE DISASTER: S.No Incharge Phone No VPN

    1 Sh.A.K.Mathur Dy.CE (Opr.& Elect. ) 9414065895 9982230914

    2713

    2 Sh.Anant Amitabh, Sr.Chemist 9413349784 22784

  • 35

    7.08.3 DETAILS OF DRILL FOR Na OH AND HCL:

    1. Block all the entries to the affected area. No, un-authorized person should be permitted in the affected area. 2. Cover the acid spill with lime for neutralization. 3. Stop unloading of hydro chloric acid in storage tank immediately, if storage tank is leaking. 4. Appropriate action should be taken on priority to evacuate the leaking tank as per following producers.

    a. By making arrangements to transfer the acid from leaking storage tank to storage take in the vicinity.

    b. By arranging road tanker and transferring acid from leaking storage tank. c. By transferring acid into measuring tanks in the plant as available.

    5. Use the appropriate personal protective equipment as given below: a. Face shield b. Apron PVC / rubber c. Rubber hand gloves d. Gas mask e. Safety Goggles. f. Self contained breathing apparatus.

    7.08.4 First Aid 1. In case of body contract use plenty of water for washing the affected part. Get Medical treatment at the earliest. 2. Do not neutralized spilled acid on body with chemical without supervision of a medical officer. 3. In case some one swallow the acid by accident / mistake rush medical aid immediately. 4. During unconscious state nothing should be allowed orally or by mouth.

    7.09 CHLORINE LEAKAGE Location: Clarifier and forebay.

    CWPH 7.09.01 Emergency team to handle the disaster:

    S.No Incharge Phone No VPN 1 Sh.A.K.Mathur Dy.CE (Opr.& Elect.) 9414065895

    9982230914 2713

    2 Sh.Anant Amitabh, Sr.Chemist 9413349784 22784

    Water treatment plant operators / helpers available at the time of disaster may also be called. 7.09.02 DETECTION OF CHLORINE LEAKEGE: chlorine has characteristic of pungent smell, this gas can be

    detected even at very low concentration of 3 PPM in air. Leakage point can be further identified with the help of Ammonia Torch. The chlorine leakage detector has been installed at Stage-I & II clarifiers plant chlorination room. The monitor of these detectors are installed at the PANEL ROOM of the respective clarifiers.

    The operator on duty must inspect the shift charge Engineer control room unit-I and assistant Engineer / Junior Engineer on duty and also take the following action:

    a.The plant operator of the concerned clarifier will acknowledge / reset the chlorine leakage alarm and

  • 36

    inform the shift charge Engineer along with Sr. chemist / Junior chemist. b.The shift charge Engineer along with Sr. chemist / Junior chemist will inform the emergency team as above for further needful action for prevention of leakage.

    7.09.03 DETAILS OF DRILL: As soon as chlorine is observed following action are to be taken:-

    1. Cordon off the area. 2. Evacuated all personnel and the plant operator and they should stand / stand in area opposite to wing

    direction. 3. Only experienced and trained personnel should attend the leakage job. 4. Use SELF CONTAINED BREATHING apparatus or chlorine gas mask for attending the leakage. 5. Trace the chlorine leakage by using ammonia torch. 6. In case of leakage from the chlorine handling equipment i.e. system connected to the tonner, the tonner

    outlet valves must be closed immediately. 7. Before attending chlorine leakage In the chlorination room please ensure, that environment is Chlorine

    Free for attending leakage on system of chlorine handling. 8. In case of leakage form the tonner or valve, the following action are recommended:

    a. Emergency chlorine handling Kit must be used for handling the leakage. b. Use proper personnel protective equipment along with self contained breathing apparatus the

    leakage. c. Please ensure the availability of supervision by a senior officer while attending the leakage. d. Shift vehicle must be ready for any emergency.

    9. No water should be sprayed or directed towards the leaking point as hydrochloric acid formed with water and chlorine can aggravate the corrosion of surface.

    10. Wherever, a leakage is detected, however minor, it may be, immediately step should be taken to stop the leakage as due to corrosive nature of chlorine gas the leakage will increase abruptly.

