Before starting a unit some basic rules should be respected, in order to avoid injury or damage. After placing the UPS(s) at it's final destination and having it unpacked, remove the side- and protection panels. With access to all parts, a thorough mechanical inspection should ensure the unit(s) has no damage or loose bolts, screws, nuts or cables. Remove transit brackets. Insure that the transit brackets and bolts on all transformers and inductors have been removed. These brackets and bolts are bright yellow in color. Connect then all Input / Output cables according the instructions in the operating manual. Inspect fans, insure that the fans spin freely. Check all fuses ohmically. Use the commissioning report , to take note of checked items and measured values during commissioning.Note: If any problems with this installation are found that pose a threat to persons or equipment, do not proceed until the problem has been corrected. Make sure all breakers are open (Q1, Q2, Q3a, Q4) then connect Mains voltage to the UPS (both if separate for Rectifier andBypass). Power supply starts a the display shows a selftest, at the end of which should result "Self test ok". Verify in Parameters for correct Date and Time. Verify in the Service Alarms for the presence of the code 9D04, which indicates the correct function of important parts of the control board IM 0007. In case you find codes 9D00, 9D01, 0D02, 9D03 instead, a malfunction on the control board is present. Change the control board !! Warning: Main Input Feed CB is closed and thus supplying LETHAL voltages to the system. Caution: It is recommanded that the load supplied by the UPS remains OFF until commissioning has been completed. Verify for correct phase rotation on power interface IM 8820 or IM 0035 . Measure and record all Power supply voltages on Power supply board IM 8845 or IM 0076 . Verify correct Power wiring. In a parallel system the outputs of all units must be connected. (Customers load not yet connected) Close Q2 on 1st Unit. Measure on 1st Unit with Voltmeter Phase L1 Mains - Phase L1 Load connection, followed by the phases L2 and L3. Measure then the same on all other units in case of a parallel system. Should you measure voltage you may have a miss wired output. Open Q2. Commisioning report Subject Description Passedè Yes þ No þ General Control on positioning the UPS General conditions: battery and UPS installation area Visual inspection, check of any transportation damage

Ge Sitepro 20kva

Embed Size (px)

DESCRIPTION

ge site pro 20kva

Citation preview

Before starting a unit some basic rules should be respected, in order to avoid injury or damage. After placing the UPS(s) at it's final destination and having it unpacked, remove the side- and protection panels. With access to all parts, a thorough mechanical inspection should ensure the unit(s) has no damage or loose bolts, screws, nuts or cables. Remove transit brackets. Insure that the transit brackets and bolts on all transformers and inductors have been removed. These brackets and bolts are bright yellow in color. Connect then all Input / Output cables according the instructions in the operating manual. Inspect fans, insure that the fans spin freely. Check all fuses ohmically.Use thecommissioning report, to take note of checked items and measured values during commissioning.Note: If any problems with this installation are found that pose a threat to persons or equipment, do not proceed until the problem has been corrected. Make sure all breakers are open (Q1, Q2, Q3a, Q4) then connect Mains voltage to the UPS (both if separate for Rectifier andBypass). Power supply starts a the display shows a selftest, at the end of which should result "Self test ok". Verify inParametersfor correct Date and Time. Verify in the Service Alarms for the presence of the code 9D04, which indicates the correct function of important parts of the control board IM 0007.In case you find codes 9D00, 9D01, 0D02, 9D03 instead, a malfunction on the control board is present. Change the control board !!Warning:Main Input Feed CB is closed and thus supplying LETHAL voltages to the system. Caution:It is recommanded that the load supplied by the UPS remains OFF until commissioning has been completed. Verify for correct phase rotation onpower interface IM 8820orIM 0035. Measure and record all Power supply voltages onPower supply board IM 8845orIM 0076. Verify correct Power wiring. In a parallel system the outputs of all units must be connected. (Customers load not yet connected)Close Q2 on 1st Unit.Measure on 1st Unit with Voltmeter Phase L1 Mains - Phase L1 Load connection, followed by the phases L2 and L3. Measure then the same on all other units in case of a parallel system. Should you measure voltage you may have a miss wired output. Open Q2.Commisioning reportSubjectDescriptionPassedYesNo

GeneralControl on positioning the UPS

General conditions: battery and UPS installation area

Visual inspection, check of any transportation damage

Check room ventilation for UPS cooling

Accessibility of UPS sides and/or rear for preventive maintenance

Control delivery completeness. Check Options (LINC, SNMP, Battery Fuse, Filter)

Remove transport protections and fixations

Mechanical inspection of screws and power connections; tighten where needed

Fans Control (running free)

Check internal connections

Verify plugs and flat-cable connections of the different PCB's

InstallationControl before powering the UPS

Check installation: sizing of cables and rating of fuses for Utility and Battery

Check all the external cable connections (utility, battery, load)

