36
Whole Number 195 Geothermal Power Generation

Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Embed Size (px)

Citation preview

Page 1: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Whole Number 195

Geothermal Power Generation

Page 2: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

FUJI ELECTRIC’S GEOTHERMAL POWER PLANTS

It is known that geothermal power plants emit no oxides of nitrogen or sulfur and the emission of carbon dioxide in question because of the earth warming is one-tenth as much as oil-burning power plants. In addition, there is no fear of geothermal energy exhaustion.

Fuji Electric has supplied about 1,700MW of geothermal power plants ranging from large-scale utility use to small and medium industrial use and is ready to propose an optimum power plant meeting the needs.

Page 3: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Cover Photo: Geothermal energy is receiving

widespread attention as a source ofclean and renewable energy. Geo-thermal power plants are being con-structed throughout the world inthose countries which have geother-mal resources.

Fuji Electric has supplied geo-thermal power units capable of pro-ducing a cumulative output of1,700MW, ranging from small ca-pacity units such as for a hotel tolarge-capacity 110MW units, de-pending on customer needs. Theunits supplied by Fuji Electric arefavorably regarded for their highreliability.

The photograph on the frontcover shows a complete view of theWayang Windu Geothermal PowerPlant in Indonesia and its 110MWgeothermal steam turbine. The tur-bine is the world’s largest single-casing-type geothermal turbine.

Head Office : No.11-2, Osaki 1-chome, Shinagawa-ku, Tokyo 141-0032, Japan

CONTENTS

Fuji’s Activities in Geothermal Power Generation 98

Wayang Windu Geothermal Power Plant 102

Berlín Geothermal Power Plant 108

Hachijo-jima Geothermal Power Plant 113

Geothermal Steam Turbines for Various Purposes 120

Recent Technology of Geothermal Steam Turbines 124

Geothermal Power Generation

Page 4: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW98

Shigeto Yamada

Fuji’s Activities in Geothermal PowerGeneration

1. Introduction

Geothermal power generation was first experi-enced in Italy in 1904 as a water-binary cycle systemthat used a reciprocating steam engine, very differentfrom the flash cycle systems of today. In 1923, also inItaly, a system which introduces geothermal steamdirectly into a steam turbine was tested for the firsttime.

Since then, this system has become the majormeans of geothermal power generation. Many geother-mal power plants which use flash cycles (naturalsteam, single flash or double flash) have been built incountries where geothermal resources are abundantsuch as New Zealand, the Philippines, the USA andJapan. According to presentations at the WorldGeothermal Congress of May, 2000 in Beppu andMorioka, Japan, the total capacity of geothermal powerplants in the world is about 8,000MW at present. Ofthat number, Fuji Electric has supplied equipmentthat produces about 1,700MW in total.

2. Current Status

Features of geothermal power generation, that it isclean and recyclable, are widely known. Since there isno combustion of fossil fuels which emit carbon dioxideand nitrous or sulphurous oxides, geothermal powergeneration contributes to the conservation of theenvironment. Geothermal steam was originally rainwater which penetrated deep underground and thenwas heated by magma. After being separated fromsteam, hot water is also returned from wells to theearth. This completes a natural recycling system.Although geothermal energy cannot be transportedlike a fossil fuel, it is actively being developed incountries where geothermal resources are abundant.Figure 1 shows geothermal zones throughout the worldand the capacity of geothermal unit installed by FujiElectric. Table 1 shows the capacity of countries inboth 1995 and 2000, and a forecast for 2005. As youcan see from this table, the development of geothermalpower generation is particularly active in those coun-tries which have no petroleum resources such as the

Philippines, New Zealand and Italy. In the USA whichhas the largest installation of geothermal power plantsin the world, and at the same time is a major oilproducing country, geothermal power generation isrecognized as an economical and environmentallybenign means of power generation, and geothermalresources are abundantly distributed in the westernstates, especially in California. Although Indonesia isblessed with fossil fuels such as oil and natural gas, itis aggressive in the development of geothermal re-sources. All geothermal energy development plans inIndonesia have been suspended ever since the econom-ical crisis, however, those plans will be revived soon. Ifpresent development plans are realized, Indonesia willbecome one of the largest geothermal power generationcountries in the world as shown in Table 1.

In the Philippines and Indonesia, geothermal pow-er plants used to be built by national utilities such asNPC (the Philippines) and PLN (Indonesia). However,it is becoming more popular to build a plant underBOT (build, operate and transfer) type contract wherea foreign developer and the national utility sign anECA (energy conversion agreement) or PPA (powerpurchase agreement). This system helps accelerate theconstruction of power plants by attracting foreigndevelopers, particularly American developers who havevast domestic experiences. In this system, either agovernmental body such as PNOC-EDC (the Philip-pines) or PERTAMINA (Indonesia) develops and main-tain geothermal fields to supply steam and developersbuild power plants, or a private developer does every-thing from drilling wells and constructing pipelines tobuilding the power plant. In either case, the maintendency is for the developer to enter into an EPC(engineering, procurement and construction) type con-tract with a supplier, where the supplier is solelyresponsible for completion of the power plant. In orderto receive financing from monetary institutions, it isessential to have a single responsible entity as themain contractor rather than having multiple contrac-tors.

Fuji Electric, a leading manufacturer of geother-mal steam turbines, recognizing the needs of geother-mal developers, has become increasingly focussed

Page 5: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Fuji’s Activities in Geothermal Power Generation 99

Fig.1 Worldwide geothermal zones and power plants supplied by Fuji Electric

Japan4 MW

USA666 MW

El Salvador96 MW

Iceland36 MW

Philippines428 MW

New Zealand55 MW

China3 MW

Indonesia385 MW

Total 1,673MW

toward total plant engineering. In the recent construc-tion of Malitbog Geothermal Project in Leyte, Philip-pines, Fuji Electric (along with a trading company asthe main contractor) worked on the project to provide afull turnkey solution, including construction, civilengineering work, manufacturing, procurement, instal-lation and commissioning of the plant which consists ofthree 77.5MW units. In this case, the only datasupplied to Fuji Electric was given were the steamconditions at the plant boundary, the site meteorology,and the customer’s required net plant output. Fujistarted the engineering work by determining thedesign wet bulb temperature, which has a largeinfluence on the plant economy and performance.Then, design conditions were determined for the mainequipment and each sub-system. The ultimate goal ofplant engineering is to realize a geothermal powerplant which is reliable, highly efficient, economical,and at the same time has a minimum influence on theenvironment.

More recently in 1999, Fuji Electric providedequipment to the Wayang Windu Geothermal PowerPlant located in West Java, Indonesia also under anEPC contract. The power plant is equipped with a110MW geothermal steam turbine, the world’s largestsingle casing turbine for geothermal service.

Another recent example, in contrast to WayangWindu in terms of its size, is the Hachijo-jimaGeothermal Power Plant also inaugurated in 1999.The power plant, whose output is 3.3MW replaceddistributed diesel power plants in Hachijo-jima islandwhich is a remote volcanic island in eastern Japan

CountriesYear 1995

* USA 2,817 2,228 2,376

* Philippines 1,227 1,909 2,637

Mexico 753 755 1,080

Italy 632 785 946

* Japan 414 547 567

* Indonesia 310 589 1,987

* New Zealand 286 437 437

* El Salvador 105 161 200

Nicaragua 70 70 145

Costa Rica 55 142 161

* Iceland 50 170 170

Kenya 45 45 173

* China 29 29 NA

Turkey 20 20 250

Russia 11 23 125

Portugal 5 16 45

France 4 4 20

Argentina 0.7 0 NA

Thailand 0.3 0.3 0.3

Australia 0.2 0.2 NA

Ethiopia 0 9 9

Guatemala 0 33 33

Total 6,833 7,974 11,398

Year 2000 Year 2005(forecast)

Capacity (MW)

Note : * shows the countries where Fuji Electric supplied geothermal power plants.

Table 1 Worldwide capacity of geothermal power plants(Source : IGA NEWS, July to September 2000)

Page 6: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW100

about 300km from Tokyo.

3. Technological Aspects

3.1 Large capacity geothermal steam turbinesIn the latter half of the 1980’s, several large scale

110 to 150MW capacity units consisting of two 55MWclass turbines coupled in tandem, were constructed inthe Geysers area of northern California to lower thecost per kWh of generating power. These large unitscan certainly help reduce the plant construction costper kilowatt, but they run the risk of causing ashortage of steam to generate the rated capacity. Infact, the last 150MW unit was manufactured anddelivered in 1989 but never installed because of theshortage of resources. A large unit is especiallyunsuited for an IPP (independent power producer),which sometimes rely on only a single unit for revenue,use of a large capacity unit is inappropriate because ofpossible shut downs of the total power plant due toscheduled maintenance or trouble. Therefore, if thedeveloper has enough steam to support 150MW, it iswiser to install three 50MW units or two 75MW unitsto increase the flexibility of plant operation.

3.2 Packaged type geothermal steam turbinesOn the other hand, there are increasing demands

to shorten the period of site work. Responding to thisdemand, Fuji Electric has standardized so-called skidmounted type turbines and has delivered several ofthem. To minimize the onsite installation work, steamturbines and generators in the 20 to 40MW range arecompletely pre-assembled on separate beds at FujiElectric’s Kawasaki Factory prior to shipment. Forsmaller units, it is possible to assemble both theturbine and the generator on one common bed. Howev-er a skid mounted configuration is impossible forlarger units such as the ones manufactured for thePhilippines and Indonesia due to transportation re-strictions, Fuji’s design aims to reduce the number ofassembled blocks per shipment in order to shorten theinstallation period. Since most geothermal sites are inremote mountainous areas, and the majority of avail-able labor cannot always be expected to be wellexperienced, reducing the number of blocks in theshipment becomes even more important from the pointof view of both the site schedule management and thepreservation of reliability.

3.3 Titanium alloy last-stage bladesGeothermal steam contains hydrogen sulphide,

and in such an environment, the internal stress ofturbine parts such as blades and rotor should bewithin the appropriate limit value for each material toavoid cracking due to stress and corrosion. Themaximum centrifugal force is exerted at the base of thelow pressure blade in the last stage. For this reasonthe length of the stainless steel blade of the last stage

is limited to 26 inches at 60Hz (nominal) or 30 inchesat 50Hz. However, since the enthalpy of geothermalsteam is low, the turbine exhaust loss cannot beignored as a portion of the heat drop across theturbine. By using longer last-stage blades, costs can belowered by reducing the exhaust loss or by implement-ing a single flow design rather than a dual flow designfor the same steam flow. A last-stage blade longerthan current limit must be made of a titanium alloywhich is lighter than stainless steel and has excellenterosion- and corrosion-resistant characteristics. FujiElectric has successfully tested long titanium alloyblades and is prepared to supply turbines that usesuch blades. The physical dimensions of turbines willinevitably increase as longer blades are employed.While contrary to the concept of above mentioned skidmounted design, this technology may be used in thenear future for a very big geothermal field if enoughsteam to support multiple 100MW class units isconfirmed.

