Upload
vanliem
View
218
Download
0
Embed Size (px)
Citation preview
Geotechnical Engineering Report
CEP Switchgear (Phase I) Underground Utility Exploratory Pit
UTHSCSA Main Campus
San Antonio, Texas
Prepared for:
S&GE, LLC
San Antonio, Texas
Prepared by:
Drash Consultants, LLC
San Antonio, Texas
February 15, 2015
Drash Project No. 116G1011.00
TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY ........................................................................................................... i
INTRODUCTION ...................................................................................................................... 1
Authorization ................................................................................................................. 1
Purpose and Scope of Services .................................................................................... 1
PROJECT INFORMATION ....................................................................................................... 1
SITE AND SUBSURFACE CONDITIONS ................................................................................ 2
Site Conditions .............................................................................................................. 2
Subsurface Conditions .................................................................................................. 2
Subsurface Stratigraphy ............................................................................................................ 2 Subsurface Water ...................................................................................................................... 2
GEOTECHNICAL RECOMMENDATIONS AND GUIDELINES ................................................ 3
Lateral Earth Pressures ................................................................................................ 3
Construction Sequence of Secant Pile Wall .............................................................................. 4
Drilled Piers .................................................................................................................. 5
Slope Stability ............................................................................................................... 8
OSHA Trench Safety Guidelines ................................................................................... 9
Slab Foundations ........................................................................................................ 10
Seismic Design Considerations ................................................................................... 11
Corrosion Considerations ............................................................................................ 11
INTERPRETATION OF REPORT ........................................................................................... 11
CONSTRUCTION MONITORING AND TESTING .................................................................. 12
LIMITATIONS OF REPORT ................................................................................................... 12
EXHIBITS
Exhibit 1 Project Location Map
Exhibit 2 Bore Location Plan
Exhibit 3 Log of Boring
APPENDIX – FIELD AND LABORATORY
Exploratory Drilling Program
Laboratory Testing Program
Notes Regarding Soil and Rock
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
i
EXECUTIVE SUMMARY
This geotechnical engineering report has been prepared for the design and construction of the
CEP Switchgear (Phase I) Underground Utility Exploratory Pit at the existing UTHSCSA Main
Campus (Project). The project is located at 7703 Floyd Curl Drive in San Antonio, Texas.
Based on the information provided to us for this study and from data developed as part of our
engineering service, the site is suitable for the planned improvements. A general summary of our
findings, conclusions, and recommendations with regard to the geotechnical engineering aspects
of the Project are provided below:
Subsurface conditions generally consist of fat clay and lean clay soils.
A secant pile wall may be used as an earth retention system for the exploratory
pit.
After excavating to 15 feet to observe and locate any existing underground
utilities in the area, the pit will be backfilled with 7 to 9 feet of material (flowable
fill) to install the proposed duct bank, manhole and utility vault.
Several of the piers on the east and west sides of the exploratory pit will need to
be “chipped out” to accommodate the installation of the duct bank.
The slab for the proposed underground duct bank (cast-in-place or pre-cast) can
be designed for a net bearing pressure of 4,000 psf on the flowable fill.
This summary is provided for convenience only. For those individuals and entities that may
need more details or technical information from this report for their use, it must be read in its
entirety to have an understanding of the information and recommendations provided for the
Project.
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
1
GEOTECHNICAL ENGINEERING REPORT
CEP SWITCHGEAR (PHASE I) UNDERGROUND UTILITY EXPLORATORY PIT
UTHSCSA MAIN CAMPUS
SAN ANTONIO, TEXAS
INTRODUCTION
This geotechnical engineering report has been prepared for the design and construction of the
CEP Switchgear (Phase I) Underground Utility Exploratory Pit at the existing UTHSCSA Main
Campus (Project). The project is located at 7703 Floyd Curl Drive in San Antonio, Texas.
Based on the information provided to us by the client, we understand that the Underground
Utility Exploratory Pit will be approximately 30 feet by 26 feet in plan dimension. The utility pit is
to identify existing utilities in the area of a proposed electrical utility vault, a duct bank with a
manhole and a future switchgear station with a vault. The utility vault and the duct bank with a
manhole are expected to be approximately 6 to 8 feet deep. The vault below the switchgear
station will be about 15 feet deep. The utility pit will be partially filled-in to support the duct bank
and manhole. Several of the piers on the east and west side will need to be “chipped out” to
accommodate the installation of the duct bank.
Authorization
This Project was authorized by Mr. Edward L. Sherfey, Jr. with S&GE, LLC, by acceptance of
our Agreement for Services, No. PG1151234.00, dated December 30, 2015.
