View
221
Download
0
Tags:
Embed Size (px)
Citation preview
1G.Barber Mice Tracker Mechanical Progress Imperial 2006
Tracker Update
Contents:-
Components
Station Layout
Light Guide Map
QA
Patch Panel
Alignment of Tracker
Installation Procedure
3D Virtual Model
Conclusions
2G.Barber Mice Tracker Mechanical Progress Imperial 2006
StationsModifications to the Carbon Fibre
The New station has had its outer diameter reduced to 396 to take into account the fact that the bore of the solenoid is not machined but a rolled tube. The connector flange has been
thickened to 3mm to allow machining. This is to ensure that there is a uniform thickness thus
ensuring that the completed tracker is ‘of one axis’ and all planes are parallel. Also the face that seats
the connectors has a completely machined face to allow all of the connectors to sit down flat thus keeping the axis of the fibres perpendicular to the plane
3G.Barber Mice Tracker Mechanical Progress Imperial 2006
Station 4 Fabrication (Finished)
4G.Barber Mice Tracker Mechanical Progress Imperial 2006
Space Frame
Modifications The components that are used
to construct the space frame are similar to before with the exception of the locating foot and the diameter change. The foot was changed because of problems during assembly, if the dowel location was pushed into the foot there was no way to extricate it. The new foot has 2 smaller dowels either side of the structural tube.
Old Foot Design New Foot Design
Gluing Fillet Design
5G.Barber Mice Tracker Mechanical Progress Imperial 2006
Space Frame
Tooling
The jigs that align the space frames will need to be modified/re-made
To accommodate the new foot design and also to match the new
station to station pitch.
This has been identified as a work package that
can be given out to contract people and will
be investigated
6G.Barber Mice Tracker Mechanical Progress Imperial 2006
Station Layout/Pitch
The final pitch has still to be decided but the two alternatives shown are
Top:-15cm, 23cm, 25cm and 47cm
Bottom:-15cm, 25cm, 23cm and 47cm
If this is the case the only need for a decision is to accommodate the length of wave guide and I’m sure we can accommodate a 2cm change in the lengths by making them the longest required.
Still to be decided
7G.Barber Mice Tracker Mechanical Progress Imperial 2006
C14
C2C3
C4
C5
C6
C7
C1
C13
C12
C11
C10
C9
C8
C15C17
C29C28
C27
C26
C25
C24
C30
C18
C19
C20
C21
C22
C23
C16
1To20
21To42 43
To64
65To86
87To108
109To128
129To148
149To170
171To192
215To236
193To214
621To640
599To620577
To598
555To576
533To554
513To532
493To512
471To492
449To470
405To426
427To448
299To320
277To298
257To276
237To256
321To342
343To364
365To384
385To404
22
22
22
20
22
20
22
22
20
22
22
22
22
22
20
20
22
22
20
22
22
22 22
20 20
20
22
22
20
22
22
View ‘X’212 Channels
View ‘V’214 Channels
View ‘W’214 Channels
Bulkhead
Connector 1
BulkheadConnector 3
Bulkhead
Connector 4 B
ulkh
ead
Con
nect
or 2
Bulkhead
Connector 5
View of the station onto the polished face of the connector
Light Guide Map
This is the final version, assuming no one finds any glaring mistakes,
of the connector map for the tracker it can be found in its full form at
http://www.hep.ph.ic.ac.uk/CAD/mice/finalmice
8G.Barber Mice Tracker Mechanical Progress Imperial 2006
Connector 1
View ‘W’
20 Way
Bundles1 – 20
To Bulkhead Connectors1, 6, 11, 16 & 21
1
5 3
7
4
6
2
8910
11
13 12141516
18 17
x x
20 19Station connectorViewed from thepolished face.Internal light guideconnector viewedfrom rear or fibre entry side.
9G.Barber Mice Tracker Mechanical Progress Imperial 2006
Internal Lightguides Station 1
C1 1 to 20
C2 21 to 42
C3 43 to 64
C4 65 to 86
C5 87 to 108
C6 109 to 128
C7 129 to 148
C8 149 to 170
C9 171 to 192
C10 193 to 214
C11 215 to 236
C12 237 to 256
C13 257 to 276
C14 277 to 298
C15 299 to 320
C16 321 to 342
C17 343 to 364
C18 365 to 384
Bulkhead 1
1 to 128
Bulkhead 3
257 to 384
Bulkhead 2
129 to 256
Length = XXXmm
Length = XXXmm
Length = XXXmm
10G.Barber Mice Tracker Mechanical Progress Imperial 2006
External Lightguides
• These are one to one connections between the external tracker bulkhead connector and the VLPC 128 way connectors.
Bulkheadconnector
VLPCconnector
11G.Barber Mice Tracker Mechanical Progress Imperial 2006
QA
Due to the problem that has been highlighted by the connectors, more thought is required for the QA. One of the things we will be doing is to manufacture a ‘GO gauge’. This would be a block of very accurately positioned pins that match the hole pattern on the connector. If the connector and the block fit together then the holes in the connector are acceptable, if not it is discarded. Such a gauge could be given to the manufacturer so as to ensure consistent quality.
12G.Barber Mice Tracker Mechanical Progress Imperial 2006
Assembly Comb
This is being manufactured in Liverpool from aluminium and will be tried with the existing
fibre ribbon (at Brunel).
