GBT Commissioning Review – Tuesday, November 12, 2002 GBT Status: Current Observing Capabilities

GBT Status: Current Observing Capabilities

  • Upload
    werner

  • View
    27

  • Download
    3

Embed Size (px)

DESCRIPTION

GBT Status: Current Observing Capabilities. Telescope Performance - Pointing. All-sky pointing rms ~ 10”. Tracking stability rms ~ 2” (5” peak-to-peak). Telescope Performance – Focus Tracking. Empirical Model. PF (800 MHz). Gregorian (X-band). Telescope Performance - Surface. - PowerPoint PPT Presentation

Citation preview

Page 1: GBT Status:  Current Observing Capabilities

GBT Commissioning Review – Tuesday, November 12, 2002

GBT Status: Current Observing Capabilities

Page 2: GBT Status:  Current Observing Capabilities

GBT Commissioning Review – Tuesday, November 12, 2002

Telescope Performance - Pointing

All-sky pointing rms ~ 10”

Tracking stability rms ~ 2”(5” peak-to-peak)

Page 3: GBT Status:  Current Observing Capabilities

GBT Commissioning Review – Tuesday, November 12, 2002

Telescope Performance – Focus Tracking

Empirical Model

PF (800 MHz)

Gregorian (X-band)

Page 4: GBT Status:  Current Observing Capabilities

GBT Commissioning Review – Tuesday, November 12, 2002

Telescope Performance - Surface

70% efficiency at long wavelengths

~60% efficiency at 20 GHz

Page 5: GBT Status:  Current Observing Capabilities

GBT Commissioning Review – Tuesday, November 12, 2002

Frequency Coverage

Page 6: GBT Status:  Current Observing Capabilities

GBT Commissioning Review – Tuesday, November 12, 2002

Observing Modes

Pulsar(SP; BCPM; GBPP)

Spectral Line(SP; Spectrometer)

Continuum (DCR)

Radar (PFS)

VLBI (VLBA)

Camilo et al. (2002)Lockman (2002)

GB Staff

Campbell et al.

Page 7: GBT Status:  Current Observing Capabilities

GBT Commissioning Review – Tuesday, November 12, 2002

Spectrometer Modes