Purpose and Scope of Services
The purposes of this engineering service were to evaluate the general subsurface conditions
(soil, rock, subsurface water) within the Project limits by drilling an exploratory boring, conduct
tests on samples recovered during drilling of the exploratory boring, analyze and evaluate the
test data, perform engineering analyses using the data analyzed and evaluated from the field
and laboratory programs to develop geotechnical engineering recommendations and guidelines
with respect to:
Site conditions as applicable Earthwork as applicable
Subsurface stratigraphy Secant pile wall recommendations
Subsurface water conditions
PROJECT INFORMATION
The following information was provided to us by the Client, design professionals working on the
Project, or was collected by our firm:
Project Location The project is located at 7703 Floyd Curl Drive in San Antonio, Texas. The
general vicinity of the Project is illustrated on Exhibit 1, the Project Location Map.
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
2
Project
The Project will involve design and construction of an underground utility
exploratory pit. The exploratory pit will be partially filled-in to install a duct bank
with a manhole and a utility vault. West of the exploratory pit a switchgear station
with a vault will be constructed.
Current Site Conditions The Project site is currently a vacant area within the existing UTHSC – San
Antonio facility.
Current Topography Based on our visual observations, the site appeared relatively flat and gently
slopes down to the west.
Proposed Topography
Based on the information provided to us, we understand that the utility vault
and the duct bank with a manhole are expected to be approximately 6 to 8 feet
deep. The vault below the switchgear station will be about 15 feet deep. If
this information changes, Drash should be contacted to re-evaluate
these recommendations.
SITE AND SUBSURFACE CONDITIONS
Site Conditions
The site, as noted previously, is currently a vacant area within the existing UTHSC – San Antonio
facility. Based on visual observations, there were no noticeable or obvious surface conditions
within the site that would affect the geotechnical engineering aspects of this Project.
Subsurface Conditions
Subsurface conditions within the Project limits were evaluated by drilling an exploratory boring at
the location shown on Exhibit 2, the Bore Location Plan. Information retrieved from the exploratory
boring is summarized herein.
Subsurface Stratigraphy
Subsurface stratigraphy, based on the exploratory boring, can be generalized as follows:
Layer
Identification
Approximate Depth
To and Thickness Of
Layer (feet)
Description of Layer
Layer 1 0 to 8½ SANDY FAT CLAY (CH); dark brown, tan and olive; medium stiff
to very stiff; with roots in the upper 1 foot.
Layer 2 8½ to 50 LEAN CLAY (CL); tan and olive, gray; very stiff to hard; partially
cemented below 18½ feet.
The log of boring, presenting more specific information about the subsurface stratigraphy
encountered at the exploratory boring location, is provided in the Exhibits section of this report.
Subsurface Water
Subsurface water was not encountered during or upon completion of our drilling activities. The
exploratory boring was backfilled with spoils generated during drilling operations.
Subsurface water is generally encountered as a ‘true’ or permanent water source or as a
‘perched’ or temporary water source. Permanent subsurface water is generally present year
round, which may or may not be influenced by seasonal and climatic changes. Temporary
subsurface water generally develops as a result of seasonal and climatic conditions.
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
3
Subsurface water levels should be re-checked prior to the planned construction activities.
GEOTECHNICAL RECOMMENDATIONS AND GUIDELINES
Based on the information provided to us by the Client and Project Team, our exploratory boring
drilled at the site, results of laboratory tests performed on samples recovered during the
subsurface exploration program, and our engineering analyses, the following statements can be
made regarding the Project site:
The site is suitable for the planned construction.
The subsurface stratigraphy exhibits a moderate potential for volume changes
(expansion and contraction) with fluctuations in its moisture content.
A secant pile wall may be used as an earth retention system for the exploratory
pit excavation.
The secant pile wall being considered must be designed to reduce the possibility of soil failure
when subjected to lateral earth pressure. The secant pile wall must also be designed so the
vertical, horizontal or rotational loads are within allowable limits of the soil and within design and
operational limits.
The following geotechnical recommendations and guidelines have been prepared based on the
data collected or developed during this Project, our experience with similar projects, and our
knowledge of sites with similar surface and subsurface conditions.
Lateral Earth Pressures
We understand that secant pile walls are being considered as the retention system for the
exploratory pit excavation. Active earth pressures should be used for the design of secant pile
walls since the top of the walls will not be restrained from horizontal movement. Presented
below are active earth pressure coefficients and equivalent fluid pressures for the existing soils
that may be used to design the secant pile wall at this site.
LATERAL EARTH PRESSURE DESIGN CRITERIA
LATERAL EARTH
COEFFICIENT
EQUIVALENT FLUID
DENSITY (pcf)
SURCHARGE
PRESSURE, p1
(psf)
EARTH PRESSURE,
p2
(psf)
Active (ka)
On-Site Soil - 0.53 64 (0.53)S (64) H.D
D: spacing between secondary (reinforced) secant piles.
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
4
A passive equivalent fluid density of 150 pcf may be used for the embedded portion of the
secant pile wall. The passive pressure should be neglected in the upper 12 inches below the
bottom of the excavation.
