Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
GEOTECHNICAL INVESTIGATION REPORT
BASEMENT FLOODING PROTECTION PROGRAM PHASE 4 (BFPP4)
ASSIGNMENT 16-12 AND ASSIGNMENT 16-22
TORONTO, ONTARIO
Submitted to:
CIMA CANADA INC.
5935 Airport Road, Suite 500
Mississauga, Ontario, L4V 1W5
Submitted by:
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited
50 Vogell Road, Unit Nos. 3 & 4
Richmond Hill, Ontario
L4B 3K6
19 March 2019
Wood Reference Number: TT183004
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited
50 Vogell Road, Units No. 3 & 4
Richmond Hill, Ontario
Canada L4B 3K6
Tel (905) 415-2632
Fax (647) 689-4876
www.woodplc.com
19 March 2019
Wood Reference Number: TT183004
CIMA Canada Inc.
5935 Airport Road, Suite 500
Mississauga, Ontario, L4V 1W5
Dear Mr. Hutu:
RE: GEOTECHNICAL INVESTIGATION REPORT
BASEMENT FLOODING PROTECTION PROGRAM PHASE 4 (BFPP4)
ASSIGNMENT 16-12 AND ASSIGNMENT 16-22
TORONTO, ONTARIO
Wood Environment & Infrastructure Solutions, a Division of Wood Canada Limited (hereinafter referred to
as Wood), is a leading environment and infrastructure, engineering, consulting and project management
organization. Our team of professionals provides a full range of services to clients in a wide range of
sectors including government, industrial & commercial, water, transportation, minerals & metals, oil & gas
clients and clean energy. Environment and Infrastructure’s core competencies are in environmental
assessments, health and environmental risk assessment, environmental geology (site investigation),
remediation engineering, geotechnical engineering and testing, and water resource services.
We take pleasure in enclosing a copy of our Geotechnical Investigation Report (final) carried out for the
above-mentioned project. The final report submitted herein has incorporated CIMA+’s comments on the
draft report.
We thank you for giving us this opportunity to be of service to you.
Yours truly,
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited
FINAL
Todd Williams, B.Eng., M. A. Sc., P. Eng.,
Associate Geotechnical Engineer/Geotechnical Team Lead
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page i
TABLE OF CONTENTS
PAGE
1.0 INTRODUCTION .................................................................................................................................... 1
2.0 PROJECT OVERVIEW ............................................................................................................................ 2
3.0 INVESTIGATION PROCEDURES .......................................................................................................... 3
3.1 Field Investigation ............................................................................................................................................... 3
3.2 Geotechnical Laboratory Testing .................................................................................................................. 5
3.3 Soil Corrosivity Analysis .................................................................................................................................... 5
3.4 Soil Chemical Quality for Reuse and / or Disposal ................................................................................ 5
4.0 GEOTECHNICAL CONSIDERATION FOR ASSIGNMENT 16-12 ....................................................... 7
4.1 Project Description ............................................................................................................................................. 7
4.2 Investigation Program ....................................................................................................................................... 8
4.3 Subsurface Conditions ...................................................................................................................................... 8
4.3.1 Ground Cover ....................................................................................................................................... 9
4.3.2 Fill Soils ................................................................................................................................................... 9
4.3.3 Organic Silty Clay .............................................................................................................................10
4.3.4 Sandy Silty Clay / Sandy Clayey Silt Till ...................................................................................10
4.3.5 Sandy Silt / Sand and Silt Till .......................................................................................................11
4.4 Groundwater Conditions ................................................................................................................................12
4.5 Asphaltic Concrete Cores ...............................................................................................................................13
4.6 Discussions and Recommendations ..........................................................................................................13
4.6.1 Subsurface Conditions at Sewer / Maintenance Hole Inverts ........................................14
4.6.2 Foundations for Maintenance Holes ........................................................................................14
4.6.3 Soil Corrosivity Analysis .................................................................................................................15
4.6.4 Construction Dewatering ..............................................................................................................16
5.0 GEOTECHNICAL CONSIDERATION FOR ASSIGNMENT 16-22 ..................................................... 17
5.1 Project Description ...........................................................................................................................................17
5.1.1 Sewer Re-construction ...................................................................................................................17
5.1.2 Roding Park – Storm Sewer and Headwalls ...........................................................................18
5.2 Investigation Program .....................................................................................................................................19
5.3 Subsurface Conditions ....................................................................................................................................20
5.3.1 Ground Cover .....................................................................................................................................20
5.3.2 Fill Soils .................................................................................................................................................20
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page ii
5.3.3 Clayey Silt / Silty Clay / Silt and Clay ........................................................................................21
5.3.4 Sandy Silty Clay / Sandy Clayey Silt Till ...................................................................................22
5.3.5 Sand and Silt Till ...............................................................................................................................24
5.3.6 Sand .......................................................................................................................................................24
5.4 Groundwater Conditions ................................................................................................................................25
5.5 Asphaltic Concrete Cores ...............................................................................................................................26
5.6 Discussions and Recommendations ..........................................................................................................28
5.6.1 Subsurface Conditions at Sewer Inverts ..................................................................................28
5.6.2 Foundations for Maintenance Holes ........................................................................................29
5.6.3 Soil Corrosivity Analysis .................................................................................................................31
5.6.4 Construction Dewatering ..............................................................................................................33
5.7 Slope Stability Analyses for Slopes at Headwalls .................................................................................33
5.7.1 Slope Conditions Considered in Analyses ..............................................................................33
5.7.2 Soil Parameters for Analyses ........................................................................................................34
5.7.3 Results of Slope Stability Analyses – South Headwalls .....................................................35
5.7.4 Results of Slope Stability Analyses – North Headwall .......................................................36
5.7.5 Conclusions and Recommendations ........................................................................................37
6.0 GENERAL DESIGN AND CONSTRUCTION CONSIDERATIONS ..................................................... 38
6.1 Site Preparation .................................................................................................................................................38
6.2 Engineered Fill ....................................................................................................................................................39
6.3 Open Cut Installation Method .....................................................................................................................39
6.3.1 Open Cut Excavation .......................................................................................................................39
6.3.2 Temporary Shoring ..........................................................................................................................40
6.3.3 Pipe Bedding ......................................................................................................................................40
6.3.4 Anti-Seepage Collars ......................................................................................................................41
6.4 Excavation Backfill .............................................................................................................................................41
6.5 Trenchless Considerations .............................................................................................................................42
6.6 Foundations .........................................................................................................................................................42
6.7 General Construction Dewatering Considerations ..............................................................................43
6.8 Earthquake Considerations ...........................................................................................................................44
6.9 Pavement Structure ..........................................................................................................................................44
7.0 ENVIRONMENTAL SOIL QUALITY ASSESSMENT ........................................................................... 44
7.1 Methodology ......................................................................................................................................................44
7.2 Regulatory Framework ....................................................................................................................................45
7.3 Field and Soil Analytical Results, Assignment 16-12 ...........................................................................45
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page iii
7.3.1 Metals and Inorganics ....................................................................................................................46
7.3.2 Petroleum Hydrocarbons Fractions (PHC F1-F4) and BTEX .............................................47
7.3.3 Volatile Organic Compounds (VOCs) .......................................................................................47
7.3.4 Polycyclic Aromatic Hydrocarbons (PAHs) .............................................................................47
7.3.5 Polychlorinated Biphenyls (PCBs) ...............................................................................................47
7.3.6 Organochlorine Pesticides ............................................................................................................47
7.3.7 Regulation 347 Waste Characterization ..................................................................................47
7.4 Field and Soil Analytical Results, Assignment 16-22 ...........................................................................47
7.4.1 Metals and Inorganics ....................................................................................................................48
7.4.2 Petroleum Hydrocarbons Fractions (PHC F1-F4) and BTEX .............................................49
7.4.3 Volatile Organic Compounds (VOCs) .......................................................................................49
7.4.4 Polycyclic Aromatic Hydrocarbons (PAHs) .............................................................................49
7.4.5 Polychlorinated Biphenyls (PCBs) ...............................................................................................49
7.4.6 Organochlorine Pesticides ............................................................................................................49
7.4.7 Regulation 347 Waste Characterization ..................................................................................49
7.5 Quality Assurance Program...........................................................................................................................49
7.6 Conclusions and Recommendations .........................................................................................................50
8.0 BULK ASBESTOS ANALYSES .............................................................................................................. 51
8.1 Scope of Work ....................................................................................................................................................51
8.2 Methodology ......................................................................................................................................................51
8.3 Summary of Results .........................................................................................................................................52
8.4 Discussion and Conclusions ..........................................................................................................................55
8.4.1 Assignment 16-12 ............................................................................................................................55
8.4.2 Assignment 16-22 ............................................................................................................................55
9.0 CLOSURE .............................................................................................................................................. 56
LIMITATIONS TO GEOTECHNICAL REPORTS
LIST OF TABLES
Table 4.1: Details of Proposed Work along Gracefield Avenue, Keele Street and Queen’s Greenbelt
(Assignment 16-12) .................................................................................................................................................. 7
Table 4.2: Borehole and Monitoring Well Locations (Assignment 16–12) ..................................................................... 8
Table 4.3: Results of Grain Size Distribution Analyses and Atterberg Limit Tests, Sandy Silty Clay
Till (Assignment 16-12) .........................................................................................................................................10
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page iv
Table 4.4: Results of Grain Size Distribution Analyses and Atterberg Limit Tests
Sandy Clayey Silt Till (Assignment 16-12) .....................................................................................................11
Table 4.5: Results of Grain Size Distribution Analyses and Atterberg Limit Tests
Sandy Silt / Sand and Silt Till (Assignment 16-12) .....................................................................................12
Table 4.6: Groundwater Level Measurement in Monitoring Wells (Assignment 16-12) ........................................12
Table 4.7: Asphaltic Concrete Core Thickness and Locations (Assignment 16–12) .................................................13
Table 4.8: Founding Stratum and Soil Bearing Capacity for Maintenance Hole (MH) Foundations
(Assignment 16–12) ................................................................................................................................................15
Table 4.9: Summarized Soil Corrosivity Test Results (Assignment 16–12)...................................................................15
Table 5.1: Details of Proposed Works along Ianhall Road, Gade Drive, Roding Street, Nash Drive,
Bunnell Crescent, Hallsport Crescent and Dorking Crescent (Assignment 16-22) ........................17
Table 5.2: Details of Proposed Works in Roding Park (Assignment 16-22) ................................................................18
Table 5.3: Borehole and Monitoring Well Locations (Assignment 16–22) ...................................................................19
Table 5.4: Results of Grain Size Distribution Analysis, Sand Fill (Assignment 16–22) .............................................21
Table 5.5: Results of Grain Size Distribution Analyses and Atterberg Limit Tests
Clayey Silt / Silty Clay / Silt and Clay (Assignment 16–22)......................................................................22
Table 5.6: Results of Grain Size Distribution Analyses and Atterberg Limit Tests, Sandy Silty Clay
Till (Assignment 16–22) .........................................................................................................................................22
Table 5.7: Results of Grain Size Distribution Analyses and Atterberg Limit Tests,
Sandy Clayey Silt Till (Assignment 16–22) .....................................................................................................23
Table 5.8: Results of Grain Size Distribution Analyses, Sand and Silt Till (Assignment 16–22) ...........................24
Table 5.9: Results of Grain Size Distribution Analyses, Sand (Assignment 16–22) ...................................................25
Table 5.10: Groundwater Level Measurement in Monitoring Wells (Assignment 16-22) ......................................25
Table 5.11: Asphaltic Concrete Core Thickness and Locations (Assignment 16–22) ...............................................26
Table 5.12: Founding Stratum and Soil Bearing Capacity for Maintenance Hole (MH) Foundations
(Assignment 16–22) ................................................................................................................................................29
Table 5.13: Summarized Soil Corrosivity Test Results (Assignment 16–22) ................................................................32
Table 5.14: Soil Parameters for Slope Stability Analyses, Roding Park (Assignment 16-22) ................................35
Table 5.15: Calculated Minimum Safety Factors against Slope Instability – South Headwall
Roding Park (Assignment 16-22) ......................................................................................................................36
Table 5.16: Calculated Minimum Safety Factors against Slope Instability – North Headwall
Roding Park (Assignment 16-22) ......................................................................................................................37
Table 8.1: Asbestos Bulk Sampling Analytical Results (Assignment 16-12) ................................................................52
Table 8.2: Asbestos Bulk Sampling Analytical Results (Assignment 16-22) ................................................................53
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page v
LIST OF FIGURES
Figure 1: Site Location Plan, Assignment 16-12 and Assignment 16-22
Figure 2: Borehole Location Plan, Assignment 16-12
Figure 3: Borehole Location Plan, Assignment 16-22
Figure 4.1: Slope Stability Analysis for Proposed South Headwall (BH 16 Location)
Case 1 – End of Construction, Measured Groundwater Level (El. 152.3 m)
Figure 4.2: Slope Stability Analysis for Proposed South Headwall (BH 16 Location)
Case 2 – During Service, Assumed Groundwater Level (El. 157.5 m)
Figure 4.3: Slope Stability Analysis for Proposed South Headwall (BH 16 Location)
Case 3 – Rapid Drawdown from 100-year Flood Level (El. 158.49 m)
Figure 5.1: Slope Stability Analysis for Existing Slope (BH 37 Location)
Case 1 – Effective Stress Analysis
Figure 5.2: Slope Stability Analysis for Existing Slope (BH 37 Location)
Case 2 – Total Stress Analysis
Figure 5.3: Slope Stability Analysis for Proposed North Headwall (BH 37 Location)
Case 3 – End of Construction, Backfill Trench with Engineered Fill, Dry Condition
Figure 5.4: Slope Stability Analysis for Proposed North Headwall (BH 37 Location)
Case 4 – During Service, Backfill Trench with Engineered Fill, Assumed Groundwater Level (El.
162.0 m)
Figure 5.5: Slope Stability Analysis for Proposed North Headwall (BH 37 Location)
Case 5 – During Service, Backfill Trench with Engineered Fill, Dry Condition
RECORD OF BOREHOLES
EXPLANATION OF BOREHOLE LOGS
RECORD OF BOREHOLES (BH 1 TO BH 37)
LIST OF APPENDICES
Appendix A1: Soil Laboratory Test Results, Assignment 16-12
Appendix A2: Soil Laboratory Test Results, Assignment 16-22
Appendix B1: Asphaltic Concrete Core Photographs, Assignment 16-12
Appendix B2: Asphaltic Concrete Core Photographs, Assignment 16-22
Appendix C: Drawing Nos. 17-03309-029 and 17-03309-030, Roding Park, Assignment 16-22
Appendix D: Existing Slope Photographs, Assignment 16-22
Appendix E1: Soil Corrosivity Analysis Results, Assignment 16-12
Appendix E2: Soil Corrosivity Analysis Results, Assignment 16-22
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page vi
Appendix F1: Tables 1 to 5: Analytical Results for Soil, Assignment 16-12
Appendix F2: Tables 1 to 5: Analytical Results for Soil, Assignment 16-22
Appendix G1: Table 6: Ontario Regulation 347/90 for Leachate Analyses, Waste Classification and Other
Analyses, Assignment 16-12
Appendix G2: Table 6: Ontario Regulation 347/90 for Leachate Analyses, Waste Classification and Other
Analyses, Assignment 16-22
Appendix H: Soil Certificate of Analyses, Assignment 16-12 and Assignment 16-22
Appendix I1: Laboratory QA/QC Review and Checklists, Soil Analytical Results, Assignment 16-12
Appendix I2: Laboratory QA/QC Review and Checklists, Soil Analytical Results, Assignment 16-22
Appendix J Asbestos Laboratory Analysis Reports, Assignment 16-12 and Assignment 16-22
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 1
1.0 INTRODUCTION
Wood Environment & Infrastructure Solutions, a Division of Wood Canada Limited (“Wood”), was retained
by CIMA Canada Inc. (“CIMA+”) on behalf of the City of Toronto to conduct a geotechnical investigation
for the “Basement Flooding Protection Program Phase 4 (BFPP4) project – Assignment 16-12 and
Assignment 16-22” under the City of Toronto’s RFP 9117-16-7066 as shown in Figure 1.
The City of Toronto (“City”) is planning to upgrade sections of the existing storm sewers and sanitary
sewers by installing additional or larger sewers in identified areas subject to potential basement flooding
throughout the City under the City’s Basement Flooding Protection Program (BFPP). The project
considered herein is to be carried out as BFPP4 Assignment 16-12 (which consists of sections of Gracefield
Avenue, Keele Street, and Queen’s Greenbelt); and Assignment 16-22 (which comprises Roding Street,
Gade Drive, Ianhall Road, Nash Drive, Bunnell Crescent, Hallsport Crescent, Dorking Crescent and Roding
Park) in the City of Toronto.
The purpose of the geotechnical investigation was to obtain information on sub-surface conditions by
means of a limited number of boreholes and, based on the results of the boreholes drilled within the
project limits, to provide recommendations on the geotechnical design aspects for the project.
Authorization to proceed with this investigation was received via e-mail from Mr. Alin Hutu of CIMA+ on
13 July 2018. The work carried out for this investigation was completed in accordance with CIMA+’s
Purchase Order B2018-002331 and Wood’s proposal P18033 Rev2 dated 12 April 2018. One additional
borehole at the proposed headwall location within Roding Park was approved by Mr. Alin Hutu and the
City on 4 October 2018, and the corresponding change order was issued on 12 October 2018.
This report contains the finding of geotechnical investigation, hydrogeological investigation and
environmental assessment for soil disposal, together with relevant recommendations and comments.
The recommendations and comments provided herein are based on factual information and are intended
only for Design Engineers’ use. The number of boreholes may not be sufficient to determine all the
factors that may affect construction methods and costs. Sub-surface and groundwater conditions
between and beyond the boreholes may differ from those encountered at the borehole locations, and
different conditions may become apparent during construction, which could not be detected at the time
of the site investigation.
The construction conditions are also discussed, but only to the extent that they will likely influence design
decisions. Construction methods discussed, however, express Wood’s opinion only and are not intended
to direct Contractors on how to carry out the construction. Contractors should be aware that the data
and their interpretation presented in this report may not be sufficient to assess all the factors that may
have an effect upon the construction.
Once the details of the proposed works are finalized, on-going liaison with Wood is recommended during
both the design and construction phases of the project to confirm that the recommendations in this
report are applicable and/or correctly interpreted and implemented. Also, any queries concerning the
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 2
geotechnical aspects of the proposed project should be directed to Wood for further elaboration and/or
clarification.
The report is prepared with the conditions that the design and construction will be in accordance with all
applicable standards, codes, regulations of authorities having jurisdiction, and carried out using good
engineering practices. Further, the recommendations and opinions in this report are applicable only to
the proposed project as described herein.
The enclosed Limitations to Geotechnical Reports are integral part of this report.
2.0 PROJECT OVERVIEW
The project includes two Assignments 16-12 and 16-22 sites as shown in Figure 1. For Assignment 16-12
(Figure 2), the project involves road resurfacing, sanitary maintenance hole sealing and storm sewer re-
construction along Gracefield Avenue; and storm sewer re-construction along Keele Street and Queen’s
Greenbelt. As for Assignment 16-22 (Figure 3), the project comprises storm sewer and sanitary sewer re-
construction along Roding Street, Gade Drive, Ianhall Road, Nash Drive, Bunnell Crescent, Hallsport
Crescent, and Dorking Crescent, together with stormwater facility work in Roding Park.