3.4 Utilization of low temperature geothermal resourcesMost geothermal power generation is in the form of

a flash cycle that introduces steam, separated fromgeothermal brine, directly into a steam turbine. To uselow temperature geothermal resources for power gen-eration, binary cycle technology employs a suitablethermal medium as the working fluid according to thehot water temperature. This technology has beenutilized mainly in the USA. The capacity of a singlebinary unit is limited from several hundred kW to4MW maximum. To build a large capacity plant suchas a 40MW plant in the USA, many small units arecombined. In Japan, NEDO (New Energy and Indus-trial Technology Development Organization) is involv-ing in the development of a geothermal binary powerplant. One problem is that a group of fluorinecompounds, which were often used as the workingfluid, can no longer be used anymore because theydestroy the ozone layer. The application of a hydrocar-bon or ammonium solution, or discovery of a newthermal medium is very important for further develop-ment of binary cycle power plants. Since medium andlow temperature resources are more common thanhigh temperature resources, it is possible that thebinary cycle power plants will become popular inJapan once their reliability and economical feasibilityare proven.

Other technologies that utilize medium and lowtemperature geothermal resources for power genera-tion are the total flow turbine and the low pressureflash cycle. The total flow turbine directly intakesgeothermal brine, which is either hot water or amixture of steam and hot water. Fuji Electric designedand manufactured a small scale total flow turbine andcarried out a series of factory tests and an onsite test ofapproximately 1,000 hours using a geothermal fluid.One possible application of the total flow turbine is to

Page 7: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Fuji’s Activities in Geothermal Power Generation 101

utilize hot water from the separator for power genera-tion, before the hot water is re-injected to compensatefor plant parasitic loads.

The low pressure flash cycle is similar to an opencycle OTEC (ocean thermal energy conversion). Itsimply generates low pressure steam by flashing hotwater, and guides that steam into the steam turbine.This method does not require the development of newtechnology because the turbine is an application of thelow pressure part of the existing dual flash steamturbine. The characteristic features of this system arethat no special working fluid is necessary and that theplant parasitic load is small compared to a binarycycle.

3.5 New technologiesThere have been several proposals to use heat from

magma or volcanoes directly for power generation, andsome basic research has been carried out. The hot dryrock (HDR) technology is probably the most advancednew technologies under development for geothermalpower generation. In Japan both NEDO and theCRIEPI are working on HDR projects and havesucceeded in retrieving injected water as steam. Thenext step will be improvement of the percentage andtemperature of retrieval. An HDR power plant mustbe a closed cycle so that the flow of injected water canbe reduced. One possibility to solve this problem is toemploy a dry type cooling tower instead of thecommonly used wet type. The application of a binarypower plant is another possibility.

4. Conclusion

This year, the total installed capacity of geother-mal power generation in Japan is 580MW, and someadditional developments are planned. The Philippinesincreased their capacity during the 5 years from 1995to 2000 by 680MW, which includes the constructionwork of geothermal power plants in Leyte and Mindan-ao, and still has further development plans. In suchCentral American countries as El Salvador and CostaRica, several new geothermal projects,each being 50 to60MW in size, were completed in late 1990s. Indonesiaonce had many plans for large capacity geothermalpower plants, but these have been suspended eversince the country’s economy crisis. However thealready signed BOT or BOO (build, operate and own)contracts are still valid, and these projects are expect-ed to resume soon. In addition to these big projects,installations of small wellhead units in remote commu-nities which will allow more people to access toelectricity are another possibility as a local energysource in a country like Indonesia.

Coping with the continuously increasing demandfor energy while striving for harmony with the globalenvironment is a serious issue for the entire world.

Geothermal power generation, however small apercentage of the total energy output, can be a majorsource of power in regions or communities wheregeothermal resources exist. Fuji Electric, through theconstruction of geothermal power plants based upon itsmany proven global technologies, as well as newtechnologies, will contribute to solving the globalenergy problem.

Page 8: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW102

Hiroshi Murakami

Wayang Windu Geothermal Power Plant

1. Introduction

Throughout the world, development of geothermalpower plants has been promoted to utilize clean andrenewable energy with low carbon dioxide emissions.The country of Indonesia has the fifth largestdevelopment of geothermal energy, following the USA,Philippines, Italy and Mexico in the world.

In June 1997, Fuji Electric of Japan, together witha trading company, entered into an engineering,procurement and construction (EPC) contract withMagma Nusantara Limited (MNL) of Indonesia tosupply equipment for the Wayang Windu GeothermalPower Plant (rated capacity : 110MW), including apower station and a steamfield above ground system(SAGS). As an independent power producer (IPP),MNL will operate the plant and sell electricity toPersahaan Listrik Negara (PLN) for 30 years.

The geothermal steam turbine manufactured atFuji Electric’s Kawasaki Factory, has the world’slargest single casing capacity of 110MW with 27.4 inchlong last-stage blades (LSB).

The plant was put into commercial operation inJune 2000. One year after commencing operation, theturbine was disassembled, inspected and checked.Visual inspection revealed neither damage nor contam-ination. Thus far, plant operation has continued withno reported problem.

2. Overview of the Plant

2.1 Plant locationWayang Windu Geothermal Power Plant is located

in Pangalengan approximately 40km south of Band-ung, West Java in Indonesia, as shown in Fig. 1. Theplant is named after nearby Mt. Wayang and Mt.Windu. A tea plantation surrounds the site and itsaltitude is approximately 1,700m above sea level.

2.2 Distinctive characteristicsSince the plant is an IPP project, low capital cost

and reliable operation with high efficiency are essen-tial from an economical point of view. The plant hasseveral distinctive characteristics including large ca-

pacity turbine, two-phase fluid pipelines with centralseparators, and integrated pressure control designatedto meet such requirements.(1) Large capacity turbine

It is well known that larger capacity turbines aremore efficient for geothermal as well as conventionalpower plants. The largest single casing capacitygeothermal turbine of 110MW is utilized at this plant.(2) Two-phase fluid pipelines

A mixture of steam and water from productionwells is led to a central separator station as two-phasefluid. Use of smaller bore piping can reduce pipingmaterial and construction costs, comparing to theconventional steam flow piping(3) Integrated pressure control system

Stable separator pressure is essential for main-taining steam quality. The integrated pressure controlsystem uses turbine governor valves to maintain steamquality by varying pressure at the same time ascontrolling flow at the production wells. Consequently,the release of geothermal steam to the atmosphere canbe minimized.(4) Local architecture

In consideration of harmony with surrounding teaplantation, locally traditional roof and color are incor-porated in the architectural design of the power plant.

3. Project Schedule

Figure 2 shows the project schedule, which includes

Fig.1 Project location

JAVA SEA

CENTRAL JAVA

SUNDA STRAIT

P.PANAITAN

INDONESIAN OCEAN

SEM.JUNGKULON

0 30 60 90 km

N

PANDEGELANGRANGKASBITUNG

TANGERANGSERANG

BOGOR

JAKARTABEKASI

KARAWANG

GARUT

MALANGBONG

CIREBON

INDRAMAYU

SUBANGPURWAKARTA

TASIKMALAYA

BANDUNGCIANJUR SUMEDANG

SUKABUMI

PROJECTLOCATION

CIAMIS

Page 9: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Wayang Windu Geothermal Power Plant 103

engineering, design, manufacturing, transportation,construction and commissioning. The contract beganin June 1997 and the plant was ready for synchroniza-tion in August 1999. After 8 months preservation, theplant went online in June 2000.

3.1 Engineering, design and manufacturingCritical equipment such as the turbine, generator

and condenser were shipped from Fuji Electric’s Ka-wasaki Factory 12 months after notice to proceed wasgiven by MNL. Major auxiliary equipment such ashotwell pumps, the cooling tower, gas removal system,main transformer and distributed control system(DCS) were shipped from Japan, USA, Australia,Singapore, etc., 12 to 16 months after signing of thecontract. SAGS piping materials designed by KingstonMorrison Limited (KML) were shipped in stages fromJapan, USA, Korea, etc., 8 to 16 months after signingof the contract.

3.2 Construction and commissioningCivil and construction work was delegated to local

subcontractors. Proposals for that work were thor-oughly evaluated in terms of technical, commercialand financial perspectives. Onsite work for powerstation started in June 1997.

SAGS onsite works started in December 1997. Alocal engineering company, which is a subsidiary of aNew Zealand engineering company, has been hired formanaging and supervising such subcontractors.

3.3 PreservationBecause the transmission line constructed by PLN

was not completed in August 1999, the plant was puton preservation for 8 months.

Mechanical equipment such as the turbine andhotwell pump were disassembled and anti-corrosivemeasures were taken. Space heaters were put intooperation for electrical equipment where necessary.Control and instrument equipment such as DCS andthe monitoring system were operated normally.

SAGS pipelines were steam-capped at low pressure

steam from production wells.

4. Power Station

Figure 3 shows an overview of the power station.The area is almost square, having 230m E-W and210m N-S. Civil and architecture for Units No.1 and 2and the power plant for Unit No.1 are completed atpresent.

The turbine is of the single flash and double flowtype. The cooling water system is a closed circuitconsisting of a direct contact condenser and wet coolingtower. The gas removal system is a hybrid systemconsisting of a steam ejector and vacuum pump.

Figure 4 shows a schematic diagram of the powerstation and Fig. 5 shows the power station layout aftercompletion of Units 1 and 2.

4.1 Steam turbineMajor specifications are listed below.Type : single cylinder, double flow and condensing

typeOutput : 110MW (MCR 115MW)Inlet steam press. : 1.02MPaInlet steam temp. : 181°CExhaust press. : 0.012 MPa

Fig.2 Project schedule

Fig.3 Power station overview

Task name

Key dateContractReady for synchronizationCommercial operation

SAGSDesign and material procurementTransportationConstruction

Power stationDesign and material procurementTransportationConstruction

PlantTest and commissioningPreservationCommisioning and performance test

1997 19986

◆(June 12)◆(Aug.27)

(June 5)◆

7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 121999 2000

1 2 3 4 5 6 1 2 3 4 5 67 8 9 10 11 12

Page 10: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW104

Fig.4 Power station schematic diagram

G

1.02P180.7T

110,000kW

23.5T

44.8THot well pump

0.12PCondenserRe-injection

Evaporation & drift losses

Auxiliary coolingwater pump

Cooler

1.06P

At plant boundary

4.08P

42.5T

23.5T23.5T23.5T

23.5T

Gas removal system

Legend:P : Pressure, MPa absT : Temperature, °C

: Steam: Water: Gas

Coolingtower

Fig.5 Power station layout

Steam header

Administrationbuilding

Cooling tower

Unit 1

Unit 2(future)

Turbine-generator

Gas removal system

Page 11: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Wayang Windu Geothermal Power Plant 105

Fig.6 Turbine cross section

Number of stages : 2 (flows ) × 8Length of LSB : 697 mm (27.4 inch)Bearing span : 5,800mmSpeed : 3,000 r/minFigure 6 shows a cross section of the turbine.