13G.Barber Mice Tracker Mechanical Progress Imperial 2006
Patch Panel Hole Requirements
Detail Drawing a
lmost
complete
14G.Barber Mice Tracker Mechanical Progress Imperial 2006
Positioning In The Solenoid
The tracker sits on 4 adjustablefeet two at the front two at the
rear and is held down by a springloaded foot at the 12 o’clock position. This aligns the axis of both tracker and solenoid
The tracker is aligned in Zand Phi by pulling a locating
block into a Vee which is located using dowels to
the patch panel.
15G.Barber Mice Tracker Mechanical Progress Imperial 2006
The Diffuser In The Solenoid
The new device to hold andchange the lead diffuser
in the solenoid will be partially mounted onto the cover of the
patch panel. The cover will need to be stiffened and tied back to the ‘solid’ region where the
patch panel is mounted to the solenoid. We have allowed
a bore of 331Ø in the cover with a series of holes and a position for an O-ring.
The final details to be worked out with Wing & Stephanie
16G.Barber Mice Tracker Mechanical Progress Imperial 2006
Installation ‘Cartoon’
The following sequence is a first attempt to show the stages of installation of the tracker into the solenoid. They are not definitive and are aimed to provoke a debate/discussion. I hope that the installation will then evolve with all interested parties contributing. It should be noted that all of this work will need to take place in a ‘light controlled’ environment (NO UV).
17G.Barber Mice Tracker Mechanical Progress Imperial 2006
Stage 1 of Installation
The patch panel is fitted and sealed to the solenoid. Hopefully at this stage we can test the seals using cover plates.
18G.Barber Mice Tracker Mechanical Progress Imperial 2006
Stage 2 of Installation
A target module is fitted into the bore of the solenoid and the feet adjusted to set the cross hairs on the same axis as the solenoid bore. Then the Phi/Z retaining bracket is fitted and the whole assembly surveyed it is carefully removed to the CMM for measurement. (As Mike pointed out, this makes a good ‘Go Gauge).
19G.Barber Mice Tracker Mechanical Progress Imperial 2006
Stage 3 of Installation
The target module is mounted onto the CMM(Computerised Measuring Machine), in a jig that simulates the bore of the solenoid. It is then surveyed.
20G.Barber Mice Tracker Mechanical Progress Imperial 2006
Stage 4 of Installation
The tracker module is then mounted into the same jig on the CMM. Using the survey from the target module we can adjust the 4 support feet until the tracker shares the same axis as the target module.
21G.Barber Mice Tracker Mechanical Progress Imperial 2006
Stage 5 of Installation
The tracker, complete with the light guide support structure is lifted onto the installation cradle. The light guide support structure is to ensure that no damaging forces are exerted on the fibres. Covers will be fitted during transit.
22G.Barber Mice Tracker Mechanical Progress Imperial 2006
Stage 6 of Installation
The tracker is then slide into its pre-determined position inside the bore of the solenoid. This position will already have been determined using the ‘tracker target’ in stage 2.
23G.Barber Mice Tracker Mechanical Progress Imperial 2006
Recap of Positioning In The Solenoid
The tracker sits on 4 adjustablefeet two at the front two at the
rear and is held down by a springloaded foot at the 12 o’clock position. This aligns the axis of both tracker and solenoid
The tracker is aligned in Zand Phi by pulling a locating
block into a Vee which is located using dowels to
the patch panel.
24G.Barber Mice Tracker Mechanical Progress Imperial 2006
Stage 7 of Installation
With the tracker in position and secure the light guides can now be carefully re-routed to their final position in the patch panel and the seals fitted. If the external light guides are not to be attached immediately then light tight/protection covers will remain fitted.
25G.Barber Mice Tracker Mechanical Progress Imperial 2006
Stage 8 of Installation
The light guides can then be secured to stop any damage and a shield (not shown) fitted to stop any damage occurring when the diffuser is installed. The Light guide support structure is now removed.
26G.Barber Mice Tracker Mechanical Progress Imperial 2006
Stage 9 of Installation
The patch panel cover is fitted and sealed to the patch panel. If we are not ready to fit the diffuser mechanism then a cover plate will be attached. We can repeat the gas seal test at this point.
27G.Barber Mice Tracker Mechanical Progress Imperial 2006
Requirements (those thought of at least)
To carry out the work we will need at least 2M of clear working area in front of the solenoid. We hope that this is achievable either by removing equipment in front of the solenoid or as is more likely, by moving the solenoid sideways out of the beamline. The solenoid and its kit would sit on a plinth and it would move as one. As already stated we will need this area to be light controlled, this will probably be achieved by building a tent structure over the area.
28G.Barber Mice Tracker Mechanical Progress Imperial 2006
Overall Layout (Land Grab)
Because of the amount of equipment required to fit into the area and possible conflicts that this may cause it has been decided to ‘build’ a 3D virtual model of the region. Also we need to be sure that all of our fibres can be accommodated in the fibre length allowed so this model will be the first step in this process. We plan to eventually build a full size model of this region to convince ourselves that what we have designed is feasible. The patch panel, fibre run, trellis and VLPC unit have been modelled and the idea is (we hope) to ask Stephanie to ‘assemble’ all of the 3D modelled items into a master model based on Tony’s floor layout.
29G.Barber Mice Tracker Mechanical Progress Imperial 2006
Layout 1st Attempt
30G.Barber Mice Tracker Mechanical Progress Imperial 2006
Layout 2nd Attempt
This was an attempt to achieve a shorter fibre run. In actual fact it increased
the longest run from 1884mm to over 2200mm
31G.Barber Mice Tracker Mechanical Progress Imperial 2006
Conclusions
• We have the design completed but for a few details and require a final set of engineering drawings.
• There is more work to be carried out on the layout and we hope to build a physical model to help.