The surrounding land use includes residential dwellings, commercial establishments and a park. The
ground surfaces of both sites are relatively flat, except the west of Roding Street (sloping downward
toward Roding Park) which is located adjacent to a slope of up to 10 m in height.
Based on the preliminary design drawings, the stormwater collected within the Assignment 16-22 area will
be discharged to Roding Park through a storm sewer leading to Roding Street and a proposed headwall
("north headwall)" to replace an existing headwall at the slope toe. Near the south end of Roding Park,
two proposed headwalls ('south headwalls") will be constructed, one at each end of a proposed 450 mm
diameter concrete storm sewer crossing underneath the proposed asphalt walkway embankment.
Based on Map 2556 ‘Quaternary Geology of Ontario, Southern Sheet’ prepared by the Ministry of
Northern Development and Mines of Ontario (1991), and Map P. 2204 ‘Quaternary Geology, Toronto and
Surrounding Area, Southern Ontario’ prepared by the Ministry of Natural Resources (MNR) (1990), the
Assignment 16-12 site and most of Assignment 16-22 site are covered by Halton Till which is
characterized by silt to silty clay till, overlying silty/sandy deposits. Roding Park within the Assignment 16-
22 site is covered by modern deposits featured by sand, silt, minor gravel and organic material.
Based on Map 2544 ‘Bedrock Geology of Ontario, Southern Sheet’ prepared by the Ministry of Northern
Development and Mines of Ontario (1991), the bedrock underlying the overburden at both sites is the
Georgian Bay Formation, which comprises shale, dolostone, interbedded siltstone and minor limestone.
The bedrock surface elevations range approximately from 105 m to 137 m (about 40 m to 70 m deep at
the sites), according to Preliminary Map 102 ‘Metropolitan Toronto Bedrock Contours’ prepared by
Ontario Department of Mines (1961).
The investigation programs implemented to obtain geotechnical data for both assignments are described
in Section 3.0; the specific proposed works and sub-surface information for each assignment are
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 3
described in Section 4.0 for Assignment 16-12 and Section 5.0 for Assignment 16-22; general design and
construction considerations that are common to the two assignments are provided in Section 6.0; the soil
chemical analyses are discussed in Section 7.0; and asbestos analyses in the asphaltic core samples are
discussed in Section 8.0.
3.0 INVESTIGATION PROCEDURES
3.1 Field Investigation
The fieldwork was carried out from 10 September 2018 to 21 November 2018. A total of thirty-seven (37)
boreholes (BH 1 to BH 37 as shown in Figures 2 and 3) were advanced along the following road sections:
Assignment 16-12:
• Gracefield Avenue: Boreholes BH 1 to BH 11
• Keele Street: Boreholes BH 12 and BH 13,
• Queen’s Greenbelt: Borehole BH 14, and
• North Park: BH 15.
Assignment 16-22:
• Ianhall Road: Borehole BH 18
• Gade Drive: Borehole BH 19
• Roding Street: Boreholes BH 20 and BH 21
• Nash Drive: Boreholes BH 22 to BH 25
• Bunnell Crescent: Boreholes BH 26 to BH 28
• Hallsport Crescent: Boreholes BH 29 to BH 32
• Dorking Crescent: Boreholes BH 33 to BH 36, and
• Roding Park: Boreholes BH 16, BH 17 and BH 37.
Borehole drilling was conducted by Drilltech Drilling Limited using a truck-mounted rig equipped with
solid stem auger on most road sections and a low track-mounted rig in the parks and on the road
sections with overhead wire constraint. The drilling activities were under full-time oversight of
geotechnical engineers from Wood, who also logged the soil types encountered during borehole
advancement and collected soil samples.
Soil samples in boreholes were collected during Standard Penetration Testing (SPT). The SPT sampling
consisted of freely dropping a 63.5 kg (140 lb) hammer for a vertical distance of 0.76 m (30 inches) to
drive a 50 mm (2 inch) diameter O.D. split-barrel (split spoon) sampler into the ground. The number of
blows of the hammer required to drive the sampler into the relatively undisturbed ground by a vertical
distance of 0.30 m (12 inches) was recorded as SPT ‘N’ value of the soil which indicated the compactness
of cohesionless soils or implied the consistency of cohesive soils. The results of SPT are shown in the
Record of Boreholes.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 4
Soil samples were visually classified in the field and later in Wood’s Richmond Hill laboratory based on
laboratory test results.
Boreholes not selected for monitoring well installation were backfilled as per the requirements of O. Reg.
903.
A total of fourteen (14) monitoring wells (as indicated in Figures 2 and 3) were installed in selected
boreholes using 50 mm diameter PVC pipe. The screen lengths were 1.5 m to 3.0 m. The base of each
monitoring well was covered with a PVC cap to prevent the influx of sediment. Clean sand was placed in
the annular space between the pipe and the borehole wall. The monitoring wells were constructed in
accordance with Ontario Regulation 903 (amended by O. Reg. 372/07) by extending a bentonite layer
from approximately 0.6 m above the screen interval to the ground surface. All the monitoring wells were
completed with protective flushmount covers at the ground surface, except one monitoring well located
in Roding Park which was protected by an above-ground protective casing. The monitoring well
construction details and groundwater level readings are presented on the Record of Boreholes, and
summarized in Section 4.0 for Assignment 16-12 and Section 5.0 for Assignment 16-22.
The groundwater conditions in the open boreholes were monitored throughout the drilling operations.
After completion of the monitoring well installation, groundwater levels were measured in one (1) site
visit.
The fieldwork also included retrieving a total of forty-two (42) asphaltic core samples, of which ten (10)
were collected from the Assignment 16-12 site and thirty-two (32) were collected from the Assignment
16-22 site. The asphaltic core samples were submitted under the chain of custody protocol to EMC
Scientific Inc. (“EMC”) in Mississauga, Ontario to determine any asbestos content by following the
polarized light microscopy (PLM) methodology (EPA/600/R-93/116). Each core sample was inspected by
EMC staff to determine if it consisted of multiple, distinct layers or was a single, consolidated material.
As part of the geotechnical investigation, the coordinates and geodetic elevations for the as-drilled
borehole locations were surveyed by Mandarin Surveyor Limited, a professional surveyor company, using
R10 Trimble GPS for both coordinates and elevations. For the vertical datum, Geoid model HTv2.0 was
used.
For the boreholes within Assignment 16-12, horizontal coordinates were M.T.M. Grid derived from the
Horizontal Control Points 020690127 and 020740634, M.T.M. Zone 10, NAD27 (TOR_H-1974):
020690127: Northing: 4841117.736; Easting: 306473.391
020740634: Northing: 4840921.490; Easting: 305785.820
Elevations surveyed were Geodetic with reference to Benchmark NY19033 (as shown on Figure 2),
with the elevation of 164.655 m.
For the boreholes within Assignment 16-22, Horizontal coordinates were M.T.M. Grid derived from the
Horizontal Control Points 020680366 and 020774515, M.T.M. Zone 10, NAD27 (TOR_H-1974):
020680366: Northing: 4842877.824; Easting: 305475.877
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 5
020774515: Northing: 4843085.339; Easting: 305741.526
Elevations surveyed were Geodetic with reference to Benchmark NY22022 (as shown on Figure 3),
with the elevation of 177.772 m.
Borehole locations are shown on Borehole Location Plan (Figure 2 for Assignment 16-12 and Figure 3 for
Assignment 16-22), and tabulated in Section 4.0 for Assignment 16-12 and Section 5.0 for Assignment 16-
22.
3.2 Geotechnical Laboratory Testing
Soil samples collected were transported to Wood’s Advanced Soil Laboratory in Richmond Hill, where they
were re-examined and representative samples were selected for geotechnical testing. The testing program
consisted of the measurement of natural water content (ASTM D-2216) of all samples, grain size
distribution analysis (ASTM D-6913 and ASTM D-7928) of fifty-three (53) selected samples, and Atterberg
limit tests (ASTM D-4318) on forty-nine (49) cohesive soil samples. The soil laboratory test results are
shown on Record of Boreholes and summarized in Sections 4.0 and 5.0.
3.3 Soil Corrosivity Analysis
A total of fifteen (15) soil samples at or near the proposed sewer invert depths were selected for
corrosivity analysis (pH, Chloride, Sulphate, Resistivity and Conductivity) to determine the soil corrosivity
potential with respect to concrete and steel. The results of the corrosivity analysis are summarized in
Section 4.0 for Assignment 16-12 and Section 5.0 for Assignment 16-22.
3.4 Soil Chemical Quality for Reuse and / or Disposal
Assignment 16-12
Soil samples for Assignment 16-12 were collected from nine (9) of the fifteen (15) borehole locations for
the preliminary assessment of soil chemical quality for the potential on-site reuse or off-site
management/disposal purposes. The soil samples were submitted for laboratory analysis of the following
chemical parameters:
• Nine (9) soil samples were analyzed for selected metals and general inorganics including pH, sodium
adsorption ratio (SAR), electrical conductivity (EC), and free cyanide;
• Nine (9) soil samples were analyzed for petroleum hydrocarbons Fractions 1 to 4 (PHC F1-F4) and
benzene, toluene, ethylbenzene, and xylenes (BTEX);
• Five (5) soil samples were analyzed for volatile organic compounds (VOCs) and polycyclic aromatic
hydrocarbons (PAHs);
• Three (3) soil samples were analyzed for polychlorinated biphenyls (PCBs);
• One (1) soil sample was analyzed for organochlorine (OC) pesticides; and
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 6
• Two (2) soil samples were submitted for chemical analyses of Regulation 347 as amended leachate
parameters including: metals and inorganics, VOCs, benzo(a)pyrene, and PCBs; and flammability and
ignitability. The tests were conducted for waste characterization purposes.
Assignment 16-22
Soil samples for Assignment 16-22 were collected from eleven (11) of the twenty-two (22) borehole
locations for the preliminary assessment of the soil quality for the potential on-site reuse or off-site
management/disposal purposes. The soil samples were submitted for laboratory analysis of the following
chemical parameters:
• Eleven (11) soil samples, plus two (2) field duplicate samples for Quality Assurance/Quality Control
(QA/QC) purposes, were analyzed for selected metals and general inorganics including pH, sodium
adsorption ratio (SAR), electrical conductivity (EC), and free cyanide;
• Eleven (11) soil samples, plus two (2) field duplicate samples for QA/QC purposes, were analyzed for
petroleum hydrocarbons Fractions 1 to 4 (PHC F1-F4) and benzene, toluene, ethylbenzene, and xylenes
(BTEX);
• Six (6) soil samples were analyzed for volatile organic compounds (VOCs) including BTEX and
polycyclic aromatic hydrocarbons (PAHs);
• Seven (7) soil samples, plus one (1) field duplicate sample for QA/QC purposes, were analyzed for
polychlorinated biphenyls (PCBs);
• Three (3) soil samples, plus one (1) field duplicate for QA/QC purposes, were analyzed for
organochlorine (OC) pesticides; and
• Three (3) soil samples were submitted for chemical analyses of Regulation 347 as amended leachate
parameters including: metals and inorganics, VOCs, benzo(a)pyrene, and PCBs; and, flammability and
ignitability. The tests were conducted for waste characterization purposes.
Selected soil samples were submitted to Maxxam Laboratories in Mississauga, Ontario, a member of the
Canadian Association for Laboratory Accreditation Inc. (CALA) that meets the requirements of certifying
that the analytical laboratory be accredited in accordance with the International Standard ISO/IEC
17025:2005 and with standards developed by the Standards Council of Canada.
The excess soils generated during borehole drilling operations were temporarily stored in environmental
drums within the two sites and later disposed offsite after waste characterization test (TCLP) results were
available. The receiving disposal site was determined based on the results of the waste characterization
tests.
The results of the soil chemical analyses are discussed in Section 7.0.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 7
4.0 GEOTECHNICAL CONSIDERATION FOR ASSIGNMENT 16-12
4.1 Project Description
Based on the preliminary design Drawings 18-01231-001 to 18-01231-008 dated 14 December 2017
provided by CIMA+, the proposed works for Assignment 16-12 will involve road resurfacing along
Gracefield Avenue and storm sewer re-construction at Gracefield Avenue, Keele Street and Queen’s
Greenbelt. All the proposed storm sewers will be concrete pipes with diameter ranging from 750 mm to
2400 mm.
The proposed storm sewers will be 900 mm in diameter and 82.5 m long at Gracefield Avenue, connecting
to the proposed storm sewer (900 mm to 750 mm in diameter and 94.5 m in length) at the proposed MH
KS1 The proposed storm sewer at Queen’s Greenbelt will be 2400 mm in diameter and 97.8 m in length,
starting from the existing headwall located at about 35 m east of Keele Street, to MH KS2 on Keele Street
and along Queen's Greenbelt.
Based on the above mentioned drawings, the proposed works will involve the installation / replacement
of various underground utilities (sewers and maintenance holes) to the invert depths ranging from about
4.5 m to 13.3 m below the existing ground surfaces throughout the Assignment 16-12 site. The details of
the proposed works for Assignment 16-12 are summarized in Tables 4.1.
Table 4.1: Details of Proposed Work along Gracefield Avenue, Keele Street and Queen’s Greenbelt
(Assignment 16-12)
Proposed
Work
Location
From To Type of Utility
Utility
Diameter/Size
(mm)
Approximate
Utility Depth
(m)
Approximate
Utility Length
(m)
Gracefield
Avenue MH GA1 Keele Street
Storm Sewer 900 4.3 82.5
Maintenance
Hole (MH GA1) 1,800 4.5 –
Keele
Street
MH KS1
near
Gracefield
Avenue
MH KS2 on
Keele Street
Storm Sewer 900 – 1,050 7.0 – 7.9 94.5
Maintenance
Hole (MH KS1
and MH KS2)
2,400 – 3,600 7.3 – 13.3 –
Queen’s
Greenbelt
35 m east
of Keele
Street
80 m west of
Keele Street
Storm Sewer 2,400 13.3 97.8
Maintenance
Hole (MH KS2) 3,600 13.3 –
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 8
4.2 Investigation Program
Borehole and monitoring well details for Assignment 16-12 are shown on Borehole Location Plan (Figure
2); Record of Boreholes and Table 4.2. The investigation procedures are described in Section 3.0.
Table 4.2: Borehole and Monitoring Well Locations (Assignment 16–12)
Borehole
Location
Borehole
No. Drilling Date Easting Northing
Ground
Elevation
(m)
Borehole
Depth
(m)
Monitoring Well
Screen Depth
(m)
Gracefield
Avenue
BH 1 Sep. 10, 2018 305645 4840891 142.1 4.3 No well
BH 2 Sep. 10, 2018 305710 4840908 144.4 3.7 No well
BH 3 Sep. 10, 2018 305795 4840933 148.5 3.7 No well
BH 4 Sep. 10, 2018 305877 4840961 151.4 3.7 No well
BH 5 Sep. 10, 2018 305940 4840980 153.5 3.7 No well
BH 6 Sep. 10, 2018 306013 4841002 155.8 3.7 No well
BH 7 Sep. 10, 2018 306094 4841027 158.2 3.7 No well
BH 8 Sep. 12, 2018 306177 4841049 161.5 3.7 No well
BH 9 Sep. 12, 2018 306263 4841076 163.5 3.7 No well
BH 10 Sep. 12, 2018 306337 4841099 162.2 6.7 4.6 – 6.1
BH 11 Sep. 12, 2018 306406 4841121 160.8 6.7 No well
Keele Street
BH 12 Sep. 21, 2018 306482 4841147 162.8 9.8 6.1 – 9.1
BH 13 Sep. 21, 2018 306475 4841228 163.5 15.8 12.2 – 15.2
Queen’s
Greenbelt
BH 14 Sep. 12, 2018 306412 4841202 153.6 14.3 10.7 – 13.7
BH 15 Sep. 24, 2018 306518 4841225 153.6 11.3 7.7 – 10.7
4.3 Subsurface Conditions
Based on the soil conditions encountered at the boreholes drilled along the existing paved roads and
within Queen's Greenbelt, the soil profile in Assignment 16-12 comprised surficial asphaltic concrete or
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 9
topsoil overlying fill soils (sandy gravel, gravelly sand, silty sand, sandy silt, clayey silt and silty clay) which
were underlain by native soils (organic silty clay, sandy silty clay / sandy clayey silt till, and sandy silt / sand
and silt till).
The subsurface soil and groundwater conditions are briefly described in this section. Additional
information is provided in Record of Boreholes.
4.3.1 Ground Cover
Asphaltic Concrete
Asphaltic concrete thickness at borehole locations drilled through the existing road pavement varied from
120 mm to 230 mm.
The existing asphaltic concrete was cored at various locations for asbestos analysis as listed in Section 4.5.
Topsoil
Topsoil, 200 mm in thickness, was encountered at Borehole BH 14 located within an unoccupied area, with
its water content of 16 %. The thickness of topsoil may vary considerably between and beyond the
borehole location at the project site.
4.3.2 Fill Soils
Fill soils were encountered below the asphaltic concrete and topsoil at all borehole locations. The fill soils
comprised sandy gravel, gravelly sand, silty sand and sandy silt, sandy silt, clayey silt and silty clay.
Dark to light brown sandy gravel and/or gravelly sand fill were present below the asphaltic concrete, while
sandy gravel was found at the ground surface in North Park at Borehole BH 15. The thickness of the sandy
gravel, gravelly sand fill ranged from 0.2 m to 2 m. Water contents were 2 % to 3 % for the sandy gravel
fill and 1 % to 8 % for the gravelly sand fill.
Silty sand fill was revealed below the sandy gravel and gravelly sand fill at the borehole locations along
Gracefield Avenue, and sandy silt fill was found below the sandy gravel at Borehole BH 15. The thickness
of the silty sand fill varied from 0.4 m to 1.9 m, with its water contents ranging from 5 % to 18 %. The
sandy silt fill was 0.4 m thick at Borehole BH 15, and its water content was 15 %.
The sandy silt fill was also found below the topsoil at Borehole BH 14 and extended to 3.2 m below grade.
The sandy silt fill was brown in colour, and contained trace clayey silt and gravel, and trace topsoil
pockets. SPT ‘N’ values of the sandy silt fill soils were 5 to 13 blows per 0.3 m, and water contents ranged
from 8 % to 12 %.
Clayey silt and silty clay fill soils were found below the gravelly sand and sandy silt fill, and extended to
1.4 m to 7.0 m below grade. The clayey silt and silty clay fill soils were brown / grey, and contained trace
sand and gravel, topsoil, organics and rootlets. The fill soils extended to depths ranging from 1.4 m to 7.0
m below the existing grades. SPT ‘N’ values for the clayey silt and silty clay fill soils ranged from 3 to 23
blows per 0.3 m, and water contents varied from 13 % to 33 %.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 10
4.3.3 Organic Silty Clay
Native organic silty clay was present below the fill soils at Borehole BH 14 location, with its thickness
being 0.6 m. The organic silty clay was black in colour, with trace sand pockets and rootlets. SPT ‘N’ value
of the organic silty clay was 11 blows per 0.3 m.