(1) High efficiency LP bladeAdvanced LP blades are employed in the last three

stages, which are designed using the fully three-dimensional (3-D) flow calculation method. The laststationary blades are angled in the radial direction toreduce losses at the root area. The airfoils near the tipof the LSB form the so called convergent-divergentchannel that minimizes the shock wave losses. Byemploying these advanced LP blades, efficiency at theLP blades can be improved by 3%.(2) Reaction blade

The turbine blades of Fuji Electric’s geothermalsteam turbines are all reaction type blades. Blades inthe first through fifth stages are integral shroudblades, each of which is machined from one piece ofmaterial. These blades are assembled in the rotor and/or the stationary blade holders so that the shroud androot have compression stress on each surface thatcontacts the adjoining blades at both sides. With thistype of assembly, high vibration damping due to dryfriction will be produced, but no gaps will formbetween the adjoining blades under any operationalconditions . The moving blades of the sixth stage havea integral shroud with zigzag contour that assuresgood damping.(3) Casing

The turbine casing has a single shell constructionand is composed of two blocks in the axial direction, i.e.the front and rear parts. The upper half of the casingis shipped as one block, bolted at the vertical jointflange of the front and rear parts assembled with theupper half of stationary holder and/or stationary bladerings, so as to decrease the work at job site. The lowerhalf is also designed as one block in the factory. Thecasing is directly supported by foundation at both sidesof the exhaust. The bearing pedestals are independentfrom the casing and directly fixed on the foundation.This construction secures the vibration stability of the

turbine rotor.(4) Corrosion protection

The turbine uses reaction blades and therefore theturbine rotor has a drum type construction. Due to theflat configuration, stress concentration and depositionof corrosive components are eliminated and the possi-bility of stress corrosion cracking (SCC) is avoided.Because the rotor has the longest LSB for geothermaluse, its maximum diameter is quite large and stresseson the blade groove are large. To reduce the maximumstress on the blade groove, the newly designed lowstress groove is employed.(5) Erosion protection

Stellite shields are brazed to the L-0 and L-1moving blades on the tip to protect against erosion bywater droplets. Also to reduce the erosion by waterdroplets, drainage is provided at the inlet chamber,fifth stage outlet, and inter-stage of LP-blade row,whereby water droplets will be discharged to thecondenser.(6) Scale protection

A blade wash system is provided as anothercountermeasure against scaling. This blade washsystem washes the turbine blades during normaloperation by injecting condensate water.

4.2 GeneratorThe air cooled turbogenerator for this plant is the

largest capacity unit developed by Fuji Electric forgeothermal power plants.(1) Major specifications are as follows:

Type : three-phase horizontal cylindrical re-volving field total-enclosed type syn-chronous generator.

Ventilation : self-ventilationCooling : totally enclosed water-to-air cooled

(TEWAC)(2) Rating

Output : 137,500kVAVoltage : 13.8kVPower factor : 0.8 (lag)Frequency : 50HzNumber of phases : 3Speed : 3,000r/min

Insulation class : FExcitation : brushless excitation

5. Steamfield Above Ground System (SAGS)

Steamfield above ground system (SAGS) is thegeneric name for facilities other than the power stationin a geothermal power plant, such as the steampipeline, brine/condensate pipeline, separator, scrub-ber, rock muffler, etc.

Figure 7 shows a schematic diagram of SAGS.

5.1 Production and injection wellsThe production and injection wells were developed

Page 12: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW106

Fig.7 SAGS schematic diagram Fig.8 Production wellpad (WWQ)

by MNL prior to commencement of the work for thepower station and SAGS. There are three productionwellpads and three brine/condensate injection well-pads. Each production wellpad has three or four wellsranging from 1,800m to 2,500m.

The altitude of the production wellpads is approx.1,850m above see water level (aswl), being higher thanthat of the power station by 150m. On the other hand,the altitude of the injection wellpads is approx. 1,500maswl, being lower than the power station by 200m.

Figure 8 shows a production wellpad (WWQ).

5.2 PipelineGeothermal steam and fluid from production wells

are piped downhill to the separators as two-phasefluid. Pipelines from each wellpad to the separatorsare made of carbon steel with a 36-inch nominal bore.The distance between the wellpads and separators isapprox. 4km. The steam pipeline from the separatorsto the power station has a 40-inch nominal bore and isapproximately 1km long. The brine pipeline from theseparators to the injection wellpads has a 30-inchnominal bore and approximately 8km long. Thecondensate pipeline from the cooling water piping tothe injection wellpad has a 28-inch nominal bore and isapproximately 9km long.

The necessary pipe loops are provided on thosepipelines to absorb thermal expansion.

5.3 Separator, scrubber and rock mufflerThree cyclone type separators are used to separate

steam from the two-phase fluid that comes fromproduction wells. Steam is fed to the power stationwhile brine is fed to the injection wells.

Two corrugate type scrubbers are provided just infront of the power station to eliminate further mois-ture.

Surplus steam is released to the atmospherethrough vent valves. Two rock mufflers are providednear the separator station to reduce the noise level of

released steam.Figure 9 shows an overview of SAGS.

6. Power Generation

Since the commencement of commercial operationin June 2000, the plant has been operating stably as abase load power supply for the West Java region. Inconsideration of recent power demand, the plant iscontrolled to generate 110MW of power during thedaytime and 105MW during the nighttime by the PLNload dispatch center in Bandung.

Figure 10 shows the monthly power generationsince June 2000.

7. Other Issues

7.1 Environmental protectionA tea plantation and villages surround the plant.

During the construction and commissioning periods,storm water discharge, soil disposal, dust, and waterquality have been controlled to ensure minimal envi-ronmental impact. Periodical monitoring reports inaccordance with AMDAL (Indonesian environmentalregulation) were submitted to the government officeevery 3 months.

7.2 WeatherThe period from May through October is usually

the dry season. Civil works such as excavation,concrete pouring and backfilling were planned to takeplace during the dry season. However, there was nodry season in 1998 due to the so called “La Ninaphenomenon” which was a consequence of “El Ninophenomenon” in 1997. The progress of civil andstructural works was significantly affected. Unantici-pated environmental protection works were imple-mented accordingly.

7.3 Economic crisis in IndonesiaIn Indonesia as well as other Southeast Asian

countries, an economic crisis occurred in 1998. Thedifficulty that local subcontractors had in raising funds

MBD WWQ WWA

WWW WWF WWP

Production wellpads

Two-phase fluid

Separators

Steam

BrineRock muffler

Injection wellpads

Condensate

T/G

Power station

Page 13: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Wayang Windu Geothermal Power Plant 107

resulted in the delay of work progress. Local subcon-tractors faced difficulty in purchasing materials fromforeign countries because foreign companies did notaccept letters of credit issued by Indonesian banks.

As a countermeasure, we offered improved terms ofpayment to the subcontractors so as to assist in solvingtheir finance problem and we purchased necessarymaterials from foreign companies and supplied them tothe subcontractors.

8. Conclusion

The world’s largest capacity geothermal turbinewas manufactured at Fuji Electric’s Kawasaki Factoryin Japan, based on extensive experience in both thegeothermal and conventional power generation busi-nesses.

The Wayang Windu Geothermal Power Plant unit

No.1 has been successfully completed in cooperationwith MNL and local subcontractors. We sincerely hopethat the electricity generated at this plant will contrib-ute to the development and improvement of life forlocal people in this area.

References(1) Esaki, Y., Murakami, H. : Topics of Geothermal Power

Generation Abroad, Geothermal Energy, Vol.24, No.3(1999)

(2) Kato,Y. et al. : Progress of geothermal steam turbinetechnology, Fuji Electric Review, Vol.42, No.2 (1996)

(3) Murakami, H. et al. : Construction of the LargestGeothermal Power Plant for Wayang Windu Project,Indonesia, WGC2000, p. 3239 - 3244 (2000)

Fig.9 Bird’s-eye view of SAGS Fig.10 Monthly power generation

10,000

0

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

June July Aug. Sept. Oct. Nov. Dec. Jan.(2000) (2001)

(MWh)

Page 14: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW108

Fig.2 Map of El Salvador and location of Berlín

Ahuachapán G.P.P Tegucigalpa

UsulutánZacatecoluca

San Salvador

Santiago de Guatemala

Nueva San Salvador(Santa Tecla)

Berlín G.P.P

San Miguel

0 50 100 150km

NEpicenter (Mw7.6)Pacific Ocean

Tadao Horie

Berlín Geothermal Power Plant

1. Introduction

The Berlín Geothermal Power Plant is located inthe province of Usulután, an eastern vicinity in theRepublic of El Salvador, Central America. The plantarea consists of 15km2, is 107km away from the capitalcity of San Salvador (See Fig. 2), and is at an altitudeof 645 meters above sea level. Geothermal resources atthe Berlín area were originally explored in 1970’s, butactual project development activities only began in theearly 1990’s. El Salvador has two existing geothermalcomplexes. One is Ahuachapán, located in the westernvicinity of the country and consisting of three unitswith 95MW net capacity in total. The other is Berlín,where two 5MW wellhead units have been operationalsince 1992. This project is the second phase ofdevelopment of Berlín Geothermal, following construc-tion of the wellhead units. This is also the secondproject for Fuji Electric to provide equipment to ElSalvador, more than 20 years after completion of theAhuachapán Unit 3 (35MW, dual pressure unit) in1980.

A turnkey contract was signed with the owner,Comisión Ejecutiva Hidroeléctrica del Río Lempa(CEL) in November 1996. After overcoming somenatural obstructions, steam was successfully produced,and continuous power generation began in April 1999,The two units were officially put into commercialoperation in November 1999.

After more than one year of continuous operation,the first major inspection was carried out in Septemberand October 2000 for each unit respectively. Duringthe inspection, no major problems were found in any ofthe plant systems and principal equipment.

2. Summary of Contract Scope of Work

The basic contract scope includes the engineering,design, supply, procurement, construction and commis-sioning of 2 units of 28MW for the condensing powergeneration plant and its associated steam productionsystem. This project involved the expansion of anexisting geothermal plant with further future expan-sion possibilities, however since the new plant is

Fig.1 Overview of Berlín Geothermal Power Plant, El Salvador

located mostly in a remote field area, infrastructurerelated works were also included in the scope of work.To summarize, the following geographical area are inour scope of work:(1) Power generation facility, consisting of 2 ×

28.12MW units (Units 1 and 2)(2) Grading/landscaping of area of future units(3) 1.2km of access road from the junction of national

road (Mercedez Umaña - Berlín Road) to thepower plant

(4) Accumulation tank for condensate overflow fromthe cooling towers

Page 15: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Berlín Geothermal Power Plant 109

maintain, to the extent possible, a constant steam flowin the cross-country pipeline, even if the steam flow tothe turbine is interrupted due to tripping of the plantor load rejection.

3.2 Power generation plant systems3.2.1 Steam turbine

The power plant has two identical steam turbinegenerator units each of which produce a total output of28.12MW. The steam turbine has a single-flow topexhaust reaction type skid mounted design. It is alsoequipped with a blade washing system, allowing theinjection of condensate water into the wheel chamberto remove deposits during load operation. The turbineis controlled by a triple-redundant microprocessorbased Woodward Governor 509DCS, which has speed,load and inlet pressure control functions. It is alsoequipped with features that enable a quick response torunback and vacuum unloading situations. Mainspecifications of the turbine generator unit are summa-rized below.(1) Steam turbine:

(5) Steam separation system and fire water tank atProduction wellpads TR-3, TR-4 and TR-5

(6) Cross-country cable ductworks between powerplant, production wellpads and CEL’s resourceoffice at existing backpressure units

(7) Remote monitoring system of reinjection wellpadsTR-1, TR-8 and TR-11

(8) 115kV switchyard equipment at Berlín and re-mote substations, 15 de Semtiembre S.S. and SanMiguel S.S.

In conjunction with the engineering work, FujiElectric supplied its own steam turbine and condenserunits and procured all other equipment and materialfrom various countries. The construction work wassubcontracted to and carried out by local firms. Forexample, earthmoving and foundation works for thepower plant, access road and accumulation tank (coldwater condensate pond) were performed by Piassa, SAde CV, architectural and electromechanical works forthe power plant were performed by Prinel SA de CV,and the steam production system was constructed byMonelca SA de CV.