    11. Avoid deep breathing in chlorine contaminated area or atmosphere.

  • 37

    Section D Natural - Hazard

    NATURAL DISASTERS 7.10.1 INTRODUCTION:

    Disaster due to earth quake, flood, storms may cause heavy devastation of man and material and may not be localized at one place. Therefore, to handle the severe situation, the in charge control Room-I after assessing the quantum will take action as under if situation warrants.

    i. He will alarm fire staff by switching on siren from Control Room-I & PA systems. ii. Intimation will be given at plant main gate to instruct security staff / Drivers residing in barracks to reach

    at location immediately. iii. If the situation is severe the following teams will also be informed immediately.

    A Administration Team: The Dy. Chief Engineer (Opr.) will be Incharge of this team. He is responsible for arranging food, drinking water, Medicine for victims hospitalized in Barmer Hospital till their recovery or as per instruction of Chief Engineer, GLPL.

    S.No Incharge Phone No: VPN 1 Sh.A.K.Mathur Dy.CE (Opr.) 9414065895

    9982230914 2713

    2 Sh. Ashok Parakh, XEn. (F/F) 9413349778 22778

    B Transportation Team:

    S.No Incharge Phone No: VPN 1 Sh.A.K.Mathur Dy.CE (Opr. & Elect.) 9414065895

    9982230914 2713

    2 Sh.O.P.Agrawal X.En(Opr-Suppt-II) 9413349727 22727 3 Sh.U.C.Chobisa A.En(F /F) 9413349779 22779

    C Information Team: Dy. CE (Opr.) will be the incharge of this team. He will be responsible to collect

    information of victims / casualties and submit to press, media, District authorities, and inform to relatives of victims, arrange transport to them for brining to hospital to them for bringing to hospital and leaving back to their homes

    (Team Incharge) Sh. A.K. Mathur, Dy. Chief Engineer (Opr.& Elect.)

    (Team Members) Sh. Ashok Parakh, Executive Engineer (Opr-Suppt-I) Sh. O.P.Agrawal, Executive Engineer (Opr-Suppt-II ) V For taking help from external sources, the medical / Police / Dist. Authorities should be contacted and informed about the incident immediately. The contact no. of these authorities are as under:-

    (i) District Collector :- 02982-220005/220006 (ii) SP :- 02982-220003/4 (iii) CMHO :- 02982-230462/220204.

  • 38

    Chapter 8

    Hazards and Medical Management

    Chlorine

    Hydro Chloric Acid

    Caustic Soda

    SULPHURIC ACID Hazards and Medical Management

    CHLORINE

    TOXICITY Chlorine is corrosive. It reacts with body moisture to form corrosive acids. Chlorine gas is primarily a respiratory irritant. Concentration above 3 to 5 ppm by volume in air is readily detectable by a normal person. Inhalation of chlorine may cause respiratory injury.

    ACUTE EFFECT The first symptom of exposure to chlorine is irritation to the mucous membranes of eyes, nose and throat which increase to smarting and burning rain. Irritations spread to the chest. A reflex cough develop which may be intense and often associated with pain behind the breastbone. The cough may lead to vomiting. If the duration of exposure or the concentration of chlorine is excessive, it will cause restlessness, throat irritation, sneezing and copious salvation. In extreme cases, lung tissues may be attected resulting in pulmonary edema, full of blood pressure.

    EFFECT OF CHLORINE AT VARIOUS CONCENTRATIONS

    Chlorine concentration in air (PPM)

    Effects

    0.2 0.5 No toxious long term effect. 0.5 Slight odour. 1.0 3.0 Definite odour, irritation to eyes and nose. 6.0 Irritation of the throat. 30.0 Intense cough fits. 40.0 60.0 Exposure without effective respirator for 30 to 60 Minutes or

    more may cause serious damage. 100 May cause lethal damage. 10000 Danger to life even after few deep inhalations.

    CHROINIA EFFECT: Prolonged exposure to concentration more then 5 ppm may result into bronchial problems. Due to long exposure to chlorine, affected persons may get Acne.

  • 39

    FIRST AID AND MEDICAL MANAGEMENT

    SYMPTOMS Skin Contact

    1. Burning. 2. Inflammation 3. Burns may be very painful, painful blisters. 4. Profound damage to tissues. 5. State of shock. Cold calmy skin Sweating over the forehead. Cold Sweet- Pale complexion. Rapid and week pulse. Cold hands and feet. Tendency to faint.