4.3.4 Sandy Silty Clay / Sandy Clayey Silt Till
Sandy silty clay / sandy clayey silt till was encountered below the fill soils or the organic silty clay at all the
borehole locations except Borehole BH 15, and extended to 8.5 m below the existing grade, or the
termination depths (up to 15.8 m) of the boreholes.
The sandy silty clay / sandy clayey silt till was brown to grey in colour, partially oxidized at the top, and
contained trace gravel and sand seams / pockets.
SPT ‘N’ values of the sandy silty clay / sandy clayey silt till ranged from 5 to 46 blows per 0.3 m, implying a
firm to hard consistency. Water contents of the sandy silty clay / sandy clayey silt till samples varied from
11 % to 22 %.
Grain size distribution plots and Atterberg Limit test results for the sandy silty clay till are shown on the
Record of Boreholes, Figures A1-1 to A1-2 in Appendix A1, and Table 4.3.
Table 4.3: Results of Grain Size Distribution Analyses and Atterberg Limit Tests, Sandy Silty Clay Till
(Assignment 16-12)
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution Atterberg Limits
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
Limit
Plastic
Limit
Plasticity
Index
BH 2 SS4 2.3 – 2.9 3 23 48 26 27 15 12
BH 4 SS5 3.1 – 3.7 2 27 50 21 25 15 10
BH 6 SS3 1.5 – 2.1 2 28 51 19 25 14 11
BH 7 SS3 0.8 – 1.4 1 32 50 17 24 15 9
BH 9 SS4 2.3 – 2.9 5 29 49 17 23 14 9
BH 9 SS5 3.1 – 3.7 1 31 51 17 23 14 9
BH 12 SS6 4.6 – 5.2 1 24 52 23 28 15 13
BH 12 SS9 9.1 – 9.7 2 29 49 20 21 12 9
BH 13 SS9 9.1 – 9.7 1 31 50 18 25 14 11
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 11
Similarly, grain size distribution and Atterberg Limit test results of the sandy clayey silt till are shown on
Record of Boreholes and Figure Nos. A1-3 and A1-4 in Appendix A1, and summarized in Table 4.4.
Table 4.4: Results of Grain Size Distribution Analyses and Atterberg Limit Tests
Sandy Clayey Silt Till (Assignment 16-12)
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution Atterberg Limits
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
Limit
Plastic
Limit
Plasticity
Index
BH 8 SS5 3.1 – 3.7 2 30 50 18 22 14 8
BH 9 SS3 1.5 – 2.1 3 30 51 16 22 14 8
BH 10 SS2 0.8 – 1.4 2 31 51 16 20 13 7
BH 10 SS5 3.1 – 3.7 1 29 52 18 21 13 8
BH 10 SS7 6.1 – 6.7 3 27 52 18 20 12 8
BH 13 SS13 15.2 – 15.8 7 32 46 15 18 12 6
BH 14 SS7 6.1 – 6.7 6 29 46 19 20 12 8
BH 15 SS6 4.6 – 5.2 3 34 47 16 18 12 6
4.3.5 Sandy Silt / Sand and Silt Till
Sandy silt / sand and silt till was encountered below the sandy silty clay / sandy clayey silt till or fill soils at
Boreholes BH 14 and BH 15 locations along Queen’s Greenbelt, and extended to the termination depths
of the boreholes. The sandy silt / sand and silt till was brown to grey in colour, and contained trace to
some clay, trace gravel, trace cobbles / boulders.
SPT ‘N’ values of the sandy silt / sand and silt till ranged from 16 to 68 blows per 0.3 m, indicating a
compact to very dense compactness. Water contents of the sandy silt / sand and silt till samples varied
from 8 % to 14 %.
Based on Atterberg Limit test results, the sandy silt / sand and silt till was of low plasticity to no plasticity
and low compressibility. Grain size distribution and Atterberg Limits of the sandy silt / sand and silt till are
shown on Record of Boreholes and Figure Nos. A1-5 and A1-6 in Appendix A1, and summarized in Table
4.5.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 12
Table 4.5: Results of Grain Size Distribution Analyses and Atterberg Limit Tests
Sandy Silt / Sand and Silt Till (Assignment 16-12)
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution Atterberg Limits
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
Limit
Plastic
Limit
Plasticity
Index
BH 14 SS9 9.1 – 9.7 2 32 62 4 – – –
BH 14 SS11 12.2 – 12.8 6 35 53 6 – – –
BH 14 SS12 13.7 – 14.3 2 37 48 13 14 12 2
BH 15 SS9 9.1 – 9.7 5 33 53 9 15 14 1
4.4 Groundwater Conditions
The groundwater conditions in the open boreholes were monitored throughout the drilling operations
and measured upon completion of drilling. Most of boreholes were open and dry upon completion.
Groundwater was present only in Boreholes BH 13 to BH 15 locations upon completion of drilling.
Monitoring wells (50 mm diameter pipes) were installed in five (5) borehole locations in Assignment 16-12
for subsequent groundwater level measurements.
On 2 and 21 November 2018, the groundwater levels in the monitoring wells were measured as shown on
the corresponding Record of Boreholes, and summarized in Table 4.6.
Table 4.6: Groundwater Level Measurement in Monitoring Wells (Assignment 16-12)
No. Monitoring Well
(MW) Location
MW
No.
Well
Depth
(m)
Ground
Elevation
(m )
Groundwater Levels in Monitoring Wells
Depth (m) / (Elevation) (m)
On Completion
of Drilling (12-24
September 2018)
2 November
2018
21 November
2018
1 Gracefield Avenue BH 10 6.1 162.2 Dry 3.3 /
(158.9)
2 Gracefield Avenue and
Keele Street BH 12 9.1 162.8 Dry
7.9 /
(154.9)
3 Keele Street BH 13 15.2 163.5 9.1 /
(154.4)
12.7 /
(150.8)
4 West of Keele Street BH 14 13.7 153.6 4.6 /
(149.0)
7.0 /
(146.6)
5 North Park BH 15 10.7 153.6 3.0 /
(150.6)
4.9 /
(148.7)
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 13
The groundwater observations indicated that the groundwater elevations ranged from 158.9 m to 146.6 m
in Assignment 16-12. It should be noted that the groundwater level at the site will fluctuate seasonally
and can be higher during the spring months and in response to major weather events.
4.5 Asphaltic Concrete Cores
Asphaltic concrete cores were collected at and near the borehole locations in Assignment 16-12. Upon
completion of coring, the core locations (Figure 2) were surveyed using a hand-held GPS. All the asphaltic
concrete cores were photographed (Appendix B1) and recorded before delivering to EMC for asbestos
analysis.
The thickness and east/north coordinates of asphaltic concrete cores for Assignment 16-12 are shown in
Table 4.7.
Table 4.7: Asphaltic Concrete Core Thickness and Locations (Assignment 16–12)
Core
Location Core No.
Asphaltic Concrete
Thickness
(mm)
Easting Northing
Gracefield Avenue
C1 (BH 1) 170 305645 4840891
C2 (BH 3) 190 305795 4840933
C3 (BH 5) 110 305940 4840980
C4 120 306069 4841016
C5 (BH 8) 150 306177 4841049
C6 120 306306 4841089
C7 (BH 11) 180 306406 4841121
Keele Street
C8 (BH 12) 200 306482 4841147
C9 180 306482 4841193
C10 (BH 13) 220 306475 4841228
The asbestos testing methodology, results and comments are presented in Section 8.0.
4.6 Discussions and Recommendations
Based on Appendix P – Preliminary Design Drawings provided by CIMA+, the proposed storm sewers in
Assignment 16-12 may be installed by open cut or supported trench excavation method.
In general, the soil conditions are capable of supporting the proposed sewers / maintenance holes and
pipe bedding Class B can be used. Groundwater levels are 3.0 m to 12.7 m deep below the existing grade,
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 14
which are higher than the proposed sewer inverts along Keele Street and Queen’s Greenbelt at some
locations and dewatering will be required in some localized areas. Dewatering during construction will
likely be required along Keele Street and Queen’s Greenbelt, from which a hydrogeological assessment
should be carried out prior to construction.
Excavation into the till may encounter cobbles / boulders which will require additional excavation effort
(e.g., impact hammer).
The specific site conditions and bearing values for maintenance hole design for Assignment 16-12 are
provided in this section, while the general design and construction considerations are shown in Section
6.0.
4.6.1 Subsurface Conditions at Sewer / Maintenance Hole Inverts
The results from the investigation along Gracefield Avenue, Keele Street and Queen’s Greenbelt in
Assignment 16-12 are presented on Record of Boreholes and described in Section 4.3.
In general, most of the storm sewers will be laid within the native soils, i.e., sandy silty clay till / sandy clay
silt till.
Based on the subsurface soil conditions encountered at the boreholes, Class ‘B’ Type bedding (i.e.,
compacted granular bedding material) or better (i.e., Class ‘A’ Type bedding) should be used for bedding
the proposed storm sewers.
Loose silty / sandy soil subgrade, where encountered, should be compacted by a vibratory compactor
prior to placing pipe bedding. Very soft to soft clayey soil subgrade, if encountered, should be covered
with lean concrete with a minimum thickness of 100 mm to provide a workable surface and support the
proposed sewers. The very soft to soft clayey soil subgrade may also be removed and replaced by
engineered fill, following the engineered fill placement procedure as discussed in Section 6.2.
4.6.2 Foundations for Maintenance Holes
Based on the design drawings and the finding from the investigation, the founding levels of the proposed
maintenance holes would be located within the sandy silty clay till / sandy clayey silt till.
The till would be capable of supporting of the proposed maintenance holes in Assignment 16-12.
Recommended geotechnical reactions / resistances for the founding stratum for the proposed
maintenance holes are summarized in Table 4.8.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 15
Table 4.8: Founding Stratum and Soil Bearing Capacity for Maintenance Hole (MH) Foundations
(Assignment 16–12)
Location
Proposed
Maintenance
Hole
Reference
Boreholes
Founding
Stratum(1)
Depth
Below
Grade
(m) (2)
Approximate
Elevation
(m)
Geotechnical
Pressure
Reaction at
SLS
(kPa)
Factored
Geotechnical
Pressure
Resistance at
ULS (3) (4)
(kPa)
Gracefield
Avenue MH GA1 BH 11
Stiff to very stiff,
sandy silty clay till 4.1 156.7 150 225
Keele
Street
MH KS1 and
MH KS2
BH 12 Stiff to very stiff,
sandy silty clay till 3.0 159.8 150 225
BH 13 Very stiff, sandy
silty clay till 7.0 156.5 200 300
Engineered fill (4) 150 225
Notes: (1) Bearing values are provided at the shallowest depth of competent soil found in the boreholes. Higher SLS/ULS
values are normally achievable at deeper depth.
(2) Founding stratum at and below the depth indicated.
(3) A resistance factor of Φ = 0.5 has been applied to the ULS values provided.
(4) Use of the existing fill soils is not recommended due to possible non-uniformly compacted soils. Existing fill soils
should be replaced with engineered fill and compacted to at least 98 % SPMDD for founding stratum. The
thickness of the engineered fill should be at least 1.0 m unless the proposed engineered fill is founded on
competent native soil.
4.6.3 Soil Corrosivity Analysis
To assess the soil aggressiveness to concrete and embedded steel structures, two (2) soil samples at or
near the sewer invert depths were selected and submitted to Maxxam Analytics Laboratory in Mississauga
for corrosivity testing (i.e., pH, soluble chloride, soluble sulphate, electrical conductivity, and resistivity).
The laboratory testing results and the Certificate of Analyses are attached in Appendix E1 and summarized
in Table 4.9.
Table 4.9: Summarized Soil Corrosivity Test Results (Assignment 16–12)
Location Sample No. Resistivity
ohm-cm
Soluble
Chloride
µg/g
Conductivity
µmho/cm pH
Soluble
Sulphate
µg/g
Gracefield Avenue BH 11 SS6 1800 240 561 7.70 <20
Keele Street
BH 12 SS8 1200 370 803 7.67 74
BH 13 SS12 3600 75 277 7.66 <20
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 16
Location Sample No. Resistivity
ohm-cm
Soluble
Chloride
µg/g
Conductivity
µmho/cm pH
Soluble
Sulphate
µg/g
Queen’s Greenbelt
BH 14 SS7 2000 53 493 7.73 270
BH 15 SS7 4900 21 202 7.83 <20
The measured soil resistivity value was 1,800 ohm-cm along Gracefield Avenue Drive, 1,200 to 3,600 ohm-
cm along Keele Street, and 2,000 to 4,900 ohm-cm along Queen’s Greenbelt.
Compared to the values in the available literature (i.e., J.D. Palmer, Soil Resistivity Measurement and
Analysis, Materials Performance, Volume 13, 1974), the above-mentioned range of soil corrosivity should
be considered as “severe” along Gracefield Avenue, “severe“ to “moderate” along Keele Street and
“moderate” along Queen’s Greenbelt, for exposed steel structures.
The measured water soluble sulphate in soil was generally low and ranged from less than 20 to 270 µg/g
in Assignment 16-12. In accordance with Table 3 of the Canadian Standards Association (CSA) Series CSA
A23.1-14, soil with the sulphate content ratio less than 0.1% (i.e., 1,000 ppm or µg/g) is not considered
aggressive to concrete. Therefore, in accordance with Table 6 of the CSA Series A23.1-14, Type GU
Portland cement may be used for concrete.
Soil corrosivity should be assessed by a corrosivity expert, if necessary.
4.6.4 Construction Dewatering
Boreholes along Gracefield Avenue were dry upon completion of drilling, and the groundwater level was
9.1 m, 4.6 m and 3.0 m deep at Boreholes BH 13 to BH 15 locations. The groundwater levels, measured in
the monitoring wells in Assignment 16-12 on 2 and 21 November 2018, were 3.3 m to 12.7 m below the
existing grade, with the corresponding elevations ranging from 158.9 m to 146.6 m. Groundwater level
measurements for Assignment 16-12 are summarized in Table 4.6.
Based on the planned sewer invert depths, the soils encountered at the boreholes and the groundwater
conditions, localized construction dewatering will likely be required to lower the groundwater level in
Assignment 16-12.
The presence of the sandy silt / sand and silt till should be relatively high permeability soil and should be
considered in the dewatering estimates. Accordingly, a hydrogeological assessment should, therefore, be
conducted for the site in order to provide construction dewatering requirements, and the associated level
of dewatering effort pertaining to construction along Keele Street and Queen’s Greenbelt.
Water seepage, if encountered, in the native cohesive soils (e.g., organic silty clay, sandy silty clay / sandy
clayey silt till) should be manageable through gravity drainage and/or a filtered sump and pump system.
Within the water-bearing sandy / silty soils, a series of sump and pump or a system of well points will be
required for dewatering.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 17
Section 6.0 provides relevant design and construction considerations.
5.0 GEOTECHNICAL CONSIDERATION FOR ASSIGNMENT 16-22
5.1 Project Description
5.1.1 Sewer Re-construction
Based on the preliminary design Drawings 17-03309-001 to 17-03309-015 dated 14 December 2017
provided by CIMA+, the proposed works for Assignment 16-22 will involve storm sewer and sanitary
sewer re-construction along Roding Street, Gade Drive, Ianhall Road, Nash Drive, Bunnell Crescent,
Hallsport Crescent and Dorking Crescent. Most of the proposed storm sewers will be concrete pipes with
diameters ranging from 450 mm to 900 mm, and the proposed sewer pipes will be PVC pipes with
diameters of 300 mm and 375 mm.
The details of the proposed sewer re-construction works for Assignment 16-22 are summarized in Table
5.1.
Table 5.1: Details of Proposed Works along Ianhall Road, Gade Drive, Roding Street, Nash Drive,
Bunnell Crescent, Hallsport Crescent and Dorking Crescent (Assignment 16-22)
Proposed
Work
Location
From To Type of Utility
Utility
Diameter/Size
(mm)
Approximate
Utility Depth
(m)
Approximate
Utility Length
(m)
Ianhall
Road
MH IR1 Gade Drive
Storm Sewer 675 3.0 – 7.0 73.7
MH IR1 1,800 3.5 – 7.2 –
MH IR1A MH IR2A
Sanitary Sewer 250 3.3 – 3.5 30.4
MH IR1A and MH
IR2A 1,200 3.5 – 4.0 –
Gade Drive Ianhall
Road
Roding
Street
Storm Sewer 675 4.5 – 6.7 93.7
MH GD1 1,800 4.9 – 7.2 –
Roding
Street
Gade
Drive Nash Drive
Storm Sewer 750 – 900 4.8 – 7.0 101.2
MH RS1 to MH RS3 1,800 – 2,400 4.9 – 7.1 –
Nash Drive Roding
Street
Bunnell
Crescent
Storm Sewer 750 – 900 3.6 – 5.5 408.8
MH RS3, MH DC1,
MH ND1, MH ND2
and MH BC2
1,500 – 2,400 4.2 – 6.2 –
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 18
Proposed
Work
Location
From To Type of Utility
Utility
Diameter/Size
(mm)
Approximate
Utility Depth
(m)
Approximate
Utility Length
(m)
Bunnell
Crescent MH BC4
Hallsport
Crescent
Storm Sewer 375 – 675 2.3 – 5.0 272.2
MH BC1 to MH BC4 1,200 – 1,800 2.5 – 5.1 –
Hallsport
Crescent MH HC1
Bunnell
Crescent
Storm Sewer 450 – 525 3.4 – 4.6 131.0
MH HC1, MH HC2
and MH BC1 1,200 – 1,800 3.6 – 4.9 –
Dorking
Crescent MH DC6 Nash Drive
Storm Sewer 300 – 375 3.4 – 4.6 131.0
MH DC1 to MH DC6 1,200 – 2,400 3.6 – 4.9 –
5.1.2 Roding Park – Storm Sewer and Headwalls
Based on Drawing Nos. 17-03309-029 and 17-03309-030 dated 11 January 2019 (Appendix C) provided
by CIMA+, a proposed concrete storm sewer (450 mm in diameter and 14 m in length) will be constructed
under an embankment for supporting the proposed asphalt walkway near the south end of Roding Park,
with one (1) precast concrete headwall at each end (near BH 16 in Figure 3) – referred to as "south walls"
herein.
At the existing slope toe (near BH 37 location in Figure 3), the existing headwall will be replaced by a
precast concrete headwall ("north headwall") and the existing 600 mm diameter storm sewer underneath
the slope will be replaced by a 975 mm diameter storm sewer. The details of the proposed works in
Roding Park are summarized in Tables 5.2.
Table 5.2: Details of Proposed Works in Roding Park (Assignment 16-22)
Proposed
Work
Location
From To Type of
Utility
Utility
Diameter/Size
(mm)
Approximate
Utility Depth
(m)
Approximate
Utility Length
(m)
Roding
Park
Near south
end of
Roding
Street (BH 16
in Figure 3)
South end of
Roding Park
Storm Sewer 450 2.0 14.0
Headwalls
("South
headwalls")
- About 2.0
below walkway –
Roding
Street
between
Nash Drive
and Gade
Drive
Existing Slope
Toe - east of
Roding Park
(BH 37 in
Figure 3)
Storm Sewer 975 0.0 – 7.6 40.6
North
Headwall -
About 10 m
below the top
of slope
–
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 19
5.2 Investigation Program
Borehole and monitoring well details for Assignment 16-22 are presented on Borehole Location Plan
(Figure 3), Record of Boreholes and Table 5.3. The investigation procedures are described in Section 3.0.