3. Description of Each Plant Subsystems

3.1 Steam production systemIn addition to existing production wellpads TR-2

and TR-9 which has been supplying steam to existingbackpressure units (2 × 5MW), new production wellswere drilled by CEL at wellpads TR-4 and TR-5. Ourcontract includes construction of 4 steam separatorsand associated piping systems at TR-4 and TR-5,which have a total of 8 production wells. The twophase fluid piping at the wellhead was designed to berouted through an underground channel so that futurere-drilling or repairing of existing wells can be execut-ed without removing large quantities of wellpad pip-ing, and with minimum disturbance of production tothat wellpad (See Fig. 3). The two-phase fluid is routedto separators (See Fig. 4) and separated steam istransported by 28-inch cross-country steam piping, onefrom the wellpad TR-5 to steam collector unit 1 locatedat the south boundary of the power plant at a distanceof approximately 2.2km, and the other one from thewellpads TR-4, TR-2 and TR-9 to steam collector unit2, at a maximum distance of approximately 1.7km. Onthe other hand, hot water from the separators is fed toreinjection wellpads TR-1, TR-8 and TR-11 alsothrough miles of cross-country pipeline.

Located immediately downstream of each separa-tor is a ball valve that protects the plant from waterinduction in case the separator should carry over hotwater into the steam lines. At the power plant side,there are two steam collectors at the boundary, eachequipped with pressure control valves, safety valve andrupture disc which connects downstream to a ventsilencer.

The intent of this steam collector design is to

Fig.3 TR-5 wellhead

Fig.4 TR-5 wellpad separators

N68-443-54

N68-443-50

Page 16: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW110

Fig.6 Turbine sectional view

Fig.7 Spray jet condenser

N68-443-62

Fig.5 Turbine and generator

N68-443-92

Type : single cylinder single flow, reaction condens-ing

Rated output : 28,120kW (condition A)Maximum output : 31,490kW (condition B)Steam pressure : 0.95MPa abs (condition A)

1.06MPa abs (condition B)Steam flow : 180t/h (condition A)

200t/h (condition B)NCG in steam : 0.4% in weightExhaust pressure : 0.01MPa abs (3 inch Hg A)Speed : 3,600r/minNumber of stages : 9 × 1Length of last stage : 581mm (22.9 inch)

(2) Generator:Type : 3 phase synchronous, TEWACRated output : 37,050kVAVoltage : 13.8kVPower factor : 0.85 laggingExcitation : brushless with PMG

3.2.2 Condenser and NCG removal systemThe condenser is a low level direct contact type and

its pressure is maintained at 0.01MPa abs by the non-condensable gas (NCG) removal system. The NCGremoval system consists of two stages, two 100%capacity ejectors and two 100% capacity ejector coolingwater pumps. The extracted NCG from the after-condenser and gland steam ejector condenser is led tothe cooling tower.3.2.3 Circulating water system

The circulating water system consists of two 60%capacity circulating water pumps which dischargecondensate from the condenser hotwell to the coolingtowers. The cooling towers have 3 cells per unit andare of the counter flow type with splash fill design.3.2.4 Auxiliary, fire and potable water system

The plant’s internal cooling water, the secondarycooling water, is fed to all of the internal subsystems,such as the turbine lube oil cooler, generator air cooler,compressed air system, air conditioning system, etc.,and is cooled by the primary cooling water systemthrough a plate type heat exchanger. While the sourceof water for the primary system is cooling tower water,potable water is used for the secondary cooling watersystem. Due to the local climate, with its clearlyseparated rainy and dry seasons, the city water supplyfrom the foothills of Berlín area becomes critical duringthe dry season and may potentially be interrupted. Tooffset such risks, a 400 cubic meter capacity fire watertank was installed at a vacant space near productionwellpad TR-3, whose elevation is 300m higher thanthat of the power plant. The power plant fireprotection water and potable water are supplied fromthis tank through an underground pipeline.

3.3 115kV substationThe Berlín Power Station is connected to two

transmission lines, one is routed to the 15 de Septiem-bre Substation and the other is routed to the San

Miguel Substation. The Berlín Substation consists oftwo circuit breakers at the main transformer side, twocircuit breakers at the line side, and one tie circuitbreaker. Each circuit breaker, except the tie circuitbreaker, has line and bypass disconnect switches.

Page 17: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Berlín Geothermal Power Plant 111

Fig.8 Berlín Substation

N68-443-70

Redundant protection from transmission line failure isprovided by conventional protection relays and ateleprotection system.

All operational conditions and status of the genera-tor’s main circuit and substation are also transmittedvia the remote terminal unit to a national dispatch

center in San Salvador.

3.4 DCS and plant operation/control systemAll plant operational conditions including those of

the production and reinjection wellpads are monitoredby DCS. The DCS itself is a fully double redundantconfiguration, but in addition to DCS, a PLC-basedauxiliary service panel is also provided as a backup inorder to realize bumpless transfer of all critical controlfunctions. In other words, operation can be continuedwithout tripping of the plant even if the entire DCSsystem fails. Pressure control of the steam/waterseparator and level control of the water tank atproduction wellpads can be controlled by either theplant’s DCS, or by the backup PLC located at eachwellpad, which also has the function of providingbumpless transfer whenever DCS control fails. TheDCS system also consists of six operating stations:three in the control room, one in the superintendent’sroom, one in the operation chief’s office (both of theserooms are located in the administration building in thepower plant), and one in CEL’s resource office (locatedat the 2 × 5MW pilot plant approximately 1km awayfrom the power station).

Fig.9 Power generation plant layout

1.000

C

C

CC

235800

2015

00

[Unit: mm]

Page 18: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW112

3.5 Reinjection systemAll hot water from the 4 wellpad separators is led

to reinjection wellpads through a cross-country waterpipeline and is continuously reinjected. To confirmsecure operation of the production wellpads, the flowand pressure of the reinjection line at each reinjectionwellhead are continuously monitored. Because of theremoteness of the reinjection wellpad area, the moni-toring panels at reinjection wellpads are powered bysolar panels and all data is transmitted to the DCS inthe plant control room via a radio frequency system.On the other hand, monitored data at productionwellpads is transmitted to the plant’s DCS via hard-wired lines.

4. Construction and Commissioning

The construction work was subcontracted to localfirms. Other contractors were also working throughoutthe Berlin geothermal area, such as cross-countrypiping installation contractors, transmission line con-struction contractors, O&M personnel camp facilitybuilding contractors, etc. All of the interfaces andpotential conflicts between the parties were wellcoordinated by CEL field personnel.

During execution of the construction work, we hadto overcome several natural difficulties.

First was the rainy season in 1997. Civil workssuch as ground breaking work in the power plant areaand the access road were started in early 1997, theyear remembered for the “El Niño phenomenon”.Although the rainy season in El Salvador normallyends in October or November, the rainy season in 1997was extremely severe and long, lasting until thebeginning of the following year.

Second was the discovery of an enormous under-ground layer of solid rock in the power plant area,whose volume was approximately 21,000m3 just inlocation of the plant building and equipment founda-tion area.

During the excavation work, a tremendous amountof dynamite was used to blast this solid rock layer.

Third was the assault of Hurricane “Mitch” inNovember 1998. This hurricane killed hundreds ofpeople nationwide in El Salvador, and plant construc-tion work was forced to slowdown due to water/electricity outages, the non-availability of transporta-tion for worker commuting, etc. Physical damage tothe construction site was minimal, however.

All of these difficulties were overcome minimumimpact on the schedule, due to the coordination anddetermined effort by CEL and local subcontractors.

The schedule also had to be coordinated withdrilling activities. The new production wells at TR-4was drilled in mid-1998, and wells at TR-5 were drilledfrom late 1998 to early 1999. Accordingly, theconstruction work at wellpad TR-4 was started afterthe completion of drilling and flow testing in late 1998.When the Unit-1 commissioning test was completed inMay 1999, TR-5 construction had not yet started.Therefore, Unit-1 was halted and the steam from TR-4was then diverted to Unit-2 for commissioning. TR-5construction work finally started in July 1999 and TR-5 began producing steam in November 1999, when thetwo units became operational.

5. Conclusion

Geothermal power generation is one of the mostproven, reliable and environmentally safe alternativeenergy sources. Fuji Electric continues to contributeits efforts in providing efficient and reliable geother-mal power plants throughout the world. In the courseof constructing the Berlín Geothermal Plant, we re-ceived tremendous and professional support from theowner, CEL, and from geothermal division companyGESAL (Geotérmica Salvadoreña S.A. de C.V.) person-nel, to whom we sincerely indebted. Fuji Electric looksforward to opportunities for participation in the nextphase of the Berlín geothermal project or in othergeothermal projects in El Salvador.

Fig.10 Plant control room

N68-443-5

Fig.11 Reinjection wellpad

N68-443-11

Page 19: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Hachijo-jima Geothermal Power Plant 113

Takashi Murakami

Hachijo-jima Geothermal Power Plant

Fig.1 Overview of Hachijo-jima Geothermal Power Plant1. Introduction

Hachijo-jima Geothermal Power Plant, the first-ever geothermal power plant to be built on a remoteisland in Japan, was constructed in the Nakanogodistrict of Hachijo-jima. Hachijo-jima is an islandlocated approximately 400km south of Tokyo, with acircumference of 58.9km and area of 65.9km2. Theisland is gourd-shaped, and has two volcanic moun-tains, Miharayama (or Eastern Mountain, located inthe south eastern part of the island) and Hachijo Fuji(or Western Mountain, located in the northwesternpart).

In 1989, New Energy and Industrial TechnologyDevelopment Organization (NEDO) selected the islandas a site to survey for the promotion of geothermaldevelopment. A drilling survey confirmed the exist-ence of promising geothermal resources in the south-ern part of the Eastern Mountain.

In 1992, The Tokyo Electric Power Co., Inc. startedgeothermal development on the site and performedproduction well drilling, blow-off tests, an environmen-tal survey, and the basic planning and design for apower generation plant. After having completedvarious pre-construction procedures, The Tokyo Elec-tric Power Co., Inc. started construction of the Hachijo-jima Geothermal Power Plant in June 1998. After trialruns, the plant began commercial operation on March26, 1999 and continues its operation today.

This paper presents an overview of the Hachijo-jima Geothermal Power Plant.

2. Overview of the Project

Before the geothermal power plant was construct-ed, electric power was supplied only from dieselgenerator units, and demand for electricity was ap-proximately 10,000kW at the maximum and 3,000kWat night.

This geothermal power plant has the capacity tosupply 1/3 of the total electricity demand in the island.The plant was projected to serve as a stable powersupply, and to reduce fuel cost and hence the cost ofpower generation compared to the existing diesel

generator units.In July 1998, Fuji Electric was awarded an order

to supply a turnkey system for the project. FujiElectric manufactured, procured, installed and com-missioned all of the equipment and system, such as aturbine and generator rated at 3,300kW, a steamgathering system, a steam scrubbing system, and anH2S abatement system.

Since only a short, 3-month installation period wasscheduled, components of the plant were designed to beskid-mount type or package-mounted to the extentpossible.

Since the steam contains high content of H2S gasand H2S gas emission is limited by local regulation, anH2S gas abatement system was installed.

This plant also provides the hot water supplyingsystem to neighbor facilities through plate-fin heatexchangers utilizing the hot water from the condenser.

Figure 1 shows an overview of Hachijo-jima Geo-thermal Power Plant.

3. Power Plant

3.1 Basic planningThe plant was planned with consideration for

environmental preservation, cost effectiveness, reli-ability, maintainability, and in accordance with Tokyometropolitan government regulations.

Page 20: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW114

3.2 Heat cycleProduction wells are steam-dominated and are

provided with a single flash cycle system because ofthe extremely low hot water content in the steam.