    Eye Contact 1. Watering of eyes. 2. Burning sensation in eyelid and eyes. 3. Inflammation of eyes (Conjunctivitis). 4. Ulcepation of the tissues. 5. Opaqueness of the cornea. 6. Loss of light. Inhalation 1. Irritation of mucous, membranes (mouth, eyes, nose and throat). 2. Watering of eyes, Nasal discharge. 3. Sneezing and coughing. 4. Difficulties in breathing and rapid breathing. 5. Headache. 6. Bluish Coloration of face and lips. 7. Salivastion. 8. Nausea and giddiness. 9. Muscular weakness. 10. Ulceration of mucous membrane (nose). 11. Acute pulmonary edema. 12. Chemical Bronchitis. 13. Secondary chemical pneumonia. 14. Death.

  • 40

    Skin Contact

    1. Remove the victims from the effected area immediately. 2. Take him to the nearest shower as early as possible. 3. Remove contaminated cloths. 4. Wash skin with large amounts of normal running water. 5. Dust the effect area with powdered sodium-bi-carbonate wash the affected area again with normal running

    water. 6. Dry the skin very gently using a clean and soft towel. 7. Do not apply oil or oily ointment without doctors advice. 8. In case of burns, apply a dry sterile dressing. 9. Keep the victims warm using a blanket. 10. Immediately take him to the nearest hospital.

    Eye Contact 1. Immediately remove the victim from the affected area. 2. Take him to the nearest eye wash or shower. 3. Flush eyes immediately with normal water for at least 15 minutes or longer, keeping his eyelids open. 4. If the pain remains, repeat washing the eye for 15 minutes or longer. 5. Do not try to neutralize with chemical. 6. Do not use any oil or oily ointment without docotors advice.

    Inhalation.

    If the victim is conscious and inhalation is mild. 1. Remove the victim from the affected area and take him to well ventilated area. 2. Loosen the clothes and remove shoes. 3. Keep him warm using a blanket. 4. Place the patient on his back with head and back elevated. 5. Rest is a must. 6. If the victim cought a great deal, make him inhale a gauze pad soaked with a little ethyl or a few drop of

    ether. 7. Cough surups like BINCTUS CODEIEN etc. and common throat lozenges such a VOX, VICKS, HALLS etc.

    can be given for smoothening irritation. 8. Milk, butter milk, lime, juice, fresh water may be given. If the victim is un-conscious but breathing has not ceased- 1. Place the patient in a comfortable position with head and trunk elevated to 45O position. 2. Remove artificial dentures. 3. Keeps the patient warm using a blanket. 4. Administer medical Oxygen under low pressure. 5. Do not give him anything to drink. If breathing has ceased. 1. Immediately remove him from the affected area.

  • 41

    2. Immediately:

    Loosen his cloth. Lay his down on his stomach. Begin artificial respiration.

    3. Immediately Administer medical Oxygen under low pressure, 4. Call a physician immediately. 5. As the victim begins to breathe un-aided or to move lay him down with his body raised and continuous to

    administer oxygen. 6. The physician will keep the victim under medical supervision for microbial infection may be caused. Therapy for specific physiological disturbance- for the guidance and attention of medical profession:-

    Pulmonary Edema 1 Administer 60 to 100% _ Oxygen at 6 ltr. / min. 2. Intermittent positive pressure breathing apparatus set to deliver positive pressure 5-15 cm. of water in the

    respiratory cycle, is valuable in reducing the formation of edema. 3. Steroid therapy, given early is effective is preventing or alleviating pulmonary edema. There is chlorine

    intoxication. 4. The use of diuretics and antibiotics should be considered to reduce adoma and protection against

    secondary pulmonary infection.

    BRONCHOSPASM 1. There is no known antidote for chlorine exposure. The exposure is associated with acute symptomatology requiring supporting therapy only. Early treatment is the most effective. 2. Broncho- dilators nebulizer into the intermittent positive pressure gas stream are often beneficial. 3. Two effective drugs are: ISSOPROTERENOL HYDROCHLORIDE CYDO PENTEMIME HYDROCHLORIDE The comm. Only employed single treatment dosage for each drug is 0.3 cc This may be altered according to clinical needs.

    1. Positive pressure treatment tends to suppress the secretion of mucous. 2. Nebulized detergent assist in the thinering of musous. There is no chromic affected of chlorine gas inhalation

    unless a person is exposed continuously for a long period.