Check and tight external connections

Check links for Bypass and Rectifier Utility according to installation

Isolation measurement (with Installer) upon Customer request

Ohmic check of the installation

Control of the batteries positioning and battery connector

Check Battery voltage (value, polarity)

Powering Load from Maintenance Bypass

Check output distribution connections and eventual external manual bypass

Connect external maintenance bypass or UPS Q2 to supply load

BatteryControl of External Battery bank

Check/screw battery connections

Check and eventually provide proper earthing of battery enclosure

Check correct polarity of the blocks

Check voltage and polarity on positive and negative pole of battery bank

Check symmetry of battery voltages to Earth

SubjectDescriptionPassedYesNo

SystemControls "on power" of UPS module

All manual switch open (Q1, Q2, Q4, Q3)

Check Input mains voltage Rectifier and By-Pass (Voltage, phase rotation)

Connect Utility and check the functionality of Power Supply board

Check RS232 communication interface running Service Application

Check and eventually adjust Battery parameters (Type, N of cells, Autonomy)

Low Voltage Start-up procedure

Perform test procedure and check correct rectifier and inverter functionality

Set correct values on modified parameters

Rectifier Section

Control rectifier soft-start

Check UDC voltage (value, polarity)

Check K3/Battery fuses closure command/indication

Connect Batteries (close fuses)

Connect and check battery temperature sensor

Inverter Section

Control Inverter soft-start

Check Inverter output voltage (value, phase-rotation, waveform)

Check CP current values

Bypass (SSM) Section

By-Pass static switch activation

Check output voltage (phase rotation)

Control fans (outflow)

Control synchronization between by-pass and inverter

Load transfer

Check bypass voltage readings on UPS display (eventually correct)

Check inverter voltage adaptation and load transfer procedure

SubjectDescriptionPassedYesNo

TuningControl and activation of special functions according to Customer requests

Information / activation of automatic battery test

Information / Parameter adjustment for General alarm (delay, etc)

Information / control signals on dry contacts

Information / check / connect LINC-Box / SNMP box/card

Delete alarm memory

ElectricUPS on LOAD

Supply load by UPS Q2

Control Load Current on output distribution (value and waveform)

Switch the load on UPS bypass (SSM)

Control (eventually correct) measurement values on display

Switch the load on inverter

Perform a Manual Battery Test

Check system operation during mains breakdown

DeliveryDelivery to customer

Instruction of the customer (Operation, service-check, alarms)

Delivery of the entire system with option (LINC and SNMP option, ...)

Fill-outs and signing of Acceptance protocol

Low voltage startup

In many occasions it might be useful to test the function of Rectifier and Inverter with a voltage low enough to avoid damage in case of malfunction, in particular to the power modules, before running the UPS in nominal voltage. Find below a description for how to proceed.Important:At the end of Low voltage startup the UPS must be shutdown completely, including power supply, to reset some Parameters to their original value. Open Q1 and Q4, disconnect Battery Connect Mains (Utility power) to the UPS. Enter third level Parameters, (seePassword) and change the values of the following 2 Parameters:- Parameter 217: 21000 (17300 in case of 12 - pulse Rectifier !!!) (Reduces the Rectifier output voltage)- Parameter 112: 00050 (Limits the Inverter voltage to 50 Volts) Connect a Voltmeter to the DC - Link (UDC) and an Oscilloscope to the Inverter ouput. Close Q4 to start the Rectifier. The DC Voltage should now gradually increase.See table below. Press now the key Inverter ON. As the Inverter starts, the DC Voltage decreases while the AC Voltage of the Inverter should be a clean sinewave. If everything looks ok, proceed and increase gradually the DC Voltage by reducing the value in Parameter 217, until you reach again the previously installed default value (4000).See in the table below the resulting voltages (approximate !!!). Att. Switch Inverter and Rectifier OFF (open Q4) before changing Parameter 217. An example of the approximately resulting voltages is shown in the table below. Should at any time of the procedure result a deformation of the Inverter output sinewave, do not continue, but check first for correct drive pulses of Rectifier and Inverter. If necessary change the Main control board IM 0007 / 0057 or one of the driver boards. SetParameter 112for nominal Inverter output voltage. (230V).Important: At the end of the procedure you must either shut down the UPS completely, including power supply, or make a reset withPB2on the main control board IM 0007, always with DC - Capacitors discharged !!!!!!With 6 - Puls Rectifier and 50Hz !!!Parameter 2176 - PulsUDC with Inverter OFFUDC with Inverter ONU Inverter

21000Att.: 17000 for 60Hz801113

205001203734

2000015074

1800029023050 (regulated)

16000375 (K3 closed)35050

1500040850

1400043642350

13000436U - floating50

04000 (Default)436U - floating50

The values shown in this table are indicational, in particular the values in Parameter 217 should be choosen on dependence of an actual existing problem !!!

Once the Rectifier is running at floating voltage, stop the Inverter and change Parameter 112 for the Inverter output voltage, back to it's nominal value.