The results of the geotechnical laboratory tests are presented in Record of Boreholes and Appendix A2.
Table 5.3: Borehole and Monitoring Well Locations (Assignment 16–22)
Borehole
Location
Borehole
No. Drilling Date Easting Northing
Ground
Elevation
(m)
Borehole
Depth
(m)
Monitoring
Well Screen
Depth
(m)
Roding Park
BH 16 Sep. 24, 2018 305285 4842680 156.9 9.8 6.1 – 9.1
BH 17 Sep. 24, 2018 305403 4842812 159.6 6.7 No well
BH 37 Oct. 26, 2018 305398 4842927 162.9 8.1 No well
Ianhall Road BH 18 Sep. 17, 2018 305577 4842858 171.1 6.6 3.1 – 6.1
Gade Drive BH 19 Sep. 17, 2018 305566 4842927 173.6 8.2 4.6 – 7.6
Roding
Street
BH 20 Sep. 25, 2018 305479 4842888 169.8 6.6 No well
BH 21 Sep. 25, 2018 305446 4842942 171.1 8.2 4.6 – 7.6
Nash Drive
BH 22 Sep. 25, 2018 305440 4842982 172.3 7.9 No well
BH 23 Sep. 25, 2018 305531 4843016 172.4 6.7 4.6 – 6.1
BH 24 Sep. 25, 2018 305629 4843047 175.1 6.7 No well
BH 25 Oct. 11, 2018 305739 4843080 178.2 6.6 No well
Bunnell
Crescent
BH 26 Sep. 26, 2018 305870 4843226 181.3 6.7 No well
BH 27 Oct. 11, 2018 305804 4843183 180.2 6.7 No well
BH 28 Sep. 26, 2018 305815 4843105 179.1 6.7 3.1 – 6.1
Hallsport
Crescent
BH 29 Sep. 26, 2018 305835 4843013 179.6 6.7 3.1 – 6.1
BH 30 Sep. 26, 2018 305799 4842995 179.3 6.7 No well
BH 31 Oct. 26, 2018 305828 4842923 179.3 6.6 3.1 – 6.1
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 20
Borehole
Location
Borehole
No. Drilling Date Easting Northing
Ground
Elevation
(m)
Borehole
Depth
(m)
Monitoring
Well Screen
Depth
(m)
Hallsport
Crescent
(cont’d)
BH 32 Sep. 26, 2018 305867 4842938 179.5 6.7 No well
Dorking
Crescent
BH 33 Oct. 26, 2018 305502 4843112 175.1 6.6 3.1 – 6.1
BH 34 Oct. 11, 2018 305562 4843130 176.2 6.6 No well
BH 35 Oct. 11, 2018 305633 4843152 177.5 6.6 No well
BH 36 Oct. 11, 2018 305705 4843164 178.7 6.6 No well
5.3 Subsurface Conditions
Based on the soil conditions encountered at the boreholes drilled along the existing paved roads and
within Roding Park, the soil profile in Assignment 16-22 comprised surficial asphaltic concrete or topsoil
overlying fill soils (sandy gravel, gravelly sand, sand, sandy silt, silty sand, clayey silt and silty clay) which
were underlain by native soils (clayey silt / silty clay / silt and clay, sandy silty clay / sandy clayey silt till,
sand and silt till, and sand).
The subsurface soil and groundwater conditions are briefly described in this section. Additional
information is provided in Record of Boreholes.
5.3.1 Ground Cover
Asphaltic Concrete
Asphaltic concrete found at the boreholes drilled through the existing pavement varied in thickness from
120 mm to 240 mm.
Asphaltic concrete cores were obtained at various locations as listed in Section 5.5 for asbestos analysis.
Topsoil
Topsoil, 150 mm to 180 mm thick, was encountered at Boreholes BH 16, BH 17 and BH 37 located within
Roding Park, with its water contents ranging from 13 % to 18 %. The thickness of topsoil may vary
considerably between and beyond the borehole locations at the project site.
5.3.2 Fill Soils
Fill soils were encountered below the asphaltic concrete and topsoil at all borehole locations. The fill soils
comprised sandy gravel, gravelly sand, sandy silt / silty sand, sand and silty clay.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 21
Dark brown to brown sandy gravel and gravelly sand, with thickness between 200 mm and 700 mm, was
found below the asphaltic concrete. Water contents were 1 % to 5 % for the sandy gravel fill and 3 % to
10 % for the gravelly sand fill.
Sandy silt / silty sand fill was found below the topsoil at Boreholes BH 16, BH 17, BH 34 and BH 37
locations; and extended to 0.4 m to 4.0 m below grade. The sandy silt / silty sand fill was brown to dark
brown in colour, and contained trace silty clay and gravel, and trace organics. SPT ‘N’ values for the sandy
silt / silty sand fill soils varied from 4 to 24 blows per 0.3 m, and its water contents ranged from 8 % to
26 %.
Clayey silt / silty clay fill soil was found below the sandy gravel / gravelly sand / sandy silt fill at Roding
Street, Nash Drive, Bunnell Crescent, Hallsport Crescent, Dorking Crescent and north of Roding Park. It
extended to 0.9 m to 6.2 m below grade. The clayey silt / silty clay fill was brown to dark grey in colour,
and contained trace sand and gravel, topsoil, brick pieces, organics and rootlets. SPT ‘N’ values for the
clayey silt / silty clay fill ranged from 3 to 20 blows per 0.3 m, and its water contents varied from 13 % to
39 %.
Sand fill was encountered below the sandy silt fill and silty clay fill at Boreholes BH 16 and BH 37 locations
in Roding Park, and extended to 7.0 m to 7.3 m below the existing grade. The sand fill contained trace silt,
and rubber pieces. SPT ‘N’ values for the sand fill ranged from 6 to 46 blows per 0.3 m, and its water
contents were 5 % to 10 %.
Grain size distribution for the sand fill is shown on the Record of Boreholes, Figure A2-1 in Appendix A2,
and Table 5.4.
Table 5.4: Results of Grain Size Distribution Analysis, Sand Fill (Assignment 16–22)
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution
Gravel
(%)
Sand
(%)
Silt and Clay
(%)
BH 37 SS6 4.6 – 5.2 - 80 20
5.3.3 Clayey Silt / Silty Clay / Silt and Clay
Native clayey silt / silty clay / silt and clay was present below the fill soils at Boreholes BH 19 to BH 22, BH
26, BH 28, BH 33, and BH 36; and extended to 2.2 m to 7.2 m below the existing grade, or 8.2 m (the
termination depth of Borehole BH 21).
The clayey silt / silty clay / silt and clay was brown to grey in colour, partially oxidized on the top, and
contained some sand to sandy. SPT ‘N’ values for the clayey silt / silty clay / silt and clay were 7 to 60
blows per 0.3 m, indicating a firm to hard consistency. Its water contents ranged from 13 % to 22 %.
Grain size distribution and Atterberg Limit test results for the clayey silt / silty clay / silt and clay are shown
on the Record of Boreholes, Figures A2-2 and A2-3 in Appendix A2, and Table 5.5.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 22
Table 5.5: Results of Grain Size Distribution Analyses and Atterberg Limit Tests
Clayey Silt / Silty Clay / Silt and Clay (Assignment 16–22)
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution Atterberg Limits
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
Limit
Plastic
Limit
Plasticity
Index
BH 20 SS7 4.6 – 5.2 - 10 71 19 24 17 7
BH 21 SS9 7.6 – 8.2 - 21 56 23 33 17 16
BH 22 SS3 1.5 – 2.1 <1 15 40 45 39 18 20
5.3.4 Sandy Silty Clay / Sandy Clayey Silt Till
Sandy silty clay / sandy clayey silt till was found below the fill soils or the silty clay / silt and clay, or
interbedded within the clayey silt / silty clay at most boreholes located on the road sections. It extended
to 5.6 m, or the termination depths of Boreholes BH 18, BH 19, and BH 23 to BH 36.
The sandy silty clay till was brown to grey in colour, and contained trace gravel. SPT ‘N’ values for the
sandy silty clay till ranged from 7 to 33 blows per 0.3 m, indicating a firm to hard consistency. Water
contents of the sandy silty clay till varied from 12 % to 20 %.
Grain size distribution and Atterberg Limit test results for the sandy silty clay till are shown on the Record
of Boreholes, Figures A2-4 and A2-5 in Appendix A2, and Table 5.6.
Table 5.6: Results of Grain Size Distribution Analyses and Atterberg Limit Tests, Sandy Silty Clay Till
(Assignment 16–22)
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution Atterberg Limits
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
Limit
Plastic
Limit
Plasticity
Index
BH 18 SS3 1.5 – 2.1 2 29 49 20 25 13 12
BH 18 SS5 3.1 – 3.7 5 29 47 19 23 13 10
BH 19 SS8 7.6 – 8.2 3 20 47 30 27 14 13
BH 23 SS7 6.1 – 6.7 1 27 43 29 28 14 14
BH 25 SS4 2.3 – 2.9 3 27 50 20 24 13 11
BH 26 SS4 2.3 – 2.9 2 27 51 20 22 13 9
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 23
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution Atterberg Limits
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
Limit
Plastic
Limit
Plasticity
Index
BH 27 SS7 6.1 – 6.7 1 25 54 20 22 13 9
BH 30 SS4 2.3 – 2.9 1 22 58 19 26 15 11
BH 30 SS5 3.1 – 3.7 1 24 55 20 24 14 10
BH 32 SS4 2.3 – 2.9 1 24 55 20 24 15 9
Similarly, the sandy clayey silt till was brown, brownish grey to grey in colour, and contained trace gravel.
SPT ‘N’ values for the sandy clayey silt till ranged from 8 to 35 blows per 0.3 m, implying a firm to hard
consistency. Water contents of the sandy clayey silt till varied from 10 % to 20 %.
The grain size distribution and Atterberg Limit test results for the sandy clayey silt till are shown on the
Record of Boreholes, Figures A2-6 and A2-7 in Appendix A2, and Table 5.7.
Table 5.7: Results of Grain Size Distribution Analyses and Atterberg Limit Tests,
Sandy Clayey Silt Till (Assignment 16–22)
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution Atterberg Limits
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
Limit
Plastic
Limit
Plasticity
Index
BH 19 SS5 3.1 – 3.7 2 30 50 18 19 13 6
BH 24 SS7 6.1 – 6.7 5 29 47 19 21 13 8
BH 25 SS6 4.6 – 5.2 4 26 51 19 21 13 8
BH 26 SS7 6.1 – 6.7 2 29 50 19 20 12 8
BH 27 SS5 3.1 – 3.7 2 33 52 13 20 14 6
BH 28 SS4 2.3 – 2.9 2 29 51 18 19 12 7
BH 28 SS6 4.6 – 5.2 3 26 51 20 21 13 8
BH 29 SS7 6.1 – 6.7 4 30 49 17 18 12 6
BH 31 SS7 6.1 – 6.7 3 26 52 19 20 13 7
BH 33 SS6 4.6 – 5.2 1 26 53 20 22 14 8
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 24
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution Atterberg Limits
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
Limit
Plastic
Limit
Plasticity
Index
BH 34 SS6 4.6 – 5.2 3 26 45 26 22 14 8
BH 35 SS5 3.1 – 3.7 2 27 52 19 21 13 8
BH 36 SS7 6.1 – 6.7 1 29 51 19 20 12 8
5.3.5 Sand and Silt Till
Sand and silt till was found below the clayey silt / silty clay / silt and clay and the sandy silty clay / sandy
clayey silt till at Boreholes BH 18, BH 20 and BH 22 locations close to Roding Park. It extended to the
termination depths of Boreholes BH 18 and BH 20 or it was underlain by the sand (Section 5.3.6) at
Borehole BH 22. The sand and silt till was grey in colour, and contained trace cobbles / boulders, some
clay and trace gravel.
SPT ‘N’ values for the sand and silt till ranged from 34 to 60 blows per 0.3 m, indicating a dense to very
dense compactness, while its water contents varied from 5 % to 9 %.
Grain size distribution for the sand and silt till are shown on the Record of Boreholes, Figures A2-8 and
A2-9 in Appendix A2, and Table 5.8.
Table 5.8: Results of Grain Size Distribution Analyses, Sand and Silt Till (Assignment 16–22)
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution Atterberg Limits
Gravel
(%)
Sand
(%)
Silt
(%)
Clay
(%)
Liquid
Limit
Plastic
Limit
Plasticity
Index
BH 18 SS7 6.1 – 6.6 5 35 48 12 15 12 3
BH 22 SS6 4.6 – 5.2 3 38 48 11 18 14 4
5.3.6 Sand
Sand was present below the fill soils or the sand and silt till at Boreholes BH 16, BH 17, BH 22 and BH 37
within or near Roding Park, and extended to the termination depths of the boreholes in Assignment 16-
22. The sand was brown to grey in colour, and contained trace to some silt and gravel.
SPT ‘N’ values for the sand ranged from 35 blows per 0.3 m to 50 blows per 0.15 m, indicating a dense to
very dense compactness, and its water contents varied from 3 % to 10 %. Grain size distribution for the
sand are shown on the Record of Boreholes, Figure A2-10 in Appendix A2, and Table 5.9.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 25
Table 5.9: Results of Grain Size Distribution Analyses, Sand (Assignment 16–22)
Borehole
No.
Sample
No.
Depth
(m)
Grain Size Distribution
Gravel
(%)
Sand
(%)
Silt and Clay
(%)
BH 16 SS8 7.6 – 8.2 22 73 5
BH 17 SS7 6.1 – 6.7 - 75 25
BH 22 SS8 7.6 – 7.9 - 75 25
5.4 Groundwater Conditions
The groundwater conditions in the open boreholes were monitored throughout the drilling operations
and measured upon completion of drilling. Most of boreholes were open and dry upon completion.
Groundwater was only found in Boreholes BH 16, BH 23 and BH 34 upon completion of drilling.
Monitoring wells (50 mm diameter pipes) were installed in nine (9) borehole locations in Assignment 16-
22 for subsequent groundwater level measurements.
On 2 and 21 November 2018, the groundwater levels in the monitoring wells were measured as shown on
the corresponding Record of Boreholes and summarized in Table 5.10.
Table 5.10: Groundwater Level Measurement in Monitoring Wells (Assignment 16-22)
No. Monitoring Well
(MW) Location
MW
No.
Well
Depth
(m)
Ground
Elevation
(m )
Groundwater Levels in Monitoring Wells
Depth (m) / (Elevation) (m)
On Completion
of Drilling (12-26
September 2018)
2
November
2018
21
November
2018
1 Roding Park BH 16 9.1 156.9 4.6 /
(152.3)
6.5 /
(150.4)
2 Ianhall Road BH 18 6.1 171.1 Dry 2.5 /
(168.6)
3 Ianhall Road and
Gade Drive BH 19 7.6 173.6 Dry
4.3 /
(169.3)
4 Entrance of Roding
Park BH 21 7.6 171.1 Dry – Dry
5 Nash Drive BH 23 6.1 172.4 4.6 /
(167.8)
1.7 /
(170.7)
6 Nash Drive and
Bunnell Crescent BH 28 6.1 179.1 Dry
1.5 /
(177.6)
7 Bunnell Crescent and
Hallsport Crescent BH 29 6.1 179.6 Dry
2.4 /
(177.2)
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 26
No. Monitoring Well
(MW) Location
MW
No.
Well
Depth
(m)
Ground
Elevation
(m )
Groundwater Levels in Monitoring Wells
Depth (m) / (Elevation) (m)
On Completion
of Drilling (12-26
September 2018)
2
November
2018
21
November
2018
8 Hallsport Crescent BH 31 6.1 179.3 Dry 1.8 /
(177.5)
9 Dorking Crescent BH 33 6.1 175.1 Dry 4.6 /
(170.5)
The measured groundwater elevations ranged from 177.6 m to 150.4 m from north to south in
Assignment 16-22. It should be noted that the groundwater levels at the site will fluctuate seasonally and
should be higher during the spring months and in response to major weather events.
5.5 Asphaltic Concrete Cores
Asphaltic concrete cores were collected at and near the borehole locations in Assignment 16-22. Upon
completion of coring, the core locations (Figure 3) were surveyed using a hand-held GPS. All the asphaltic
concrete cores were photographed (Appendix B2) and recorded before delivering to EMC.
The thickness and east/north coordinates of asphaltic concrete cores are shown in Table 5.11.
Table 5.11: Asphaltic Concrete Core Thickness and Locations (Assignment 16–22)
Core
Location Core No.
Asphaltic Concrete
Thickness
(mm)
Easting Northing
Ianhall Road
C11 (BH 18) 170 305577 4842858
C12 150 305570 4842896
Gade Drive
C13 (BH 19) 120 305566 4842927
C14 130 305525 4842912
Roding Street
C15 (BH 20) 190 305479 4842888
C16 (BH 21) 150 305446 4842942
Nash Drive
C17 (BH 22) 180 305440 4842982
C18 170 305483 4842998
C19 (BH 23) 220 305531 4843016
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 27
Core
Location Core No.
Asphaltic Concrete
Thickness
(mm)
Easting Northing
Nash Drive
(cont’d)
C20 150 305576 4843028
C21 (BH 24) 160 305629 4843047
C22 170 305683 4843062
C23 (BH 25) 140 305739 4843080
C24 170 305783 4843095
Bunnell Crescent
C25 (BH 26) 170 305870 4843226
C26 150 305829 4843211
C27 (BH 27) 240 305804 4843183
C28 190 305810 4843152
C29 (BH 28) 190 305815 4843105
C30 150 305838 4843061
Hallsport Crescent
C31 (BH 29) 150 305835 4843013
C32 120 305820 4843006
C33 (BH 30) 150 305799 4842995
C34 140 305805 4842958
C35 (BH 31) 180 305828 4842923
C36 130 305844 4842928
C37 (BH 32) 160 305867 4842938
Dorking Crescent
C38 180 305513 4843061
C39 (BH 33) 190 305502 4843112
C40 (BH 34) 170 305562 4843130
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 28
Core
Location Core No.
Asphaltic Concrete
Thickness
(mm)
Easting Northing
Dorking Crescent
(cont’d)
C41 (BH 35) 190 305633 4843152
C42 (BH 36) 160 305705 4843164
The asbestos testing methodology, results and comments are presented in Section 8.0.
5.6 Discussions and Recommendations
Based on the preliminary design drawings provided by CIMA+, the proposed storm and sanitary sewers in
Assignment 16-22 may be installed by open cut or supported trench excavation method.
In general, the soil conditions are capable of supporting the proposed sewers / maintenance holes and
pipe bedding Class B can be used. Groundwater levels are 1.5 m to 6.5 m deep below the existing grade,
which are higher than the proposed sewer inverts in the majority of the project area. Dewatering during
construction will likely be required at the majority of the roads (i.e., Ianhall Road, Gade Drive, Nash Drive,
Bunnell Crescent and Hallsport Crescent), from which a hydrogeological assessment should be carried out
prior to construction.