Applicable conditions to the above table include:
Uniform surcharge, S, should be included where applicable.
For on-site soil, use a maximum total unit weight of 120 pcf.
The earth pressure criteria presented in the table do not include:
o Hydrostatic conditions developing behind the retaining wall.
o Surcharge loading from compaction equipment and floor slabs.
o A factor of safety.
Construction Sequence of Secant Pile Wall
Pertinent details of secant pile wall construction are presented below:
All existing above-grade and below-grade structures that interfere with the secant
pile installation will be relocated or removed.
Install secant piles beginning with the Primary Piles (“non-reinforced piles).
Install the Primary Piles and Secondary Piles (“reinforced piles”) as presented in
the typical installation sequence.
Complete the secant pile wall as follows:
o Power-wash all the soil off the exposed face of the secant pile wall.
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
5
o Install the applicable water-proofing material at all applicable joints.
o Concurrent with the water-proofing activity, construct the drainage channel
along the bottom of the secant pile wall.
Typical construction sequence of secant pile walls is presented below:
Drilled Piers
Drilled piers will be used to construct the secant pile wall for this Project. The drilled piers must
be straight-sided piers. The drilled piers should not bear deeper than 45 feet below the
existing ground surface without contacting our office.
Design Considerations. Reinforced and unreinforced drilled piers will be installed for the
proposed secant pile wall. There will not be much in the way of compressive axial loads or uplift
loads on the drilled piers in the secant pile wall. The drilled piers will primarily need to be
designed for lateral loading. However, the clay soils will apply axial tension loads on the drilled
piers due to shrinking and swelling of the near surface clay soils.
A number of methods, including hand solutions and computer programs, are available for
calculating the lateral behavior of drilled piers. The majority of these methods rely on “key” soil
parameters such as soil elastic properties (E and k), strain at 50 percent of the principal stress
difference (50), undrained shear strength (c), angle of internal friction (), and load-deflection (p-
y) criteria. The p-y criteria, which are commonly used to model soil reaction, were developed
from instrumented load tests and are generally considered to provide the best model of soil
behavior under short-term lateral loading. It should be noted that the p-y criteria is not only a
function of the soil properties but also the diameter of the structure foundation.
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
6
The majority of p-y curve models use a form of parabola to describe the initial portion of a p-y
curve; at small deflections the slope of these p-y curves approaches infinity. This is an
important consideration, since most laterally loaded pile analysis programs use p-y curves to
develop equivalent soil springs in their computations. These soil springs are defined as the soil
reaction, p, divided by the soil deflection, y, or the secant modulus of the p-y curve.
Factors of safety are not generally applied to the lateral load analysis. A performance criteria,
or “limit state”, is usually considered. The analysis is generally conducted using the working
loads and the limit state values. A limit state value of 1 inch of groundline deflection should be
used for design of the secant pile wall.
The choice of the final design embedment depth is also evaluated by determining the critical
depth of the foundation. The critical depth is actually a depth range and can be defined as that
range in depth at which a small decrease in the pier embedment depth will result in a large
increase in the groundline deflection of the pier. The analysis is conducted by incrementally
decreasing the embedment depth and plotting the resultant groundline deflection versus
embedment depth. The embedment depth is then chosen below the critical depth range. In
some cases, groundline deflections significantly less than one (1) inch are needed to satisfy the
critical depth issue.
Criteria for the LPILE series program are contained in Table 1 below. It should be noted that
the initial elastic moduli for soil is referred to as soil modulus (k) in the Table and in the LPILE
program. The parameters provided on these tables can be used for lateral design of concrete
piers with or without reinforcing steel.
TABLE 1
Soil
Layer
LPILE Depth to Soil
Layer
LPILE
Soil Effective Undrained Internal
LPILE
Soil
Soil Type &
Number
Top Bottom Modulus Unit
Weight
(pcf)
Shear
Strength
(psf)
Friction
Angle
(degrees)
Strain
Factor
ε50 (feet) (feet)
k
(pci)
1 Stiff Clay without
Free Water (3) 0 2 351 110 600 0 0.014
2 Stiff Clay without
Free Water (3) 2 8 622 120 2,000 0 0.007
3 Stiff Clay without
Free Water (3) 8 18 815 120 3,000 0 0.006
4 Stiff Clay without
Free Water (3) 18 38 1395 125 6,000 0 0.004
5 Stiff Clay without
Free Water (3) 38 50 1782 125 8,000 0 0.003
Construction Considerations. The pier foundation excavations should be augered and
constructed in a continuous manner. Steel and concrete should be placed in the excavations
immediately following drilling and evaluation for proper bearing stratum, embedment, and
cleanliness. Under no circumstances should the excavations remain open overnight.