3.3 System configurationFigure 2 shows the main piping diagram. Two-

phase flows from the production wells, HT-1 and HT-2,are combined along their way to a steam separator.After being separated from hot water in the steamseparator, the steam enters the turbine via the steamscrubbing system, expands in the turbine and thenturns into condensate in the condenser. Hot waterreturns underground via a re-injection pump pit, re-injection pumps and a re-injection well.

With the exception of the two re-injection pumpunits, the two steam ejector units and some auxiliarymachines, the plant is not provided with standbyequipment.

3.4 Plant layoutFigure 3 shows the overall plant layout. There are

Fig.2 Main piping diagram

M

Venturitube

Silencer

Mist separator

Steam turbine

Genera-tor

Gas removal system

1st-stage steam ejector

Hot wellpump(100%¥1)

Auxiliarycooling waterpump(100%×1)

A main oil cooler

B main oil cooler

Aircooler

Raw water pump(100%×1)

Rawwatertank

Re-injection well

Drainagepump

Hot water

pitB

A

Flashtank

Steam separator

Production well(HT-1)

Production well(HT-2)

Re-injection   pump

PCoolingtower

Chemicals feed tank

Intercooler

Aftercooler

V6-

136

15A

2nd-

stag

e st

eam

eje

ctor

B A B A

Mesh demist-er

A B

Con-denser

G

H2S abate-ment

system

B

M

P

TP-7

M

U

U

S

mountains to the north and east of the power plant,and private houses to the south and west. The planscalled for machines and equipment to be installed inthe eastern part of the plant.

4. Overview of Facilities and their Features

4.1 Steam gathering systemGeothermal fluid is fed as a two-phase flow to the

steam separator. There, the fluid is separated intosteam and hot water by centrifugal force. Lengths ofthe two-phase flow piping and steam piping are veryshort, approximately 30m from the master valve of theproduction well to the steam separator and approxi-mately 70m from the steam separator to the steamturbine via the steam scrubbing system. Diameters ofthe pipes are designed to be larger than usual in orderto reduce velocity to protect the sand erosion whichwill be caused by solid impurities and tiny rock.

Figure 4 shows an exterior view of the steamseparator. Its specifications are as follows:(1) Steam separator

Type: vertical cyclone, top-outlet type

Page 21: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Hachijo-jima Geothermal Power Plant 115

Number of units : 1Separated steam : 40t/hSeparated hot water : 4t/hDesign pressure : 1.07MPaDesign temperature : 200°CSeparation efficiency: 99.9%

Fig.3 Overall plant layout

Fig.4 Exterior view of the separator

4770

019

300

Ele

ctri

cal

cont

rol r

oom

Tu

rbin

e

Generator

PR hall

Gas removalsystem

Cooling towerH2S abatement system

98250

Condenser

4.2 Steam scrubbing systemSteam from the steam separator contains a fine

mist of sprayed-off hot water. The power plant isprovided with a steam scrubbing system to trap themist and to improve steam quality.

The system consists of a venturi tube, whichinjects water into the main steam and mixes andcollides the injected water drops with mist, and a mistseparator, which separates such mist from steam anddrainage after water injection.

Figures 5 and 6 show an exterior view of theventuri tube and mist separator. Their specificationsare as follows:(1) Venturi tube

Steam : 40t/hNumber of nozzles: 4 × 50A (A: nominal diameter)Injection water : 3.7t/h

(2) Mist separatorType: vertical cyclone, top-outlet typeNumber of units : 1Separated steam : 40t/hSeparated hot water: 4t/hDesign pressure : 1.07MPaDesign temperature : 200°C

4.3 Turbine and auxiliary equipmentA high-speed turbine is adopted based on the

results of an assessment to optimize steam conditions,

Page 22: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW116

Fig.8 Exterior view of the condenser

Fig.7 Cross-sectional view of the turbine

plant efficiency and cost of the turbine and its relatedequipment.

Upward exhaust and skid-mount construction areemployed in consideration of the short installationperiod. In the skid-mount construction, a reductiongear assembly and a generator are mounted on acommon bed.

The turbine and generator were installed with anoutdoor cover.

A drum-type rotor, reaction-type blading, highpressure blades with an integral shroud and free-standing low pressure blades, all standard features ofFuji Electric’s geothermal turbines are utilized. Inaddition, the turbine includes a skid-mount type oilconsole with a main oil tank, an oil pump andlubricating oil filters mounted on the skid.

Figure 7 shows a cross-sectional view of the

turbine. Its main specifications are as follows.Type: single cylinder, single flow, top exhaust

condensing, high-speed turbineOutput: 3,300kWSteam conditions

Pressure: 0.79MPa Temperature: 170°C

Exhaust pressure : 143kPaGas content in steam: 2.7% (wt%)Revolution speed : 7,266 r/minNumber of stages : 8

4.4 Condenser and gas removal systemA spray-jet, direct-contact-type condenser is em-

ployed. Fuji Electric has supplied many condensers ofthis type, which have reliable operational experiences.

To resist corrosion by the geothermal fluid, stain-less-clad steel is used for the shell and stainless steel isused for all internal components.

Figure 8 shows an exterior view of the condenser.Specifications of the condenser and gas removal systemare as follows:(1) Condenser

Type: spray jet, direct-contact low-level typeInternal pressure: 133kPa (4 in. Hg)Cooling water : 1,032m3/h

Fig.5 Exterior view of the venturi tube

Fig.6 Exterior view of the mist separator

Page 23: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Hachijo-jima Geothermal Power Plant 117

Cooling water temperature: 33.2°C(2) Non-condensable gas removal system

Type: 2 × 100% 2-stage steam ejectorNumber of units: 2 (including one standby unit)Capacity : 1,181kg/hDriving steam

Pressure : 0.71MPa Flow rate: 3.9 t/h

4.5 H2S abatement systemThe content of H2S gas in the plant’s geothermal

steam is very high. To comply with the maximumpermissible emission of 10ppm specified by the Tokyometropolitan government, dilution of the exhaust gasonly with exhaust air from the cooling tower wouldrequire an extremely large cooling tower and impracti-cal. Thus, an H2S abatement system was introduced.In introducing the system, a flue gas desulfurizationmethod was selected based on consideration of theparticular circumstances for an island, raw materialcost and maintainability. In this method, H2S gas ismixed with LPG, combusted, converted into SOx andthen desulfurized with injected magnesium hydroxide.The H2S abatement system consists of combustionequipment which combusts the H2S gas, a desulfurizerwhich produces harmless magnesium sulfate by sprin-kling magnesium hydroxide on the generated SOx, anda sludge processing unit to remove suspended solid(SS) content from the powdered magnesium hydroxideraw material.

Figure 9 shows an exterior view of the H2Sabatement system. Its main specifications are asfollows.(1) Combustion equipment

(a) Combustion furnaceType: fixed horizontal, cylindrical combustion

furnaceNumber of units : 1Design pressure : 108.7kPaDesign temperature: 1,200°C

(b) Combustion air blowerType: centrifugal typeNumber of units: 1Capacity : 3,000 Nm3/h × 170.0kPaMotor output : 11kW

(c) LPG supply equipmentType: LPG cylinder (50kg)Number of cylinders: 18 (9 × 2 lines)Supply pressure : 116 to 121kPa

(2) Desulfurizer(a) Absorber

Type: vertical, cylindrical filling typeNumber of units: 1Dimensions : 800mm × 2,000mm (diameter

× height)(b) Oxidation air blower

Type: root typeNumber of units: 1Capacity : 1,140 Nm3/h × 150kPaMotor output : 30kW

(3) Sludge processing equipment(a) Filter press

Type: hydraulic automatic clamping typeNumber of units: 1Capacity : 300 liter

4.6 Cooling water systemCooling water is fed to the condenser by the

pressure difference and elevation difference (head)between the cooling tower cold water basin and thecondenser.

After being mixed with cooling water, geothermalsteam turns into condensate, and is fed to the coolingtower by a hot well pump. After being cooled at thecooling tower it returns to the cooling tower cold waterbasin and is again fed to the condenser.

To reduce the noise generated by the splashing ofwater droplets, the body of the cooling tower is made ofconcrete. In addition, to prevent ventilation noise fromdisturbing the local community, the cooling toweremploys a single suction type ventilation system inwhich air intake vents are provided only on the eastside of the cooling tower at a considerable distancefrom private houses.

The height of the cooling tower is limited to within13m by environmental regulation.

Figures 10 and 11 show exterior views of the hotwell pump and cooling tower, respectively. Their mainspecifications are as follows:(1) Hot well pump

Type: vertical mixed flow typeNumber of units: 1Capacity : 1,300t/hTotal head : 23mMotor output : 110kW

(2) Cooling towerType: induced draft, counter flow, single suction typeNumber of units: 1

Fig.9 Exterior view of the H2S abatement system

Page 24: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW118

Water quantity : 1,262m3/hInlet water temperature : 46.6°COutlet water temperature : 33.2°CDesign wet-bulb temperature: 21°CFan: 2 × 55kW

5. Electric and Control Systems

5.1 Electric systemFigure 12 shows a single line diagram. Electric

power generated in the geothermal power plant issupplied to the transmission line of the diesel powerstation. Even if a failure should occur on thetransmission line, the electric system is designed sothat isolated operation can be performed by disconnect-ing the circuit breaker for transmission and insteadusing in-house auxiliary power.

Fig.11 Exterior view of the cooling tower

Fig.10 Exterior view of the hot well pump To protect the generator, digital duplex protectiverelays are employed for redundancy.

Figure 13 shows an exterior view of the generator.The electric system’s main specifications are as follows:(1) Generator

Type: horizontal cylindrical, air cooled typeCapacity: 3,660kVAVoltage : 6.9kVPower factor : 0.93, leadingRevolution speed: 1,500 r/minFrequency : 50HzExcitation : brushless type

(2) House transformerType: molded typeCapacity: 600kVAVoltage : R6.9-F6.6-F6.3kV/460V

5.2 Instrumentation and control systemsPlant starting and stopping is performed at the

electrical control room of the plant.After the system is brought up to a steady

condition, all necessary monitoring and control of thevoltage or load are performed by the ITV at the remotecentral control room of the diesel power station about12km far from this plant.

In parallel operation, turbine is usually operatedunder power control as base load using turbine bypasssystem, which controls constantly turbine inlet steampressure by releasing the surplus steams to thecondenser.

A hydraulic blow down control valve is provideddownstream from the steam separator. This valverapidly discharges steam when the turbine trips, andalso serves as a backup in case of malfunction of theturbine bypass control valve.

A digital governor named “TGR”, which has neces-sary functions such as turbine automatic start up,power control, inlet steam pressure control, loadlimiting, and AVR, operates this plant.

TGR consists of the digital voltage source, I/Odevices and has redundancy. Generator protectionrelays also have redundancy.

Electrical and control panels are installed in thepackaged type electrical and control room.

5.3 Package-type electrical control roomThe electrical control room is a compact package-

type housing, comprised of seven modules.As the countermeasures against H2S gas corrosion

to the electrical and instrumentation equipment in thepackaged type electrical and control room, H2S gasabsorption filter is installed at air intake of airconditioner.

In addition, the corrosion protection measures suchas tin plating, epoxy coating, and special greases aretaken to the electrical and instrumentation apparatus.

Figure 14 shows a view of the package-type electri-cal control room.