Excavation into the till may encounter cobbles / boulders which will require additional excavation effort
(e.g., impact hammer).
Slope stability analyses at the proposed headwalls have been carried out and the results are discussed in
Section 5.7.
The specific site conditions and bearing values for maintenance hole design for Assignment 16-22 are
provided in this section, while the general design and construction considerations are shown in Section
6.0.
5.6.1 Subsurface Conditions at Sewer Inverts
The results of the investigation along the roads in Assignment 16-22 were presented on Record of
Boreholes as described in Section 5.3. In general, most of the sewers will be installed within the native
soils, i.e., silty clay / silt and clay, silty clay / clayey till, sand and silt till and / or sand.
Based on the subsurface soil conditions encountered at the boreholes, Class ‘B’ Type bedding (i.e.,
compacted granular bedding material) or better (i.e., Class ‘A’ Type bedding) should be used for bedding
the proposed storm and sanitary sewers.
Loose silty / sandy soil subgrade, if encountered, should be compacted by a vibratory compactor prior to
placing pipe bedding. Very soft to soft clayey soil subgrade, if encountered, should be covered with lean
concrete with a minimum thickness of 100 mm to provide a workable surface and support the proposed
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 29
sewers. The very soft to soft clayey soil subgrade may also be removed and replaced by engineered fill,
following the engineered fill placement procedure as discussed in Section 6.2.
General discussions and recommendations, site specific design and construction considerations during
installation of the proposed utilities are presented in Section 6.0.
5.6.2 Foundations for Maintenance Holes
Based on the design drawings and the findings from the investigation, the founding levels of the
proposed maintenance holes would be mostly located within native competent soils. Recommended
geotechnical reactions / resistances for the founding stratum for the proposed maintenance holes are
summarized in Table 5.12.
Table 5.12: Founding Stratum and Soil Bearing Capacity for Maintenance Hole (MH) Foundations
(Assignment 16–22)
Location Type of
Proposed Utility
Reference Boreholes
Founding
Stratum(1)
Depth Below Grade
(m)(2)
Approximate
Elevation
(m)
Geotechnical
Pressure
Reaction at
SLS
(kPa)
Factored
Geotechnical
Pressure
Resistance at
ULS (3) (4)
(kPa)
Roding
Park
South
Headwalls
and
manhole
BH 16
Engineered
fill(4) (at least 1
m thick below
headwall base)
Minimum
1.2 m 157.0 150 225
Dense, sand 7.3 149.6 300 450
North
Headwall BH 37
Engineered
fill(4) (at least 1
m thick below
headwall base)
Minimum
1.2 m 163.0 150 225
Very dense,
sand 7.0 155.9 300 450
Ianhall
Road
MHs for
Storm and
Sanitary
Sewer
BH 18
Firm to hard,
sandy silty clay
/ sandy clayey
silt till
0.9 170.1 100 150
Gade
Drive
MH for
Storm
Sewer
BH 19
Very stiff to
hard sandy
silty clay /
sandy clayey
silt till
1.4 172.2 200 300
Roding
Street
MHs for
Storm
Sewer
BH 20 Stiff to hard,
clayey silt 4.1 165.7 150 225
BH 21 Stiff, silty clay 7.3 163.8 150 225
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 30
Location Type of
Proposed Utility
Reference Boreholes
Founding
Stratum(1)
Depth Below Grade
(m)(2)
Approximate
Elevation
(m)
Geotechnical
Pressure
Reaction at
SLS
(kPa)
Factored
Geotechnical
Pressure
Resistance at
ULS (3) (4)
(kPa)
Nash
Drive
MHs for
Storm
Sewer
BH 22 Stiff, silt and
clay 0.5 171.8 150 225
BH 23
Hard to very
stiff, sandy silty
clay / sandy
clayey silt till
4.1 168.3 200 300
BH 24
Very stiff to
stiff, sandy silty
clay / sandy
clayey silt till
2.0 173.1 150 225
BH 25
Very stiff to
hard, sandy
silty clay /
sandy clayey
silt till
2.0 176.2 200 300
Bunnell
Crescent
MHs for
Storm
Sewer
BH 26
Very stiff to
stiff, sandy silty
clay / sandy
clayey silt till
2.2 179.1 150 225
MHs for
Storm
Sewer
BH 27
Very stiff to
stiff, sandy silty
clay / sandy
clayey silt till
2.0 178.2 150 225
BH 28 Very stiff, silty
clay 0.9 178.2 150 225
BH 29
Very stiff to
stiff, sandy silty
clay / sandy
clayey silt till
1.8 177.8 150 225
Hallsport
Crescent
MHs for
Storm
Sewer
BH 30
Stiff to very
stiff, sandy silty
clay / sandy
clayey silt till
2.1 177.2 150 225
BH 31
Very stiff,
sandy silty clay
/ sandy clayey
silt till
2.2 177.1 200 300
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 31
Location Type of
Proposed Utility
Reference Boreholes
Founding
Stratum(1)
Depth Below Grade
(m)(2)
Approximate
Elevation
(m)
Geotechnical
Pressure
Reaction at
SLS
(kPa)
Factored
Geotechnical
Pressure
Resistance at
ULS (3) (4)
(kPa)
Hallsport
Crescent
(cont’d)
MHs for
Storm
Sewer
BH 32
Firm to stiff,
sandy silty clay
/ sandy clayey
silt till
2.4 177.1 100 150
Dorking
Crescent
MHs for
Storm
Sewer
BH 33
Very stiff,
sandy silty clay
/ sandy clayey
silt till
2.4 172.6 200 300
BH 34
Stiff to very
stiff, sandy silty
clay / sandy
clayey silt till
2.7 173.5 150 225
BH 35
Hard to stiff,
sandy silty clay
/ sandy clayey
silt till
2.2 175.3 150 225
BH 36
Very stiff,
sandy silty clay
/ sandy clayey
silt till
1.2 177.5 200 300
Notes: (1) Bearing values are provided at the shallowest depth of competent soil found in the boreholes. Higher
SLS/ULS values are normally achievable at deeper depth.
(2) Founding stratum present at the depth indicated and below.
(3) A resistance factor of Φ = 0.5 has been applied to the ULS values provided.
(4) Use of the existing fill soils is not recommended due to possible non-uniformly compacted soils. Existing fill
soils should be replaced with engineered fill and compacted to at least 98 % SPMDD for founding stratum.
The thickness of the engineered fill should be at least 1.0 m unless the proposed engineered fill is founded
on competent native soil.
5.6.3 Soil Corrosivity Analysis
To assess the soil aggressiveness to concrete and embedded steel structures, nine (9) soil samples at or
near the sewer invert depths were selected and submitted to Maxxam Analytics Laboratory in Mississauga
for corrosivity testing (i.e., pH, soluble chloride, soluble sulphate, electrical conductivity and resistivity).
The laboratory testing results and the Certificate of Analyses are attached in Appendix E2 and summarized
in Table 5.13.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 32
Table 5.13: Summarized Soil Corrosivity Test Results (Assignment 16–22)
Location Sample No. Resistivity
ohm-cm
Soluble
Chloride
µg/g
Conductivity
µmho/cm pH
Soluble
Sulphate
µg/g
Roding Park
BH 16 SS2 5700 <20 176 7.56 <20
BH 17 SS3 5900 <20 168 7.60 <20
BH 37 SS5 16000 <20 61 7.59 20
Ianhall Road BH 18 SS6 2000 170 497 7.84 <20
Gade Drive BH 22 SS7 5600 50 180 7.93 <20
Roding Street BH 24 SS6 4300 <20 231 7.82 46
Nash Drive BH 26 SS5 4200 28 240 7.77 58
Bunnell Crescent BH 28 SS6 1500 290 660 7.78 65
Hallsport Crescent BH 32 SS5 2800 58 353 7.81 130
Dorking Crescent BH 36 SS5 2200 120 445 7.77 96
The measured soil resistivity values were 5,700 to 16,000 ohm-cm in Roding Park; 2,000 ohm-cm at Ianhall
Road; 5,600 ohm-cm at Gade Drive; 4,300 ohm-cm at Roding Street; 4,200 to 1,500 ohm-cm along Nash
Drive and Bunnell Crescent; 2,800 ohm-cm at Hallsport Crescent and 2,200 ohm-cm at Dorking Crescent.
Compared to the values in the available literature (i.e., J.D. Palmer, Soil Resistivity Measurement and
Analysis, Materials Performance, Volume 13, 1974), the above-mentioned range of soil resistivity
measured leads to soil corrosivity potential as “severe” along Ianhall Road and Bunnell Crescent,
“moderate” along Roding Street, Nash Drive, Hallsport Crescent and Dorking Crescent, and “mild” in
Roding Park and Gade Drive.
The measured water soluble sulphate in soil was generally low and ranged from <20 to 130 µg/g in
Assignment 16-22. In accordance with Table 3 of the Canadian Standards Association (CSA) Series CSA
A23.1-14, soil with the sulphate content ratio less than 0.1% (i.e., 1,000 ppm or µg/g) is not considered
aggressive to concrete. Therefore, in accordance with Table 6 of the CSA Series A23.1-14, Type GU
Portland cement may be used for concrete.
Soil corrosivity should be assessed by a corrosivity expert, if necessary.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 33
5.6.4 Construction Dewatering
The majority of boreholes were dry upon completion of drilling in Assignment 16-22, except for Boreholes
BH 16 and BH 23, where the initial groundwater level was 4.6 m below grade. The subsequent
groundwater monitoring on 2 and 21 November 2018 showed that the groundwater levels were 1.5 m to
6.5 m below the existing grade, with the corresponding elevations ranging from 177.6 m to 150.4 m.
Groundwater level measurements for Assignment 16-22 are summarized in Table 5.10.
Based on the planned sewer invert depths, the soils encountered at the boreholes and the groundwater
depths encountered at the boreholes, localized construction dewatering will likely be required to lower
the groundwater level in Assignment 16-22.
The presence of the sandy / silty soils should be relatively high permeability soil and should be considered
in dewatering planning. Accordingly, a hydrogeological assessment should be conducted for the site in
order to provide construction dewatering requirements in Assignment 16-22.
Water seepage, if encountered, in the native cohesive soils (clayey silt / silty clay / silt and clay, sandy silty
clay / sandy clayey silt till), should be manageable through gravity drainage and/or a filtered sump and
pump system. Within the water-bearing sandy/silty soils, a series of sump and pump or a system of well
points will likely be required for dewatering.
Section 6.0 provides relevant design and construction considerations.
5.7 Slope Stability Analyses for Slopes at Headwalls
As per Drawing Nos. 17-03309-029 and 17-03309-030 shown in Appendix C of this report, three (3)
precast concrete headwalls at slope toes in Roding Park are proposed, i.e., two 'south headwalls' located
underneath an embankment supporting the proposed asphalt walkway at the south of Roding Park (BH
16 in Figure 3), and one 'north headwall' at the northeastern part of Roding Park (BH 37 in Figure 3).
The existing slope at the north headwall was inspected on 17 January 2019 from which site photographs
are shown on Appendix D. At the time of inspection, the slope was approximately 8 m high and its surface
was covered with small trees and bushes. The existing headwall was about 10 m south of Borehole BH 37
location. The top of slope was a parking lot which showed numerous cracks on the asphalt-paved surface.
The mature trees on top of the slope were not inclined. The existing slope appeared to be stable,
although there could be some settlement at the top of the slope as indicated by the cracked pavement.
5.7.1 Slope Conditions Considered in Analyses
Slope stability analyses were conducted at the proposed headwalls located in Roding Park in order to
provide geotechnical recommendations for slopes to be built by backfilling trenches, if open cut is used to
install the sewers and headwalls. The analyses were carried out using the software package GeoStudio
SLOPE/W (Version 7.17) produced by GEO-SLOPE International Limited, employing the Morgenstern-Price
method of analyses with circular slip surfaces.
The following cases were considered for the slope stability analyses:
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 34
South headwalls (BH 16 Location)
• Case 1 – End of construction (replace the loose fill with engineered fill above El 156.0 m and build
walkway embankment with sewer and headwall), with measured groundwater level (El. 152.3 m),
• Case 2 – During service, with assumed groundwater level (El. 157.5 m) representing the probable water
level in the sewer,
• Case 3 – Rapid drawdown from 100-year flood level (El. 158.49 m) to the ground surface, assuming
flood water can seep into the embankment.
North headwall
• Case 1 – Existing slope, effective stress analysis,
• Case 2 – Existing slope, total stress analysis,
• Case 3 – End of construction (i.e., excavate to install the sewer and headwall, and backfill to form slope
over sewer), with no measured groundwater level (dry),
• Case 4 – During service, with assumed groundwater level (El. 162.0 m) representing the probable water
level in the sewer at the outlet (not along the sewer pipe). It should be noted that the soils
surrounding the sewer should be low permeability soils (i.e., clayey silt / silty clay) in order to prevent
surface water seeping into the slope and/or sewer leakage which may lead to groundwater flow within
the slope. Based on the investigation results and the recommended soil types around the sewer, there
should be no groundwater within the slope.
• Case 5 – During service, dry condition.
A surcharge of 10 kPa was applied on the asphalt walkway to represent the pedestrian load. The analytical
results are shown in Figures 4 and 5.
5.7.2 Soil Parameters for Analyses
Based on the findings from Boreholes BH 16, BH 21 and BH 37, the following soil parameters were
considered for the slope stability analyses, as shown in Table 5.14.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 35
Table 5.14: Soil Parameters for Slope Stability Analyses, Roding Park (Assignment 16-22)
Headwall Soil Type Unit Weight
γ (kN/m3)
Total Stress Effective Stress
Cohesion
c (kPa)
Friction Angle
ф (°)
Cohesion
c’ (kPa)
Friction Angle
ф’ (°)
General
Headwall (assumed to
be hard soil) 24 500 0 500 0
Engineered Fill 21 0(1) 30(1) 0(1) 30(1)
South Headwall
(BH 16)
Loose Sandy Silt Fill 18 0 26 0 26
Compact to Dense
Sand Fill 18 0 30 0 30
North Headwall
(BH 21 and BH 37)
Soft to firm Clayey Silt
/ Silty Clay Fill 19 50 0 0(2) 30(2)
Stiff Silty Clay 20 60 0 0(2) 30(2)
Very dense Sand 21 0 32 0 32
Notes:
(1) Applicable to both silty / sandy soil and clayey silt / silty clay soil. To be conservative, cohesion in clayey silt
/ silty clay soil is not considered (i.e., zero).
(2) Conservative long-term analysis since cohesion is not considered.
5.7.3 Results of Slope Stability Analyses – South Headwalls
Detail 1 in Drawing No. 17-03309-030 provided by CIMA+ was used as the cross section for the slope
stability analyses for the south headwalls. As the two headwalls are approximately at the same height,
only one case (the proposed headwall - north of walkway) was selected for slope stability analyses.
To support the walkway embankment with the proposed sewer, the loose sandy silt fill found near the
ground surface should be replaced with engineered fill from approximate El. 156 m up to the final grade.
The engineered fill should extend horizontally at least 5 m beyond both headwalls. Such
recommendation is used in the analytical model. Only deep-seated slip surfaces, i.e., underneath the
headwall and not above the top of the headwall (e.g., slope surface erosion), are considered. The
minimum calculated factors of safety (FOS) for the south headwall are presented in Figures 4.1 to 4.3 for
Case 1 to Case 3, and summarized in Table 5.15.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 36
Table 5.15: Calculated Minimum Safety Factors against Slope Instability – South Headwall
Roding Park (Assignment 16-22)
Case of Analysis
Soil
Parameters
Used
Figure
No.
Groundwater
Elevation
(m)
Minimum
Factor of
Safety (FOS)
Comments
Case 1 – End of construction
Measured groundwater level Total Stress 4.1 152.3 1.97 Stable
Case 2 – During service
Assumed groundwater level Effective Stress 4.2 157.5 1.54 Stable
Case 3 – Rapid drawdown from
100-year flood level (El. 158.49
m) to ground surface, assuming
flood water can seep into the
embankment
Total Stress 4.3 158.5* 1.46
(~ 1.5)
Stable, protect
slope surface
with dense
vegetation
Note: * elevation of 100-year flood level for the area.
The slope stability analysis results presented in Table 5.15 indicate that the south headwall slopes should
be stable, provided that:
(a) The existing loose fill is replaced with engineered fill (above El. 156 m to the final design grade),
(b) The embankment is built with engineered fill,
(c) Slope inclination is equal to or flatter than 2H:1V, and
(d) Protect slope surface with thick vegetation and topsoil.
5.7.4 Results of Slope Stability Analyses – North Headwall
Detail 2 in Drawing No. 17-03309-030 provided by CIMA+ was used as the cross section for slope stability
analyses for the north headwall. As per Detail 2, the proposed slope is 2H:1V with the height from El.
171 m to El. 161 m.
In the analyses, engineered fill was considered as backfill soil forming the slope after open cut excavation
to install the sewer and the headwall. The excavated soil can be reused to backfill the trench if it is clayey
silt / silty clay and can be compacted as engineered fill (Section 6.2), provided that the soil is
environmentally acceptable.
The calculated minimum factors of safety for the north headwall under the five (5) different cases (Section
5.7.1) are presented in Figures 5.1 to 5.5 and summarized in Table 5.16. Since the 100 year flood level is at
El. 158.49 m which is below the lowest ground surface elevation of the slope at El. 161.0 m, rapid
drawdown is not considered in the slope stability analysis.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 37
Table 5.16: Calculated Minimum Safety Factors against Slope Instability – North Headwall
Roding Park (Assignment 16-22)
Case of Analysis
Soil
Parameters
Used
Figure
No.
Groundwater
Elevation (m)
Minimum
Factor of
Safety (FOS)
Comments
Case 1 – Existing slope, (Effective
stress analysis) Effective Stress 5.1 Dry(1) 1.35(2) Stable
Case 2 – Existing slope
(Total stress analysis) Total Stress 5.2 Dry(1) 2.30(2) Stable
Case 3 – End of construction
(backfill trench with engineered
fill), dry condition
Total Stress 5.3 Dry(1) 1.62 Stable (2H:1V
slope)
Case 4 – During service
Assumed groundwater level Effective Stress 5.4 162.0 1.43 Stable
Case 5 – During service, dry
condition Effective Stress 5.5 Dry(1) 1.62
Stable
(Actual slope
condition)
Notes (1) Groundwater was not encountered in the boreholes. (2) The difference in the calculated FOS is due to the soil parameters used.
The analyses indicate that the existing slope should be stable under the current condition, and the new
slope formed by using engineered fill to backfill the trench for installing the sewer and headwall would be
stable, provided that:
(a) The existing fill is replaced with engineered fill,
(b) The slope is built with engineered fill prepared according to Section 6.2. The excavated soil may be
reused as engineered fill if it is clayey silt / silty clay and can be compacted as engineered fill, in
addition to being environmentally acceptable as mentioned in Section 6.2.
(c) Slope inclination is equal to or flatter than 2H:1V,
(d) Protect slope surface with thick vegetation and topsoil.
5.7.5 Conclusions and Recommendations
For the construction of slopes at the proposed headwalls, the following conclusions and
recommendations should be considered in the detail design and construction:
For the south headwalls:
• At least 1 m thick loose fill near the existing ground surface should be removed and replaced
engineered fill. Such replacement should extend horizontally at least 5 m from both headwalls.