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
7
As stated previously, no subsurface water was encountered during or immediately after drilling
of the exploratory boring. For the initial piers in the secant pile wall, the foundation contractor
should be prepared to use casing to control sloughing of the excavation sidewalls and to reduce
the influx of water (should any water be encountered) into the excavation. The casing method is
discussed in the following paragraphs:
Casing Method - Casing will provide stability of the excavation walls and will
reduce water influx; however, casing may not completely eliminate potential
subsurface water influx potential. In order for the casing to be effective, a “water
tight” seal must be achieved between the casing and surrounding soils. The
drilling subcontractor should determine the type of casing, casing depths and
casing installation procedures. Water that accumulates in excess of six (6)
inches in the bottom of the pier excavation should be pumped out prior to steel
and concrete placement. If the water is not pumped out, a closed-end tremie
should be used to place the concrete completely to the bottom of the pier
excavation in a controlled manner to effectively displace the water during
concrete placement. If water is not a factor, concrete should be placed with a
short tremie so the concrete is directed to the bottom of the pier excavation. The
concrete should not be allowed to ricochet off the walls of the pier excavation nor
off the reinforcing steel.
If dry augering after casing installation is not successful or to the satisfaction of
the design engineer, the pier excavation should be flooded with fresh water to
offset the differential water pressure caused by the unbalanced water levels
inside and outside of the casing. When the pier excavation depth is achieved
and the bearing area has been cleaned, steel and concrete should then be
placed immediately in the excavation. The concrete should be tremied
completely to the bottom of the excavation with a closed-end tremie.
Removal of casing should be performed with extreme care and under proper
supervision to minimize mixing of the surrounding soil and water with the fresh
concrete. Rapid withdrawal of casing or the auger may develop suction that
could cause the soil to intrude into the excavation. An insufficient head of
concrete in the casing during its withdrawal could also allow the soils to intrude
into the wet concrete. Both of these conditions may induce "necking", a section
of reduced diameter, in the pier.
In addition to the lateral loads acting on the drilled piers due to the retained soil, the drilled piers
will also be subjected to axial tension loads due to swelling of the near surface clay soils and
possibly due to other induced structural loading conditions. To compute the axial tension force
due to the swelling soils along straight-sided piers, the following equation may be used.
Qu = 37 ● d
Where: Qu = Uplift force due to expansive soil conditions in kips (k)
d = Diameter of pier in feet (ft)
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
8
This calculated force can be used to compute the longitudinal reinforcing steel required in the
pier to resist the uplift force induced by the swelling clays.
All aspects of concrete design and placement should comply with the most recent version of
American Concrete Institute (ACI) 318 Building Code Requirements for Structural Concrete, ACI
336.1, the section titled Standard Specification for the Construction of Drilled Piers, ACI 336.3,
the section titled Suggested Design and Construction Procedures for Pier Foundations, ACI
305.1 Hot-Weather Concreting and ACI 306.1 Cold-Weather Concreting. Concrete should be
designed to achieve the specified 28-day strength when placed at an 8-inch slump with a 1
inch tolerance. Adding water to a mix that has been designed for a lower slump does not meet
the intent of this recommendation. If a high range water reducer is used to achieve this slump,
the span of slump retention for the specific admixture under consideration should be thoroughly
investigated. Compatibility with other concrete admixtures should also be considered. A
technical representative of the admixture supplier should be consulted on these matters.
Successful installation of drilled piers is a coordinated effort involving the general contractor,
design consultants, subcontractors and suppliers. Each must be properly equipped and
prepared to provide their services in a timely fashion. Several key items are:
Proper drilling rig with proper equipment (including casing, augers, and teeth);
Reinforcing steel cages tied to meet project specifications;
Proper scheduling and ordering of concrete for the piers; and
Monitoring of the installation by design professionals.
Foundation construction should be carefully monitored to assure compliance of construction
activities with the appropriate specifications. Particular attention to the referenced publication is
warranted for foundation installation. A number of items for foundation installation include those
listed below.
Foundation locations Concrete properties and placement
Vertical alignment Proper casing seal for subsurface water control
Competent bearing Casing removal
Steel placement
Slope Stability
The soil outside of the exploratory pit will be excavated and sloped back to install the duct bank
and utility vault. The length of duct bank and utility vault outside of the exploratory pit will need
to be sloped back at (3H:1V) for excavations open longer than 24 hours or trench shields should
be used.
We understand that the excavation of the underground sections may require sloping back the
sides of the trench excavations. Analysis for slope stability and slope performance evaluation
were not part of this study. However, general information regarding slope stability is presented
in the following paragraphs.
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
9
Slopes will be created or constructed at this site with cuts into the existing subsurface soils
(natural slopes) and by constructing fill pads or embankments for the construction. The stability
of a created or constructed slope is dependent on several criteria and include:
The height of the slope;
The material comprising the slope;
The slope angle; and
Erosion considerations.
