Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE
Prof. J. N. Mandal
Department of civil engineering, IIT Bombay, Powai , Mumbai 400076, India. Tel.022-25767328email: [email protected]
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Module - 9LECTURE - 46
Geosynthetics for ground improvement
Recap of previous lecture…..
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Bearing capacity and settlement
Principles and functions of vertical drains
Basic principles of prefabricated vertical drains
Design charts without and with smear effect
DESIGN CHART WITH SMEAR EFFECT AND WELL RESISTANCE
Design Procedure:
Step 1: Determine the characteristics of soilCh = Coefficient of consolidation for horizontal drainagem2/sec or m2/month,Kh = Coefficient of horizontal permeability in undisturbed zone,(m/sec),Ks = Coefficient of permeability in the disturbed or smear zone(m/sec)
Step 2: Determine following drain propertiesdw = Diameter of the drain, m,ds = Diameter of the disturbed (smear) zone, m, andqw = Discharge capacity of the drain, m3/sec
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Step 3: Determine the following consolidation requirementsU = Average degree of consolidation, and
t = Time required to achieve the degree of consolidation
Step 4: Determine factor for soil disturbance (Fs)
Assume, ds/dw = 2 to 8
Now, Fs can be determined from following Figure.
w
s
s
hs d
dln1KKF
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Soil disturbance factor (Fs) versus Kh / Ks
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Step 5: Determine factor for drain resistance (Fr)
w
hr q
KzLzF
z = Distance from the drainage end of the drain (m),
L = Length of the drain when drainage occurs at oneend only (Put ‘L/2’ replacing ‘L’ when drainage occursfrom both the ends)
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Well resistance (Fr) versus Length (L) Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Product of Ch and t versus time (t)
Step 6: Determine the required consolidation time, t inmonths and obtain product (Ch x t) from the following Figure.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Step 7: Determine the parameter, λ from the followingFigure based on the required degree of consolidation (U)and (Ch x t).
Product of Ch and time (t) versus Lambda (λ)Ch = Coefficient of consolidation in horizontal direction, t = Required time for consolidation
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Step 8: Add Fs and Fr obtained from steps 4 and 5respectively.
Fsr = Fs + Fr
Determine the design diameter ‘D’ (in meter) from thefollowing Figure based on λ and appropriate Fsr for n = 20.
2h8 = D F1ln
1
C t
U
43
dDln
n1
43)nln(
n1n)n(F
w2
2
F = Fsr + F(n)
Fr = Well resistance factor Fs = Smear effect factorF(n) = Spacing factorn = spacing ratio
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Design diameter, D (m) versus Lambda, λ for n = 20
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Step 9: Find the spacing (S)
D = 1.05 S (For triangular pattern), and
D = 1.13 S (For square pattern)
The above design is developed by Mandal and Fulzele(2008).
The similar design charts are also developed byMandal and Shiv (1992) for prefabricated geocompositedrain.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Example:L = Length of the soil strata = 20 m, Kh/ Ks = 5,
Ch = 3.9 x 10-1 m2/month, ds/dw = 2, U = 80 %, t = 11 months
Determine the design diameter of the drain influence zone.Solution: Kh/Ks = 5, and ds/dw = 2
From Figure, Fs = 2.9.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
L = 20 m, and Kh/qw = 0.001
Well resistance (Fr) versus Length (L)
From Figure, Fr = 0.9
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Therefore, Fsr = Fs + Fr = 2.9 + 0.9 = 3.8
U = 80 % and Ch x t = (3.9 x 10-1) x 11 ≈ 4
From Figure, λ = 20
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Fsr = 3.8 ≈ 4 and λ = 20
From Figure, design diameter of influence (D) = 1.8 m
D = 1.05 S (For triangular pattern), andD = 1.13 S (For square pattern)
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
1. Marking of Points 2. Installation of PVD 3. Sand Blanket4. Geotextile placement 5. Instruments Installation 6. Preloading stages
Instrumentation of embankment on soft sol with PVDsInstrumentation of embankment on soft sol with PVDs
PVD spacing
Inclinometer Piezometer Settlement gauge
PVD up to mid depth of blanket
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Pneumatic Piezometer: To monitor the pore water pressureat the desired depth of the compressible soil
Inclinometer: To measure the lateral movement of the soilat the site slopes.