    CHLORINE: Properties: Greenish yellow gas at normal ambient temperature with a pungent irritating smell- B.P. 34.50C Vapour density 2.49 T.L.V. 1 ppm in air (3mg / NM3 air)

  • 42

    HAZARDS 1. TOXICITY: Causes immediate irritation of throat eyes, preparatory tract and lungs. Dangerous even in short

    exposure. A brief exposure to a concentration of 1000 ppm may prove to be fatal. Reaction with water produces highly toxic and corrosive hydrogen chloride fumes.

    2. Fire: Non-flammable by itself but can react vigorously with other chemical like turpentine, ether ammonia,

    hydrogen, hydrocarbons to cause fire.

    3. Explosion: Vigorous reaction with reducing agents can cause explosion. PRECAUTIONS IN STORAGE & HANDLINHG 1. Do not expose containers to direct sunlight, store in a shaded area. 2. Do not pour water on breaking containers or valve. 3. Use PVC protection suit and gloves, specific respirator for chlorine service 4. In Case of Leakage use emergency kit for stopping the leak. 5. Avoid skin contact.

    FIRST AID: i. In case of skin contacts wash thoroughly with excess of water. ii. In case of inhalation, move person to well ventilated area and obtain medical assistance at once. iii. Use cough syrup and throat lozenge to reduce irritation.

    HYDROCHLORIC ACID PROPERTIES: Physical Stage : Yellowish colored liquid. Concentration : 30% Nature : Fuming, liquid, causes irritation to nose, if inhaled.

    HAZARDS: 1. Toxicity: Local toxicity can injury on body contact. Toxic fumes which may cause irritation and injury to

    the respiratory track.

    2. Fire: Can causes for hazards by vigorous exothermic chemical reactions. Powerful oxidizing can cause fire on contact with combustibles.

    SAFETY PRECUTIONS.

    i. Use rubber gloves, shoes and PVC suit while working in acid area.

    ii. While working in fumes area, use proper breathing appratus. iv. Avoid body contact.

    v. Do not spray water on acid leaks or spills.

    FIRST AID: i. In case of body contact use plenty of water for washing. Get medical at the earliest in case of severe

    burns. ii. Do not try neutral the acid spill on body with chemicals. iii. Do not anything on burns without proper medical assistance.

  • 43

    CAUSTIC SODA SOLUTION. PROPERTIES: Physical Stage : Colorless, sticky, liquid. Concentration : 2 mg / NM3 air. Nature : Reacts with water and system steam generating excessive heat corrosive action on skin.

    HAZARDS: 1. Toxicity: Reacts corrosively with body tissues, causing irritation, scaring and ulceration. Inhalation of mist

    can damage the respiratory track and lungs. 2. Fire: Non-flammable. 3. Corrosion: Highly corrosive.

    SAFETY PRECAUTIONS. i. Use rubber gloves, shoes and PVC suit while working in caustic area.

    b. Avoid body contact with liquid and mist.

    FIRST AID: 1. In case of body contact use plenty of water for washing. 2. Use plenty of warm water for washing eyes. 3. Do not to neutralize caustic spill on body with chemical. 4. Get medical help at the earliest.

  • 44

    vkikr fLFkfr ,oa izkFkfed mipkj-

    fdlh nq?kZVuk ls ihfMr O;fDr dks rqjar ihMk ls cpkus ds fy;s mipkj gsrq nh tkus okyh izkFkfed lgk;rk dks izkFkfed mipkj dgrs gSA bldk mn~ns; thou dks cpkuk rFkk fpfdRld dh lsok, le;

    ij miyC/k u gksus ij fLFkfr dks fcxMus ls jksduk gSA blfy;s t:jh gS fd vki vius IykaV es QLVZ ,M ckDl

    dh Bhd izdkj ls ns[kHkky j[ks vkSj izkFkfed lgk;rk ls lacaf/kr nokbZ;ks dh vkSj muds miHkksx dh tkudkjh