• The proposed headwalls should be founded on engineered fill.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 38
• The proposed embankment should be constructed with engineered fill at 2H:1V or flatter slope and its
surface should be protected against erosion by surface water (e.g., thick vegetation, rip-rap on top
geotextile, etc.).
• The inlet / outlet at the headwalls should be protected against erosion by surface water and against
surface water seeping underneath the headwalls.
For the north headwall:
• Trench used to install the sewer and headwall should be backfilled with engineered fill from the sewer
invert up to the final ground surface. The excavated soil may be used as engineered fill if it is clayey
silt / silty clay and can be compacted as engineered fill, together with being environmentally
acceptable.
• The new backfill slope should be constructed at a slope of 2H:1V or flatter and its surface should be
protected against erosion (e.g., thick vegetation, bush, trees, etc.).
• The sewer should be properly sealed against leakage.
• The outlet should be protected against erosion by surface water.
6.0 GENERAL DESIGN AND CONSTRUCTION CONSIDERATIONS
General discussions and recommendations are presented in the following sections. Site specific
information for each project area is provided in Section 4.0 for Assignment 16-12 and Section 5.0 for
Assignment 16-22.
6.1 Site Preparation
Site preparation works for installing the proposed utilities (storm sewers, sanitary sewers and associated
maintenance holes) along the investigated roads will require excavation to depths ranging approximately
from 2.8 m to 13.5 m below the existing grades. Dewatering during site preparation will likely be required
in some areas.
The site preparation would require removing the existing asphaltic concrete pavement, the existing fill
soils and part of the native soils. Any topsoil and deleterious materials encountered during site
preparation should be removed from the founding subgrade.
It is recommended that incompetent soils (e.g., soft clayey soils), if encountered at and/or below the
planned founding elevations, be removed and replaced with engineered fill or equivalent material to
provide a uniform and competent subgrade for utility support. Engineered fill placement is discussed in
Section 6.2. Loose sandy soil subgrade, if encountered, should be re-compacted prior to installing the
proposed utilities. Soft clayey soil subgrade, if encountered, should be replaced with engineered fill.
If unsupported open cut cannot be carried out due to site constraints, temporary shoring will be required.
Temporary shoring is discussed in Section 6.3.2.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 39
6.2 Engineered Fill
Engineered fill should be used to backfill the excavations/soft spots and/or to raise the grade (if required).
Engineered fill should be placed after stripping existing fill materials, any soils containing organic matter
and otherwise unsuitable soils. Engineered fill would then be suitable to support the sewers and
associated maintenance holes. The City of Toronto's standards/specifications for preparing engineered fill
should be followed. Otherwise, engineered fill should be placed in thin layers not exceeding about 200
mm when loose and each fill layer should be uniformly compacted to at least 95 % of its Standard Proctor
Maximum Dry Density (SPMDD).
Excavated soils may be reused if compactable and environmentally-acceptable. For the north slope, the
excavated soils, if to be reused as engineered fill, should be clayey silt / silty clay and compactable as
engineered fill.
6.3 Open Cut Installation Method
The proposed storm and sanitary sewers may be installed by using open cut excavation method. The
proposed maintenance holes could be installed by open cut or augering.
6.3.1 Open Cut Excavation
The proposed storm and sanitary sewers may be installed by open cut in the areas where there are no site
restrictions or by trench excavation with temporary support in the areas where existing structures are
located close to the alignments of the proposed sewers and maintenance holes.
Where temporary shoring is necessary, the recommendations provided in Section 6.3.2 should be
adopted. All excavations should be carried out in accordance with the Occupational Health and Safety Act
and Regulations for Construction Projects. The soils to be excavated can be classified as follows:
Existing fill soils Type 3
Firm silty/clayey soils Type 4
Stiff to very stiff silty/clayey soils Type 3
Hard silty/clayey soils Type 2
Loose silty/sandy soils Type 4
Compact to dense silty/sandy soils Type 3
Very dense silty/sandy soils Type 2
Accordingly, a sideslope of 1H:1V is required for excavations in Type 2 and Type 3 soils in accordance with
the Ontario Health and Safety Regulations. For Type 2 soil, a 1.2 m high vertical cut at the bottom of
excavation may generally be constructed. However, a 1.2 m high vertical cut in silty/sandy soils under
groundwater table may not be stable and flatter slopes may be required. For Type 4 soil, a 3H:1V
sideslope is required.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 40
Near the ground surface, occasional 3H:1V slopes may be required due to loose/soft surficial soils.
Should site boundary or existing structures restrict open cut excavation, a shoring system should be
considered. The shoring system should be designed and approved by a Professional Engineer.
Conventional excavation equipment should be suitable for excavation through the existing fill and native
soils. Cobbles and/or boulders may be encountered during excavation. Water seepage, if encountered
during excavation, should be manageable through appropriate construction dewatering means as
discussed in Section 6.7.
The terms describing the compactness (very loose, loose, compact, dense and very dense) or the
consistency (very soft, soft, firm, stiff, very stiff and hard) of soil give an indication of the effort needed for
excavation. For dense / hard soils, additional efforts, including use of hydraulic impact hammers during
excavation, may be required.
Stockpiles of excavated materials should be kept at least at the same distance as the excavation depth
from the top edge of the excavation to prevent slope instability, subject to confirmation by a Geotechnical
Engineer. Care should also be taken to avoid overloading any existing underground services/structures by
stockpiles.
6.3.2 Temporary Shoring
Temporary shoring may be required during vertical excavation and installation of the proposed storm and
sanitary sewers, and maintenance holes in areas of limited available space. This can be accomplished by a
sheetpile and bracing system or a trench box (or similar) in order to support the sides of the excavation.
The temporary shoring system should be designed by a professional engineer and should resist the lateral
earth, surcharge and hydrostatic pressures which could occur during construction. Bracings should also
be installed within the shoring system to minimize movements of the soils. The temporary shoring system
should be designed in accordance with the Canadian Foundation Engineering Manual’s latest Edition and
the requirements of the Ontario Health and Safety Regulations.
The following soil parameters may be adopted for design:
Coefficient of Lateral Earth Pressure at rest = 0.5
Bulk Unit Weight of Retained Soils = 21 kN/m3
6.3.3 Pipe Bedding
Based on the subsurface soil conditions encountered at the boreholes, Class ‘B’ Type bedding (i.e.,
compacted granular bedding material) or better (i.e., Class ‘A’ Type bedding) should be used for bedding
during installation of the proposed sewers.
A filter fabric (e.g., non-woven geotextile, with FOS of 75 - 150 μm, Class II) should be placed as a
separator underneath the granular bedding material. Due to the presence of silty/sandy soils, a filter
fabric should be placed between all types of granular bedding material and the on-site silty/sandy soil
subgrade to restrict fines migration.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 41
The minimum thickness of granular bedding below the invert should be 150 mm. The thickness of the
bedding may, however, have to be increased depending on the sewer diameter or if wet or weak
subgrade conditions are encountered.
Loose silty/sandy soil subgrade, if encountered and exposed, should be compacted by a vibratory
compactor prior to placing pipe bedding. Very soft to soft clayey soil subgrade, if encountered, may
require Class A bedding and should be covered with lean concrete with a minimum thickness of 100 mm
to provide a workable surface and support to the proposed sewers. Otherwise, the very soft to soft clayey
soil subgrade should be removed and replaced by engineered fill, following the engineered fill placement
procedure as discussed in Section 6.2.
All pipe bedding and pipe cover materials should conform to the requirements of the Ontario Provincial
Standards Drawing Series OPSD 802.033 (Rigid Pipe Bedding, Cover and Backfill Rock Excavation) and/or
OPSD 802.010 (Flexible Pipe Embedment and Backfill – Earth Excavation).
6.3.4 Anti-Seepage Collars
For pipes installed under groundwater table, seepage through the granular pipe bedding and pipe cover
may cause erosion of the silty/sandy soils around the pipes. It is recommended that nominal anti-
seepage collars be provided at regular intervals, where the pipes are installed under groundwater table, to
prevent erosion of the granular soils placed around the pipes and/or loss of native soils around the pipes
through pipe bedding.
Anti-seepage collars should be placed at minimum intervals of lengths not exceeding 50 m along the
sewer alignments. Anti-seepage collars should also be placed at the locations where water seepage
through the pipe bedding to potential drainage outlets is high, including the vicinity of maintenance hole
locations.
The anti-seepage collar may consist of a clay plug (or similar material) surrounding the sewer pipe. A
typical clay plug should be about 1.0 m thick and extend laterally to a minimum distance of 0.5 m from
the pipe circumference.
The on-site native clayey soils should be suitable for such purpose. The excavated cohesive soils should
be confirmed as suitable clayey soils by carrying out geotechnical testing, including determination of
index properties and gradation, prior to utilization.
Uniform compaction of the soil around the collar may be difficult, depending on soil characteristics. It is
recommended that the compaction around the collars be carried out with adequate equipment and
compaction methods.
6.4 Excavation Backfill
Based on the visual and tactile examination of the soil samples, the on-site excavated fill soils (sandy
gravel, gravelly sand, sand, silty sand, sandy silt, clayey silt and silty clay), and the native soils (clayey silt /
silty clay / silt and clay, sandy silty clay to sandy clayey silt till, sandy silt to sand and silt till, and sand) may
be re-used as backfill soils in service trenches provided that all organic matters and deleterious materials,
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 42
if any, are removed and their water contents are approximately within 2 % of the optimum water
content.
The clayey soils will likely be excavated in cohesive chunks or blocks that will be difficult to handle and
compact. For use as backfill, these blocks should be reduced to less than 100 mm in size, placed in thin
layers, and compacted using suitable heavy equipment, particularly in narrow trenches.
Unless clayey soils are properly reduced in size and compacted in sufficiently thin lifts, post-construction
settlement could occur. It is therefore, recommended that in settlement-sensitive areas (i.e., along
investigated roads), granular materials be used as backfill to minimize subsequent settlement. Such
materials should be tested and approved by a Geotechnical Engineer prior to backfilling.
The on-site excavated soils may need reconditioning (e.g., drying) prior to use. The backfill material
should be placed according to the City of Toronto's standards/specifications. Alternatively, the backfill
should be placed in maximum 200 mm thick layers within ± 2 % of their optimum water content, and each
layer should be compacted to at least 95 % Standard Proctor Maximum Dry Density. This value should be
increased to at least 98 % within 0.6 m below the top surface of the backfill (i.e., the bottom of road sub-
base) to minimize road settlement.
The on-site excavated soils should not be used in confined areas (e.g., narrow trenches) where heavy
compaction equipment cannot be operated. The use of good backfill together with an appropriate frost
taper would be preferable in confined areas. Unsuitable material such as organic soils, boulders, cobbles,
frozen soils, etc., should not be used for backfilling.
It is recommended that frost taper be provided at backfilled trenches, along the roads to be excavated, to
promote gradual transition from the frost-free materials to the frost susceptible in-situ soils, otherwise
differential frost heaving may occur. Frost taper would not be necessary if the backfill material can be
matched within the frost zone (i.e., within about 1.2 m depth below the pavement surfaces) with the
subgrade-type material.
6.5 Trenchless Considerations
Trenchless installation methods may be considered for the installation of the proposed utilities along
some roads where the open cut construction method cannot be used due to the site constraints (e.g.,
underground utilities, trees), or due to deep excavation depth.
If tunnelling is considered in some areas, applicable recommendations to trenchless installation should be
developed for the design and construction. Additional investigation may be required.
6.6 Foundations
The subsurface investigation results indicated that the proposed maintenance holes and headwalls would
be founded within highly-variable soil types and consistency/compactness, together with different
groundwater conditions. It should be cautioned that loose silty soils under high groundwater level and
soft clayey soils are present in some localized areas (as shown in Record of Boreholes), which would cause
difficulty in construction and lead to relatively-low bearing capacity.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 43
The existing fill soils are not, generally, considered suitable for supporting heavy loads due to possible
non-homogeneous compaction. Accordingly, the existing fill soils should be replaced by engineered fill
following the fill placement procedures as discussed in Section 6.2.
In general, most native soils would be suitable to provide adequate support for the proposed
maintenance holes.
Recommended geotechnical reactions / resistances for the founding stratum for the proposed
maintenance holes are summarizes in Table 4.8 in Section 4.0 for Assignment 16-12, and Table 5.12 in
Section 5.0 for Assignment 16-22.
For foundations designed and constructed as recommended in Sections 4.6.2 and 5.6.2 and in accordance
with good construction practice, the SLS soil bearing values provided would correspond to total and
differential settlements of not more than 25 mm and 20 mm, respectively. More representative values of
SLS/ULS soil bearing pressures, if required, should be estimated by conducting detailed foundation
analysis. In order to achieve the SLS/ULS soil bearing pressures as indicated in Table 4.8 and Table 5.12,
the exposed subgrade should be free of loose/soft, disturbed wet or otherwise deleterious materials.
The subgrade should be inspected and evaluated by a geotechnical engineer to confirm that the
proposed maintenance holes and headwalls are founded on competent subgrade capable of supporting
the recommended design pressures. The exposed subgrade should not be disturbed by construction
activities. Groundwater level, if encountered, should be lowered to at least 1.0 m below the lowest
foundation subgrade level during construction to maintain dry working conditions and stable excavation
bottom and slopes.
6.7 General Construction Dewatering Considerations
The groundwater levels encountered during drilling boreholes and measured in the monitoring wells are
provided on the Record of Boreholes and summarized in Table 4.6 for Assignment 16-12 and Table 5.10
for Assignment 16-22.
Based on the proposed sewer invert depths, the soils encountered at the boreholes and the groundwater
conditions, construction dewatering will likely be required in some areas during installation of the
proposed sewers and maintenance holes.
As the measured groundwater levels are higher than the majority of the proposed sewer invert elevations,
it is recommended that a hydrogeological site assessment be conducted for Assignments 16-12 and 16-
22 to assess any construction dewatering requirements and the associated level of dewatering effort
pertaining to construction along each road section to be excavated.
Water seepage, if encountered, in clayey soils, should be manageable through gravity drainage and/or a
filtered sump and pump system. Within the water-bearing silty / sandy soils, a series of sump and pump
or a system of well points may be required for dewatering.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 44
6.8 Earthquake Considerations
In conformance with the criteria in Table 4.1.8.4.A, Part 4, Division B of the Ontario Building Code (2012),
the project site may generally be classified as Site Class “D-Stiff Soil”.
The four (4) values of the spectral response acceleration, Sa (T), for different periods and the Peak Ground
Acceleration (PGA) can be obtained from Table C-2 in Appendix C, Division B of the National Building
Code (2010).
The design values of Fa and Fv for the project site should be determined in accordance with Table
4.1.8.4.B and Table 4.1.8.4.C in Part 4, Division B of the Ontario Building Code (2012).
6.9 Pavement Structure
To replace the existing pavement along the roads after excavation for installing sewers, the standard
pavement structure of the City of Toronto should be used.
7.0 ENVIRONMENTAL SOIL QUALITY ASSESSMENT
7.1 Methodology
The evaluation of the potential Contaminants of Concern (CofC) for Assignment 16-12 was based on a
cursory review of the City of Toronto and Google Maps aerial photographs only. Completion of Phase I
Environmental Site Assessments (ESAs) was not included the scope of work for this assignment nor was
Wood provided with Phase I or Phase II ESAs by others to evaluate the CofCs.
From a review of 1940s to current City of Toronto and Google Maps aerial photographs, it was noted that
the areas investigated, and their surrounding properties were previously occupied by agricultural land
uses and are currently residential. Based on the aerial photograph review, potential COCs are
metals/inorganics parameters, PHCs, VOCs, PAHs, and PCBs in fill and OC-pesticides in landscaped/grassy
areas.
The soil samples retrieved during drilling were examined for visual and/or olfactory indicators of impact
and subsequently split into duplicate fractions. The primary sample fractions were placed into appropriate
sample containers provided by the laboratory and stored in ice-packed coolers for future laboratory
analysis. The duplicate sample fractions were placed in resealable plastic sample bags and stored at
ambient temperature for subsequent field vapour screening.
The duplicate sample fractions were field screened for combustible organic vapours (COVs) and total
organic vapours (TOVs) to assist in selecting the samples to be sent for laboratory analysis. The soil
samples were stored and sealed in resealable plastic bags and allowed to reach a temperature of
approximately 20 degrees Celsius. The soil vapours were measured with an RKI Eagle 2 (“Eagle”) organic
vapour meter calibrated using hexane gas (1,650 ppm) and isobutylene (100 ppm).
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 45
Each of the samples selected for chemical analysis were labelled using a unique identifier (borehole of
origin and sample interval) except for blind duplicate samples that were collected for Quality
Assurance/Quality Control (QA/QC) purposes that were assigned an alias. All primary samples were
stored in coolers on ice after collection and during transportation to the laboratory, Maxxam Analytics,
where they were delivered under continuous Chain of Custody documentation. Maxxam Analytics is
accredited in accordance with the International Standard ISO/IEC 17025 by the Standards Council of
Canada and has met the standards for parameters set out in the Soil, Ground Water and Sediment
Standards for Use Under Part XV.1 of the Environmental Protection Act”, dated 15 April 2011.
7.2 Regulatory Framework
Soil quality was evaluated with respect to the regulatory requirements for contaminated sites in Ontario
established by Ontario Regulation 153/04 - Records of Site Condition, Part XV.1 of the Environmental
Protection Act (EPA), dated 15 April 2011, as amended (“O.Reg.153/04”).
The evaluation was completed by comparing the bulk analytical results to the Generic Site Condition
Standards (SCS) set out under O.Reg.153/04. The following assessment criteria were used for evaluation
of the results:
• Table 1 Full Depth Background SCS for residential / parkland / institutional / industrial / commercial /
community property use (Table 1 SCS). The Table 1 SCS would be applicable when assessing surplus
soil for off-site management when the receiving site type is unknown, is considered environmentally
sensitive, or is licensed to receive inert fill only.
• Table 2 Full Depth Generic SCS in a potable groundwater condition for industrial / commercial /
community property use and coarse textured soils (Table 2 SCS). The Table 2 SCS would be applicable
when assessing evaluating alternative locations for off-site soil management at a receiver site within a
potable ground water condition.
• Table 3 Full Depth Generic SCS in a non-potable groundwater condition for industrial / commercial /
community property use and coarse textured soils (Table 3 SCS). The Table 3 SCS would be applicable
when assessing surplus soil for off-site management at a receiver site within a non-potable ground
water condition.
In addition, the following assessment criteria were used to evaluate the soil quality for disposal purposes:
1. Schedule 4 Leachate Quality Criteria as outlined under Ontario Regulation 347/90, as amended.
7.3 Field and Soil Analytical Results, Assignment 16-12
Field screening soil samples were collected from each SPT interval at every borehole. The maximum
measured COV was 5 ppmv and the TOVs were non-detectable. No staining, debris, or odour were noted
in the screening samples. The measured COV and TOV are presented in the Records of Boreholes and in
analytical results Tables 1 to 5 (Appendix F1).