We anticipate that on-site soils may be excavated and sloped back to install the duct bank and
utility vault. For cut slopes, in the on-site soils, a permanent slope of four (4) horizontal to one
(1) vertical (4H:1V) can be used. On a temporary basis, OSHA will allow slopes up to 1H:1V for
excavation less than 20 feet deep.
Steeper slopes might be considered if the face of the slope is protected from erosion and/or if
the fill section is reinforced with soil reinforcement such as geogrid. Any surcharge loads should
not be placed within 10 feet of the crest of any fill or natural slope at this site.
Further protection of the sloped section may be provided with the use of concrete terrace drains
or other interceptor drains designed to protect the slope from surface water. Maintenance of the
slope should be done on an “as needed basis”.
OSHA Trench Safety Guidelines
Occupational Safety and Health Administration (OSHA) Safety and Health Standards (29 CFR
Part 1926 Revised, 1997) require that all trenches in excess of five (5) feet deep be shored or
appropriately sloped unless the trench sidewalls are comprised of "solid" rock. Clayey soil was
encountered at this site within the depths explored.
Our recommendations are intended for use in conjunction with OSHA safety regulations and not
as a replacement of those regulations. Based on the laboratory results, we feel that soils
encountered at the boring locations would be considered as Type B soils according to OSHA
soil classification guidelines.
As stated previously, OSHA requires all soil trenches in excess of five (5) feet be shored or
appropriately sloped. Currently available and practiced methods for achieving slope and/or
trench wall stability includes sloping, benching, combinations of sloping and benching, and
installation of shoring systems (hydraulic, timber, etc.). Trench shields may also be considered
for use. However, these shields only provide protection to workers; they are not a means for
providing slope or trench wall stability.
OSHA addresses construction slopes in large excavations that are less than 20 feet deep. The
table shown below is a reproduction of the OSHA Table B-1:
OSHA TABLE B-1 MAXIMUM ALLOWABLE SLOPES
Soil or Rock Type Maximum Allowable Slopes (H:V)1 for Excavations Less Than 20 Feet Deep3
Stable Rock VERTICAL(90º)
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
10
OSHA TABLE B-1 MAXIMUM ALLOWABLE SLOPES
Soil or Rock Type Maximum Allowable Slopes (H:V)1 for Excavations Less Than 20 Feet Deep3
Type A ¾:1 (53º)
Type B 1:1 (45º)
Type C 1 ½:1 (34º)
1. Numbers shown in parentheses next to maximum allowable slopes are angles expressed in degrees from
the horizontal. Angles have been rounded off.
2. A short-term maximum allowable slope of ½H: 1V (63°) is allowed in excavations in Type A soil that are 12
feet or less in depth. Short-term maximum allowable slopes for excavations greater than 12 feet in depth
shall be ¾H: 1V (53°).
3. Sloping or benching for excavations greater than 20 feet shall be designed by a registered professional
engineer.
The OSHA regulations define short-term as a period of 24 hours or less.
Slab Foundations
We understand that a pre-cast concrete duct bank or utility vault will be placed approximately 6
to 8 feet deep from the ground surface. The subsoils at approximately 6 to 8 feet depth yield a
Potential Vertical Rise (PVR) of about 1½ inches in their current state. The actual movement
could be greater if inadequate drainage or other sources of water are allowed to infiltrate
beneath the structure after construction. Recommendations for this foundation type are
presented below.
In order for the duct bank, manhole or utility vault to only be 6 to 8 feet below the existing
ground surface in the area of the exploratory pit, the pit excavation will need to be filled-in with 7
to 9 feet of flowable fill. The flowable fill should have a minimum compressive strength of 100
psi and a maximum compressive strength of 150 psi. Washed or crushed gravel should not be
used to fill the excavation, because the clay bottom and secant pile wall will cause water to be
trapped in the gravel, creating a “bathtub” situation. Due to the size of the excavation, moisture
conditioning and compacting lean clay fill in the excavation would be difficult to install safely and
properly.
The bedding for the duct bank, manhole and utility vault outside of the exploratory pit should be
excavated 12 inches below the proposed bearing elevation and backfilled with flowable fill to
provide a uniform bearing surface along the length of the duct bank, manhole and utility vault.
This will also prevent creating a channel for water to collect in and travel under the electrical
structures.
Several of the piers in the secant pile wall will need to be “chipped out” on the east and west
sides of the exploratory pit to accommodate the duct bank, manhole and utility vault. The walls
should be removed at least 6 inches below the proposed bearing elevations of the new
structures to place flowable fill across the wall threshold.
The precast concrete duct bank, manhole or utility vault may be designed for a net bearing
pressure of 4,000 psf on the flowable fill.
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
11
Seismic Design Considerations
Presented below are the seismic design criteria for the project site and immediate area.