Page 25: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Hachijo-jima Geothermal Power Plant 119

Fig.12 Single line diagram

Fig.13 Exterior view of the generator

SYN1

BM

Generator circuit braker

Generator3,660kVA 6,900V306A 0.93pf leading1,500 r/min

41

31

3 × CT 600/5A40VA,1PS

PR

64G

SYN2 64B

GSR

Line circuit brakerVCB 7.2kV

Vo

Ao

WH VarH W PF

V

To diesel power station6.9kV

F

VT,FT,AT,PFT,WT

95B

27B

TCP

ZCT 200mA/1.5mA

DGR15,60,25

43-25

3-25G

SYN1 SYN2 SYN3

3-25S

V

F

V

F

SY

25P

DV DA

6.9kV

64EF

SYN3

VT, FT, AT,PFT, WT, VarT

A

VAuxiliary transformerR6.9-F6.6-F6.3kV/460V600kVA

460V power center

2 × CT100/5A 40VA1PS

50-51

F

WH W Var

Pf

WT

AVR

51E PMG

BM

64GF

ACEx

67RG51G

67G

40G

SG

87G

59G 27G

Vo

60G

6. Conclusion

This paper has presented an overview of Hachijo-jima Geothermal Power Plant. At present, the power

Fig.14 View of the package-type electrical control room

plant is playing an important role in supplying basepower in Hachijo-jima.

It is hoped that this paper will provide usefulinformation for future similar geothermal powerplants.

Page 26: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW120

Fig.2 Svartsengi Unit 5 system

Two extraction steam turbine G

Geothermal steam

Regional heating

Ground water

Coolingtower water

Shigeto Yamada

Geothermal Steam Turbines forVarious Purposes

Fig.1 Installed capacity of geothermal power plants

1. Introduction

Geothermal power generation was first experimen-tally developed in Italy in 1904, and commercial powergeneration also commenced in Italy in 1913. At first,geothermal power generation utilized natural steamfrom production wells. The first flash system was wentonline in 1958 in New Zealand, and the subsequentinstallation of geothermal power plants spreadthroughout the world.

As of 2000, the total installed capacity of geother-mal power generation units worldwide is about8,000MW (Fig. 1). Most plants utilize flash cycletechnology and are constructed only for power genera-tion.

In cases where the resource temperature is nothigh enough to generate steam efficiently above atmo-spheric pressure, binary cycle technology has beenutilized. Even for such low temperature geothermalresources, it is possible to plan for steam turbines thatutilize flash cycle technology. Although binary cycletechnology offers the greatest benefit, that is, it doesnot emit non-condensable gases including hydrogensulfide gas into the atmosphere, it uses working fluidsother than water, which makes system operation andmaintenance more sensitive and costly compared toflash cycle technology.

Here, two samples of geothermal power plantshaving other functions in addition to power generationare introduced. One is the Svartsengi Unit 5 inIceland, which has two extractions pipes for theheating steam used in district heating. The other isSalton Sea Unit 5, which has two intake pipes from amineral recovery plant. Also a plan for a geothermalsteam turbine for use with a very low pressure (VLP)flash system is introduced.

The proprietary technology Fuji Electric employsin its geothermal steam turbines will contribute tosatisfying the various requirements for the efficientutilization of geothermal energy.

2. Svartsengi Unit 5 (30MW)

Iceland has been utilizing the geothermal resourc-

es for district heating. Sudurnes Regional HeatingCorp. (SRH), a company that supplies hot water to itslocal community, operates the Svartsengi GeothermalPower Plant consisting of the back pressure turbineunit, binary units and a condensing turbine unit. Unit5 is of the condensing type, and has two output ports tosupply the heating steam for the district heatingwater. Unit 5 was delivered to the plant in 1998 and

0 2,000 4,000 6,000

Capacity

Data from IGA homepage (http://www.demon.co.uk/wrtab.html) as of 27 May 1996

(MW)

8,000 10,000 12,000

USA2005

2000

1995

1990

Philippines Mexico Italy Indonesia the othersJapan

Page 27: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Geothermal Steam Turbines for Various Purpose 121

went online in 1999. Figure 2 shows a schematic of theUnit 5 system.

Geothermal steam is supplied to the turbine forgenerating 30MW and for heating fresh water. Theturbine has an exhaust pipe leading to the condenseras well as two extraction pipes. Exhaust steam iscondensed in the condenser by the cooling tower water.The condenser is divided into two sections, one is anormal condensing zone, and the other is a condensingzone that functions also as a pre-heater for the districtheating water. Ground water is first fed to thecondenser. Two steam pipes are used for heating theground water. Then the heated water is supplied tothe particular region. Table 1 lists major technicalspecifications of the Unit 5 turbine.

The extracted steam pressure is externally con-trolled to maintain the heated water temperature. Bychanging the ground water flow and by the controllingthe extraction pressure, four season operation patternsare planned as shown in Table 2.

Figure 3 shows the section of the Svartsengi Unit 5

turbine.

3. Salton Sea Unit 5

Salton Sea is located in Imperial Valley California,and it is one of the largest geothermal power genera-tion area in the world. Table 3 lists the powergenerating units currently in operation.

Unit 5, introduced here, is located in the Region 1,where four level of steam pressure are utilized: highpressure (HP), standard pressure (SP), low pressure(LP) and very low pressure (VLP). Unit 1 is a simplestraight condensing unit and Unit 2 is a turboexpander from HP to SP. Unit 3 intakes SP and LPsteam, and Unit 4 intakes SP steam and extracts LPsteam. Unit 5 intakes SP, LP and VLP steam. Usagethese four levels of steam pressure is coordinated inthe Region 1 area to optimize the steam usage andpower generation.

Unit 5 was delivered to the plant in 1999 and wentonline in 2000. Table 4 lists major technical specifica-tions of Unit 5.

Unit 5 contains not only a power generation unitbut also a mineral recovery plant. The LP and theVLP steam for Unit 5 are generated in the mineralrecovery plant. Figure 4 shows the rough schematic ofthe Unit 5 system.

The SP steam supplied to Unit 5 is delivered fromUnit 3 and 4 located next to Unit 5. SP brine is alsofed from Units 3 and 4 areas to the mineral recoveryplant., LP and VLP steam is generated in the mineralrecovery plant, and fed to the Unit 5 turbine.

Figures 5 and 6 show the Unit 5 turbine.

Table 1 Features of Svartsengi Unit 5 turbine

Fig.3 Section of Unit 5 turbine

30,000 kWOutput

0.65 MPa absMain steam

0.29 MPa absNo.1 extraction

0.16 MPa abs

262,800 kg/h

14,400 kg/h

97,200 kg/hNo.2 extraction

0.01 MPa absExhaust

3,000 r/minSpeed

Table 2 Four season operation patterns

Summer normal

Spring Autumn WinterItem

Winterpeak

0 18,000 14,400 39,600No.1 Extraction(kg/h)

54,000 57,600 97,200 108,000No.2 Extraction(kg/h)

432,000 432,000 864,000 864,000Hot water supply(kg/h)

Table 3 Power generating units in Salton Sea Area

10 MW

4 MW

Unit 1

54 MW

Unit 2

49 MW

Unit 3

58 MW

Unit 4

Unit 5

27 MWVulcan (HP)

9 MWVulcan (LP)

36 MWHoch

36 MWElmore

36 MWLeathers

Region 1

Region 2

Region 3

319 MWTotal

Table 4 Features of Salton Sea Unit 5 turbine

58,320 kWOutput

0.86 MPa absSP steam inlet

0.37 MPa absLP steam inlet

0.14 MPa abs

16 kg/s

73 kg/s

65 kg/sVLP steam inlet

0.0096 / 0.013 MPa absExhaust

3,600 r/minSpeed

Page 28: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW122

Fig.7 Flash pressure vs. output

2,6002,7002,8002,9003,000

Ou

tpu

t (

kW

)

3,1003,2003,3003,4003,5003,600

0.05 0.06 0.07Flash pressure ( MPa abs )

0.08 0.09 0.1 0.11 0.12

For 1,000t/h hot waterat 130 °C

Because the amount of the SP steam is very smallcompared to LP and VLP steam as shown in Table 4,the SP steam section is single-flow. After being mixedwith LP steam, both LP and VLP sections are double-flow. Some of the SP steam flow is branched to theother side at the LP steam inlet so that the exhauststeam flow on both sides is equal. The turbineexhausts are connected to the condenser, which isdivided into two independent condensing zones withdifferent vacuum to increase the unit efficiency com-pared to a conventional single vacuum condenser.

4. Very Low Pressure (VLP) Flash System

When low temperature geothermal resources areused for the power generation, binary cycle technologyis normally used. For such geothermal resources,

Fig.6 Salton Sea Unit 5 turbine rotor

steam turbines can be utilized by flashing the geother-mal brine to very low pressure such as atmospheric oreven sub-atmospheric pressure. The binary cycle has asuperior to the flash cycle in that the geothermal fluidcan be circulated from the production wells to the re-injection wells without emitting gases and impuritiesfrom the brine into the atmosphere. However thebinary cycle normally requires larger parasitic loadscompared to the flash cycle. The working fluidnormally used in a binary system is flammable ortoxic. The VLP system is planned as one solution thatallows utilization of low temperature geothermal re-sources ranging about 100 to 120°C.

An example of the VLP system plan is show below.The sample plan is based on the conditions shown

in Table 5.The flash pressure is usually optimized to obtain

maximum output. Figure 7 is an example of theoptimization for the 130°C saturated hot water. Asshown in Fig. 7, maximum output can be achieved atapproximately 0.065MPa abs of flash pressure in thisexample.

Figure 8 shows an example heat and mass balancediagram for this system. Although the maximumoutput would be achieved at 0.065MPa abs based onFig. 7, the flash pressure of 0.07MPa abs is selectedsince the steam flow at 0.065MPa abs does not fit withthe selected turbine model for this example. Theselected turbine model is a single-flow skid mountedtype with 467mm last-stage blades. Figure 9 shows thecross-sectional view of the turbine. As shown in Fig. 9,the turbine is quite similar to a conventional geother-mal steam turbine except that the number of stages isonly three.

A liquid ring vacuum pump is considered to extractsmall quantities of leaked air and accompanyingsteam.

This example has the following parasitic loads;hotwell pump (110kW), auxiliary cooling water pump

Fig.4 Salton Sea Unit 5 system

Fig.5 Section of Salton Sea Unit 5 turbine

Mineralrecovery

plant

SP brine, from Units 3 and 4Reinjection

SP(8k) steam, from Units 3 and 4

LP(2.5k) steam

VLP(1.5k) steam

Table 5 Basis of sample VLP system

130°C saturated waterHot water temperature

1,000 t/hHot water flow

20°CAmbient wet bulb temperature

Page 29: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Geothermal Steam Turbines for Various Purpose 123

(5.5kW), cooling tower fans (110kW), vacuum pump(15kW) and power for the control system (Ca. 10kW)such as an air compressor; totaling approximately250kW which is roughly 7% of the gross output.

There may be a various other cases in addition tothe example described in the previous section. Ifgeothermal hot water contains some percentage ofsteam, the turbine inlet pressure can be raised, forexample, to 0.09MPa abs, thereby increasing the grossoutput; however in such cases, more power must beconsumed for gas extraction because non-condensablegases are usually contained in steam. Condenserpressure plays a very important role in determiningthe output since the heat drop across the VLP turbineis quite low compared to that of an ordinary geother-mal turbine. With a VLP flash system, compared toordinary geothermal power generation, it is moreeffective to lower the design condenser pressure toincrease the output under the same brine consump-tion.