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 46
The results of the soil sample analyses along with the applicable SCS are summarized in Tables 1 through
6 (Appendices F1 and G1) and copies of the laboratory Certificates of Analyses are presented in Appendix
H. A summary of the samples exceeding the SCS for each of the analysed chemical parameter groups
(Section 3.4) is described in Sections 7.3.1 through 7.3.6.
7.3.1 Metals and Inorganics
The results of the metals and inorganics analyses and their respective SCS are presented in Table 1,
Appendix F1.
pH
The pH of surface soil samples (i.e., samples from a depth of less than 1.5 mbgs) ranged from 7.70 to 7.87
which is within the applicable range of 5 to 9 for surface soil as required for the application of the Generic
SCS.
The pH of sub-surface soil samples (i.e. samples from depths greater than 1.5 mbgs) ranged from 7.35 to
7.75 which is within the applicable pH range of 5 to 11 for sub-surface soil as required for the application
of the Generic SCS.
Electrical Conductivity (EC)
Table 3 SCS Exceedances – BH 1 SS2 (0.8-1.4 mbgs) and BH 13 SS4 (2.3 – 2.9 mbgs).
Table 1 SCS Exceedances - Three (3) soil samples, BH 7 SS2 (0.8 – 1.4 mbgs), BH 9 SS-2 (0.8 – 1.4 mbgs),
BH 11 SS4 (2.3 – 2.9 mbgs) had levels that exceeded the Table 1 SCS but were below the Table 2 and
Table 3 SCS.
The remaining four (4) samples met the SCS.
Sodium Adsorption Ratio (SAR)
Table 3 SCS Exceedances – BH 7 SS2 (0.8 – 1.4 mbgs), BH 9 SS2 (0.8 – 1.4 mbgs), BH 11 SS4 (2.3 – 2.9
mbgs).
Table 1 SCS Exceedances – BH 1 SS2 (0.8 – 1.4 mbgs), BH 3 SS2 (0.8 – 1.4 mbgs), BH 5 SS2 (0.8 – 1.4
mbgs), and BH 13 SS4 (2.3 – 2.9 mbgs), had levels that exceeded the Table 1 SCS, but were below the
Table 2 and Table 3 SCS.
The remaining two (2) samples met the SCS.
Cyanide
All nine (9) samples had measured concentrations of cyanide below the Table 1, Table 2, and Table 3 SCS.
Metals
All nine (9) samples had measured concentrations of metals below the Table 1, Table 2, and Table 3 SCS.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 47
7.3.2 Petroleum Hydrocarbons Fractions (PHC F1-F4) and BTEX
The results of the PHC F1-F4 and BTEX analyses and their respective SCS are contained in Table 2 in
Appendix 1.
Table 1 SCS Exceedance – BH 15 SS3 (1.5 – 2.1 mbgs) has a PHC F4 concentration that exceeded the Table
1 SCS, but it was below the Table 2 and Table 3 SCS. BH 3 SS2 (0.8 – 1.4 mbgs) had Reportable Detection
Limits (RDLs) (Section 7.5) for benzene and xylenes that exceeded the Table 1 SCS but was below the
Table 2 and Table 3 SCS.
The remaining seven (7) samples met the SCS.
7.3.3 Volatile Organic Compounds (VOCs)
The results of the VOCs analyses are summarized in Table 3, Appendix F1. VOCs were not detected in the
analysed soil samples, so VOCs meet the SCS.
7.3.4 Polycyclic Aromatic Hydrocarbons (PAHs)
The results of the PAHs analyses are summarized in Table 4, Appendix F1. The analysed soil samples had
PAH concentrations that were below the SCS.
7.3.5 Polychlorinated Biphenyls (PCBs)
Three (3) soil samples were submitted for laboratory analyses of PCBs. The results of the PCBs analyses
are summarized in Table 5, Appendix F1. PCBs were not detected in the analysed soil samples, so PCBs
would meet the SCS.
7.3.6 Organochlorine Pesticides
The results of the OC-pesticides analysis are summarized in Table 5, Appendix F1. OC-pesticides were not
detected, so OC-pesticides would meet the SCS.
7.3.7 Regulation 347 Waste Characterization
The results of the O. 347, as amended leachate analyses and their respective Schedule 4 Leachate Quality
Criteria are summarized in Table 6, Appendix G1. Based on the results of these analyses, all parameters
were within the leachate quality criteria for inorganics, metals, VOCs, benzo(a)pyrene, PCBs, and the
sample was not characterized as ignitable.
7.4 Field and Soil Analytical Results, Assignment 16-22
Field screening soil samples were collected from each SPT interval at every borehole. The maximum
measured COV was 10 ppmv and the TOVs were non-detectable. No staining, debris, or odour were noted
in the screening samples. The measured COV and TOV are presented in the borehole logs (Appended)
and in analytical results Tables 1 to 5 (Appendix F2).
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 48
The results of the soil sample analyses along with the applicable SCS are summarized in Tables 1 through
6 (Appendix F2) and copies of the laboratory Certificates of Analyses are presented in Appendix H. A
summary of the samples exceeding the SCS for each of the analyzed chemical parameter groups (Section
3.4) is described in Sections 7.4.1 through 7.4.6.
7.4.1 Metals and Inorganics
The results of the metals and inorganics analyses and their respective SCS are presented in Table 1,
Appendix F2.
pH
The pH of surface soil samples (i.e., samples from a depth of less than 1.5 mbgs) ranged from 7.39 to 7.84
which is within the applicable range of 5 to 9 for surface soil as required for the application of the Generic
SCS.
The pH of sub-surface soil samples (i.e. samples from depths greater than 1.5 mbgs) ranged from 7.21 to
7.85 which is within the applicable pH range of 5 to 11 for sub-surface soil as required for the application
of the Generic SCS. Note: the 7.21 pH is based on the average pH for sample BH 23 SS3 and its duplicate
BH 23 DUP2.
Electrical Conductivity (EC)
Table 1 SCS Exceedances – BH 19 SS2 (0.8 – 1.4 mbgs), BH 21 SS2 (0.8 – 1.4 mbgs), BH23 SS3 (1.5 – 2.1
mbgs) and its duplicate BH 23 DUP2, BH27 SS3 (1.5 –2.1 mbgs), BH 27 SS3 (1.5 – 2.1 mbgs), BH 29 SS2
(0.8 – 1.4 mbgs) and its duplicate BH 29 DUP1, BH 32 SS2 (0.8 – 1.4 mbgs) and BH 35 SS2 (0.8 – 1.4 mbgs),
exceeded the Table 1 SCS, but were below the Table 2 and Table 3 SCS, for EC.
The remaining four (4) samples met the SCS for EC.
Sodium Adsorption Ratio (SAR)
Table 3 SCS Exceedances – BH 19 SS2 (0.8 – 1.4 mbgs), BH 27 SS3 (1.5 – 2.1 mbgs), BH 29 SS2 (0.8 – 1.4
mbgs) and its duplicate BH 29 DUP1. Note: the SAR exceedance for BH 29 SS2 (0.8 – 1.4 mbgs) and its
duplicate BH 29 DUP1 is based on their average.
Table 1 SCS Exceedances – BH 21 SS2 (0.8 – 1.4 mbgs), BH 23 SS3 (1.5 – 2.1 mbgs) and its duplicate BH 23
DUP2, BH 25 SS2 (0.8 – 1.4 mbgs), BH 32 SS2 (0.8 –1.4 mbgs) and BH 35 SS2 (0.8 – 1.4 mbgs), exceeded
the Table 1 SCS, but were below the Table 2 and Table 3 SCS.
The remaining three (3) samples met the SCS.
Cyanide
All eleven (11) samples, and the two (2) field duplicates, had measured concentrations of cyanide below its
Table 1, Table 2, and Table 3 SCS.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 49
Metals
All eleven (11) samples, and the two (2) field duplicates, had measured concentrations of metals below
their Table 1, Table 2, and Table 3 SCS.
7.4.2 Petroleum Hydrocarbons Fractions (PHC F1-F4) and BTEX
The results of the PHC F1-F4 and BTEX analyses are summarized in Table 2, Appendix F2.
Table 1 SCS Exceedance – BH 27 SS3 (1.5 - 2.1 mbgs) had Reportable Detection Limits (RDLs) (Section 7.5)
that exceeded Table 1 SCS but was below the Table 2 and Table 3 SCS for benzene and xylenes.
The remaining ten (10) samples and two (2) field duplicate samples met the SCS.
7.4.3 Volatile Organic Compounds (VOCs)
The results of the VOCs analyses are summarized in Table 3, Appendix F2. As shown, VOCs were not
detected, so they would meet the SCS.
7.4.4 Polycyclic Aromatic Hydrocarbons (PAHs)
The results of the PAHs analyses are summarized in Table 4, Appendix F2. The analysed soil samples had
PAH concentrations that were below the SCS.
7.4.5 Polychlorinated Biphenyls (PCBs)
The results of the PCBs analyses are summarized in Table 5, Appendix F2. The analysed soil samples had
PCB concentrations that were below the SCS.
7.4.6 Organochlorine Pesticides
The results of the OC-pesticides analyses are summarized in Table 5, Appendix F2. The analysed soil
samples had OC-pesticide concentrations that were below the SCS.
7.4.7 Regulation 347 Waste Characterization
The results of the Reg. 347, as amended, leachate analyses and their respective Schedule 4 Leachate
Quality Criteria are summarized in Table 6, Appendix G2. Based on the results of these analyses, all
parameters were within the leachate quality criteria for inorganics, metals, VOCs, benzo(a)pyrene, PCBs,
and the sample was not characterized as ignitable.
7.5 Quality Assurance Program
In addition to field activities pertaining to quality assurance (decontamination of non-dedicated
equipment, instrument calibration, etc.), an analytical quality assurance program was also implemented.
The analytical quality assurance program usually includes the collection of blind duplicate samples. As the
drilling program for Assignments 16-12 and 16-22 was completed concurrently, blind duplicate soil
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 50
samples which are also collected for the quality assurance program were collected from Assignment 16-
12.
The validity of the analytical results reported for the samples collected during this investigation has been
assessed using the criteria presented in Protocol for Analytical Methods Used in the Assessment of
Properties under Part XV.1 of the Environmental Protection Act, 09 March 2004, amended as of 01 July
2011 (the “Analytical Protocol”). The Analytical Protocol establishes Acceptance Limits for use when
assessing the reliability of data reported by analytical laboratories. These include maximum hold times for
the storage of samples/sample extracts between collection and analysis, specified/approved analytical
methods, required field and/or laboratory quality assurance samples such as blanks and field and
laboratory duplicate, specified recovery ranges for spiked samples and surrogates (compounds added to
samples in known concentrations for data validation purposes), required Reporting Limits and specified
precision required when analysing laboratory duplicate samples.
It should be noted that the requirements of the Analytical Protocol are applicable to analytical data used
in support of the filing of a Record of Site Condition and that their use on other types of projects is on a
best scientific practice basis rather than as a mandatory requirement.
The results of the QA/QC analyses are included on the laboratory Certificates of Analyses presented in
Appendices F for Assignments 16-12 and 16-22 and are further discussed in Appendices H1 (Assignment
16-12) and H2 (Assignment 16-22).
Based on the results reported for the laboratory and field quality control samples, it is considered that
laboratory analysis, sample collection, sample storage, and transportation of the samples to the
laboratory, had no material effect on the quality of the analytical results reported for the collected soil
samples except for sample BH3 SS2 (0.8 – 1.4 mbgs) (Assignment 16 – 12 and BH27 SS3 (1.5-2.1 mbgs)
(Assignment 16-22). Due to elevated Reportable Detection Limits for benzene and xylenes in both of the
subject samples, there is uncertainty as to whether the actual concentrations of the subject analytes
exceed the Table 1 SCS.
7.6 Conclusions and Recommendations
1. Based on the limited soil chemical analyses results currently available, the quality of excess soil
generated during the program is expected to be variable and as such, soil quality will need to be
monitored during excavation activities.
2. Additional sampling may be required to delineate and define the extent of impact above the Table 1
SCS and to ensure appropriate management/disposal of the excess soil. If stockpiling of soil is not
permitted during construction, additional sampling may be required prior to initiating the
construction activities.
3. Excess soils with concentrations of benzene, and xylenes exceeding the Table 1 SCS may not be
suitable for offsite management at un-regulated receiver sites without additional volume / area-
based characterization and management unless otherwise confirmed by the receiver’s Site’s Qualified
Person (QP) as part of a Fill Management Plan.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 51
4. Soils with concentrations exceeding the Table 1 SCS are not considered to be inert fill but can be
disposed at MECP authorized disposal sites or to a suitable receiver that accepts soil meeting Table
2/3 SCS.
5. As per the guidelines of the MECP document entitled, Management of Excess Soils: A Guide for Best
Management Practices, dated 06 June 2017, these soil sampling results should be used in the
preparation of an excess Soil Management Plan authored by a QP before excess soils are removed
for offsite management/disposal. Note: the MECP are currently preparing proposed regulations for
the management of excess soil. If the new regulations are approved and enacted before
construction, their requirements will need to be fulfilled.
The characterization and assessment of soil were based on Wood’s understanding of site conditions and
available information at the time of the geotechnical investigation. Phase I and Phase II ESAs have not
been conducted by Wood for the Site and Wood does not warrant that the analytical schedule addresses
all the potential environmental issues at the site. The soil chemical analyses results are preliminary and
not intended to provide a complete assessment of conditions at the Site. Further assessment and/or
chemical analyses would be considered appropriate depending on the soil management option selected
and/or receiver’s requirements.
8.0 BULK ASBESTOS ANALYSES
8.1 Scope of Work
The geotechnical fieldwork included retrieval of asphaltic core samples from existing asphaltic concrete
pavement for the purposes of determination of asbestos content. A total of forty-two (42) asphaltic core
samples were collected before the geotechnical investigation, which consisted of ten (10) asphaltic
concrete core samples collected at Assignment 16-12 and thirty-two (32) asphaltic concrete core samples
collected at Assignment 16-22.
The asphaltic concrete core locations for Assignments 16-12 and 16-22 are provided in Tables 4.7 and
5.11 respectively.
Asphalt samples were submitted under chain of custody protocol to an accredited laboratory for analysis
to determine asbestos content.
8.2 Methodology
Asphaltic concrete was encountered at the ground surface at all boreholes located on road sections and
the asphaltic core samples were collected. Based on existing information regarding the existing asphalt
and visual observations at the time of sampling, each street was considered to be a unique location.
Despite the laboratory layering out two (2) phases within the individual core samples, Wood did not
visually observe specific distinctions within individual core samples to indicate distinct separable layers.
As such, each asphalt core to be disturbed during this project is considered to be a homogeneous material.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 52
The asphaltic core samples were submitted under chain of custody protocol to EMC Scientific Incorporated
(“EMC”) in Mississauga, Ontario for asbestos analysis. The core samples were reduced in volume by EMC
staff so that the subsequent samples (sub-samples) were representative of the entire depth of the original
core samples. EMC is accredited for bulk asbestos fiber analysis by the National Voluntary Laboratory
Accreditation Program (NVLAP).
Bulk samples of suspected asbestos-containing materials (ACMs) are analyzed following polarized light
microscopy (PLM) methodology. This method is specified by Ontario Regulation 278/05 “Designated
Substance – Asbestos On Construction Projects And In Buildings And Repair Operations” (O. Reg. 278/05) for
establishing whether the material is an ACM and defining the content and type of asbestos, if any. However,
in certain non-friable organically bound (NOB) materials (such as asphalt), small asbestos fibres may be
missed by PLM due to resolution limitations of the optical microscope that can result in a false negative
analytical result. Transmission Electron Microscopy (TEM) can be used as a confirmatory technique for
asbestos composition. TEM analysis is more sensitive than PLM analysis and is generally regarded as more
definitive regarding asbestos analysis. TEM analysis was not included in this project.
A material is considered to be an ACM if the content of asbestos is 0.5% or greater in accordance with O.
Reg. 278/05. Further, as per Section 3(4) of O. Reg. 278/05, “if analysis establishes that a bulk material
sample contains 0.5 per cent or more asbestos by dry weight, the entire area of homogeneous material from
which the bulk material sample was taken is deemed to be asbestos-containing material.”
8.3 Summary of Results
Analytical Certificates of Analysis for asphaltic concrete core samples are attached in Appendix J for
Assignment 16-12 and Assignment 16-22 in this report, and the analysis results for the asphaltic concrete
core samples at Assignment 16-12 are presented in Table 8.1 below:
Table 8.1: Asbestos Bulk Sampling Analytical Results (Assignment 16-12)
Sample
No. Lab Sample ID Sample Location Description
Friable/Non-
Friable
Laboratory Results
Asbestos
Fibres (%)
Asbestos
Types
C1 A43576-1 Gracefield Avenue N/A None Detected
C2 A43576-2 Gracefield Avenue N/A None Detected
C3 A43576-3 Gracefield Avenue N/A None Detected
C4 A43576-4 Gracefield Avenue N/A None Detected
C5 A43576-5 Gracefield Avenue N/A None Detected
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 53
Sample
No. Lab Sample ID Sample Location Description
Friable/Non-
Friable
Laboratory Results
Asbestos
Fibres (%)
Asbestos
Types
C6 A43576-6 Gracefield Avenue Non-Friable
0.5% Chrysotile
1% Chrysotile
C7 A43576-7 Gracefield Avenue N/A None Detected
C8 A43576-8 Gracefield Avenue and Keele
Street N/A <0.5% Chrysotile
C9 A43576-9 Keele Street N/A None Detected
C10 A43576-10 Keele Street N/A None Detected
Note:
An asbestos-containing material is defined as a material that contains to 0.5, or greater, percent asbestos by dry
weight in accordance with O. Reg. 278/05.
The analysis results for the asphaltic concrete core samples for Assignment 16-22 are presented in Table
8.2 below:
Table 8.2: Asbestos Bulk Sampling Analytical Results (Assignment 16-22)
Sample
No. Lab Sample ID Sample Location
Friable/Non-
Friable
Laboratory Results
Asbestos
Fibres (%)
Asbestos
Types
C11 A43576-11 Ianhall Road N/A None Detected
C12 A43576-12 Ianhall Road N/A None Detected
C13 A43576-13 Gade Drive N/A None Detected
C14 A43576-14 Gade Drive N/A <0.5% Chrysotile
C15 A43576-15 Gade Drive and Roding Street N/A None Detected
C16 A43576-16 Roding Park Entrance N/A None Detected
C17 A43576-17 Roding Street and Nash Drive N/A None Detected
C18 A43576-18 Nash Drive N/A None Detected
C19 A43576-19 Nash Drive N/A None Detected
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 54
Sample
No. Lab Sample ID Sample Location
Friable/Non-
Friable
Laboratory Results
Asbestos
Fibres (%)
Asbestos
Types
C20 A43576-20 Nash Drive N/A None Detected
C21 A43576-21 Nash Drive and Gade Drive N/A None Detected
C22 A43576-22 Nash Drive N/A None Detected
C23 A43576-23 Nash Drive N/A None Detected
C24 A43576-24 Nash Drive N/A None Detected
C25 A43576-25 Bunnell Crescent N/A None Detected
C26 A43576-26 Bunnell Crescent N/A None Detected
C27 A43576-27 Bunnell Crescent N/A None Detected
C28 A43576-28 Bunnell Crescent N/A None Detected
C29 A43576-29 Nash Drive and Bunnell
Crescent N/A None Detected
C30 A43576-30 Between 43 Nash Drive and 35
Hallsport Crescent N/A None Detected
C31 A43576-31 Bunnell Crescent and Hallsport
Crescent N/A None Detected
C32 A43576-32 Hallsport Crescent N/A None Detected
C33 A43576-33 Hallsport Crescent N/A None Detected
C34 A43576-34 Hallsport Crescent N/A None Detected
C35 A43576-35 Hallsport Crescent N/A None Detected
C36 A43576-36 Hallsport Crescent N/A None Detected
C37 A43576-37 Hallsport Crescent and Agate
Road N/A None Detected
C38 A43576-38 Dorking Crescent N/A None Detected
C39 A43576-39 Dorking Crescent N/A None Detected
C40 A43576-40 Dorking Crescent N/A None Detected
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 55
Sample
No. Lab Sample ID Sample Location
Friable/Non-
Friable
Laboratory Results
Asbestos
Fibres (%)
Asbestos
Types
C41 A43576-41 Dorking Crescent N/A None Detected
C42 A43576-42 Dorking Crescent N/A None Detected
Note:
An asbestos-containing material is defined as a material that contains to 0.5, or greater, percent asbestos by dry
weight in accordance with O. Reg. 278/05.