Description Value
2015 IBC Site Classification1 C2
Site Latitude 29.50652°
Site Longitude -98.57713°
Maximum Considered Earthquake 0.2 second Design Spectral Response Acceleration (SDS) 0.061
Maximum Considered Earthquake 1.0 second Design Spectral Response Acceleration (SD1) 0.033
1 As per the requirements of Section 1613.3.2 in the 2015 IBC, the site class definition was determined
using Table 20.3-1 of Chapter 20 of American Society of Civil Engineers (ASCE) 7. The Spectral
Acceleration values were determined using publicly available information provided on the United States
Geological Survey (USGS) website.
2 Note: Chapter 20 of ASCE 7 requires a site soil profile determination extending to a depth of 100 feet for
seismic site classification. The current scope does not include the required 100-foot soil profile
determination. The boring extended to a maximum depth of 50 feet, and this seismic site class definition
considers that hard soil continues below the maximum depth of the subsurface exploration. Additional
exploration to deeper depths would be required to confirm the conditions below the current depth of
exploration.
Corrosion Considerations
Laboratory tests were conducted on a soil sample recovered from the boring to assess the
corrosivity risk of the soils at the site. The soil sample was submitted to an analytical lab for
determination of the sulfate content. The result of the laboratory test is provided below.
Summary of Laboratory Sulfate Tests
Boring No. Sample
Depth (ft) Sulfate (ppm)
B-1 6½ to 8 136
According to the 2015 IBC, concrete that is exposed to sulfate-containing solutions should be
designed in accordance with ACI 318. The sulfate test result indicates that the sulfate exposure
level is low. Therefore, Type I or Type II cement may be used at this site.
INTERPRETATION OF REPORT
Drash understands that its geotechnical engineering report is used by the Client and various
individuals and firms involved with the design and construction of the Project. Drash should be
invited to attend Project meetings (in person or teleconferencing) or be contacted in writing to
address applicable issues relating to the geotechnical engineering aspects of the Project. Drash
should also be retained to review the final construction plans and specifications to evaluate if the
information and recommendations in our geotechnical engineering report has been properly
interpreted and implemented in the design and specifications.
Drash Project No. 116G1011.00
CEP Switchgear (Phase I)
Underground Utility Exploratory Pit
12
CONSTRUCTION MONITORING AND TESTING
The performance of the foundation system for the proposed structure will be highly dependent
upon the quality of construction. As the Geotechnical Engineer of Record for this Project, Drash
should be retained to provide construction observation and materials testing services during the
Project, particularly the construction activities relating to foundations, generator pad,
pavements, excavation and site grading.
LIMITATIONS OF REPORT
This geotechnical engineering report is based upon the information provided to us by the Client
and various other individuals and entities associated with the Project, exploratory boring drilled
within the Project limits, laboratory testing of randomly selected soil or rock samples recovered
during drilling of the exploratory boring, and our engineering analyses and evaluation. The
Client and readers of this geotechnical engineering report, should realize that subsurface
variations and anomalies can and will exist across the site and between the exploratory boring.
The Client and readers should realize that site conditions will change due to the modifying
effects of seasonal and climatic conditions.
The nature and extent of such site or subsurface variations may not become evident until
construction commences or is in progress. If site and subsurface anomalies or variations exist
or develop, Drash should be contacted immediately so that the situation can be evaluated and
addressed with applicable recommendations. The contractor and applicable subcontractors
should familiarize themselves with this report prior to the start of their construction activities,
contact Drash for any interpretation or clarification of the report, retain the services of their own
consultants to interpret this report, or perform additional geotechnical testing prior to bidding and
construction.
Unless stated otherwise in this report or in the contract documents between Drash and Client,
our scope of services for this Project did not include, either specifically or by implication, any
environmental or biological assessment of the site or buildings, or any identification or
prevention of pollutants, hazardous materials or conditions at the site or within buildings. If the
Client is concerned about the potential for such contamination or pollution, Drash should be
contacted to provide a scope of services to address the environmental concerns. Also,
permitting, site safety, excavation support, and dewatering requirements are the responsibility of
others.
This geotechnical engineering report has been prepared for the exclusive use of our Client for
specific application to this Project. This geotechnical engineering report has been prepared in
accordance with generally accepted geotechnical engineering practices. No warranties,
express or implied, are intended or made.
Should the nature, design, or location of the Project, as outlined in this geotechnical engineering
report, be modified, geotechnical engineering recommendations and guidelines provided in this
document will not be considered valid unless Drash reviews the changes and either verifies or
modifies the applicable Project changes in writing.