    j[ksaAfQj IykaV es fuEufyf[kr LFkkuks ij QLVZ ,M ckDl mi;ksx gsrq miyC/k gS%&

    1- eq[; fu;a=.k d{k bdkbZ izFke o f}rh; A 2- dksy gS.Mfyax fu;a=.k d{k A 3- ,sk gS.Mfyax IykaVA 4- Mh-,e IykaV A 5- DysjhQk;j IykaVA 6- dSehdy yScA 7- oSxu fViyj A 8- eSdsfudy eSUVhuSUl o`rA 9- bysDVhdy o`rA 10- Qk;j QkbZfVax foax 11- lqj{kk dk;kZy; xsV l&2

    ihfMr O;fDr dks lHkkyus okys O;fDr }kjk ;ksX; ckrs%&

    1- tks Hkh dk;Zokgh djuh gS]kh/kzrk ls djsaA 2- MkDVj dks kh/kz cqyk;saA 3- izHkkfor O;fDr dks [kqyh gok es ys tkos ;k goknkj dejs es fyVkosA 4- ;fn ihfMr O;fDr B.M eglwl dj jgk gks rks mls xehZ es igqpk;s kkUr j[ksA 5- ihfMr O;fDr dks FkksMk Wpk j[k ihB ds cy ij lh/kk fyVkosA 6- jksxh okgu o LVspj dk izcaU/k djsaA 7- izkFkfed lgk;rk ds fy;s lHkh miyC/k lk/kuks dks dke es ysA

    ,slk u djsa%&

    1- xSl yhdst okys vlqjf{kr LFkku ij u tkosaA 2- Hk;Hkhr u gks A 3- xgjh lkWl u ysosA 4- [kkWlh dks jksdus dk iz;kl djsaA

  • 45

    vkW[ks ihfMr gksus ij mipkj%&

    vkW[kks es ,flM lkY;wku ds NhVs iM tkus ij vFkok vU; ckgjh ds d.k fxj tkus ij ihMk gksus yx

    tkrh gSA blds fy;s fuEufyf[kr mipkj gksus pkfg,A

    1- vkW[kks dks vf/kd ek+++=k es ikuh ls /kks;sA 2- vkbZ yksku dh 2&3 cwans vkW[k es MkysA 3- fQj vkW[kks dks ikuh ls /kksosaA 4- LoPN xkWt iSM ls vkW[k dks

  • 46

    4- gkFkks vkSj iSjks dks ij dh rjQ MkysaA 5- kh/kzrk ls mipkj ds fy;s MkDVj ds ikl ;k fMLisUljh igqpkWus dk izca/k djsaA

    ,slk djsa ihfMr O;fDr }kjk

    1- yhd gksrh xSl dh fnkk tkusaA 2- izHkkfor {ks= ls nwj gks tkos A 3- kh/kz LoPN okrkoj.k es tkosaA 4- yhd gksrh xSl dh fnkk es vyx gV tkus ds fy;s vU; yksxks dks Hkh crk;sA 5- eqWg caUn j[ks vkSj xhyk diMk iSM vFkok :eky dks ukd vkSj eqWg ij yxk;saA 6- ikuh ls eqga vk[ksa /kks Mkys vkSj diM+s cnysaA 7- rqjUr izkFkfed mipkj ysaA

    izkFkfed lgk;rk dk {ks=%&

    1- jksx dk irk djuk] ftlls cqf)erkiw.kZ vkSj dqky mipkj fd;k tk ldsaA 2- ;g fufpr djuk fd fdl lhek rd mipkj fd;k tk;saA 3- nq?kZVuk ls ihfMr O;fDr dks ?kj] vLirky];k vU; lqjf{kr txg ij igqpkukA

    pksV yxus vFkok ?kko gksus ij%&

    fdlh rst ;k uqdhyh oLrq ekhu ds dyiqtsZ] dkWp ds VqdMs]uqdhys gfFk;kj ds yxus ;k dqpys

    tkus ls pksV yx tkrh gS] vkSj vDlj ?kko ;k jDr L=ko gksrk gSA ,slh gkyr es rqjUr izkFkfed

    mipkj djuk pkfg,A mipkj es nsjh djus ls ?kko es bIQsDku gksus dh laHkkouk jgrh gS] ftlls