Settlement gauges: To measure the long term settlement atthe original ground surface of drainage blanket.
Settlement Plate: To monitor the settlement readings
Water stand pipe: To monitor the level of water in thecompressible soil layer either the Piezometers orsettlement gauges are installed immediately or during theinstallation of the vertical drains.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
1
2
3
4
5
0 10 20 30
Time in days
Settl
emen
t (m
)Without PVD
32
10
10 100 1,000 10,000 100,000
With PVD
1
2
3
4
5
0 10 20 30
Time in days
Settl
emen
t (m
)Without PVD
32
10
10 100 1,000 10,000 100,000
With PVD
1
2
3
4
5
0 10 20 30
Time in days
Settl
emen
t (m
)
1
2
3
4
5
0 10 20 30
Time in days
Settl
emen
t (m
)Without PVD
32
10
10 100 1,000 10,000 100,000
With PVD
Settlement versus time curve without and with PVD
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Installation of PVD:
The vertical drains are availabel in the form of roll.
The band drain is wrapped around a base plate or asteel bar at the bottom of the hollow steel lance.
The lance, band drain and steel rod will be pushedinto the soft cohesive soils to the desired depth.
When the band drain is reached to the desireddept, the lance is to be withdrawn keeping behind thesteel rod and band drains.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Installation of PVD drain (Photo Compliments of DBM Geotechnics)
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Installation of PVD at JNPT for national HighwayAuthority of India
Installed 7,00,000 Rmt (Sohams Foundation)
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Installation of PVD atJNPT for Maersk India Ltd
Installed PVD 8,50,000 Rmtin 40 Days Period(Sohams Foundation)
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Cross section of mandrel anddrain (After Rixner et al., 1986)
Different base plates to maintainwick drains at the base of theinstallation lance
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Band drains can be installed very fast. It isprefabricated, lighter as well as easy to transport andstore.
It is also economical with respect to the conventionalsand drains. The equipment is lighter than the rigs.
15 m long drains at spacing of 1 m to 2.5 m at aplacement rate of 375 m/hr is possible (Hausmann,1990).
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Summary on band drain Geotechnical engineers generally faced problem toconstruct structures on very soft soil.
It is necessary to prevent excessive settlement as well asimprove the bearing capacity of soft soil. Therefore, groundimprovement techniques are needed.
Combination of preloading and installation of prefabricatedvertical band drains in the subsoil layers can serve thepurpose.
Prefabricated vertical drains accelerate the consolidationprocess as well as dissipate excess pore water pressurewithin very short period.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
The PVD drains have many advantages comparedto the sand drains.
Rapid settlement of the soft soil is required forconstruction of embankments, oil tank foundations,landfills and underwater constructions.
PVD drains are efficient and most economical.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Example:
Compute time required for 60%, 70%, 80% and 95%consolidation at different spacing of PrefabricatedVertical Band Drain.