EXHIBITS
EXHIBITDrawn By:
Checked By:
Reviewed By:
Project Mngr:
Date:
Scale:
Project No. PROJECT LOCATION MAP
NOT TO SCALE
02-02-2016
116G1011.00KS
SR
1045 Central Parkway North, Suite 103 ▪ San Antonio, Texas 78232Office: 210.340.5004 ▪ Facsimile: 210.340.5009
1
N
SR
GKCEP SWITCHGEAR (PHASE 1): UNDERGROUND UTILITY EXPLORATORY PIT
UTHSCSA MAIN CAMPUSSAN ANTONIO, TEXAS
TBPE Firm Registration F-13654
PROJECT SITE
B-1
EXHIBITDrawn By:
Checked By:
Reviewed By:
Project Mngr:
Date:
Scale:
Project No. BORE LOCATION PLAN
NOT TO SCALE
02-2-2016
116G1011.00SR
KSGK
SR1045 Central Parkway North, Suite 103 ▪ San Antonio, Texas 78232
Office: 210.340.5004 ▪ Facsimile: 210.340.5009TBPE Firm Registration F-13654
CEP SWITCHGEAR (PHASE 1): UNDERGROUND UTILITY EXPLORATORY PITUTHSCSA MAIN CAMPUS
SAN ANTONIO, TEXAS2
N
MERTON MINTER
SYMBOLS:Exploratory Boring Location
54
49
35
N=5
N=13
N=16
N=18
N=22
N=26
N=ref/5"
N=ref/4"
N=75
N=50/5"
N=ref/5"
N=ref/5"
N=ref/4"
15
15
14
14
18
9
8
14
13
16
11
11
10
19
17
15
35
32
20
Layer 1SANDY FAT CLAY (CH); dark brown to tan and olive;
medium stiff to very stiff; with roots in the upper 1 foot
Layer 2LEAN CLAY (CL); tan and olive; very stiff to hard
- partially cemented below 18½ feet
- becomes gray below 43½ feet
Boring Terminated at 50 feet.
64
88
5
10
15
20
25
30
35
40
45
50
DRILLING METHOD(S):
PISA
MP
LES
PROJECT NO.BORING NO.
DATESURFACE ELEVATION
REMARKS
N: B
LOW
S/F
TP
: TO
NS
/SQ
FT
T: T
ON
S/S
Q F
TP
ER
CE
NT
RE
CO
VE
RY
/R
OC
K Q
UA
LIT
Y D
ES
IGN
AT
ION
The boring was backfilled with cuttings after completion of drilling activities.
116G
1011
.00
- C
EP
Sw
itchg
ear
(Pha
se I)
: Und
ergr
ound
Util
ity E
xplo
rato
ry P
it -
Thi
s Lo
g is
not
val
id if
sep
erat
ed fr
om o
rigin
al r
epor
t.
CO
NF
ININ
G P
RE
SS
UR
E
(PO
UN
DS
/SQ
IN)
DESCRIPTION OF STRATUMMO
IST
UR
E C
ON
TE
NT
(%
)
CEP Switchgear (Phase I): Underground Utility Exploratory PitSan Antonio, Texas 116G1011.00
B-11/20/2016
Existing Grade
SO
IL S
YM
BO
L
LOG OF BORING
LABORATORY DATAFIELD DATA
DR
Y D
EN
SIT
Y
(PO
UN
DS
/CU
FT
)
S&GE, LLCSan Antonio, Texas
CLIENT:
PL
3
EXHIBIT
FA
ILU
RE
ST
RA
IN (
%)
MIN
US
NO
. 200
SIE
VE
(%
)
LIQ
UID
LIM
IT
PLA
ST
IC L
IMIT
PLA
ST
ICIT
Y IN
DE
X
PROJECT:
LLDE
PT
H (
FT
)
Dry augered from 0 to 50 feet.
Subsurface water was not encountered during or upon completion of our drillingactivities.
PAGE 1 OF 1
ATTERBERGLIMITS (%)
CO
MP
RE
SS
IVE
ST
RE
NG
TH
(TO
NS
/SQ
FT
)
SUBSURFACE WATER INFORMATION:
APPENDIX – FIELD AND LABORATORY
EXPLORATORY DRILLING PROGRAM
LABORATORY TESTING PROGRAM
NOTES REGARDING SOIL AND ROCK
EXPLORATORY DRILLING PROGRAM
A truck-mounted, drilling rig was used to drill the exploratory boring and to recover soil/rock samples during
the drilling. Soil samples were obtained by pushing thin wall tube samplers (“Shelby tube”) or with a split-
barrel (“split-spoon”) sampler while performing the Standard Penetration Test (“SPT”). Rock samples were
obtained by performing the SPT or coring.
When a soil sample was recovered using a Shelby tube sampler, a pocket penetrometer test (“PPT”) or
hand torvane (“TV”) was conducted and recorded on the applicable exploratory field log of boring (“field
log”). When a soil/rock sample was recovered using a split-barrel sampler, the SPT N-value was recorded
on the applicable field log. The SPT procedure consists of driving the split-barrel into the subsurface
stratum with a 140-pound hammer falling a distance of 30 inches. The number of blows (“N”) required to
advance the split-spoon sampler the last 12 inches during a normal 18-inch penetration is the SPT
resistance value or N-value. These N-values are indicated on each applicable field log at the depths of
occurrence. The samples were sealed and transported to the laboratory for testing and classification.
