37
Kenneth J. Andrews EMP-5179-6-1 Gen-X: Manufacturing Analysis What is the process? Build & test of AXIS machine for a specific Customer Who is the customer? MegaPower - product quality - install time - on-time delivery - ship what ordered - good training Installation - complete shipment - documentation - tested, working - acceptance test OK - early notification

Gen-X: Manufacturing Analysis

Embed Size (px)

DESCRIPTION

Gen-X: Manufacturing Analysis. What is the process?Build & test of AXIS machine for a specific Customer - PowerPoint PPT Presentation

Citation preview

Kenneth J. Andrews EMP-5179-6-1

Gen-X: Manufacturing Analysis

What is the process? Build & test of AXIS machine for a specific Customer

Who is the customer? MegaPower - product quality

- install time- on-time

delivery- ship what

ordered- good

training

Installation - complete shipment

- documentation

- tested, working

- acceptance test OK

- early notification

Kenneth J. Andrews EMP-5179-6-2

Gen-X: Manufacturing Analysis – Flowchart (1)

1. Order is logged in2. Scheduled by the Manufacturing Manager (remote board)3. Order sent to Manufacturing Engineer4. Wait for drawings – always 5 days late5. Initiate system build (before designs arrive)6. Designs are checked, mistakes noted – no direct feedback7. Problems with designs – try to reach designer WAIT8. Mfg. Engineer modifies the designs (inventory-driven)9. Supervisor takes the new designs10.Systems are re-worked to account for actual designs11.Parts are requested from Stores WAIT12.Problems during build Mfg. Eng Mfg. Mgr Eng. Mgr

13.System hardware completed14.System moved to Test

Kenneth J. Andrews EMP-5179-6-3

Gen-X: Manufacturing Analysis – Flowchart (2)

15.Chase software from Design WAIT16.Software arrives (late)17.Hardware functional check – problems fixed – no

feedback18.Software check – patches for bugs – documentation?19.No time for Acceptance Test20.System moved to shipping dock21.Install Coordinator advised about imminent ship

Kenneth J. Andrews EMP-5179-6-4

Gen-X: Manufacturing Analysis – Flowchart (1)

1. Order is logged in2. Scheduled by the Manufacturing Manager (remote board)3. Order sent to Manufacturing Engineer4. Wait for drawings – always 5 days late5. Initiate system build (before designs arrive)6. Designs are checked, mistakes noted – no direct feedback7. Problems with designs – try to reach designer WAIT8. Mfg. Engineer modifies the designs (inventory-driven)9. Supervisor takes the new designs10.Systems are re-worked to account for actual designs11.Parts are requested from Stores WAIT12.Problems during build Mfg. Eng Mfg. Mgr Eng. Mgr

13.System hardware completed14.System moved to Test

Kenneth J. Andrews EMP-5179-6-5

Gen-X: Manufacturing Analysis – Flowchart (2)

15.Chase software from Design WAIT16.Software arrives (late)17.Hardware functional check – problems fixed – no

feedback18.Software check – patches for bugs – documentation?19.No time for Acceptance Test20.System moved to shipping dock21.Install Coordinator advised about imminent ship

Kenneth J. Andrews EMP-5179-6-6

Process Improvement

What process?

Customer +requirements

Map currentprocess

Identifyhot-spots

Root-causeanalysis

Improvements toa) fix root causes b) meet C requirements

Metrics (1-3 months)

Communicate plan

Implement,measure,fine-tune

Kenneth J. Andrews EMP-5179-6-7

Manufacturing Systems: EMP-5179

Module #6: Manufacturing Metrics

Dr. Ken AndrewsHigh Impact Facilitation

Fall 2010

Kenneth J. Andrews EMP-5179-6-8

EMP-5179: Module #6

Sigma, Variance, SPC etc. Revisited

Factory Physics

Balanced Scorecard

Kenneth J. Andrews EMP-5179-6-9

Variability

The world tends to be bell-shaped

Most outcomes

occur in the middle

Fewer in the “tails”

(lower)

Fewer in the “tails” (upper)

Even very rare outcomes are

possible(probability > 0)

Even very rare outcomes are

possible(probability > 0)

Kenneth J. Andrews EMP-5179-6-10

Nu

mb

er o

f S

amp

les

Process Spread/Variability

Mean

Process variability is determined by US

Kenneth J. Andrews EMP-5179-6-11

Nu

mb

er o

f S

amp

les

Specification Tolerance

MeanUpper

Specification Limit (USL)

Lower Specification

Limit (LSL)

Specification tolerance is defined by the Customer

Kenneth J. Andrews EMP-5179-6-12

Tolerance Limits

Kenneth J. Andrews EMP-5179-6-13

Variation in Process Output Due to Random Causes

Kenneth J. Andrews EMP-5179-6-14

Low Process Capability

Kenneth J. Andrews EMP-5179-6-15

High Process Capability

Kenneth J. Andrews EMP-5179-6-16

We can be much more specific about process capability by measuring the process variability and comparing it directly to the required tolerance. Common measures are called Process

Capability Indices (PCIs)

6LSLUSL

C p

3

),min( LSLUSLC pk

μ= meanσ= std. deviationUSL= Upper Spec. LimitLSL= Lower Spec. Limit

Process Capability Indices

Kenneth J. Andrews EMP-5179-6-17

Process Capability

Cpk = min

USL – μ3σ

μ - LSL3σ

14 20 26 15 24

24 – 203(2)

= =.667

20 – 153(2)

= =.833

Kenneth J. Andrews EMP-5179-6-18

Cpk measures “Process Capability”

Good quality:defects are rare (Cpk>1)

μtarget

Kenneth J. Andrews EMP-5179-6-19

Cpk measures “Process Capability”

Poor quality: defects are common (Cpk<1)

μtarget

If process limits and control limits

are at the same location, Cpk = 1

Cpk ≥ 2 is exceptional.