Size of PVD drain: 100 mm x 5 mm (TriangularPattern) Assume Ch = 6.27 x 10-6 m2/min
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Solution:
Consolidation time,
a = 100 mm (width of band drain)b = 5 mm (thickness of band drain)
dw = equivalent diameter of PVD = 2(a + b)/
D = equivalent diameter of influence = 1.05 × S (forTriangular pattern)S = Drain Spacing (c/c between drains) (m)
Ch = 6.27 x 10-6 m2/min
U11ln
43
dwDln
C8Dt
h
2
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
l = Length of prefabricated vertical drain (m)
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Spacing (m) Consolidation time, t (months) S (m) 60% (U) 70% (U) 80% (U) 95% (U)
2 5.029 6.608 8.833 16.441.71 3.484 4.577 6.119 11.391.43 2.246 2.951 3.944 7.342
1.333 1.899 2.495 3.336 6.2091.24 1.584 2.082 2.783 5.181.14 1.301 1.71 2.286 4.2551.05 1.049 1.378 1.842 3.43
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Consolidation time versus spacing for Prefabricated vertical drain under different degree of consolidation
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Example: Design steps for Prefabricated Vertical Drain(PVD) in a runwaySubsoil condition: Available borehole information showsthat very soft silty clays exist up to approximately 10 m to14 m below the existing ground level underlain by firm tostiff clays.
Standard penetration test value (N) within the very softlayer does not exceed 5, whereas it exceeds 10 in thefirm/stiff layer. The stratum is found to contain considerableorganic materials.
Area for the proposed runway extension is a low linearea where the ground water table has been observe closeto the ground level approximately 1.0 m to 1.5 m below theexisting ground level.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
For the construction of runway and taxiway extension,the existing ground level is needed to be raised by fillingabout 2 meter to 3 meter.
After construction, considerable live loads are expecteddue to heavy aircraft movements. It is required to improvethe very soft sub-soil by accelerating its consolidation;thereby increasing its bearing capacity as well.
Most cost effective way to improve the underlying verysoft clay is installation of prefabricated vertical drains(PVD) or band drains and preloading.
The required drain spacing, time required forconsolidation etc. are designed based on the soilcharacteristics and period available for consolidation.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
The pre-loading requirements consist of the following:
(a) Load from pavement
- Concrete- 0.45 m thick x 2.4 t/m3 = 1.1 t/m2
- GSB layer- 0.90m thick x 1.8 t/m2 = 1.7 t/m2
(b) Live load from aircraft on pavement (estimated) = 4.6 t/m2
Total load from aircraft at sub-grade level = 7.4 t/m2
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Pavement cross-section
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Solution:
Step 1: Calculate safe bearing capacity of soft soil stratum
. .c
uCNQF S
Qu = Safe bearing capacity (t/m2),C = Undrained cohesion (t/m2),Nc = Bearing capacity factor (5.7), F.S. = Factor of safety
Calculation of Safe Bearing Capacity
Input Data Values
1 Cohesion (T/sqm) 2.52 Bearing Capacity Factor 5.73 F.S. 3
CALCULATE
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Value of Safe Bearing Capacity
Safe Bearing Capacity (T/sqm) 4.75
Back Go to Main
Safe bearing capacity of soil = 4.75 t/m2 < 7.4 t/m2.
Therefore, we have to go for ground improvement.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Step 2: Calculate the settlement of soft soil stratum usinggeneral consolidation theory
0
0 0
log1
cC H p pe p
δ = Settlement (m),Cc = Compression index of soil,H = Thickness of compressible clay layer (m),p0 = Effective overburden pressure at the middle ofcompressible clay layer (kPa),Δp = Increase in surcharge (kPa), ande0 = Initial void ratio of soil
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Calculation of settlement
In put data Values
1 Thichkness of compressible clay layer (m) 102 Height of embankment (m) 4.353 Compression Index 0.2434 Initial void ratio 1.25 Bulk Unit weight of soil (T/cum) 1.76 Unit weight of embankment (T/cum) 1.8
CALCULATE Go to Main
Output value of settlement
563.497Total Settlement of compressible clay layer in mm
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Step 3: Calculate the time required for total settlement(calculated in earlier step)
2v
v
T HtC
2
4vT U (For U ≲ 60%)
1.781 0.933log(100 %)vT U (For U > 60%)
t = Time to achieve required degree of consolidation (month),Tv = Time factor,H = Thickness of compressible clay layer in meter (H forsingle way drainage and H/2 for both way drainage),Cv = Coefficient of consolidation of soil in m2/month, andU = Degree of consolidation in %
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
General Consolidation Theory
Design Input
Vertical coefficient of consolidation (Cv) in m2/month 0.334
Average degree of consolidation (U) % 90
Thickness of the compressible layer (H) in meter 10
CALCULATE
General Consolidation Theory
Design Output
Time required for the given degree of consolidation (years) 21.167
Time Factor (Tv) 0.848
Time required to attain 90% consolidation without anyground improvement is 21.167 years.