Our field representative prepared the field logs as part of the drilling operations. The field logs included
visual classifications of the materials encountered during drilling, our field representative interpretation of
the subsurface conditions between samples, and recording the results of various tests (N-values, PPT, and
TV) performed during drilling and sampling. Each field log included with this report represents our technical
interpretation of the field log and includes modifications based on visual observations and testing of the
samples in the laboratory.
The scope of services for our geotechnical engineering services does not include addressing any
environmental issues pertinent to the site.
LABORATORY TESTING PROGRAM
Samples retrieved during the field exploration were taken to the laboratory for further observation by one
of our technical representatives, and they were classified in accordance with the Unified Soil
Classification System (USCS). At that time, the field descriptions were confirmed or modified as
necessary and an applicable laboratory testing program was formulated to determine the physical (index)
and engineering properties of the soil/rock.
Laboratory tests were conducted on selected soil samples and the test results are presented in this
appendix. The laboratory test results were used for the geotechnical engineering analyses, and the
development of foundation and earthwork recommendations. Laboratory tests were performed in general
accordance with the applicable ASTM or other accepted standards. The following tests were conducted:
Moisture Content
Atterberg Limits
Amount of Material In-Soil Finer than the No 200 Mesh (75-µm) Sieve
Sample Disposal
All samples were returned to our laboratory. Unless stated otherwise in this report or the Project contract,
the samples not tested in the laboratory will be stored for a period of 30 days subsequent to submittal of
this report and will be discarded after this period, unless other arrangements are made prior to the
disposal period.
NOTES REGARDING SOIL AND ROCK
GEOTECHNICAL SAMPLING SYMBOLS:
SS: Split Barrel (Split Spoon) ST: Thin-Walled Tube (Shelby tube)
AG: Auger Sample, Grab Sample, or Bulk Sample
RC: Rock Coring Sample
WATER LEVEL MEASUREMENT SYMBOLS:
Water Level Encountered While Drilling and Sampling.
▼ Water Level Measurement After Initial Water Level Encountered During Drilling and Sampling.
DESCRIPTIVE SOIL CLASSIFICATION: Soil classification is based on the Unified Soil Classification System (ASTM D2487).
Coarse Grained Soils have more than 50 percent of their dry weight retained on a No. 200 sieve. The primary descriptors of these soils are: boulders, cobbles, gravel, or sand. In addition to gradation, coarse-grained soils are defined on the basis of their in-place relative density. Fine Grained Soils have less than 50 percent of their dry weight retained on a No. 200 sieve. These soils are principally described as clays if they are plastic (have binding/molding characteristics), and silts if they are slightly plastic or non-plastic. Fine-grained soils are defined on the basis of their consistency.
CONSISTENCY OF FINE-GRAINED SOILS RELATIVE DENSITY OF COARSE-GRAINED SOILS
Undrained
Shear
cu, psf
Standard Penetration Test (SPT) N-value
Blows Per Foot Consistency
Standard Penetration Test (SPT) N-Value
Blows Per Foot Relative Density
< 250 < 2 Very Soft 0 – 3 Very Loose
250 – 500 2 - 3 Soft 4 – 9 Loose
500 – 1,000 4 - 6 Medium Stiff 10 – 29 Medium Dense
1,000 – 2,000 7 - 12 Stiff 30 – 49 Dense
2,000 – 4,000 13 - 26 Very Stiff 50+ Very Dense
4,000+ 26+ Hard
RELATIVE PROPORTIONS OF SAND AND GRAVEL GRAIN SIZE TERMINOLOGY
Descriptive Terms Percent of Dry Weight Major Constituent of
Soil Sample Particle Size Trace < 15 Boulders Over 12 in. (300mm)
With 15 – 29 Cobbles 12 in. to 3 in. (300mm to 75 mm)
Modifier > 30 Gravel 3 in. to No. 4 sieve (75mm to 4.75 mm)
Sand
Silt or Clay
No. 4 to No. 200 sieve (4.75mm to 0.075mm)
Passing No. 200 Sieve (0.075mm)
RELATIVE PROPORTIONS OF CLAYS AND SILTS PLASTICITY DESCRIPTION
Descriptive Terms Percent of Dry Weight Term Plasticity Index (PI)
Trace < 5 Non-plastic 0
With 5 – 12 Low 1 - 10
Modifier > 12 Medium 11 - 30
High 30+
CLASSIFICATION OF ROCK WITH RESPECT TO STRENGTH
Very Low Strength 18 – 72 ksf Low Strength 72 – 288 ksf Medium Strength 288 – 1,152 ksf High Strength 1,152 – 4,608 ksf Very High Strength 4,608 – 18,432 ksf
RQD DESCRIPTION OF ROCK QUALITY
0 – 25 Very Poor 25 – 50 Poor 50 – 75 Fair 75 – 90 Good 90 - 100 Excellent