SCHOOL BOARD OF VOLUSIA COUNTYAUGUST 29, 2018

GEORGE MARKS ELEMENTARY MASTER PLANPHASE I PLANS

Page 2: GEORGE MARKS ELEMENTARY MASTER PLAN PHASE I PLANS

Existing Site Plan

Page 3: GEORGE MARKS ELEMENTARY MASTER PLAN PHASE I PLANS

Conceptual Site Plan 5-16-18

Page 4: GEORGE MARKS ELEMENTARY MASTER PLAN PHASE I PLANS

Conceptual Site Plan 8-20-18

Page 5: GEORGE MARKS ELEMENTARY MASTER PLAN PHASE I PLANS

First Floor Plan 8-20-18

Page 6: GEORGE MARKS ELEMENTARY MASTER PLAN PHASE I PLANS

Second Floor Plan 8-20-18

Page 7: GEORGE MARKS ELEMENTARY MASTER PLAN PHASE I PLANS
Page 8: GEORGE MARKS ELEMENTARY MASTER PLAN PHASE I PLANS
Page 9: GEORGE MARKS ELEMENTARY MASTER PLAN PHASE I PLANS
Page 10: GEORGE MARKS ELEMENTARY MASTER PLAN PHASE I PLANS
Page 11: GEORGE MARKS ELEMENTARY MASTER PLAN PHASE I PLANS

SCHEDULE

PORTABLE VILLAGEDesign & Permitting - November 1, 2018

Bidding & GMP - December 2018

Construction - January - April 2019

SCHOOLDesign & Permitting - April 1, 2019

Bidding & GMP - June 25, 2019

Construction - July 1, 2019

NEW SCHOOL OPENING: August 2020

REMODELING: June 2020 - December 2020