Kenneth J. Andrews EMP-5179-6-20

EMP-5179: Module #6

Sigma, Variance, SPC etc. Revisited

Factory Physics

Balanced Scorecard

Kenneth J. Andrews EMP-5179-6-21

Factory Dynamics: Batch ProductionConsider a simple 4-station production line, where the

processing time at each station is exactly 1 minute

Batch Size(WIP)

Cycle Time(minutes)

Throughput(pieces/minute)

Throughput(pieces/hour)

10 40 0.25 15

9 36 0.25 15

8 32 0.25 15

7 28 0.25 15

6 24 0.25 15

5 20 0.25 15

4 16 0.25 15

3 12 0.25 15

2 8 0.25 15

1 4 0.25 15

Kenneth J. Andrews EMP-5179-6-22

Factory Dynamics: Single-Piece FlowConsider a simple 4-station production line, where the

processing time at each station is exactly 1 minute

Batch Size(WIP)

Cycle Time(minutes)

Throughput(pieces/minute)

Throughput(pieces/hour)

1 4 0.25 15

2 4 0.50 30

3 4 0.75 45

4 4 1.00 60

5 5 1.00 60

6 6 1.00 60

7 7 1.00 60

8 8 1.00 60

9 9 1.00 60

10 10 1.00 60

Kenneth J. Andrews EMP-5179-6-23

Production Throughput

Kenneth J. Andrews EMP-5179-6-24

“Decrease Inventories”

A factor of variability

Lower WIP = Less Throughput = Not Good

Kenneth J. Andrews EMP-5179-6-25

“Reduce Variability AND Inventories”

Reduced variability

Lower WIP + Reduced variability = Higher Throughput = Good

Kenneth J. Andrews EMP-5179-6-26

Self-Paced Study

Review and research the following material relating to:

SCV

Availability

Factory Physics

Confirm your understanding by following the examples provided.

Kenneth J. Andrews EMP-5179-6-27

Objective Measure of Variability

For example, an assembly operation with an average process timeof 20 minutes and a standard deviation of 1 minute:

scv = (1/20) 2 = 0.0025

Kenneth J. Andrews EMP-5179-6-28

Availability

Consider a workstation that operates an average of 70 hoursbefore it must be shut down for maintenance, lasting 10 hours.

Kenneth J. Andrews EMP-5179-6-29

Optimal Maintenance Intervals?

Infrequent maintenance:70 hours on, 10 hours off

Frequent maintenance:3.5 hours on, 0.5 hours off

What about variability? Isn’t that important too?

Kenneth J. Andrews EMP-5179-6-30

0.028

Optimal Maintenance Intervals?

Kenneth J. Andrews EMP-5179-6-31

Optimal Maintenance Intervals?

scv = squared coefficient of variationmr = mean time to repairA = availabilityt0 = original processing time

Kenneth J. Andrews EMP-5179-6-32

Optimal Maintenance Intervals?

Infrequent maintenance: 70 hours on, 10 hours off

Frequent maintenance: 3.5 hours on, 0.5 hours off

For the same equipment availability,shorter repair times lead to lower variability

i.e. they are better

Kenneth J. Andrews EMP-5179-6-33

Utilization: High or Low?

One way to improve Return on Investment (ROI) is to maximize the revenue generated by utilizing production resources to the fullest extent possible = high capacity utilization.

Is a 24/7/52 factory a good strategy?

It depends on whether you are striving for shorter cycle times

It also depends on whether you are living in a:

deterministic (ideal) world = very low variability

stochastic (real) world = moderate/high variability

Kenneth J. Andrews EMP-5179-6-34

Cycle Time, Utilization & Variability

High Variability

Low Variability

20% 50% 100%

CycleTime

Capacity Utilization

ModerateVariability

Standard & Davis: “Running Today’s Factory”

Kenneth J. Andrews EMP-5179-6-35

Causes of Variability Equipment downtime

Excessive set-up time

Uneven production demand

Batch material movement

Non-standard processes

Human factors

Supplier problems

Unexpected outages (e.g. power)

1. Reduce variability wherever possible throughout the production process.2. Do not strive for 100% capacity utilization.

Kenneth J. Andrews EMP-5179-6-36

Balanced Scorecard Perspectives

Learning and Growth

Are we able to sustaininnovation, change, and

continuous improvement?

Internal Business Process

How well do we perform at keyinternal business processes?

Customer

How well do we satisfy ourinternal and externalcustomer’s needs?

Financial

How do we look to ourstakeholders?

Primary Driver of Performance Secondary Influence on Performance

Kenneth J. Andrews EMP-5179-6-37

Preparation for Next Week

Watch for new articles/links on the website

Download material for module #7