8.4 Discussion and Conclusions
8.4.1 Assignment 16-12
Results of analysis of the ten (10) asphaltic core samples collected from Assignment 13-12 indicate the
following:
• One (1) sample, C6 (Lab Sample #A43576-6), Table 8.1, was found to contain chrysotile asbestos
(identified as 0.5% chrysotile in one laboratory identified layer and 1% chrysotile in a second laboratory
identified layer).
• One (1) sample, C8 (Lab Sample #A43576-8), Table 8.1, was found to contain <0.5% chrysotile
asbestos, which is not considered to be asbestos-containing as per O. Reg. 278/05.
• Asbestos was not detected in the remaining nine (9) samples.
Based on the results of analysis, the asphalt sampled in Assignment 16-12 along Gracefield Avenue was
found to contain asbestos.
8.4.2 Assignment 16-22
Results of analysis of the thirty-two (32) asphaltic core samples collected from Assignment 16-22 indicate
the following:
• One (1) sample, C14 (Lab Sample #A43576-14), Table 8.2, was found to contain <0.5% chrysotile
asbestos, which is not considered to be asbestos-containing as per O. Reg. 278/05.
• Asbestos was not detected in the remaining thirty-one (31) samples in Assignment 16-22.
All asphaltic concrete to be disturbed during this project are considered to be a homogeneous material as
noted by street and road locations above. In accordance with O. Reg. 278/05, correspondingly, all asphaltic
concrete road sections having asbestos-containing cores should be treated as asbestos-containing and
handled in accordance with O. Reg. 278/05. This includes all asphaltic concrete road along Gracefield
Avenue in Assignment 16-12.
CIMA Canada Inc.
Geotechnical Investigation Report
Basement Flooding Protection Program Phase 4 (BFPP4)
Assignment 16-12 and Assignment 16-22
Wood Reference No.: TT183004
19 March 2019
Page 56
Asphaltic concrete along the remaining roads in Assignment 16-12 and 16-22 are considered to be non-
asbestos-containing as per O. Reg. 278/05.
All ACM must be removed from the work area prior to renovation and/or demolition projects. Removal or
abatement of ACM must be completed by a qualified asbestos abatement worker and in accordance with
the requirements of O. Reg. 278/05.
9.0 CLOSURE
The subsurface soil conditions and recommendations contained in this report should be used solely for
the purpose of design of the project. All the works were conducted under the Terms and Conditions which
form a part of CIMA+’s Purchase Order B2018-002331 and a change order issued on 12 October 2018, for
one additional borehole at the proposed headwall location.
It is recommended that Wood, formerly Amec Foster Wheeler, be retained to review the subsurface
information and recommendations for this specific applicability, once the details of the development are
available and prior to the final design stage of the project. Additional borehole investigation and analyses
may be required to fulfil the final design requirements.
The environmental part of this report was prepared by Edwin Whitford, P. Eng. and reviewed by Ian
Powell, P. Geo.; the bulk asbestos analyses was prepared by Lisa Scolaro, ROH, CRSP, CHSC and reviewed
by Rita Korczynski, PhD, CIH, CRSP; and the geotechnical part of this report was prepared by Wenqi
(Linda) Ji, M. Sc., P. Eng., P. Geo. A senior technical review of the report was completed by Prapote
Boonsinsuk, Ph.D., P. Eng.
The attached Limitations to Geotechnical Reports are an integral part of this report.
Sincerely,
Wood Environment & Infrastructure Solutions
a Division of Wood Canada Limited
Prepared by: Reviewed by:
Wenqi (Linda) Ji, M.Sc. P. Eng., P. Geo. Prapote Boonsinsuk, Ph.D., P. Eng.
Project Manager/Senior Geotechnical Engineer Principal Geotechnical Engineer
LIMITATIONS TO GEOTECHNICAL REPORTS
1. The work performed in the preparation of this report and the conclusions presented herein are subject to the
following:
a) The contract between Wood and the Client, including any subsequent written amendment or Change Order dully signed by the parties (hereinafter together referred as the “Contract”);
b) Any and all time, budgetary, access and/or site disturbance, risk management preferences, constraints or
restrictions as described in the contract, in this report, or in any subsequent communication sent by Wood
to the Client in connection to the Contract; and
c) The limitations stated herein.
2. Standard of care: Wood has prepared this report in a manner consistent with the level of skill and are ordinarily
exercised by reputable members of Wood’s profession, practicing in the same or similar locality at the time of
performance, and subject to the time limits and physical constraints applicable to the scope of work, and terms
and conditions for this assignment. No other warranty, guaranty, or representation, expressed or implied, is
made or intended in this report, or in any other communication (oral or written) related to this project. The
same are specifically disclaimed, including the implied warranties of merchantability and fitness for a particular
purpose.
3. Limited locations: The information contained in this report is restricted to the site and structures evaluated by Wood and to the topics specifically discussed in it, and is not applicable to any other aspects, areas or locations.
4. Information utilized: The information, conclusions and estimates contained in this report are based exclusively on:
i) information available at the time of preparation, ii) the accuracy and completeness of data supplied by the Client
or by third parties as instructed by the Client, and iii) the assumptions, conditions and qualifications/limitations set
forth in this report.
5. Accuracy of information: No attempt has been made to verify the accuracy of any information provided by the
Client or third parties, except as specifically stated in this report (hereinafter “Supplied Data”). Wood cannot be held
responsible for any loss or damage, of either contractual or extra-contractual nature, resulting from conclusions that
are based upon reliance on the Supplied Data.
6. Report interpretation: This report must be read and interpreted in its entirety, as some sections could be
inaccurately interpreted when taken individually or out-of-context. The contents of this report are based upon the
conditions known and information provided as of the date of preparation. The text of the final version of this report
supersedes any other previous versions produced by Wood.
7. No legal representations: Wood makes no representations whatsoever concerning the legal significance of its
findings, or as to other legal matters touched on in this report, including but not limited to, ownership of any
property, or the application of any law to the facts set forth herein. With respect to regulatory compliance issues,
regulatory statutes are subject to interpretation and change. Such interpretations and regulatory changes should be
reviewed with legal counsel.
8. Decrease in property value: Wood shall not be responsible for any decrease, real or perceived, of the property or
site’s value or failure to complete a transaction, as a consequence of the information contained in this report.
9. No third party reliance: This report is for the sole use of the party to whom it is addressed unless expressly stated
otherwise in the report or Contract. Any use or reproduction which any third party makes of the report, in whole or
in part, or any reliance thereon or decisions made based on any information or conclusions in the report is the sole
responsibility of such third party. Wood does not represent or warrant the accuracy, completeness, merchantability,
fitness for purpose or usefulness of this document, or any information contained in this document, for use or
consideration by any third party. Wood accepts no responsibility whatsoever for damages or loss of any nature or
kind suffered by any such third party as a result of actions taken or not taken or decisions made in reliance on this
report or anything set out therein, including without limitation, any indirect, special, incidental, punitive or
consequential loss, liability or damage of any kind.
10. Assumptions: Where design recommendations are given in this report, they apply only if the project contemplated
by the Client is constructed substantially in accordance with the details stated in this report. It is the sole
responsibility of the Client to provide to Wood changes made in the project, including but not limited to, details in
the design, conditions, engineering or construction that could in any manner whatsoever impact the validity of the
recommendations made in the report. Wood shall be entitled to additional compensation from Client to review and
assess the effect of such changes to the project.
11. Time dependence: If the project contemplated by the Client is not undertaken within a period of 18 months
following the submission of this report, or within the time frame understood by Wood to be contemplated by the
Client at the commencement of Wood’s assignment, and/or, if any changes are made, for example, to the elevation,
design or nature of any development on the site, its size and configuration, the location of any development on the
site and its orientation, the use of the site, performance criteria and the location of any physical infrastructure, the
conclusions and recommendations presented herein should not be considered valid unless the impact of the said
changes is evaluated by Wood, and the conclusions of the report are amended or are validated in writing
accordingly.
Advancements in the practice of geotechnical engineering, engineering geology and hydrogeology and changes in
applicable regulations, standards, codes or criteria could impact the contents of the report, in which case, a
supplementary report may be required. The requirements for such a review remain the sole responsibility of the
Client or their agents.
Wood will not be liable to update or revise the report to take into account any events or emergent circumstances or
facts occurring or becoming apparent after the date of the report.
12. Limitations of visual inspections: Where conclusions and recommendations are given based on a visual inspection
conducted by Wood, they relate only to the natural or man-made structures, slopes, etc. inspected at the time the
site visit was performed. These conclusions cannot and are not extended to include those portions of the site or
structures, which were not reasonably available, in Wood’s opinion, for direct observation.
13. Limitations of site investigations: Site exploration identifies specific subsurface conditions only at those points
from which samples have been taken and only at the time of the site investigation. Site investigation programs are a
professional estimate of the scope of investigation required to provide a general profile of subsurface conditions.
The data derived from the site investigation program and subsequent laboratory testing are interpreted by trained
personnel and extrapolated across the site to form an inferred geological representation and an engineering
opinion is rendered about overall subsurface conditions and their likely behaviour with regard to the proposed
development. Despite this investigation, conditions between and beyond the borehole/test hole locations may
differ from those encountered at the borehole/test hole locations and the actual conditions at the site might differ
from those inferred to exist, since no subsurface exploration program, no matter how comprehensive, can reveal all
subsurface details and anomalies.
Final sub-surface/bore/profile logs are developed by geotechnical engineers based upon their interpretation of field
logs and laboratory evaluation of field samples. Customarily, only the final bore/profile logs are included in
geotechnical engineering reports.
Bedrock, soil properties and groundwater conditions can be significantly altered by environmental remediation and/or
construction activities such as the use of heavy equipment or machinery, excavation, blasting, pile-driving or
draining or other activities conducted either directly on site or on adjacent terrain. These properties can also be
indirectly affected by exposure to unfavorable natural events or weather conditions, including freezing, drought,
precipitation and snowmelt.
During construction, excavation is frequently undertaken which exposes the actual subsurface and groundwater
conditions between and beyond the test locations, which may differ from those encountered at the test locations. It
is recommended practice that Wood be retained during construction to confirm that the subsurface conditions
throughout the site do not deviate materially from those encountered at the test locations, that construction work
has no negative impact on the geotechnical aspects of the design, to adjust recommendations in accordance with
conditions as additional site information is gained and to deal quickly with geotechnical considerations if they arise.
Interpretations and recommendations presented herein may not be valid if an adequate level of review or
inspection by Wood is not provided during construction.
14. Factors that may affect construction methods, costs and scheduling: The performance of rock and soil materials
during construction is greatly influenced by the means and methods of construction. Where comments are made
relating to possible methods of construction, construction costs, construction techniques, sequencing, equipment
or scheduling, they are intended only for the guidance of the project design professionals, and those responsible
for construction monitoring. The number of test holes may not be sufficient to determine the local underground
conditions between test locations that may affect construction costs, construction techniques, sequencing,
equipment, scheduling, operational planning, etc.
Any contractors bidding on or undertaking the works should draw their own conclusions as to how the subsurface
and groundwater conditions may affect their work, based on their own investigations and interpretations of the
factual soil data, groundwater observations, and other factual information.
15. Groundwater and Dewatering: Wood will accept no responsibility for the effects of drainage and/or dewatering
measures if Wood has not been specifically consulted and involved in the design and monitoring of the drainage
and/or dewatering system.
16. Environmental and Hazardous Materials Aspects: Unless otherwise stated, the information contained in this report in
no way reflects on the environmental aspects of this project, since this aspect is beyond the Scope of Work and the
Contract. Unless expressly included in the Scope of Work, this report specifically excludes the identification or
interpretation of environmental conditions such as contamination, hazardous materials, wild life condi tions, rare
plants or archeology conditions that may affect use or design at the site. This report specifically excludes the
investigation, detection, prevention or assessment of conditions that can contribute to moisture, mould or other
microbial contaminant growth and/or other moisture related deterioration, such as corrosion, decay, rot in
buildings or their surroundings. Any statements in this report or on the boring logs regarding odours, colours,
and unusual or suspicious items or conditions are strictly for informational purposes
17. Sample Disposal: Wood will dispose of all uncontaminated soil and rock samples after 30 days following the
release of the final geotechnical report. Should the Client request that the samples be retained for a longer
time, the Client will be billed for such storage at an agreed upon rate. Contaminated samples of soil, rock or
groundwater are the property of the Client, and the Client will be responsible for the proper disposal of these
samples, unless previously arranged for with Wood or a third party.
Wood Environment & Infrastructure Solutions,
a Division of Wood Canada Limited
FIGURES
FIGURE 1: SITE LOCATION PLAN, ASSIGNMENT 16-12 AND ASSIGNMENT 16-22
FIGURE 2: BOREHOLE LOCATION PLAN, ASSIGNMENT 16-12
FIGURE 3: BOREHOLE LOCATION PLAN, ASSIGNMENT 16-22
FIGURE 4.1: SLOPE STABILITY ANALYSIS FOR PROPOSED SOUTH HEADWALL (BH 16 LOCATION)
CASE 1 – END OF CONSTRUCTION, MEASURED GROUNDWATER LEVEL (EL. 152.3 M)
FIGURE 4.2: SLOPE STABILITY ANALYSIS FOR PROPOSED SOUTH HEADWALL (BH 16 LOCATION)
CASE 2 – DURING SERVICE, ASSUMED GROUNDWATER LEVEL (EL. 157.5 M)
FIGURE 4.3: SLOPE STABILITY ANALYSIS FOR PROPOSED SOUTH HEADWALL (BH 16 LOCATION)
CASE 3 – RAPID DRAWDOWN FROM 100-YEAR FLOOD LEVEL (EL. 158.49 M)
FIGURE 5.1: SLOPE STABILITY ANALYSIS FOR EXISTING SLOPE (BH 37 LOCATION)
CASE 1 – EFFECTIVE STRESS ANALYSIS
FIGURE 5.2: SLOPE STABILITY ANALYSIS FOR EXISTING SLOPE (BH 37 LOCATION)
CASE 2 – TOTAL STRESS ANALYSIS
FIGURE 5.3: SLOPE STABILITY ANALYSIS FOR PROPOSED NORTH HEADWALL (BH 37 LOCATION)
CASE 3 – END OF CONSTRUCTION, BACKFILL TRENCH WITH ENGINEERED FILL, DRY
CONDITION
FIGURE 5.4: SLOPE STABILITY ANALYSIS FOR PROPOSED NORTH HEADWALL (BH 37 LOCATION)
CASE 4 – DURING SERVICE, BACKFILL TRENCH WITH ENGINEERED FILL, ASSUMED
GROUNDWATER LEVEL (EL. 162.0 M)
FIGURE 5.5: SLOPE STABILITY ANALYSIS FOR PROPOSED NORTH HEADWALL (BH 37 LOCATION)
CASE 5 – DURING SERVICE, BACKFILL TRENCH WITH ENGINEERED FILL, DRY
CONDITION
ASSIGNMENT 16-12
ASSIGNMENT 16-22
MTM Zone 10
PROJECTION:
NAD27
DATUM:
SITE LOCATION PLAN
TITLE
PROJECT
CLIENT LOGO
FIGURE No.
CIMA CANADA INC.
LEGEND
ASSIGNMENT NO:
1
PROJECT NO:
TT183004
16-12 & 16-22
CLIENT:
DWN BY:
CHK'D BY:
JANUARY 2019
DATE:
SCALE:
WJ
AS SHOWN
KW
GEOTECHNICAL INVESTIGATION REPORT
BASEMENT FLOODING PROTECTION PROGRAM PHASE 4 (BFPP4)
ASSIGNMENT 16-12 AND ASSIGNMENT 16-22
TORONTO, ONTARIO
50 Vogell Road, Units 3 & 4, Richmond Hill, Ontario, L4B 3K6
a Division of Wood Canada Limited
Wood Environment & Infrastructure Solutions,
N
0 150 300
APPROXIMATE SCALE
600m450
G
r
a
c
e
fie
ld
A
v
e
G
r
a
d
e
D
r
N
a
s
h
D
r
D
o
r
k
in
g
C
r
e
s
B
u
n
n
e
ll C
r
e
s
H
a
lls
p
o
r
t C
r
e
s
BH 13
BH 14
BH 15
C9
MH KS2
BH 11
BH 9
BH 8
BH 10
BH 12
C6
C5
BM NY19033
MH KS1
MH GA1
C7
C8
BH 7
BH 6
BH 5
C3
C4
BH 4
BH 1
BH 2BH 3
C1
C2
0 15 30
APPROXIMATE SCALE
60m45
MTM Zone 10
PROJECTION:
NAD27
DATUM:
TITLE
PROJECT
CLIENT LOGO
FIGURE No.
CIMA CANADA INC.
ASSIGNMENT NO:
2
PROJECT NO:
TT183004
16-12
CLIENT:
DWN BY:
CHK'D BY:
MARCH 2019
DATE:
SCALE:
WJ
AS SHOWN
KW
GEOTECHNICAL INVESTIGATION REPORT
BASEMENT FLOODING PROTECTION PROGRAM PHASE 4 (BFPP4)
ASSIGNMENT 16-12 AND ASSIGNMENT 16-22
TORONTO, ONTARIO
50 Vogell Road, Units 3 & 4, Richmond Hill, Ontario, L4B 3K6
a Division of Wood Canada Limited
Wood Environment & Infrastructure Solutions,
N
Site Map - N.T.S.
N
Matchlin
e A
-A
Ma
tch
line
B
-B
Ma
tchline A
-A
Matchline B
-B
BR
YN
R
D
DE
L R
IA
D
R
Q
U
E
E
N
S
D
R
CU
LF
OR
D R
D
BOREHOLE WITH MONITORING WELL LOCATION
BOREHOLE LOCATION
SITE AND BOREHOLE LOCATION PLAN
LEGEND
ASPHALTIC CONCRETE CORE LOCATION
BENCHMARK (NY19033)
HORIZONTAL CONTROL POINTS
020740634
020690127
2460 K
eele S
t
PROPOSED MANHOLE