    pksV ;k ?kko c< tkrk gS] vkSj mles lwtu ;k lMus ds vklkj jgrs gSA

    izkFkfed mipkj-

    1- jksxh ds cSBs vFkok ysVh voLFkk es jDr L=ko de gksrk gSA 2- [kwu cgrs gq, vax dks FkksMk ij jf[k;sA 3- ?kko ds ij ds oL= dks mrkj dj j[k nsosA 4- ?kko es ckgjh oLrq fn[kkbZ iMus ij lkQ xkWt ls ljyrk iwoZd gVk nssaA 5- ejge ls ;qDr xkWt dkWVu iSM yxk dj iV~Vh ckW/k nhft,A

    tyus ij mipkj%&

    1- izHkkfor vax dks rqjUr ,ejtSUlh kkoj ;k uy ds uhps ys tkdj vPNh rjg ls ikuh ls /kks;sA 2- vxj diMs ty x;s gS] rks lko/kkuh iwoZd vius kjhj ls vyx dj nsA 3- tys gq, fgLls ij LoPN dhVk.kq jfgr fdk gqvk xkWt ouZ vkbUVeSUV yxk dj gYdh iV~Bh ckW/k nhft,A 4- ?kk;y O;fDr dks vxj B.M yx jgh gks rks mls xekZgV igqpkus ds fy;s mfpr mik; djsaA 5- kh/kzrk ls mipkj ds fy;s MkDVj ds ikl ;k fmLisUljh igqpkWus dk izca/k djsaA

  • 47

    PERSONAL PROTECTION EQUIPMENT. 1. Introduction. In industry when a potential hazard gets out of hand and may affect the safety of people who are in its ranges, suitable protective devices are required to be used. The personal protection equipments do not eliminate a hazard however these devices are designed to interpose an effective barrier between a person and harmful objects sustance of radiation. When we deal with chlorine and ammonia one may expose to hazards which can be harmful to his respirating tract and other body parts.

    2. Requirement of P.P.E:- Suitably of PPE can be listed as under:-

    1. Adequate protection against the hazards to which the works will be exposed. 2. Maximum comfort and minimum capability with protective efficiency 3. No restriction in essential.

    3. TYPE OF PROTECTIVE EQUIPMENTS:- Personal protective equipments are classified as under:-

    Respiratory protective equipments. This appliances can further be classified in two classes:-

    1- Air Purifying type. 2- Supplied Air Type.

    1- Air Purifying type. In this type of appliance according to the degree of respiratory hazard, that is, the concentrations of the toxic gas present one may opt for either CARTRIDGE TYPE GAS MASK or CANISTER TYPE GAS MASK. The cartridge or canister are filled with appropriate chemicals to be used in a particular gas. When the chemical exhausts Cartridge/Canister should be replaced with a fresh one.

    2- Supplied Air type. In this type these equipments are covered which are capable of providing respiratory protection in any concentration of contaminant gas as these equipments have their own source of breathable air hence isolate the user from the contaminated atmosphere. To accomplish it, either the air source (a compressed air cylinder) remain with the user in that case it is known as SELF CONTAINED BREATHING APPRATUSor the breathable air is supplied from plants service air-line/ big air-cylinder/manual or electrical air blower through a tube and mask.

    NON RESPIRATORY PROTECTIVE EQUIPMENTS. In this class these equipments are covered whether provide protection on the body as a whole or in part. The details are given below:-

    1- SAFETY HELMETS: - Safety helmets are used for protection of head against fall of corrosive / toxic liquids and hard objects. These are made from thermoplastic material.

    2- SAFETY GOGLES:- Safety goggles are used for protection of eyes against splash of corrosive/ toxic liquids. These are made having one piece rubber / plastic molded frame and toughened visor.

    3- FACE SHIELD:- Face shield protects the face of the user against splash of corrosive /toxic liquids. It is

    available in 6, 9 and 12 with head band.

  • 48

    4- PVC APRON:- PVC apron/ suit protect the users body against the splash of corrosive/ toxic liquids. These are also available in rubber or leather. A coating of fabric or reinforcement is also available with synthetic rubber.

    5- HAND GLOVES & GUM BOOTS:-Hand gloves and gum boots protect the hand & feet of the user against corrosive /toxic liquids. Gloves are available in leather to handle sharp objects.

    6- FIRE ALLUMINISED SUIT:- This suit is made of alumished asbestos, its function is to enable a man to go near a fire and work and to enter into flame for short duration of time. Its temperature range is 1300oF for 5 to10 minutes and 1000oF for 20 minutes.

  • 49