5. Conclusion

Geothermal energy is regarded as renewable and

Fig.8 Example heat and mass balance of the VLP flashsystem

G

3,500kW

0.07P

0.05P

0.15P130T

1,000,000F

Legend

P : MPa absT : °CH : kJ/kgF : kg/h

920,250F

0.067P88.6T

2,658H73,750F-ST

0F-NC

73,750F-ST0F-NC

0.011P 33.0T

265F

200F44,200F

2,673,950F66,849F

6,901FBlowdown

44.7T2,673,950F

29.0T2,600,000F

44,000FCoolers

0NC54Air65ST

WBT20.0T domestic energy source, and continuous development is

expected in all geothermal countries. In order toutilize geothermal energy more effectively, it is antici-pated that geothermal power plants having additionalfunctions, as introduced here, will be planned. FujiElectric’s geothermal steam turbines will contribute askey components to such plans for multi-purpose geo-thermal plants.

Low temperature geothermal resources are plenti-ful. In addition to low temperature geothermalresources, hot water that is being re-injected can be aresource for a VLP flash system, if lowering the re-injection temperature is allowed. Nature characteris-tics of geothermal resources vary area to area, and siteconditions also differ. The important consideration isto select the most suitable system under the givenconditions. The VLP flash cycle will contribute toexpanding the range of selections available for geother-mal power generation with low temperature resources.

References(1) Esaki, Y. : Very Low Pressure Flash Cycle Geothermal

Power Generation, Proceedings of 20th Annual PNOCEDC Geothermal Conference, Manila, Philippines,March, 1999

(2) Yamada, S. : Flash Cycle for Low Temperature Geo-thermal Resources – Very Low Pressure (VLP) FlashCycle, Proceedings of the World Geothermal Congress2000

Fig.9 Cross-sectional view of the turbine for very low pressure

Page 30: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW124

Yoshifumi Kato

Recent Technology ofGeothermal Steam Turbines

1. Introduction

The cumulative capacity of geothermal powerplants constructed worldwide has reached 7,974MW,which is a 16.6% increase in the last 5 years(1). Thecumulated capacity of the geothermal turbines FujiElectric has manufactured increased from 1,253MW asof 1995 to 1,566MW as of September 2000, which is a25% increase in terms of capacity. This reveals thatincreased international environmental awareness hasresulted in a larger total geothermal capacity and thatthroughout the world, users have appreciated thereliability and performance of Fuji’s geothermal steamturbines.

The evolution of geothermal steam turbine technol-ogy was introduced in a previous paper(2). Develop-ment of the geothermal steam turbine has continued tomake progress over the past 5 years. This paperintroduces the recent technology of geothermal steamturbines, and also presents the features of two typicalgeothermal steam turbines that were put into commer-cial operation in 2000.

Decreasing production well pressure is an inevita-ble consequence of geothermal power generation. Twosolutions to maintain the output of geothermal powerplants in cases of decreasing production well pressurewill be described.

2. Recent Technology of Geothermal SteamTurbines

Geothermal steam turbines have been developedbased upon fossil fueled steam turbines, and thereforeseveral new technologies employed by geothermalsteam turbines are the same as those used in fossilfueled steam turbines. This section describes thosetechnologies which are shared with fossil fueled steamturbines as well as specific technology for the geother-mal steam turbine.

2.1 Advanced reaction blade airfoil having higher efficiencyAn advanced reaction blade airfoil (Fig. 1) was

developed to reduce the number of stages in fossilfueled steam turbines by increasing the heat drop per

stage. Through employing the new reaction bladeairfoil, stage efficiency will be increased by 1.5%.

2.2 Advanced low pressure (LP) bladeA sudden increase in the cross sectional area of the

steam line in the last few stages of a condensing steamturbine is necessary due to the huge steam expansionthat occurs in a vacuum. Long LP blades are employedfor the last three stages.

Progress in computational fluid dynamics (CFD)has enabled the development of advanced LP blades.

Following the development of a 38.5-inch LP bladefor use at 3,000 r/min in the latter half of 1980s, aseries of advanced LP blades has been completed,

Fig.1 Comparison in efficiency of reaction blade airfoil N1 andT4

Fig.2 Last stage stationary blade ring

0 1.0 2.0 3.0 4.0 5.0 6.00.88

0.90

0.92

0.94

0.96

0.98

1.00

1.02Airfoil N1

Airfoil T4

Loading factor

Rel

ativ

e ef

fice

ncy

Page 31: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Recent Technology of Geothermal Steam Turbines 125

spanning the entire output range.The last (L-0) stationary blades are radially angled

in order to increase reaction degree near the root andto reduce secondary losses (Fig. 2). Airfoils near the tipof the last stage blades (LSB) are contoured to form aso-called convergent-divergent passage that preventsthe generation of normal shocks which cause largelosses in the transonic cascades (Fig. 3).

By employing the advanced LP blades, stageefficiency will be improved by approximately 3%.

2.3 Large bore sized, triple eccentric butterfly valvesLiquid dominated geothermal power plants tend to

employ double flash technology to increase generatoroutput.

In a double flash system, the separated hot waterin an HP flasher is fed to an LP flasher to generate lowpressure steam. The low-pressure steam is thensupplied to the intermediate stage of the steamturbine. The bore size of stop valves and steam controlvalves for LP steam is normally very large, since the

specific volume of the low pressure inlet steam is large.Double eccentric butterfly valves were employed

for the low pressure inlet steam as general stop valves.However, opening a double eccentric butterfly valveusually requires a large torque from an actuator due tothe large wedge force generated by the point contact onthe sealing surface between the disk and the sheet.

A feature of the triple eccentric buttery valve isthat its sealing surface is contoured in the shape of acone whose center does not coincide with the diskcenter (Fig. 4). The seal rings installed in the disk arepushed into the disk when the valves closed. As theresult, sealing is achieved through surface contactinstead of point contact. A comparably small actuatorforce is sufficient to open these valves smoothly.

3. Recent Geothermal Steam Turbines

Fuji Electric has two types of geothermal steamturbines, a packaged type and a dual exhaust flowtype. Packaged type turbines range up to 40MW incapacity, and dual exhaust flow types range from55MW on up.

The packaged type turbines are completely pre-assembled at the factory and are delivered as a singlepackage in order to reduce the onsite installation work.

The dual flow exhaust turbine is inspected at thefactory and then dissembled into parts, which aresmall enough to be readily transported to the site, suchas the rotor and the upper and lower half of the casing.

The following describes geothermal steam turbinesrecently put into the commercial operation.

3.1 Wayang Windu 110MW geothermal steam turbine(3)

Figure 5 shows the cross section of the steamturbine for the Wayang Windu Geothermal PowerPlant in Indonesia, which was put into the commercialoperation in June 2000. The turbine is of a singleflash, dual exhaust flow and single casing type. Majorspecifications of the geothermal turbine are as follows:(1) Inlet steam pressure: 1.02MPa(2) Inlet steam temperature: 181°C

Fig.5 Cross section of 110MW geothermal steam turbine forWayang Windu Geothermal Power Plant (Indonesia)

Fig.4 Triple eccentric butterfly valve

Fig.3 Mach number distribution at tip airfoil of LSB

Disk

Seal ring

Sheet

Page 32: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW126

(3) Condenser vacuum: 12kPa(4) Speed: 3,000 r/min(5) Rated output: 110MW

The rated output of 110MW is the largest in theworld for a single casing geothermal steam turbine.Previously, all installed geothermal turbines rated atmore than 100MW had been of the dual casing,tandem compound type.

The advanced LP blades with a 27.4-inch LSBenable the realization of a single casing 110MWgeothermal turbine.

Moving blades in the last 2 stages are freestanding, without lacing wires on the airfoil. Absent ofbosses for lacing wires, the airfoil is free from anystress concentrations and deposits of corrosive compo-nents. Furthermore, the vibration modes of freestanding blades are so simple that natural frequenciesof the blades can be precisely predicted by calculation.As the result, the LP blades can operate withoutlimitation within ±5% of the 50Hz rated frequency.

The blade row is composed of 8 double flow stages.The 1st through 5th stages are equipped with reactionblades with an integral shroud. The blades withintegral shroud are free from any residual stressesthat tend to be generated on riveted shroud blades.This is an advantage of the integral shroud blades.Another advantage of the integral shroud blades istheir good damping characteristics.

The 1st through 5th stage stationary blades areinstalled in a stationary blade holder, which is dividedinto upper and lower halves. The upper and lowerhalves of the stationary blade holders are bolted to therespective upper and lower halves of the outer casing.The upper and lower halves of the stationary bladeholders are also tightened by bolts at the horizontaljoint flange in order to prevent steam leakage anderosion of the horizontal joint flange.

The turbine rotor is of the non-concave, drum type,so that no stress concentrations will be generated. Theshaft is formed from CrMoNiV forged steel, consistingof relatively low nickel content in order to prevent

stress corrosion cracking (SCC). The large inertiaweight of the drum type rotor ensures stable operation.

3.2 Salton Sea 58.32MW geothermal steam turbineFigure 6 shows a cross section of the 58.32MW

geothermal steam turbine for the Salton Sea Unit 5geothermal power plant in the USA, which begancommercial operation in August 2000. The plantemploys a triple flash system, that is, standardpressure steam (SP), low pressure steam (LP) and verylow pressure steam (VLP) are supplied to the steamturbine. The Salton Sea Unit 5 geothermal steamturbine is the first unit having triple inlet pressure.

The plant employs a dual vacuum condenser, inwhich one exhaust pressure differs from that ofanother one.(1) SP steam pressure : 0.86MPa(2) SP steam temperature : 174°C(3) LP steam pressure : 0.367MPa(4) LP steam temperature : 141°C(5) VLP steam pressure : 0.137MPa(6) VLP steam temperature: 110°C(7) High vacuum side exhaust pressure: 9.6kPa(8) Low vacuum side exhaust pressure : 13kPa(9) Speed : 3,600 r/min(10) Rated output: 58.32MW

The SP steam enters the steam turbine from thebottom of the lower half casing through the stop valveand the steam control valve. The LP steam enters theintermediate stage of the steam turbine from bothsides of the lower half casing through two steamcontrol valves branched from a single stop valve. TheVLP steam enters from four inlet ports located on theupper half of both exhaust sides, through four steamcontrol valves branched from two stop valves (Fig. 7).

The SP stop valve is a swing-check-type valve witha 14-inch bore size. The LP and VLP stop valves aretriple eccentric butterfly valves with 44-inch bore sizes.The 44-inch bore size is the largest size in the world forbutterfly valves of geothermal use. The SP steamcontrol valve is a butterfly type valve with a 14-inch

Fig.7 Casing upper half of geothermal steam turbine forSalton Sea U5

Fig.6 Cross section of 58.32MW geothermal steam turbine forSalton Sea U5 (USA)

+-

Page 33: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Recent Technology of Geothermal Steam Turbines 127

bore size, and the LP and VLP steam control valves arebutterfly type valves with 30-inch bore sizes. Duringnormal operation, the SP and VLP steam controlvalves are used to control the corresponding inletsteam pressure, and the LP control valves are used tocontrol the turbine load.

The blade row is composed of 4 single-flow stages,followed by 5 dual-flow stages. The four single-flowstages and the next two dual-flow stages are equippedwith integral shroud blades. The last three stages areequipped with advanced LP blades with a 26.2-inchLSB.

4. Solutions for Decreased Production WellPressure

Geothermal resources generally decline over along-term operation, even when employing a re-injec-tion system in which surplus hot water is injected backto the reservoir underground.