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Step 4: Calculate the time required for particular degreeof consolidation using PVDs
2 2
2
ln / 3 ( / ) 1ln8 4 11 /h
D dD d DtC Ud D
t = Time required for the given degree of consolidation,D = Effective diameter of influence for the PVD
=1.13 S (for square pattern),= 1.05 S (for triangular pattern)
S = Spacing of PVDsd = Equivalent diameter of the PVD
2( )b td
b =Width of the PVD, t = Thickness of the PVD,
Ch = Horizontal coefficient of consolidationProf. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Designing with Prefabricated Vertical Drains
Design Input
Horizontal coefficient of consolidation (Ch) in m2/month 6.7E-01
Average degree of consolidation (U) % 90
Width of the PVD (b) in mm 100
Thickness of the PVD (t) in mm 4
PVD Spacing (s) in m 1.2
CALCULATE
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
1.52
1.81(With Square Pattern)
1. For Triangle Pattern =1.05 × Spacing 1.262. For square Pattern =1.13 × Spacing 1.356
Effective Diameter of influence of PVD (D)
Time required for the given degree of consolidation with PVD (month)(With Triangular Pattern)
Time required for the given degree of consolidation with PVD (month)
Back MAIN SCREEN
Go for Stage loading
In triangular pattern, time required for 90% consolidationwith PVD is 1.52 months i.e. 45 days
In square pattern, the time required for 90%consolidation with PVD and 1.81 month i.e. 55 days
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Step 5: Calculate the required height of embankment thatcan be safely placed on soft soil stratum
usafe
Soil
Qh
hsafe = Height of embankment that can be safely placed on soft soil stratum in meter,Qu = Safe bearing capacity of soil = 4.75 t/m2, and γsoil = Unit weight of compressible soil = 1.7 t/m3
m37.175.4hsafe
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Step 6: Decide the number of stages and days required forapplication of embankment loading in such a manner thatthe total number of days (D) should be greater than thedays required for desired settlement using the PVDs.Step 7: Determine the improvement in initial cohesion and thus in shear strength in each stage
100%U.(%)I.P0045.015.0
pc )increased(u
)increased(u)initial(u)final(u ccc
Cu(increased) = Increment in initial cohesion,
Cu(final) = Cohesion after the improvement
p100
%U.(%)I.P0045.015.0cc )initial(u)final(u
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Cu(initial) = 2.5 t/ m2
U% = Desired degree of consolidation = 91%, 55%, 33%P.I. = Plasticity Index of soil = 27%, andΔp = Increase in overburden pressure
= height of fill x fill density, fill density = 1.8 t/m3
Improvement in cohesion due to consolidation in stage I,
Improvement in cohesion due to consolidation in stage II,
Improvement in cohesion due to consolidation in stage III,
Δp = (3 x 1.8) t/ m2
Δp = (4 x 1.8) t/ m2
Δp = (5 x 1.8) t/ m2
2)final(u m/t83.3)8.13(
10091270045.015.05.2c
2)final(u m/t9.4)8.14(
10055270045.015.083.3c
2)final(u m/t7.5)8.15(
10033270045.015.09.4c
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Please let us hear from you
Any question?
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay
Prof. J. N. Mandal
Department of civil engineering, IIT Bombay, Powai , Mumbai 400076, India. Tel.022-25767328email: [email protected]
Prof. J. N. Mandal, Department of Civil Engineering, IIT Bombay