Two solutions where Fuji geothermal steam tur-bines have employed are described below:

4.1 NCPA U2The plant was put into commercial operation in

1983. After more than 10 years of operation, thepressure of the production well had decreased. Origi-nal specifications of the steam turbine are as follows:(1) Inlet steam pressure : 0.799MPa(2) Inlet steam temperature: 169°C(3) Inlet steam flow: 107.65kg/s (NCG content: 0.4%)(4) Condenser vacuum : 10.2kPa(5) Number of blade rows : 2 (flow) × 8 stages(6) Speed : 3,600 r/min(7) Rated output: 55MW

The steam turbine was modified so that thegenerator output can be maintained despite decreasingwell pressure.

Specifications of the steam turbine after modifica-tion are as follows.(1) Inlet steam pressure : 0.572MPa(2) Inlet steam temperature: 157°C(3) Inlet steam flow: 124kg/s (NCG content: 0.4%)(4) Condenser vacuum : 10.2kPa(5) Number of blade rows : 2 (flow) × 8 stages(6) Speed : 3,600 r/min(7) Rated output: 55.6MW

As a result of increasing the steam generation ofthe production well, the generator output of themodified unit became greater than the original output,

despite the pressure decrease.In the re-powering modification, the original tur-

bine casing and the bearing pedestals are used as is,with no modification. The original rotor was employedafter exchanging the blade rows. The 1st through 5thblade rows (double flow) are replaced with new bladerows re-designed conforming in accordance with thespecifications; the remaining LP blade rows of the lastthree stages (L-0 through L-2) are unchanged.

Table 1 shows the major modified and replacementparts.

In this modification, future decreases in the wellpressure was took into account.

The new specifications taken the future decrease inpressure into account are the following:(1) Inlet steam pressure : 0.434MPa(2) Inlet steam temperature: 143°C(3) Inlet steam flow: 124kg/s (NCG content: 0.4%)(4) Condenser vacuum : 10.2kPa(5) Number of blade rows : 2 (flow) × 7 stages(6) Speed : 3,600 r/min(7) Rated output: 51.4MW

The generator output decreases from 55.6MW to51.4MW due to the decreasing pressure of the produc-tion well while the steam generation remains un-changed.

A future modification is simply to remove the 1ststage blade row from the rotor and the casing. Thiscan be performed quickly and at low cost.

4.2 Palimpinon IIFour geothermal steam turbines for Palimpinon II

in the Philippines were put into commercial operationin 1993 and 1994. Palimpinon II consists of NasujiUnit 1, Okoy Unit 1 and Sogongon Units 1 and 2.

Table 2 shows the specifications of these power

Table 1 Renewed and/or re-constructed parts and their detailsfor NCPA U2

Parts Details

Blade 1st to 5th stationary and moving blades, stationary blade rings were renewed.

Rotor The original rotor is applied, being milled for 1st to 5th stage blade root.

Main stop & control valves

Stop valve and steam control valve were replaced.

Steam strainer,inlet steam piping

Replaced steam strainer as well as inlet steam piping with larger size are employed.

Governor An actuator of steam control valves is modified.

Table 2 Major specifications of the geothermal steam turbines in Palimpinon II district

Plant nameItem Rated output

(MW)

Nasuji

Okoy

Sogongon

20

20

20

Number of unit(unit)

1

1

2

Main steampressure (MPa)

0.57

0.77

0.57

Main steamtemperature (°C)

162

174

162

Exhaust steampressure (MPa)

0.0137

0.0127

0.0137

Main steam flow(kg/s)

43.89

40.56

43.89

Number ofstage (stage)

8

9

8

Page 34: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Vol. 47 No. 4 FUJI ELECTRIC REVIEW128

plants.The turbine inlet pressure of Okoy is higher than

that of the other two plants, and the turbine for Okoyhas 1 more stage than the other units.

The design philosophy is to maintain the generatoroutput of Okoy by removing the 1st stage blade row incase there is a future decrease in production wellpressure (Fig. 8).

By removing (machining off) the 1st stage bladerow of the Okoy turbine, the turbine rotor will becommon among these three geothermal power plants.A spare rotor can be used in any of the four units.

4.3 Selection of the appropriate solutionAs described above, two solutions are available to

maintain the generator output in case of a decrease inproduction well pressure, removal of the 1st stage andmodification of the blade rows.

Selection of the appropriate solution depends onthe characteristics of the production well.

Figure 9 shows the pressure versus steam genera-tion in the production well with inlet pressure versussteam flow of the turbine blade rows.

When the pressure versus steam generation char-acteristic of the production well is similar to thatshown in Fig. 9 (a) in which steam generation simplyincreases with decreasing pressure, the large capitalinvestment would pay off due to the increase in outputdespite the decrease in well pressure.

In this case, modification of the blade rows isselected to obtain greater output than that obtained byjust removing the 1st stage.

However, the large capital investment might notpay off if the steam generation increases only moder-ately as the pressure decreases [Fig. 9 (b)]. In such acase, removal of the 1st stage may be selected tomaximize the generator output.

5. Conclusion

Fuji’s geothermal steam turbines have consistentlyevolved through employing state-of-the-art technolo-gies developed for fossil fueled steam turbines as wellas through improvements base on our wealth ofexperience with geothermal steam turbines. Shouldproduction well pressure decrease in the future, twosolutions are available to maintain generator output ofFuji Electric’s geothermal steam turbines.

References(1) Huttrer, G.W. : The Status of World Geothermal Power

Generation 1995-2000, Proc. World Geothermal Con-gress 2000, p. 23-37 (2000)

(2) Kato,Y. et al. : Progress of Geothermal Steam TurbineTechnology, Fuji Electric Review, Vol.42, No.2, p. 45-62(1996)

(3) Murakami, H. et al. : Construction of the LargestGeothermal Power Plant for Wayang Windu Project,Indonesia, Proc. World Geothermal Congress 2000,p. 3239-3244 (2000)

Fig.8 Geothermal steam turbine blade row as well as rotor forPalimpinon II district

Stationary blade holder

Blade row and rotor for Okoy

Blade row and rotor for Nasuji and Sogongon

After removal of the 1st stage

Fig.9 Reduction of production well and pressure characteris-tics of turbine blade row

Ste

am f

low

Ste

am f

low

(a) Pressure of production well

(b) Pressure of production well

Steam generation vs. pressure of the original wellSteam generation vs. pressure of the declined wellPressure characteristics of the original blade rowPressure characteristics of the redesigned or original blade row with removal of 1st stage

: Increase in steam generation: Decrease in pressure

∆ G∆ P

∆ P

∆ G

∆ P

∆ G

Page 35: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

AMERICA

EU

FUJI ELECTRIC CORP. OF AMERICAUSATel : +1-201-712-0555 Fax : +1-201-368-8258

U.S. FUJI ELECTRIC INC.USATel : +1-732-560-9410 Fax : +1-732-457-0042

GE FUJI DRIVES USA, INC.USATel : +1-540-387-5925 Fax : +1-540-387-8580

GE FUJI DRIVES AMERICA S.A. DE C.V.MEXICOTel : +52-8-154-7000 Fax : +52-8-154-7007

FUJI ELECTRIC CO., LTD.Erlangen Representative OfficeF.R. GERMANYTel : +49-9131-729613 Fax : +49-9131-28831

FUJI ELECTRIC GmbHF.R. GERMANYTel : +49-69-6690290 Fax : +49-69-6661020

FUJI ELECTRIC (SCOTLAND) LTD.U.K.Tel : +44-1355-234111 Fax : +44-1355-238810

FUJI ELECTRIC FRANCE S.A.FRANCETel : +33-4-73-98-26-98 Fax : +33-4-73-98-26-99

ASIA

FUJI ELECTRIC CO., LTD.Beijing Representative OfficeTHE PEOPLE

,S REPUBLIC OF CHINA

Tel : +86-10-6505-1263 Fax : +86-10-6505-1851

FUJI ELECTRIC (SHANGHAI) CO., LTD.THE PEOPLE

,S REPUBLIC OF CHINA

Tel : +86-21-6466-2810 Fax : +86-21-6473-3292

FUJI ELECTRIC DALIAN CO., LTD.THE PEOPLE

,S REPUBLIC OF CHINA

Tel : +86-411-762-2000 Fax : +86-411-762-2030

SHANDONG LUNENG FUJI ELECTRIC CO., LTD.THE PEOPLE

,S REPUBLIC OF CHINA

Tel : +86-531-723-1138 Fax : +86-531-726-1737

SHANGHAI FUJI ELECTRIC SWITCHGEAR CO., LTD.THE PEOPLE

,S REPUBLIC OF CHINA

Tel : +86-21-5718-5741 Fax : +86-21-5718-1448

SHANGHAI FUJI ELECTRIC TRANSFORMER CO., LTD.THE PEOPLE

,S REPUBLIC OF CHINA

Tel : +86-21-5718-5746 Fax : +86-21-5718-5745

SHANGHAI GENERAL FUJI REFRIGERATION EQUIPMENT CO., LTD.THE PEOPLE

,S REPUBLIC OF CHINA

Tel : +86-21-6921-1088 Fax : +86-21-6921-1066

FUJI GE DRIVES (WUXI) CO., LTD.THE PEOPLE

,S REPUBLIC OF CHINA

Tel : +86-510-521-7932 Fax : +86-510-521-5052

HONG KONG FUJIDENKI CO., LTD.HONG KONGTel : +852-2664-8699 Fax : +852-2664-8040

FUJI ELECTRIC (ASIA) CO., LTD.HONG KONGTel : +852-2311-8282 Fax : +852-2312-0566

FUJI ELECTRIC CO., LTD.Taipei Representative OfficeTAIWANTel : +886-2-2561-1255 Fax : +886-2-2561-0528

FUJI ELECTRIC TAIWAN CO., LTD.TAIWANTel : +886-2-2515-1850 Fax : +886-2-2515-1860

FUJI/GE TAIWAN CO., LTD.TAIWANTel : +886-2-2556-0716 Fax : +886-2-2556-0717

ATAI FUJI ELECTRIC CO., LTD.TAIWANTel : +886-3-358-5000 Fax : +886-3-356-4359

FUJI ELECTRIC KOREA CO., LTD.KOREATel : +82-2-780-5011 Fax : +82-2-783-1707

: Representative Office : Sales Bases : Manufacturing Bases

Global Network

East Asia Southeast Asia

FUJI ELECTRIC CO., LTD.Bangkok Representative OfficeTHAILANDTel : +66-2-653-2020, 2021 Fax : +66-2-653-2022

FUJI ELECTRIC (MALAYSIA) SDN. BHD.MALAYSIATel : +60-4-403-1111 Fax : +60-4-403-1491

FUJI ELECTRIC PHILIPPINES, INC.PHILIPPINESTel : +63-2-844-6183 Fax : +63-2-844-6196

P. T. BUKAKA FUJI ELECTRICINDONESIATel : +62-21-572-4281 Fax : +62-21-572-4283

P. T. FUJI DHARMA ELECTRICINDONESIATel : +62-21-4606247 Fax : +62-21-4610338

FUJI ELECTRIC SINGAPORE PRIVATE LTD.SINGAPORETel : +65-479-5531 Fax : +65-479-5210

FUJI/GE PRIVATE LTD.SINGAPORETel : +65-533-0010 Fax : +65-533-0021

Page 36: Geothermal Power Generation - Fuji · PDF file110MW geothermal steam turbine, the world’s largest ... To minimize the onsite installation work, steam turbines and generators in the

Printed on recycled paper